Product Backlog and User Stories
Product Backlog, User Stories and Estimation
BeginnerLesson 3 of 6 in Agile and Scrum Course
What you will learn
- Explain what the Product Backlog is, who is accountable for it, and how continuous refinement keeps its top items small, clear and ready for Sprint Planning.
- Describe the Product Backlog and who manages itDefine the Product Backlog and its items, explain the Product Owner’s accountability and the Developers’ part, and recognize a healthy backlog.
- Refine the backlog continuouslyExplain what backlog refinement is, who takes part, when it happens and what it produces, so that items are ready for selection in Sprint Planning.
- Describe the Product Backlog and who manages it
- Write user stories from the user’s point of view, check them against INVEST, and split large stories into small slices that each deliver working value.
- Write a user story with a role, a goal and a benefitExplain what a user story is, write one with the common three-part template, and use the card, conversation and confirmation idea to keep it a prompt for collaboration.
- Check story quality with INVESTUse the six INVEST criteria to judge a user story, explain what each letter means and improve a story that fails one of them.
- Split large stories into thin vertical slicesBreak epics and oversized stories into smaller stories that each deliver working value, using common splitting patterns and avoiding splits by technical layer.
- Write a user story with a role, a goal and a benefit
- Write acceptance criteria that make each story testable, and tell them apart from the Definition of Done that applies to all work.
- Write clear, testable acceptance criteriaWrite acceptance criteria as a rule checklist or as Given-When-Then scenarios, make each criterion specific and testable, and use them to find gaps and oversized stories.
- Tell acceptance criteria apart from the Definition of DoneExplain how story-specific acceptance criteria, the team-wide Definition of Done and an optional Definition of Ready work together, and sort conditions into the right one.
- Write clear, testable acceptance criteria
- Size backlog items by comparing them with each other in story points, and reach shared estimates as a team with Planning Poker.
- Size items relatively with story pointsExplain why agile teams estimate by comparison, what a story point measures, and how to use a point scale, reference stories and affinity estimation.
- Estimate as a team with Planning PokerRun a round of Planning Poker step by step, use differing estimates to share knowledge, and avoid anchoring and false consensus.
- Size items relatively with story points
- Decide what comes first by weighing value, cost, risk and dependencies, and apply MoSCoW and Weighted Shortest Job First (WSJF) to real ordering decisions.
- Order items by value, cost, risk and dependenciesExplain the main factors behind backlog order, including cost of delay, and combine value with size to decide what to do first.
- Prioritize release scope with MoSCoWSort the requirements of a release or timebox into Must, Should, Could and Won’t Have, check the share of Must Have effort and use the categories to protect the release.
- Rank work with Weighted Shortest Job First (WSJF)Calculate WSJF from relative cost of delay and job size, rank a set of items, and interpret the result, including when a large item should be split.
- Order items by value, cost, risk and dependencies
- Measure velocity, use it as a range to forecast how much can be delivered by when, and track release progress with burn-down and burn-up charts.
- Measure and use velocityCalculate velocity from completed work, use a range from recent Sprints, adjust for capacity, and avoid turning velocity into a performance target.
- Forecast a release from velocityUse a velocity range to answer “When will this scope be done?” and “How much can we deliver by this date?”, and present the answer as a range with its assumptions.
- Track progress with burn-down and burn-up chartsRead and update release burn-down and burn-up charts, make scope changes visible and project a likely finish range.
- Measure and use velocity
Product Backlog and User Stories study guide
1Keep product work visible and ready
A useful backlog helps people see what matters next without pretending to know every future detail. Features, fixes, technical changes and research compete for attention in the same list. The Product Owner makes that order clear, while Developers bring knowledge of the work. Ongoing refinement turns the next few items into pieces the team understands well enough to discuss at Sprint Planning.
1.1 One list, with a clear owner
The Product Backlog is the changing, ordered list of work needed to improve a product. It gives the Scrum Team one source of product work. Its commitment is the Product Goal, the longer-term objective that helps explain why an item deserves attention.
What belongs on the list
A backlog item can be a feature, a bug fix, technical work or research. For a grocery delivery app, paying by card and correcting a coupon error belong alongside a payment-library upgrade and a short investigation of barcode scanning. Keeping technical work visible lets the Product Owner weigh its urgency against feature requests.
Scrum does not require a particular item format. A user story is useful for a user need; a plainly worded fix or upgrade can be clearer for other work. Refinement adds details such as description, order and size as needed. Items far from selection can stay rough.
The Sprint Backlog has a different purpose. It holds the Sprint Goal, the selected items and the Developers' plan for delivering them. Detailed tasks such as creating a test or changing a screen belong in that delivery plan; the Product Backlog does not need to become a list of every implementation task.
Who decides what
| Person or group | Responsibility |
|---|---|
| Product Owner | Communicates the Product Goal and items, orders the list, and keeps it visible and understood. |
| Developers doing the work | Size items and explain technical effort, risks and dependencies. |
| Stakeholders | Explain needs and discuss changes with the Product Owner. |
The Product Owner can delegate work, including writing items, but keeps accountability for effective backlog management. Explaining an item's value can help Developers understand it; it does not give the Product Owner control of the estimate. One product has one Product Owner and one Product Backlog, including when several teams work on it.
Order gives a usable sequence
“High priority” on five items leaves the next choice unresolved. An ordered backlog gives each item a position. For example, its top could be “Pay by credit card” (5 points), the coupon fix (2), the library upgrade before support ends on March 31 (3), a barcode-scanning investigation limited to 2 days, and “Save favorite products” (8). The sequence makes competing kinds of work visible together.
A common health check is DEEP: Detailed appropriately, Estimated, Emergent and Prioritized. “Detailed appropriately” means enough detail for how soon the work is likely to start. “Estimated” means useful sizes develop as work approaches selection. “Emergent” means learning changes the list. “Prioritized” points to an actual order, not a pile of tied labels.
Treating the backlog as a fixed contract creates waste: people fully describe distant items that may never be useful. Remove stale ideas, merge duplicates and revise the order as evidence changes.
Key Takeaways
- The Product Backlog is one changing, ordered source of product work serving the Product Goal.
- The Product Owner can delegate backlog work but keeps accountability for its management.
- Developers doing the work are responsible for sizing; the Sprint Backlog holds their delivery plan.
- DEEP calls for appropriate detail, useful estimates, adaptation and a clear order.
1.2 Refinement makes the next work clear
Backlog refinement means breaking items down and adding useful detail as the team learns. It happens throughout the Sprint. It is an ongoing activity, with no required Scrum meeting format or fixed duration.
