Running Sprints in Practice
BeginnerLesson 4 of 6 in Agile and Scrum Course
What you will learn
- Prepare and guide Sprint Planning so the Scrum Team leaves with a clear Sprint Goal, a realistic selection of work and a plan the Developers own.
- Prepare the inputs for Sprint PlanningGather what the team needs before the event starts: a refined Product Backlog, the Product Goal, the Definition of Done, the team's capacity and its past performance.
- Agree on a Sprint Goal and select the workGuide the Scrum Team through why, what and how, write a Sprint Goal that gives the Sprint focus, and let the Developers decide how much work they take on.
- Build a Sprint Backlog the Developers ownTurn the selected items into an actionable plan, break the work into small pieces, and avoid planning habits that undermine the team's self-management.
- Prepare the inputs for Sprint Planning
- Use a task board and burndown and burnup charts to show the state of the Sprint honestly, read the patterns they reveal and avoid using them to judge people.
- Run the Sprint from a task boardLay out the Sprint Backlog on a physical or digital board, keep it current, and read it to spot stuck work, too much work in progress and hidden risks.
- Draw and interpret burndown and burnup chartsPlot a Sprint burndown, compare it with the ideal line, recognize common patterns, and know when a burnup chart or a product-level chart tells the story better.
- Run the Sprint from a task board
- Run a focused Daily Scrum, recognize and correct its common anti-patterns, and handle impediments so the team keeps moving toward the Sprint Goal.
- Run a Daily Scrum that serves the Sprint GoalHold a short daily inspection in which the Developers check progress toward the Sprint Goal and adapt their plan for the next day of work.
- Spot and correct Daily Scrum anti-patternsRecognize the habits that turn the Daily Scrum into a status meeting or a ritual, and apply a practical correction for each.
- Handle impediments without taking overMake impediments visible, sort out who can resolve them, escalate the ones beyond the team's reach and learn from recurring causes, while leaving the team in charge of its own problems.
- Run a Daily Scrum that serves the Sprint Goal
- Use the Definition of Done to decide what is truly finished, inspect Done work with stakeholders at the Sprint Review, and run Sprint Retrospectives that lead to real improvement.
- Write a Definition of Done that fits the productExplain what the Definition of Done is and who sets it, write checkable criteria for a real product, and tell the Definition of Done apart from acceptance criteria.
- Apply the Definition of Done and inspect Done work at the Sprint ReviewUse the Definition of Done to decide which items are finished, deal correctly with undone work, and facilitate a Sprint Review that works as a working session with stakeholders.
- Facilitate a Sprint RetrospectivePlan and run a Sprint Retrospective with a clear structure and suitable activities, so the whole Scrum Team inspects how the Sprint went and finds what to improve.
- Turn Retrospective insights into lasting improvementsChoose a few specific improvements, give them a place in the next Sprint, follow them up, and use them to strengthen the Definition of Done over time.
- Write a Definition of Done that fits the product
- Serve the Scrum Team, the Product Owner and the organization by choosing the right stance for each situation, coaching with questions and protecting the team's self-management.
- Choose the right Scrum Master stanceDescribe whom the Scrum Master serves and how, and switch between teaching, mentoring, coaching and facilitating as the situation and the team's experience require.
- Coach with questions rather than answersUse open questions, active listening and a simple conversation structure to help individuals and the team reach their own decisions, and recognize when teaching is the better choice.
- Protect and grow the team's self-managementShield the team from disruption without becoming a gatekeeper, help it make and keep its own decisions and agreements, and step back as the team grows.
- Choose the right Scrum Master stance
- Set up a team whose members work in different places or time zones so it can collaborate well, and facilitate every Scrum event remotely without losing its purpose.
- Set up a distributed Scrum team to collaboratePlan around time zones and working hours, agree on how the team communicates and which tools it uses, and avoid set-ups that split the team into separate sites.
- Facilitate Scrum events remotelyAdapt Sprint Planning, the Daily Scrum, the Sprint Review and the Sprint Retrospective for online and cross-time-zone work while keeping each event's purpose and timebox.
- Set up a distributed Scrum team to collaborate
Running Sprints in Practice study guide
1Plan a Sprint the team can deliver
Sprint Planning connects a useful product outcome with the work the Developers believe they can finish. Preparation gives the conversation a sound starting point; the event then turns that information into a shared objective and an actionable plan. Learn how to bring capacity and past performance into the discussion, guide the three planning topics, and leave room for the Developers to adapt their work as they learn.
1.1 Bring the right information to Sprint Planning
Sprint Planning begins the Sprint. The whole Scrum Team creates the plan together, with advice from invited specialists when useful. For a one-month Sprint, the event lasts at most eight hours; shorter Sprints usually need less time.
Prepare the product conversation
Bring the ordered Product Backlog, the Product Goal, the latest Increment, and the Definition of Done. The Product Owner checks that likely items are clear enough to discuss and proposes how the product could gain value this Sprint. A proposal starts a conversation: the whole Scrum Team will define the Sprint Goal.
Refinement is ongoing work. It makes the next likely items understandable without attempting to specify the entire future product. Items may still be clarified, created, or sized during Sprint Planning. Leaving every open question until that event, however, can turn planning into a long requirements workshop. A short refinement conversation earlier in the Sprint can expose a dependency while there is still time to investigate it.
Estimate available capacity
Capacity is the time the Developers actually have for Sprint work. Start with their working days, then subtract leave, holidays, training, support duties, and other known commitments. Keep the units clear: one person available for one working day contributes one person-day.
Five Developers in a 10-working-day Sprint have 50 person-days before absences. One holiday affects all five people, and one Developer takes two additional days of leave:
Available capacity is 43 person-days. Check whose skills are available as well as the total. Losing two days from the only person familiar with a payment system can affect the selection differently from losing two days spread across routine work. Capacity is an input to judgment, not a demand to fill every available hour.
Use past performance as a reality check
Suppose the last three Sprints each had the full 50 person-days and finished 21, 24, and 27 story points of Done work. Their average is 24 points. A rough adjustment gives:
That suggests about 20 to 21 points as a starting forecast. The Developers still inspect the actual items, uncertainty, dependencies, and skills before choosing. The calculation does not convert story points into fixed hours or guarantee an output.
Count only work that met the Definition of Done. Including partially finished items would inflate the record that the next forecast depends on. A team's past performance, sometimes called “yesterday's weather,” belongs to that team; another team's point scale is different, so velocity cannot rank teams fairly.
Make the event ready to use
The Scrum Master prepares the setting: a usable room or call, a shared board, accessible backlog items, a visible timebox, and an agenda covering why, what, and how. If a database specialist is needed to explain a dependency, invite that person for advice. Preparation supports the team's decisions; it does not preselect their answer.
Key Takeaways
- Bring product direction, current work, quality standards, capacity, and past performance.
- Subtract known absences and duties before forecasting.
- Use only Done work in the performance record.
- Adjust the forecast for the work and skills available.
- Refine throughout the Sprint; further refinement can still happen in Sprint Planning.
1.2 Choose an outcome and a realistic selection
Sprint Planning answers three connected questions: why is this Sprint valuable, what can be Done, and how will the work get done? The discussion can move between them as the team discovers what is feasible.
Start with why
The Product Owner proposes how the product could increase its value. The whole Scrum Team then defines a Sprint Goal, the single objective for the Sprint. It must be finalized before Sprint Planning ends and becomes part of the Sprint Backlog. The Developers commit to that objective.
