Project Requirements and Scope

Learn how a project turns stakeholder needs into a clear scope that stays under control. You elicit requirements with interviews, workshops, surveys, observation and other techniques, write them so they can be tested and prioritized, and trace each one to the work that delivers it. You then write a scope statement with exclusions and acceptance criteria, break the work down into a work breakdown structure with a WBS dictionary, and keep the scope under control with a change control process that stops scope creep and leads to formal acceptance of each deliverable. One office move for 120 staff runs through the material as a worked example.

BeginnerLesson 4 of 9 in Project Management Foundations Course

What you will learn

  1. Explain what requirements, scope and deliverables are, how detailed scope grows out of the project charter, and how predictive, adaptive and hybrid projects plan and handle scope.
    • Tell requirements, scope and deliverables apart
      Define requirements, product scope, project scope and deliverables, sort requirements into their main types, and see how the charter's high-level scope becomes detailed scope.
    • Plan scope management in predictive and adaptive projects
      Describe what a scope management plan and a requirements management plan settle, and compare how predictive, adaptive and hybrid approaches define, fix and change scope.
  2. Draw out requirements from the right stakeholders with suitable techniques, write them so they can be tested and prioritized, and trace each one from its source to the deliverable and the check that satisfy it.
    • Choose and use elicitation techniques
      Match interviews, workshops, focus groups, surveys, observation, document analysis, prototypes and other techniques to the situation, and plan an elicitation that reaches every relevant stakeholder.
    • Write, analyze and prioritize requirements
      Turn raw stakeholder input into clear, testable requirements, resolve conflicts between stakeholders, prioritize with MoSCoW and get the requirements documentation approved.
    • Trace requirements with a traceability matrix
      Build a requirements traceability matrix, use it forward and backward to find gaps and unrequested work, and use it to judge the impact of changes and readiness for delivery.
  3. Write a scope statement that sets out the product, the deliverables, the boundaries, the assumptions and the constraints, and attach acceptance criteria that make every deliverable checkable.
    • Write a project scope statement
      Turn approved requirements and the charter into a scope statement with a product scope description, deliverables, exclusions, constraints and assumptions.
    • Write acceptance criteria that can be tested
      Define measurable acceptance criteria for deliverables and requirements, and tell acceptance criteria apart from project success criteria and the definition of done.
  4. Decompose the project scope into a deliverable-oriented work breakdown structure, check it against the 100% rule, document each element in the WBS dictionary, and connect it to schedule, cost and responsibility planning.
    • Decompose the scope into a work breakdown structure
      Build a numbered, deliverable-oriented WBS down to work packages, choose how to organize its top levels and decide when to stop decomposing.
    • Check a WBS and connect it to the rest of the plan
      Apply the 100% rule and the no-overlap rule, tell a WBS from a product breakdown structure, and use work packages for scheduling, cost estimates and responsibility assignment.
    • Write the WBS dictionary
      Document each WBS element, especially each work package, with its description, owner, acceptance criteria, estimates and dependencies, so the short WBS labels have one agreed meaning.
  5. Recognize scope creep and gold plating, run a change control process with impact analysis and recorded decisions, and verify, validate and accept deliverables against the scope baseline.
    • Recognize and prevent scope creep
      Explain scope creep and gold plating, identify their causes and early signs, and prevent them with clear scope, sign-off and a single route for changes.
    • Run a change control process
      Log, assess, decide and implement scope change requests, use impact analysis and decision authority, and explain how configuration management supports change control.
    • Verify, validate and accept deliverables
      Check deliverables against requirements and acceptance criteria, obtain formal acceptance from the customer or sponsor, and use the results to keep scope under control until handover.

Project Requirements and Scope study guide

5 chapters

1

Understand requirements, scope and how scope is managed

A project begins with a purpose, but a purpose alone cannot tell a team what to build. Requirements describe the needs to meet; scope sets the product's boundaries and the work needed to deliver it. You will separate these ideas, recognize different kinds of requirements, and see how the charter becomes a usable plan. You will also compare how predictive and adaptive teams make scope decisions as information grows.

1.1 Tell requirements, scope and deliverables apart

A requirement describes a condition or capability needed to meet a business or stakeholder need. It gives the team something to satisfy. A task describes work the team does to satisfy it.

Separate the need, the result, and the work

In an office move, “Every desk has a wired network port” is a requirement. Buying 120 network cables is a task. The installed, tested network and its test report are deliverables: unique, verifiable products, results, or capabilities. A deliverable can be internal, such as an approved floor plan, or external, such as the office handed over to the sponsor.

Product scope describes the features and functions delivered. A meeting room that seats 12 belongs here. Project scope includes all the work to provide those features: planning, buying furniture, installing equipment, testing, and managing the project. A list of physical deliverables alone misses work such as reporting, coordination, and handover.

Recognize different kinds of requirements
TypeWhat it describesOffice move example
BusinessThe organization's high-level need“Reduce office rent by 20%.”
StakeholderA person or group's need“Finance needs a lockable payroll room.”
Functional solutionWhat the product does“The access system records each badge entry.”
Nonfunctional solutionHow well or under what conditions it works“The badge reader unlocks the door within 2 seconds.”
TransitionA temporary need during the move to the new state“All staff learn to use door badges before move day.”
ProjectA condition on carrying out the project“Obtain the floor plan approval before fit-out.”
QualityA standard or criterion the work or result must meet“Electrical work passes the building's safety inspection.”

Functional and nonfunctional requirements are both solution requirements. Ask explicitly about performance, reliability, security, and usability. People may describe the action they want while taking an acceptable level of performance for granted.

Keep the need separate from its design

“Staff can hold private video calls” states a need. “Install six phone booths” names a possible design. Recording the design first can shut out a less costly solution that serves the same need. Elicit the need, compare possible solutions, and keep a link from the chosen solution back to that need.

The project charter authorizes the project and establishes its high-level purpose, objectives, deliverables, and boundaries. Detailed requirements and scope develop within those boundaries. A proposal that goes beyond them needs the sponsor's decision.

Record the conditions shaping the plan too. An assumption is treated as true without proof: “The landlord completes the fire inspection by June 1.” A constraint is a fixed limit: “The budget is $240,000” or “The old lease ends July 31.” A failed assumption or changed constraint can force a scope decision, so neither should stay hidden in someone's expectations.

Key Takeaways

  • A requirement states a need; a task is work done to meet it; a deliverable is a verifiable result.
  • Product scope describes features and functions. Project scope includes all required delivery and management work.
  • Elicit nonfunctional requirements explicitly, including performance, security, reliability, and usability.
  • Record the need before choosing a design, and trace the design back to that need.
  • Detailed scope develops from the charter. Record assumptions and constraints alongside it.

1.2 Plan scope management in predictive and adaptive projects

Scope management keeps the project focused on all required work and only required work. It covers planning, requirements, scope definition, work breakdown, acceptance, and control. The team first agrees how these decisions will be made.

Set the rules for decisions

The scope management plan explains how to define, develop, monitor, control, and validate scope. It identifies who writes and approves the scope statement, how the WBS is built and maintained, who accepts deliverables, and how changes are decided.

The requirements management plan explains how to elicit, analyze, document, prioritize, trace, and change requirements. It can name the elicitation methods, prioritization method, traceability fields, and requirement approval authority. These plans guide the work; they are different from the requirements and scope records produced through that work.

Choose how much scope to fix early
ApproachHow scope is plannedHow it stays controlled
PredictiveMost scope is detailed and approved earlyChanges to the baseline follow formal change control
AdaptiveScope evolves through short iterations and feedbackAn ordered backlog, iteration planning, acceptance criteria, and a definition of done guide delivery
HybridDifferent parts use different approachesEach part follows its agreed controls within shared project boundaries

The scope baseline has three parts: the approved scope statement, WBS, and WBS dictionary. A predictive team measures work against this agreement and changes it through the approved process. “Fixed baseline” means a controlled reference, not a ban on learning or change.

In adaptive work, time and cost per iteration are usually fixed, and content varies with priority. The product owner orders the backlog by value and priority. The team selects iteration work with the product owner, considering capacity and the iteration goal; in Scrum, Developers make the selection. Clear criteria and a shared definition of done prevent unfinished work from being presented as complete.

Add detail as it becomes useful

Progressive elaboration means adding planning detail as more becomes known. Rolling wave planning puts that into practice: detail near-term work and keep later work at a higher level until it approaches. Predictive projects use this too. A high-level description of a distant phase can be a deliberate planning choice.

For the office move, a signed lease and known headcount support predictive planning for the fit-out. A staff intranet can develop through iterations as users try features. A hybrid WBS can show “staff intranet” as one deliverable while its features are refined within releases. The team still needs agreed boundaries and a route for deciding changes to them.

Key Takeaways

  • The scope management plan governs scope definition, work breakdown, acceptance, and changes.
  • The requirements management plan governs how requirements are gathered, analyzed, prioritized, and traced.
  • The scope baseline consists of the approved scope statement, WBS, and WBS dictionary.
  • Adaptive scope evolves through controlled prioritization, iteration planning, and clear completion checks.
  • Rolling wave planning details near-term work while leaving later work at a higher level.
  • Hybrid projects can plan a stable fit-out predictively and develop an intranet through iterations.
2

Elicit, document and trace requirements

People rarely hand a project team a complete, consistent list of needs. Some needs emerge in conversation; others become visible only when you watch the work. You will choose ways to elicit requirements, turn rough requests into clear statements, and decide their priority. A traceability matrix then connects each approved need to its source, its deliverable, and the evidence that it has been met.

2.1 Choose and use elicitation techniques

Elicitation is the active work of drawing out needs. People often know their jobs better than they can describe them. Useful elicitation combines questions with observation, existing evidence, and opportunities to react to a possible result.