Bring the right knowledge together
The Product Owner explains the need and its value. Developers ask how the work could fit together, identify risks and size it. A tester may expose an overlooked exception; a stakeholder or specialist may explain a rule. The Scrum Master can help the conversation stay useful.
Refinement includes clarifying needs, drafting acceptance criteria, splitting large items, sizing or resizing work, changing the order, and adding or removing items. A written item becomes clearer through this discussion. The Product Owner writing a complete document alone would miss questions that only the people doing the work can raise.
Add detail when it becomes useful
Imagine the backlog as an iceberg. The visible top contains small, well-understood items for the next Sprint or two. Deeper items are larger outlines, and distant ideas may have only a sentence. As an item rises, the team adds detail and checks its size. Writing all the detail months early risks having to rewrite it after users teach the team something new.
In the Scrum Guide, an item is ready for selection when Developers believe it can be completed within one Sprint. Many teams keep roughly one or two Sprints of ready work near the top. That gives Sprint Planning a useful starting point without committing the team to deliver that whole buffer.
Some teams use a Definition of Ready: for example, “acceptance criteria are clear,” “the item is sized,” and “blocking dependencies have been resolved.” It is an optional checklist. Use it to find the next conversation; a rigid approval gate can leave people waiting for paperwork instead of resolving the actual uncertainty.
Work through a refinement session
The grocery app's Product Owner brings “Pay by credit card.” Developers ask what happens when a bank declines payment, when a request times out and when an order is canceled. Those questions reveal several pieces of behavior.
The group separates approved payments, a clear declined-payment message, and card refunds. It drafts acceptance criteria for the first two. Developers size the three items at 5, 2 and 5 points. The Product Owner places refunds lower because cancellations are expected to be rare in the first month. The session has changed both the understanding of the work and its order.
A team might schedule 60 minutes each Wednesday and hold quick discussions between sessions. Earlier Scrum Guides, including 2013 and 2017, described refinement as usually taking no more than 10% of Developers' capacity. The 2020 Guide gives no percentage. Choose enough ongoing attention to keep near-term work understandable.
Leaving all refinement until Sprint Planning turns planning into a search for missing meaning. Refining everything far ahead produces detail that goes stale. The backlog can change during a Sprint as learning arrives; those changes must respect the current Sprint Goal.
Key Takeaways
- Refinement is an ongoing activity that clarifies, splits, sizes and reorders work.
- The Product Owner and Developers refine together, with experts when needed.
- Items ready for selection can be completed within one Sprint.
- Near-term items need more detail than distant ideas.
- A Definition of Ready is optional; the 2020 Scrum Guide sets no refinement percentage.
2Turn needs into small user stories
A short story helps a team discuss a real need before choosing the details of a solution. The role, goal and benefit give that discussion a direction; the three Cs connect the written card with conversation and checks. INVEST then helps the team find weak spots. When a story is too large, a useful split leaves a small behavior that works from end to end and can teach the team something through use.
2.1 The user, the capability and the reason
A user story describes something a person wants from a product, in that person's everyday language. It connects a capability to a reason for wanting it. The practice comes from Extreme Programming and became widely known through Mike Cohn's User Stories Applied (2004).
Make the need specific
A common template, usually credited to Connextra around 2001, is “As a [role], I want [goal] so that [benefit].” For the grocery app: “As a returning shopper, I want to save my delivery address so that I can check out faster.”
The role tells the team whose problem matters. “Returning shopper” is more useful than “user”: a delivery driver or store manager has different needs. A persona, a short profile of a typical user, can add context. A shopper who orders after night shifts may value different delivery choices from someone shopping for a business.
The goal states what the person needs to do. The benefit explains why. “Filter products by price” suggests a feature, but “so that I can stay within my weekly budget” exposes the purpose. The team can then discuss whether a running basket total could serve that purpose more simply.
A card starts a conversation
Ron Jeffries describes the three Cs:
- Card: a short record of the need, enough to remember and discuss it.
- Conversation: the exchange that uncovers rules, exceptions and possible solutions.
- Confirmation: the acceptance criteria or tests that show the story works.
The written sentence does not contain every requirement. Its job is to bring the right people into a useful conversation. The criteria capture what that conversation establishes about expected behavior.
Consider “Add an export button.” Ask who needs it and what they will do with the result. The request becomes “As a small-business owner, I want to export my monthly orders to a spreadsheet so that I can send them to my accountant.” Discussion then reveals a CSV file with date, amount and sales-tax columns. A CSV (comma-separated values) file stores rows of data with commas between fields. The story holds the purpose; the criteria hold these observable details.
Keep the format useful
An epic is a story too large to complete in one Sprint. “Pay online so that I don't need cash at the door” may need several smaller stories. A theme groups related stories, such as checkout. These labels help organize work without replacing the need to make near-term items small and clear.
Other backlog items can use direct wording. “Fix: the order total ignores the coupon” is clear. An upgrade can state its reason: “Upgrade the database before vendor support ends on March 31 so that security patches remain available.” Recasting that as “As a developer, I want an upgrade so that it is upgraded” adds no useful need.
Two weak stories fail in different ways. “I want a great app” gives no behavior to discuss or test. “I want a dropdown with every address field fixed in advance” chooses the design before the team understands the need.
Key Takeaways
- A story connects a specific role, a desired capability and its benefit.
- The three Cs are Card, Conversation and Confirmation.
- An epic needs splitting; a theme groups related stories.
- Bug fixes, technical changes and research can use clear direct descriptions.
2.2 Use INVEST to improve a story
INVEST, introduced by Bill Wake in 2003, names six qualities that help a team discuss a story: Independent, Negotiable, Valuable, Estimable, Small and Testable. A weak letter points to a question or improvement.
Check all six qualities
| Quality | What to check | A useful response |
|---|---|---|
| Independent | Can the story be delivered without waiting for another story? | Reduce the dependency or make the necessary order visible. |
| Negotiable | Can the team discuss details while keeping the purpose? | Remove design choices that close discussion too early. |
| Valuable | Does the story give a user or customer something useful? | Connect the work to a real outcome. |
| Estimable | Do Developers understand enough to size it? | Clarify the business rule, investigate or split it. |
| Small | Can it fit comfortably in one Sprint? | Find a smaller useful slice. |
| Testable | Can someone observe whether it works? | Add specific acceptance criteria. |
Independence gives the Product Owner more freedom to order work. Suppose two card-network stories both need the same payment flow. Building the first includes setup that the second reuses. Calling them separate stories does not remove that dependency. The team can combine them if small enough, find another split, or keep the dependency visible and order them accordingly.
Negotiable stories leave room to find a workable solution. Valuable stories have a reason beyond completing an internal component. “Create the orders table” may be needed, but “View past orders so that I can reorder quickly” expresses the user outcome it supports. Technical work with its own business reason can still be a backlog item.
