Project Scheduling

Learn how a project plan becomes a schedule people can follow. Break work packages into activities and milestones, link them with dependencies, and draw a network diagram that shows every path through the project. Estimate durations with analogous, parametric, bottom-up and three-point techniques, then use the critical path method to find early and late dates, float and the critical path. Present the result as a Gantt chart with milestones, track progress against the baseline, and check that people are not overbooked using resource leveling and smoothing. One office-move example runs through the whole material, from activity list to finished schedule.

BeginnerLesson 5 of 9 in Project Management Foundations Course

What you will learn

  1. Explain what a project schedule does and how it is built, then turn the work packages of the scope into a clear list of activities and milestones that can be sequenced and estimated.
    • Explain what a project schedule is and how it is built
      Describe the purpose of a schedule, the steps that produce it, the difference between the schedule model, its views and the baseline, and how much detail to plan at each moment.
    • Break work packages into activities
      Decompose each work package into activities that can be estimated, assigned and checked, and record them with their attributes in an activity list.
    • Set milestones that mark key points in the schedule
      Define milestones as zero-duration markers of significant events, choose useful ones, name them clearly and use a milestone list or chart to communicate progress.
  2. Identify how activities depend on each other, choose the right relationship type with any lead or lag, and draw an activity-on-node network that shows every path through the project.
    • Identify dependencies and relationship types
      Distinguish mandatory, discretionary, external and internal dependencies, and use finish-to-start, start-to-start, finish-to-finish and start-to-finish relationships with leads and lags.
    • Draw and read an activity-on-node network diagram
      Turn a dependency table into an activity-on-node network, check it for logic errors, and list every path from start to finish with its length.
  3. Turn work into realistic durations by separating effort from time, choosing a suitable estimating technique and recording each estimate with its assumptions.
    • Separate effort, duration and calendar time
      Distinguish work effort from duration and elapsed time, convert between them using people, availability and calendars, and record estimates with their basis and assumptions.
    • Apply duration estimating techniques
      Use expert judgment, analogous, parametric, bottom-up and three-point estimating, and choose between them by the information available and the accuracy needed.
  4. Use the critical path method to calculate early and late dates, total and free float and the critical path, and use them to judge how delays and deadlines affect the finish date.
    • Calculate early and late dates with forward and backward passes
      Run a forward pass to find early start and early finish times and the project duration, then a backward pass to find late start and late finish times.
    • Determine float and the critical path
      Calculate total float and free float for each activity, identify the critical path and near-critical paths, and explain what float means when managing the work.
    • Use float to judge delays and deadlines
      Predict how a delay affects successors and the finish date from an activity's float, handle imposed dates and negative float, and recalculate when the schedule changes.
  5. Turn the critical path results into a Gantt chart with calendar dates and milestones, and read it to communicate the plan and track progress against the baseline.
    • Build a Gantt chart from the network
      Convert early start and finish times into calendar dates on a working calendar and draw activities, milestones, summary rows and float on a time scale.
    • Read and use a Gantt chart to communicate and track
      Read timing, overlap, float and progress from a Gantt chart, compare the current schedule with the baseline, and choose the right schedule view for each audience.
  6. Check whether the people and equipment a schedule needs are available when it needs them, and resolve overloads with resource smoothing and resource leveling.
    • Load resources and find overallocation
      Assign resources to activities, build a resource histogram from the schedule, and find the periods where demand exceeds availability.
    • Resolve overallocation with resource leveling and smoothing
      Apply resource smoothing within float and resource leveling that may move the finish date, and explain how each changes float and the critical path.

Project Scheduling study guide

6 chapters

1

Plan the schedule and define its activities and milestones

An agreed scope tells you what the project must produce. A schedule turns that scope into work people can arrange and track. Begin with the rules for managing time, then identify the activities and the milestones that show meaningful progress. The office move starts here: before assigning dates, the team needs a clear account of what must happen and how it will recognize completion.

1.1 Explain what a project schedule is and how it is built

A project schedule sets out the activities, their order and durations, their start and finish dates, and the milestones to reach. It connects the agreed scope with the people and equipment needed to deliver it. A useful schedule helps answer both “When can we finish?” and “When do you need me?”

Build the schedule from scope

The work breakdown structure (WBS) divides deliverables into work packages. Scheduling takes the next step: identify the activities needed to complete every work package. Check in both directions. A work package with no activity may be missing from the timeline. An activity with no work package may reveal missing scope or unnecessary work.

A predictive, or plan-based, schedule develops through these steps:

  1. Decide how to create and manage the schedule.
  2. Define the activities.
  3. Sequence them using dependencies.
  4. Estimate durations.
  5. Calculate dates, critical path and float, and check resources.
  6. Approve the schedule baseline, then monitor and control the work.

These steps inform one another. A resource check may change a duration estimate, which changes the calculated dates. Repeat the relevant steps when better information becomes available.

Agree how time will be managed

The schedule management approach records the method and software, time units, working calendar, rounding rules, update frequency and reporting thresholds. For an office move, the team might use working days, a Monday-to-Friday calendar and weekly updates. A “two-day delay” is hard to interpret until everyone knows which calendar and activity it refers to.

Estimates rely on assumptions. Record them alongside the plan so the team can see what a date depends on. A schedule built around a supplier's promised delivery is affected when that promise changes.

Separate the model, views and baseline
ItemWhat it does
Schedule modelHolds activities, durations, relationships, calendars and resource data.
Schedule viewPresents that data for a purpose: network logic, Gantt timing or milestone dates.
Schedule baselinePreserves the approved start and finish dates for comparison with progress.

The current schedule changes as work happens. The baseline changes only through formal change control. Overwriting approved dates with the latest forecast removes the reference needed to explain a delay. Different views should come from the same current model, so a changed dependency appears consistently wherever it affects timing.

Add detail when it becomes useful

Rolling wave planning gives near-term work detailed activities and leaves later work at a higher level. In a 12-month sales-system rollout, the first three months can be planned in detail while months 4–12 remain at work-package level until the pilot results are available. The team still plans the whole scope; it adds detail as knowledge improves.

Many adaptive approaches use timeboxes, such as two-week iterations. Their end dates stay fixed; less scope is delivered when time runs short. Other adaptive approaches manage continuous flow and pull work when capacity is free. A project can combine these approaches, using a predictive fit-out schedule and timeboxed software work.

Key Takeaways

  • Trace every scheduled activity to a work package.
  • Build dates from activities, dependencies, durations, calendars and resources.
  • Keep the approved baseline available when the current schedule changes.
  • Use rolling wave planning to add detail as later work becomes clearer.
  • A timebox fixes the period; scope can change to fit it.

1.2 Break work packages into activities

An activity is a distinct piece of scheduled work with a start, finish and duration. It usually needs people or equipment. A work package describes a deliverable or part of one; activities describe the steps that produce it.

Turn a deliverable into actions

Take the work package “New office network.” Ask the people doing the work which steps will complete it. The activity list might contain:

  • “Survey the new office.”
  • “Order cables and switches.”
  • “Install network cabling.”
  • “Install and configure switches.”
  • “Test network connections.”

This process is decomposition. Each activity name uses a verb and an object. “Network cabling” names a thing; “Install network cabling” tells the team what must happen. Keep the work package as the place to group those actions in the WBS.

Choose useful detail

An activity needs an owner, an estimate and a clear completion criterion. For “Test network connections,” completion could mean that every installed outlet has passed the agreed test and the results are recorded. That lets the owner report a finish based on evidence.

Most activities should be short enough for progress to be visible between reports. One or two reporting periods is a useful rule of thumb. An activity lasting several months may remain “in progress” for so long that a problem becomes visible late. Break it into meaningful parts that can be checked.

Detail also has a maintenance cost. Hundreds of one-hour tasks are unlikely to help control a small six-week move. Choose detail that matches the project's size, risk and reporting needs. A risky test may deserve separate preparation, execution and review activities; an ordinary short task may need only one row.

Record the activity and its attributes

The activity list contains a unique identifier and a name for every scheduled activity. Codes can extend the WBS: work package 1.3 might contain activities 1.3.1 and 1.3.2. The identifier keeps links clear when names change.

Activity attributes develop as planning continues. They include the description and completion criterion, owner and resources, location, duration, predecessors and successors, relationship types, leads or lags, imposed dates and assumptions. The first draft need not contain estimates that have not yet been developed. Add them through sequencing and estimating.

Include work that is easy to miss

Reviews, approvals, permits, ordering, training and testing take time even when they do not directly create the final physical product. Ask what must happen before each item can start and what must be checked before it can finish. An installation estimate alone misses the approval and procurement work that makes installation possible.

Waiting also occupies the timeline. A supplier's five-week delivery can be a supplier activity or a lag after ordering. Record it once. If a wait requires active checking by a team member, showing that work as an activity makes its resource need visible. Milestones belong in the list too, with zero duration, to mark the events reached by these activities.

Key Takeaways

  • Name an activity with a verb and object.
  • Choose detail that supports estimating, ownership and progress checks.
  • Give every activity a unique identifier and clear completion criterion.
  • Include approvals, procurement, testing and waiting time.

1.3 Set milestones that mark key points in the schedule

A milestone marks a significant event or point in the project. It has zero duration and uses no resources. “Office ready for staff” marks the moment a useful state has been reached; the work needed to reach it belongs in activities.

Name a state people can verify

Use names such as “Lease signed,” “Design approved” or “Network tested.” Each describes an achieved result. “Approve design” describes work and belongs in the activity list with a duration. If testing takes five days, schedule “Test the system” for five days and place “System tested” at its finish.

A milestone and a deliverable describe different things. The network is a deliverable. “Network tested” is the event showing that it has reached the required state. A payment milestone may depend on acceptance of a deliverable, so hours spent alone do not establish that the milestone has been reached.

Choose meaningful checkpoints

Useful milestones include the project start and finish, phase endings, go/no-go decisions, major deliverable acceptance, approvals, external deliveries and fixed outside dates. Choose events that matter to the people reading the schedule. Too many markers make the important ones difficult to find; too few leave long stretches without a useful checkpoint.

