Project Life Cycles and Delivery Approaches
BeginnerLesson 2 of 9 in Project Management Foundations Course
What you will learn
- Explain what a project life cycle is, how phases divide the work, and how a review at the end of each phase decides whether the project continues.
- Explain the project life cycle and its phasesDefine the project life cycle and its phases, tell it apart from the product life cycle, and describe how cost, risk and the cost of change behave from start to finish.
- Use phase gates to decide whether a project continuesDescribe the review at the end of a phase: who decides, what is checked, which decisions are possible and why stopping a project can be the right result.
- Explain the project life cycle and its phases
- Describe the five groups of project management processes, what each one produces, and how they repeat and overlap inside the phases of a project.
- Describe the five process groupsState the purpose and main outputs of the initiating, planning, executing, monitoring and controlling, and closing process groups, and sort project activities into them.
- Relate the process groups to phases and to the improvement cycleExplain why process groups are not phases, how they repeat and overlap within each phase, and how they connect to plan-do-check-act and to adaptive work.
- Describe the five process groups
- Recognize how each life cycle plans, builds and delivers the work, and which kinds of project each one suits.
- Describe the predictive life cycleExplain how a predictive life cycle fixes scope early, moves through sequential phases and controls change, and judge when it is a good fit.
- Distinguish iterative and incremental life cyclesTell apart refining a solution through repeated cycles and delivering it in usable pieces, with examples of each and of when each helps.
- Explain adaptive and agile life cyclesDescribe how agile life cycles plan and deliver in short cycles from a prioritized backlog, compare iteration-based and flow-based work, and correct common myths.
- Describe the predictive life cycle
- Weigh the factors that point toward a predictive, adaptive or hybrid approach, combine approaches where that helps, and adapt the chosen approach to the project and the organization.
- Weigh the factors that guide the choice of approachAssess the product, the project and the organization to decide whether a predictive, adaptive or hybrid approach fits, and explain the decision.
- Combine approaches in a hybrid life cycleDescribe the common patterns for mixing predictive and adaptive work, coordinate the parts, and judge when a hybrid helps.
- Tailor the approach to the project and organizationAdapt the life cycle, processes and level of formality to the size, risk and setting of a project while keeping the essential controls.
- Weigh the factors that guide the choice of approach
- Describe how PRINCE2 organizes a project into management stages with clear roles, and follow its seven processes from start-up to closure.
- Describe how PRINCE2 structures a projectName PRINCE2's integrated elements, principles and practices, explain its levels of management and management stages, and apply management by exception.
- Follow the seven PRINCE2 processes from start-up to closureDescribe the purpose, owner and main outputs of each of PRINCE2's seven processes and trace them through a project.
- Describe how PRINCE2 structures a project
Project Life Cycles study guide
1Describe how a project moves through its life cycle
A project becomes easier to manage when its work has clear sections and decision points. You will connect phases to the deliverables they produce, see why early choices have lasting effects, and distinguish the project's end from the product's continued use. Gate decisions bring these ideas together: the next block of work needs accepted results, a sound business case and people ready to carry it out.
1.1 the project life cycle and its phases
A project life cycle is the series of phases from a project's start to its completion. A phase groups related activities and ends with one or more deliverables. A feasibility report is a deliverable even though it never becomes part of the finished building.
Give the work a useful structure
Phase names and lengths follow the work. Construction might use feasibility, design, construction and handover. Software might use discovery, build and release. These names express four broad parts: starting, organizing and preparing, carrying out the work, and closing. They do not prescribe one universal schedule.
A warehouse project has 6 weeks of feasibility, 10 of design, 30 of construction and 4 of handover. Adding these sequential phases gives 50 weeks. The life cycle supplies that high-level structure. The schedule goes inside it, giving activities, dates and dependencies, such as when the electrical drawings must be ready.
Separate project, product and development
The product life cycle runs from an idea through development, launch, growth, maturity and decline to retirement. The warehouse's construction project ends after handover; operating and maintaining the warehouse continues. Later projects may expand it or replace equipment. A product can therefore be served by several projects.
The development life cycle concerns the phases that create the deliverables. The development approach determines how that work is organized: predictively, adaptively or through a hybrid. Different deliverables in one project can use different approaches, such as a building planned predictively and its software developed through short feedback cycles.
Decide how phases connect
| Relationship | When the next phase starts | Main trade-off |
|---|---|---|
| Sequential | After the previous phase ends | More settled information, potentially a longer schedule |
| Overlapping | Before the previous phase ends | Potential time savings, more risk of rework |
Starting foundations while interior design continues overlaps phases. A later design decision may affect what has already been built. The saved time must be weighed against that exposure to change.
Notice what changes over time
In a typical project, spending and staffing start low, peak during the main work and fall quickly at closure. Risk and uncertainty begin high and decline as the team makes decisions and accepts results. These are typical patterns, so a project's own estimates still matter.
Stakeholders have their greatest ability to shape the result early. Once choices are built into physical work or connected systems, changes become harder and more expensive. Moving a warehouse loading dock during design costs about $2,000 in revised drawings. After the concrete floor is poured, breaking out and repouring it costs about $60,000: 30 times as much.
Early involvement helps reveal needs while changes are affordable. Adaptive work reduces late surprises through small deliveries and early feedback, although changing completed work still has a cost. Phases also create shorter planning horizons, review points and opportunities to authorize the next block of funding.
Key Takeaways
- A phase ends with deliverables, which can include reports and approved designs.
- The life cycle gives the phase structure; the schedule gives activities, dates and dependencies.
- A product can continue in operations and be changed by later projects.