A goal gives the team a reason to make choices. For an online grocery product, “Returning customers can reorder a previous basket in under a minute” describes an outcome. “Finish stories 112, 115, 118, and 121” lists work but gives little help when a story proves harder than expected. A useful question is, “If we achieve one thing this Sprint, what should it be?”
The outcome should be understandable to stakeholders. A list of technical components may help plan implementation, but it does not explain the value those components deliver together.
Let the Developers select what
Through discussion with the Product Owner, the Developers select Product Backlog items they believe they can finish. They consider capacity, past performance, the Definition of Done, and the particular work. The Product Owner explains value and order and answers questions; the Developers decide the amount.
If candidate work exceeds capacity, explore a smaller slice, defer a lower-value item, or narrow the proposed goal before finalizing it. Do not make overtime the hidden assumption that makes an overloaded plan appear possible. Some room for unexpected work, collaboration, and learning helps keep the goal achievable.
For a booking service, the team might aim to let customers cancel an eligible reservation themselves. Cancellation and confirmation are essential to that outcome. A redesigned reservation history page might wait. Asking which items the outcome needs makes the trade-off visible without treating all candidate items as equally urgent.
Work through how
The Developers plan how the selected items will become an Increment that meets the Definition of Done. This may reveal missing testing, specialist input, or a larger task than expected. Bring that learning back into the selection before closing the event. Why, what, and how need to fit together.
The facilitator can keep the goal visible and ask, “What could stop us from reaching it?” Give each Developer a chance to raise concerns. A fist-of-five confidence check is one optional technique: everyone shows one to five fingers, and low scores prompt discussion. A vote helps expose concerns; it cannot replace the Developers' judgment about their own plan.
Keep flexibility attached to the objective
The Sprint Goal creates focus without freezing every item. As more is learned, the Developers and Product Owner may clarify or renegotiate selected work while preserving the goal. A checklist masquerading as a goal makes that adaptation harder: dropping any task then looks like abandoning the objective, even when the customer outcome remains achievable.
Key Takeaways
- Use why, what, and how to connect value, selection, and delivery.
- Finalize one Sprint Goal before Sprint Planning ends.
- The Developers decide how much work to select.
- Clarify or renegotiate selected work with the Product Owner while protecting the Sprint Goal.
1.3 Make the Sprint Backlog actionable
The Sprint Backlog combines the Sprint Goal, selected Product Backlog items, and an actionable plan for delivering the Increment. These are its why, what, and how. The plan belongs to the Developers, who update it as the Sprint unfolds.
Break work into visible pieces
Developers often split selected items into work of one day or less. For a reorder feature, tasks might include adding a button, building the service that copies a basket, testing out-of-stock behavior, and updating help text. Small pieces let the team see progress and discover misunderstandings early.
A task describes an activity; a Product Backlog item describes a piece of product work that must meet the Definition of Done. Completing the button task does not make the reorder item Done while its tests are missing. Keep those two levels visible so task movement does not hide unfinished product work.
If the Developers cannot explain the work well enough to begin, investigate the uncertainty. They can refine the item with the Product Owner, select a thinner slice, or choose different work that still serves the Sprint Goal. Turning an unclear item into many vague task names does not make it actionable.
Plan quality work from the start
The plan must account for everything the Definition of Done requires. Include review, testing, documentation, security checks, and deployment activities that apply to the product. Omitting these activities makes the initial selection look smaller than the real effort needed to finish it.
For example, a notification item might have a completed message template but still need a delivery test and an accessibility check. Putting those activities on the plan before implementation starts allows the Developers to arrange help and suitable test data. Discovering them on the last afternoon leaves little room to adapt.
Decide ownership inside the team
Developers decide who does what, when, and how. They may pull tasks as they become free or agree on initial owners during planning. Both can support self-management when the choices remain theirs and can change as needed.
Watch for personal queues: one person has several waiting reviews while others begin less important work. The Developers can pair or swarm, bringing several people together to finish a high-priority item. The question is what helps the shared goal, not whether everyone keeps the task assigned on day one. A manager or Scrum Master who allocates every task takes that decision away from the Developers.
Update the plan as knowledge grows
Sprint Planning does not require a complete task list for the entire Sprint. Developers can plan the first few days in detail and describe later work more broadly, then add detail when they know more. The Sprint Backlog should remain a current picture, not a record nobody is allowed to change.
The board displays this plan, and a burndown can measure its remaining work. At the Daily Scrum, the Developers inspect it and agree on the next day's plan. Unfinished items do not automatically become next Sprint's work: they return to the Product Backlog for ordering and possible selection at the next Sprint Planning.
Key Takeaways
- The Sprint Backlog contains the goal, selected items, and delivery plan.
- Small tasks expose progress and uncertainty.
- Plan the activities needed to satisfy the Definition of Done.
- Developers choose and adapt task allocation.
- The plan grows and changes during the Sprint.
- Unfinished items return to the Product Backlog for future consideration.
2See what is happening in the Sprint
A visible plan helps the team notice trouble while there is still time to act. A task board shows where work is waiting or moving; a chart shows how the amount of work changes over time. Learn to read both views together, check what their measures mean, and use the evidence to guide a conversation about the Sprint Goal. Honest updates matter more than making a line or a column look reassuring to someone outside the team.
2.1 Read and maintain a useful task board
A task board, also called a Sprint board or Scrum board, makes the Sprint Backlog visible. A physical wall or a digital tool can work. Scrum requires transparency of the Sprint Backlog; it does not prescribe a board or a particular set of columns.
Show the path to Done
A simple board places the Sprint Goal above the work. One row, or swimlane, represents each selected Product Backlog item, ordered by importance. Columns might be “To do,” “In progress,” and “Done.” Add “In review” or “Testing” when these are actual stages that people need to see.
Make the meaning of Done clear at both levels. A task moves to Done when that task is finished. The parent item is Done only when it meets the Definition of Done. If all listed tasks are complete but the item still needs a security check, the plan has missed work. Add the missing activity and show the item's true state.
Developers update the board as they work. Waiting for the Scrum Master to reconstruct changes after a meeting leaves the team making decisions from old information. On a shared digital board, a person working elsewhere should see the same state as someone in the office.
Read toward completion
Read from right to left to notice work closest to Done, and from top to bottom to notice the work most important for the Sprint Goal. Ask what would finish an item before starting something new. This is a useful team habit, not a required Scrum procedure.
Look for these signals:
- Many items have started but few are finished.
- A task remains in the same column for several days.
- A blocked flag has no visible next action.
- Every task is complete but the item is still not Done.
These are prompts to investigate. A waiting task might need help, a decision, or an update; its position alone does not prove which cause applies. Mark a blockage with a flag and the date so its age and impact stay visible.
Work through a board decision
On day 6 of a 10-day Sprint, item A is central to the Sprint Goal. One of its four tasks is done and three have not started. Item B has four of five tasks in progress, each with a different person. Item C is Done.
The team sees two risks: B has many separate pieces in motion, while the essential A has barely begun. It agrees that two people will finish B together while two others start A. The response changes how the team works on the shared objective. Simply asking each person to move a card would not address the risk.
A team may choose an in-progress limit, such as no more than two items at once, to encourage finishing. Set and revisit that agreement based on the actual work. The board must not become an individual scorecard: counting cards per person rewards easy tasks and discourages helping with difficult work that another person started.
Key Takeaways
- A board is an optional way to make the Sprint Backlog transparent.
- Distinguish a finished task from a Done Product Backlog item.
- Developers keep the board current as they work.
- Inspect waiting work and finish valuable items before opening more.
- Use board evidence to support the team, not rank individuals.