For the office move, use “Move plan approved” after planning the layout, “Equipment moved” after moving the equipment and “Office ready for staff” at the project finish. Each marks the end of a group of work the sponsor can recognize. The activities leading to it supply its calculated date.

Distinguish calculated and imposed dates

A calculated milestone date follows from the schedule logic. If its preceding activities move, its forecast moves with them. An imposed date comes from outside that calculation, such as a contract requiring “Pilot site live” by June 30, 2027.

Keep both the required date and the calculated result visible. If the work finishes after the required date, the plan misses the requirement. Entering the preferred date on a diamond does not make the preceding work fit. Critical path calculations express the shortfall as negative float.

Keep a list and choose a view

A milestone list records each milestone's identifier, name, short description, planned date and whether it is mandatory or optional. Mandatory milestones are required by a contract, law or sponsor. Optional milestones are checkpoints chosen by the team. As the project proceeds, add actual dates.

A milestone chart shows just these events along a timeline, including planned, forecast or actual dates as needed. It gives sponsors and clients a short view of the project. In a network diagram, a milestone is a node with duration 0. In a Gantt chart, it appears as a diamond, ◆, at its date. Keep activities available in the detailed view so the team can see what must happen before each diamond can be reached.

Key Takeaways

  • A milestone marks an event with zero duration and no resource demand.
  • Name milestones as verifiable states that have been reached.
  • Separate a deliverable from the moment it is accepted.
  • Show an imposed date alongside the date calculated from the work.
  • Use milestone charts for readers who need the key dates.
2

Sequence activities and draw network diagrams

The order of work comes from relationships between activities. Some relationships are unavoidable; others reflect a team choice or an outside event. Recording these reasons helps you build a network that supports realistic dates. Follow the office move through its parallel branches, check the points where branches meet, and see why a drawing of the logic answers questions a simple task list cannot.

2.1 Identify dependencies and relationship types

A dependency records how one activity controls another's timing. The controlling activity is the predecessor; the activity that depends on it is the successor. In the office move, packing IT equipment must finish before the equipment can move.

Read the two ends of a relationship

The first word in a relationship names the predecessor's event. The second names the successor's event.

RelationshipTiming ruleExample
Finish-to-start (FS)The successor cannot start before the predecessor finishes.Install cabling before starting connection tests.
Start-to-start (SS)The successor cannot start before the predecessor starts.Begin carpet laying before starting furniture assembly in the first rooms.
Finish-to-finish (FF)The successor cannot finish before the predecessor finishes.Editing can overlap writing, but cannot finish before writing ends.
Start-to-finish (SF)The successor cannot finish before the predecessor starts.The old phone service continues until the new service starts.

FS is the most common type. SF is rare and easy to reverse: the new service is the predecessor because its start controls the old service's finish. These are timing limits; other links or resources may make the successor start or finish later.

Record why the link exists

A mandatory dependency, or hard logic, follows from the nature of the work or a contract. Installed cabling is needed before it can be tested. A discretionary dependency, or soft logic, reflects a team preference, such as painting before laying carpet. Record its reason so the team can reconsider it if needed.

A second classification asks who controls the activities. External dependencies involve events outside the project team's control, such as a landlord's handover. Internal dependencies link work the team controls. The classifications combine: a required city inspection is mandatory and external.

Add waiting or overlap explicitly

A lag adds a delay to a relationship. “Paint the walls” FS + 2 working days “Hang pictures” places hanging two working days after painting finishes. A lead permits overlap and is written as a negative lag. FS − 3 days allows the successor to start three days before its predecessor finishes.

A lag represents waiting without work. If someone must inspect or tend the work during the wait, a separate activity shows that resource demand. Keep risk reserve visible instead of hiding it inside an unexplained lag.

Sequence the office move

All links below are FS without lags. Durations are working days.

IDActivityDurationImmediate predecessors
APlan the move layout3None
BBook the movers2A
COrder and deliver new furniture7A
DPack IT equipment4B
EInstall network cabling3A
FMove equipment2D, E
GAssemble furniture2C
HSet up and test workstations3F, G

Record immediate predecessors. F needs D and E; a direct A-to-F link adds clutter because A already precedes both branches. Missing real links permits impossible overlaps. Adding a link merely because one person is double-booked confuses work logic with resource availability; record and resolve the resource constraint separately.

Key Takeaways

  • Read each relationship from the predecessor event to the successor event.
  • FS, SS, FF and SF constrain different ends of activities.
  • Classify the reason for a dependency and who controls it.
  • A positive lag adds waiting; a lead is a negative lag.
  • Record immediate predecessors, including every branch needed at a merge.
  • Treat shared-resource clashes separately from work logic.

2.2 Draw and read an activity-on-node network diagram

A network diagram shows the logical relationships between activities. In activity-on-node (AON) diagrams, each box is an activity and each arrow points from predecessor to successor. This is also called the precedence diagramming method (PDM). It can show all four relationship types, leads and lags.

Build from the dependency table

Begin with a zero-duration Start milestone. Place activities with no predecessors after it. Add each remaining activity when all its predecessors have been placed, drawing one incoming arrow from each. Connect activities with no successors to a Finish milestone. Arrange the boxes roughly left to right and label links that differ from plain FS, such as “SS + 2.”

For the office move, the complete link list is:

  • Start → A.
  • A → B, A → C and A → E.
  • B → D.
  • D → F and E → F.
  • C → G.
  • F → H and G → H.
  • H → Finish.

A is a burst point because several branches leave it. F and H are merge points because several branches enter them. At F, both packing and cabling must be complete. At H, equipment movement and furniture assembly must both be complete. A merge waits for the last required branch, which makes incoming delays important.

Trace every route

A path follows arrows continuously from Start to Finish. With FS links and no lags, add the activity durations along each path:

PathCalculationLength
A–B–D–F–H3 + 2 + 4 + 2 + 314 days
A–C–G–H3 + 7 + 2 + 315 days
A–E–F–H3 + 3 + 2 + 311 days

The longest path sets the shortest possible project duration: 15 working days before checking resource limits. Adding the durations of every activity would count parallel work as though it all happened in sequence.

Check the drawing before calculating

A loop such as A → B → C → A is a logic error: each activity waits for another in the loop. A dangling activity has an unconnected end, so a change to it may fail to affect the finish calculation. Connect all open starts and ends to the Start and Finish milestones. Check that every arrow points forward through the work's logic.

AON position and box size do not measure time. A seven-day activity may be drawn beside a two-day activity in equal-sized boxes. Read the durations and links; use a Gantt chart for calendar timing. Node layouts also vary. A common layout places ES, duration and EF above the activity name, and LS, total float and LF below it; read the legend first.

Recognize the older arrow form

In activity-on-arrow (AOA) diagrams, arrows represent activities and circles represent events. This form shows FS logic. It sometimes needs dashed, zero-duration dummy activities to express a dependency without adding real work. If C requires A and B while D requires only A, a dummy can carry A's completion into C's start event without making D depend on B. The dummy represents logic, so it consumes no time or resources.

Key Takeaways

  • AON boxes represent activities; arrows represent dependencies.
  • A merge waits for all incoming predecessors.
  • Sum durations along each complete FS path when there are no lags.
  • Remove loops and connect open ends to Start and Finish.
  • Read the legend; box position alone does not show dates.
  • In AOA, a dummy activity carries logic with zero duration.
3

Estimate activity durations

A duration estimate must describe how the work will actually be done. Separate the labor required from the time available, account for working calendars, and choose a technique that fits the information you have. A clinic network installation provides examples of effort, production rates and uncertain work. Keeping the basis of each estimate visible makes later revisions easier to explain.

3.1 Separate effort, duration and calendar time

An estimate connects the amount of work with the capacity available to do it. Three quantities must stay separate: effort is labor, duration is working time from start to finish, and elapsed time counts all calendar time, including weekends and holidays.

Convert effort into duration

Effort is measured in person-hours or person-days. For work that can be divided among people, calculate duration by dividing effort by the team's daily productive capacity.

The clinic network needs 72 person-hours. Two technicians each supply 6 productive hours per day. Together they supply 12 person-hours daily, so the work takes 6 working days. With three technicians supplying the same daily hours, capacity becomes 18 person-hours daily and duration becomes 4 working days.

A half-time assignment changes capacity. A person who could provide 6 productive hours daily but is assigned half-time supplies only 3 hours to the project. A 24-person-hour task then needs 8 working days. Use the hours available for this work, after allowing for meetings, other assignments and routine demands.

Check whether work can be divided

The effort calculation fits divisible work at the stated productivity. More people also need coordination and space, and some work has a fixed duration. Adding installers cannot shorten a supplier's five-week delivery or a 24-hour drying period. Check the work before assuming twice as many people means half as many days.

QuantityWhat it measuresExample
EffortTotal labor needed72 person-hours
DurationWorking periods occupied6 working days
Elapsed timeAll calendar time between datesWorking days plus intervening weekends
Apply the right calendar

On a Monday-to-Friday calendar with no holidays, 15 working days starting Monday, March 1, 2027 finish Friday, March 19. That spans 19 calendar days counting both ends. A contractor may work Saturdays while another person is unavailable on vacation, so resource calendars can differ from the project calendar.

Waiting can use a different clock too. If paint finishes Friday evening, a lag of two working days occupies Monday and Tuesday and allows hanging pictures Wednesday morning. Two elapsed days occupy Saturday and Sunday and allow a Monday start. Record which type of day the estimate uses.

Keep the basis visible

Write an estimate with its assumptions: “6 working days, based on 72 person-hours with two technicians, assuming the building is empty; range 5–8 days.” Ask the people doing the work or relevant experts to help estimate it. Early estimates usually have wider ranges; the range narrows as the work becomes clearer, often shown as an estimating funnel.

A target date expresses what someone wants. It does not replace an estimate of the work. If the estimate misses the target, show the gap so a decision can be made. Hidden padding makes each estimate's basis harder to judge and can get used up. Use realistic activity estimates and visible schedule reserve where identified risks justify it, such as three working days before the finish milestone managed by the project manager.

Key Takeaways

  • Effort measures labor; duration measures working time; elapsed time includes nonworking days.
  • Calculate capacity from productive hours and actual assignment levels.
  • Check whether adding people can shorten this work.
  • State the calendar and assumptions behind every duration.
  • Keep justified schedule reserve visible instead of padding estimates.