Match the remedy to the problem
“Not estimable” has several possible causes. A missing business rule calls for a conversation with the Product Owner or users. An unknown technical capability may call for a short, time-boxed investigation, called a spike. A story covering too much behavior needs splitting. Voting harder does not resolve missing knowledge.
Small means comfortably finishable within a Sprint, often a few days for a few Developers, leaving room for other work. Testable means there is an observable result. “Checkout is fast” leaves room for disagreement. “Checkout confirms an order within 2 seconds for 95% of orders” gives a measurable condition.
Improve a vague payment story
“As a user, I want the app to support payments” leaves payment methods and completion unclear. The team cannot yet judge its size or test it. Rewrite it as “As a shopper, I want to pay for my order with a credit card so that I don't need cash at the door.” Add a criterion such as “A successful payment shows an order confirmation number.” Developers can now assess the scope and decide whether another split is needed.
The letters sometimes pull in different directions. A smaller slice can create a dependency; an independent technical piece may give no visible user value. Work through those trade-offs in refinement. A slice must still deliver useful behavior that the team can demonstrate working.
Key Takeaways
- INVEST names six qualities: Independent, Negotiable, Valuable, Estimable, Small and Testable.
- Fix an unclear business rule through conversation; use a spike for a technical unknown.
- Small stories fit comfortably in a Sprint and have observable completion conditions.
- Splitting can create dependencies, so check the resulting slices again.
- Use INVEST to guide improvements and discuss trade-offs.
2.3 Split work so each slice works
A large story hides choices, unknowns and risk. Split it during refinement when it is too big for one Sprint, hard to estimate, or contains pieces with very different value. The aim is a small useful result that can be completed and tested.
Cut through the layers
A vertical slice includes the screen, logic and data work needed for one behavior to work from end to end. An API is a connection through which software parts exchange requests and data. A horizontal split separates components: database first, API next, screen last. Those pieces can be implementation tasks, but users cannot try the feature until they come together.
For delivery scheduling, “Create the scheduling database” leaves shoppers unable to choose a delivery. “Choose a day from the next 7 days with a standard daytime window” gives them a usable first version. Later stories can add 2-hour windows, show full windows, allow changes after ordering and add an evening fee.
The first slice is usable by itself. Later slices can build on it: changing a delivery time needs scheduling to exist, and an evening fee needs time windows. Record and respect those dependencies. Size each slice separately; discovering work while splitting can make their total larger than the original rough estimate.
Choose a useful splitting pattern
| Pattern | First slice | Later slice |
|---|---|---|
| Workflow | Search for products | Add a selected product to the basket |
| Business rule | Standard delivery | Express or weekend delivery |
| Data | One supported address format | Additional address formats |
| Interface | Website | Mobile app |
| Operation | Create a saved entry | Edit or delete it |
| Simple then complex | Place one order | Place bulk orders |
| Quality improvement | Support 100 users | Tune for 10,000 users |
Mike Cohn's SPIDR groups five prompts: Spike, Paths, Interfaces, Data and Rules. Paths can separate approved payments from declined payments or timeouts. Interfaces separate channels or devices. Data and Rules reduce the range handled by the first useful version. A spike investigates a question before the team sizes the delivery work.
Make the happy path a complete behavior
For card payment, first handle an approved card and show confirmation. Add separate behavior to explain a decline while keeping the basket, then allow retry after a timeout. Each later story improves a working payment flow. The team must still meet the Definition of Done for every delivered slice; reducing scope does not remove the quality standard.
A spike has a time limit and a learning outcome, such as spending at most 2 days checking whether a mapping service can calculate delivery times. It produces knowledge. Use that knowledge to size or split the feature next. An open-ended “research everything” item gives no useful stopping point.
Avoid splitting into design, coding and testing stories, which delays proof that the behavior works. Also avoid fragments such as “Add the Save button” when nothing useful can yet be saved. The Product Owner may decide a low-value later slice is unnecessary after seeing what people do with the first version.
Key Takeaways
- A vertical slice delivers a small behavior through all the layers it needs.
- Split by behavior, path, interface, data or rule; keep dependencies visible.
- SPIDR means Spike, Paths, Interfaces, Data and Rules.
- A spike has a time limit and produces knowledge that helps the next decision.
- Estimate slices independently; their total can differ from the epic estimate.
- Skipping low-value later slices is a useful outcome of splitting.
3Make completion clear
People can agree on a story title and still picture different results. Acceptance criteria turn that discussion into observable behavior, including exceptions and limits. A shared Definition of Done adds the quality standard for every finished item. Keeping these two ideas clear helps the team size the work honestly, test the intended result and avoid treating a partly finished feature as progress that is ready to release.
3.1 Write criteria people can check
Acceptance criteria describe the conditions a particular story must meet. They make its Confirmation concrete by saying what the product should do. The Product Owner brings business rules; Developers and testers help expose missing cases before the team sizes or builds the item.
Start with observable rules
For “As a returning shopper, I want to save my delivery address so that I can check out faster,” a checklist could say:
- A signed-in shopper can save up to 5 addresses.
- One saved address can be marked as the default.
- Checkout preselects the default address.
- The ZIP code must have 5 digits.
- A shopper can delete a saved address.
These are rules for this example's address service. Each states a result someone can check. “Store the address in table X” chooses an implementation, while “The default address is preselected” describes the expected behavior. The team can discuss different designs that satisfy that outcome.
Turn a rule into a scenario
Given-When-Then, used in behavior-driven development, separates three parts of an example:
| Part | Purpose | Address example |
|---|---|---|
| Given | Starting situation | “I am signed in and have a default address.” |
| When | Action or event | “I start checkout.” |
| Then | Expected result | “My default address is preselected.” |
A scenario can also use “And” to add a related step or result. For invalid input: “Given I am adding a new address, When I enter the ZIP code ‘9021’ and select Save, Then the address is not saved And I see ‘Enter a 5-digit ZIP code.’” This gives a tester a starting state, a specific input and an observable result.
A rule checklist is compact when many cases follow one rule. A scenario makes a particular example concrete. Either can support manual or automated checks; the format itself does not ensure the behavior is well understood.
Find the missing cases
After the success path, ask what happens at a limit or an exception. What happens on a sixth saved address? What if the shopper deletes the default? What should a signed-out shopper see? These questions can uncover decisions that change the estimate.
Replace words such as “quick,” “easy” and “user-friendly” with observable behavior. “Order history shows the latest 20 orders within 2 seconds” gives a measurable target. “A shopper can reorder a past order with one tap” describes an action. A performance criterion also needs agreed test conditions so people can apply it consistently.