Match the method to the gap

Start with the stakeholder register. Include people who use, provide, approve, or are affected by the result. A sponsor's view helps establish purpose, but reception staff may know daily steps the sponsor never sees.

TechniqueWhen it helpsWhat to watch for
InterviewAn expert, senior person, or confidential topic needs depthSeparate interviews can produce conflicting needs
Facilitated workshopDifferent functions need to resolve conflicts and agreeA neutral facilitator must let each group contribute
Focus groupSelected users can discuss expectations and attitudesIt explores user reactions, not cross-function approval
SurveyMany people can answer known, countable questionsIt is weak at discovering a problem nobody has described
ObservationRoutine actions are hard for people to recallWatch the actual workflow, including informal steps
Document analysisExisting rules and records constrain the workCheck leases, contracts, process descriptions, and lessons learned

An interview might open with “Walk me through a normal morning at reception.” Follow up on specific steps and confirm what you understood. A leading question such as “You want more meeting rooms, don't you?” pushes the person toward the interviewer's preferred answer.

Help people make needs visible

Brainstorming generates many possible ideas before judging them. The nominal group technique adds voting to rank ideas. Benchmarking compares plans or practices with those of similar organizations.

A prototype, mock-up, or storyboard lets people react to something they can see. A desk layout may expose a storage or privacy problem that an abstract discussion missed. A use case follows a user's interaction with a system toward a goal, including exceptions such as an unrecognized door badge. Adaptive teams often capture short user stories with acceptance criteria in a backlog.

Build a combined elicitation plan

For the move of 120 staff, use different methods for different information:

  1. Survey all 120 staff about attendance, seating, and parking needs.
  2. Interview the five department heads about space and storage.
  3. Observe reception and the mailroom for a day to find routine work that was not mentioned.
  4. Analyze the lease, building requirements, and IT equipment list.
  5. Facilitate a workshop with department representatives to settle conflicting requests.

Observation might reveal that the mailroom sorts deliveries on a counter absent from the proposed floor plan. The workshop can then compare that need with competing space requests. Confirm the resulting requirements with the people who supplied them and record unresolved questions. Without that confirmation, a neatly written record can still misrepresent what someone needs.

Key Takeaways

  • Choose elicitation methods for the information needed and the people involved.
  • Use open questions and confirm your understanding with the source.
  • Observation reveals routine steps; document analysis reveals existing constraints and evidence.
  • Workshops support agreement across functions; focus groups explore user expectations.
  • Combine methods so that one method covers gaps left by another.

2.2 Write, analyze and prioritize requirements

A request is a starting point for analysis. Before approving it, check what need it serves, whether its meaning is clear, and whether the project can deliver it alongside the other requirements.

Turn rough input into one checkable statement

Remove duplicates, separate needs from suggested designs, and split statements that contain separate demands. “Staff can book rooms and see who is in each room” contains two requirements. Separate IDs let them have different priorities, owners, and checks.

A sound requirement is clear, testable, complete, consistent, feasible, necessary, and traceable. Clear means it has one meaning. Testable means a reviewer can determine whether it is met. Feasible means it can be delivered within the project's constraints. Necessary and traceable mean it supports a known need and has an identifiable source.

Consider “The new office should have enough meeting rooms.” Nobody can test “enough” reliably. Replace it with “The new office has at least 8 bookable meeting rooms: 6 seating 4 to 6 people and 2 seating at least 12.” A reviewer can count the rooms and seats.

For performance, replace “The booking system is fast” with “The room-booking page loads within 2 seconds for at least 95% of requests during office hours.” The condition and threshold matter: a test outside office hours or a single quick response would not establish that result. Words such as “easy,” “as needed,” and “etc.” leave similar gaps unless the team replaces them with observable conditions.

Prioritize with MoSCoW
PriorityMeaningOffice move example
Must haveThe solution is unacceptable without itA wired port at every desk
Should haveImportant, but a workaround existsA quiet room on each floor
Could haveDesirable if time and budget allowA coffee machine in each meeting room
Won't have this timeAgreed to be left out of this project or releaseA rooftop terrace

“Won't have this time” records a present boundary; it does not promise a later release. If every request becomes a Must, the list gives the team no useful way to protect the deadline or budget. Ask what makes the solution unacceptable without each claimed Must, and record the agreed priority.

Resolve conflicts and get approval

When one group wants open-plan seating and another needs confidential work areas, return to the charter's business objectives. Make the trade-off visible, then refer the decision to the person with authority, usually the sponsor or product owner. Record both the decision and its reason.

Requirements documentation brings these decisions together. For each requirement, record its ID, description, type, source, priority, owner, acceptance criteria, and status. Key stakeholders review and approve the record. Approved requirements feed the scope statement; in a predictive project, later changes follow change control.

Key Takeaways

  • Analyze raw input for duplicate, conflicting, missing, and combined requirements.
  • Write one clear, testable requirement per statement, with an ID and a known source.
  • Replace vague adjectives with a measurable result and the conditions under which it must hold.
  • MoSCoW separates essential needs, important needs with workarounds, optional features, and agreed exclusions.
  • Resolve conflicts against business objectives through the authorized decision maker, then record the reason.
  • Get key stakeholders to review and approve the requirements documentation.

2.3 Trace requirements with a traceability matrix

A requirement can be well written and still disappear during planning. Traceability connects the need to the work and evidence that satisfy it. It also lets the team ask where a planned piece of work came from.

Build the links

A requirements traceability matrix (RTM) usually uses one row per requirement. The requirements management plan sets the fields worth maintaining. Useful columns include the ID, description, source, priority, business objective, WBS element or deliverable, test or acceptance check, and status.

RequirementPriorityWork or deliverableEvidence
R-01: Wired port at each of 120 desksMust3.1 Network cabling and Wi-FiPort test report
R-03: All staff trained on door badges before move dayMust5.2 Door-badge trainingTraining records
R-04: Lockable payroll room for financeShouldNo link yetNo check yet

The third row exposes a planning gap. Recording a need has not yet assigned work to deliver it or a way to check it. Confirm its agreed place in scope and add the missing links; do not mark it ready merely because someone has captured its description.

Trace in both directions

Forward traceability starts with a requirement and follows it to the deliverable and check. It asks whether the team will build and prove every approved need.

Backward traceability starts with work or a deliverable and follows it back to a requirement and objective. Suppose the WBS includes “lobby art installation” but no requirement supports it. The team must determine whether a valid need was missed in documentation or whether unrequested work should be removed. A requirement link gives the work a reason; it does not replace approval.

Use the matrix during delivery

When a requirement changes, its row identifies affected deliverables and tests. Follow related links too: a changed room layout may affect installation work and the checks tied to that layout. The matrix supports impact analysis by making these connections visible.

Before handover, review the evidence and status for each Must. For R-01, a report showing 112 working ports out of 120 leaves 8 failures. The network is not ready against that requirement. Record defects, repair them, retest, and update the row with the new evidence. “Installed” and “passed its check” are different statuses.

Keep the table current as plans change and results arrive. Excess columns become a burden if nobody updates them. In adaptive work, backlog items similarly connect needs, acceptance criteria, and completed work. A team can also retain a light RTM when a contract or regulator requires explicit evidence links.

Key Takeaways

  • An RTM connects a requirement's source and objective to its deliverable and acceptance evidence.
  • Forward tracing finds requirements without delivery or test coverage; backward tracing finds work without a justified need.
  • Use traceability links to find the effects of a proposed change.
  • Readiness depends on passed evidence for required criteria, not on an “installed” label.
3

Define the project scope

A project needs an agreed answer to two questions: what are we delivering, and how will we know it is acceptable? The scope statement makes that agreement visible, including the boundaries people might otherwise assume. Acceptance criteria turn the agreement into checks. You will build both from approved requirements and distinguish a deliverable's acceptance from the wider business results the project is meant to support.

3.1 Write a project scope statement

The project scope statement turns the charter and approved requirements into a detailed agreement about delivery. It describes the product, major deliverables, acceptance criteria, exclusions, constraints, and assumptions.

Make each part do a distinct job

The product scope description explains the features and functions being provided. Deliverables name verifiable results. Acceptance criteria say what those results must meet. Exclusions show what the project leaves out, while assumptions and constraints expose the conditions shaping the plan.

Not every request gathered during elicitation enters the project. Some are approved, some are deferred, and some are rejected. The scope statement makes the selected boundaries visible. Otherwise a stakeholder may reasonably expect an item that the team quietly left out.

Work through the office move

The product scope is “A furnished, networked office at 40 Harbor Street for 120 staff, ready for work on Monday, June 29.” Its main deliverables include:

  • An approved floor plan and completed electrical, lighting, painting, and flooring work.
  • Network cabling, Wi-Fi, and 120 working workstations.
  • Installed furniture, a moving service, and the cleared old office.
  • A staff briefing and door-badge training.

The statement explicitly excludes moving the paper archive, buying new laptops, and landscaping the parking lot. It records a budget constraint of $240,000 and the old lease ending July 31. It also records the assumption that the landlord completes the fire inspection by June 1.

These are different kinds of statements. The lease end is a limit the plan must respect. The inspection date is a planning belief that needs checking. If it proves false, the team investigates its effect and raises a change request when needed.

Write results people can recognize

“Approved floor plan” describes an outcome that a reviewer can inspect. “Work on the floor plan” describes activity without saying what completion looks like. Use result names in the deliverables list, and attach the agreed criteria for accepting each result. Detailed activity order belongs in the schedule.

An exclusion can prevent a large disagreement in a few words. “Office move” might sound as if it includes every object in the old building. “Moving the paper archive is not included” makes a consequential boundary explicit before anyone books that work.

Keep authority and detail aligned

The charter authorizes the project at a high level. The scope statement elaborates that agreement so the team can plan, estimate, and accept the work. Copying the charter leaves too many delivery questions unanswered. Adding an unsupported deliverable goes beyond elaboration and needs the sponsor's approval.