3.2 Apply duration estimating techniques

Choose an estimating technique from the information available. A quick estimate from a comparable project can help early planning. Detailed activity data supports a more careful estimate later. Expert knowledge helps judge both the inputs and whether the result makes sense.

Compare the techniques
TechniqueBasisUseful when
Expert judgmentRelevant experiencePeople understand the work and its conditions.
AnalogousActual duration of similar past workDetail is limited and a quick estimate is needed.
ParametricQuantity divided by a reliable production rateWork repeats at a measured rate.
Bottom-upEstimates of smaller parts combined through their sequenceActivities are defined in enough detail.
Three-pointOptimistic, most likely and pessimistic durationsUncertainty needs to be visible.

Experts can estimate together or use the Delphi technique: anonymous answers, a shared summary and several rounds of revision. This reduces the influence of a single strong voice.

An analogous estimate might use last year's three-week move of a 30-person team as the basis for a similar move. Check what makes the comparison relevant. A different building or procurement route may weaken it.

Calculate a rate-based estimate

A crew installs 8 network outlets per day. For 120 outlets with two crews, combined output is 16 outlets per day. Dividing 120 by 16 gives 7.5 days. Enter 8 working days if the schedule uses whole days. The rate must fit the building and the work: a rate measured in easy-to-drill walls may be too optimistic for a harder surface.

Combine bottom-up estimates through the logic

For a clinic network, “Survey the site” takes 1 day. Cabling takes 6 days and switch configuration takes 2 days, both after the survey and in parallel. Testing takes 1 day after both finish. The package takes 1 + 6 + 1 = 8 days. The shorter parallel activity fits inside the six-day branch. Adding all durations gives 10 days and wrongly turns the parallel work into a sequence. Effort adds across the parts; duration follows their dependencies.

Use three estimates for uncertain work

Let O be optimistic, M most likely and P pessimistic. The triangular average gives all three equal weight: (O + M + P) ÷ 3. The beta, or PERT, average weights M four times: (O + 4M + P) ÷ 6. The denominator 6 matches the total weight of 1 + 4 + 1.

For cabling with O = 4, M = 6 and P = 14 days, the triangular result is 24 ÷ 3 = 8 days. The beta result is 42 ÷ 6 = 7 days. Both exceed M because the long pessimistic duration pulls the average upward. Enter the chosen calculated estimate, not M by habit.

The spread (P − O) ÷ 6 is commonly used as the beta estimate's standard deviation. Here it is 10 ÷ 6, about 1.67 days. A wider range means more uncertainty even when two activities have the same average. Useful three-point estimates still depend on knowledgeable people supplying credible O, M and P values.

Key Takeaways

  • Use analogous estimates for quick comparisons and parametric estimates for reliable rates.
  • Combine bottom-up durations through the sequence, allowing parallel work to overlap.
  • Triangular gives equal weight to O, M and P.
  • Beta uses (O + 4M + P) ÷ 6.
  • A wider optimistic-to-pessimistic range signals greater uncertainty.
  • Choose the technique for the available evidence and detail.
4

Find the critical path and float

Parallel work makes a project shorter than the sum of all its activities, but some chains still control the finish. Calculate the earliest and latest times for the office move, then use their differences to find float. These results let you judge a late activity by its effect on the whole project. They also show when an imposed deadline conflicts with the plan and when a different path becomes critical.

4.1 Calculate early and late dates with forward and backward passes

The critical path method (CPM) calculates early and late times from activity durations and dependencies. It first treats the required resources as available. Resource limits are checked after the logic-based dates are known.

Keep one counting convention

Time starts at 0. An early finish of 3 means the end of working day 3. An activity starting at time 3 begins at the start of working day 4. Calculate early finish (EF) by adding duration to early start (ES). Calculate late start (LS) by subtracting duration from late finish (LF).

Some schedules count from day 1 and use EF = ES + duration − 1, with the next FS activity starting at EF + 1. Both systems give the same dates when applied consistently. All calculations below use time 0.

Move forward through every predecessor

Start activities have ES 0. For an FS activity without lag, take the largest predecessor EF as its ES, then add its duration. A successor waits for every required input, so the latest incoming finish controls a merge.

In the office move, A takes 3 days, giving ES 0 and EF 3. B, C and E all follow A: their early finishes are 5, 10 and 6. D follows B and takes 4 days, so it runs from 5 to 9. F needs D and E: compare 9 and 6, choose 9, and add F's 2 days to reach 11. G follows C and ends at 12. H waits for F and G, starts at 12 and ends at 15.

Work backward from the finish

Set the last activity's LF to the calculated project finish, 15. Subtract its duration to find LS. Moving right to left, set each earlier LF to the smallest LS of its successors. It must finish in time for every successor.

H has LF 15 and LS 12. F and G must finish by 12, so both have LS 10. C must finish by G's LS 10 and therefore starts no later than 3. D and E must finish by F's LS 10, giving LS 6 and 7. B must finish by D's LS 6, so its LS is 4. A must finish by the earliest of B's 4, C's 3 and E's 7: its LF is 3 and LS is 0.

ActivityDurationESEFLSLF
A30303
B23546
C7310310
D459610
E336710
F29111012
G210121012
H312151215
Include lags and check the results

For FS links with lags, compare predecessor EF + lag on the forward pass. On the backward pass compare successor LS − lag. If painting ends at 8 and hanging has FS + 2, hanging cannot start before 10. With FS − 2, it can start at 6.

Choosing the smallest predecessor EF would let F begin before packing finishes. Choosing the largest successor LS would let A finish too late for furniture delivery. Without imposed dates, the backward pass from the calculated finish gives LS at least as large as ES for every activity. At least one complete path has equal early and late times throughout.

Key Takeaways

  • Use time 0 consistently: EF = ES + duration and LS = LF − duration.
  • Forward pass: choose the largest predecessor finish, including lag.
  • Backward pass: choose the smallest successor start, subtracting lag.
  • The calculated office-move finish is time 15.
  • Check all branches at merges and bursts before accepting dates.

4.2 Determine float and the critical path

Float describes timing flexibility. It helps you see which activities can move and which paths require close attention. Two measures answer different questions: can this activity move without affecting the project finish, and can it move without affecting its next activities?

Calculate total and free float

Total float, also called total slack, is LS − ES, or equivalently LF − EF. It is the delay available from the early dates without delaying the finish or breaking a schedule constraint.

Free float, or free slack, is the delay available without moving any immediate successor's early start. For FS links without lags, subtract the activity's EF from the smallest successor ES. An activity ending the project uses the project finish in place of a successor ES.

ActivityTotal floatFree float
A00
B10
C00
D10
E43
F11
G00
H00

For E, total float is 7 − 3 = 4 days. F starts at 9 and E finishes at 6, so free float is 9 − 6 = 3 days. E can use three days without moving F; the fourth day moves F but still fits before H.

In a network without imposed dates, free float cannot exceed total float. An imposed deadline can make total float negative even while free float remains zero or positive, because the project requirement and the next activity's timing are different tests.

Find the path controlling the finish

The critical path is the longest path through the network and determines the shortest possible project duration. With the backward pass anchored to the calculated finish, its activities have zero total float. The office move's A–C–G–H path takes 15 days; its early and late times match throughout.

The 14-day A–B–D–F–H path has only one day of flexibility. It is near-critical: a small delay can make it the longest path. The 11-day A–E–F–H path is shorter, but F also lies on the 14-day path. F therefore has only one day of total float, not four.

“Critical” describes timing. Cabling is essential even though E has float. A project can also have more than one critical path. Every such path needs attention because a delay on any one can move the finish.

Treat float as shared time

B, D and F each show one day of total float. Those values describe the same one-day gap on their chain. If B starts one day late, it pushes D and F one day later and uses the gap. Giving each activity its own day would delay the finish by two days.

Float can help absorb delays or spread demand for people and equipment. Each use leaves less room for later changes, so record the movement and recalculate. Shortening a non-critical activity alone does not shorten the project: reducing E from three days to one leaves A–C–G–H at 15 days. The finish moves earlier only when the controlling path becomes shorter, and then only until another path controls it.

Key Takeaways

  • Total float protects the project finish; free float protects immediate successors’ early starts.
  • For plain FS links, free float is the smallest successor ES minus the activity EF.
  • The office-move critical path is A–C–G–H, 15 days.
  • Float is shared along a chain, not available separately to every activity.
  • Near-critical paths can become critical after a small delay.
  • Shortening work with float alone leaves the controlling path unchanged.

4.3 Use float to judge delays and deadlines

A late activity does not always mean a late project. Compare the delay with free float and total float, then trace its effect through the network. This comparison applies to one delayed activity with FS logic and nothing else changing.

Test a delay against both limits
Delay from early timingEffect
No greater than free floatImmediate successors keep their early starts.
Greater than free float, but no greater than total floatSome successors move; the project finish holds.
Greater than total floatThe finish moves by the excess over total float.

E, “Install network cabling,” has 3 days of free float and 4 days of total float. A two-day delay fits inside free float and moves no other activity. A four-day delay moves E's finish from 6 to 10 and F's start from 9 to 10; H still starts at 12 and finishes at 15. A six-day delay makes E finish at 12, F run from 12 to 14, and H run from 14 to 17. The project is two days late because the delay exceeds total float by two days.

Recheck which path controls the project

D has only one day of total float. If packing takes three extra days, its path becomes 3 + 2 + 7 + 2 + 3 = 17 days. A–B–D–F–H now controls the finish. The previous critical path still takes 15 days, but its earlier finish cannot make up for unfinished packing on the other branch.

Handle imposed dates openly

An imposed date is a constraint entered from outside the network calculation. A “start no earlier than” requirement can delay work even when its predecessors are complete. If the landlord hands over the keys at time 5, E starts at 5 and finishes at 8. F still starts at 9, so the project finish holds.

A required finish earlier than the calculated finish has a different effect. Start the backward pass at that required finish. If the office must be ready at time 13, H has LF 13 and LS 10. Working backward gives total float −2 for A, C, G and H; −1 for B, D and F; and +2 for E.

