Project Risk Management

Learn how to spot what could go wrong on a project, and what could go better than planned, before it happens. You will tell risks apart from issues, assumptions and constraints, identify risks with proven techniques and write them as clear cause, event and effect statements. You will rate and rank them with a probability and impact matrix, choose responses for threats and opportunities, and keep a risk register with named owners up to date until the project closes.

BeginnerLesson 7 of 9 in Project Management Foundations Course

What you will learn

  1. Explain what a project risk is, tell risks apart from issues, assumptions and constraints, and describe how a project sets up its risk management.
    • Tell risks apart from issues
      Define risk as uncertainty that matters to project objectives, recognize threats and opportunities, and separate risks from issues that have already happened.
    • Find the risks behind assumptions and constraints
      Define assumptions and constraints, keep them in an assumption log, and test each assumption to reveal the risks it hides.
    • Plan how the project will manage risk
      Describe the steps of the risk management cycle, the decisions recorded in a risk management plan, and how risk appetite and thresholds set the limits the project works to.
  2. Use a range of techniques to find threats and opportunities, and write each risk as a clear statement of cause, event and effect.
    • Use techniques to identify risks
      Choose and run identification techniques that find threats and opportunities from many angles, and keep identifying risks throughout the project.
    • Write clear risk statements and group them
      Describe each risk by its cause, uncertain event and effect, and group risks by category to spot clusters and gaps.
  3. Rate risks on agreed scales, rank them with a probability and impact matrix, and refine the ranking with urgency and escalation rules so that effort goes where it matters most.
    • Rate probability and impact on agreed scales
      Use the project's scales to rate how likely each risk is and how strongly it would affect each objective, and judge how reliable each rating is.
    • Rank risks with a probability and impact matrix
      Combine probability and impact ratings in a matrix, read the priority bands, and apply the project's rules for threats and opportunities.
    • Weigh urgency and decide what to escalate
      Refine priorities with proximity, urgency and other factors, judge the project's overall risk, and decide which risks belong above the project.
  4. Choose fitting responses for threats and opportunities, prepare contingency plans with clear triggers, and check what risk remains or newly appears.
    • Choose responses to threats
      Select among avoid, mitigate, transfer, accept and escalate, and match each response to the threat it is meant to handle.
    • Choose responses to opportunities
      Use exploit, enhance, share, accept and escalate to make positive risks more likely or more valuable.
    • Prepare contingency plans and check what remains
      Set triggers, write contingency and fallback plans, build responses into the plan, and identify the residual and secondary risks of each response.
  5. Keep a complete and current risk register, give every risk a responsible owner, and monitor risks so that responses keep working as the project moves on.
    • Build and maintain a risk register
      Record each risk with the fields a team needs, write a complete entry, and keep the register current from the first risk to project closure.
    • Assign risk owners and action owners
      Choose the right owner for each risk, separate owning a risk from carrying out its actions, and know who decides when a risk goes beyond the project.
    • Monitor risks and keep responses working
      Review risks regularly, watch triggers, track response actions, and update, close or convert risks into issues as the project moves on.

Project Risk Management study guide

5 chapters

1

Understand project risk and what shapes it

Projects depend on events that nobody can fully control: deliveries, approvals, weather, and people. Some uncertainty threatens the plan; some offers a benefit. Before choosing a response, you need to know what is still uncertain, what has already happened, and what the plan takes for granted. A clear risk approach then gives everyone shared rules for deciding which uncertainties deserve attention and who can authorize action.

1.1 Tell risks apart from issues

A risk deserves attention because something uncertain could change a project objective. That objective might concern scope, schedule, cost, quality, or the benefits people expect. Ask two questions: could the event happen, and would it matter if it did?

See both directions of risk

A threat could harm an objective. An opportunity could help one. In a 12-week office move with a budget of $250,000 and 60 staff, late desk delivery is a threat to readiness. A possible 10% discount on a large furniture order is an opportunity to spend less. Both belong in risk management: one needs protection, the other may deserve effort to capture it.

A vague concern such as "the weather" does not explain a risk. "Heavy snow on the moving weekend may stop the trucks and delay the move by a week" identifies the uncertain event and its effect. A certainty such as "the software needs testing" belongs in the work plan.

Decide whether it has happened
StatementClassificationReason
"The city may close the street during move week."ThreatAccess might be lost.
"The movers’ quote is $4,000 over its budget line."IssueThe cost problem exists now.
"The landlord may allow an early exit from the old lease."OpportunityA possible agreement could save money.
"The new office must pass a fire inspection."RequirementIt states a condition the project must meet.

An issue is a current condition or an event that has happened and needs action. "The lead developer may resign before launch" is a risk; "the lead developer has resigned" is an issue. The possible failure of the fire inspection is a risk, even though the inspection requirement itself is certain.

Move from prevention to action

Keep uncertain events in the risk register and current problems in the issue log. If a recorded risk occurs, carry out its planned response, log the issue, and update the risk’s status to show that it occurred. Keep the link between the records so the history remains clear.

Resolve an issue through a short sequence:

  1. Capture it in the issue log.
  2. Assess its effect and urgency.
  3. Decide on action; escalate if the decision exceeds the project manager’s authority.
  4. Carry out the action.
  5. Check the result, close the issue, and record useful lessons.

An issue can create a new risk. After the developer resigns, the departure is certain, but whether a replacement will learn the system before launch remains uncertain.

Look beyond single entries

Individual risks are the separate uncertainties recorded in the register. Overall project risk concerns all uncertainty affecting the project, including how risks combine. Several modest threats to the same deadline can make the overall delivery date doubtful.