- Overlapping phases can save time while increasing rework risk.
- Early input has more influence; changes usually become more costly as work progresses.
1.2 Using phase gates to decide whether a project continues
A phase gate is a review at a phase end where authorized decision makers decide what happens next. It is also called a stage gate, phase review, decision point, phase exit or kill point. Its purpose is to test whether further commitment is justified.
Prepare evidence for a real decision
The project manager assembles the evidence and recommends a course of action. A sponsor, steering committee or project board decides. These people have authority over the project and stand outside its daily management, so the manager does not approve the project's own continuation.
A gate compares progress with the business case, charter and plans. Three checks answer different questions:
- Exit criteria: Are this phase's deliverables complete and accepted?
- Business justification: Are the expected benefits still worth the updated costs and risks?
- Entry criteria: Are the next phase's plan, people and funding ready?
A finished design answers the first question. It does not, by itself, show that construction remains affordable or that a supplier is ready to start. Agree the criteria before the review so the team knows what evidence to prepare.
Choose the next step
The decision makers can continue, continue with conditions or changes, stay in the current phase or repeat work, or end the project. A gap in testing might require another test before approval. A worthwhile project with a manageable cost increase might continue under tighter spending conditions.
A booking-system replacement originally costs $400,000 and promises $900,000 of benefits over three years. Supplier quotes raise the cost estimate to $520,000. The difference between total expected benefits and total cost falls from $500,000 to $380,000. The board continues with conditions: seek savings and report the updated estimate at the next gate. This decision combines the new evidence with a specific follow-up action.
Keep past spending out of future justification
A sunk cost is spending that has already happened and cannot be recovered. If $150,000 has been spent on the booking system, the remaining cost is $370,000. The continuation decision weighs this remaining spending against benefits still expected, together with risks and alternatives. The statement "We have spent too much to stop now" gives past spending a role it cannot justify.
Stopping can be a useful gate outcome because it releases people and money for better work. Rubber-stamping happens when continuation is approved without a meaningful review against criteria. A project may legitimately pass every gate; what matters is that each review can change or stop it when the evidence calls for that decision.
Hand work on properly
Before passing the gate, close the phase: hand on its deliverables, update documents and record lessons. Learning at each phase end lets the next phase benefit immediately. Adaptive projects also review iterations or releases, and organizations can retain formal gates for decisions such as funding a major release. Short development cycles and formal commitment decisions can operate together.
Key Takeaways
- A gate checks exit criteria, continued justification and next-phase readiness.
- The project manager prepares evidence; an authorized sponsor or board decides.
- Possible decisions include conditions, repeated work and termination as well as continuation.
- Compare future costs, benefits and risks without using sunk costs as a reason to continue.
- An effective gate can change the project; repeated approvals alone do not mean rubber-stamping.
- Close each phase and record lessons before handing work onward.
2Explain the process groups from initiating to closing
Authorizing, planning, doing, checking and finishing work are needed throughout a project. Their timing changes as the project develops, and several can happen together. You will learn the purpose and outputs of the five process groups, then follow them through a pilot and a rollout. This makes it possible to recognize management work by what it achieves, even when the project's phases have unfamiliar names.
2.1 the five process groups
The five process groups organize management work by its purpose: Initiating, Planning, Executing, Monitoring and Controlling, and Closing. PMI's PMBOK Guide uses this familiar grouping; the eighth edition calls the five groupings focus areas. They apply across industries and delivery approaches.
Authorize and plan
Initiating defines a project or phase and obtains permission to start. The project charter formally authorizes the project, names its manager and gives high-level objectives, budget and milestones. A first stakeholder register identifies the people and groups involved.
Planning refines objectives, defines scope and decides how to achieve the result. The project management plan brings together plans for scope, schedule, cost, quality, resources, communication, risk, procurement and stakeholder engagement. Approved scope, schedule and cost baselines provide the reference points for measuring performance.
Planning gains detail through progressive elaboration as information improves. Rolling wave planning is a specific use of this idea: detailed near-term work, higher-level later work. It allows useful preparation without pretending distant activities are already fully understood.
Do the work and keep it under control
Executing carries out the plan. It includes producing results, directing teams, managing quality, engaging stakeholders, communicating, buying goods and services, and carrying out risk responses. It normally consumes the largest share of effort and budget.
Monitoring and Controlling tracks progress, compares results with plans and regulates the work. It also handles changes: analyze a change request's effects on scope, schedule, cost, quality and risk, then obtain approval or rejection from the appropriate authority. Carry out approved changes and update the affected documents.
An approved change alters a baseline only when it affects that baseline. A corrective action that returns work to the existing plan leaves the reference point intact. Quietly changing the baseline to match poor performance would hide the problem.
Finish the commitment
Closing formally completes a project, phase or contract. Confirm acceptance, hand deliverables to the customer or operations, close contracts, release the team, record lessons and archive records. These tasks still apply when the project ends early.
Recognize the purpose in workplace actions
| Intranet upgrade action | Process group |
|---|---|
| Sponsor signs the charter | Initiating |
| Team estimates page-template effort | Planning |
| Developers build templates; communications officer sends an update | Executing |
| Manager compares 420 actual hours with 380 planned and raises a change request | Monitoring and Controlling |
| Operations signs acceptance; team records lessons | Closing |
The overrun is 40 hours, about 10.5% of the planned 380. Measuring it is control work; building the templates is execution. A knowledge area or performance domain, such as scope or risk, describes a subject. A process group describes management purpose. Scope can be defined during planning and checked during monitoring and controlling.
Key Takeaways
- Initiating authorizes; planning defines how to deliver and establishes baselines.