Once approved, the statement forms the scope baseline with the WBS and WBS dictionary. An approved boundary change must reach these connected records so the team keeps working from one agreement.

Key Takeaways

  • Write the product description, deliverables, acceptance criteria, exclusions, assumptions, and constraints.
  • Select requirements for this project explicitly and make deferred or rejected scope visible.
  • Name deliverables as verifiable results; put activity timing and sequence in the schedule.
  • Use exclusions to clarify boundaries that stakeholders might otherwise assume.
  • Elaborate the charter within its authority and baseline the approved statement with the WBS and dictionary.

3.2 Write acceptance criteria that can be tested

Acceptance criteria are the conditions a deliverable must meet before the customer or sponsor accepts it. Agree them before work starts, with the people who will accept and use the result. That gives the team a checkable meaning of finished.

Specify the result and its check

A useful criterion names the result, its measure or condition, and how it will be checked. For the office workstations:

“All 120 workstations start, log in to the network, and print a test page by 9:00 a.m. on move day; checked by the IT lead with a desk-by-desk checklist.”

The count, deadline, actions, and checklist make the criterion usable. “The electrician worked on the lighting” records effort, not an acceptable result. “The customer is happy” leaves the expected standard undefined.

The pattern Given …, when …, then … can expose missing detail. For example: “Given a staff member with an active badge, when they hold it to the main door reader, then the door unlocks within 2 seconds and the entry is logged.” The starting condition prevents confusion about invalid badges; the final clause states an observable outcome.

Keep thresholds faithful to requirements

Criteria can allow an agreed threshold. A staff briefing might require at least 90% of 120 staff to attend in person, with everyone else receiving the recording before move day. The threshold is 108 people. Writing both the percentage and count prevents disagreement about what must be achieved.

That briefing criterion cannot replace door-badge training for everyone. Training is a Must for all 120 staff before move day, so its criterion requires all 120 and uses training records as evidence. A lower threshold would change the requirement and needs approval through the change process.

Separate three meanings of success
TermWhat it applies toExample
Acceptance criteriaA particular deliverable or requirement“Meeting rooms match the approved floor plan.”
Project success criteriaThe project's wider objectives“Office rent falls by 20% within a year.”
Definition of doneShared completion conditions for adaptive items“Tested and documented.”

A deliverable can pass its checks before a business result can be measured. The rent result may be assessed after the move is complete. A shared definition of done supports consistent quality across items, while each item's acceptance criteria still describe its particular result.

Write criteria wherever delivery decisions need them: with requirements, with scope-statement deliverables, and with work packages in the WBS dictionary. Facilities can check room counts and sizes, while staff representatives help agree a measurable privacy standard for calls. Both perspectives belong in the agreement before the team builds the rooms.

Key Takeaways

  • Agree acceptance criteria before work starts, including an observable result and a way to check it.
  • A threshold must preserve the requirement; reducing a required standard needs an approved change.
  • Acceptance criteria concern deliverables, success criteria concern project objectives, and a definition of done sets shared completion conditions.
  • “Given …, when …, then …” states the starting situation, action, and observable outcome.
4

Break down the work with a work breakdown structure

A scope statement names the results a project promises. The work breakdown structure makes the work behind those results small enough to estimate, assign, and check. You will build a numbered hierarchy, test it for missing and overlapping work, and add the details that short labels cannot hold. These work packages become a shared starting point for the schedule, budget, and assignment of responsibility.

4.1 Decompose the scope into a work breakdown structure

A work breakdown structure (WBS) divides the total project scope into a hierarchy of manageable parts. It is deliverable-oriented: its branches describe what the work produces, down to work packages that someone can estimate, own, and check.

Build the hierarchy with the people doing the work

Start with the whole project. Identify major deliverables or phases, then decompose each into smaller results. For the office move, the major branches are project management, new office fit-out, IT and network, furniture and moving, and staff transition.

The numbered structure can look like this:

  • 1 Project management: 1.1 Plan; 1.2 Status meetings and reports; 1.3 Change control and closeout.
  • 2 New office fit-out: 2.1 Floor plan approved; 2.2 Electrical and lighting work; 2.3 Painting and flooring.
  • 3 IT and network: 3.1 Network cabling and Wi-Fi; 3.2 Workstations set up; 3.3 Phones and door access.
  • 4 Furniture and moving: 4.1 Furniture bought and installed; 4.2 Packing and moving service; 4.3 Old office cleared.
  • 5 Staff transition: 5.1 Staff briefing; 5.2 Door-badge training.

The code 3.2 means the second element under branch 3. It does not say that workstation setup happens second in time. Numbering identifies a place in the hierarchy; activity order comes later in the schedule.

Stop at a manageable work package

A work package sits at the lowest level of its WBS branch. It has one accountable owner and a verifiable result. Stop decomposing when the work can be estimated, scheduled, assigned, and checked. Building the WBS with package owners helps reveal work and boundaries a project manager might miss.

Two useful rules of thumb are the 8/80 rule, suggesting 8 to 80 hours of effort per package, and the reporting-period rule, suggesting a package should last no longer than one reporting period. They support judgment; they are not mandatory size limits. The network package in the example has a 96-hour estimate, so the team should consider whether it remains manageable or needs a further breakdown.

Organize for clarity without making a task list

The top levels can use major deliverables, phases, or phases with deliverables below them. In each case, use nouns or result names such as “network cabling installed.” A detailed list of actions belongs below the work packages in scheduling, where dependencies and dates can be added.

Later work may remain at a higher level as a planning package until the team knows enough to decompose it. Rolling wave planning adds detail when useful information arrives.

A control account is a management point, usually above work packages, where scope, budget, actual cost, and schedule are combined and compared. The IT lead could manage branch 3 as one control account containing its three work packages. Management work needs a branch too: leaving it out hides effort that the project still must fund and perform.

Key Takeaways

  • A WBS hierarchically decomposes the total project work into deliverable-oriented parts.
  • A work package has one accountable owner and a result that can be estimated, scheduled, and checked.
  • WBS codes show position in the hierarchy, not activity sequence.
  • The 8/80 and reporting-period rules guide package size; use judgment about manageability.
  • Planning packages hold later work at a higher level until it can be detailed.
  • Control accounts combine scope, budget, actual cost, and schedule for management.
  • Include project management work and build the WBS with the people responsible for delivery.

4.2 Check a WBS and connect it to the rest of the plan

A WBS must describe the full agreed scope without omissions, extra work, or overlaps. A tidy hierarchy and consistent totals help reviewers, but the scope statement and requirements determine whether its content is complete.

Apply the 100% rule at every level

The 100% rule requires all work in the defined scope, including project management, and no work outside it. Each parent's children must cover exactly that parent's work. Each piece of work appears once. If network-port testing sits under two packages, effort can be counted twice and responsibility can become unclear.

Check both content and estimates. Compare branches with the scope statement and traceability matrix, then add the child estimates to see whether they reconcile with their parent.

Investigate a roll-up gap

The IT lead estimates branch 3, IT and network, at 316 hours. The draft lists 3.1 Network cabling and Wi-Fi at 96 hours and 3.2 Workstations set up at 180 hours.

96+180=276

The gap is 40 hours. A review against the scope finds the omitted 3.3 Phones and door access, estimated at 40 hours. Adding it gives:

96+180+40=316

The arithmetic now reconciles. Still compare every required result with the branch: missing work and duplicated work can offset each other numerically. Equal totals establish consistent estimates, not complete scope.

For the whole office move, branch estimates are 120 hours for management, 304 for fit-out, 316 for IT, 212 for furniture and moving, and 40 for transition.

120+304+316+212+40=992

That is total effort. It is not the project's elapsed duration, because different packages can run in parallel.

Connect the WBS to other plans

A product breakdown structure (PBS) groups products or deliverables. A WBS covers the deliverables and the work needed to produce them, including management. A team can begin with a PBS and use it to develop the WBS.

Planning needHow work packages help
ScheduleBreak packages into activities, then sequence and time them
Cost and budgetRoll package estimates up into larger totals, sometimes organized in a cost breakdown structure (CBS)
ResponsibilityCombine work with the organizational breakdown structure (OBS) in a responsibility assignment matrix (RAM)

A RACI chart is one form of RAM: Responsible, Accountable, Consulted, and Informed. It connects people and roles to work packages.

In hybrid projects, a high-level deliverable such as a staff intranet can remain in the WBS while its features evolve through iterations. Apply the 100% rule to that deliverable's agreed boundaries. An approved WBS joins the scope statement and dictionary in the baseline, so an omitted package can leave work without planned time or budget.

Key Takeaways

  • Each WBS parent must be fully covered by its children, with no extra work or overlap.
  • Reconcile estimates, then check the actual scope; equal totals alone cannot establish completeness.
  • A PBS organizes products; a WBS also covers the work needed to produce them.
  • Work packages feed schedule activities, cost roll-ups, and responsibility assignments.
  • In hybrid work, apply the 100% rule to agreed deliverable boundaries while adaptive detail evolves.

4.3 Write the WBS dictionary

A short WBS label cannot settle every delivery question. The WBS dictionary gives each element, especially each work package, a detailed agreed meaning. Package owners help write it so boundaries and completion checks reflect the real work.

Describe what the label leaves open

Typical fields include the code and name, work description, deliverable, acceptance criteria, responsible owner, assumptions, constraints, milestones, estimates, resources, dependencies, quality requirements, and linked requirement IDs.

These fields serve decisions. The description sets the boundary; the owner knows who must coordinate delivery; the estimate supports planning; dependencies show what the package needs from other work; acceptance criteria establish what evidence will demonstrate completion.

