Projects and Project Management
BeginnerLesson 1 of 9 in Project Management Foundations Course
What you will learn
- Tell projects apart from ongoing operations, explain why organizations start projects, and see how projects fit into programs and portfolios.
- Tell a project apart from ongoing operationsUse the defining features of a project, temporary and unique, to sort real work into projects and operations, and describe how the two connect at handover.
- Explain why organizations start projectsDescribe projects as the way organizations move from a current state to a desired future state, recognize the common drivers behind them, and separate a project from the product it creates.
- Place projects within programs and portfoliosDistinguish projects, programs and portfolios by purpose, scope and measures of success, and place real initiatives in the right category.
- Tell a project apart from ongoing operations
- Follow the chain from what a project delivers to the value it creates, and set clear, measurable criteria for judging whether a project succeeded.
- Trace value from deliverables to benefitsSeparate outputs, outcomes, benefits and value, recognize tangible and intangible value, and check a simple benefit-versus-cost example.
- Define and judge project successSet measurable success criteria with the sponsor, separate delivering the project well from achieving its purpose, and judge real cases on both.
- Trace value from deliverables to benefits
- Identify the limits a project works within, keep constraints, assumptions, risks and issues apart, and make and escalate trade-off decisions with clear reasoning.
- Identify a project's constraints and how they interactRecognize the classic and wider sets of project constraints, see how a change to one affects the others, and decide which constraint is the most fixed.
- Distinguish constraints, assumptions, risks and issuesClassify statements about a project as constraints, assumptions, risks or issues, explain how one can turn into another, and record each in the right way.
- Make and escalate trade-off decisionsAnalyze options when a constraint changes, compare their effects with numbers, and know which decisions the project manager can make and which go to the sponsor.
- Identify a project's constraints and how they interact
- Explain what the sponsor, the project manager and the other key roles do, and lead with sound management, emotional intelligence and professional ethics.
- Explain the sponsor's roleDescribe what a project sponsor is accountable for from start to finish, how a governing board shares that role, and which decisions belong to the sponsor rather than the project manager.
- Explain the project manager's role and the roles around itDescribe the project manager's responsibilities and everyday roles, how organizational structure shapes their authority, and what the team, functional managers and a project management office contribute.
- Lead with integrity and emotional intelligenceDistinguish leadership from management, use emotional intelligence in team situations, and apply the core values of professional ethics to everyday project dilemmas.
- Explain the sponsor's role
- Recognize what the main standards and frameworks are and how they differ, and use their principles to guide decisions in real project situations.
- Recognize the main standards and frameworksTell apart a body of knowledge, a method, a competence baseline and an international standard, and describe the PMBOK Guide, PRINCE2, IPMA ICB4, the APM Body of Knowledge and ISO guidance.
- Apply the six principles of the PMBOK GuideExplain each of the PMBOK Guide's six principles in plain terms and recognize which principle applies in a given project situation.
- Apply PRINCE2's principles and IPMA's competence areasExplain PRINCE2's seven principles, recognize them in project situations, and compare them with the PMBOK principles and IPMA's competence areas.
- Recognize the main standards and frameworks
Projects and Project Management study guide
1Recognize projects and organizational change
Work can keep a service running, change how it works, or coordinate several changes toward a shared purpose. Recognizing which kind of work you face helps you choose sensible objectives and management. Start with the features that distinguish a project from operations, then connect projects to the changes organizations need. Finally, look at how a single project can contribute to a program's benefits and a portfolio's strategy.
1.1 Temporary work with a unique result
A project is a temporary effort to create a unique product, service, or result. Its purpose might be to open a shop, investigate a research question, or replace a booking system. The size of the budget does not decide whether work is a project. The nature of the work does.
What temporary and unique mean
Temporary means a definite start and end. A bridge project can last five years; the bridge can last a century. Once the project ends, its team is usually reassigned or disbanded. The life of the result and the life of the effort that creates it are different.
Unique means this particular result has not been produced in exactly this form before. A builder may use familiar methods for a fiftieth house, but the client, site, design details, timing, and conditions differ. Repeated tasks can sit inside a project. They do not remove the uniqueness of the combined result.
PMI emphasizes the temporary effort and unique result. APM emphasizes a unique, temporary effort directed toward planned objectives. PRINCE2 describes a temporary organization delivering business products under an agreed business case. Each definition connects bounded work to a particular result.
Work that keeps going
Operations sustain an organization's services through ongoing, repeated work. Processing payroll, cleaning a building, and taking customer calls continue while the business function is needed. They are judged by steady performance, efficiency, and service levels.
| Work in a bakery chain | Classification and reason |
|---|---|
| Open a new shop | Project: a particular shop is prepared and handed over. |
| Bake bread each morning | Operations: the production service repeats. |
| Launch a seasonal cake range | Project: a new range is developed and introduced. |
| Count stock each month | Operations: the same control activity recurs. |
A deadline alone does not make work a project. The monthly stock count has a deadline every month. Ask whether the whole effort has a planned end and creates something new. Routine scheduled maintenance is operations; a one-time equipment upgrade is a project.
Connect delivery to daily use
At handover, the project passes its result to the people who will operate it. A customer database needs installation, testing, and acceptance. It also needs trained users, instructions, and a support arrangement. Preparing those things belongs in the project's work; running and maintaining the accepted database belongs to operations.
Plans become more detailed as the team learns. This is progressive elaboration. For example, a team can first identify a need for user training, then plan the sessions once the system's functions are clear. Refining that plan makes an agreed piece of work more precise.
A project ends when its objectives are achieved or it is terminated. Funding may disappear, the result may no longer be needed, or the objectives may become impossible. Closing work that no longer makes business sense releases people and resources for other uses.
Key Takeaways
- A project combines a definite start and end with a unique result.
- Operations sustain repeated services; a deadline or large budget does not change that classification.
- Handover includes preparing the people, information, and support needed for daily use.
- Progressive elaboration refines plans as knowledge grows.
- A project can end through completion or a justified decision to stop.
1.2 Projects move an organization toward a future state
Projects move an organization from a current state to a desired future state. That future may be a faster process, an improved service, a new product, or compliance with a requirement. Operations keep the existing service working while the project develops the change.