Negative float measures the shortfall against the required date. The lowest-float path is still A–C–G–H, now with −2 days. The team must change the plan—scope, resources or the way work is done—or agree on a later date. A deadline entered into software does not reduce the work's duration.

Explain the effect when reporting

Report both the activity and the project consequence: “Cabling is two days late. The finish remains Friday, March 19, 2027, but cabling now has only two days of total float left.” This tells the sponsor what has changed and what flexibility remains.

Recalculate after actual starts and finishes, revised estimates, new activities or changed constraints. Shared float cannot be spent repeatedly by successive owners. Missing links can also create apparent flexibility that the real work does not have, so inspect the network when a result looks unexpectedly generous.

Key Takeaways

  • Compare a delay with free float and then total float.
  • For one isolated delay, finish slippage is the amount exceeding total float.
  • A near-critical path can replace the original critical path.
  • An imposed finish earlier than the calculated finish creates negative float.
  • Recalculate and report both finish-date effects and remaining flexibility.
5

Present the schedule in Gantt charts

People need calendar dates they can act on, as well as the logic behind them. Turn the office-move calculations into bars and milestone dates on a working calendar. Then compare actual progress and forecast dates with the approved plan. A detailed team chart, a summary chart and a milestone view each answer different questions while drawing on the same schedule model.

5.1 Build a Gantt chart from the network

A Gantt chart lists activities as rows against a horizontal time scale. Bars show the interval from each start date to its finish date. Milestone diamonds mark events. The chart translates network results into dates people can use to arrange their work.

Put the calculation onto a calendar

Choose a daily or weekly scale, group activities under suitable WBS rows, and use the working calendar to convert early times. With time counted from 0, ES s begins at the start of working day s + 1. EF f falls at the end of working day f.

The office move starts Monday, March 1, 2027. Its calendar is Monday through Friday, with no holidays in this example.

ActivityES–EFStart dateFinish date
A0–3Mon, March 1Wed, March 3
B3–5Thu, March 4Fri, March 5
C3–10Thu, March 4Fri, March 12
D5–9Mon, March 8Thu, March 11
E3–6Thu, March 4Mon, March 8
F9–11Fri, March 12Mon, March 15
G10–12Mon, March 15Tue, March 16
H12–15Wed, March 17Fri, March 19

For E, ES 3 means the fourth working day, Thursday, March 4. Its three working days are Thursday, Friday and Monday. A bar that crosses a weekend does not turn the weekend into working time. Shade nonworking days so the difference is visible. C spans nine calendar days but contains seven working days.

Add the marks that help the reader

Draw each bar between its dates, then add milestone diamonds. “Office ready for staff” sits at the end of Friday, March 19, the end of working day 15. Critical activities can use a distinct color, often red, with a legend so color has a clear meaning. Dependency arrows can show how bars connect.

A float line runs from an activity's early finish to its late finish. E finishes at time 6 but can finish as late as time 10, Friday, March 12. Its thin extension therefore shows four working days of total float. Critical activities in the unconstrained CPM result have no such extension.

Roll up groups without adding work

A summary row spans the earliest start to the latest finish among its child activities. It helps a manager read a WBS group as a whole. Do not estimate it as another activity or add its span to the children's durations. Its dates are calculated from the group below it.

Keep the bars linked to the model

A linked Gantt chart updates when its durations or dependencies change. If D slips one day, F shifts one day and uses its float; H and the finish remain on their original dates. A longer D delay pushes H too.

Entering every start as a fixed date prevents the work's logic from setting the timing. A hand-drawn bar can look tidy while violating a predecessor or resource limit. Keep the underlying dependencies, calendars and resources current, then use the chart to show their result.

Key Takeaways

  • Convert ES to working day ES + 1 and EF to the end of working day EF.
  • Use the project calendar; weekends can fall inside a bar without adding work.
  • Draw milestone diamonds and explain any color or line conventions.
  • A float line extends from early finish to late finish.
  • Summary rows roll up child dates; they do not add another activity.
  • Let a linked model calculate the bars’ dates.

5.2 Read and use a Gantt chart to communicate and track

A Gantt chart answers practical timing questions: what work overlaps, who needs to prepare for the next activity, and when the main events are forecast. It also provides a clear way to compare today's plan with the approved baseline.

Read across a period

For the office move, the week of March 8–12, 2027 includes C throughout the week, D from Monday through Thursday, E on Monday and F starting Friday. Follow the rows across those dates to see overlapping work. Overlap alone does not tell you whether the same person is needed for two activities; resource loading supplies that check.

Critical markings identify the bars controlling the calculated finish. A float line shows room for timing changes. In a large chart, follow the network diagram when you need to understand why a bar is critical: many crossing arrows can make the Gantt view difficult to read.

Compare progress at a status date

The status date, also called the data date, is the point through which progress has been recorded. It is often drawn as a vertical line. Completed bar shading or a percentage reports work done by that point; it should be based on evidence about the activity.

D is planned for March 8–11, four working days. If packing is planned at an even rate, the end of Wednesday, March 10 is the point when 75% should be complete. Suppose only 50% is done and the remaining half still takes two working days. The forecast finish becomes Friday, March 12, one working day late.

D's one day of total float absorbs the delay, so the project finish stays March 19. F moves and both D and F lose their remaining float. Three days passing does not establish that three quarters of the equipment is packed. Elapsed time and physical progress answer different questions.

Preserve the approved comparison

Many charts show a gray baseline bar under the current bar. A current finish farther right than its baseline finish shows a slip. Keep that original approved reference until a change is formally approved. Replacing it after every update conceals how far the work has moved from the agreement.

Long activities with vague completion criteria can be reported as “90% done” for weeks. Shorter, checkable activities support more reliable reporting. Ask what is finished and what remains, then estimate the remaining work.

Match the view to the reader
Reader's needUseful view
Check dependencies and pathsNetwork diagram
Coordinate detailed team workDetailed Gantt chart
Review WBS groupsSummary Gantt chart
Review key events and datesMilestone chart

All views come from one model. A date can move within available float when dependencies, calendars, resources and constraints still permit it. For example, F can move from ES 9 to ES 10 without moving H. Review those requirements before moving a bar; a visually convenient position may promise work the team cannot deliver.

Key Takeaways

  • Read current and baseline bars together to see date changes.
  • The status date states how far reported progress extends.
  • Measure physical progress separately from time elapsed.
  • Estimate remaining work to forecast a finish.
  • Choose the view for the reader’s decisions.
6

Balance resources across the schedule

A schedule can satisfy every dependency and still double-book someone. Check demand for each resource in each period before treating the dates as workable. The office move shows why a small overlap matters even when total workload looks manageable. Compare moving work within float with moving it beyond float, and trace how each choice changes the dates and the flexibility that remains.

6.1 Load resources and find overallocation

A logic-based schedule assumes that the resources needed on each activity's dates are available. Test that assumption before approving the plan. A person, room, vehicle or machine can be needed by several otherwise independent activities at once.

Load the resources period by period

Resource loading adds the units of each resource needed in each period. One person assigned full-time is 1 unit; a half-time assignment is 0.5 units. A resource histogram shows periods across the horizontal axis and resource demand up the vertical axis. A line at available capacity makes overloads visible.

Overallocation occurs when demand exceeds availability. A person assigned 12 hours of work in an eight-hour day is overallocated. Two activities each needing the same person full-time also create demand of 2 units against capacity of 1. Underallocation is spare capacity or idle time.

Check Priya's office-move workload

One IT technician, Priya, is assigned full-time to E, D and H. Their early dates occupy working days 4–6, 6–9 and 13–15 respectively.

Working daysActivities needing PriyaUnits needed
1–3None0
4–5E1
6E and D2
7–9D1
10–12None0
13–15H1

Day 6 is Monday, March 8, 2027. Both cabling and packing require Priya for that whole day. She cannot satisfy the plan as drawn. Yet her total assignment is only 3 + 4 + 3 = 10 days within a 15-day project. The average workload hides the one-day peak.

Compare with real availability

Check the resource calendar as well as the project calendar. Vacation, part-time work, other projects and equipment bookings reduce availability. A single activity needing one full-time technician is already an overload if only half a technician's time is available.

Check each resource separately. Enough total staff does not remove a shortage of a specific qualified technician or the only test machine. A histogram for “all people” can hide that difference just as a project-wide total hides a daily peak.

Identify which limit is firm

A resource-constrained project has a fixed supply, such as one crane or a team of four. Dates may need to move to respect that capacity. A time-constrained project has a fixed finish, such as a trade show's opening. Its solution may need more resources or less scope.

Possible responses include moving work within float, delaying work beyond float, assigning another qualified person, contracting help, using overtime, splitting work that can be paused, or changing how the work is done. Review cost and risk with each choice. First make the clash visible, then choose a response that satisfies the work's logic and the project's firm limits.

Key Takeaways

  • Add demand for each resource in each period.
  • Overallocation means period demand exceeds available capacity.
  • A low project-wide average can hide an impossible daily peak.
  • Use resource calendars and specific skills or equipment limits.
  • Identify whether the resource limit or the finish date is firm.

6.2 Resolve overallocation with resource leveling and smoothing

Resources can force dates to move even when no work dependency requires the movement. Compare the shift needed to remove a clash with the float available.

Distinguish smoothing and leveling
ApproachTiming limitConsequence
Resource smoothingMove work within available floatPreserve the project finish; some clashes may remain.
Resource levelingFit demand to available resources, including moves beyond floatThe critical path can change and the finish can move later.

Smoothing leaves the existing logic-critical path and finish dates in place. Using all the float on another branch can make that branch critical too, especially when a shared resource must now work continuously through it.

Resolve the office-move clash

Priya is needed for E on days 4–6 and D on days 6–9. There is a clash on day 6. E has four days of total float and D has one.

First test delaying D until E finishes. D moves one day, to days 7–10, or ES 6 and EF 10. F then runs on days 11–12, while H stays on days 13–15. The project still ends Friday, March 19, 2027. The one-day shift fits D's one day of float, so it is smoothing.