2.2 Interpret burndown and burnup charts
A Sprint burndown plots remaining work on the vertical axis against Sprint days on the horizontal axis. Its units may be task hours, task counts, or points of unfinished items. Check the measure before interpreting a line: remaining task hours and completed story points tell different stories.
Compare with a reference line
The ideal line joins the starting amount to zero on the last day. It shows an even rate for comparison. It is not a schedule that the team must follow exactly, and actual work rarely falls at an even rate.
A 10-day Sprint starts with 80 task hours. The ideal daily decrease is:
At the end of day 5, the ideal remaining work is 40 hours. Actual values for days 1 to 5 are 78, 74, 72, 64, and 52 hours, so the team is 12 hours above that reference:
So far, remaining work has fallen by 28 hours, averaging 5.6 hours per day. Finishing the remaining 52 hours in five days would require 10.4 hours per day:
That is a reason to inspect the board and discuss the Sprint Goal. Which items are stuck? Can the Developers and Product Owner reduce or simplify scope without endangering the objective? The chart alone cannot answer those questions.
Read patterns without guessing causes
A flat line can mean a blocker, unfinished work, or missing updates. A rising line can mean added work or a larger estimate of remaining work. An early line far below the ideal might reflect a small initial selection or generous estimates. A final-day cliff can reveal batch completion, often with testing left late. Investigate the work behind the shape before deciding what caused it.
A points burndown drops only when an entire item meets the Definition of Done. Its steps are normal. A long flat period followed by one large drop can prompt the team to split items and test earlier; it does not justify giving partial points to make the line smoother.
Separate scope from completion
A burnup draws total scope and completed work separately. Suppose 30 of 40 points are complete, then scope rises to 50 while no more work is finished. Remaining work rises from 10 to 20 points. A burndown shows that jump, but a burnup makes its source clear: scope steps from 40 to 50 and completed work stays at 30.
Product-level burndowns or burnups span several Sprints and help the Product Owner forecast progress toward a larger goal. The Scrum Guide recognizes such forecasting practices, including cumulative flow diagrams, but the forecasts must keep responding to observed results.
Update Sprint charts each working day, manually or through the tool. Do not pressure a team to match the ideal line or compare teams by their points. That encourages premature Done labels and data gaming. Read the chart with the board: one reveals the trend; the other helps locate the work behind it.
Key Takeaways
- Check the chart units and update remaining work daily.
- The ideal line is a comparison reference.
- A chart pattern is a signal to investigate, not proof of one cause.
- Points fall only when whole items are Done.
- A burnup separates changes in total scope from completion.
- Use observed results to revise forecasts.
- Read charts with the board to choose an action.
3Inspect and adapt the plan each day
A Sprint plan becomes useful through daily decisions. The Daily Scrum gives the Developers a regular opportunity to inspect progress toward the Sprint Goal and coordinate their next steps. Between events, they keep talking and raise blockers promptly. Learn to recognize meetings that produce reports without decisions, restore a useful focus, and get impediments resolved by the people best placed to act without taking ownership away from the team.
3.1 Turn the Daily Scrum into a plan for today
The Daily Scrum is a 15-minute event for the Developers to inspect progress toward the Sprint Goal and adapt the Sprint Backlog. It takes place at the same time and place every working day of the Sprint. This regular arrangement reduces the effort of coordinating the event.
Let the Developers conduct it
The Developers choose the structure and techniques. The 2020 Scrum Guide does not require the three questions about yesterday, today, and impediments that appeared as examples in earlier versions. A team can use them if they help it inspect and adapt; answering them is not itself the purpose.
The Scrum Master ensures the event takes place and helps the team learn to use it well. The Scrum Master need not lead or attend it. A Product Owner or Scrum Master actively working on Sprint Backlog items participates as a Developer. Other attendees must not turn the event into task assignment or status reporting.
The output is an actionable plan for the next day of work, based on the current progress and coordination needed to reach the Sprint Goal.
Walk the work together
Walking the board is a common technique. Begin with an important item or work closest to Done and ask, “What do we need to finish this?” Discuss how the work connects, including help or decisions needed. Keep the Sprint Goal visible so the conversation has a shared reference.
For a document-sharing product, a Developer might say, “The permission check is ready. I'll pair with Noor on the link flow so we can test sharing today.” Another might say, “The test service is unavailable. I'll contact the service owner after this call.” These contributions explain what changes in the plan, not just what each person did.
Detailed design debate belongs in a follow-up with the people who need it. Put the topic on a visible parking-lot list and agree who will join. Capturing it protects the timebox without losing an issue that matters.
Adapt during the day as well
The Daily Scrum is a regular inspection, not a queue for communication. Raise a blocker when it appears. Developers can update the Sprint Backlog, arrange help, and coordinate throughout the day.
If new learning threatens the Sprint Goal, the Developers and Product Owner discuss scope. They may clarify selected items, reduce an optional part, or choose a different way to achieve the objective. No change may endanger the Sprint Goal, and quality does not decrease during the Sprint.
A hard Sprint is different from an obsolete goal. If a market or strategy change makes the goal no longer useful, the Product Owner can cancel the Sprint. Only the Product Owner has that authority. A team being behind its forecast is a reason to inspect and adapt the work, not automatically a reason to cancel.
Key Takeaways
- The Daily Scrum is a 15-minute inspection and adaptation event for Developers.
- The Developers choose its structure and conduct it.
- Produce an actionable plan for the next day of work.
- Raise blockers immediately and keep coordinating between events.
- Renegotiate scope with the Product Owner while protecting goal and quality.
- Only the Product Owner can cancel a Sprint whose goal becomes obsolete.
3.2 Correct Daily Scrum habits that waste the timebox
An anti-pattern is a familiar-looking practice that undermines its own purpose. For a Daily Scrum, ask whether the Developers leave knowing their progress toward the Sprint Goal and their plan for today. A punctual round of reports can still fail that test.
Redirect status reports toward the work
Notice who people face and address. If everyone reports to the Scrum Master or manager, the event has become a reporting line. The Scrum Master can move out of the center or stay away, and the Developers can face the board and speak to one another.
Walking the board helps connect work that individual updates leave separate. A person may be “busy with tests” while another has started an item that needs those same tests. Discussing each important item reveals that coordination need. The correction is a shared plan, not a new script recited to a different chairperson.
Separate coordination from detailed problem solving
A technical question may deserve an hour, but it should not consume the Daily Scrum. When two people begin a long design debate, record the topic and arrange a follow-up immediately after the event with those needed. Keep the 15-minute timebox visible.
Do not postpone a blocker just to preserve the agenda. State enough to understand its impact and who will act; move the detailed investigation to the follow-up. This lets the team adapt without making everyone sit through a conversation that only two people need.
Break the ritual of unchanged updates
Repeated “same task, no impediments” updates deserve a look at the work. Has anything changed? Is the board current? Is an important item waiting? A plan may stay the same for a sound reason, but it should follow inspection. A useful outcome might be pairing on a stuck item or finishing a review before starting another item.
Blockers must not wait for tomorrow's event. Agree on a way to raise them immediately, such as the team chat. The next Daily Scrum can inspect the response already under way instead of discovering a day-old problem for the first time.
Handle interference and unstable routines
A manager assigning tasks takes the plan away from the Developers. A Product Owner adding work without discussion bypasses their forecast. New requests go through the Product Owner; changes to Sprint work are negotiated with the Developers in light of the Sprint Goal.
Hold the event at its agreed time and place and start on time. Quiet days still need the brief inspection; repeatedly moving or skipping it makes coordination less reliable.