Draft criteria during refinement. Writing them after building tends to describe the implemented result, even when it misses the need. A long list covering several kinds of addresses can reveal an oversized story: group related behavior into smaller stories. Shared requirements such as code review belong in the Definition of Done, so they do not need to be copied into every story's criteria.
Key Takeaways
- Acceptance criteria state observable outcomes for one item.
- Given sets the starting state, When names the event, and Then gives the result.
- Cover important exceptions, limits and permissions alongside success.
- Write criteria before building; a long list may reveal a useful split.
3.2 Apply the right completion standard
An item can do what its story asks and still have unfinished quality work. Acceptance criteria describe its required behavior. The Definition of Done describes the quality state an Increment must reach. A finished item must satisfy both.
Three checks with different jobs
| Check | Applies to | Main question |
|---|---|---|
| Acceptance criteria | One story or item | Does this behavior work as agreed? |
| Definition of Done | The Increment and every completed item | Does the work meet the product's quality measures? |
| Definition of Ready | Items approaching selection, if the team uses it | Is there enough understanding to plan the work? |
Scrum requires the Definition of Done. A Definition of Ready is an optional team practice. When an organization sets a Definition of Done standard, teams follow it as a minimum. Without one, the Scrum Team creates a suitable definition for the product.
For the grocery app, a team might require a second Developer's code review, passing automated tests, test coverage for new behavior, support for the two latest iOS and Android versions, accessibility checks and deployment to a test environment. These measures apply across features. They do not say how many addresses a shopper may save or what checkout should preselect.
Sort by purpose
“A shopper can save up to 5 addresses” is an acceptance criterion for saved addresses. “The ZIP code field rejects letters” also describes that feature's behavior. “Automated regression tests pass” is a shared quality measure and belongs in the Definition of Done. “The item is small enough for a Sprint” is a possible readiness check before selection.
A useful test is to ask whether the condition changes with the feature. The address limit belongs to that item. Code review continues to apply when the team moves on to payment or delivery scheduling.
Handle work that is not done
Suppose saved addresses behave correctly, but the required accessibility checks have not passed. The item is unfinished. It cannot be released or presented at the Sprint Review. It returns to the Product Backlog for future consideration. If the team uses velocity, its points do not count for this Sprint.
Passing acceptance criteria does not excuse missing quality work. “Done except for testing” hides a real gap: testing is part of the work needed to reach the agreed standard. Passing shared tests alone still leaves the story's particular behavior to check.
The Definition of Done can become stricter as the team improves, such as adding performance checks once they can be run consistently. Lowering it to make more items appear complete changes what the numbers mean and hides unfinished work. Keep the shared definition in one clear place; copying it into every story's criteria creates repeated text that can drift out of date.
Key Takeaways
- Acceptance criteria define item behavior; the Definition of Done supplies shared quality measures.
- An item must meet both before it counts as finished.
- An organizational Definition of Done is the minimum standard.
- An item missing the Definition of Done returns to the Product Backlog and earns no velocity points.
- A Definition of Ready is optional and checks readiness before selection.
4Size work through comparison
An estimate helps a team compare work and discuss what it understands. Story points combine effort, complexity and uncertainty on a shared team scale. Familiar reference stories keep that scale steady. Planning Poker brings individual judgments into the open at the same time, so a surprising estimate can reveal a missing rule or technical risk before the team chooses a size and starts the work.
4.1 Build a steady story-point scale
Relative estimation asks how large one item is compared with known work. It can be quicker than predicting hours because people can compare familiar pieces without planning every task. The Scrum Guide makes Developers doing the work responsible for sizing; it does not prescribe story points or require a number on every item.
What points measure
A story point is a unit-free measure of overall size. It combines the amount of work, complexity and uncertainty. For one team, an 8-point item represents roughly four times the effort of a 2-point item. A point value stays attached to the work, not to the speed of a particular person.
Teams often use 1, 2, 3, 5, 8, 13, 20, 40 and 100. The widening gaps acknowledge the uncertainty of large items. Some decks add 0 and ½; early rough estimates may use T-shirt sizes from XS to XL. An item above about 13 points often needs splitting, although the team's actual ability to finish it within a Sprint is what matters.
Choose anchors, then compare
Take a story everyone understands, such as “Show the shopper's order history,” and agree it is a 3. A new item that looks slightly smaller may be a 2. An item that looks about twice as big suggests 6; because 6 is off the scale, discuss whether 5 or 8 better reflects the work and uncertainty.
Check against more than one anchor. A new 5 should look larger than established 3s and smaller than established 8s. This triangulation catches a gradual shift in what the numbers mean. The purpose is a stable comparison, not a mathematically precise measurement of effort.
For many items, affinity estimation offers a quick first pass. Team members silently arrange cards from smallest to largest. They discuss cards that keep moving, then group the row under point values. The contested items get attention while routine comparisons take little time.
Keep estimates useful over time
The Product Owner explains value and acceptance criteria, and Developers supply sizes. New knowledge can justify resizing an item that has not started. A completed item keeps its estimate; changing it afterward to fit the time spent would distort the history used for forecasting.
Point scales belong to teams. A 5 on one team may represent different work from a 5 on another. Comparing their point totals says little about productivity. Setting “1 point = 6 hours” also changes the method into time estimation, losing the flexible comparison that points provide. Relative estimates are not established as more accurate than hour estimates; their usefulness comes from the team's shared understanding and consistent use.
Agree how to handle bugs and spikes. Either can receive points or be handled without them, but switching rules between Sprints makes velocity hard to interpret. The estimate helps planning; treating it as a deadline or letting someone reduce it by authority prevents the team from reporting what it actually expects.
Key Takeaways
- Story points compare overall work, complexity and uncertainty within a team.
- Use reference stories and several comparisons to keep sizes consistent.
- Affinity estimation orders many items before grouping them into sizes.
- Resize unstarted work when knowledge changes; keep completed estimates unchanged.
- Points do not convert to fixed hours or compare productivity across teams.
4.2 Use Planning Poker to uncover assumptions
Planning Poker combines a private estimate with a shared discussion. Developers reveal their chosen cards at the same time. The useful result is an agreed view of the work and its size, including any questions that must be resolved first.
Run a round
- Give each estimator the team's point scale.
- Have the Product Owner explain the item and its acceptance criteria.
- Let estimators ask questions and discuss briefly.
- Have each person choose a card privately.
- Reveal all cards together.
- Ask the highest and lowest estimators to explain their reasons.
- Discuss what those reasons change, then vote again.
- Record a size once the estimates converge.
The Developers doing the work vote. The Product Owner answers questions about need and scope but does not set or vote on the size. The Scrum Master or another team member can facilitate and keep time.