Now test delaying E until D finishes. E would run on days 10–12, or ES 9 and EF 12. That shifts E six days from its original ES 3, exceeding its four days of total float. F moves to days 13–14, H to days 15–17, and the finish becomes Tuesday, March 23. Delaying the activity with more float has produced the worse result because its required shift was much larger.

Recheck flexibility after moving work

After the first choice, E, D and F have no remaining total float in the resource-feasible schedule. The original A–C–G–H logic path still controls a day-15 finish. A second time-critical chain, A–E–D–F–H, now reflects Priya's availability between E and D. Record that as a resource constraint so it can be reconsidered if another technician becomes available. It is not a new dependency inherent in the work.

Recognize when smoothing cannot solve it

Suppose X takes four days and Y three days. Both start the project and lead directly to Finish, so the logic schedule takes four days. One designer must do both full-time. Y has only one day of float; moving it one day still leaves an overlap with X. Leveling puts the activities in sequence and takes seven days. The resource limit adds three days to the finish.

Use a repeatable process: calculate the logic schedule, load resources, find each clash, compare candidate moves with float, move the work, and recalculate. Check the next period too, because a move can create a new clash. Review software's choices and report the new finish and remaining float. Complete this check before baselining so the approved plan is one the available resources can perform.

Key Takeaways

  • Smoothing uses float and preserves the finish date.
  • Leveling can exceed float and delay the finish.
  • Compare the shift needed with the float available for each candidate.
  • Recheck loading and float after every move.
  • Resource-driven chains can become time-critical without a new work dependency.
  • Approve the baseline after resource feasibility has been checked.

Project Scheduling examples

6 Walkthroughs

1

Turn Scope into Activities and Checkpoints

12 steps
Build the planning foundation for an office move, then check the difference between work, events and approved dates.
  1. 1
    IntroductionMake the work schedulable

    An office move needs more than a desired opening date. Someone must plan the layout, arrange deliveries, prepare equipment and test the workstations.

    A schedule connects that work with time. Begin by deciding how to manage the schedule, then turn the work packages into clear activities and meaningful checkpoints.

  2. 2
    ExplanationAgree how the schedule will work

    Before detailed dates, agree the time unit, calendar and update rules. The office move uses working days on a Monday-to-Friday calendar.

    The management approach also records rounding, tools and reporting thresholds. These choices make estimates comparable: “three days” needs a shared meaning before it can be placed on the timeline.

  3. 3
    ConnectionKeep one model and several views

    The schedule model holds activities, durations, dependencies, calendars and resources. A network shows their logic, a Gantt chart their timing and a milestone chart the main events.

    Once approved, the baseline preserves the reference dates. Current forecasts can change while that approved comparison stays available.

  4. 4
    ChallengeShow the slip clearly

    After a delivery delay, the forecast finish changes from day 18 to day 21. The baseline has not been formally changed. What should the planner retain and update?

    ---reveal---

    Retain the day-18 baseline and update the current forecast to day 21. The three-day gap shows the slip. Overwriting the approved reference would hide the change from the original agreement.

  5. 5
    ExampleBreak down the network work package

    The work package “New office network” becomes a sequence of actions: survey the office, order cables and switches, install cabling, configure switches and test connections. This is decomposition.

    Each activity names work a person can own and estimate. The deliverable groups the actions; its noun label alone does not tell someone what to do.

  6. 6
    TipMake a finish checkable

    “Test network connections” needs a clear finish, such as every installed outlet passing the agreed test and the results being recorded. Add an owner and later its duration and dependencies. Keep enough detail to see progress between reports, but avoid hundreds of tiny rows that cost more to maintain than they help control.

  7. 7
    ChallengeInclude the missing approval

    A schedule contains “Install access system” but leaves out a required two-day approval review before use. How should the missing time be represented?

    ---reveal---

    Add a review activity with its own duration and completion criterion. Link it before use. A zero-duration “Access approved” milestone can mark its end, but the milestone cannot carry the review’s two days of work.

  8. 8
    ExplanationMark meaningful states

    A milestone marks an event with zero duration and no resource demand. Use achieved states: “Move plan approved,” “Equipment moved” and “Office ready for staff.” Each should be verifiable. Place important approvals, major deliverable completions and phase decisions where stakeholders need checkpoints, then keep their planned and actual dates.

  9. 9
    ChallengeSeparate a requirement from a forecast

    “Site accepted” is required by day 24. Its linked work currently ends at day 27. Does changing the diamond to day 24 solve the timing problem?

    ---reveal---

    No. Keep the required date and day-27 forecast visible. The milestone has no duration to shorten. Review the plan or agree a later requirement; acceptance cannot truthfully be shown before its required work is complete.

  10. 10
    Key InsightPlan more detail as knowledge grows

    In rolling wave planning, the next phase has detailed activities while later phases remain at work-package level until information improves. A timebox makes a different choice: its end stays fixed, and delivered scope can reduce to fit.

    Some adaptive work uses continuous flow instead. Choose the planning approach that fits how the work is managed.

  11. 11
    ChallengeBuild a useful chain of work and events

    The work package “Training ready” needs a two-day preparation activity and a one-day review. Propose two activity names and a final milestone.

    ---reveal---

    Use “Prepare training materials” and “Review training materials,” followed by “Training approved.” The first two carry time and ownership. The final marker records the achieved state with zero duration and can appear in a sponsor’s milestone view.

  12. 12
    RecapCheck before assigning dates

    Check the scope-to-work connection first. Every work package needs activities, every activity needs a useful finish criterion, and every milestone needs an observable event. Keep the current schedule linked to one model and preserve its approved baseline. Those decisions give sequencing and estimating a dependable starting point.

2

Trace the Office-Move Network

12 steps
Choose relationships, draw the branches and compare the three routes through the office move.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionFind what controls the order
  2. 2
    ExplanationRead the predecessor first
  3. 3
    ExampleKeep service during a handover
  4. 4
    ExplanationExplain the reason for a link
  5. 5
    ChallengeInterpret a signed lag
  6. 6
    ExamplePlace the first three branches
  7. 7
    ExampleJoin the required inputs
  8. 8
    ChallengeCatch an omitted branch
  9. 9
    ExampleCompare complete paths
  10. 10
    TipAudit open ends and loops
  11. 11
    ChallengeDistinguish logic from limited staff
  12. 12
    RecapRead the network as required events
3

Build and Compare Duration Estimates

13 steps
Estimate a clinic installation from labor, production rates, parallel steps and uncertain durations.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionAsk what the estimate rests on
  2. 2
    ExplanationSeparate labor from time
  3. 3
    ExampleCalculate productive capacity
  4. 4
    ChallengeApply a half-time assignment
  5. 5
    Key InsightCheck which clock the wait uses
  6. 6
    ExplanationChoose the evidence for the estimate
  7. 7
    ExampleUse a measured rate
  8. 8
    ChallengeCombine detailed parts
  9. 9
    ExampleWeight an uncertain estimate
  10. 10
    Key InsightRead the spread beside the average
  11. 11
    TipRecord assumptions and reserve
  12. 12
    ChallengeDiagnose a shorter promise
  13. 13
    RecapChoose a supported duration
4

Calculate the Office Move and Test Its Float

18 steps
Work through early and late times, shared flexibility, delays and an imposed deadline.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionFind the dates that control the move
  2. 2
    ExplanationStart from a time boundary
  3. 3
    ExampleCalculate the branches after A
  4. 4
    ExampleWait for the later input at F
  5. 5
    ChallengeComplete the forward pass
  6. 6
    ExampleBegin the backward pass
  7. 7
    ExampleChoose the earlier limit at A
  8. 8
    TipAdjust each link before comparing
  9. 9
    ExplanationMeasure two kinds of room
  10. 10
    ExampleCalculate E’s float
  11. 11
    ChallengeSpend a shared gap once
  12. 12
    Key InsightIdentify the controlling route
  13. 13
    ExampleTrace a delay beyond float
  14. 14
    ChallengeJudge a smaller delay
  15. 15
    ExampleUse an imposed finish
  16. 16
    ChallengeFind the new critical path
  17. 17
    ConnectionReport the effect and remaining room
  18. 18
    RecapCheck the controlling limit
5

Put the Office Move on a Calendar

11 steps
Convert calculated times to dates, then read progress and baseline differences from a Gantt chart.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionGive the team usable dates
  2. 2
    ExplanationConvert time 0 correctly
  3. 3
    ExampleCross the weekend without adding work
  4. 4
    ExampleFinish the bars and milestone
  5. 5
    ChallengeDraw a float extension
  6. 6
    ExplanationRead work at the status date
  7. 7
    ExampleForecast the remaining packing
  8. 8
    ChallengeKeep the comparison visible
  9. 9
    ConnectionChoose the reader’s view
  10. 10
    ChallengeExplain a valid bar movement
  11. 11
    RecapRead dates with their basis
6

Remove a Technician’s Double Booking

12 steps
Load the office-move resources and compare two ways of moving the clashing work.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionTest whether the dates can be staffed
  2. 2
    ExampleAdd Priya’s daily demand
  3. 3
    ChallengeCheck the average against the peak
  4. 4
    ExplanationCompare float with the required shift
  5. 5
    ExampleTry moving packing one day
  6. 6
    Key InsightNotice what flexibility was spent
  7. 7
    ExampleTry moving cabling instead
  8. 8
    ChallengeChoose by the required move
  9. 9
    ConnectionIdentify the firm limit
  10. 10
    ChallengeRecognize a clash float cannot remove
  11. 11
    TipRecheck after every change
  12. 12
    RecapApprove a feasible schedule

Project Scheduling practice questions

50 Practice Questions in 5 sets

Set 1: Apply Logic, Estimates and Float10 Practice Questions

Question 1 of 10

A team details the next month but keeps later phases at work-package level until a pilot finishes. What planning approach is it using?
  1. Resource leveling
  2. Rolling wave planning
  3. Baseline comparison
  4. Parametric estimating
Show answerHide answer
Answer: B
Rolling wave planning adds detail as work approaches and the team learns more. The later phases remain planned at a higher level while the next month has actionable activities. Resource leveling also changes a schedule, but its purpose is to fit work to available capacity, not to decide when detail is developed.