Recognize why the change starts
Four common drivers explain why organizations start projects:
- Requirements: meet a legal, regulatory, or social obligation, such as changing how a bank stores customer records.
- Stakeholder needs: respond to people using or affected by a service, such as patients requesting online appointments.
- Improvements: create, improve, or fix a product, process, or service, such as reducing waste on a factory line.
- Strategy: implement a business or technology direction, such as a retailer starting to sell online.
One project can have several drivers. External triggers include competition, technology, economic shifts, and environmental pressures. Internal triggers include operational problems and staff ideas. Link the change to an organizational objective before committing the money, people, and attention it will use.
Connect delivery to adoption
A city library takes 20 minutes to register each member on paper. Residents want online services, and the city has a digital-services strategy. The desired future state is online registration taking 5 minutes: 15 minutes saved from the original 20.
That is a 75% reduction. The project delivers the online system; operations then run it. Staff training, communication with members, and support help people adopt the service. A working system cannot shorten registration while everyone continues using the paper process.
A product can outlive its projects
A product, such as an app, may have an initial build project, years of operational support, and a redesign project. Its product life cycle spans that whole existence. Project management organizes one temporary effort; product management looks after the product across its life.
Projects occur in services, construction, research, software, events, and nonprofit work. Tailoring adapts management to size and context: a small internal change may need a short plan and brief check-ins, while a large, risky change needs more formal coordination and control.
Key Takeaways
- Projects connect a current state to a desired future state.
- Drivers include requirements, stakeholder needs, improvements, and strategic change.
- People must adopt a result before it can change their work.
- A product can continue through multiple projects and periods of operations.
1.3 Coordinate shared benefits and strategic investment
The terms project, program, and portfolio describe different management purposes. To distinguish them, look at the relationship between the work and the result expected from managing it together.
Programs coordinate related work for benefits
A program coordinates related projects, and sometimes ongoing activities, for benefits that separate management would not achieve. Dependencies between the results explain why coordination matters.
A hospital’s digital patient records program has projects to install software, transfer 15 years of paper records, train 1,200 staff, and redesign admissions. Software alone cannot produce faster, more accurate admissions: staff need accessible records and a workable process too. Program management makes those contributions fit together.
A program has broader scope than one project. Its scope can develop as benefits become clearer, and it ends when those benefits are delivered or handed over to those sustaining them.
Portfolios align investment with strategy
A portfolio groups projects, programs, smaller portfolios, and operations to achieve strategic objectives. Its components need no delivery dependency. They share investment priorities and compete for funding and people.
The hospital’s portfolio can include the records program, an unrelated parking garage renovation, and ongoing services. Leaders review how that mix serves strategy. The portfolio continues as priorities and conditions change.
| Level | Management focus | Main success question |
|---|---|---|
| Project | Particular outputs and objectives within agreed limits. | Were the agreed results delivered? |
| Program | Dependencies and shared benefits of related work. | Did the combined benefits happen? |
| Portfolio | The overall mix of investment. | Does the mix advance strategy? |
Size does not decide the category
Building one stadium is still a project. A program could coordinate the stadium, transport links, and related services when their combined benefits require joint management. Calling a costly stadium a program simply because it is large misses that relationship.
A project can stand alone, belong to a program, or sit directly in a portfolio. It need not pass through every level. Everyday phrases such as "training program" do not necessarily carry the technical meaning of related components coordinated for shared benefits.
Key Takeaways
- A program coordinates related work for benefits that separate management would not achieve.
- A portfolio aligns a mix of investment with strategy; its components need no delivery dependency.
- Project, program, and portfolio success are judged at different levels.
- Large size alone does not turn a project into a program.
- A project can sit directly in a portfolio without belonging to a program.
2Follow value and judge success
A finished result matters because of what people can do with it. Trace that connection from delivery to changed behavior, measurable improvements, and overall value. Then separate the quality of project delivery from the achievement of the project's purpose. These distinctions help you evaluate a business case, calculate a simple payback period, and agree success measures that still mean something after the project team has handed over its work.
2.1 From delivered outputs to lasting value
A team can deliver everything on its list and still create little value. To understand why, follow four connected terms: output, outcome, benefit, and value. Each asks a different question about the change.
Follow the chain
An output, also called a deliverable, is a verifiable product, result, or capability produced by the project. An outcome is the change that happens when people use that output. A benefit is a measurable improvement that stakeholders view positively. Value is the overall worth of the result after weighing benefits against costs, effort, and risks.
For a restaurant chain, the output is an ordering website and app. The outcome is customers placing orders online. A benefit is 125 fewer paid overtime hours each month spent taking phone orders, along with fewer wrongly recorded orders. Value considers the lower costs and customer experience against the cost and risk of building and running the system.
Tangible value can be counted in money or assets, such as reduced spending or new revenue. Intangible value is harder to price but still matters: trust, reputation, goodwill, and staff morale. Public and nonprofit projects may aim mainly at social value, such as safer roads. A dis-benefit is a negative consequence of the change, such as slower staff performance during the first month of a new system. Include it when judging the change.
Calculate cash savings and payback
The ordering system costs $90,000 to build. Removing 125 paid overtime hours each month at $20 an hour reduces spending by $2,500 monthly. Hosting and support cost $500 each month.
- Calculate the gross monthly saving: .
- Subtract the running cost: .
- Divide the build cost by the net monthly saving: .
The simple payback period is 45 months, or 3.75 years. Over five years, 60 months of net savings total $120,000. Subtracting the original $90,000 build cost leaves $30,000 above that cost. Ignoring the $500 monthly running cost would give a misleading payback of 36 months.
Payback counts cash. If staff use 125 freed regular hours for other work while their pay stays the same, the benefit is extra capacity, not reduced spending. Simple payback also leaves out intangible benefits and the time value of money. Receiving money years from now has a different financial worth from receiving it today; fuller financial appraisal accounts for that difference.
Read the payback answer correctly
The 45-month figure is the recovery point, not a recurring monthly benefit. At that point, accumulated net savings equal the initial cost. The five-year figure asks a different question: how much is left after recovering that cost? Keep the investment out of the monthly running-cost subtraction, then deduct it once from the accumulated net savings.