James Grenning described Planning Poker in 2002, and Mike Cohn popularized it. Like the older Wideband Delphi method, it brings separate judgments into a group discussion. A few minutes per well-refined item often gives enough time; repeated long debates can indicate that the item needs further refinement.
Follow a disagreement
For “Reorder a past order with one tap,” the first reveal is 3, 5, 5 and 13. The low estimate assumes the existing basket can be reused. The high estimate includes finding substitutes for products now out of stock.
Those are different understandings of scope. The team agrees to skip unavailable products in this story and handle substitutes separately. The next reveal is 5, 5, 5 and 8. After hearing the plan, the estimator who chose 8 agrees to 5. The team records 5 and creates a separate substitute-products story.
The discussion has changed what will be built. Averaging the first cards would give 6.5, an off-scale number that conceals the disagreement. A majority vote could also overlook the one person who spotted a real complication.
Protect independent judgment
When a senior person announces “This is a 3” first, others may drift toward 3. This is anchoring. Simultaneous reveal protects the first judgment of each estimator and gives quieter people a way to show a different view. Remote tools need to hide votes until everyone has chosen for the same reason.
A question-mark card means more information is needed. An infinity sign or the highest card can mean the story is too big; a coffee-cup card can request a break. A missing business rule calls for clarification. A technical unknown may call for a short spike. An oversized item needs splitting.
Most items converge in a few rounds. If one does not, the team can gather information, split it or agree a more cautious size. The facilitator helps expose the reason for disagreement; pressuring people to match the majority creates a neat number without shared understanding.
Key Takeaways
- Explain the item, choose privately, reveal together, discuss extremes and vote again.
- Developers vote; the Product Owner clarifies scope and value.
- Simultaneous reveal reduces anchoring.
- Discuss differing assumptions instead of averaging the cards.
- An unresolved unknown or oversized item goes back to refinement.
5Choose what delivers value soonest
A backlog order turns competing needs into a sequence the team can act on. Value matters, but size, risk, deadlines and dependencies can change which item should come first. MoSCoW helps stakeholders agree the scope a release needs and the flexibility it retains. WSJF adds a comparison of delay cost with size, giving the Product Owner another way to discuss the order as circumstances change.
5.1 Balance value, size, risk and delay
Ordering gives each backlog item a place in the sequence. The Product Owner is accountable for that order, and the organization respects those decisions. Useful inputs include user and business value, cost, risk, dependencies, learning and time constraints.
Value must be weighed against size
Value can mean revenue, saved cost, greater customer satisfaction, compliance or progress toward the Product Goal. Before release, its size is uncertain. Rough relative judgments support comparisons; actual use provides better evidence for later decisions.
An item with value 8 and size 8 offers 1 unit of value per point. Another with value 5 and size 2 offers 2.5. The second can deliver more value for the same sized investment, even though its total value is lower. A deadline or dependency can still change the order, so the ratio starts a discussion.
Risk also matters. Connecting the grocery app to an unfamiliar payment provider early may reveal a serious problem while there is time to respond. The learning can justify doing it before a more visible enhancement. Dependencies create required sequences: showing a driver on a map needs a way for the driver to share location. Reduce that dependency if possible, or make it explicit.
Make the cost of waiting visible
Cost of delay is value lost per period while an item remains unavailable. A feature might lose sales each week; a deadline can make the cost rise sharply as it approaches. Unlike total value, this measure asks what waiting costs.
For work done one item at a time, compare cost of delay divided by duration, often called CD3. Feature A loses $10,000 per week and takes 2 weeks, giving a score of 5,000. Feature B loses $4,000 per week and takes 1 week, giving 4,000. The higher score suggests A first.
Check the whole sequence
Each feature incurs delay until it is available. If A goes first, it waits 2 weeks and B waits 3 weeks, including A's development:
- A's delay costs $20,000.
- B's delay costs $12,000.
- Total delay costs $32,000.
If B goes first, B waits 1 week and A waits 3:
- B's delay costs $4,000.
- A's delay costs $30,000.
- Total delay costs $34,000.
A first gives the lower combined loss under these durations and steady delay costs. Choosing B merely because it is shorter would miss how expensive A is to postpone.
Revisit the order with new evidence
A stakeholder's seniority is not a measure of value, and a loud request can hide a smaller but more urgent need. Ask what outcome matters, what delay costs, what is required first and what the team needs to learn. The Product Owner uses these answers to set one visible sequence.
After a Sprint Review or a refinement conversation, an item's value, size or risk may look different. Update the order then. An old ranking should not keep directing work after its reasons have changed.
Key Takeaways
- The Product Owner orders work using value, size, risk, learning, deadlines and dependencies.
- Value per point can reveal small items with strong returns.
- Cost of delay measures value lost for each period of waiting.
- For sequential work with steady delay costs, a higher delay-cost/duration score favors earlier delivery.
- Check dependencies and refresh the order when evidence changes.
5.2 Protect release scope with MoSCoW
MoSCoW sorts work into Must Have, Should Have, Could Have and Won't Have this time. Dai Clegg developed the technique, which became a core practice of DSDM. It helps people agree what a particular release or timebox needs and what can give way if work takes longer.
State the timeframe first
An item can be a Should for March and a Must for June. Always name the release or timebox before assigning a category. Without that boundary, people tend to treat every valuable future need as essential now.
| Category | Meaning for the chosen timeframe |
|---|---|
| Must Have | The release would be unusable, unsafe or illegal without it, with no workable alternative. |
| Should Have | Important, but the release can work without it, perhaps using a painful workaround. |
| Could Have | Desirable, with less impact if omitted. |
| Won't Have this time | Explicitly outside this release or timebox. |
DSDM uses “Minimum Usable SubseT” to help explain Must. Ask what would happen if the item were missing. Strong stakeholder enthusiasm alone does not answer that question. “Won't Have this time” manages expectations for this release; the item can be reconsidered later.
Leave room for uncertainty
DSDM recommends no more than about 60% of planned effort in Must Haves and about 20% in Could Haves. The remaining effort is typically Should Have work. These shares describe effort, not the number of items.
Shoulds and Coulds supply flexibility: when work takes longer, lower-priority scope can be dropped while Musts remain achievable. Labeling almost everything Must removes that flexibility. Counting tiny Could items alongside large Musts can also make a risky plan look balanced.
Check a release plan
The grocery team expects about 30 points per Sprint over 3 Sprints, or about 90 points. Sixty percent of 90 is 54, giving a guide of no more than about 54 Must points.
It chooses 50 Must points, 22 Should points and 18 Could points. Musts take about 56% of effort; Coulds take 20%. If only 75 points are completed, 50 points can still satisfy all Musts, leaving 25 for selected Shoulds and Coulds. The exact selection follows the Product Owner's order and any dependencies.