Consider nine Developers whose event takes 35 minutes: everyone reports to the Scrum Master, and two people debate database design. The Scrum Master raises those observations at the Retrospective and asks what the team needs from the 15 minutes. The Developers agree to walk the board, park detailed topics, and rotate a timekeeper weekly. They then check whether their chosen changes produce a clear daily plan within the timebox.
Key Takeaways
- Judge the Daily Scrum by its inspection and daily plan.
- Redirect person-by-person reporting toward shared work.
- Park detailed discussions and follow up with the people needed.
- Raise blockers promptly and preserve the Developers’ ownership of the plan.
3.3 Make impediments visible and get them resolved
An impediment blocks or slows progress toward the team's goals. Examples include missing access, a failing build, another team's dependency, or a slow approval. Here the term covers obstacles broadly; practitioners sometimes reserve it for obstacles outside the team's ability to remove.
Match the response to the obstacle
Developers resolve problems within their capabilities as part of managing their work. A broken test setup or an internal design disagreement does not automatically need escalation. The Scrum Master is accountable for causing the removal of impediments to the team's progress. That can mean coaching the team, connecting it with help, or working with organizational decision-makers.
Causing removal does not mean doing every fix personally. Before stepping in, ask, “What have you tried?”, “Who could help?”, and “What do you need from me?” The answers show whether intervention is useful and leave the team room to develop its own ability.
Follow an impediment through to action
- Make it visible with a dated flag on the board and an entry in an impediment list.
- Clarify what is blocked and its effect on the Sprint Goal.
- Agree who acts: Developers for problems they can solve, Scrum Master support or escalation where needed.
- Follow up until the blockage is resolved.
- Examine the cause so the same problem is less likely to return.
A visible entry needs an action and follow-up. Without them, the list becomes a record of complaints that people stop trusting.
Work through an access delay
On day 2, a Developer requests test-database access but tells nobody about the blockage. It becomes visible at the Daily Scrum on day 4. The team flags the affected item and continues other work that supports the Sprint Goal. The Scrum Master contacts the infrastructure lead, explains the impact, and follows up; access arrives on day 5.
The immediate problem is solved, but the delay also reveals a process issue. At the Retrospective the team agrees to raise blockers within the hour and asks the infrastructure team how far ahead requests should be made. Earlier visibility and known lead times can prevent another late surprise.
Investigate recurring causes
The “five whys” technique asks why repeatedly until an actionable cause emerges. Tests failed late because the environment arrived on day 8. It arrived late because it was requested on day 6. The request was late because nobody knew the two-day lead time. That lead time was not recorded. Publishing it addresses a cause that another team can encounter again. Five is a useful name for the technique, not a required stopping point.
Organizational causes may outlast a Sprint. Keep them visible and ordered by impact, with evidence such as days lost or delayed items. Bring that evidence to people who can change the system. If the current goal is threatened while a fix is pending, the Developers adapt their plan and discuss scope with the Product Owner. Escalation provides transparency and help; it does not transfer the Sprint plan to a manager.
Key Takeaways
- Make the blockage, date, goal impact, and next action visible.
- Developers resolve what is within their capabilities.
- The Scrum Master causes removal where support or organizational action is needed.
- Follow up and investigate recurring causes.
- Adapt Sprint work with the Product Owner if the goal is threatened.
4Build quality and learn from each Sprint
Quality makes progress trustworthy, and improvement makes later Sprints more effective. A shared Definition of Done tells everyone which work is usable. The Sprint Review brings that work into a conversation with stakeholders, while the Retrospective examines how the Scrum Team worked. Learn to apply the quality standard consistently, facilitate both conversations, and turn a few well-chosen insights into changes the team can try and check.
4.1 Write a quality standard people can check
The Definition of Done describes the state of an Increment when it meets the quality measures required for the product. It is the Increment's commitment. When a Product Backlog item meets it, an Increment is born. Developers must conform to this shared standard.
Decide the standard together
An organizational Definition of Done is a minimum for every Scrum Team it applies to. A team may add stronger criteria. If no organizational standard exists, the Scrum Team creates an appropriate Definition of Done. Several Scrum Teams working on the same product must define and comply with the same standard together.
This prevents private meanings of “finished.” Without a shared standard, one person might mean “written,” another “tested,” and a stakeholder “ready to use.” Decisions about progress would then rest on different states of work.
Make each criterion checkable
“Good quality” and “tested enough” leave room for hidden disagreement. A useful criterion has a clear yes-or-no check. For a web application, criteria could include:
- Code reviewed by at least one other Developer.
- Automated unit and integration tests passing.
- Acceptance criteria verified by automated or recorded tests.
- No known critical or high-severity defects.
- Accessibility checks passed for changed screens.
- Deployment to staging completed and smoke-tested.
- User help updated where behavior changed.
Choose criteria because they protect the product's quality and usability. For example, “test coverage of new code is at least 80 percent” can be checked, but the team still needs tests that meaningfully examine the behavior. A measurable criterion gives a clear check; its relevance to quality gives it a reason to exist.
The same approach works outside software. A marketing product might require a second person's proofreading, a completed legal check, tested links and tracking, and publication on all planned channels. Done describes usable work without hidden finishing activities.
Separate shared quality from item behavior
| Question | Definition of Done | Acceptance criteria |
|---|---|---|
| What does it describe? | The shared quality state of the Increment | The expected behavior of one item |
| Where does it apply? | Across product work | To its particular Product Backlog item |
| What might it say? | Changed screens pass accessibility checks | An unavailable basket item shows a warning |
An item must satisfy its acceptance criteria and the Definition of Done. Passing its behavior checks does not excuse a missing quality check. Conversely, a technically clean implementation that fails the intended behavior is not a completed item.
Some teams use a Definition of Ready to remind them what helps an item enter planning. It is a complementary practice, not a Scrum requirement. Used as a rigid gate, it can block the very conversations that clarify work.
Keep the Definition of Done visible and use it when planning and checking items. A checklist on the wall that nobody applies provides little transparency. Quietly skipping a criterion near the Sprint's end hides work and can build technical debt: quality problems that make later changes harder.
Key Takeaways
- The Definition of Done is the shared quality commitment for the Increment.
- Follow an organizational standard as a minimum.
- Teams on one product share one Definition of Done.
- Write criteria that can be checked and protect usability or quality.
- Acceptance criteria describe an item’s behavior; they do not replace shared quality.
- A Definition of Ready is optional.
4.2 Use Done work in a productive Sprint Review
An item is Done only when it meets the Definition of Done. Developers plan the required quality activities and check the criteria before showing an item as Done. “Almost done” is still unfinished, even when most of the effort has already been spent.
Count completed work honestly
A team selects items sized 5, 3, 8, and 2 points, totaling 18. The 5-, 3-, and 2-point items meet the Definition of Done. The 8-point item is coded but untested. Completed work is:
The team completed 10 points. It cannot count all 18, or invent partial credit for the untested item. That item returns to the Product Backlog, where the Product Owner orders it for future consideration. It is not automatically selected next Sprint.
An item that misses the Definition of Done cannot be released or presented at the Sprint Review. Make the unfinished state transparent when discussing progress and problems, but do not demonstrate the item as part of the Increment. A convincing demonstration cannot substitute for its missing tests.
Inspect results with stakeholders
The Sprint Review inspects the Sprint's outcome and determines future adaptations. The Scrum Team and key stakeholders examine what was accomplished, what changed in their environment, and progress toward the Product Goal. The Product Backlog may change as new opportunities become clear.