A faster payback is useful financial information, but it does not settle whether customers use the service or whether the whole change is worthwhile. An unused system cannot earn the predicted ordering savings. Benefit measurement therefore checks the behavior and the improvement behind the cash forecast, as well as recording payments.
Keep the business reason under review
The business case explains the reasons, options, expected benefits, costs, timing, and main risks. It is checked at key decision points. Changed conditions can make changing or stopping the project the sound choice.
Benefits often build after closure as people use the result. The sponsor or a business owner keeps measuring them after handover. Compare improvements with what would have happened without the project so the project is not credited for changes it did not cause.
Key Takeaways
- Outputs enable outcomes; outcomes can create measurable benefits.
- Value weighs benefits, including intangible ones, against costs, effort, and risks.
- Simple payback divides the initial cost by the net cash saving per period.
- Redeployed staff time adds capacity but does not itself reduce payroll spending.
- The business case is reviewed as conditions change.
- Benefits need an owner and measurement after handover.
2.2 Measure delivery and achievement of purpose
Before work begins, the sponsor and key stakeholders agree how success will be judged. Success criteria turn objectives into measures people can check. They cover both how the project is delivered and whether its intended change actually happens.
Two views of success
Project management success concerns delivery performance: agreed scope, schedule, budget, and required quality. Project success concerns purpose: the outcomes, benefits, and value the project was started to achieve.
A staff intranet can arrive on time and under budget while few staff use it six months later. Delivery performance is strong, but the intended change in information sharing has not happened. The project cannot claim that benefit merely because the software works.
The Sydney Opera House shows the opposite tension. Its 1957 cost estimate was A$7 million, or £3.5 million in the currency of the time, with completion planned for 1963. It opened in 1973 at a cost of A$102 million: about ten years late and roughly 14.6 times the estimate. Those figures show poor performance against the original delivery plan. Its lasting cultural value and recognition as a UNESCO World Heritage site in 2007 show why that is a different judgment from its long-term significance.
Make criteria checkable
For an office move, the sponsor and stakeholders might agree:
- "All 140 staff working at the new site by June 30."
- "Total move cost within $250,000."
- "No more than four hours of IT downtime."
- "Average staff rating of at least 4 out of 5 one month after the move."
Each states what will be checked and gives a threshold. The final criterion also fixes when to measure. "The move goes smoothly" leaves people free to apply different meanings afterward. Record the agreed criteria, often in the document that authorizes the project, so delivery and later benefits can be assessed consistently.
Acceptance, progress, and success
Acceptance criteria are the conditions a deliverable or the whole solution must meet before the customer accepts it. "Every page loads in under two seconds" is an acceptance condition. Passing it shows the solution meets that requirement. It does not show that customers have changed their behavior or that a benefit target has been reached.
A key performance indicator, or KPI, is a measure tracked during or after the work. Registration time, adoption rate, or downtime can provide evidence of progress toward a criterion. A measure needs an agreed target to support a judgment of success.
Stakeholders bring different interests: users want an easy service, the sponsor wants value, and the team considers workload. Agreeing priorities early helps resolve those differences. If circumstances change, the sponsor agrees and records revised criteria. Quietly changing the target at the end hides the project's actual performance. Ending a project after its business case collapses can protect resources even though the original result is never delivered.
Key Takeaways
- Delivery performance and achievement of purpose are separate judgments.
- Agree measurable success criteria and their priorities early.
- Acceptance criteria test readiness for acceptance; KPIs track relevant measures.
- Changed success criteria require an agreed and recorded decision.
3Make clear trade-offs within agreed limits
A deadline, a budget, and a list of desired features rarely move independently. When one changes, the team needs to see what happens to the others and who can approve the response. Begin by identifying constraints and their flexibility. Then separate known limits from assumptions, uncertain events, and existing problems. Use those distinctions to compare options, calculate tolerances, and bring decisions to the right person before a limit is breached.
3.1 See how project limits affect one another
A constraint limits how a project can be carried out. It can be a budget cap, a fixed completion date, available staff, a contract, a law, or a technical standard. Good planning makes these limits visible so people can discuss a feasible combination.
The triangle and the wider picture
The classic triple constraint, or iron triangle, is scope, time, and cost. Scope means what will be delivered. Time concerns the schedule; cost concerns the budget. Quality is often shown in the middle because pressure on the three sides can put it at risk.
Adding features can require more effort, more money, or a later finish. Bringing a finish date forward can require fewer features or extra resources. Cutting the budget can increase risk if it leaves too little support for the work. These effects are connected, but they are not a fixed arithmetic rule: a better method or removal of waste can sometimes improve several things together.
Wider models also consider quality, resources, and risk. PRINCE2 7 has performance targets for benefits, cost, time, quality, scope, risk, and sustainability. A choice can satisfy the date and budget while damaging a benefit or increasing environmental costs. The useful question is what the choice does to the whole project.
Identify what can move
Internal constraints come from the organization, such as budget rules, staff availability, and company standards. External constraints include client contract dates, legal requirements, supplier lead times, and conditions for outdoor work. Their origin does not decide their flexibility: an internal limit may be firm, while a supplier may agree a different delivery date.
A flexibility matrix records the sponsor's priorities:
| Priority | Meaning | Trade fair example |
|---|---|---|
| Fixed | Must be met. | The exhibition date cannot move. |
| Optimize | Improve it where possible. | Deliver the most useful launch scope. |
| Accepted | Allow it to move within the agreed authority. | Spend more when approved to protect the date. |
If the exhibition project falls behind, a later launch misses its purpose. Hiring help or reducing the launch scope are options to assess. "Accepted" cost still has limits and an approval route; it does not mean unlimited spending. Marking every target fixed can expose an impossible plan that needs a sponsor decision.
Protect quality while choosing grade
Quality is how well the result meets requirements. Grade is its category or level of features. A basic hotel room can be clean, safe, and fully meet its promises. A premium room with broken fittings has more features but poor quality.
Removing an optional feature can reduce grade or scope through an agreed decision. Quietly skipping required tests makes defects more likely and hides the real trade-off. Show the effects on quality and benefits alongside the effects on time and cost so the decision-maker can judge what the option actually delivers.
Key Takeaways
- Scope, time, and cost interact with quality, resources, risk, and benefits.