Build the network entry

For the office move, the entry for 3.1 Network cabling and Wi-Fi can record:

  • Work: Install and label a wired port at each of the 120 desks, provide Wi-Fi on both floors, and test every port.
  • Deliverables: The working network and a port test report.
  • Acceptance criteria: All 120 ports pass testing, and Wi-Fi reaches the agreed signal level in every room.
  • Owner and estimate: IT lead; 96 hours and $14,400.
  • Dependency: 2.2 Electrical and lighting work.
  • Assumption: The building's cable routes are accessible.
  • Requirement link: R-01.

Agree the Wi-Fi signal threshold before installation so the owner and acceptor can use the same pass condition.

Set the boundary between neighboring packages

The entry should specify that 3.1 includes cables, ports, and Wi-Fi access points, while desk phones belong to 3.3. Otherwise one owner may assume the other provides the phones, or both may estimate the same installation work.

Use linked requirement IDs to connect the dictionary to the RTM. R-01 points toward the package that delivers wired desk ports; the dictionary explains that package's work and evidence. The acceptance team can check the resulting network against the same agreement used by the installation team.

Keep the detail under control

After the WBS is baselined, changes to its entries follow change control. Record approved changes to estimates, boundaries, and dependencies in the affected entry, then communicate the current version to the owners who rely on it.

An entry that merely says “Network cabling: network cabling” adds no usable detail. An entry with no owner leaves coordination unclear; one with no acceptance criteria leaves completion open to dispute. Writing detailed entries only for top-level branches leaves the people doing the lowest-level work without the information they need.

Key Takeaways

  • The WBS dictionary supplies the detailed description behind each WBS element.
  • An entry connects work boundaries, ownership, estimates, dependencies, requirements, and acceptance criteria.
  • Write neighboring package boundaries explicitly to prevent gaps and overlap.
  • Keep dictionary entries current through change control after baselining.
5

Control scope and changes through delivery

Requests continue after the scope is agreed. Some are valuable changes; others quietly consume time and money without a decision. You will recognize uncontrolled additions, assess change requests, and keep the approved plan and its versions current. You will then follow a deliverable from the team's quality checks to recorded customer acceptance, using evidence to decide what is ready and what still needs repair.

5.1 Recognize and prevent scope creep

Scope creep is uncontrolled expansion of product or project scope without matching adjustments to time, cost, and resources. It often starts as a stream of small requests that seem too minor to document.

Recognize where additions come from

A stakeholder might ask a team member to add shelving while they are already working nearby. A supplier may suggest extra fittings. The project manager may agree to a favor. Each route can put work into delivery without the project's agreed decision process.

Gold plating starts inside the team: adding features or quality beyond the requirements, such as a second monitor at every desk because money remains. Good intentions do not supply approval. Extra equipment uses resources, creates support needs, and adds risks the organization has not chosen.

An approved scope change is different. It has been assessed, decided by the authorized person or board, and reflected in the relevant plans and baselines. Change can improve the project; control makes its consequences visible before the team commits to them.

Add up apparently small favors

The office move is planned for 60 working days. Staff informally request six extras, each taking about 3 days of team effort.

6×3=18

The additions consume 18 days of team effort, an amount equal to 30% of the 60 planned working days. That signals a substantial extra demand even though each request sounded small.

Effort and finish-date delay are different quantities. If all this additional work falls on the critical path, the finish moves from day 60 to day 78, a 30% delay. Parallel work delays the finish less. The schedule needs analysis before the project manager can claim a particular new end date; the unauthorized effort is a problem either way.

Prevent informal additions from becoming commitments

Clear requirements, explicit exclusions, agreed acceptance criteria, and scope sign-off reduce conflicting expectations. Elicit needs from all key groups early so that less visible stakeholders do not first appear after the baseline is fixed.

Make one request route known to everyone, including suppliers and the sponsor. A team member can acknowledge a useful suggestion and direct it into that route without promising delivery. Sponsor support matters: bypassing the process at the top makes it hard for the team to maintain it elsewhere.

Notice early warning signs

Compare current work with the WBS dictionary and RTM. Work with no package or requirement behind it needs investigation. Packages consuming more hours than expected may reflect hidden additions, although estimating errors or other causes are possible too. A stakeholder who describes a deliverable differently from the scope statement signals a disagreement to resolve before acceptance.

Key Takeaways

  • Scope creep is uncontrolled expansion without matching adjustments to time, cost, and resources.
  • Gold plating is unapproved extra scope added by the team.
  • An approved change can be valuable; it needs assessment, authority, and updated plans.
  • Small additions accumulate. Extra effort requires schedule analysis before it can be translated into delay.
  • Use clear boundaries, early stakeholder involvement, and one supported route for change requests.

5.2 Run a change control process

Change control turns a proposed change into a visible decision. A request can concern scope, corrective or preventive action, or defect repair. Submitting it begins an assessment; it does not authorize work.

Follow the request through six steps
  1. Submit and log. Give the request an ID and record it in the change log.
  2. Review initially. Check that it is complete and not a duplicate.
  3. Analyze impacts. Assess scope, schedule, cost, quality, risk, resources, and benefits. Use the RTM and WBS to find linked work and checks.
  4. Decide. The authorized person or board approves, rejects, or defers it.
  5. Update and implement. For approval, update the affected baselines and plans, communicate the decision, and carry out the change.
  6. Check and close. Confirm the implemented result and close the change log entry.

A change control board (CCB) is a formally chartered group with decision authority. Smaller decisions may be delegated. For example, a project manager may approve a change under $2,000 only if it also leaves the end date unchanged. A request meeting one condition but failing the other must go to the higher authority. The person or group with delegated authority is also called the change authority.

Assess an excluded archive move

Halfway through the office move, finance asks to move and index the paper archive. The approved scope excludes it. The assessment finds 48 extra hours of work, 6 more working days, $9,600 of additional cost, and a need for storage space absent from the floor plan. The extra cost is 4% of the $240,000 budget.

The old lease continues until July 31, so the archive can move after staff. The board approves added budget and a later closing date while keeping the June 29 opening. The decision has considered delivery timing, not just the price of the extra work.

Approval removes the archive exclusion and adds the deliverable to the scope statement. Add WBS element 4.4 Paper archive moved and indexed, its dictionary entry, and the new requirement's RTM links. Update the schedule and cost baselines as well. Record a rejection or deferral with its reason too, and tell the requester what was decided.

Protect the resulting versions

Configuration management identifies and controls product and document versions. Its five activities are planning the procedures; identifying items and their references; controlling changes; status accounting to record current versions and history; and verification audits to compare products with their records.

Change control decides whether to change the floor plan. Configuration management identifies the resulting approved version, keeps its history, and helps people use the right drawing. A decision left only in a meeting note cannot protect installers who still have the old plan.

Key Takeaways

  • Log, review, assess, decide, update and implement, then check and close each request.
  • Impact analysis covers scope, schedule, cost, quality, risk, resources, and benefits.
  • Decisions belong to the authorized person or board within the agreed delegation limits.
  • Approval must reach the affected scope records, traceability links, and other baselines.
  • Record and communicate rejected and deferred requests as well as approvals.
  • Configuration management protects item identities, current versions, and change history.

5.3 Verify, validate and accept deliverables

A team needs evidence that a deliverable meets its requirements and a record that the authorized customer or sponsor accepts it. These decisions are connected, but the team's own test result is not formal customer acceptance.

Verify before seeking acceptance

Verification asks whether the result was built correctly to specification. The team checks quality through testing, measurement, examination, or demonstration. Validation asks whether the result meets customer needs; in scope management, validating scope means obtaining formal acceptance of completed deliverables.

Use the normal sequence: complete the deliverable, verify it, inspect it with the customer or sponsor against the agreed criteria, and record acceptance if it meets them. The scope statement, WBS dictionary, and RTM provide the agreement and evidence links for this review.

Inspection can be a walk-through of the office with the approved floor plan and a checklist. It can also include measurements or tests. The method must establish the relevant criteria: counting meeting rooms answers a different question from testing whether the network works.

Follow a failed network check

Facilities confirms that all 8 required meeting rooms exist. The port test, however, shows only 112 working desks out of the required 120. The IT and network deliverable is not ready for acceptance. Another deliverable's passed room count cannot compensate for these failed network criteria.

Record the 8 failed ports as defects, arrange repair through the agreed process, and retest them. Update the evidence and status in the RTM. Once all 120 pass and the other agreed criteria are satisfied, obtain the named acceptor's recorded sign-off. Defect repair commonly leads to a change request; the project's controls determine its route.

Keep scope control active during delivery

Scope control compares completed work with the baseline. Review which packages are finished, which are behind, and whether unapproved work has appeared. Investigate the cause of each variance before choosing corrective action or requesting a change. A variance might reflect a defect, hidden scope, or a planning problem; its cause affects the response.

Agree and record acceptance as deliverables finish. Waiting until the whole project ends can leave a large set of disputes when rework is costly. In adaptive work, review completed increments regularly with stakeholders and use item criteria and the shared definition of done. A Scrum Sprint Review inspects results and informs adaptation; it is not a required release approval gate.

Formal acceptance is recorded by the person named in the scope management plan. Accepted deliverables move toward handover, and the accepted final result supports project closing. If a stakeholder asks for a new feature during inspection, record it as a change request. Do not quietly rewrite the acceptance criteria to include a new demand or to excuse a failed check.

Key Takeaways

  • Verification checks conformance to specification; scope validation obtains formal acceptance.
  • Inspect against agreed criteria using the scope statement, dictionary, and traceability evidence.
  • Record defects, repair and retest, then obtain acceptance when the criteria are met.
  • Investigate scope variances and route corrective action and changes through the agreed controls.
  • Record acceptance throughout delivery, and keep new requests separate from acceptance checks.

Project Requirements and Scope examples

5 Walkthroughs

1

Turn a project purpose into scope decisions

12 steps
Separate needs, results, and work, then choose how the scope agreement will develop and change.
  1. 1
    IntroductionGive the team a usable agreement

    “Move the office” gives a project a direction, but leaves many delivery decisions open. How many desks need connections? Who approves the finished rooms? Can a new feature be added midway?