For a one-month Sprint, the Review lasts at most four hours; shorter Sprints usually need less time. The whole Scrum Team contributes. A Product Owner presenting alone while Developers are absent loses direct discussion with the people who built the product and understand its trade-offs.
Treat the event as a working session. Let stakeholders try the Increment, ask what surprised them, and discuss what to change next. Consider relevant changes in market conditions, budget, or timing. Close with a visible picture of how the Product Backlog responds to what was learned.
For example, stakeholders testing a Done appointment reminder discover that customers now need to reschedule more often. The conversation can reveal a valuable next item and change the backlog order. Replaying a slide deck without inviting that discussion would miss the adaptation the event exists to enable.
Keep delivery independent of the event
The Sprint Review is not a release gate or stakeholder acceptance ceremony. Usable Increments can reach users before the Sprint ends, and a Sprint can create several Increments. Meeting the Definition of Done makes the quality state transparent; the Review supplies inspection and feedback about the product's direction.
If checks repeatedly uncover unfinished testing, bring that pattern to the Retrospective. The Review asks what the product results mean for future work. The Retrospective asks how the team can improve the way it creates those results. Neither event can turn an untested item into Done by agreement.
Key Takeaways
- Count only items that meet the Definition of Done as completed.
- Undone items return to the Product Backlog and are not released or presented at the Review.
- The Scrum Team and stakeholders inspect results and adapt future work.
- Use the Review as a working session; delivery can happen before it.
4.3 Guide a Retrospective from facts to choices
The Sprint Retrospective plans ways to increase quality and effectiveness. The whole Scrum Team inspects the last Sprint, including people, interactions, processes, tools, and the Definition of Done. It concludes the Sprint and lasts at most three hours for a one-month Sprint.
Give the conversation a useful shape
A widely used approach from Esther Derby and Diana Larsen has five phases. It is a facilitation practice, not a required Scrum agenda.
- Set the stage. State the focus and invite everyone to speak early.
- Gather data. Build a shared account of what happened before choosing explanations.
- Generate insights. Look for patterns and causes in those observations.
- Decide what to do. Choose a small number of concrete improvements.
- Close. Confirm actions and finish the conversation clearly.
For a two-week Sprint, a 60-minute session could use 5 minutes to set the stage, 15 to gather data, 15 for insights, 15 for decisions, and 10 to close. The total is 60 minutes. Use the time where the work needs it; the framework helps prevent a rush from one complaint straight to a solution.
Choose an activity that fits the issue
Start, Stop, Continue asks what to begin, end, and keep. Mad, Sad, Glad gathers reactions to events. The 4 Ls organize what people liked, learned, lacked, and longed for. A Sailboat uses wind for helpful forces, anchors for obstacles, rocks for risks, and an island for the destination.
If several people describe the same access delay differently, a Sprint timeline can help establish when the request, blockage, escalation, and resolution happened. If the team has a clear shared picture already, spend more time investigating causes and deciding what to try. Varying activities can keep the conversation useful, but novelty is not a substitute for a clear purpose.
Ground the discussion in evidence
Bring board history, chart patterns, impediment dates, items that missed Done, and Review feedback. Combine facts with people's experience. “Testing started on day 8” is a useful observation; “the testers never help” is an accusation that hides the process the team could change.
Facilitators often use Norm Kerth's Prime Directive to encourage a charitable starting point: understand people's actions in light of what they knew, their skills, resources, and circumstances. This supports investigation without pretending the results were satisfactory.
Silent writing before discussion gives everyone time to think. Turn-taking helps quieter people contribute before a confident speaker sets the explanation for the whole group. Keep attention on changes the team or organization can make.
The Scrum Master often facilitates but is also part of the team being inspected. Another Scrum Master or a Developer can facilitate occasionally so the Scrum Master can participate fully. Do not skip a Retrospective because the Sprint went well: useful practices may need protecting, and the team can still inspect how to improve them.
Key Takeaways
- Include the whole Scrum Team in inspecting quality and effectiveness.
- Gather observations before drawing conclusions or choosing actions.
- Choose a format that serves the issue.
- Use evidence, silent writing, and turn-taking to support a fair discussion.
- Keep the focus on causes and workable changes.
4.4 Turn an improvement into a checked experiment
A Retrospective produces value when the team changes something and learns whether it helps. “Communicate better” sounds positive but does not say what to do, who will drive it, or how to check its effect.
Choose a small number of actions
A useful action is specific, has someone to drive it, and can be checked. For example: “From next Sprint, review each item before it moves to testing. Sam will coordinate the experiment and bring the defect count from the Sprint Review to the next Retrospective.” The team can see both the new behavior and how it will examine the result.
Pick one to three improvements per Sprint. Finishing a few changes makes their effects easier to inspect than carrying ten unfinished actions. The most impactful improvements should be addressed as soon as possible; a team can improve its work in the middle of a Sprint without waiting for the next Retrospective.
Dot voting can help choose a focus. Six people with three dots each have 18 dots. Their votes might be 7 for an unstable test environment, 5 for too many meetings, 4 for unclear stories, and 2 for keeping successful pairing. This suggests investigating the environment first and possibly meetings second. Voting helps prioritize attention; the team must still choose a concrete response.
Reserve time and follow through
Make a chosen action visible. It may be added to the next Sprint Backlog so the Developers can account for its capacity and inspect it on the board. Work that relies on spare time is easy to postpone when delivery becomes busy.
Frame the action as an experiment: state the expected change, try it for a Sprint, and inspect the result at the next Retrospective. Keep, adjust, or stop the practice based on what happened. Open the next Retrospective by checking earlier actions so they do not disappear under new ideas.
Suppose a team expects a daily early review window to reduce items waiting overnight. A Developer coordinates the trial, and the team records whether review requests still wait into the next day. If waiting persists, inspect why before declaring the idea a success or failure. Perhaps the window conflicts with the reviewer's support duty, which the next version of the experiment can address.
Strengthen shared quality as capability grows
Better tools and skills can support a stronger Definition of Done, such as performance checks at expected peak load or production deployment where the product needs it. Plan the extra effort openly; the team may initially select less product work.
Quality must not decrease during a Sprint. A change to the Definition of Done must remain transparent, preserve product usability, and respect any organizational minimum. An end-of-Sprint deadline does not permit skipping a required check.
Some improvements need organizational help. A shared environment owned by another department may need an agreement beyond the team's control. Record the impediment and its impact, and involve the Scrum Master in reaching the people who can change it. The team can keep adapting what is within its own control while that work continues.
Key Takeaways
- Choose one to three specific improvements with a driver and a check.
- Make room for the action, including in the Sprint Backlog when useful.
- Try, inspect, and revise improvements as experiments.
- Stronger quality standards need visible capacity planning.
- Quality cannot decrease during a Sprint; organizational minimums still apply.
- Escalate improvement barriers that need organizational action.
5Help the team grow its own capability
A Scrum Master helps people make Scrum work and improve the team’s effectiveness. The useful response changes with the situation: explaining an unfamiliar rule, facilitating a decision, sharing experience, or helping someone think through a problem. Learn to choose that response deliberately, listen without steering people toward a hidden answer, and support self-management while still addressing obstacles and ineffective practices.
5.1 Choose how to help as a Scrum Master
The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide and for the Scrum Team's effectiveness. The 2020 Guide describes Scrum Masters as true leaders who serve. Earlier wording used “servant-leader,” a term still common in practitioner writing.
Serve three connected groups
For the Scrum Team, service means coaching self-management and cross-functionality, helping people focus on high-value Done Increments, causing impediments to be removed, and ensuring useful events within their timeboxes.