- A flexibility matrix distinguishes fixed, optimized, and accepted constraints.
- An allowed change still needs to stay within delegated authority.
- Grade concerns the level of features; quality concerns meeting requirements.
- Make effects on quality visible when comparing options.
3.2 Sort limits, planning beliefs, uncertainty, and current problems
Four statements can all concern the same delivery date but require different responses. The useful distinction is whether the statement is a known limit, a planning belief, an uncertain event, or a problem that already exists.
Classify the statement
| Type | What it means | Appropriate handling |
|---|---|---|
| Constraint | A known limiting fact. | Plan within it. |
| Assumption | Something treated as true for planning without proof. | Record it in an assumption log and check it. |
| Risk | An uncertain event or condition that would affect an objective. | Record it in a risk register and plan a response. |
| Issue | A relevant event or condition that already exists. | Record it in an issue log and resolve or escalate it. |
A risk can be negative, a threat, or positive, an opportunity. A chance of extra sponsorship is a risk in the technical sense because it is uncertain and could improve the project's cost position.
Work through a conference
The conference is scheduled for September 18, and its room holds 300 people. These are constraints that shape the plan. The team is treating its keynote speaker's attendance as certain after an email confirmation. That is a planning assumption to check as the event approaches.
The speaker could become ill and cancel. That uncertain future event is a threat. A local company might sponsor lunch and reduce costs: that is an opportunity. The catering company went out of business last week. That is an issue now, even though the conference is still in the future. The team needs a replacement caterer; estimating the probability of the company's closure no longer helps.
Keep the record current
Categories change as knowledge changes. A possible late delivery is a risk. A confirmed missed delivery is an issue. An assumption that turns out to be false creates a problem the team must address. An assumption still waiting for evidence can expose a risk worth planning for.
Checking assumptions therefore helps find uncertainty early. For example, treating a room as available lets the team prepare a plan, but it still needs confirmation. Record what is believed and arrange to check it. Leaving the belief unexamined makes the schedule depend on something the team has never established.
Write a risk people can act on
A clear statement connects cause, uncertain event, and effect: "Because the supplier has one delivery van, deliveries may arrive late, delaying installation by up to two weeks." The cause helps the team understand exposure; the event identifies what may happen; the effect connects it to an objective.
"Risk: budget" does not show whether prices might rise, funding might fall, or work might take longer. The response depends on that missing relationship. Likewise, "the server is down" describes an issue if the outage exists now. Record the current fact and act on it, while separately considering uncertain consequences that have not yet occurred.
Key Takeaways
- A constraint is known; an assumption is a planning belief that needs checking.
- A risk is uncertain and may be a threat or an opportunity.
- An issue exists now, even when its effect on delivery lies ahead.
- An event can move from risk to issue as facts become known.
- A useful risk statement connects a cause, an uncertain event, and an objective.
3.3 Compare options and escalate before a breach
A trade-off gives up some of one thing to gain another. Spending more to protect a launch date is a trade-off between cost and time. The decision needs to serve the project's priorities and business case, with approval from the person who holds the necessary authority.
Build a decision from the effects
Describe the problem, identify the constraints it changes, and list realistic options. For each option, estimate scope, time, cost, quality, risk, and benefits. Compare those effects with the agreed priorities and limits. Recommend an option, obtain the required decision, and then update plans and tell the people affected.
A website project has a $60,000 budget, ten weeks, and 12 pages plus an online store. The sponsor requests launch in eight weeks for a trade fair.
| Option | Effect on delivery | Cost or consequence |
|---|---|---|
| Add a developer for four weeks | Full scope at week 8. | Four weeks at $2,500 adds $10,000; total $70,000. |
| Launch the pages first | Pages at week 8, store later. | Similar cost, but store sales begin later. |
| Skip most testing | Saves testing time. | More risk of faults that damage the launch benefit. |
The extra developer raises the budget by about 16.7%. The sponsor must weigh that cost against the later store sales under the reduced-scope option and the quality risk of cutting tests.
Calculate the limit of authority
A tolerance is an agreed range within which a management level may act. The website project manager has a cost tolerance of 5% of the $60,000 budget: $3,000. The extra developer costs $10,000, more than three times that allowance. Also, the choices change agreed objectives. The sponsor must decide between more funding and reduced launch scope.
For a separate stage budget of $40,000 with a tolerance of ±10%, the allowed range is $36,000 to $44,000. A $43,000 forecast is within that range. A $45,500 forecast is $1,500 above the upper limit and must be escalated before the spending happens. Managing by exception combines continuous monitoring with escalation when a breach is forecast.
Check the remaining room before committing
With the $40,000 stage, the upper limit remains $44,000 even after the forecast reaches $43,000. Only $1,000 of cost headroom remains. A further $2,500 would produce the $45,500 forecast and its $1,500 breach. Comparing the added $2,500 with the original $4,000 allowance would wrongly ignore the amount already used.
Cost is only one boundary. An option can stay below $44,000 while changing scope or a date the manager cannot alter. Check every affected authority limit before approving it. If an option exceeds one, bring the sponsor the forecast and alternatives; being within cost tolerance does not grant authority over all objectives.
Distinguish a recommendation from an approval. The manager can recommend the higher-cost website option because it protects launch scope. That judgment does not authorize the spending. After a sponsor decision, the approved cost, date, and scope become the basis for updated plans and reporting.
Avoid hidden additions
Scope creep is gradual, uncontrolled expansion without matching changes to time, cost, or resources. Gold plating is the team adding extras nobody requested. A change control process exposes each addition and its effects so it can be approved or declined.
Adding people also has costs beyond pay. New members need time to learn, and coordination increases. A late addition to complex work may bring little time saving or even slow the team down. Estimate the real effect before promising a faster finish.
Write decisions in a decision log and reflect them in the current plan.
Key Takeaways
- Compare each option against priorities, constraints, risks, quality, and benefits.
- Tolerances define delegated authority.
- Escalate a forecast breach before the limit is actually exceeded.
- Scope creep and gold plating hide additions that need visible decisions.
- Adding people late can increase learning and coordination work.
- Record decisions and update the plan people use.