Question 2 of 10

A team estimates equipment installation but omits the required two-day review before use. What change makes the activity list complete?
  1. Add two days to the installation without naming the review
  2. Show “Review complete” as a two-day milestone
  3. Mark installation complete before the review starts
  4. Add the review with its duration and completion criterion
Show answerHide answer
Answer: D
The review is work that takes time, so it needs an activity with a checkable finish. Its completion can then be a zero-duration milestone. Adding two unexplained days to installation may lengthen the picture, but it hides the separate review and makes ownership and progress harder to track.

Question 3 of 10

A supplier finishes a prototype at time 12. Validation has an FS + 3-working-day link from that activity. What is validation’s earliest start if nothing else constrains it?
  1. 15
  2. 9
  3. 12
  4. 16
Show answerHide answer
Answer: A
An FS link starts from the predecessor’s finish; the positive lag adds three working periods. The earliest start is 12 + 3 = 15. Time 9 would apply a lead, allowing validation to begin before the prototype finishes, which reverses the meaning of the stated positive lag.

Question 4 of 10

A crew checks 15 records per day. Two equivalent crews check 180 records at that same rate. Whole-day rounding is unnecessary. How long will the work take?
  1. 12 working days
  2. 15 working days
  3. 6 working days
  4. 24 working days
Show answerHide answer
Answer: C
The crews together check 30 records per day. Dividing 180 by 30 gives six days. Twelve days uses only one crew’s rate and ignores the second crew; the rate per crew stays the same while the combined daily production doubles under the conditions given.

Question 5 of 10

A coating finishes Friday evening. Its required wait is two elapsed days, and the next team works Monday through Friday. When can that team first start, with no holidays?
  1. Tuesday morning
  2. Wednesday morning
  3. Monday morning
  4. Friday morning
Show answerHide answer
Answer: C
The two elapsed days are Saturday and Sunday, so the wait is complete by Monday morning. Wednesday would follow a two-working-day wait, counting Monday and Tuesday instead. The next team’s working calendar prevents a weekend start but does not stop the elapsed waiting time from running.

Question 6 of 10

Two immediate predecessors have EF 7 and EF 10. Their links to R are FS + 2 and FS + 0, respectively. R lasts four days. What are R’s ES and EF?
  1. ES 10, EF 14
  2. ES 9, EF 13
  3. ES 12, EF 16
  4. ES 7, EF 11
Show answerHide answer
Answer: A
The incoming limits are 7 + 2 = 9 and 10 + 0 = 10. R waits for both, so ES is 10 and EF is 14. Using 9 considers the lagged predecessor but overlooks the second branch, which is not ready until time 10.

Question 7 of 10

An activity has free float 2 days and total float 5 days. It slips four days with FS logic and nothing else changing. What happens?
  1. No successor moves and the finish holds
  2. A successor moves and the finish slips two days
  3. No successor moves but the finish slips four days
  4. A successor moves, but the project finish holds
Show answerHide answer
Answer: D
Four days exceeds the two-day free float, so at least one successor moves. It stays within the five-day total float, so the project finish holds. Subtracting free float to claim a two-day project delay confuses the limit protecting a successor with the limit protecting the whole project.

Question 8 of 10

At a status date, an evenly planned six-day activity has used four days but completed half its work. The remaining half is estimated at three working days. How does its forecast compare with the plan?
  1. It finishes on time at 67% complete
  2. It finishes one working day late
  3. It finishes two working days late
  4. It finishes one working day early
Show answerHide answer
Answer: B
Four days have passed and three remain, giving a seven-day forecast against six planned days. The activity is one working day late. Reporting 67% complete from four of six days would confuse elapsed time with measured output; the stated physical progress is only 50%.

Question 9 of 10

Two full-time activities share one technician. Moving K two days ends the clash; K has three days of total float. Moving L four days also ends it; L has two days of total float. Nothing else changes. Which move preserves the finish?
  1. Move L four days within its float
  2. Move K three days and L two days
  3. Move K four days; leave L unchanged
  4. Move L two days and leave K unchanged
Show answerHide answer
Answer: C
K’s required two-day shift fits inside its three-day float, so that move removes the clash without delaying the finish. L needs four days but has only two days of float. Moving L only two days preserves its limit but does not meet the stated four-day shift needed to end the clash.

Question 10 of 10

A single unbranched non-critical chain U–V–W shares three days of total float. U finishes two days later than planned and V then takes two extra days. Everything else stays unchanged. How far does the project finish move?
  1. 1 day
  2. 0 days
  3. 2 days
  4. 4 days
Show answerHide answer
Answer: A
The chain accumulates four days of delay against one shared three-day gap, so the finish slips one day. Giving U and V three separate days would count the same flexibility twice. After U uses two days, only one day remains to absorb V’s additional two-day delay.
Set 2: Build and Read a Small Schedule10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A WBS contains the work package “Customer help center.” What is a clear activity name for work needed to produce it?
  1. Write help articles
  2. Customer help center
  3. Articles ready
  4. Help center accepted
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A team schedules a three-day approval review. What duration belongs to the milestone “Design accepted” at the review’s completion?
  1. 1 day
  2. 3 days
  3. 4 days
  4. 0 days
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A report’s editing can overlap its writing, but editing cannot finish until writing finishes. What relationship captures this rule, with writing as predecessor?
  1. Finish-to-start
  2. Finish-to-finish
  3. Start-to-start
  4. Start-to-finish
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A museum project has FS paths of 2 + 5 + 3 days and 2 + 8 + 3 days, with no lags or resource limits. What is its shortest duration?
  1. 10 days
  2. 13 days
  3. 18 days
  4. 23 days
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

An inspection needs 84 person-hours of divisible work. Three inspectors each supply four productive hours daily. What duration should be estimated?
  1. 4 working days
  2. 12 working days
  3. 21 working days
  4. 7 working days
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Time starts at 0. An activity has ES 6 and duration 5 days. What is its EF?
  1. 11
  2. 10
  3. 12
  4. 30
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

An activity lasts three days and has one FS successor with LS 14 and no lag. What are its LF and LS?
  1. LF 14, LS 17
  2. LF 17, LS 14
  3. LF 14, LS 11
  4. LF 13, LS 10
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A project starts Monday, May 3, 2027 on a Monday-to-Friday calendar with no holidays. Time starts at 0. An activity has ES 4 and EF 7. When does it run?
  1. Thursday, May 6–Monday, May 10
  2. Friday, May 7–Sunday, May 9
  3. Monday, May 10–Wednesday, May 12
  4. Friday, May 7–Tuesday, May 11
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A project has new forecast dates after a supplier delay. What should the team preserve for comparison with the approved plan?
  1. The revised forecast
  2. The list of activities
  3. The schedule baseline
  4. The supplier’s calendar
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A specialist has capacity of one full-time unit. On Tuesday, two activities need 0.6 units each; on Wednesday, demand is 0.8. What does the loading show?
  1. Tuesday exceeds capacity by 0.2 units
  2. Wednesday exceeds capacity by 0.2 units
  3. Both days fit when averaged together
  4. Tuesday fits as each task is below 1.0
Show answerHide answer

Save this lesson to see this answer.

Set 3: Connect Dates, Paths and Resources10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A zero-duration “Trial accepted” milestone immediately follows a trial, with no lag or outside date imposed. What determines its forecast date?
  1. The trial’s calculated completion date
  2. The project’s original start date
  3. The milestone’s estimated work duration
  4. The sponsor’s preferred reporting date
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

In an AON network, Q must follow both M and N. M must follow L. N can start at project start. What incoming links belong at Q?
  1. L → Q and N → Q
  2. Q → M and Q → N
  3. M → Q and N → Q
  4. M → Q with N left unconnected
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A required inspection is performed by an authority outside the project team. How should its dependency be classified?
  1. Discretionary and external
  2. Mandatory and internal
  3. Discretionary and internal
  4. Mandatory and external
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A survey takes two days. After it, installation takes nine days and configuration four days in parallel. A three-day test follows both. With FS links and no lags or resource limits, what is the package duration?
  1. 18 days
  2. 14 days
  3. 12 days
  4. 16 days
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

An activity lasts five days and has two FS successors without lags, with LS 16 and LS 13. What are its LF and LS?
  1. LF 16, LS 11
  2. LF 13, LS 8
  3. LF 13, LS 9
  4. LF 18, LS 13
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

An activity has ES 5, EF 9, LS 11 and LF 15. Its two immediate FS successors have ES 12 and ES 10, with no lags. What are its total and free float?
  1. Total 6 days; free 1 day
  2. Total 6 days; free 3 days
  3. Total 4 days; free 1 day
  4. Total 1 day; free 6 days
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A network’s longest path takes 22 days and a second path takes 20 days. An activity only on the second path takes four extra days. FS logic and all other conditions stay unchanged. What is the new duration and controlling path?
  1. 26 days, controlled by the original longest path
  2. 22 days, controlled by both paths
  3. 24 days, controlled by the second path
  4. 24 days, controlled by the original longest path
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A Gantt group has child activities running working days 2–5, 4–8 and 7–10. What dates should its summary row span?
  1. Working days 4–8
  2. Working days 2–23
  3. Working days 5–10
  4. Working days 2–10
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

An activity forecasts two working days later than its unchanged baseline. It originally had one day of total float, and nothing else changes in the FS network. What should the report say?
  1. The activity slips one day; the project slips two days
  2. The activity slips two days; the project holds
  3. The activity slips two days; the project slips one day
  4. The activity holds; the project slips one day
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Two activities start together and lead directly to Finish. They take six and four days, need the same person full-time, and cannot be split. With no extra person, what are the logic-only and leveled durations?
  1. 6 days and 10 days
  2. 6 days and 8 days
  3. 10 days and 10 days
  4. 4 days and 6 days
Show answerHide answer

Save this lesson to see this answer.