For the Product Owner, it includes finding effective Product Goal and backlog techniques, helping make items clear and concise, supporting empirical planning, and facilitating stakeholder collaboration. This helps the Product Owner fulfill the accountability; it does not transfer backlog ordering to the Scrum Master.
For the organization, service includes training and coaching Scrum adoption, advising on implementation, explaining how decisions can respond to observed results, and removing barriers between stakeholders and teams. An approval policy that repeatedly blocks usable work may need organizational discussion as well as team-level adaptation.
Match the stance to the need
Barry Overeem's practitioner model describes eight Scrum Master stances: servant leader, facilitator, coach, manager, mentor, teacher, impediment remover, and change agent. “Manager” here concerns impediments, boundaries, and process, not managing people. The model offers ways of helping; it does not add Scrum accountabilities.
Four stances are especially useful to distinguish:
| Stance | What the Scrum Master contributes | Example |
|---|---|---|
| Teacher | Knowledge and explanation | Explain the Daily Scrum's purpose and timebox |
| Mentor | Relevant personal experience and advice | Describe a technique used with an earlier team |
| Coach | Questions, listening, and reflection | Help the team explore why coordination is poor |
| Facilitator | A neutral process for discussion or decisions | Guide the team through comparing options |
A new team running long Daily Scrums may first need teaching. If the same issue returns, the Scrum Master might facilitate a Retrospective discussion. With an experienced team, coaching could begin with, “What does this event give you, and what would make its 15 minutes useful?”
Change the support as learning grows
Shu-Ha-Ri is a learning model borrowed from Japanese martial arts: follow the rules, adapt with understanding, then go beyond the learned forms. In Scrum coaching it can help explain why beginners often need more teaching and experienced teams more coaching. It is not permission to discard Scrum's essential elements while still calling the result Scrum.
Watch for roles that create dependence: writing every note, managing every calendar, policing rules without explaining purpose, assigning work as a boss, collecting daily status, or rescuing every problem. Administrative help can be useful, but it must not become the Scrum Master's identity while team effectiveness receives little attention.
Key Takeaways
- The Scrum Master is accountable for establishing Scrum and team effectiveness.
- Serve the team, Product Owner, and organization in distinct ways.
- Teach knowledge, mentor from experience, coach thinking, and facilitate a process.
- Choose and adjust the stance to the situation and the team’s experience.
- Avoid patterns that make the team dependent on a boss or rescuer.
5.2 Use questions and listening to support a decision
Coaching helps someone reach an insight and decision through questions, listening, and reflection. The people doing the work often understand their situation best. Exploring their own options can build more ownership than carrying out a solution handed to them.
Ask without hiding an answer
Open questions invite exploration: “What options do you see?” or “What have you already tried?” Closed questions confirm a fact or agreement: “Have you discussed this with the Product Owner?” Both can be useful. A leading question such as “Shouldn't you just split the story?” suggests that the coach has already decided.
Ask one question, then listen. Allow silence so the other person can think. Summarize what you heard and check it: “So the concern is that the item changes after planning. Have I understood?” The check matters because an inaccurate summary can steer the rest of the conversation toward the wrong problem.
“What” and “how” questions often invite a fuller account with less defensiveness than “Why did you do that?” A stream of open questions can still feel like interrogation if the person has no space to answer or sees no purpose in the conversation.
Structure the conversation with GROW
The GROW model, associated with John Whitmore's coaching work, offers four prompts:
- Goal: What do you want to achieve?
- Reality: What is happening now?
- Options: What could you do?
- Will, or Way forward: What will you do, and when?
Use the structure to support thinking, not to force a rigid sequence when new information changes the issue.
A Developer asks the Scrum Master to tell the Product Owner that items are unclear. First clarify the goal: “What would a clear item let you do?” Explore reality: “Which two items caused difficulty, and what was missing?” Explore options: “How could you raise those examples with the Product Owner?” Then agree a way forward: “What will you try before the next refinement?”
The Developer might choose to bring two examples to refinement and propose clearer acceptance criteria. The decision and conversation remain with the person who needs them. If organizational access or authority prevents action, the Scrum Master can help with that barrier without automatically taking over the whole problem.
Know when to give information directly
Coaching assumes there is something useful for the person to explore. A team that does not know the purpose of the Sprint Review needs teaching, not a guessing game. A Scrum Master who has relevant information should share it openly.
A serious imminent risk also needs a direct statement. If a planned release would expose customer data, name the concern and help the team respond. Do not withhold essential information to create a learning experience. Over several Sprints, watch the effect of your support: whether people make clearer decisions and increasingly handle the work themselves.
Key Takeaways
- Open questions explore; closed questions confirm; leading questions steer.
- Listen, leave thinking time, and check your understanding.
- GROW connects a goal, present reality, options, and a chosen next step.
- Use teaching when knowledge is missing and speak directly about serious risks.
5.3 Support self-management without becoming a gatekeeper
A self-managing Scrum Team decides internally who does what, when, and how. It is also cross-functional: together, members have the skills needed to create value each Sprint. These capabilities work within the Scrum framework, the Product Goal, the Definition of Done, and organizational constraints.
Protect ownership of the plan
The Scrum Master supports the Developers' right to plan and allocate their work. Assigning their tasks, setting their estimates, deciding technical approaches, or settling disagreements by decree takes those decisions away. Facilitate a way for the team to decide and make concerns visible instead.
For a new mid-Sprint request, connect the requester with the Product Owner. The Developers and Product Owner discuss any change to Sprint work in light of the Sprint Goal. This protects focus while keeping a path for valuable information.
Protection must not make the Scrum Master a gatekeeper for every conversation. Stakeholders and Developers can speak directly, including during refinement and at the Sprint Review. Product understanding suffers when every question has to pass through one person.
Agree how to decide
A clear decision rule helps people know what agreement means before discussion begins. A team might use consent, where no one has a serious objection; a majority vote; a fist-of-five check; or a designated person who decides after consultation. Choose a rule suited to the decision.
For a fist-of-five check, the team can agree that three to five fingers indicate support and one or two call for discussion of the concern. The value is making reservations visible. Treating a silent person as automatically agreeing would defeat that purpose.
Working agreements make the team's chosen habits visible. Examples include “Daily Scrum starts at 9:30,” “reviews within one working day,” or “core hours are 10:00 to 15:00.” The Scrum Master can facilitate writing them; the team owns and revisits them at Retrospectives.
Make progress transparent at team level
A manager asks for weekly hours per Developer. First ask what the manager needs to understand. If the concern is product progress, discuss the Increment, backlog, board, and forecasts and invite participation in the Sprint Review. Individual hours do not show whether the team is creating usable value.
If an individual report remains an organizational requirement, raise the tension openly and work with those who can address it. Quietly turning the Scrum Master into an individual performance reporter undermines trust and can encourage people to optimize personal numbers.
Step back without abandoning the accountability
As Developers run their own Daily Scrum, resolve more obstacles, and sometimes facilitate Retrospectives, the Scrum Master can reduce direct involvement. Success shows in the team's growing ability to act.
Stepping back still includes noticing ineffective patterns. If the team ignores its Sprint Goal or quality standard, make the observation visible and help it decide how to respond. Self-management needs room for ownership and clear feedback about the results of its choices.
Key Takeaways
- The team decides who does what, when, and how within shared boundaries.
- Protect focus and planning ownership while keeping direct collaboration possible.
- Agree decision rules and working agreements together.
- Make team progress transparent without turning it into individual scoring.
- Step back as capability grows and keep ineffective patterns visible.