4Lead the work and make responsibilities clear
Projects need both senior support and day-to-day coordination. The sponsor keeps the business reason and resources in place; the project manager brings people and work together within agreed authority. Other roles supply expertise, express user needs, and build the result. Clear responsibilities help those people act without confusion. Leadership, emotional intelligence, and ethical choices then shape how they raise problems, resolve conflicts, and earn trust.
4.1 The sponsor keeps the business purpose in view
The sponsor provides resources and support and is accountable for making the project possible. Usually a senior manager with authority over funding and priorities, the sponsor owns the business case and expected benefits.
Keep senior support active
Before work starts, the sponsor builds or approves the business case, secures resources, champions the project, approves its authorization document, and appoints the project manager. During delivery, the sponsor sets priorities, removes obstacles beyond the team’s authority, approves major changes, and checks whether the work remains justified at decision points.
At closure, the sponsor accepts the result and formally closes the project. Afterward, the sponsor or a business owner tracks benefits as people use it. Funding the work at the start is only one part of sponsorship. Agree regular meetings and escalation routes so decisions reach the sponsor in time, with options and a recommendation.
Separate direction from daily management
| Sponsor directs | Project manager coordinates |
|---|---|
| Business purpose and intended achievements. | How the agreed work is organized. |
| Funding, priorities, and decisions outside delegated authority. | Daily progress, risks, and changes within authority. |
| The business case and expected benefits. | Delivery integration and handover. |
Approving an extra $15,000 for testing required by a new regulation belongs to the sponsor. Assigning a tester to a module belongs to daily management. Direct task orders from the sponsor can give team members conflicting priorities.
Represent business, users, and suppliers
Larger projects often use a steering committee or project board. PRINCE2 defines three board roles:
- Executive: represents the business and owns the business case; closest to the general sponsor role.
- Senior User: represents users and the benefits the result should bring.
- Senior Supplier: represents those designing and building the result and commits their resources.
For a customer-service system, these might be the chief operating officer, head of customer service, and IT director or vendor account manager. They bring value for money, usefulness, and technical feasibility into decisions.
One person can hold several roles on a small project. Sponsor, customer, and user remain distinct responsibilities even when the names overlap.
Key Takeaways
- The sponsor owns the business case, secures support, and directs major decisions.
- Sponsor involvement continues through delivery, closure, and benefit follow-up.
- The project manager manages daily work within delegated authority.
- PRINCE2 board roles represent business, user, and supplier interests.
- One person can hold several roles, but their responsibilities remain distinct.
4.2 Coordinate people without assuming unlimited authority
The project manager leads the team responsible for achieving the project’s objectives. The job is to integrate and coordinate the work, support people, and prepare the result for operational use.
Bring the parts together
A supplier’s delivery affects installation, testing, and training. The manager connects those plans, tracks progress, communicates with stakeholders, manages risks and issues, handles changes within authority, and reports the actual position. Closure includes handover to operations.
The manager’s everyday roles vary: initiator gets work moving; negotiator agrees resources and dates; listener hears concerns; coach helps people develop; facilitator helps a group reach decisions. On a small project, the manager may also be a working member doing specialist tasks.
Team members estimate and perform their own work, report honestly, and raise problems early. Many organize their daily tasks themselves. Coordination makes dependencies clear while allowing specialists to use their expertise.
Understand the authority available
| Structure | Authority over people and budget |
|---|---|
| Functional | Department heads direct staff; the project manager has little authority. |
| Matrix | Functional and project managers share authority. Weak, balanced, and strong describe the project manager’s share. |
| Projectized | The project manager directly controls the team and budget. |
Around the project, functional managers provide people and expertise. Customers and users state needs and accept results. Suppliers deliver under contract. A PMO supports projects with standards, templates, training, and reporting; some PMOs also direct projects.
Resolve a shared-resource conflict
Two department heads need the same engineer in weeks 5 and 6. First negotiate a feasible allocation: move a task or find another qualified person. If the unresolved conflict threatens agreed dates, escalate to the sponsor with options and effects. A project title does not grant control over departmental staff.
PMI’s Talent Triangle combines ways of working (suitable approaches and techniques), power skills (communication, empathy, collaboration, and leadership), and business acumen (strategy and finance). IPMA groups comparable territory as practice, people, and perspective. A manager needs these together when a problem involves delivery technique, relationships, and business priorities.
Key Takeaways
- The project manager integrates and supports delivery across the whole project.
- Team members carry out specialist work and raise problems early.
- Functional, matrix, and projectized structures give different levels of authority.
- Functional managers, users, suppliers, and the PMO contribute distinct support.
- Negotiate resource conflicts, then escalate unresolved priority decisions.
- Effective project management combines technical, interpersonal, and business skills.
4.3 Build trust through leadership, emotional intelligence, and ethics
Reliable delivery needs both management and leadership. Management organizes work through planning, control, processes, and authority. Leadership gives direction, builds trust, and helps people commit to the work. A project manager needs both, particularly when the team spans departments.
Match the response to the need
After a supplier delays delivery by two weeks, updating the schedule, reordering tasks, and notifying stakeholders are management actions. Meeting a discouraged team, explaining why the launch still matters, and agreeing a recovery approach are leadership actions. A revised plan gives people structure; leadership helps them act on it.
Any team member can lead by offering a solution or supporting a colleague. Servant leadership emphasizes removing obstacles, protecting focus, and helping others grow. It can give a team more ability to solve its own problems within agreed boundaries.
Use emotional information well
Emotional intelligence means recognizing and managing your emotions and responding well to other people's emotions. A common model has four parts:
- Self-awareness: notice what you feel and how it affects you.
- Self-management: choose how to respond instead of reacting impulsively.
- Social awareness: recognize others' feelings and perspectives, including empathy.
- Relationship management: communicate and handle difficulties constructively.
Some models identify motivation as a fifth part. The practical skill is to understand emotions and use that understanding in your actions.
In a status meeting, a team member snaps at a colleague. The project manager notices their own irritation, stays calm, and checks privately afterward. The person explains that two projects are drawing on the same work time. The manager helps rebalance the load. This response addresses both the behavior and its cause. Avoiding the conversation would leave the conflict in place.