- Executing carries out the work; monitoring and controlling compares and regulates it.
- Closing includes acceptance, handover, records and releasing resources, including early termination.
- Rolling wave planning gives near-term work more detail than distant work.
- An approved action changes a baseline only if the action affects that baseline.
- Process groups describe purpose; knowledge areas and performance domains describe subjects.
2.2 Relate the process groups to phases and to the improvement cycle
A phase is a section of the project life cycle. A process group is a kind of management work. A phase can contain authorization, planning, execution, monitoring and control, and closure. These groups can repeat when the next phase begins.
Follow a pilot into a rollout
A company introduces accounting software through a pilot in one office, followed by rollout to five offices. During the pilot, the sponsor authorizes the work, the team plans the trial, staff install and use the software, and the manager tracks progress and handles issues. The phase closes with accepted results and a pilot report.
At the gate, the board reviews the evidence and approves rollout. Rollout then needs its own authorization and detailed plan, followed by execution, monitoring and control, and closure. Calling the pilot the "planning phase" would hide its installation, checking and acceptance work. Calling rollout the "executing phase" would hide its planning and authorization.
Understand overlap within a phase
The groups have different levels of activity over time. Initiating is concentrated near the start and closing near the end. Planning is strongest early but continues as information changes. Executing usually peaks during the main work. Monitoring and controlling runs alongside the other groups from start to finish.
Suppose a pilot reveals that training takes longer than expected. The manager checks the results against the plan. The team revises the remaining training arrangements while other planned tasks continue. Planning and executing are active together, with monitoring and controlling connecting the actual work to the revised decisions.
See how the outputs connect
A plan guides execution. Measurements from execution allow performance to be checked. An approved change can send work back into planning, while checked and accepted deliverables provide the basis for closure. This is a flow of information and decisions, not five isolated boxes on a calendar.
The relationship resembles plan-do-check-act, or PDCA:
| Improvement activity | Related process group |
|---|---|
| Plan the work | Planning |
| Do the work | Executing |
| Check performance and act on findings | Monitoring and Controlling |
Initiating gives the cycle authority to begin; closing brings the commitment to an orderly end. Monitoring and controlling covers both checking what happened and acting on what needs attention.
Apply the same purposes at a shorter rhythm
An adaptive team may plan a two-week iteration, do the work, review the result and improve its working methods before the next iteration. Project or release initiation and closure still surround those repeated cycles. An iteration review does not have to create a new project charter every time.
The amount of formality follows the setting. A six-week internal project may place its planning in one short document. A large regulated project may need separate approved plans. Both need management work that authorizes, directs, checks and finishes the commitment.
Key Takeaways
- Phases divide the life cycle; process groups describe management purposes within them.
- The groups repeat across phases and overlap in time.
- Plans guide execution, performance checks feed changes, and acceptance supports closure.
- PDCA links planning, execution, and monitoring and controlling.
- Adaptive work repeats these purposes on a shorter rhythm with suitable formality.
3Compare predictive, iterative, incremental and agile life cycles
The way a team builds a result affects when it plans, learns and delivers value. A clear design with expensive late changes calls for different choices from a service that users need to try before they can describe it. You will compare predictive, iterative, incremental and agile work, follow examples of each, and separate the rhythm of development from the timing of releases to users.
3.1 the predictive life cycle
A predictive life cycle sets scope, schedule and cost as early as possible. Its phases occur once and typically follow a sequence. The terms plan-driven, linear and waterfall describe this approach. It relies on knowing enough about the result to plan the route before committing to most of the work.
Establish a reference for delivery
Requirements are defined up front and expected to remain stable. Design, building and testing address the whole planned result in their respective phases. Delivery can happen once at the end or at a few planned points. The main aim is predictable coordination and control of cost.
Approved scope, schedule and cost baselines let the team compare actual performance with agreed expectations. A baseline remains useful because it changes through authorized decisions, not every time reality differs from the plan.
A predictive plan can still gain detail. In rolling wave planning, the next part is detailed while later activities stay at a higher level. The overall scope and delivery route can be settled even when a distant task's precise assignment is still being developed.
Process a change without losing control
A two-story office building has a $3.2 million baseline and a 14-month schedule. In month 9, the client requests an extra glass wall. The team assesses the request: $45,000 more and three additional weeks. The change board approves it, so the cost baseline becomes $3,245,000 and the schedule extends by three weeks.
The request does not become authorized just because the client would like it. Its impact must be understood, the authorized decision recorded, and affected plans updated before the additional work is treated as part of the agreed scope. Predictive means controlled change, not an absence of change.
Judge whether prediction is practical
| Predictive work fits when… | Why this matters |
|---|---|
| Requirements are clear and stable | A detailed plan is less likely to become obsolete |
| Technology is proven | The method and effort are easier to estimate |
| Late changes are costly or impossible | Early agreement prevents expensive rebuilding |
| The result is useful only when complete | Frequent partial release offers little benefit |
| A required approval fixes the design | Work must follow the approved basis |
| A fixed-price contract fixes scope | Suppliers need a clear commitment to price |
A bridge cannot provide its intended service while only partly built. Concrete and steel also make late changes expensive. These features explain the fit more clearly than the industry name alone: design exploration inside a construction project can still use iteration.
Weigh strengths against exposure to late feedback
Predictive work supports clear contracts, supplier coordination, records and visible commitments. Its weakness is that users may encounter the actual result late. If the requirements were misunderstood, much work may already be complete before the problem becomes obvious.
A single-delivery project provides its usable result at the end. Planned staged deliveries can provide earlier value, so predictive work should not be equated with an unavoidable wait for every benefit. The release plan and the certainty of the work both matter when judging the approach.