6Collaborate across locations and time zones
A distributed team needs the same shared decisions and usable results as a team in one room. Distance makes access, timing, and participation more deliberate. Plan when everyone can collaborate, keep one visible record of work and decisions, and adapt event facilitation so people can contribute from every location. Hybrid teams need particular care when an office conversation could leave remote members outside the decision.
6.1 Create shared working conditions across locations
A distributed team works in different locations; a hybrid team combines people in an office with remote members. Scrum's accountabilities, events, artifacts, and commitments remain the same. The practical arrangements must give everyone access to the work and the decisions.
Find the real overlap
Suppose Amsterdam and New York members each work 9:00 to 17:00 local time. In January, Amsterdam is UTC+1 and New York UTC−5, so Amsterdam is six hours ahead. New York's 9:00 is Amsterdam's 15:00. Their overlap is 9:00–11:00 in New York and 15:00–17:00 in Amsterdam: two hours.
Place events that need everyone inside that overlap. Keep calendar invitations tied to named city time zones so the calendar can adjust for clock changes. A statement such as “the call is at 9:15” is incomplete for people in different places.
Under current rules, the United States changes clocks on the second Sunday in March and the first Sunday in November. The European Union changes on the last Sunday in March and October. The Amsterdam–New York gap is therefore five hours during the intervening weeks. A Daily Scrum at 9:15 New York then occurs at 14:15 Amsterdam, compared with 15:15 when the gap is six hours. Recheck the schedule around these transitions.
Write agreements people can use
Agree core hours, expected response times, urgent channels, camera use, and where decisions are recorded. A practical arrangement could put quick questions in chat, current work status on the board, and urgent or sensitive discussions on a call. Record local holidays so an apparent delay is not mistaken for a missed commitment.
Use one shared digital board and backlog, plus suitable calls, chat, and an online whiteboard. A physical office board with a separate remote copy creates a reconciliation problem: people may inspect different states of work. Everyone needs the same current picture.
If an occasional event must fall outside someone's working hours, rotate the inconvenience. A routine that always makes one location join late makes equal participation harder even if the meeting link works.
Collaborate on the same items
Avoid designing the work around location-based handoffs, such as building in one country and testing in another. Those handoffs add waiting and can conceal problems until the next location starts work. People across sites can pair, review, and test the same items so the team works toward shared Done results.
Hybrid events need explicit attention. People around a table may hear side comments that remote members miss, and hallway decisions may never reach the board. Having everyone join from their own device can put participation on a more equal footing; arrange the audio so this does not create echo. Record decisions in the shared place the team agreed to use.
Key Takeaways
- Find overlap from named city time zones and real working hours.
- Check daylight-saving transitions and share inconvenient meeting times fairly.
- Keep one shared board, backlog, and decision record.
- Collaborate across sites on the same items instead of separating work by location.
- Give remote members equal access to discussion and decisions.
6.2 Facilitate useful remote Scrum events
Remote Scrum events keep their purposes and timeboxes. Good tools help people participate, but a recording or a page of updates cannot perform an interactive decision on their behalf. Prepare the meeting around the work the participants must do together.
Prepare people and technology
Test access, sound, and shared tools before the event. Show the agenda and timer, and use short blocks with breaks when needed. A timebox is a maximum; there is no benefit in filling unused minutes after the event has achieved its purpose.
Agree how people ask to speak, such as a raised hand or a speaking order. Watch the chat as well as the call. Invite contributions from locations that have been quiet and leave time for someone to unmute or formulate a response. A written decision record helps people act afterward, but does not replace their participation.
Plan together on the shared board
For remote Sprint Planning, send candidate items a day ahead for individual reading. During the event, keep the draft Sprint Goal visible and build the plan on the shared board. Check agreement explicitly, for example by hearing from each person or using a fist-of-five check. Silence may reflect a connection delay, uncertainty, or disagreement.
Hold the Daily Scrum at the same time each working day inside the overlap. Walk the board and move detailed issues to a follow-up call. Written updates let others catch up, but the Developers still need to inspect progress and agree on the day's plan together. A list of independent updates can leave a dependency unresolved even when everyone has posted on time.
Make product feedback active
At a remote Sprint Review, give stakeholders a way to try the Done Increment during the session. With many participants, breakout discussions can gather more specific feedback than one long presentation. Collect observations in a shared document and show how the Product Backlog responds. Confirm access to the product before the session so time is spent inspecting it.
Create space for reflection
An online whiteboard can support the Retrospective. Begin with silent writing so people can contribute before a dominant speaker frames the issue. Anonymous input can help when trust is still growing. Invite people in turn, group observations, investigate causes, and choose actions the whole team can see.
A Scrum Master who facilitates should monitor both the chat and who has not spoken. If that person also wants to explore their own conduct, another facilitator can help them participate without managing the discussion at the same time.
Inspect the remote arrangement
Frequent late starts, multitasking, or one location dominating are evidence for a working-agreement discussion. Camera use should support participation under the team's agreement; an unseen face alone does not establish disengagement. Finish events with a short record of decisions and actions, and inspect later whether people could actually follow through from each location.
Key Takeaways
- Keep each event’s purpose and timebox when working remotely.
- Prepare shared access and check agreement explicitly.
- Written updates support the Daily Scrum but do not replace joint inspection and planning.
- Let stakeholders interact with Done work at the Review.
- Use silent input and deliberate turn-taking in remote Retrospectives.
- Inspect participation problems through the team’s working agreements.
Running Sprints in Practice examples
1Build a realistic Sprint plan
13 steps
- 1IntroductionStart with value and available effort
A useful Sprint plan connects an outcome with work the Developers can finish to the required quality. Follow a team preparing a two-week Sprint, then make planning choices in new situations.
The planning conversation has three topics: why the Sprint is valuable, what can be Done, and how to deliver it. Capacity and evidence make those choices informed; they do not make the choices for the team.
- 2ExplanationMake the inputs available
Bring the ordered Product Backlog, Product Goal, latest Increment, Definition of Done, projected capacity, and past performance. The whole Scrum Team creates the plan, with invited specialists advising where useful.
The Product Owner proposes value and prepares likely items. The Scrum Master prepares access, the setting, and the agenda. Planning is at most eight hours for a one-month Sprint, usually shorter for a shorter Sprint.
- 3ExampleCalculate the available person-days
Five Developers each have 10 working days before absences. A holiday affects all five, and one Developer also takes two days of leave.
The team has 43 person-days available. The holiday removes five person-days because it affects five people. The two leave days are additional, so they are subtracted once. Next, compare that capacity with a genuinely comparable performance record.
- 4ExampleUse a comparable record
The previous three Sprints each had 50 person-days and completed 21, 24, and 27 points of Done work. Their average is 24. A rough capacity adjustment gives:
About 20 to 21 points is a starting forecast. Developers must still check the specific work and available skills. A point total cannot show whether the only person who knows an essential system is on leave.
- 5ChallengeCheck the forecast input
Four Developers have 10 working days each, with 4 person-days of known absences. Earlier comparable Sprints had 40 person-days and averaged 20 Done points. What rough adjusted forecast follows?
---reveal---
Capacity is 36 person-days. The proportional forecast is:
Use 18 points as a starting judgment, then check items, skills, and uncertainty. Selecting 20 without review would ignore the lower capacity.
- 6ExplanationAgree on why the Sprint matters
The Product Owner proposes how the product could gain value. The whole Scrum Team defines one Sprint Goal, finalized before Sprint Planning ends. It is the Developers’ commitment and gives the Sprint focus.