Methods use "issue" with different breadth. PMI includes current conditions affecting objectives; APM emphasizes problems breaching or about to breach delegated tolerances and needing sponsor support. PRINCE2 also includes change requests and work that misses its specification. The practical distinction remains useful: current matters need action now; uncertain events need forward planning.

Key Takeaways

  • A project risk combines uncertainty with an effect on an objective.
  • Threats can harm objectives; opportunities can improve them.
  • An occurred risk is handled as an issue, with both records updated.
  • Overall project risk includes how separate uncertainties combine.

1.2 Find the risks behind assumptions and constraints

Every plan rests on things believed to be true and limits that must be respected. Writing them down makes it easier to see where the plan could break and which responses are possible.

Separate a belief from a limit

An assumption is something treated as true for planning without proof. "The landlord will hand over the keys at the start of week 4" lets the team schedule work, but the handover still needs checking.

A constraint is a limit the project must work within. In the office move, the old lease ends at the end of week 12, the budget is $250,000, and staff must move over a weekend to keep the business running. These limits restrict the plan. A fixed deadline leaves less room to absorb a delay and may rule out a response that simply moves the finish date.

High-level assumptions and constraints appear in the charter and scope statement. An assumption log tracks the assumptions in detail: the statement, owner, date raised, status, and follow-up action. Status might be open, confirmed, or proven false. Some teams also record constraints there.

Test what the plan depends on

Assumption analysis asks how likely an assumption is to be wrong and what would change if it were. Consider both harm and benefit. If the team assumes a permit is needed but learns that it is unnecessary, work could start sooner.

For the office move, work through the cabling assumption:

  1. State the belief: "The contractor will finish the network cabling by the end of week 8."
  2. Examine the evidence: the contractor missed deadlines on two earlier jobs.
  3. Trace the dependency: staff need a network to work in the new office.
  4. Describe the risk: "Because the contractor has missed earlier deadlines, the cabling may finish after week 8, delaying the move and possibly pushing it beyond the old lease in week 12."
  5. Enter the risk in the register and link it to the assumption that needs checking.

The belief is both uncertain and important, so it deserves a risk entry. The assumption that staff will keep their current monitors is much less important in this example and stays in the assumption log.

Find assumptions hidden inside estimates

An estimate may quietly depend on a specialist working full time or on an approval taking one week. Ask, "What must be true for this estimate to hold?" Check the answer with the people who supply the resource or make the decision. An estimate based on a person’s availability is weak if their manager has not agreed to release them.

A constraint is certain as a planning limit. A possible change to it is a separate uncertainty: "The board may cut the budget by 10% at the mid-year review." Record that possible decision as a risk, with its effect on the work.

Revisit the log as evidence arrives. A confirmed assumption becomes a fact. A false assumption may require replanning or may already be an issue if it is affecting the project. Keeping an old assumption marked open after it has been disproved hides the need for action.

Key Takeaways

  • An assumption is an unproved planning belief; a constraint is a limit.
  • Test how uncertain and how important each assumption is.
  • A false assumption can reveal a threat or an opportunity.
  • Ask what must be true for important estimates to hold.
  • Update the assumption log when evidence confirms or disproves a belief.

1.3 Plan how the project will manage risk

Risk management helps a team make decisions with uncertainty in view. Its aim is to reduce threats and make the most of opportunities so the project is more likely to meet its objectives. Some uncertainty remains because a project creates something new.

Set up a repeating cycle

The work follows a cycle: plan the approach, identify risks, analyze them, plan responses, carry out those responses, and monitor results. Monitoring can uncover new risks or show that a rating needs to change, so the team returns to earlier steps throughout the project.

Communication runs through the cycle. A well-rated risk has little value if the person able to act never hears about it. Short review cycles in agile projects serve the same purpose: feedback on small increments reduces the risk of building the wrong thing, and stand-ups, reviews, and retrospectives reveal new uncertainty. A spike is a short, time-boxed experiment that explores technical uncertainty early; resulting response work goes into the backlog.

Agree how decisions will be made

The risk management plan records the project’s working rules. It is called a risk management approach in PRINCE2. It sets out:

  • Methods, tools, categories, and the format of the register.
  • Probability and impact definitions, the matrix, and priority rules.
  • Roles, review frequency, reporting, and escalation routes.
  • The time and budget allowed for risk work.
  • Appetite and measurable thresholds for decisions.

Scale this approach to the project. A two-week internal job may need one page and a short register. A large infrastructure project needs a more formal approach, regular reviews, and independent checks. The work needed to manage risk should fit the decisions at stake.

Turn appetite into limits

Risk appetite is the amount of uncertainty a person or organization is willing to accept in pursuit of a reward. "Low appetite for safety and legal risk; moderate appetite for schedule risk on internal projects" gives a broad direction.

A risk threshold, also called a tolerance in some methods, turns that direction into a measurable limit. For the office move, the sponsor might require any risk that could delay the move by more than 10 working days or add more than $25,000 to be reported within two working days.

Apply each part of that rule. A possible $30,000 extra cost crosses the cost limit even if the schedule effect is small. A possible 12-working-day delay crosses the time limit even if the response is inexpensive. The word "or" means either breach is enough.

Give the rules clear owners

The sponsor sets appetite, approves thresholds, and decides on escalated risks. The project manager leads the process and keeps the register. Team members and stakeholders identify risks and take on agreed ownership and actions.

People’s personal comfort with uncertainty differs. Optimism may make one person dismiss a threat that another person rates highly. Written scales and thresholds give them a shared basis for discussing evidence and authority instead of treating confidence as a rating method.