Key Takeaways
- Predictive work settles scope early and estimates schedule and cost against it.
- Formal change control assesses and authorizes changes before updating affected baselines.
- Stable requirements, proven methods and costly late change support predictive delivery.
- Predictive projects can refine plans and can provide planned staged deliveries.
3.2 Distinguish iterative and incremental life cycles
Iterative and incremental describe different ways of developing a result. Iterative work improves a solution through repeated feedback cycles. Incremental work adds usable parts over a series of deliveries. A project can use either idea or combine them.
Refine the solution through iterations
An iteration is a planned cycle of development and learning. The team creates a version, gets feedback and uses it to improve the next version. Scope is usually set early in an iterative life cycle, while time and cost estimates change as understanding grows. The final result can still be released all at once.
A hospital redesigns a patient-intake form. The first paper mock-up has 22 fields. Nurses identify 7 that are never used, leaving 15. A second, clickable prototype reveals that the field order is confusing. The third round produces the final form, which is released to all wards together.
These are planned learning cycles. A draft gives users something concrete to react to, exposing needs that can be hard to express in an abstract discussion.
Add value through increments
An increment is a usable addition to the product. A new HR system delivers time-off requests in month 3, expense claims in month 6 and performance reviews in month 9. Staff begin receiving value at month 3, although the planned system is complete only at month 9.
The first release must work for its users. A database with no screens for entering required data is a technical component, but it is not a usable service increment for those staff. Usability is what connects an increment to early value.
Compare the central questions
| Feature | Iterative | Incremental |
|---|---|---|
| Main question | How can this solution improve? | What useful part can users receive next? |
| What changes | The solution is refined | Usable functionality grows |
| Main aim | Get the solution right | Deliver value sooner |
| Final release | Can be one release at the end | Follows earlier usable deliveries |
Match the idea to the uncertainty
Iterative development helps when the product is new or complex and feedback makes its requirements clearer. Incremental delivery helps when the result splits into independently useful parts and users benefit before the whole scope is finished.
Agile combines both ideas. It releases usable additions and uses feedback to refine what is built and what comes next.
Key Takeaways
- Iterative work refines a solution through planned feedback cycles.
- Incremental work adds usable functionality before the whole product is complete.
- An iterative project can release only at the end.
- A technical component is not a usable increment unless it serves users on its own.
- Agile combines iterative learning with incremental delivery.
3.3 adaptive and agile life cycles
An adaptive, or agile, life cycle is both iterative and incremental. The team expects requirements to change, plans continuously and delivers small usable results for customer feedback. In iteration-based work, detailed scope is agreed just before each iteration.
Use values to guide choices
The Agile Manifesto began in software in 2001. It values individuals and interactions over processes and tools; working software over comprehensive documentation; customer collaboration over contract negotiation; and responding to change over following a plan. The items on the right still have value. Twelve principles support the four values.
The practical meaning is to keep plans, tools, agreements and documents useful to delivery. Agile teams still plan and document their work. Similar short feedback cycles can help product design or marketing, as well as software.
Order the next work by value
A backlog is an ordered list of features and tasks. A customer representative maintains its order, with the highest-value work at the top. The team selects the next items from that order. New ideas enter the backlog and are ranked against existing work, so a new request does not silently become an extra commitment.
| Working rhythm | How work starts | How the amount of active work is controlled |
|---|---|---|
| Iteration-based | Select work for a fixed-length timebox, often 1–4 weeks | Agree a small set of finished features for the cycle |
| Flow-based | Pull the next item when capacity becomes available | Limit work in progress |
Scrum is a well-known iteration-based framework. A Kanban board often helps make flow and work in progress visible. Flow-based work does not require fixed iterations.
Work within time and cost constraints
Predictive projects fix scope and estimate time and cost. Agile projects often keep a stable team and fixed working periods, allowing lower-priority scope to move as learning changes priorities. A release date may be a fixed constraint or a forecast. The iteration's fixed length does not make every forecast release date fixed.
Five people work in two-week iterations toward a release in 12 weeks: six iterations. At 80 hours per person and $70 per hour, an iteration costs $28,000 and six cost $168,000. With about six backlog items completed per iteration, about 36 of 40 items are ready. The four lowest-ranked items wait for a later release. This is a forecast from observed pace, not a guarantee that every item takes equal effort.
Separate building rhythm from release rhythm
Delivery cadence means when usable results reach users: once at the end, at several planned points, regularly or continuously. An iteration-based team can release within an iteration, at its end or after several iterations. A flow-based team can also choose selected release dates.
Agile fits uncertainty, changing needs, usable small pieces and customers available for regular feedback. Small teams in close contact support that learning. It fits less well when no part can be tested early or every detail must be approved before work starts. Fixed deadlines and necessary documentation can still be part of agile delivery.
Key Takeaways
- Adaptive work combines iterative learning and incremental value.
- The Agile Manifesto values people, working results, collaboration and response to change.
- A backlog ranks work; new ideas must compete for priority.
- Iteration-based work uses fixed timeboxes; flow-based work pulls within capacity limits.
- Time and cost constraints can hold while lower-priority scope changes.
- Release cadence is a separate choice from the development rhythm.
- Agile still requires planning and useful documentation.
4Choose and tailor a delivery approach
Choosing an approach starts with the work: what is known, what can change and when people need usable results. The organization also brings contracts, policies and ways of making decisions. You will weigh these factors, combine approaches where different deliverables need different treatment, and scale the controls to the project. The aim is a practical way of working whose decisions remain clear as conditions change.