    Requirements describe needs. Scope turns the agreed needs into boundaries and work. Follow the office move from a high-level charter toward an agreement the team can plan and control.

  2. 2
    ExplanationSeparate a need from a task

    A requirement states a needed condition or capability. “Every desk has a wired network port” describes what must be true of the result.

    “Buy 120 network cables” is a task that contributes to that result. Purchasing the cables alone does not establish that the ports are installed and working. Requirements guide the work and the later checks.

  3. 3
    ExampleIdentify the result and its work

    The office needs a meeting room seating 12. That feature belongs to product scope. The approved floor plan and the finished room are verifiable deliverables.

    Project scope covers the work to provide them: plan, buy, install, test, and hand over. It also includes managing the project. A room list alone leaves some required work invisible.

  4. 4
    ExplanationAsk what it does and how well

    “The access system records each badge entry” is a functional requirement: it states what the product does. “The badge reader unlocks within 2 seconds” is nonfunctional: it sets performance.

    Also ask about security, reliability, and usability. People may describe a function clearly while assuming everyone shares their expectations about acceptable performance.

  5. 5
    ConnectionConnect needs to their level

    A business requirement might be a 20% rent reduction. A stakeholder requirement could be secure payroll storage. Solution requirements describe the finished office or system.

    Temporary badge training is a transition need. A required approval step concerns how the project is run. A safety inspection standard is a quality requirement. These different views help the team uncover missing needs.

  6. 6
    ChallengeLook behind the proposed booths

    Staff request “six phone booths” because calls must stay private. What should the team record before committing to that design?

    ---reveal---

    Record the need for private calls and clarify its conditions with users. Six booths are one possible solution. Keeping the need visible lets the team compare designs and later show how the chosen result satisfies it.

  7. 7
    Key InsightExpose planning beliefs and limits

    The move plan assumes the landlord completes the fire inspection by June 1. That is an assumption, treated as true without proof. The old lease ending July 31 is a constraint, a fixed limit.

    Record both. A failed assumption can make planned work impossible or require a scope decision. Treating an expected inspection date as a confirmed fact hides that exposure.

  8. 8
    ExplanationAgree how decisions will be made

    The scope management plan names how scope is developed, changed, and accepted, including who decides. The requirements management plan sets how needs are elicited, analyzed, prioritized, traced, and changed.

    These are procedures for making the agreement. The detailed requirements, scope statement, and work breakdown are records produced by following those procedures.

  9. 9
    ExampleChoose controls for different work

    The building fit-out has a known headcount and lease, so the team can plan most scope predictively. Its approved scope statement, WBS, and dictionary form the scope baseline.

    The intranet can evolve through iterations. Its ordered backlog, iteration planning, acceptance criteria, and definition of done control selection and completion. Combining the two creates a hybrid approach.

  10. 10
    TipAdd detail when knowledge improves

    Rolling wave planning details near-term work while leaving later work higher level until useful information arrives. It is one way to progressively elaborate a plan.

    Predictive teams can do this too. The important question is whether the work remains inside agreed boundaries and follows its controls. Equal detail in every phase is not a test of planning quality.

  11. 11
    ChallengeJudge a larger office proposal

    The charter authorizes an office for 120 staff. A later planning session proposes a second building for another team. Is this simply rolling wave planning, and what decision is needed?

    ---reveal---

    No. The proposal expands the charter’s boundary instead of detailing agreed work. It needs the sponsor’s decision. After authorization, the affected scope records and controls must reflect the changed agreement.

  12. 12
    RecapCarry the distinctions into planning

    Use the need to judge designs, the product scope to describe features, and project scope to capture their full delivery work. Keep assumptions and fixed limits visible.

    Then apply the agreed decision rules: a predictive baseline changes through formal control, while adaptive content evolves through prioritized selection and clear completion checks. Both need authority for changes to their boundaries.

2

Build a requirement trail from people to proof

14 steps
Choose elicitation methods, rewrite and prioritize needs, and trace them through delivery and testing.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionFind needs that are easy to miss
  2. 2
    ExplanationChoose a method for the information gap
  3. 3
    ExampleCombine methods for the office move
  4. 4
    TipGive people something to react to
  5. 5
    ChallengeInvestigate the missing sorting space
  6. 6
    ExampleReplace “enough” with a check
  7. 7
    ExplanationSeparate needs before prioritizing
  8. 8
    ExampleMake priorities useful
  9. 9
    ChallengeResolve competing room requests
  10. 10
    ExplanationBuild one row from need to evidence
  11. 11
    ExampleFind a gap and an unexplained addition
  12. 12
    ChallengeDecide whether the network is ready
  13. 13
    ChallengeFollow a changed training need
  14. 14
    RecapPreserve the chain through delivery
3

Agree boundaries and acceptance checks

10 steps
Build a scope statement and criteria that make delivery and acceptance a shared agreement.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMake the promise checkable
  2. 2
    ExplanationGive each part a purpose
  3. 3
    ExampleWrite the office boundary
  4. 4
    ConnectionSeparate a belief from a fixed limit
  5. 5
    ChallengeHandle an archive expectation
  6. 6
    ExampleSpecify workstation acceptance
  7. 7
    Key InsightPreserve the required threshold
  8. 8
    ExplanationDistinguish delivery from business results
  9. 9
    ChallengeRepair a vague scope promise
  10. 10
    RecapAgree scope and evidence together
4

Build and check the work breakdown

14 steps
Decompose the office move, reconcile its work and estimates, and give packages precise dictionary entries.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMake the scope manageable
  2. 2
    ExplanationStart with the whole project
  3. 3
    ExampleBreak the IT branch into results
  4. 4
    TipStop where ownership becomes practical
  5. 5
    ChallengeJudge a package that is still too broad
  6. 6
    ExampleReconcile the branch estimates
  7. 7
    ExampleFind the omitted work
  8. 8
    ChallengeCatch a duplicated check
  9. 9
    ConnectionUse packages for the next plans
  10. 10
    ExplanationAdd the agreement behind the label
  11. 11
    ExampleDescribe network work precisely
  12. 12
    ChallengeUpdate both sides of a transfer
  13. 13
    ChallengeSeparate total effort from duration
  14. 14
    RecapUse one consistent work agreement
5

Control additions and accept finished work

15 steps
Assess requests, maintain the approved versions, and use evidence to obtain formal acceptance.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionKeep requests and commitments distinct
  2. 2
    ExplanationRecognize uncontrolled additions
  3. 3
    ExampleCalculate effort before claiming delay
  4. 4
    ChallengeRespond to a free extra
  5. 5
    ExplanationLog and assess before deciding
  6. 6
    ExampleAssess the excluded archive move
  7. 7
    ExampleKeep the opening and revise closing
  8. 8
    ChallengeApply both delegation conditions
  9. 9
    Key InsightProtect the version after the decision
  10. 10
    ExplanationSeparate verification and acceptance
  11. 11
    ExampleRead the network evidence
  12. 12
    ChallengeHandle a new request during inspection
  13. 13
    ConnectionReview results throughout delivery
  14. 14
    ChallengeKeep the whole agreement aligned
  15. 15
    RecapFinish with an agreed result and record

Project Requirements and Scope practice questions

40 Practice Questions in 4 sets

Set 1: Find gaps and assess change10 Practice Questions

Question 1 of 10

An equipment project keeps distant installation work at a high level while detailing next month’s design work. It uses an approved predictive baseline. What planning approach explains the different detail levels?
  1. Gold plating to expand the later installation scope.
  2. Scope validation to accept unfinished design work.
  3. Rolling wave planning within a predictive approach.
  4. Uncontrolled change caused by an absent scope baseline.
Show answerHide answer
Answer: C
Rolling wave planning details near-term work while later work remains at a higher level until more is known. Predictive projects can use it alongside an approved baseline. Less detail for distant work alone is not evidence of uncontrolled change; the agreed boundaries and controls still apply.

Question 2 of 10

A team wants selected customers to discuss their expectations and reactions to a proposed self-service kiosk. What elicitation technique fits that purpose?
  1. A moderated focus group of selected customers.
  2. A facilitated workshop for department heads.
  3. A series of interviews with internal experts.
  4. A fixed survey of customers’ current kiosk use.
Show answerHide answer
Answer: A
A focus group lets selected users discuss attitudes and expectations with a moderator. It can explore reactions that the team has not yet turned into fixed survey questions. A cross-function workshop is better for reconciling departments’ requirements than for this customer discussion.

Question 3 of 10

A logistics WBS contains a custom executive display with no requirement link. An executive says it is useful, but no decision record exists. How should the team resolve its status?
  1. Create a requirement ID and keep building because the executive likes it.
  2. Check for a missed approved need, then document it or remove unauthorized work.
  3. Mark it accepted because a stakeholder has confirmed its business value.
  4. Delete the display immediately without checking for missing requirement records.
Show answerHide answer
Answer: B
Backward tracing identifies unexplained work, not its final cause. The team must check whether an approved requirement was omitted from the records or whether the display is unauthorized. A new ID alone supplies no approval, while immediate deletion could discard work that an existing agreement actually requires.

Question 4 of 10

A charter authorizes replacing a payroll system. The draft scope adds recruitment software after interviews reveal interest, but no sponsor decision covers it. What needs to happen before the addition becomes agreed scope?
  1. Treat the interview notes as authorization for the added deliverable.
  2. Place recruitment work in the schedule without changing the statement.
  3. Call the recruitment software a transition requirement and include it.
  4. Seek the sponsor’s decision on the expanded boundary and document it.
Show answerHide answer
Answer: D
Elicitation discovers needs, but it does not authorize an expansion beyond the charter’s boundaries. The sponsor must decide whether the recruitment deliverable belongs in the project. Relabeling it as transition work cannot supply that authority or change what the charter currently supports.