Set 4: Diagnose Schedule Problems10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A long activity repeatedly reports “almost done.” What addition most directly makes its completion checkable?
  1. A more optimistic percent-complete figure
  2. A fixed start date for every later activity
  3. A larger unexplained duration allowance
  4. A clear criterion for the finished result
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A network contains Start → R → S → T → R, with T also connected to Finish. All links are FS. What must be corrected before calculating a workable schedule?
  1. The direct link from T to Finish
  2. The circular dependency among R, S and T
  3. The presence of three separate activity boxes
  4. The fact that R has a link from Start
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A specialist can supply six productive hours per full working day but is assigned 50% to this project. How many working days are needed for 27 person-hours of divisible work?
  1. 9 days
  2. 4.5 days
  3. 6 days
  4. 13.5 days
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

An activity has O = 3, M = 6 and P = 15 days. What are its beta average and commonly used beta standard deviation?
  1. 7 days and 2 days
  2. 8 days and 2 days
  3. 7 days and 3 days
  4. 8 days and 3 days
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

R lasts four days. Its two successors have LS 18 and LS 15, with FS + 3 and FS + 1 links from R, respectively. What are R’s LF and LS?
  1. LF 15, LS 11
  2. LF 16, LS 12
  3. LF 14, LS 10
  4. LF 18, LS 14
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A project has two FS paths of 18 and 16 days, sharing only Start and Finish. A required finish at time 15 is used for the backward pass. What total float applies to activities unique to each path?
  1. 0 days on the 18-day path; 2 on the 16-day path
  2. −1 day on the 18-day path; −3 on the 16-day path
  3. 3 days on the 18-day path; 1 on the 16-day path
  4. −3 days on the 18-day path; −1 on the 16-day path
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A planner wants to inspect why a delayed branch now controls the project. What view best reveals the dependency routes?
  1. A milestone chart
  2. A network diagram
  3. A resource histogram
  4. A percent-complete list
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A test machine is available at 0.5 units on Monday and 1.0 on Tuesday. Demand is 0.75 Monday and 1.0 Tuesday. What does the comparison show?
  1. An overload of 0.25 units on both days
  2. No overload because neither demand exceeds 1.0
  3. An overload of 0.25 units on Monday only
  4. An overload of 0.5 units on Monday only
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A proposed move removes a resource clash but exceeds an activity’s total float by two days. FS logic and everything else stay unchanged. How should the move and its finish effect be described?
  1. Leveling that delays the finish two days
  2. Smoothing that delays the finish two days
  3. Leveling that preserves the finish date
  4. Smoothing that preserves the finish date
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Two FS paths share only Start and Finish and take 12 and 11 days. An activity unique to the 12-day path is shortened by three days. No resource limits or other changes apply. What is the new duration?
  1. 9 days
  2. 10 days
  3. 12 days
  4. 11 days
Show answerHide answer

Save this lesson to see this answer.

Set 5: Make and Defend Scheduling Decisions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A sponsor needs key event dates and the team needs detailed activity bars. How should the planner keep their views consistent?
  1. Maintain two independently typed schedules
  2. Generate both views from one schedule model
  3. Put every activity into the sponsor’s milestone chart
  4. Use the baseline as the team’s current forecast
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

An acceptance milestone is required by day 20 but the linked work currently finishes at day 23. How should the schedule show this?
  1. Set the milestone to day 20 and leave the work ending at 23
  2. Change the requirement to day 23 without approval
  3. Keep the requirement and show the day-23 forecast
  4. Give the milestone a duration of three days
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A warehouse must continue using its old dispatch service until the replacement service starts. With the replacement as predecessor, what relationship models this rule?
  1. Start-to-finish
  2. Finish-to-start
  3. Start-to-start
  4. Finish-to-finish
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Two crews normally each install 12 outlets daily. Restricted access reduces the first crew’s output by half; the second crew keeps its normal rate. What parametric duration follows for 360 outlets under these conditions?
  1. 15 working days
  2. 30 working days
  3. 40 working days
  4. 20 working days
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

P ends at 8 and Q at 11. R follows P with FS + 4 and Q with FS − 1, then takes three days. With time counted from 0 and no other constraints, what is R’s EF?
  1. 14
  2. 13
  3. 16
  4. 15
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Three FS paths share only Start and Finish and take 19, 19 and 17 days. Work unique to the first path is shortened two days; work unique to the third takes one extra day. With no other changes, what controls the new finish?
  1. 19 days, controlled by both original longest paths
  2. 19 days, controlled only by the unchanged second path
  3. 18 days, controlled by the extended third path
  4. 17 days, controlled by the shortened first path
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

An activity has EF 10, free float 3 and total float 5. Its finish slips to 16 with FS logic and nothing else changing. How far does its earliest affected successor move, and how far does the project finish move?
  1. Successor 3 days; project 1 day
  2. Successor 6 days; project 6 days
  3. Successor 1 day; project 3 days
  4. Successor 3 days; project 3 days
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A project starts Monday, June 7, 2027. The calendar is Monday–Friday, except Wednesday, June 9 is nonworking. Time starts at 0. An activity has ES 2 and EF 5. What are its dates?
  1. Wednesday, June 9–Friday, June 11
  2. Thursday, June 10–Sunday, June 13
  3. Thursday, June 10–Monday, June 14
  4. Tuesday, June 8–Thursday, June 10
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A team has one available technician. Two activities each require that technician full-time on Thursday, although only eight technician-days are needed across the ten-day project. What is the resource problem?
  1. Thursday has demand of two units against one available
  2. The whole project exceeds capacity by eight days
  3. There is no overload because eight is less than ten
  4. Each activity’s duration must be cut in half
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

One technician is assigned full-time to M on working days 2–4 and N on days 4–7. M has five days of total float; N has one. With no other changes, what move removes the clash and preserves the finish?
  1. Delay M six days
  2. Delay N one day
  3. Delay M five days
  4. Delay N two days
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

78 Key Terms, each with its definition

A

Activity
An activity is a distinct piece of scheduled work with a start, finish and duration, usually requiring people or equipment to complete it.
The activity “Test network connections” finishes when every required connection has passed its test.
Activity attributes
Activity attributes are the planning details attached to an activity, such as its owner, resources, duration, relationships and assumptions.
The activity attributes show the installer’s calendar and the delivery on which the work depends.
Activity list
An activity list records the unique identifier and name of each scheduled activity, providing the basis for sequencing and estimating.
The planner adds a missing approval to the activity list before calculating the installation dates.
Activity-on-arrow
Activity-on-arrow is a network format with activities drawn as arrows between event circles, using dummies for some finish-to-start logic.
An activity-on-arrow diagram uses a dashed dummy to carry an extra dependency without adding time.
Activity-on-node
Activity-on-node is a network format that draws each activity as a box and each dependency as an arrow from predecessor to successor.
In an activity-on-node view where F depends on D and E, box F has two incoming arrows, one from each.
Analogous estimating
Analogous estimating bases a duration on actual results from similar past work, giving a quick estimate whose quality depends on comparability.
Analogous estimating uses last year’s three-week office move as a starting point for a similar move.

B

Backward pass
A backward pass calculates late times from a project finish, using the earliest required successor timing at each FS branch.
If furniture procurement must start by time 3, the backward pass gives its predecessor a late finish of 3.
Beta average
A beta average weights the most likely duration four times and the optimistic and pessimistic values once, then divides the total by six.
The beta average of four, six and fourteen days gives seven days because the middle value has more weight.
Bottom-up estimating
Bottom-up estimating estimates smaller parts in detail and combines their durations through the sequence, allowing parallel work to overlap.
When a clinic package’s parts are estimated separately and configuration runs in parallel, bottom-up estimating gives eight days.
Burst point
A burst point is an activity with several immediate successors, sending work along multiple branches in a network diagram.
A move-layout activity is a burst point when booking, furniture procurement and cabling all follow it.

C

Critical path
A critical path is a longest path through the schedule network that controls the shortest possible project duration under its timing logic.
In an office move whose longest path A–C–G–H takes 15 working days before resource checks, A–C–G–H is the critical path.
Critical path method
The critical path method calculates early and late activity times from durations and dependencies to find project duration and timing flexibility.
For an office move, the critical path method gives a 15-working-day duration before resource limits are checked.

D

Decomposition
Decomposition breaks a work package into the practical steps needed to complete it at a level that supports estimating and tracking.
Decomposition separates network installation into surveying, ordering, cabling, configuring and testing.
Deliverable
A deliverable is a product or result the project produces; the moment when it is completed or accepted can be marked by a milestone.
The network is a deliverable, while “Network tested” marks an event associated with that result.
Delphi technique
The Delphi technique gathers anonymous expert estimates over several rounds, sharing summaries so experts can revise without one voice dominating.
The Delphi technique gives each specialist a chance to reconsider the estimate after seeing the group summary.
Dependency
A dependency is a logical relationship in which an event at one activity constrains the timing of an event at another activity.
A dependency prevents connection tests from starting before the required cabling has been installed.
Discretionary dependency
A discretionary dependency is a sequence chosen by the team although another sequence is possible, with the reason recorded for review.
Painting before laying carpet is a discretionary dependency chosen to protect the new flooring.
Dummy activity
A dummy activity is a zero-duration dashed arrow used in an activity-on-arrow network to express a dependency without adding work.
When C needs both A and B but D needs only A, a dummy activity carries A’s completion to C’s start without forcing D to wait for B.
Duration
Duration is the number of working periods an activity occupies from start to finish, excluding nonworking time on its calendar.
The installation’s duration is six working days when two technicians each supply six productive hours daily.

E

Early finish
An early finish is the earliest calculated completion time of an activity, found by adding duration to early start when time starts at 0.
An early finish of 11 places the equipment move’s completion at the end of working day 11.
Early start
An early start is the earliest time an activity can begin under the calculated dependencies, durations and relevant schedule constraints.
An activity with an early start at time 9 begins at the start of working day 10 in the time-0 convention.
Effort
Effort is the total labor required to complete an activity, measured in person-hours or person-days independently of calendar span.
If a clinic installation needs an effort of 72 person-hours, the available technicians share those hours between them.
Elapsed time
Elapsed time is the total calendar time between start and finish, including weekends, holidays and other nonworking periods.
Paint can dry during a weekend because that waiting requirement is measured in elapsed time.
Estimating funnel
An estimating funnel illustrates how estimate ranges usually narrow as the work becomes better defined and more information is available.
The estimating funnel explains why a rollout’s early estimate range is wider than its estimate after a site survey.
Expert judgment
Expert judgment uses relevant experience to estimate work and assess whether the assumptions, production rates and resulting durations fit it.
Expert judgment from installers helps the planner allow for difficult access to the old building.
External dependency
An external dependency ties project timing to work or an event outside the project team’s control, such as a supplier delivery.
The landlord’s handover creates an external dependency for the team preparing the new office.