Apply ethical values to daily decisions
PMI's Code of Ethics and Professional Conduct centers on responsibility, respect, fairness, and honesty. Responsibility means owning decisions and consequences. Respect means consideration for people and resources. Fairness means impartial decisions free of favoritism and self-interest. Honesty means truthful communication and conduct.
A late project should be reported accurately, with a recovery plan. A manager whose friend's company is bidding for a contract discloses the conflict and steps back from the decision. Someone asked to do work beyond their competence explains the gap. Confidential salary information stays confidential. These ordinary choices shape trust as directly as major financial decisions do.
Finally, distinguish responsibility from accountability. Responsible people perform the work. The accountable person answers for the result and has the final say. Several people can share the work; each task or decision should have one accountable person so final authority is clear.
Key Takeaways
- Management organizes and controls work; leadership builds direction and commitment.
- Emotional intelligence supports calm, direct action on difficult issues.
- Responsibility, respect, fairness, and honesty guide everyday professional choices.
- Responsible people do the work; one accountable person answers for the result.
5Use standards and principles to guide decisions
Shared frameworks give project teams a common language, but they serve different purposes. A guide describes good practice, a method organizes decisions and responsibilities, and a competence baseline helps people develop their abilities. Compare those purposes, then use the PMBOK Guide and PRINCE2 principles in practical situations. The aim is to recognize how the guidance changes a decision about value, quality, authority, or the people affected.
5.1 Choose guidance that answers the right question
Standards and frameworks let people from different organizations work with a shared vocabulary and a common understanding of good practice. They also support consistent ways of working and professional development. The main references differ in what they describe and prescribe.
Four types of guidance
| Type | Question it helps answer | Examples |
|---|---|---|
| Body of knowledge or guide | What does good project management involve? | PMBOK Guide; APM Body of Knowledge. |
| Method | Who does what, and when? | PRINCE2. |
| Competence baseline | What must a capable individual be able to do? | IPMA ICB4. |
| International standard | What high-level guidance is agreed internationally? | ISO 21502:2020. |
The PMBOK Guide, published by the Project Management Institute, or PMI, is a guide and standard, not a fixed step-by-step method. Its eighth edition, published in November 2025, has six principles and seven performance domains: governance, scope, schedule, finance, stakeholders, resources, and risk. Its five focus areas are initiating, planning, executing, monitoring and controlling, and closing. The guidance supports different delivery approaches without prescribing one sequence.
PRINCE2, now owned by PeopleCert and originating with the UK government, is a process-based method. Version 7, released in 2023, integrates principles, people, practices, processes, and project context. Its seven practices are business case, organizing, plans, quality, risk, issues, and progress. Seven processes provide a management structure from before the start through closure.
IPMA, the International Project Management Association, is a federation of national associations. Its Individual Competence Baseline version 4, or ICB4, describes perspective, people, and practice competences. It has 28 elements for project management and 29 for program and portfolio management. The emphasis is the individual's ability to apply knowledge and skills.
The UK's Association for Project Management publishes the APM Body of Knowledge. Its eighth edition appeared in April 2025. It covers concepts, functions, and activities across projects, programs, and portfolios. ISO 21502:2020 gives project management guidance, while ISO 21500:2021 provides the context and shared concepts for projects, programs, and portfolios.
Combine and tailor the references
A housing project can use PRINCE2 for board responsibilities and stage approvals, draw on PMBOK or APM guidance for techniques, and use ICB4 to identify development needs. Each answers a different question, so combining them can be useful.
Terms also vary. PRINCE2's Executive is close to the general sponsor role. Its current practices were called themes in earlier versions. Match the meaning before assuming different labels describe different ideas.
All the main frameworks expect tailoring to size, complexity, risk, and context. A small project needs lighter documentation than a national infrastructure project. In PRINCE2, tailoring changes application and formality while all seven principles still apply. Knowing the terminology or holding a certificate does not replace the ability to make sound decisions in real work.
Key Takeaways
- A body of knowledge, method, competence baseline, and international standard serve different purposes.
- The PMBOK Guide describes good practice without prescribing one fixed sequence.
- PRINCE2 structures management; ICB4 develops individual competence.
- Frameworks can be combined and tailored to context.
- Match the meaning of terms when moving between frameworks.
5.2 Put the six PMBOK principles into action
A principle guides behavior and decisions across projects. It differs from a process, which describes activities, and a performance domain, which identifies an area of practice. The PMBOK Guide's eighth edition has six principles that work together.
Adopt a holistic view
See the project as connected parts within a wider organization and environment. Moving a launch forward two weeks also changes marketing, warehouse staffing, and customer support needs. Check those relationships before deciding. A locally convenient change can create a larger problem elsewhere.
Focus on value
Judge work by its contribution to outcomes and benefits. If customers struggle with checkout, fixing that step can create more value than adding a feature few people use. When the expected value of the whole project disappears, this principle can support stopping it. Completing a list of outputs is useful only through what those outputs enable.
Embed quality into processes and deliverables
Build quality in from the start. Clear requirements, early reviews, and testing during the work help prevent defects or find them while they are cheaper to fix. A one-hour requirements review can catch a misunderstanding that would take weeks to correct after development. Inspection at the end cannot undo all the time spent building the wrong result.
Be an accountable leader
Own decisions and consequences, act with integrity, and set an example. A manager who underestimated the work tells the sponsor promptly and proposes a response. Hiding the gap prevents the people with authority from acting. This principle applies to everyone exercising leadership, including team members without a management title.
Integrate sustainability within all project areas
Consider environmental, social, and economic effects throughout the life of the result. Heating equipment may cost more to buy but use less energy over 20 years. The choice affects running costs and emissions, while the installation plan can limit disruption to neighbors. Sustainability reaches beyond purchase price and the project's closing date.
Build an empowered culture
Give people information, authority within agreed limits, and the confidence to contribute or raise concerns. A tester who finds a serious Friday afternoon defect should be able to report it promptly. An empowered culture combines freedom to act with clear boundaries and support, making bad news available when the team can still respond.
Link authority with accountability
Empowerment gives the team room to act; accountability makes the limits and consequences clear. A tester may investigate a fault within their authority while a manager brings a launch decision outside tolerance to the sponsor. Encouraging the report helps the organization see the problem. Clear decision rights determine who can commit to a response.