Question 5 of 10

A WBS branch covers a later rollout whose detail depends on a pilot. What is a suitable way to represent that future work now?
  1. Keep a higher-level planning package and decompose it when enough is known.
  2. Remove the rollout entirely until every activity can be dated precisely.
  3. Estimate detailed rollout packages now by assuming the pilot has no effect.
  4. Represent the rollout only through pilot activities until its detail is known.
Show answerHide answer
Answer: A
A planning package keeps future scope visible while detailed decomposition waits for useful information. The team can elaborate it as the pilot provides evidence. Removing the rollout would hide required work; inventing detail would create an unreliable plan without resolving the uncertainty.

Question 6 of 10

A service rollout’s parent estimate is 250 hours. Its children total 250, but checking is duplicated and training is absent. The manager proposes a RACI chart as the fix. How should the team proceed?
  1. Assign every listed package a role; equal totals already establish complete scope.
  2. Add training, retain both checks, and use RACI to let the two owners coordinate them.
  3. Correct scope gaps and overlap, re-estimate, then connect the work to roles in RACI.
  4. Reduce the parent estimate, remove training, and use RACI to establish the boundary.
Show answerHide answer
Answer: C
A RACI chart assigns responsibility but cannot repair missing or duplicated scope. First give training a place, assign the duplicated checking work once, and reconcile the revised estimates; then connect the corrected WBS to organizational roles. Equal initial totals do not establish complete scope.

Question 7 of 10

An approved change transfers equipment calibration from package 4.1 to package 4.3. What dictionary update is needed?
  1. Change the owner’s name in 4.3 and leave both descriptions unchanged.
  2. Update both entries’ boundaries and affected dependencies or estimates.
  3. Delete the calibration acceptance criteria because the package changed.
  4. Record only the new parent total because individual entries are historical.
Show answerHide answer
Answer: B
Transferring work changes both the package losing it and the package gaining it. Their entries need consistent boundaries and any affected planning details so owners use the same approved agreement. Updating only a name leaves calibration assigned ambiguously and can preserve double counting or a gap.

Question 8 of 10

A clinic project excludes appointment reminders. A supplier offers them at no purchase cost, but integration and support would require work. The team wants to accept informally. What is the appropriate response?
  1. Accept because an item without purchase cost cannot affect scope.
  2. Add reminders as a quality improvement without changing the records.
  3. Accept if the supplier documents the feature in its own release notes.
  4. Raise a change request and assess the full delivery consequences.
Show answerHide answer
Answer: D
The reminder feature crosses an explicit scope boundary and introduces integration and support work. Its purchase price is only one part of its impact, so the request needs assessment and an authorized decision. A supplier’s release note cannot update the project’s approved scope or resource commitments.

Question 9 of 10

A change board defers a storage upgrade until more evidence is available. What should the project manager do with that decision?
  1. Record the deferral and reason, and inform the requester.
  2. Remove the request so the log contains only approved changes.
  3. Treat the deferral as approval to begin reversible work.
  4. Update the baseline to include the upgrade provisionally.
Show answerHide answer
Answer: A
A deferral is a decision worth preserving in the change log, with its reason and communication to the requester. It leaves the request unresolved for implementation. Beginning the upgrade or adding it to the baseline would treat the absence of approval as a commitment the board has not made.

Question 10 of 10

A delivery criterion requires every one of 64 sensors to pass a response test. Results show 61 passes. The team has met the launch date and spent less than budget. How should acceptance proceed?
  1. Accept because the date and budget compensate for three failures.
  2. Lower the criterion to 95% without reopening the requirement.
  3. Record three defects, repair and retest, then seek acceptance.
  4. Treat the test as passed because most sensors meet the criterion.
Show answerHide answer
Answer: C
The agreed criterion applies to all 64 sensors, leaving three defects to resolve before acceptance. Repair and retest provide the missing evidence. Meeting date and budget targets does not satisfy a separate deliverable criterion, and lowering it informally would change the agreed requirement.
Set 2: Keep the whole scope agreement consistent10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A team records “install four soundproof booths” after users ask for private calls. The design has not been compared with alternatives. What should the team clarify first?
  1. The activity sequence for installing exactly four booths.
  2. The underlying privacy need before selecting the design.
  3. The completion status of the four proposed booths.
  4. The final supplier invoice for the preferred booth design.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A hybrid project baselines a production-line installation while trialing a scheduling app in iterations. Users request a new app feature and a larger installation area. How should the two requests be handled?
  1. Add both through backlog ordering because the project has adaptive work.
  2. Freeze both requests because any scope baseline forbids later changes.
  3. Use app prioritization within its boundaries and formal control for the area change.
  4. Let each supplier decide because the two parts use different delivery approaches.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Two departments request conflicting retention periods for the same records. The team has identified both sources and confirmed the conflict. How should it reach an approved requirement?
  1. Compare needs with business objectives, obtain the authorized decision, and record its reason.
  2. Keep both periods as Must requirements and let the implementation team choose during testing.
  3. Use the longer period because the most demanding request always determines project scope.
  4. Use the period mentioned first and preserve the second as an unreviewed acceptance criterion.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A changed training requirement affects two course packages and their assessments. The RTM still links only one package to an old test. What must the impact review do before a decision?
  1. Use the old linked test alone because it belongs to the current baseline.
  2. Approve the change and let the instructors find affected work during delivery.
  3. Estimate only the added training hours because tests are separate quality work.
  4. Update the affected links and assess both packages and their changed checks.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A project will measure reduced processing costs six months after launch. Its new forms must pass field-validation tests before handover. How should these measures be classified?
  1. Cost reduction is acceptance; field testing is a project assumption.
  2. Cost reduction is a success criterion; field testing supports acceptance.
  3. Both are the shared definition of done for every future project.
  4. Both are work package activities with no link to project objectives.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A branch estimated at 288 hours lists packages of 92, 104, and 68 hours. Review finds required training absent, but its effort is not yet estimated. What can be concluded?
  1. The training is proven to require 24 hours, so the branch is complete.
  2. The parent must be lowered to 264 hours without further scope review.
  3. The gap is 24 hours, but training’s estimate still needs independent assessment.
  4. The gap is 36 hours, so training can be added with that effort immediately.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A WBS dictionary entry gives a work description and estimate but names nobody responsible for the package. What field is missing?
  1. The responsible work package owner.
  2. The sequence of all project activities.
  3. The business case for the whole course.
  4. The customer’s final acceptance signature.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A board approves adding equipment storage. The team updates the schedule and cost baseline, but the scope statement still excludes storage and the WBS has no storage package. What is required before implementing a consistent approved plan?
  1. Keep the exclusion because only the budget needs to show board decisions.
  2. Add storage only to the next status report and retain the original work boundaries.
  3. Start work and wait until acceptance to reconcile the conflicting scope records.
  4. Update the scope statement, WBS, dictionary, and requirement links for the addition.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A change is approved, but two crews install equipment from different drawing versions. The manager needs to identify the current approved drawing and its history. What control addresses this problem?
  1. Configuration management with version status records.
  2. MoSCoW ranking of the original equipment requirements.
  3. A new focus group about preferred equipment features.
  4. Backward tracing with all drawing versions marked current.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

During inspection, a customer asks for an extra language on a display. The display meets all agreed language criteria. How should the new request enter the project?
  1. As a failed test against a criterion that was never agreed.
  2. As a revised acceptance condition imposed without assessment.
  3. As a change request assessed separately from the agreed checks.
  4. As an automatic extension of the team’s existing verification results.
Show answerHide answer

Save this lesson to see this answer.

Set 3: Make requirements and work packages usable10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

Two package owners each assume the other will supply device chargers. Where should they record the agreed boundary so the WBS labels have a precise meaning?
  1. In the project’s business objective only.
  2. In the current version number alone.
  3. In the affected WBS dictionary entries.
  4. In the change log as a completed delivery.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A museum renovation plan assumes a lender will release an exhibit by August 10, but the release is not confirmed. How should the team record this planning condition?
  1. As an approved deliverable with a completed status.
  2. As an acceptance criterion already met by the lender.
  3. As a fixed constraint established by the project team.
  4. As an assumption that needs checking during planning.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Customer support and finance disagree about the information a new refund form must capture. Both groups know their needs. What elicitation technique best helps them reach a shared agreement?
  1. Separate surveys that count each group’s preferred fields.
  2. A facilitated workshop with representatives of both groups.
  3. A focus group of customers discussing general expectations.
  4. Observation of finance staff without support staff involvement.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Users ask for a “quick search.” The agreed need is a result within 3 seconds for at least 98% of searches during working hours. How should the requirement be written?
  1. “The search should respond quickly whenever possible.”
  2. “The search is fast and uses a modern search engine.”
  3. “At least 98% of searches return results within 3 seconds during working hours.”
  4. “Every search returns a result within 3 seconds under all operating conditions.”
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

How do the project charter and the detailed scope statement differ?
  1. The charter authorizes high-level scope; the statement details delivery boundaries.
  2. The charter defines all work packages; the statement authorizes the project.
  3. The charter records actual costs; the statement defines the original business need.
  4. The charter sets activity dates; the statement replaces the project’s objectives.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A mobile form has item-specific acceptance criteria. The adaptive team also requires every completed item to be tested and documented. What is the role of that shared requirement?
  1. It is a project benefit measured after the release.
  2. It is a separate business case for each form field.
  3. It is a substitute for the form’s specific criteria.
  4. It is part of the team’s shared definition of done.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A team divides equipment installation until each part has one accountable owner, a verifiable result, and enough detail to estimate and schedule it. What has it reached?
  1. A project charter ready to authorize the equipment purchase.
  2. A work package suitable for managing that part of scope.
  3. A complete schedule showing all installation dependencies.
  4. A product backlog that replaces the agreed scope baseline.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A 45-working-day project receives four informal extras, each requiring 2 days of team effort. No dependency analysis has been done. What can the manager conclude?
  1. The extras add 8 days of effort; the finish-date effect needs analysis.
  2. The extras add exactly 8 days to the approved project finish date.
  3. The extras have no schedule effect if the budget remains available.
  4. The extras add 4 days of effort because requests can run in parallel.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A manager may approve changes costing under 1,500 budget units only if the end date is unchanged. A request costs 1,200 units and delays completion by 2 days. What should happen before implementation?
  1. The manager approves because the cost is below the limit.
  2. The team starts while the requester obtains extra funding.
  3. The request goes to the higher authorized decision maker.
  4. The manager records the request as already within baseline.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A team’s checks show a new records system meets every technical specification. The scope plan names the customer director as acceptor, but no acceptance is recorded. What remains before formal scope acceptance?
  1. Replace the approved criteria with the team’s test report.
  2. Obtain and record the director’s acceptance against the criteria.
  3. Reclassify technical testing as the customer’s acceptance.
  4. Close the project because specification conformance is sufficient.
Show answerHide answer

Save this lesson to see this answer.