4.1 Weigh the factors that guide the choice of approach
Choose a development approach for the product, project and organization. Different deliverables can need different approaches within the same project. The useful question is what helps this work succeed, not which method is newest.
Inspect the product
Start with agreement about what to build and confidence about how to build it. Clear requirements and proven technology support predictive planning. Unclear needs or unfamiliar technology call for feedback and experiments. If both are highly uncertain, small experiments establish enough knowledge to plan sensibly.
Change cost and the ability to deliver usable parts also matter. Replacing words on an unbuilt screen is easier than moving a finished concrete structure. A service that offers useful features separately can provide early value; a result that works only when complete offers fewer release options.
Safety and regulation affect required evidence and approvals. Find out what a real requirement demands. Compliance checks can be built into adaptive development. Add a fixed approval or sequence where it is actually required.
Inspect the project and organization
| Factor | Questions to ask |
|---|---|
| Feedback | Are users available often enough to review results? |
| Value timing | Is there pressure to provide useful parts early? |
| Funding | Is money released all at once or in stages? |
| Contract | Does it fix price and scope, or pay for team time? |
| Culture and structure | Who decides, and how much autonomy do teams have? |
| Experience and location | Does the team know the approach, and how will it coordinate? |
A fixed price for fixed scope supports prediction. Paying for a team's time supports changing priorities within that capacity. Agile work is most natural for small teams in close contact; large or distributed teams need added coordination. An unfamiliar approach also requires a realistic plan for support and learning.
Use scores to support discussion
A team rates six factors from 1, pointing toward predictive, to 5, pointing toward adaptive. A customer app scores 4 for requirements uncertainty, 5 for ease of change, 5 for usable parts, 4 for customer availability, 2 for regulation and 3 for agile experience. The total is 23 and the average about 3.83, suggesting adaptive work.
A warehouse scores 1, 1, 2, 2, 2 and 3 on the same factors. Its total is 11, averaging about 1.83, suggesting predictive work. The numbers organize the conversation; they do not calculate the correct method. Check each rating's meaning and direction before comparing results.
Explain and revisit the decision
One critical factor can outweigh an average. In the app, the low regulation score prompts investigation of data-protection evidence and approvals. It does not settle the delivery method by itself. The team might use adaptive development with a formal launch approval, producing a useful hybrid.
Record why the approach fits and revisit the choice when conditions change. Industry alone is insufficient: construction designs can be refined iteratively, and a well-specified data migration can be predictive. An organization benefits from selecting by the work instead of imposing one method on every project.
Key Takeaways
- Choose using product, project and organizational factors.
- Check certainty about both requirements and technology.
- Feedback, contracts, funding and team coordination affect the fit.
- Ratings support discussion; a critical constraint can outweigh the average.
- Record the reasons and revisit them when conditions change.
4.2 Combine approaches in a hybrid life cycle
A hybrid life cycle combines predictive and adaptive elements in one project. Use stable planning where the work is well understood or expensive to change, and feedback cycles where learning and flexibility add value. The mix follows the deliverables and constraints.
Recognize four useful patterns
| Pattern | How it works | Example |
|---|---|---|
| One after the other | One approach prepares for another | Agile discovery followed by a predictive build |
| Side by side | Different streams use different approaches together | Building fit-out beside an iterative booking app |
| Mainly predictive | An adaptive part sits inside a larger predictive project | Software iterations within a construction project |
| Mainly agile | A predictive part supports mostly adaptive delivery | An agile product with fixed external certification |
These patterns can overlap in practice. A hybrid does not have to be half predictive and half agile. Each element should solve a real need, since unexplained mixing adds complexity.
Link parallel streams
A clinic must open in 18 months. Its building fit-out uses predictive design, construction and inspection phases, with gates between them. Its patient-booking app uses two-week iterations. Both streams meet at a shared milestone in month 15: a go-live readiness test on the clinic network and front desk.
The app team cannot judge readiness only by completed features. It needs the network and workplace available for that shared test. The construction stream needs to know what the software requires. The milestone connects those dependencies before the opening date.
Use learning before a larger commitment
A company tests self-service portal prototypes with customers for 6 weeks, using three two-week iterations. It then builds the agreed design through a 20-week predictive phase. The sequential work takes 26 weeks. Early learning reduces requirement uncertainty before the larger commitment of money and effort.
This pattern differs from parallel streams: the later build uses what discovery has learned. Its handover needs a clear agreed design, so the second part does not begin with unresolved expectations about scope.
Give both parts a shared control structure
Coordinate the project through shared milestones and gates, a schedule linking streams at milestone level, one risk and issue log, clear decision rights and reports that both groups understand. "Features finished" may need translation into "percentage of release scope complete" for a combined progress report. Agree what each measure means so equal-looking numbers do not hide different ideas of completion.
Hybrid delivery provides predictability where necessary and flexibility where helpful. Its risks concentrate at the interfaces: incompatible handover dates, different working cultures and duplicate reporting. A shared decision about readiness is stronger than two separate teams declaring their own work done without checking whether the combined service works.
Key Takeaways
- Hybrid combines predictive and adaptive elements for a reason.
- Approaches can run sequentially, in parallel, or as a smaller part of another approach.
- Shared milestones, decision rights and common risk reporting coordinate streams.
- The main risks lie at interfaces between approaches and deliverables.
4.3 Tailor the approach to the project and organization
Tailoring deliberately adapts the approach, governance and processes to a project and its setting. Governance means how authority and oversight are arranged. A small internal improvement needs clear control, but the same paperwork as a large regulated project could consume time without helping decisions.