Compare that with 75 Must points in the same 90-point plan. Almost 84% of effort is now essential. The team has little room to absorb uncertainty without cutting something described as indispensable. Recheck whether the scope can be reduced, split or moved to another timeframe.
Keep an ordered backlog
MoSCoW supplies categories for agreeing scope; it does not create a full sequence. Two Must items still need an order, and an enabling dependency may affect when work can start. The Product Owner keeps the Product Backlog ordered within the release plan and revisits categories when the timeframe or evidence changes.
Key Takeaways
- Assign MoSCoW categories for a named release or timebox.
- A Must is essential to a usable, safe, lawful release with no workaround.
- DSDM recommends about 60% or less Must effort and about 20% Could effort.
- Shoulds and Coulds create scope flexibility; Won't means outside this timeframe.
- MoSCoW categories still need a Product Backlog order.
5.3 Calculate and interpret WSJF
Weighted Shortest Job First (WSJF) compares the cost of waiting with how long a job takes. Donald Reinertsen's work on product development flow underlies the approach. SAFe popularized a relative-score version, often applied to larger features and epics.
Build the score
SAFe adds three relative judgments to estimate cost of delay:
- User-business value: what users and the organization gain.
- Time criticality: how quickly value decays or a deadline approaches.
- Risk reduction and/or opportunity enablement: how much the work reduces risk or makes future work possible.
Then calculate WSJF = cost of delay ÷ job size. Size acts as a stand-in for duration. A higher result is an earlier candidate.
Score one column across all items before moving to the next column. Within each column, give the smallest a 1 and compare the others on a scale such as 1, 2, 3, 5, 8, 13 and 20. Do this for the three delay components and job size. Column-by-column comparisons keep the scale relative. Do not mix dollar values in one column with relative scores in another.
Work through a ranking
| Item | Value | Time | Risk/opportunity | Cost of delay | Size | WSJF |
|---|---|---|---|---|---|---|
| A: One-tap reorder | 13 | 5 | 3 | 21 | 8 | 2.625 |
| B: Saved addresses | 8 | 3 | 2 | 13 | 3 | 4.333… |
| C: Fraud screening | 3 | 13 | 8 | 24 | 5 | 4.8 |
| D: Dark mode | 1 | 1 | 1 | 3 | 1 | 3.0 |
For C, first add 3, 13 and 8 to get 24. Divide 24 by 5 to get 4.8. Repeat for each row, then rank from highest to lowest: C, B, D, A. Ranking by the total delay score alone would miss how quickly a smaller job can deliver its benefit.
Use a low score to ask a better question
A has the largest user-business value but finishes last because of its size. Splitting may reveal a useful first slice. If that slice has cost of delay 13 and size 3, its score is about 4.3, near B. Reassess the slice's value and size; keeping all the epic's value while shrinking its size would exaggerate the benefit.
Product Owner and business stakeholders contribute knowledge of value, deadlines and risk. Developers contribute knowledge of size. A score is a shared judgment, so a difference such as 3.0 versus 3.2 needs discussion, not claims of precision.
Recalculate when deadlines approach or new facts arrive. For started work, use remaining job size, because effort already spent cannot be recovered. Dependencies and the Product Goal still shape the Product Owner's final order. Reversing the division to size ÷ cost of delay would favor large, low-benefit work and invert the intended ranking.
Key Takeaways
- Add value, time criticality and risk/opportunity scores to get relative cost of delay.
- Divide cost of delay by size and rank higher scores first.
- Score each column across items, with the smallest in that column set to 1.
- A low score caused by size can suggest splitting into valuable slices.
- Refresh scores and discuss close results, dependencies and the Product Goal.
- Use remaining size for started work; sunk effort cannot be recovered.
6Forecast from work that is actually done
A forecast connects the work still needed with the team's recent delivery. Velocity gives one view of that history, provided estimates and completion standards stay consistent. Use a range to explore fixed-scope and fixed-date questions, then update it as scope or capacity changes. Release charts make those changes visible so stakeholders can respond while there are still useful choices about scope and timing.
6.1 Measure velocity without hiding unfinished work
Velocity is the amount of work a team finishes in a Sprint, usually the sum of the story points of done items. It is a complementary planning practice. Scrum does not require it, and the Sprint Goal remains more important than reaching a point total.
Count only completed items
Suppose the grocery team finishes items sized 5, 3, 8 and 5. Another 8-point item is 90% complete but misses the Definition of Done. Velocity is 21 points. Adding 7.2 points for the unfinished item would make partially completed work look available when it is not.
The unfinished item returns to the Product Backlog for future consideration. Its points count in the Sprint where it becomes done. This keeps the measure tied to usable work, including all the quality checks in the Definition of Done.
Use several recent Sprints
Recent velocities of 27, 31, 24, 30 and 28 total 140. Dividing by 5 gives an average of 28, with an observed range from 24 to 31. Using the last three instead gives about 27.3. Either working window should be chosen consistently and interpreted with the team's circumstances.
The idea that upcoming delivery may resemble recent delivery is sometimes called “yesterday's weather.” The best Sprint alone is a poor guide to normal planning. A recent range exposes variation that a single average hides. Developers use that history alongside capacity when selecting work at Sprint Planning.
Adjust for known capacity changes
If 28 points were typical with 50 developer-days available, an upcoming Sprint with 40 developer-days suggests a rough adjustment: 28 multiplied by 40, divided by 50, gives 22.4, or about 22 points. A developer-day measures one person's available workday; it is not a fixed number of story points.
This proportional adjustment is rough. A change in skills, a bottleneck or unusually complex work can change delivery differently. Developers still choose what they believe fits. A new team starts without velocity, selects what it believes it can finish, and measures the result over its first Sprints.
Preserve a comparable history
Membership, Sprint length, point scale and the Definition of Done affect the meaning of the data. After a substantial change, older velocities become less useful; collect observations under the new conditions. Keep the same policy for whether bugs and spikes receive points.
Comparing teams' velocities mixes different scales and different work. Setting a target to raise velocity by 10% invites bigger estimates for unchanged work. That can raise the number without increasing delivered value and makes future forecasts harder to trust. Some teams instead count completed items, called throughput, when items are similarly small. Whichever measure is used, it should help understand delivery and plan the next work.
Key Takeaways
- Velocity sums points of fully done items in one Sprint; unfinished items receive no partial credit.
- Use several recent Sprints and keep the observed variation visible.
- Adjust roughly for known capacity changes, then let Developers judge the selection.
- Changes in team, Sprint length, scale or quality standard weaken old comparisons.
- Velocity supports a team's forecast and should not become a productivity target.