Key Takeaways

  • Plan, identify, analyze, respond, implement, and monitor throughout the project.
  • The risk management plan sets shared methods, responsibilities, and decision rules.
  • Appetite gives broad direction; thresholds make limits measurable.
  • Agile feedback and spikes help reduce uncertainty early.
  • Risk work is scaled to the project’s size and stakes.
  • The sponsor approves limits and handles decisions beyond project authority.
2

Identify and describe project risks

Useful risk identification draws on several views of the work. A supplier may see a problem that the project team misses, while an experienced user may see an opportunity. Different techniques help people bring those views forward. Clear descriptions then turn a collection of concerns into risks that can be rated, assigned, and acted on. Categories help reveal shared causes and areas the team has not yet examined.

2.1 Use techniques to identify risks

Risk identification finds and records threats and opportunities while there is time to act. Bring in people who understand different parts of the work: team members, users, the sponsor, suppliers, and subject experts. Their different knowledge helps expose blind spots.

Choose a way to hear the right people
TechniqueHow it worksWhen it helps
BrainstormingGather ideas without judging them, then group and refine them.A mixed group needs to explore widely.
Nominal group techniquePeople write alone, share in turn, then rank ideas.Senior or outspoken people might dominate.
InterviewsAsk experienced people individually about uncertainty.A concern is sensitive or needs specialist discussion.
Delphi techniqueCollect anonymous expert views, summarize them, and repeat rounds.Independent judgment matters and status could sway opinions.

For example, a workshop about the office move might quickly focus on furniture because the procurement lead speaks first. Individual writing before discussion gives the IT and facilities staff room to raise network readiness and building access. A private supplier interview can then explore a concern that would be difficult to discuss openly.

Search the records and the surroundings

Checklists draw on risks identified on earlier projects, lessons learned, and expert knowledge. They make experience easy to reuse, including risks that were spotted but never occurred. They need other techniques alongside them because a new project can face unfamiliar risks.

Document review examines the scope, WBS, schedule, estimates, requirements, and contracts. Look for single suppliers, tasks with no slack, vague requirements, and unclear contract terms. Ask what assumptions make important estimates possible and what constraints leave the project little room to recover.

A prompt list gives broad sources to consider. PESTLE covers political, economic, social, technological, legal, and environmental factors. In the office move, those prompts can reveal material-price increases, staff concerns about commuting, delayed permits, and snow. TECOP uses technical, environmental, commercial, operational, and political categories. A category is a starting question; it still needs a specific risk statement.

Examine causes and positive possibilities

SWOT analysis separates internal strengths and weaknesses from external opportunities and threats. An experienced installation team is a strength that may support an early finish. Limited purchasing capacity is a weakness that may contribute to missed orders.

Root cause analysis works backward from a possible problem to its causes, often using a fishbone diagram. An overloaded procurement team might cause late orders, missed discounts, and contract errors. Finding that shared cause can support one useful response across several risks.

In a pre-mortem, imagine the project has already failed and ask why. Treating failure as the starting situation can make it easier to voice doubts that sound too negative during ordinary planning.

Identification continues after kickoff. A scope change, a replacement supplier, or new information from completed work can create fresh risks. Ask about both threats and opportunities during status meetings and iteration reviews, then record new risks before detailed rating begins.

Key Takeaways

  • Use several perspectives and techniques to reduce blind spots.
  • Nominal groups and Delphi reduce different forms of group influence.
  • Checklists reuse experience; document review tests the current plan.
  • Prompt lists and SWOT widen the search for threats and opportunities.
  • Root cause analysis can reveal a cause shared by several risks.
  • A pre-mortem starts by imagining failure and asking what caused it.
  • Keep identifying risks when the work or its setting changes.

2.2 Write clear risk statements and group them

A risk statement should let someone outside the workshop understand what might happen and why it matters. Separate the conditions that exist now from the uncertain event and the effect it would have.

Build cause, event, and effect

The cause is a current fact or condition. The event is uncertain. The effect is the change to an objective if the event occurs. A useful sentence pattern is:

"Because of [cause], [uncertain event] may occur, which would lead to [effect on objectives]."

Start with the vague office-move entry "Supplier problems."

  1. Identify the cause: the only furniture supplier is fitting out two other offices this spring.
  2. Name the event: it may deliver the desks after week 10.
  3. Explain the effect: 60 staff would have no workstations during their first week in the new office.
  4. Join the parts: "Because our only furniture supplier is fitting out two other offices this spring, it may deliver our desks after week 10, leaving 60 staff without workstations in their first week."

The cause suggests where to investigate or intervene. The effect shows what the project needs to protect. A shorter "If [event], then [effect]" form works too when the cause is recorded separately.

Describe benefits with the same care

An opportunity also has a cause, event, and effect. "Because the supplier offers volume pricing above 50 desks, ordering for both floors together may earn a 10% discount, saving about $8,000 on the $80,000 furniture budget."

The saving follows from the size of the order and discount: 10% of $80,000 is $8,000. Recording the benefit makes it possible to judge whether coordinating the orders deserves effort.

Avoid four weak descriptions. "We have a new team" gives a fact without an uncertain event. "The project will be late" gives an effect without the uncertainty that could cause it. A certain task belongs in the plan. "The supplier may be late and prices may rise" combines two risks that need separate ratings and responses.

Group entries to reveal patterns

A risk category groups similar sources. A risk breakdown structure (RBS) arranges these categories in levels. For example:

  • Technical: requirements, technology, quality.
  • Management: estimates, resources, communication.
  • Commercial: contracts and suppliers.
  • External: regulation, markets, weather.

Risks can also be grouped by the WBS area or objective they affect. Several supplier risks may point to overloaded purchasing staff or dependence on one supplier. An empty external category deserves another look: the team may have missed it during the workshop.