Work from the organization to the project
A practical sequence has four steps:
- Choose an initial development approach.
- Adapt it to organizational standards, mandatory policies and governance.
- Adapt it to the project's size, risk, duration, team and stakeholders.
- Improve it during delivery using reviews and lessons.
The organization may require an approval regardless of project size. The team can still choose a simpler way to gather the necessary evidence. Project-specific tailoring operates within those mandatory requirements.
Scale formality to the consequences
A 6-week internal project with 3 people and a $20,000 budget might use a one-page charter and plan, a 15-minute weekly check-in and one final review. Its small team can keep decisions visible with a light process.
A 2-year project with 80 people and a $12 million budget needs fuller planning, a monthly steering committee, a formal change board and gates between phases. More people, larger commitments and complex dependencies make informal agreements harder to coordinate and verify.
| What can change | What the choice needs to achieve |
|---|---|
| Plans and documentation | Enough detail to guide work and support decisions |
| Approvals and gates | Authority proportionate to the commitment and risk |
| Reporting and meetings | Timely information for the people who must act |
| Processes, tools and techniques | A practical way to manage the actual work |
| Life cycle and approach | A suitable route from uncertainty to accepted results |
Formality grows with size, risk, complexity and regulation. A small project with serious safety consequences can need more control than its headcount suggests.
Retain essential control
Every project still needs clear objectives, authorization from someone with authority, one accountable person, progress tracking, change handling and proper closure. Tailoring changes how formally these are done. Removing the only approval or leaving changes untracked would remove control instead of adapting it.
Tailoring can add requirements. A laboratory system used in medicine production needs the validation records and sign-offs demanded by regulators. Its screens can still be developed in short cycles with scientists. Different parts of the method support different needs.
Make the working agreement visible
The project manager works with the team, sponsor and any project office to decide the tailored arrangements. Record them, for example in the project management plan, so everyone knows the reporting rhythm, required documents and decision authority.
Revisit those arrangements as evidence develops. If weekly reports arrive too late to reveal problems, increase their frequency or change what they show. If two reports serve the same decision, combine them. Lessons become useful when they change a process that is not working.
Key Takeaways
- Tailoring adapts approach, governance, processes and formality.
- Choose an approach, fit organizational requirements, fit the project, then improve.
- Size, risk, complexity and regulation determine suitable formality.
- Keep objectives, authorization, accountability, tracking, change handling and closure.
- Tailoring can add controls as well as simplify them.
- Agree, record and revisit the tailored way of working.
5Outline the PRINCE2 method and its processes
PRINCE2 connects business justification, clear responsibilities and decisions about the next stage of work. Its project board directs the project while the project manager and teams handle management and delivery. You will follow that division of work through the seven processes, see how stage authorization controls commitment, and use tolerances to recognize when a forecast needs a board decision.
5.1 how PRINCE2 structures a project
PRINCE2, short for PRojects IN Controlled Environments, is a process-based project management method. It began in UK government and is now owned by PeopleCert. PRINCE2 7 was published in 2023 and is used in the UK public sector and many other settings.
Connect the method's elements
PRINCE2 7 combines five elements: principles, practices, processes, project context and people at the center. Context concerns tailoring to the setting; people make the method work through relationships and decisions.
Its seven principles are:
- Ensure continued business justification.
- Learn from experience.
- Define roles, responsibilities and relationships.
- Manage by stages.
- Manage by exception.
- Focus on products.
- Tailor to suit the project.
All seven principles must apply for a project to use PRINCE2. They guide decisions throughout the method. For example, continued justification means checking that the project remains worthwhile, not relying forever on the original approval.
The seven practices are business case, organizing, plans, quality, risk, issues and progress. They are aspects managed throughout the project. Earlier versions called these aspects themes; the issues practice replaces the former change theme. Principles guide behavior, practices identify continuing management concerns, and processes arrange who does what and when.
Distinguish directing, managing and delivering
| Level | Main role | Responsibility |
|---|---|---|
| Directing | Project board | Direction and key authorizations |
| Managing | Project manager | Day-to-day management |
| Delivering | Team managers and teams | Producing and checking products |
The board brings together the executive, accountable for the project and business case; the senior user, representing those who use the products; and the senior supplier, representing those who build them. The commissioning organization above the project sets overall limits.
Authorize one management stage at a time
A management stage is an authorized section of the project, ending at a decision point. Every PRINCE2 project has at least two: initiation and at least one further stage. The board commits resources stage by stage, using new evidence before approving more work.
Management stages provide a control layer. They need not match technical phases such as design and build: a management stage can contain parts of several technical phases. Products inside a stage can be developed linearly or through agile iterations. PRINCE2 does not require waterfall development.
Delegate within tolerances
Manage by exception means setting permitted deviations, called tolerances, and delegating daily decisions within them. If a forecast exceeds a tolerance, the manager escalates to the board before the breach becomes an accomplished fact. The board also reviews regular reports and makes planned authorizations; it has work beyond handling exceptions.
A stage budget is $200,000 with a ±10% tolerance. Ten percent is $20,000, giving an allowed range from $180,000 to $220,000. A $228,000 forecast is $8,000 above the upper tolerance, requiring escalation. The manager cannot silently expand the authorized range.
Tolerance areas are time, cost, quality, scope, benefits, risk and, in PRINCE2 7, sustainability. Tailoring determines suitable formality, so the method need not create heavy paperwork for every project.
PRINCE2 prescribes processes, roles, responsibilities and management products. PMI's PMBOK Guide is a body of good practice that organizations can draw on to develop their way of working. A method and a body of knowledge can support the same project.