Set 4: From needs to a clear scope10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A warehouse project requires its scanner to display a result within 1 second. What type of solution requirement is this?
  1. A functional requirement describing the scan action.
  2. A transition requirement describing temporary training.
  3. A nonfunctional requirement describing response time.
  4. A project requirement describing an approval process.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A team needs to decide who formally accepts deliverables and how scope changes are approved. Where should it establish these procedures?
  1. In the scope management plan.
  2. In the traceability matrix.
  3. In the product description.
  4. In the work package estimates.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Depot supervisors describe the official dispatch process, but cannot explain the small adjustments staff make during busy periods. How should an analyst first investigate those missing steps?
  1. Survey all staff using a list of official process steps.
  2. Compare dispatch targets with another depot’s targets.
  3. Ask the sponsor to approve the supervisors’ description.
  4. Observe staff dispatching orders during a busy period.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A requirement is labeled “Should have” under MoSCoW. What does that priority mean?
  1. The solution is unacceptable if the requirement is absent.
  2. The requirement is important, but a workaround exists.
  3. The requirement is desirable only with spare capacity.
  4. The requirement is agreed to be outside this release.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

An approved requirement for accessible training materials has a source and priority in the RTM, but no linked deliverable or acceptance check. What planning action is needed?
  1. Define the delivery work and check, then add both links.
  2. Mark the requirement complete because it was approved.
  3. Move its priority down until a deliverable is available.
  4. Retain the source link and add the planned finish date.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A laboratory relocation includes moving equipment but excludes disposing of old chemicals. A department assumes disposal is included. What should the scope statement make explicit?
  1. The sequence in which equipment will be moved.
  2. The names of staff assigned to each moving activity.
  3. The exclusion of old chemical disposal from delivery.
  4. The estimated hours spent discussing disposal requests.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A project requires all 75 operators to complete safety-system training before launch. A draft acceptance criterion asks for 90% completion. How should the team resolve the mismatch?
  1. Accept 68 completions because the percentage rounds up.
  2. Use 75 completions; lowering the requirement needs approval.
  3. Retain 90% because acceptance criteria set the requirement.
  4. Use the average attendance across the training sessions.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A package has WBS code 2.4. What does the code establish?
  1. The work starts in week 2 and lasts 4 days.
  2. The work depends on completion of four activities.
  3. The work is the second package scheduled to finish.
  4. The element occupies position 4 under branch 2.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A service rollout has a parent estimate of 220 hours. Its children total 220 hours, but staff training is absent and data checking appears in two branches. What conclusion follows?
  1. The 100% rule is met because the estimates reconcile.
  2. Only the parent estimate needs adjustment before approval.
  3. The content fails completeness and no-overlap checks.
  4. The repeated work compensates for the missing training.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A designer adds an unrequested reporting dashboard because the team has spare budget. No scope change has been approved. How should this addition be classified?
  1. Gold plating that adds unapproved scope.
  2. Progressive elaboration of approved scope.
  3. Formal validation of a completed deliverable.
  4. A controlled change within the remaining budget.
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

86 Key Terms, each with its definition

A

Acceptance criteria
Acceptance criteria are agreed, testable conditions a deliverable must meet before the customer or sponsor accepts it.
The workstation acceptance criteria require all 120 desks to start, log in, and print a test page.
Adaptive approach
An adaptive approach develops evolving scope through short iterations, ordered work, and stakeholder feedback on completed results.
An adaptive approach lets staff try intranet features before the team chooses the next iteration’s content.
Assumption
An assumption is something treated as true for planning without proof, which may affect scope if it later proves false.
An office move plan’s assumption is that the landlord completes the fire inspection by June 1.

B

Backward traceability
Backward traceability follows work or deliverables back to requirements and objectives to find work with no documented justification.
Backward traceability finds that the lobby art installation has no supporting approved requirement.
Benchmarking
Benchmarking compares plans or practices with those of similar organizations to inform decisions about a proposed solution.
Benchmarking other offices helps the team compare ways of providing shared meeting space.
Brainstorming
Brainstorming is a technique for producing many ideas in a short period before those ideas are evaluated or selected.
The team uses brainstorming to suggest ways of creating private call spaces before comparing designs.
Business requirement
A business requirement states the organization’s high-level need or objective that the project’s solution must support.
The business requirement to cut office rent by 20% gives an office move a measurable purpose.

C

Change authority
A change authority is the person or group holding delegated power to decide changes within specified limits and conditions.
The change authority must refer a request upward when its effect on the end date exceeds the delegation.
Change control
Change control identifies, documents, assesses, and approves, rejects, or defers changes to documents, deliverables, or baselines.
Change control assesses a request to add an excluded archive move before the team promises its additional work.
Change control board
A change control board is a formally chartered group authorized to evaluate change requests and approve, reject, or defer them.
The change control board decides a request to add archive moving because its impacts exceed the manager’s delegated limits.
Change log
A change log records change requests with identifiers, decisions, reasons, and progress so their status can be followed.
The change log preserves the reason for deferring a request, so the requester knows what remains unresolved.
Change request
A change request is a formal proposal to modify a project document, deliverable, or baseline, including a proposal for defect repair.
Finance submits a change request to add archive moving and indexing to the office move.
Configuration management
Configuration management identifies and controls product and document versions, preserving their approved status and change history.
Configuration management helps installers identify the current approved floor plan before starting work.
Configuration status accounting
Configuration status accounting records and reports current item versions and their histories within configuration management.
Configuration status accounting shows which floor plan replaced the old drawing after an approved change.
Configuration verification audit
A configuration verification audit checks that a product conforms to its requirements and its recorded configuration information.
The configuration verification audit compares the installed layout with the approved floor plan and item records.
Constraint
A constraint is a fixed limit within which the project must operate, such as an available budget or required completion date.
The old lease ending July 31 is a constraint on how long the team can use the original office.
Control account
A control account is a management point, usually above work packages, that combines scope, budget, actual cost, and schedule.
The IT lead reviews three IT work packages together at the control account above them.
Cost breakdown structure
A cost breakdown structure organizes project costs into components that help estimates and budgets be grouped and reviewed.
The cost breakdown structure groups package costs so the project manager can review the budget totals.
Could have
A Could have is a desirable requirement included if time and budget allow after higher-priority requirements are protected.
A coffee machine in each meeting room is a Could have that the team can drop to protect the deadline.

D

Decomposition
Decomposition divides deliverables and project work into smaller, manageable parts until work packages can be estimated and controlled.
Decomposition splits the IT branch into cabling, workstation setup, and phones and door access.
Defect
A defect is a gap between a deliverable’s actual condition and the requirement or acceptance criterion it must satisfy.
A desk port that fails its required test is a defect to record, repair, and retest before acceptance.
Definition of done
A definition of done sets shared completion conditions for adaptive items, such as testing and documentation, alongside specific criteria.
The definition of done prevents an untested intranet feature from counting as complete after an iteration.
Deliverable
A deliverable is a unique, verifiable product, result, or capability required to complete a process, phase, or project.
The approved floor plan is an internal deliverable that the installation team needs before fitting out the office.
Dependency
A dependency is a relationship in which one element’s work relies on another element, recorded to support planning and coordination.
The network entry records its dependency on electrical work so the two owners can coordinate delivery.
Document analysis
Document analysis reviews existing records, contracts, rules, and lessons learned to identify requirements and planning constraints.
Document analysis of the lease reveals limits the team must consider when planning the fit-out.

E

Elicitation
Elicitation is the active work of drawing out requirements through questions, observation, models, and existing information.
Elicitation reveals the mailroom’s need for a sorting counter that managers had not mentioned.
Exclusion
An exclusion is an explicit statement of work or a result that the project or release will not include within its agreed scope.
An exclusion for paper archive moving prevents staff from assuming that every paper record will move with the office.

F

Facilitated workshop
A facilitated workshop brings stakeholders together with a neutral facilitator to define requirements, resolve conflicts, and agree.
The facilitated workshop helps reception and security agree how visitors will enter the new office.
Focus group
A focus group is a moderated discussion with selected users that explores their expectations and attitudes toward a proposed product.
The focus group discusses what staff expect from the proposed self-service room-booking screen.
Formal acceptance
Formal acceptance is the recorded decision by the authorized customer or sponsor that a completed deliverable meets the agreed criteria.
The sponsor records formal acceptance of the network after all required ports pass their checks.
Forward traceability
Forward traceability follows requirements to deliverables and tests to reveal whether each approved need will be delivered and checked.
Forward traceability exposes a training requirement with no linked training package or completion record.
Functional requirement
A functional requirement states what a product or system must do, such as recording an entry or allowing a booking.
A functional requirement asks the access system to record each entry against the badge number.

G

Gold plating
Gold plating is the team’s addition of unapproved features or quality beyond the requirements, often with helpful intentions.
Adding second monitors at every desk without a requirement or approval is gold plating.