Record each new risk promptly with a unique ID, description, category, date, and the person who raised it. Detailed rating and response planning can follow. Keeping one risk per entry allows its owner to update it without mixing several different events into one status.

Key Takeaways

  • Cause is present; the event is uncertain; effect concerns objectives.
  • Describe one specific risk per entry, including opportunities.
  • Categories and an RBS help reveal clusters and blind spots.
  • Record a new risk promptly before completing its analysis.
3

Analyze and prioritize risks

A long risk list gives little guidance about where to act first. Shared scales turn judgments about likelihood and consequences into a consistent starting point for priority. The project’s matrix, the time available to respond, and the limits of the project manager’s authority then shape the decision. You will work through those judgments separately, so that a striking consequence does not quietly inflate the probability rating.

3.1 Rate probability and impact on agreed scales

Qualitative analysis rates each risk so the team can decide where to focus. Probability describes the chance of the event. Impact describes the effect on an objective if it happens. Judge these separately: a frightening consequence does not make an event more likely.

Use written scales

A project can use these probability levels:

RatingDescriptionChance
1Very lowBelow 10%
2Low10% to 29%
3Medium30% to 49%
4High50% to 69%
5Very high70% or more

A certain event is a fact to plan for. The scale describes uncertainty; its top category does not turn certainty into a risk.

Impact definitions depend on the objective and the project’s size. For the 12-week office move with a $250,000 budget, use:

RatingSchedule delayExtra cost
1Up to 1 dayUp to $2,500 (1%)
2More than 1 day, up to 1 weekMore than $2,500, up to $12,500 (5%)
3More than 1 week, up to 2 weeksMore than $12,500, up to $25,000 (10%)
4More than 2 weeks, up to 4 weeksMore than $25,000, up to $50,000 (20%)
5More than 4 weeksMore than $50,000

Read endpoints carefully. An extra cost of exactly $25,000 is impact 3; a larger cost up to $50,000 is impact 4. The percentages relate these amounts to this project’s budget.

Rate the cabling risk step by step

The team estimates a 40% chance of late cabling, a delay of about 3 weeks, and extra costs of about $20,000.

  1. A 40% chance sits in the 30% to 49% band: probability 3.
  2. A 3-week delay sits above 2 and up to 4 weeks: schedule impact 4.
  3. An extra $20,000 sits above $12,500 and up to $25,000: cost impact 3.
  4. The plan uses the highest impact across objectives, so the risk’s impact is 4.

Keep the separate impact ratings in the record so the reason for choosing 4 is visible. Opportunities use the same method with impact measuring benefit: an $8,000 discount is cost impact 2, and its probability rating is 3.

Check the evidence behind the numbers

Bring together people who know the work and record why each rating was chosen. A supplier’s delivery record supports a stronger estimate than a guess about an unfamiliar supplier. Risk data quality describes that reliability. Mark weak evidence and gather more before a major decision depends on it.

Rate the risk as it stands now. An early-order action that has merely been proposed has not yet reduced the current probability; judge the residual risk after the response is carried out.

The ratings are ranks. A probability rating of 4 is not twice the chance of 2, and impact 4 is not twice the cost of impact 2. Quantitative analysis estimates effects in units such as money or days; multiplying scale ranks does not perform that analysis.

Key Takeaways

  • Rate probability separately from the severity of the consequence.
  • Use the same written definitions for every risk on the project.
  • Rate all affected objectives and apply the plan’s impact-selection rule.
  • An opportunity’s impact measures the benefit.
  • Record evidence quality and improve weak estimates.
  • Current ratings cannot assume that proposed responses have worked.

3.2 Rank risks with a probability and impact matrix

A probability and impact matrix turns ratings into priority bands. Probability runs along one axis and impact along the other. Each cell has a defined priority, often shown as high, medium, or low with red, amber, or green shading.

Calculate a score

A common starting rule is:

Risk score=probability rating×impact rating

With whole-number ratings from 1 to 5, the possible scores run from 1 to 25. The office-move example uses low for 1–4, medium for 5–12, and high for 15–25. Scores 13 and 14 do not occur because no two whole numbers from 1 to 5 multiply to make them.

Apply the rule to the move:

RiskProbabilityImpactScoreInitial band
Desks delivered late4416High
Cabling finished late3412Medium
Servers damaged in transit2510Medium
Bulk-order discount326Medium opportunity
Snowstorm during the move133Low

For the desks, multiply 4 by 4 to get 16, then locate 16 in the high band. For cabling, 3 times 4 gives 12, the upper end of medium. Keep the threat or opportunity label visible so a high benefit is not read as a large problem.

Apply the project’s special rules

The raw score is a starting point. A project may make every threat with impact 5 high priority, whatever its probability. With that rule, the server risk is high even though its score of 10 lies in the medium numerical band.

Equal products also hide different profiles. A risk rated 4 by 2 and one rated 2 by 4 both score 8. The second has a less likely but more severe outcome. The plan may give that profile greater priority, so read the actual matrix and any override rules before choosing an action.

A score of 12 is not a precise measurement of how much worse a risk is than one scoring 10. Both depend on judgments and broad bands. Scores from projects with different scales are not directly comparable.

Connect a band to action

High risks need response planning now, a named owner, and sponsor reporting. Medium risks need responses and regular review. Low risks go on a watch list with set review intervals; they can become more serious as circumstances change.

Rank opportunities too. A double matrix can put threats on one side and opportunities on a mirrored side. A high-priority opportunity deserves attention to capture its value.

A heat map places each risk’s ID in its probability-impact cell. At the next review, moving an ID to a different cell shows a change in exposure. It also helps the sponsor notice clusters of risks with severe consequences, even when their individual probabilities are low.