This also explains why embedded quality reaches into the working process. Agreeing requirements and checking work early gives the people making decisions better information. A team can welcome concerns while still requiring evidence that the product meets its quality criteria. Safe participation supports the checks; it does not remove them.
Read situations through more than one principle
Checking residents' access during road construction can express both a holistic view and sustainability. An honest report on a defect can express accountable leadership and an empowered culture. The aim is to explain what the action protects, not to force every situation into a single label.
The seventh edition had twelve principles; the eighth organizes them into six. Ideas such as stewardship, teamwork, complexity, risk, adaptability, and change continue in the current principles and performance domains, while tailoring is treated separately. Use the edition to understand a list's wording and structure. Principles guide continuing choices; producing a report or completing a checklist is not, by itself, evidence that the principle is being applied.
Key Takeaways
- A holistic view checks effects across connected work and the wider environment.
- Value and embedded quality guide what to build and how to build it.
- Accountable leadership makes decisions and their consequences visible.
- Sustainability considers environmental, social, and economic effects over the result’s life.
- Empowerment combines information, safe participation, and bounded authority.
- One action can apply several principles together.
5.3 Apply PRINCE2 principles and develop IPMA competences
PRINCE2's seven principles define the method: all seven must apply for a project to be a PRINCE2 project. IPMA ICB4 approaches effective project management through individual competence. The two perspectives can support the same work without serving the same purpose.
Keep the work justified and learn as you go
Ensure continued business justification: confirm a valid reason to start and keep reviewing it at decision points. If the reason disappears, change or close the project. Learn from experience: use earlier lessons when planning, record new lessons during delivery, and share them at the end. Learning is useful while choices can still change.
Clarify authority and results
Define roles, responsibilities, and relationships: make clear who decides, who does the work, and where business, user, and supplier interests are represented. Focus on products: define outputs and their quality criteria before starting work on them. A product can be software, a document, or a service; the principle is not limited to manufactured goods.
Control commitment and delegated authority
Manage by stages: divide the project into management stages. The board checks an updated plan and business case before approving the next commitment. Stages are control points; they can support iterative delivery.
Manage by exception: set tolerances and monitor forecasts. An eight-week stage with a time tolerance of ±1 week can run up to nine weeks. When the forecast reaches 9.5 weeks, the manager escalates immediately. Waiting until week nine passes would waste the warning supplied by the forecast.
Tailor to suit the project: adapt the method to environment, size, complexity, importance, capability, and risk. A four-week internal effort can use a one-page business case and combined roles. A large public project needs more formal arrangements. Tailoring does not remove any of the seven principles.
Suppose a competitor launches a similar product halfway through a project and expected sales fall by half, taking forecast benefits outside tolerance. Update the business case and escalate. The board decides whether to change, pause, or close the work. Continued justification explains why the decision is needed; exception management explains why it goes upward now.
Keep the two approval mechanisms distinct
A stage boundary is a planned decision point before another commitment. A forecast exception can arise between those points. The manager cannot postpone the 9.5-week forecast until the scheduled stage review: the current delegation already stops at nine weeks.
Stage approval and exception management therefore answer different questions. The first asks whether the board authorizes the next part using current plans and justification. The second asks whether a decision in the current work has moved beyond delegated authority. Both give the board a chance to act before the organization commits more than it has agreed.
Compare behavioral guidance and competence
PRINCE2's continued business justification overlaps with PMBOK's focus on value. Clear roles support accountable leadership; product quality criteria support embedded quality. PRINCE2 requires its principles as part of a defined method. PMBOK principles guide behavior without prescribing that management structure.
ICB4 asks what a person can do in three areas:
- Perspective: understand strategy, governance, compliance, power and interests, and culture.
- People: communicate, lead, work with others, negotiate, handle conflict, and act with integrity.
- Practice: manage objectives, scope, time, quality, finance, resources, risk, stakeholders, and change.
A manager can use PRINCE2 to clarify an escalation route and ICB4 to identify the negotiation or business understanding needed to use that route well.
Key Takeaways
- PRINCE2 requires all seven principles, with an approach tailored to the project.
- Continued justification and learning shape decisions throughout delivery.
- Products and roles need clear expectations before work starts.
- Stage approval controls commitment; tolerances define delegated authority.
- Managing by exception requires escalation when a breach is forecast.
- ICB4 develops perspective, people, and practice competences.
- PRINCE2 and PMBOK principles overlap while serving different management approaches.
Projects and Project Management examples
1From a service problem to a coordinated change
13 steps
- 1IntroductionFind the effort with an endpoint
A repair service answers booking calls every day. It now wants one shared booking system across three sites.
Find the temporary effort: what changes, what marks its end, and who uses the result afterward? The daily service continues around that change.
- 2ExplanationSeparate change from recurring service
Answering booking calls is operations: repeated work sustaining the service. Introducing the shared system is a project: temporary work creating a particular result.
The same people can do both. Classify the purpose and endpoint of the work, not the team’s name.
- 3ExampleTest temporary and unique
The team has ten weeks to build, test, and introduce the system using familiar software.
It is temporary because it has an endpoint. The result is unique because this combination of sites, requirements, users, and timing has not been delivered before. Repeated tasks can contribute to it.
- 4ChallengeA deadline every day
Each site must send its usual closing report by 18:00 every day. Does that deadline make the reporting work a project? Explain.
---reveal---
No. This is an ongoing, repeated service activity, so it is operations. A deadline alone does not establish a temporary effort creating a unique result. A separate effort to introduce a new reporting system could be a project.
- 5ConnectionPrepare the people who take over
Training, instructions, and an agreed support arrangement prepare handover to daily operations.
As the software becomes clearer, the team refines its training plan: progressive elaboration. The system can keep working for years after the project team is reassigned.
- 6ExplanationDescribe the change people need
The current state is separate diaries and calls between sites. The desired future state is one booking service staff can check together.
Customers want easier booking, and the organization wants closer cooperation. The project has both a stakeholder driver and a strategic driver.
- 7Key InsightA system must become part of work
Staff could keep separate diaries even after installation. The intended change needs adoption.
Training shows how to use the service; communication explains the switch; support helps with difficulties. These prepare people to turn a delivered system into changed work.