Key Takeaways
- PRINCE2 7 integrates principles, practices, processes, context and people.
- Its seven principles all apply; practices are continuing management concerns.
- The board directs, the project manager manages, and teams deliver.
- The board represents business, user and supplier interests.
- At least two management stages provide stage-by-stage authorization.
- Management stages can contain linear or agile technical work.
- Escalate forecast tolerance breaches; the board also makes planned decisions.
- PRINCE2 is a method; the PMBOK Guide is a body of good practice.
5.2 Follow the seven PRINCE2 processes from start-up to closure
PRINCE2's seven processes describe management from the initial request through closure. They are not seven consecutive technical phases: directing spans the project, while stage control and product delivery run together.
Establish whether and how to begin
Starting up a project happens before the project formally begins. A project mandate, the request to start, triggers it. The executive and project manager are appointed, previous lessons gathered, and the management team designed. An outline business case, project brief, chosen approach and initiation stage plan establish whether the idea is worthwhile enough to initiate.
Directing a project belongs to the project board. From the end of start-up through closure, the board authorizes initiation, the project, each stage or exception plan, and closure. It gives direction when asked. These are governance decisions, not daily supervision of teams.
Initiating a project creates a firm basis for delivery. It establishes management approaches for risk, quality, issues, communication and other concerns; sets controls; creates the project plan; refines the business case; and tailors the method. The project initiation documentation, or PID, records the agreement between the board and manager.
Manage delivery at two levels
Controlling a stage is the project manager's daily work. The manager authorizes work packages, monitors progress, sends highlight reports to the board, examines risks and issues, takes corrective action within tolerance and escalates forecast breaches.
Managing product delivery is the team manager's process. The team accepts a work package, builds and quality-checks its products, reports progress through checkpoint reports and returns the finished package. The team can use the delivery method that suits the work, including agile methods.
Prepare the next decision or finish
Managing a stage boundary gives the board an end stage report, next stage plan, updated project plan and updated business case. It runs at each stage end except the final one. It also prepares an exception plan when forecast tolerance breaches require a replacement plan. The board authorizes that plan through directing a project.
Closing a project confirms product acceptance, hands results over, evaluates performance against the PID, records lessons in an end project report and recommends closure to the board. It also applies to premature closure when the project loses justification. Benefits that appear after the products enter use are measured after closure according to the agreed arrangements.
Trace a three-stage project
A library-system replacement begins with a director's mandate. Start-up produces a brief in two weeks, then the board authorizes initiation. Stage 1 creates the PID. Stage 2 configures the system and tests migration; stage 3 rolls it out to 12 branches.
Managing a stage boundary runs twice: after initiation and after stage 2. The final stage leads to closing a project. Throughout, the board's directing process supplies the authorizations. Controlling a stage and managing product delivery connect daily management with team work in the delivery stages.
The five process groups provide another view of these purposes. Start-up and initiation cover authorization and much planning; stage control covers monitoring, control and direction of execution; product delivery carries out work; boundaries report and plan; closure completes the commitment.
Key Takeaways
- Start-up tests viability and prepares the brief; initiation establishes the PID.
- Directing holds board authorizations across the project.
- The manager controls stages; team managers manage product delivery.
- Stage-boundary work prepares reports and plans for board decisions.
- Closure confirms acceptance, handover, evaluation and lessons, including early closure.
- Benefits can be measured after closure according to the agreed plan.
Project Life Cycles examples
1Take a project through phases and gates
11 steps
- 1IntroductionSeparate work from commitment
A project needs both a structure for doing work and decisions about further commitment. Its life cycle groups related work into phases; a gate checks whether the next phase should proceed.
Follow a distribution-center project to see how outputs, changing costs and future value shape these decisions. The project can finish while the center continues operating.
- 2ExplanationName the phase and its output
A phase groups related activities and ends with deliverables. Feasibility can end with a report, design with accepted drawings, and construction with a completed facility. A deliverable does not have to be part of the final physical result.
The life cycle provides these large sections. A schedule adds the activities, dates and dependencies needed to carry them out.
- 3ExampleWork out the high-level duration
The center plans 5 weeks of feasibility, 9 of design, 24 of construction and 3 of handover, with each phase waiting for the previous one to finish.
Add the sequential durations: 5 plus 9 gives 14 weeks; adding 24 gives 38; adding 3 gives 41 weeks. This is the phase-level duration. Detailed tasks and dates still belong in the schedule inside those phases.
- 4Key InsightLook at when decisions become costly
Changing the loading area on a drawing requires design work. Changing it after the floor is built can require demolition and rebuilding. Stakeholders therefore have more influence while choices are still open and inexpensive to revise.
Spending and staffing usually peak during the main work. Uncertainty typically falls as decisions are made and deliverables are accepted, while late changes become more expensive.
- 5ChallengeWhat changes if phases overlap?
The team starts buying equipment before the design phase is complete. What phase relationship is this, and what trade-off should the manager explain?
---reveal---
The phases overlap. Earlier procurement can shorten the schedule, but unresolved design decisions can make equipment unsuitable and cause rework. The 41-week sequential total no longer describes the revised timing without checking the actual overlap and dependencies.
- 6ExplanationPrepare three different gate checks
At the design gate, the manager prepares evidence for the sponsor or board. Check accepted deliverables against exit criteria, the updated business case for continued value, and the plan, people and funding against next-phase entry criteria.
These checks are separate. Accepted drawings do not establish construction readiness or prove that the completed center is still worth its remaining cost.
- 7ExampleAllow more than go or stop
The board can continue, continue with conditions or changes, keep the project in its current phase or repeat work, or stop it. Suppose the design is accepted but a required staffing arrangement is incomplete.