Key Takeaways

  • Multiply probability and impact ratings to find the score.
  • Use the project’s bands and override rules to set priority.
  • Equal scores can represent very different risk profiles.
  • Keep low risks on a watch list and rank opportunities too.
  • A heat map shows where risks sit and how their ratings move.

3.3 Weigh urgency and decide what to escalate

A priority score does not tell you when the team must act or who can authorize the response. Timing, connections between risks, and decision limits refine the initial ranking.

Compare occurrence time with action time

Proximity is when a risk could occur. Urgency is how soon a response must start to work. A late occurrence can demand an early decision if resources or approvals take time.

The desks cannot arrive late before week 10, but the supplier needs the order confirmed by week 3. Waiting until week 9 would leave little useful response time. The action is urgent even though the possible event is distant.

Now compare two risks scoring 12. Cabling could be late in week 8; weekly inspections must be agreed before work starts in week 4. A second risk concerns returning the old keys in week 12. The cabling response goes first because its useful action window closes sooner. This refines the order without pretending the cabling score has changed.

Consider how a risk behaves

Three further questions help explain priority:

  • Manageability: how far can the team influence the event or its effect?
  • Detectability: how much early warning would the team receive?
  • Connectivity: could this event set off other risks?

A supplier problem that affects furniture, equipment, and training readiness can matter more than its isolated entry suggests. A risk with no warning may need preparation that cannot wait for a trigger. These judgments supplement the matrix; record the reasons so another reviewer can follow the decision.

Escalate through the agreed route

A risk needs escalation if it affects matters beyond the project, needs authority the project manager lacks, or exceeds a sponsor-set threshold. Send it to the sponsor or other level able to decide. A possible company acquisition that could cancel the move belongs with the executive team.

A useful escalation contains the risk description, current rating, the limit or authority problem, response options with costs, and a recommendation. Send it while there is still time for a decision. The person who accepts ownership at the higher level owns the risk; the project marks it escalated and keeps it visible in its records.

Judge whether the project is still acceptable

Overall project risk asks whether combined uncertainty threatens the project as a whole. Look at the number of high risks, clusters around the same objective, and whether exposure is rising or falling. Compare that picture with the sponsor’s appetite.

The sponsor weighs the overall picture and any single intolerable risk when deciding to continue, change, or stop. Several medium risks can together threaten delivery; one unacceptable risk can also be enough to require a different course. Revisit this judgment when evidence improves, responses take effect, or the period in which a risk could occur passes.

Key Takeaways

  • Proximity concerns occurrence; urgency concerns the response deadline.
  • Manageability, warning time, and risk connections can refine priority.
  • Escalate beyond project authority or thresholds, with a recommendation.
  • Judge overall exposure alongside any individually unacceptable risk.
4

Plan responses to threats and opportunities

A response turns a risk judgment into a decision about the work. Threats may call for a change of plan, preventive action, or an agreed way to absorb the consequences. Opportunities call for action that secures or increases a benefit. Choosing a strategy is only the start: someone must carry it out, resources must be available, and the team must know when to use a prepared backup plan and how to judge the risk that remains.

4.1 Choose responses to threats

A threat response changes the work or prepares the team to handle harm. Choose an affordable, realistic action that can work in time, and agree it with the person who will own it. The aim is to bring exposure within the project’s thresholds.

Match the strategy to the change
StrategyWhat changesOffice-move example
AvoidRemove the threat or its effect on the objective.Use existing, tested cabling instead of installing new cabling.
MitigateReduce probability, impact, or both in advance.Order desks early and seek regular delivery updates.
TransferShift specified financial consequences and response responsibility to a third party.Buy transit insurance for server repairs.
AcceptAcknowledge the threat and decide how to live with it.Prepare an alternative moving weekend for snow.
EscalateMove the decision to the level with authority to act.Refer possible cancellation after an acquisition to executives.

Avoidance may require a different solution or less scope. If tested existing cabling meets the project’s needs, using it removes the particular threat associated with finishing new cabling late. That choice still needs agreement about the changed approach.

Mitigation, called reduction in some methods, acts before the event. Specialist IT movers can lower the chance of damage; backups can reduce the harm if damage occurs. These actions can be combined because they address different parts of the threat.

Know what a contract changes

Insurance, fixed-price contracts, warranties, and performance bonds can transfer specified financial effects. Check which effects are actually covered. Transit insurance can pay server repair costs, but damaged servers may still delay work and disrupt staff. The project must manage those consequences.

Some methods also list sharing a threat. Two parties might agree to split a fit-out cost overrun 50/50, giving both a reason to control it. Sharing divides an agreed consequence; transferring assigns a specified consequence to another party.

Make acceptance an explicit decision

Passive acceptance means taking no preventive action, reviewing the risk, and handling it if it occurs. Active acceptance prepares a contingency plan or sets aside time or money. An agreed alternative move weekend is active acceptance of the snow threat.

Acceptance can suit a low-priority threat or one whose possible effect is smaller than the cost of a useful response. Simply writing "monitor it" for a high threat leaves the team with passive acceptance unless a further action is agreed.

Combine responses where needed

The desks risk scores 16, high. The team orders in week 2 and obtains weekly updates: mitigation. A late-delivery penalty transfers part of the financial effect to the supplier. The team prepares to rent 60 temporary desks at $50 each for one week: active acceptance of what remains. The rental total is $3,000.

Each action needs an owner, a due date, and funding. "Be careful" gives none of those and cannot be checked at review. Put the agreed actions into the schedule and budget so the response can actually be carried out.