6.2 Forecast scope or timing as a range
A release forecast asks either how many Sprints a chosen scope needs or how much work might fit before a date. Both questions use the current backlog and recent delivery, with the conditions for the forecast stated clearly.
Fixed scope: how many Sprints?
Divide remaining points by velocity and round up to a whole Sprint. With 196 points remaining and recent delivery from 24 to 31 points per Sprint:
| Scenario | Calculation | Sprints spanned |
|---|---|---|
| High velocity, 31 | 196 ÷ 31 ≈ 6.3 | 7 |
| Average velocity, 28 | 196 ÷ 28 = 7 | 7 |
| Low velocity, 24 | 196 ÷ 24 ≈ 8.2 | 9 |
The forecast spans 7 to 9 Sprints. With two-week Sprints, that is 14 to 18 weeks. Rounding up matters: after eight Sprints at 24 points, 192 points are complete and 4 remain. The release work extends into a ninth Sprint.
Done work can be released during a Sprint. Reporting that the scope spans nine Sprints does not require holding an Increment until the ninth Sprint ends.
Fixed date: how much scope?
Multiply the number of Sprints left by the velocity range. With 6 Sprints left, 24 to 31 points per Sprint gives about 144 to 186 points. Walk down the ordered backlog and add complete item sizes.
Items within the first 144 points fit the low-delivery scenario. Those from 144 to 186 points need higher delivery. Work beyond 186 fits neither scenario. When a boundary cuts through an item, that whole item needs more room or a useful split. The scenarios do not award partial completion.
Make the release choices visible
MoSCoW can connect these numbers with release scope. Must Haves should fit comfortably within the low scenario. Shoulds and Coulds provide options if more can be done. If Musts already exceed the low end, raise that risk early and discuss reducing or splitting scope, moving the date or accepting greater uncertainty.
Say “7 to 9 Sprints if scope stays at 196 points and the team stays the same.” A range based on observed low and high velocities gives scenarios, not statistical confidence limits. Future delivery can fall outside it.
Refresh the inputs
Include all remaining release work, giving rough sizes to items still unclear. Unsized work does not disappear just because it is missing from the arithmetic. Add new scope and adjust remaining work as the team learns. Reforecast every Sprint from the current figures, or explicitly account for observed scope growth.
Check for known changes in capacity, membership or the Definition of Done before carrying old velocity forward. Assuming overtime will close a gap hides a choice stakeholders need to make about scope or time. A forecast is useful when its inputs, uncertainty and next update are visible.
Key Takeaways
- Fixed scope: divide remaining points by velocity and round Sprint counts up.
- Fixed date: multiply velocity by remaining Sprints and check whole items in order.
- Use low and high delivery scenarios with explicit scope and team assumptions.
- Keep Must Have scope comfortably within the low scenario.
- Include unsized work and scope growth; update the forecast every Sprint.
6.3 See progress and scope on release charts
Release charts show how completed work and changing scope affect a forecast. Put Sprints on the horizontal axis and points on the vertical axis. Update the chart each Sprint using done items only.
Read a burn-down
A release burn-down shows remaining work. Its line falls when items become done, rises when scope is added and can fall when scope is removed. A trend extended toward zero can suggest a finish under the conditions used.
A flat line has more than one possible cause. If the team finishes 30 points and adds 30 points, remaining work stays the same. The team made progress, but growth canceled it in that single measure. A flat burn-down therefore calls for a scope check before drawing conclusions about delivery.
Read a burn-up
A release burn-up separates total scope from completed work. The gap between the two lines is the work remaining. Added scope moves the scope line up while completed work still records delivery.
| Chart | Lines | What scope growth looks like |
|---|---|---|
| Burn-down | Remaining work | Growth can hide completion in a flat or rising line. |
| Burn-up | Total scope and completed work | The scope line rises independently of the completed-work line. |
Neither chart requires a straight actual-progress line. An ideal straight line is a planning reference; plot the observations even when they look uneven.
Update and reforecast
The grocery release starts with 196 points. The team completes 27, 31 and 24 points over three Sprints, for 82 done. Meanwhile, the Product Owner adds 20 points. On a burn-up, total scope is now 216 and completed work is 82. The gap is 134 points.
At 31 points per Sprint, 134 divided by 31 is about 4.3, so the remaining work spans 5 more Sprints. At 24 points per Sprint, it is about 5.6, or 6 more Sprints. Starting again from 196 would omit the added scope and overstate progress toward completion.
To visualize the range, extend the completed-work line at the low and high velocities. Where each meets the scope line gives a finish scenario. If scope is expected to keep growing, extend that trend too. When scope grows as fast as delivery, the gap does not close; the Product Owner needs a scope or ordering decision to make a release achievable at that rate.
Keep the chart tied to its purpose
A Sprint burn-down tracks work inside one Sprint, often tasks or hours, to help Developers follow their plan toward the Sprint Goal. A release chart tracks work across Sprints for a broader forecast. Scrum names forecasting charts as useful practices but requires none of these formats.
Share updated release observations with stakeholders, for example at the Sprint Review. Count completed work consistently, show scope changes honestly and update projections when the actual lines change.
Key Takeaways
- A release burn-down shows remaining work; a burn-up separates total scope and completed work.
- The burn-up gap equals total scope minus completed work.
- A flat burn-down can result from completion matched by scope growth.
- Project low and high delivery scenarios against the current scope.
- A release chart spans Sprints; a Sprint burn-down follows work within one Sprint.
- Plot actual done work and scope changes, not an ideal line presented as actual progress.
Product Backlog and User Stories examples
1Make the next backlog items understandable
10 steps
- 1IntroductionStart with competing needs
The grocery team wants card payments, a coupon fix and a payment-library upgrade. A driver also asks whether a phone camera can scan barcodes. All four requests compete for the same team’s attention.
Build one visible sequence, the ordered Product Backlog, then add enough detail to the next items through refinement so Developers can judge what they can complete in a Sprint.
- 2ExplanationGive all product work one place
The Product Backlog is the changing, ordered source of work to improve the product. Features, fixes, technical work and research belong there together. Its commitment is the Product Goal.
Developers keep the detailed plan for selected Sprint work in the Sprint Backlog. Putting product work in one list does not require putting every implementation task there.
- 3ExampleMake the trade-off visible
The Product Owner places card payments first, the coupon fix second, the library upgrade third and barcode research fourth. Each now has a visible position.
“High priority” on the first three would leave the next choice unresolved. The order can change when the team learns more, including when the approaching library-support deadline raises its urgency.
- 4ChallengeWho decides the size?
The Product Owner asks Developers to write the upgrade item, then tells them it must be 2 points to fit a plan. Who should size it, and who remains accountable for backlog management?