F

Finish-to-finish
Finish-to-finish is a dependency in which the successor cannot finish until the predecessor finishes, adjusted by any lead or lag.
A finish-to-finish link allows editing alongside writing but prevents editing from finishing first.
Finish-to-start
Finish-to-start is a dependency in which the successor cannot start until the predecessor finishes, adjusted by any lead or lag.
A finish-to-start link keeps the equipment move after packing, with no overlap in those activities.
Float line
A float line extends an activity’s bar from early finish to late finish to show its total float on the chart’s time scale.
An activity’s float line reaches March 12 when its early finish is March 8 and it has four working days of total float.
Forecast finish
A forecast finish is the current expected completion date, based on reported progress, remaining work and the updated schedule logic.
The forecast finish for packing moves to March 12 when two days of work remain after March 10.
Forward pass
A forward pass calculates early times through a network, using the latest required predecessor timing at each FS merge.
If packing finishes at time 9 and cabling finishes earlier, the forward pass sets the equipment move’s early start at 9.
Free float
Free float is the delay available to an activity without delaying the early start of any of its immediate successors.
An activity with three days of free float can slip three days before its delay changes its successor’s early start.

G

Gantt chart
A Gantt chart displays scheduled activities as horizontal bars against a time scale, with bar positions and lengths showing dates and durations.
The Gantt chart shows the equipment move crossing a weekend without treating that weekend as working time.

I

Imposed date
An imposed date is a schedule requirement set from outside the network calculation, such as a required finish or an earliest permitted start.
An imposed date for handing over the keys prevents cabling from starting before access is available.
Internal dependency
An internal dependency links activities controlled by the project team, whether the sequence is mandatory or chosen by preference.
Packing before moving the team’s equipment is an internal dependency within the office-move project.

L

Lag
A lag is a delay added to a dependency, placing the linked successor event later than the predecessor event by a stated amount of time.
A two-working-day lag after painting allows curing before the team starts hanging pictures.
Late finish
A late finish is the latest time an activity can complete without missing the finish used in the backward pass or a relevant constraint.
An activity has a late finish of 12 when its successor, workstation setup, must start at that time.
Late start
A late start is the latest time an activity can begin without missing the finish used in the backward pass or a relevant constraint.
If an activity’s early start is time 3, a late start of time 7 falls four working days later.
Lead
A lead permits a successor to overlap its predecessor relative to the specified relationship and is recorded as a negative lag.
A three-day lead allows training-material writing to start three days before configuration finishes.
Linked Gantt chart
A linked Gantt chart draws bars from a schedule model so that changing a duration or dependency updates the affected activity dates.
When packing slips a day, a linked Gantt chart moves the activity that follows packing and leaves a later activity at its original start.

M

Mandatory dependency
A mandatory dependency is a sequence required by the nature of the work or by a contract, also called hard logic.
Testing after installation is a mandatory dependency because the network must exist before it can be tested.
Merge point
A merge point is an activity with several immediate predecessors whose relationship requirements must all be met before it proceeds.
Moving equipment is a merge point when it can start only after both packing and cabling are finished.
Milestone
A milestone is a significant project event or point with zero duration and no resource demand, often marking completion or approval.
The milestone “Office ready for staff” occurs after workstation setup and testing are complete.
Milestone chart
A milestone chart places key events on a timeline so readers can compare planned, forecast or actual dates without detailed activity bars.
The sponsor reviews a milestone chart to check whether delivery and opening dates have moved.
Milestone list
A milestone list records identifiers, names, descriptions, required or optional status, planned dates and later actual dates for key events.
The milestone list identifies “Lease signed” as required and records the date it was actually reached.

N

Near-critical path
A near-critical path is a path with little timing flexibility that can become critical after a small delay or another schedule update.
A 14-day packing route is a near-critical path when the project has only one day to absorb its delay.
Negative float
Negative float is a shortfall against a schedule constraint, produced when the allowed late timing falls before the calculated early timing.
Negative float of two days on the longest route shows that a day-13 deadline conflicts with a day-15 plan.
Network diagram
A network diagram shows activities and their logical relationships so a planner can trace branches, meeting points and complete paths.
The network diagram shows that moving equipment requires both packing and cabling to be complete.

O

Overallocation
Overallocation occurs when scheduled demand for a resource exceeds its available capacity during a particular period.
A technician’s overallocation on Monday comes from full-time assignments to both cabling and packing.

P

Parametric estimating
Parametric estimating calculates duration from a quantity of work and a reliable production rate under comparable working conditions.
Parametric estimating converts 120 outlets and two eight-outlet-per-day crews into 7.5 working days.
Path
A path is a continuous chain through a network from Start to Finish; for FS links without lags, its length is the sum of its durations.
In an office move whose path A–C–G–H takes 15 working days, that path controls the logic-based finish.
Percent complete
Percent complete expresses how much of an activity’s work is finished, measured from output or other suitable evidence rather than time alone.
Packing’s percent complete is 50% even though three of its four planned working days have passed.
Predecessor
A predecessor is the activity whose start or finish controls a linked event at another activity under the specified relationship.
The new phone service is the predecessor when its start allows the old service to finish.
Project schedule
A project schedule sets out activities, their order, durations and dates, together with the milestones needed to deliver the agreed scope.
The project schedule shows when the office team needs the movers and when staff can use the new site.

R

Resource calendar
A resource calendar records when a particular person or item of equipment is available, including working patterns and absences.
The technician’s resource calendar removes vacation days from the capacity available for installation.
Resource constraint
A resource constraint limits when work can happen because the required people or equipment are unavailable for all requested activities.
A resource constraint between two activities needing the same technician disappears if another qualified technician becomes available.
Resource histogram
A resource histogram is a bar chart of demand by period, often shown with a capacity line to make peaks above availability visible.
A resource histogram shows a two-unit bar against one available technician on a day when two of her assignments overlap.
Resource leveling
Resource leveling adjusts activity dates to fit resource supply and can exceed float, change the critical path and delay the finish.
Resource leveling gives one designer seven days to do four-day and three-day activities in sequence.
Resource loading
Resource loading adds the units of each resource required by scheduled activities in each period so demand can be checked against availability.
Resource loading shows that a technician is needed twice on working day 6 even though her total work is ten days.
Resource smoothing
Resource smoothing adjusts activity timing within available float to keep resource demand within limits while preserving the project finish.
In an office move due to finish on day 15, resource smoothing moves packing one day later and keeps that finish.
Resource-constrained project
A resource-constrained project must fit work to a fixed supply of people or equipment, so its finish date may need to move.
A resource-constrained project with one designer must sequence work that initially appeared in parallel.
Rolling wave planning
Rolling wave planning details near-term activities while keeping later work at a higher level until more information becomes available.
Rolling wave planning lets the rollout team refine later sites after reviewing the first pilot.

S

Schedule baseline
A schedule baseline is the approved schedule kept as the date reference for measuring progress and changed through formal change control.
The team compares a forecast opening date with the schedule baseline to show the effect of a delay.
Schedule management approach
A schedule management approach records how a schedule is built and maintained, including calendars, time units, update rules and reporting thresholds.
The schedule management approach sets weekly updates and states how the team will report significant slips.
Schedule model
A schedule model is the working collection of activities, dependencies, durations, calendars and resources from which schedule views are produced.
Changing a delivery duration in the schedule model updates its linked Gantt and milestone views.
Schedule reserve
Schedule reserve is visible extra time justified by identified risks and managed separately from realistic activity duration estimates.
The project manager keeps three working days of schedule reserve before the planned finish milestone.
Start-no-earlier-than constraint
A start-no-earlier-than constraint prevents an activity from starting before a specified time even when its predecessors are complete.
A start-no-earlier-than constraint at time 5 keeps an activity waiting for access while the project still finishes on day 15.
Start-to-finish
Start-to-finish is a dependency in which the successor cannot finish until the predecessor starts, adjusted by any lead or lag.
A start-to-finish link keeps the old service running until the replacement service has started.
Start-to-start
Start-to-start is a dependency in which the successor cannot start until the predecessor starts, adjusted by any specified lag.
A start-to-start link allows furniture assembly to begin after carpet laying has started in the first rooms.
Status date
A status date is the point through which progress information has been recorded, used to compare completed work and remaining forecasts.
At the March 10 status date, the team records half the packing complete and estimates two days remaining.
Successor
A successor is an activity whose start or finish is constrained by a linked event at its predecessor under a specified relationship.
Testing is a successor of installation because testing cannot start before installation finishes.
Summary row
A summary row rolls up a group of activities from their earliest start to their latest finish without adding a separate piece of work.
A summary row for a network work package spans survey through testing while its child activities carry the detail.

T

Three-point estimating
Three-point estimating uses optimistic, most likely and pessimistic durations to make uncertainty part of the selected activity estimate.
Three-point estimating lets the cabling plan reflect the possibility of removing old wiring first.
Time-constrained project
A time-constrained project has a firm timing requirement, so it may need more resources or less scope to produce a feasible schedule.
A trade-show opening date makes a project time-constrained when installation capacity is insufficient.
Timebox
A timebox is a fixed period for completing selected work; its end stays fixed when the amount of scope delivered must be reduced.
A two-week timebox ends on its planned date even when some selected software features remain unfinished.
Total float
Total float is the delay available from an activity’s early dates without delaying the project finish or breaking a schedule constraint.
In one network, activity E has four days of total float, while activity F has only one day before its successor H.
Triangular average
A triangular average weights optimistic, most likely and pessimistic durations equally by adding them and dividing their sum by three.
The triangular average of four, six and fourteen days gives an eight-day estimate for cabling.

W

Work package
A work package is the lowest-level WBS component describing a deliverable or part of one, which scheduling breaks into activities.
The “New office network” work package groups survey, installation and testing activities.

About this lesson

By StudeliReport a mistake