The board can require that gap to be resolved before the next commitment proceeds. The manager recommends a response; someone with authority outside daily management makes the continuation decision.
- 8ChallengeCompare the costs that can still change
The center has spent $120,000 that cannot be recovered. Completion requires another $360,000, and future benefits are estimated at $310,000 with no other benefits or exit cost. Does past spending justify continuation?
---reveal---
No. Future benefits are $50,000 below remaining cost. The $120,000 cannot be changed by continuing or stopping, so it does not repair that shortfall. Using it as a reason to continue is the sunk cost trap.
- 9TipLeave a useful phase behind
Before the project passes a gate, hand on deliverables, update documents and record lessons so the next phase can use them. A lesson about missing design reviewers can improve the next review immediately.
Meaningful review matters even if every gate approves. Rubber-stamping means approval without examining evidence against criteria; a gate must be able to change or stop the project.
- 10ChallengeConnect handover and the product
Construction has finished, but acceptance evidence is missing. The sponsor says, "The product will operate for years, so keep the project open until it retires." What two distinctions should guide the decision?
---reveal---
Complete acceptance and proper handover before closing the project. The product life cycle then continues in operations; the project does not need to remain open for the product's entire useful life. Physical completion alone has not supplied the missing acceptance evidence.
- 11RecapCheck the next commitment
Use the phase structure to identify the output being completed and the work that follows. At each gate, examine accepted results, continued value and readiness; keep past unrecoverable spending out of future justification.
The useful endpoint is an accepted, orderly handover of the project's result. Operations and later improvement projects can continue serving the product after this project closes.
2Recognize management work inside each phase
10 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionTwo ways to organize the same work
- 2ExplanationEstablish permission and a reference plan
- 3ExampleIdentify doing and checking
- 4ChallengeDoes approval always move the baseline?
- 5ExplanationFinish work formally
- 6ConnectionRepeat purposes in the next phase
- 7ChallengeClassify the response to pilot findings
- 8AnalogyConnect the improvement cycle
- 9ChallengeFix the proposed phase plan
- 10RecapAsk what the action achieves
3Compare planning, learning and usable delivery
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionAsk when the team learns and delivers
- 2ExplanationPredict from a stable scope
- 3ExampleTrace an authorized change
- 4ChallengeChoose from the cost of late change
- 5ExplanationImprove the same solution
- 6ExampleAdd usable parts
- 7ChallengeDistinguish drafts from usable additions
- 8ExplanationCombine feedback with value
- 9ExamplePlan within a stable capacity
- 10Key InsightChoose the working rhythm
- 11ChallengeHandle a new request
- 12ConnectionSet release cadence separately
- 13ChallengeInterpret a mixed delivery description
- 14RecapUse three discriminating questions
4Choose and tailor an approach that fits
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionStart with the work
- 2ExplanationInspect uncertainty and constraints
- 3ChallengeLook beyond one average
- 4ExplanationCombine for a clear reason
- 5ExampleMake the interface visible
- 6ChallengeFind the real readiness problem
- 7ExplanationScale the working agreement
- 8ExampleMatch formality to risk
- 9ChallengeRespond to an ineffective report
- 10TipInvestigate the actual compliance need
- 11ChallengeKeep learning and authority together
- 12RecapMake the choice explainable
5Follow PRINCE2 decisions from mandate to closure
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionFollow who decides and who delivers
- 2ExplanationPlace the elements around people
- 3ExplanationSeparate the three management levels
- 4ExampleCalculate the delegated range
- 5ChallengeDoes the board only handle exceptions?
- 6ExplanationStart with a worthwhile proposal
- 7ExampleBuild the agreement in initiation
- 8ChallengeChoose the agreement for authorization
- 9ConnectionConnect management to team delivery
- 10ExamplePrepare the next commitment
- 11Key InsightClose even when value continues
- 12ChallengeSeparate stages from technical phases
- 13ChallengeHandle a forecast that needs a new plan
- 14RecapTrace the responsibility at each decision
Project Life Cycles practice questions
Set 1: Recognize life cycles and management work10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Apply gates, delivery choices and PRINCE210 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Resolve competing project demands10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Judge complex life-cycle decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Adaptive life cycle
Agile Manifesto
B
Backlog
Baseline
Business case
C
Change control
Change request
Checkpoint report
Closing
Closing a project
Constraint
Controlling a stage
D
Decision rights
Deliverable
Delivery cadence
Development life cycle
Directing a project
E
Entry criteria
Exception plan
Executing
Executive
Exit criteria
F
Fixed-scope contract
Flow-based agile
Formality
G
Governance
H
Highlight report
Hybrid life cycle
I
Increment
Incremental life cycle
Initiating
Initiating a project
Iteration
Iterative life cycle
L
Lessons learned
M
Management by exception
Management stage
Managing a stage boundary
Managing product delivery
Monitoring and controlling
O
Overlapping phase relationship
P
Phase
Phase gate
Plan-do-check-act
Planning
Predictive life cycle
PRINCE2
Process group
Product life cycle
Progressive elaboration
Project board
Project brief
Project charter
Project initiation documentation
Project life cycle
Project management plan
Project mandate
Prototype
R
Requirements uncertainty
Rolling wave planning
Rubber-stamping
S
Senior supplier
Senior user
Sequential phase relationship
Shared milestone
Stakeholder register
Starting up a project
Suitability assessment
Sunk cost
T
Tailoring
Technology uncertainty
Timebox
Tolerance
W
Waterfall
Work in progress
Work package