Key Takeaways

  • Avoid removes the threat; mitigation reduces its probability or impact.
  • Transfer covers specified consequences while other effects can remain.
  • Active acceptance prepares resources or a plan; passive acceptance does not.
  • Sharing divides an agreed threat consequence between parties.
  • Responses can be combined to address different parts of a threat.
  • Actions need agreement, ownership, dates, and resources.

4.2 Choose responses to opportunities

An opportunity is uncertain good news worth considering deliberately. A response can secure the benefit, improve its chance or value, or put it with a partner who can capture it. Give it an owner and review it just as you would a threat.

Decide whether to secure or improve the benefit

Exploit means taking action that makes the opportunity certain. Suppose the furniture supplier has made a firm offer: an order above 50 desks placed before the deadline earns the discount. Combining both floors into one qualifying order secures the $8,000 saving. The response removes the uncertainty about receiving that discount.

Enhance means increasing the chance or size of the benefit while uncertainty remains. An extra fit-out crew can raise the chance of leaving the old office early, but other delays could still prevent an early finish. The action improves the prospect without guaranteeing the result.

The distinction turns on the outcome, not on how hard people work. Giving a task to experienced staff is exploitation when it secures the benefit; if an early finish still depends on uncertain approvals or deliveries, the action enhances the opportunity.

Work with someone better placed to capture it

Share gives part of the opportunity’s ownership to a third party and divides the gain. The partner should contribute something that helps realize the benefit.

In the office move, the landlord can re-let the old space if the team leaves two weeks early. The parties agree to split the rent saving. At $3,000 per week, the two-week saving is $6,000; each receives $3,000. The project contributes early access to the space, and the landlord contributes the ability to find a new tenant.

An ordinary supplier payment does not by itself make a response sharing. The agreement must connect the parties to capturing and dividing the opportunity’s gain.

Accept or escalate deliberately

Accept means being ready to benefit if the opportunity arises without actively pursuing it. Some methods also use reject for a recorded decision not to pursue an opportunity, for example when the effort or added threats outweigh its value.

Escalate moves an opportunity beyond project scope or authority to people who can act. The move team might discover a spare floor suitable for a regional training center. That investment decision belongs to senior management, even if project staff first noticed it.

Pursuit can introduce extra work and new threats. Adding a crew costs money; combining orders may create coordination work. Record the response actions and check their effects. Any change to approved scope goes through change control, so a promising benefit does not quietly turn the move into a larger project.

Key Takeaways

  • Exploit secures a benefit; enhance improves its chance or size.
  • Sharing combines a partner’s contribution with an agreed split of the gain.
  • Accepted opportunities remain visible without active pursuit.
  • Escalate opportunities beyond project scope or authority.
  • Opportunity responses need owners, review, and scope control.

4.3 Prepare contingency plans and check what remains

A response plan needs a clear point for action and a way to handle what remains. Prepare those details before the team is under pressure to recover from a problem.

Set a trigger and a prepared response

A contingency plan is prepared in advance and used if the risk occurs or warning signs appear. A trigger is the observable condition that starts it. A useful trigger is specific, measurable, and checked on a schedule.

For cabling, use "less than 60% complete at the week 6 inspection." If the inspection finds 45% complete, the condition has been met. The team starts the planned temporary wireless network, costing about $4,000. It does not wait until staff arrive and find no connection.

A fallback plan is the second plan if the main response or contingency fails. If the temporary wireless network cannot support work, staff will work from home for up to one week. Agree the resources and authority for that step before it is needed.

A workaround is different: it is an unplanned response devised after an issue or threat has occurred. The timing of the preparation distinguishes it from contingency planning.

Re-rate the remaining risk

Residual risk is what remains after the response has been carried out. Early desk ordering reduces probability from 4 to 2 while impact remains 4:

4×4=16⟶2×4=8

The score falls from high to medium under the example bands. Check the residual against the project’s thresholds. If it is still unacceptable, add further responses or obtain the sponsor’s informed acceptance.

A secondary risk is a new risk directly caused by a response. The temporary wireless network might expose client data if it is less secure than the wired network. Give this new threat its own entry, rating, owner, and response. It is a different event from the late cabling that prompted the network.

Provide resources and schedule the work

A contingency reserve is time or money in the baseline for identified, accepted risks. A management reserve is held outside the baseline under management control for unforeseen work within approved scope, including risks that were not identified. Neither term means an unrestricted fund for extra scope.

Put response actions into the schedule, budget, and work assignments, or into the agile backlog. Name the action owner and due date. A backup system that has not been ordered or funded cannot be relied on simply because its name appears in the register.

Key Takeaways

  • A measurable trigger tells the team when to start a contingency plan.
  • A fallback is a prepared second plan; a workaround is improvised afterward.
  • Residual risk remains after a response; secondary risk is created by it.
  • Re-rate residual risk and check whether it is acceptable.
  • Contingency reserve sits in the baseline; management reserve sits outside it.
  • Build response work into the project’s schedule, budget, and assignments.
5

Own, monitor and update risks

Risk information changes as the work moves forward. A delivery date is confirmed, a warning sign appears, or an action misses its deadline. The team needs a record that shows those changes and a person who is accountable for each risk. Regular reviews connect that record to decisions, while reporting gives the sponsor a view of the project’s exposure. At closure, the same history helps future teams learn what worked and what was missed.

5.1 Build and maintain a risk register

The risk register is the central record of individual risks and how the project is handling them. Start it when the first risk is identified, update it throughout delivery, and archive it at closure. Its format can be simple, provided it supports decisions and follow-up.

Record enough to act

A complete entry needs several groups of information:

  • Identity: unique ID, date raised, date updated, description, threat or opportunity, and category.
  • Analysis: probability, impact, score, proximity, and the reasons for ratings.
  • Response: strategy, actions, action owners, due dates, trigger, contingency, and fallback.
  • Accountability and review: named risk owner, residual rating, secondary risks, and status.