H

Hybrid approach
A hybrid approach combines predictive and adaptive ways of planning and delivering different parts of a project.
An office move uses a hybrid approach: a planned building fit-out and iterative development of the staff intranet.

I

Impact analysis
Impact analysis assesses a proposed change’s effects on scope, schedule, cost, quality, risk, resources, and benefits before a decision.
An impact analysis of adding archive moving identifies extra storage space as well as added work, cost, and time.
Inspection
Inspection examines, measures, or tests a deliverable against agreed conditions and is the main technique used in validating scope.
The office inspection uses the approved floor plan and checklist to check rooms and installed equipment.
Interview
An interview is a prepared conversation with a person or small group used to explore needs through open and follow-up questions.
An interview with the finance lead explores confidential storage needs that a general staff survey might miss.

M

MoSCoW prioritization
MoSCoW prioritization groups requirements as Must have, Should have, Could have, or Won’t have this time to guide trade-offs.
MoSCoW prioritization keeps essential desk connections ahead of optional meeting-room coffee machines.
Must have
A Must have is a requirement whose absence would make the solution unacceptable, so it cannot be dropped without changing that agreement.
A working network port at every desk is a Must have in the approved office move requirements.

N

Nominal group technique
The nominal group technique adds voting to idea generation so a group can rank the ideas it has produced.
Using the nominal group technique, staff vote to rank the proposed improvements to the reception area.
Nonfunctional requirement
A nonfunctional requirement specifies how well a product works or the conditions it must meet, such as speed, security, or reliability.
The nonfunctional requirement sets a 2-second response time for a valid door badge.

O

Observation
Observation is watching people carry out their work to discover routine actions, workarounds, and needs they may omit when asked.
Observation shows that reception staff sort deliveries on a counter missing from the proposed layout.
Organizational breakdown structure
An organizational breakdown structure represents the organizational units or roles that can be connected to project work.
The organizational breakdown structure supplies the role side of the work responsibility chart.

P

Planning package
A planning package holds future scope at a higher level until enough information is available to define detailed work packages.
The later rollout stays in a planning package until the pilot provides enough information for decomposition.
Predictive approach
A predictive approach defines most scope in detail early, approves a baseline, and changes that agreement through formal control.
The team uses a predictive approach for the office fit-out because the lease and headcount are well understood.
Product breakdown structure
A product breakdown structure is a hierarchy of the products or deliverables, which can provide a starting point for a WBS.
The product breakdown structure lists the finished office products before the team adds their required work.
Product scope
Product scope is the set of features and functions of the product, service, or result that a project delivers.
The product scope specifies meeting rooms with enough seats for the agreed team sizes.
Product scope description
A product scope description explains the features and functions to be delivered, elaborating the charter and approved requirements.
The product scope description identifies a furnished, networked office for 120 staff at 40 Harbor Street.
Progressive elaboration
Progressive elaboration is the addition of detail to a plan as more information becomes available and decisions become clearer.
The fit-out estimate gains detail through progressive elaboration after the contractor inspects the space.
Project charter
A project charter authorizes a project and establishes its high-level purpose, objectives, main deliverables, and boundaries.
The project charter supports an office move; adding a separate warehouse needs a sponsor’s decision.
Project requirement
A project requirement sets a condition for how the project is carried out, such as a deadline or required approval step.
A project requirement makes approval of the floor plan necessary before the fit-out begins.
Project scope
Project scope is all the work needed to deliver the agreed product, service, or result, including project management work.
The project scope includes testing the network and handing it over, as well as installing it.
Prototype
A prototype is a model or mock-up of a proposed product that helps stakeholders react to its features and clarify their needs.
The desk-layout prototype exposes a storage problem before furniture is purchased for the new office.

Q

Quality requirement
A quality requirement sets a standard or criterion that the deliverable or the project must meet when its quality is checked.
The quality requirement calls for the electrical work to pass the building’s safety inspection.

R

RACI chart
A RACI chart is a responsibility assignment matrix using Responsible, Accountable, Consulted, and Informed roles for the work.
The RACI chart shows who carries out network testing and who must be consulted about its results.
Reporting-period rule
The reporting-period rule is a guideline suggesting that a work package should last no longer than one reporting period.
The reporting-period rule helps the team judge whether completion can be checked between regular reports.
Requirement
A requirement is a condition or capability needed in a product, service, or result to meet a business or stakeholder need.
The requirement for a lockable records room comes from the finance team’s need to protect payroll files.
Requirements documentation
Requirements documentation records agreed needs and attributes such as identifiers, sources, priorities, owners, criteria, and status.
Stakeholders approve the requirements documentation before it feeds the detailed scope statement.
Requirements management plan
A requirements management plan establishes how requirements are elicited, analyzed, documented, prioritized, traced, and changed.
The requirements management plan specifies the columns and update responsibilities for the traceability matrix.
Requirements traceability matrix
A requirements traceability matrix is a table linking each requirement to its source, objective, delivery work, evidence, and status.
The requirements traceability matrix shows that the need for a lockable payroll room has no assigned work or check yet.
Responsibility assignment matrix
A responsibility assignment matrix connects WBS work packages with organizational roles or people to show who does what.
The responsibility assignment matrix names the role accountable for each of the office move work packages.
Rolling wave planning
Rolling wave planning details near-term work while later work remains at a higher level until enough is known to break it down.
Rolling wave planning keeps the later rollout broad while the team details next month’s pilot work.

S

Scope baseline
A scope baseline is the approved scope statement, WBS, and WBS dictionary used as the reference for scope planning and control.
An approved scope change requires updates to the scope baseline so its records describe the new agreement.
Scope control
Scope control compares delivery with the scope baseline, investigates differences, and routes corrective action or changes through agreed controls.
Scope control reveals unapproved shelving work when the manager compares actual work with the WBS.
Scope creep
Scope creep is uncontrolled expansion of product or project scope without matching adjustments to time, cost, and resources.
Several informal shelving and equipment requests create scope creep when the team accepts them without review.
Scope management plan
A scope management plan establishes how scope is defined, developed, monitored, changed, and formally accepted, and who decides.
The scope management plan names the customer representative who can formally accept the completed network.
Scope statement
A scope statement describes the detailed product scope, deliverables, acceptance criteria, exclusions, constraints, and assumptions.
The scope statement names the cleared old office as a deliverable and paper archive moving as an exclusion.
Should have
A Should have is an important requirement with an available workaround, allowing delivery to proceed if it must be left out.
A quiet room on each floor is a Should have because staff can use a room on another floor as a workaround.
Solution requirement
A solution requirement describes a feature, function, performance level, or operating condition needed in the product itself.
The solution requirement specifies that the badge reader must unlock the door within 2 seconds.
Stakeholder requirement
A stakeholder requirement states what a person or group needs from the project’s product, service, or result.
Reception’s stakeholder requirement identifies space for receiving and sorting visitor deliveries.
Success criteria
Success criteria are measures of the project’s wider objectives or results, which may be assessed after its deliverables are accepted.
An office move’s success criteria include reducing office rent by 20% within a year, beyond the handover checks.
Survey
A survey collects answers from many people efficiently and works well for known questions with countable responses.
The survey asks all 120 staff how many days each week they expect to work in the new office.

T

Testability
Testability is the quality that lets a reviewer determine whether a requirement is satisfied using observable conditions or measures.
Replacing “fast” with a measured load-time threshold improves the booking requirement’s testability.
Traceability
Traceability is the ability to follow a requirement from its source and objective through the deliverable and check that satisfy it.
Traceability connects the need for wired desk ports to the installation package and its test report.
Transition requirement
A transition requirement describes a temporary capability needed to move from the current state to the intended future state.
Door-badge training is a transition requirement that prepares staff to enter the new office on move day.

U

Use case
A use case describes how a user interacts with a system to reach a goal, including relevant exception paths or failures.
The door-entry use case describes both a valid badge entry and the response to an unrecognized badge.

V

Validation
Validation checks whether the result meets customer needs; in scope management, validation involves formal acceptance of deliverables.
Validation considers whether the completed office provides the agreed result that its users and sponsor need.
Variance
A variance is a difference between planned and actual results that must be investigated to understand its cause and required response.
An unexplained hours variance prompts the owner to check whether extra work entered the package informally.
Verification
Verification checks whether a deliverable conforms to its specification, typically through the team’s quality checks before acceptance.
Verification of the desk network reveals 8 failed ports that need repair before the customer accepts it.

W

WBS dictionary
A WBS dictionary gives detailed information about each WBS element, including its work, deliverable, owner, and acceptance checks.
The WBS dictionary assigns desk phones to the phones and door access package and keeps them out of the cabling package.
Won’t have this time
Won’t have this time is a MoSCoW priority that records an agreed exclusion from the current project or release.
The rooftop terrace is marked Won’t have this time, so nobody includes its construction in the move plan.
Work breakdown structure
A work breakdown structure is a hierarchy that decomposes the total project work into smaller, deliverable-oriented elements.
The work breakdown structure gives IT, furniture, transition, and project management work identifiable places.
Work package
A work package is a lowest-level WBS element with one accountable owner and an estimable, schedulable, and verifiable result.
The IT lead owns the network work package and supplies its completed port test report.
Work package boundary
A work package boundary states what an element includes and excludes, clarifying where its responsibilities meet neighboring work.
The work package boundary puts Wi-Fi access points in the cabling package while desk phones remain in the phones and door access package.

#

8/80 rule
The 8/80 rule is a planning rule of thumb suggesting work packages of 8 to 80 hours of effort, subject to management judgment.
The team considers the 8/80 rule when reviewing whether a large network package needs further decomposition.
100% rule
The 100% rule requires each WBS parent’s children to cover all its agreed work and no extra work, with no missing parts.
The 100% rule review finds that management work must be included alongside installation deliverables.