- 8ChallengeIdentify the driver and the missing link
A supplier introduces a new booking tool. The service chooses it to remove repeated data entry, but offers staff no guidance on using it. What is the improvement driver, and what must happen for the change to work?
---reveal---
The driver is process improvement: removing repeated entry. Staff must adopt the tool in their work, supported by training, communication, or help. Buying it alone does not change the process.
- 9TipKeep the product’s life separate
The booking tool can pass through an initial build, routine support, and a redesign. The product’s life spans them all; each project has its own endpoint.
Tailoring adjusts planning, documentation, and control to the size and risk of each effort.
- 10ExplanationCoordinate work for a shared benefit
Suppose the organization adds separate projects for shared customer records and staff training. The intended benefit depends on all three working together: staff must find the right information and know how to use the booking tool.
A program coordinates these related projects for benefits that separate management would not achieve. The relationship between the results explains the program.
- 11ExamplePlace the program in a wider investment mix
The organization also funds an unrelated roof repair project. Leaders compare that work with the service-change program when allocating money and staff.
The portfolio groups this mix around strategy. The roof and booking system need no delivery dependency. Projects deliver particular results; the program coordinates combined benefits; the portfolio aligns the overall investment.
- 12ChallengeBuild the arrangement from the purpose
A service funds two changes that need joint delivery for a shared benefit, plus a separate equipment replacement. All support its strategy. How can it organize them without calling every change one program?
---reveal---
Coordinate the two related changes as a program. Put that program and the standalone equipment project in a portfolio. Shared strategy supports the portfolio; the joint benefit supports the program.
- 13RecapUse the purpose to choose the level
Ask what the management effort must achieve:
- Operations: sustain a repeated service.
- Project: deliver a unique result through temporary work.
- Program: coordinate related work for combined benefits.
- Portfolio: align the investment mix with strategy.
Then prepare the handover and adoption that connect the temporary change to the people who will use it.
2Trace a system’s value and test its success
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionLook beyond installation
- 2ExampleName the output and the outcome
- 3ExplanationIdentify the improvement and its worth
- 4ExampleCalculate the net cash saving
- 5ExampleRecover the initial investment
- 6ChallengeCapacity or cash?
- 7ConnectionKeep an owner for the later benefits
- 8ExplanationWrite two sets of success questions
- 9ExampleGive the criterion a target and a date
- 10ChallengeAcceptance and purpose
- 11ChallengeA useful result with a delivery overrun
- 12RecapKeep the measures connected
3Make a trade-off and check who can approve it
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake the change visible
- 2ExplanationIdentify the connected limits
- 3ExampleFix the priority before choosing
- 4ChallengeReduce features without hiding defects
- 5ExplanationClassify the facts before responding
- 6TipMake uncertainty specific
- 7ChallengeUpdate a planning belief
- 8ExplanationPut real options beside the priorities
- 9ExampleCalculate the upper spending limit
- 10ExampleCompare the forecast after the change
- 11ExampleMake the scope alternative explicit
- 12ChallengeTest cost and scope authority together
- 13Key InsightUnrequested work also uses the budget
- 14ChallengeAct before the limit is crossed
- 15RecapFinish with a recorded decision
4Resolve a team problem through clear roles
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionA resource problem becomes a leadership task
- 2ExplanationKeep business ownership with the sponsor
- 3ExampleRepresent three different interests
- 4ChallengeChoose the decision owner
- 5ExplanationCoordinate the work people depend on
- 6ExampleRead authority from the structure
- 7ChallengeHandle a shared specialist
- 8ConnectionDevelop the ability the problem needs
- 9ExplanationUse both management and leadership
- 10ExampleRespond to an emotional signal
- 11ChallengeBe fair when a relationship overlaps work
- 12ChallengeReport the delay and request the right help
- 13RecapMatch responsibility, authority, and behavior
5Use frameworks to improve real decisions
20 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake a framework useful
- 2ExplanationDistinguish a guide from a method
- 3ConnectionAdd a competence view and agreed guidance
- 4ChallengeMatch three needs to three references
- 5ExampleCheck the wider effects
- 6ExamplePrioritize the improvement people need
- 7ExamplePrevent a defect early
- 8ExampleOwn a decision’s consequences
- 9ExampleConsider effects over the result’s life
- 10ExampleMake it safe to raise bad news
- 11ChallengeIdentify the actions behind the labels
- 12ExplanationKeep a reason to continue
- 13TipUse lessons while decisions can change
- 14ExplanationDefine the result and decision roles
- 15ExampleApprove the next commitment in stages
- 16ExampleMonitor limits between approval points
- 17ChallengeTailor the method while keeping it intact
- 18ConnectionDevelop the person using the method
- 19ChallengeCombine justification and authority
- 20RecapConnect guidance with action
Projects and Project Management practice questions
Set 1: Recognize the work and its purpose10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Apply value, authority, and principles10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Connect delivery, people, and benefits10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Judge changing plans and responsibilities10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Resolve connected project dilemmas10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Acceptance criterion
Accountability
Accountable leadership
Assumption
Assumption log
B
Benefit
Body of knowledge
Business acumen
Business case
C
Competence baseline
Conflict of interest
Constraint
Continued business justification
Current state
D
Decision log
Dependency
Desired future state
Dis-benefit
E
Embedded quality
Emotional intelligence
Empowered culture
Escalation
Executive
F
Flexibility matrix
Focus on value
Functional organization
G
Gold plating
Grade
H
Handover
Holistic view
I
Intangible value
International standard
Issue
Issue log
K
Key performance indicator
L
Leadership
Learning from experience
M
Manage by exception
Management
Management stage
Matrix organization
Method
O
Operations
Opportunity
Outcome
Output
P
People
Performance domain
Perspective
Portfolio
Practice
Principle
Product
Product focus
Program
Progressive elaboration
Project
Project board
Project driver
Project management office
Project management success
Project manager
Project success
Projectized organization
Q
Quality
R
Responsibility
Risk
Risk register
S
Scope
Scope creep
Senior Supplier
Senior User
Servant leadership
Simple payback period
Sponsor
Strategic objective
Success criterion
Sustainability
T
Tailoring
Tangible value
Termination
Threat
Tolerance
Trade-off
Triple constraint
V
Value
About this lesson