Use one risk per entry and consistent scales. Keep IDs unique and never reuse them. Date updates so the team can distinguish a new judgment from an old one.

Read a complete entry

The office-move desks entry has ID R2, raised in week 1, and a commercial/supplier category. Its description explains the supplier’s workload, possible delivery after week 10, and the effect on 60 staff. Probability 4 and impact 4 give a score of 16, high. The event’s proximity is week 10, but the order is needed by week 3.

The strategy combines mitigation and active acceptance. The procurement lead places the order in week 2 with a late-delivery penalty and requests weekly updates from week 6. The trigger is no confirmed delivery date by week 6. The contingency is to rent 60 temporary desks for $3,000. Once early ordering has taken effect, the residual rating is probability 2 and impact 4, giving score 8, medium.

In a working register, replace the role title with the agreed individual’s name, such as "Jordan Lee, procurement lead." The person must know that they own the risk. The entry is open while late delivery remains possible.

Keep the status and history clear

Open means active. Occurred means the event is now handled as an issue. Escalated means ownership has passed above the project. Closed means the risk can no longer occur or has been dealt with.

Retain closed entries with their closure dates and reasons. Deleting a risk erases evidence of what the team anticipated, which response it used, and whether it worked. An occurred event also needs an issue-log entry, with the risk record updated to show the change.

Connect the register to other records

The risk management plan sets the method; the register records actual risks. The assumption log holds planning beliefs, and the issue log tracks current matters. A risk report summarizes the top risks, overall status, trends, and changes for stakeholders.

Agile teams may track risks on a board or in the backlog. The location changes, but the record still needs the risk, seriousness, owner, and response. A dated response task can link to the risk entry so its completion is visible during review.

Key Takeaways

  • The register records individual risks, analysis, responses, and accountability.
  • Use unique IDs, consistent scales, and dated updates.
  • Keep closed entries with reasons and dates.
  • Link risk records to issues, assumptions, and scheduled response work.

5.2 Assign risk owners and action owners

A risk needs one named person who makes sure it is managed. That person may ask others to do specific tasks, but accountability for the risk must remain clear.

Choose someone able to act

The risk owner makes sure responses are planned and carried out, watches triggers, and reports changes. Choose a person with knowledge of the risk, authority to influence it, and enough time to manage it. They must agree to take the role.

The person who first spots the risk is not always the best owner. A junior team member might identify a supplier problem but lack authority to change a purchase order. Put the risk with the person able to manage the supplier, and acknowledge the team member’s contribution without assigning authority they do not have.

Separate accountability from a task

An action owner, also called a risk actionee in some methods, carries out a particular response task and reports progress to the risk owner. One person may fill both roles, but delegating a task does not transfer accountability for the whole risk.

For example, Jordan Lee, the procurement lead, owns the late-desks risk. A purchasing assistant sends delivery-update requests, while Jordan decides whether the reply is satisfactory and whether to activate the rental contingency. The assistant reports completion and concerns to Jordan. Jordan remains accountable even when the assistant has finished sending the messages.

Know the supporting roles
RoleResponsibility
SponsorSets appetite and thresholds, decides on escalated risks, and approves responses beyond project authority.
Project managerLeads the process, facilitates identification, keeps the register, and checks that every risk has an owner.
Risk ownerManages one risk and its responses, triggers, and reporting.
Action ownerCompletes a specific response action.
Team memberIdentifies uncertainty, reports warning signs, and carries out agreed work.

For the move, the procurement lead owns the desks risk, the IT manager owns server damage, and the facilities manager owns snow and cabling risks. The project manager checks these entries at reviews without taking ownership of every one.

Make escalation actionable

If the risk crosses a threshold or needs a decision beyond the project manager’s authority, the risk owner and project manager escalate promptly through the agreed route. Include the description, current rating, and recommended response. Identify the higher-level person who accepts ownership so the entry does not disappear into a general referral.

"IT" or "everyone" is too vague for a named owner. Recording a department leaves reviewers unsure whom to contact, and actions can stall while people assume someone else will act. Record the individual and check acceptance of the role when responsibilities change.

Key Takeaways

  • Choose an agreed individual with knowledge, authority, and time.
  • The risk owner stays accountable when an action is delegated.
  • The project manager leads the process without owning every risk.
  • The sponsor handles decisions beyond the project’s authority.
  • Escalation needs a recommendation and an accepted owner at the higher level.

5.3 Monitor risks and keep responses working

Monitoring keeps the risk record aligned with the project as it is today. It tracks triggers and actions, checks whether responses work, updates ratings, and finds new risks. A completed response task is evidence to examine, not a reason to stop reviewing the risk.

Review on a useful schedule

Make risks a standing item in regular status meetings and review them in more depth at stage or phase boundaries. The frequency must allow triggers to be noticed in time. A weekly meeting alone is insufficient for a trigger that needs checking every day.

At each review, ask:

  • What new risks have appeared?
  • Have evidence, ratings, or response deadlines changed?
  • Are response actions complete and effective?
  • Has a trigger appeared?
  • Does anything need escalation, issue handling, or closure?

Record the date and reason for each change. If an action is late, find out whether the delay has reduced the response’s usefulness and decide what must happen next.

Work through the week 6 review

The desks were ordered in week 2. At week 6, the supplier confirms delivery for week 9. The procurement lead now judges probability 2 instead of 4. With impact still 4, the score falls from 16 to 8. Record the evidence behind the reduction, while keeping the risk open because delivery has not yet occurred.