“Returning customers can reorder a basket in under a minute” states an outcome. A story-number checklist names work but gives less direction when the implementation must change.
- 7ExampleChoose what supports the outcome
For the reorder outcome, copying a past basket and handling unavailable products may be essential. A redesigned history page may be optional. Ask which items the objective actually needs.
The Developers select the amount of work through discussion with the Product Owner. When it exceeds their forecast, they can split a usable slice, defer lower-value work, or narrow the proposed goal before finalizing it.
- 8ChallengeMake a planning trade-off
A planning proposal lets members pause a subscription themselves. The Developers can finish the pause flow and confirmation this Sprint, but cannot also finish an optional animation. What should the team discuss?
---reveal---
Discuss leaving the animation out of the selected slice while keeping the pause outcome. The Developers own the amount selected; the Product Owner helps judge value. Hidden overtime would make the forecast less realistic.
- 9ExplanationTurn selection into an actionable plan
The Sprint Backlog joins the goal, selected items, and delivery plan: why, what, and how. The Developers own and update all the planning detail needed to deliver the Increment.
Work often breaks into tasks of one day or less. Include required review, tests, documentation, and deployment work. A list of coding tasks alone understates what must happen before an item can be Done.
- 10TipLet detail grow with knowledge
The plan must be actionable, but every later task need not be known at the end of planning. Detail the near work and add tasks as learning grows.
If the Developers cannot describe how to begin an item, investigate it with the Product Owner. Refine or split it, or select another item that serves the goal. Vague task names will not resolve the missing understanding.
- 11ChallengeDeal with a personal queue
Developers agreed initial task owners. Now one person has three reviews waiting while another is available. Must the original owners remain fixed?
---reveal---
No. The Developers can adapt allocation, pair, or swarm to finish important items. Initial owners were their choice, and changing them can also be their choice. Having the Scrum Master hand out new assignments would move ownership outside the Developers.
- 12ChallengeConnect goal, scope, and quality
A goal-critical item is larger than expected. Developers could deliver a smaller usable slice within capacity, but only if they remove an optional behavior. Required tests still fit. What should they do with the Product Owner?
---reveal---
Discuss the smaller slice against the Sprint Goal and update the selected work and plan if it preserves that objective. Keep the required tests. Scope flexibility helps protect a useful, Done result without pretending the original selection is fixed.
- 13RecapLeave with a plan that can guide decisions
Before closing planning, check three things together: is the value clear, does the selected work fit the Developers’ informed forecast, and is there enough delivery detail to begin?
Make concerns explicit while the team can still change the proposal. During the Sprint, new knowledge goes into the Developers’ current plan. Unfinished items later return to the Product Backlog for ordering, not automatic carryover.
2Read the board and the charts together
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionTwo views of the same work
- 2ExplanationShow the real work states
- 3ExampleNotice a shared priority
- 4ChallengeRead toward completion
- 5ExplanationCheck the axes and units
- 6ExampleFind the midpoint gap
- 7ExampleCompare the rates required
- 8Key InsightSeparate scope from completion
- 9ChallengeInterpret a new chart change
- 10ChallengeCombine the trend with the board
- 11RecapTurn a signal into an investigation
3Recover a useful daily rhythm
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake daily coordination useful
- 2ExplanationInspect the goal in 15 minutes
- 3ExampleConnect contributions into a plan
- 4ChallengeChoose an outcome for today
- 5ExplanationRecognize reporting and debate
- 6TipPark detail without losing it
- 7ChallengeCorrect the cause of a long event
- 8ExampleExpose an access delay
- 9ExplanationAgree who can act
- 10ExamplePrevent the same delay next time
- 11ChallengeChoose the level of response
- 12Key InsightSeparate difficult work from an obsolete goal
- 13ChallengeAct before the next meeting
- 14RecapKeep the loop moving
4Follow quality into feedback and improvement
18 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionUse quality to make learning trustworthy
- 2ExplanationSet one shared quality standard
- 3ExampleMake the standard checkable
- 4Key InsightSeparate behavior from shared quality
- 5ChallengeApply both kinds of criteria
- 6ExampleCount only completed items
- 7ExplanationMake the Review a working session
- 8ChallengeKeep delivery and Review distinct
- 9ConnectionChange the question at the Retrospective
- 10ExplanationMove from observations to insight
- 11TipGive everyone a way to contribute
- 12ChallengeDelay the solution until the evidence is shared
- 13ExampleTurn a theme into a specific trial
- 14ExplanationUse voting to focus attention
- 15ChallengeClose the experiment loop
- 16Key InsightPlan for stronger quality
- 17ChallengeConnect Done work with the improvement choice
- 18RecapKeep the product and process learning connected
5Choose support that builds ownership
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionHelp without taking over
- 2ExplanationRecognize the accountability
- 3ExplanationMatch the stance to the need
- 4ChallengeChoose a first response
- 5ExplanationAsk and listen without a hidden solution
- 6ExampleClarify the goal and present reality
- 7ExampleExplore options and choose a next step
- 8ChallengeKnow when questions are insufficient
- 9ExplanationProtect decisions and collaboration
- 10TipMake the way of deciding explicit
- 11ChallengeSupport an effective boundary
- 12ChallengeRespond to a progress request
- 13RecapChoose support deliberately
6Make remote collaboration work
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionBuild one shared working environment
- 2ExampleFind the January overlap
- 3TipRecheck clock transitions
- 4ExplanationAgree the shared record and habits
- 5ChallengeChoose a shared slot
- 6ExplanationPrepare remote Planning
- 7ChallengeConnect written updates to daily planning
- 8ExampleGive stakeholders something to inspect
- 9TipOpen the remote Retrospective to every voice
- 10ChallengePrepare a constrained remote Review
- 11RecapInspect access as well as attendance
Running Sprints in Practice practice questions
Set 1: Plan, inspect, and finish useful work10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Coordinate the team and improve its work10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Read evidence and adapt the Sprint10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Resolve competing demands without hiding risk10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Connect quality, coaching, and adaptation10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Acceptance criteria
Action driver
Actionable plan
Active listening
Anti-pattern
Asynchronous update
B
Blocked marker
Burndown chart
Burnup chart
C
Capacity
Coaching
Consent
Core hours
Cross-functionality
D
Daily Scrum
Decision record
Definition of Done
Definition of Ready
Distributed team
Dot voting
E
Escalation
F
Facilitation
Fist-of-five check
Five whys
Follow-up
G
Gather data
Generate insights
GROW
H
Hybrid team
I
Ideal line
Impediment
Impediment list
Improvement experiment
Increment
L
Leading question
M
Mentoring
O
Open question
Organizational minimum
Overlap hours
P
Parking-lot list
Past performance
Person-day
Personal queue
Product-level forecast
R
Remote facilitation
Retrospective Prime Directive
Root cause
S
Scope negotiation
Scrum Master
Self-management
Set the stage
Shu-Ha-Ri
Silent writing
Single source of truth
Sprint Backlog
Sprint cancellation
Sprint forecast
Sprint Goal
Sprint Planning
Sprint Retrospective
Sprint Review
Stakeholder feedback
Stance
Start, Stop, Continue
Status reporting
Swarming
Swimlane
T
Task
Task board
Teaching
Technical debt
Thin slice
Timebox
Total scope
Transparency
U
Undone work
V
Velocity
W
Walking the board
Work in progress
Working agreement
- 1Agile Values and Principles
- 2Scrum Framework
- 3Product Backlog and User Stories
- 4Running Sprints in Practice
- 5Kanban and Flow
- 6Scaling Agile
About this lesson