---reveal---
Developers doing the work size it. The Product Owner can explain trade-offs but cannot set that estimate. Delegating the writing does not transfer the Product Owner’s backlog-management accountability.
- 5ExplanationRefine with the people who know
Refinement breaks items down and adds description, order and size as needed. The Product Owner explains the need, Developers question the work and experts help resolve unfamiliar rules.
The activity continues throughout the Sprint. A scheduled conversation can help, but Scrum specifies neither a separate refinement event nor a fixed percentage in the 2020 Guide.
- 6ExampleOpen the payment request
The team discusses “Pay by credit card.” Developers ask what happens when payment is declined, when the request times out and when the order is canceled.
These questions expose different behaviors and different amounts of work. They need answers before a useful estimate can describe the intended scope. The Product Owner brings the business rules into that conversation.
- 7ExampleTurn questions into items
The group separates approved card payment, a clear declined-payment message and a refund to the original card. It drafts criteria and Developers size the items at 5, 2 and 5 points.
The Product Owner places refunds lower because cancellations are expected to be rare initially. Refinement has improved understanding and changed the order without detailing every distant idea.
- 8TipGive detail a useful timing
Near-term items need enough clarity for selection; distant ideas can remain broad. A team might keep one or two Sprints of ready items and use a light Definition of Ready to find missing information.
A checklist should lead to the needed conversation. Turning it into a rigid approval handoff can leave people waiting even when they could resolve the question together.
- 9ChallengeConnect readiness and order
A refund item now has clear behavior and fits a Sprint, but the Product Owner still places it below payments. Must it be selected next because it is ready?
---reveal---
No. Ready means Developers believe it can be finished within one Sprint. It does not give the item first place or guarantee selection. The Product Owner’s order and the team’s Sprint Goal still guide the choice.
- 10RecapA useful list can keep changing
Keep competing product work visible in one ordered backlog. Let the Product Owner account for its management and Developers account for sizing.
Refine near-term work together until it is understandable and fits a Sprint. Add detail as items approach selection, and remove or reorder work when learning changes what matters.
2Rewrite and split a user need
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionBegin with the reason
- 2ExampleRewrite the export request
- 3ConnectionKeep the three Cs connected
- 4ChallengeFind the missing purpose
- 5ExplanationCheck the six INVEST qualities
- 6ExampleRepair a vague payment story
- 7ChallengeChoose the right remedy
- 8ExplanationMake the first slice usable
- 9ExampleGive scheduling a first version
- 10TipUse SPIDR to find another cut
- 11ChallengeSpot a split that delays value
- 12ChallengeBalance Small and Independent
- 13RecapKeep purpose and working value
3Turn a story into clear completion checks
10 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionAgree what people will observe
- 2ExampleList the address rules
- 3ExplanationBuild a Given-When-Then scenario
- 4ExampleTest an exception
- 5ChallengeReplace a vague criterion
- 6ExplanationSeparate behavior and quality
- 7ChallengeSort an entry check
- 8Key InsightUnfinished quality is unfinished work
- 9ChallengeCheck both before reporting done
- 10RecapKeep three questions clear
4Reach a shared estimate
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionEstimate by comparison
- 2ExplanationGive points a clear meaning
- 3ExampleChoose a reference, then compare
- 4TipHandle many items with affinity sizing
- 5ChallengeCan points become fixed hours?
- 6ExplanationChoose privately, reveal together
- 7ExampleListen to the high and low votes
- 8ExampleClarify before voting again
- 9ChallengeRespond to an information gap
- 10ChallengeUse refinement before sizing
- 11RecapRecord understanding with the size
5Choose a release scope and an order
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake the reasons for order visible
- 2ExampleCompare value with size
- 3ConnectionGive risk and learning a place
- 4ExplanationMeasure the cost of waiting
- 5ChallengeCheck the sequence cost
- 6ExplanationName the release before MoSCoW
- 7ExampleCheck effort, not item counts
- 8ChallengeRespond when capacity tightens
- 9ExplanationBuild the WSJF numerator
- 10ExampleCalculate two complete scores
- 11ExampleFinish the four-item ranking
- 12Key InsightA low score can suggest a split
- 13ChallengeUse the score that matches the decision
- 14ChallengeConnect scope and sequencing
- 15RecapUse each comparison for its job
6Build and update a release forecast
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionBegin with evidence of completion
- 2ExampleCount only done items
- 3ExampleDescribe recent variation
- 4ChallengeAdjust for less available time
- 5ExplanationChoose the forecast question
- 6ExampleForecast a fixed scope
- 7ChallengeForecast a fixed date
- 8TipState what must stay comparable
- 9ExplanationChoose what each chart reveals
- 10ExampleUpdate scope before subtracting
- 11ExampleReforecast from the new gap
- 12ChallengeExplain a gap that will not close
- 13Key InsightKeep velocity useful for planning
- 14ChallengeCheck a forecast before sharing it
- 15RecapUpdate the evidence each Sprint
Product Backlog and User Stories practice questions
Set 1: Estimate work and choose a useful sequence10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: From a request to work the team understands10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Read delivery data and forecast a release10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Make connected backlog and release decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Acceptance criteria
Affinity estimation
Anchoring
API
B
Backlog refinement
Behavior-driven development
C
Capacity
CD3
Consensus estimate
Cost of delay
Could Have
CSV file
D
DEEP
Definition of Done
Definition of Ready
Dependency
E
Edge case
Epic
Estimable
F
Fixed-date forecast
Fixed-scope forecast
Forecast scenario
G
Given-When-Then
H
Happy path
Horizontal split
I
Increment
Independent
INVEST
J
Job size
M
Modified Fibonacci scale
MoSCoW
Must Have
N
Negotiable
P
Persona
Planning Poker
Product Backlog
Product Backlog item
Product Goal
Product Owner
R
Ready for selection
Reference story
Regression test
Relative estimation
Release burn-down
Release burn-up
Release forecast
Remaining work
Risk reduction and opportunity enablement
Role-goal-benefit template
S
Should Have
Simultaneous reveal
Small
SPIDR
Spike
Sprint Backlog
Sprint burn-down
Story point
T
T-shirt sizing
Testable
Theme
Three Cs
Throughput
Time criticality
Triangulation
U
User story
V
Valuable
Value
Velocity
Vertical slice
W
Weighted Shortest Job First
Won’t Have this time
Y
Yesterday’s weather
- 1Agile Values and Principles
- 2Scrum Framework
- 3Product Backlog and User Stories
- 4Running Sprints in Practice
- 5Kanban and Flow
- 6Scaling Agile
About this lesson
Make your own Study Materials
Turn your notes, slides and documents into Study Guides, Practice Questions, Flashcards and 6 more tools.