The cabling inspection finds 45% complete, below the 60% trigger. The facilities manager starts the prepared temporary wireless-network plan. The register records the trigger, decision, dated action, and follow-up. The team also checks the new network’s security risk and whether the response is ready when needed.

Update, close, or handle an issue

When a risk occurs, use the prepared contingency if one exists, log the event as an issue, and mark the risk as occurred. If there is no prepared response, the team develops a workaround. If the main response or contingency fails, use the fallback or propose a new response.

Close a risk when it can no longer happen or its response has removed it. After the moving weekend passes without snow disruption, close the snowstorm risk with the date and reason. Retain the entry. A passed date supports closure only when the relevant event can no longer occur; an unresolved delayed delivery still needs handling.

Report the picture and improve the process

Risk reporting shows top risks, exposure trends, open high risks, overdue actions, and overall exposure compared with appetite. In agile work, a risk burndown chart plots total remaining exposure across iterations; a falling line indicates reduced exposure.

A risk audit examines whether the process works: consistent identification and rating, real ownership, and action on responses. It often involves someone outside the team. This differs from a review of an individual risk’s current rating.

At project closure, record which risks occurred, which responses worked, and which risks were missed. Use those lessons to improve future checklists and estimates.

Key Takeaways

  • Review triggers, actions, evidence, and new risks throughout delivery.
  • Record why ratings change, not just the new number.
  • Start agreed contingency actions when their trigger appears.
  • An occurred risk needs issue handling and an updated risk status.
  • Close risks when they can no longer occur and retain their history.
  • Report overall trends and overdue actions as well as top risks.
  • Audits assess the process; lessons learned improve future projects.

Project Risk Management examples

5 Walkthroughs

1

Separate uncertainty from current problems

13 steps
Use an office move to distinguish risks, issues, assumptions, and constraints, then connect them to shared decision rules.
  1. 1
    IntroductionStart with what the project needs

    A team is moving 60 staff to a new office over 12 weeks with a budget of $250,000. Deliveries, access, and network readiness all matter to its objectives.

    You will sort what might happen from what already needs action (a risk versus an issue, so each gets the right response), examine what the plan assumes (an assumption, unlike a fixed constraint), and see how the team agrees limits for risk decisions.

  2. 2
    ExplanationApply the two risk tests

    A risk is uncertain and would affect an objective if it occurred. Ask: "Could this happen?" and "What would it change?"

    Late desk delivery could delay staff readiness, so it is a threat. A possible supplier discount could reduce spending, so it is an opportunity. The direction of the effect changes, but both need a decision about uncertainty.

  3. 3
    ExampleDecide whether it has happened

    "The movers’ quote is $4,000 above its budget line" describes a problem that exists now. It is an issue, even though the move is weeks away.

    The team logs it, assesses its effect, decides on action or escalation, carries out the decision, and checks the result. "The movers may increase their quote" would instead describe an uncertain event to assess as a risk.

  4. 4
    ChallengeClassify the resignation

    The lead developer has resigned. The team is unsure whether a replacement can learn the system before launch. Which part is an issue, and which is a risk?

    ---reveal---

    The resignation is an issue because it has happened. The replacement’s possible lack of readiness is a risk because its effect on launch is still uncertain. Handle the departure now and assess the new uncertainty separately.

  5. 5
    ExplanationSeparate a belief from a limit

    "Keys will be available at the start of week 4" is an assumption if it has not been confirmed. Planning can use it, but someone must check it.

    "The old lease ends at the end of week 12" is a constraint. It limits the plan and the responses available. Record assumptions with owners and status in the assumption log; high-level assumptions and constraints also appear in planning documents.

  6. 6
    ExampleTest the cabling assumption

    The schedule assumes the cabling contractor will finish by week 8. The contractor missed deadlines on two earlier jobs, and staff cannot work in the new office without a network.

    The belief is uncertain and important. It creates a threat: cabling may finish after week 8, delaying the move and possibly pushing it beyond the week 12 lease deadline. Record the risk and keep checking the assumption.

  7. 7
    ChallengeFollow a possible budget change

    The budget cap is $250,000. The board may cut it by 10% at its next review. Is the possible cut another fixed constraint or a risk?

    ---reveal---

    The existing cap is a constraint. The cut is a risk because the decision is uncertain and could affect the work. A future decision should not replace the current approved limit before it has been made.

  8. 8
    ExplanationAgree how risk work runs

    The risk management plan defines methods, categories, scales, the matrix, roles, reporting, review frequency, resources, and escalation routes.

    Risk work repeats: plan, identify, analyze, plan responses, implement, and monitor. Monitoring supplies new evidence and can send the team back to earlier steps. Communication keeps the people who can act informed throughout the cycle.

  9. 9
    ExampleTurn appetite into a decision limit

    The sponsor accepts some schedule uncertainty but wants large effects raised promptly. The threshold is: possible delay above 10 working days or extra cost above $25,000 must be reported within two working days.

    A potential $30,000 cost crosses that limit even if time is unaffected. A potential 12-working-day delay crosses it even if extra cost is small. Either condition is enough.

  10. 10
    ConnectionInvestigate uncertainty early

    Agile teams apply the same risk ideas in shorter cycles. Feedback on small increments helps discover whether the product meets people’s needs before too much work is committed.

    A spike is a short, time-boxed technical experiment. Its findings improve the team’s decisions, while response tasks go into the backlog. Iterations provide review opportunities; they do not remove the need for ownership.

  11. 11
    ChallengeUse the threshold as written

    A move risk could add $20,000 and delay the move by 11 working days. Does the example threshold require sponsor reporting?

    ---reveal---

    Yes. The possible delay is above 10 working days, so it meets the time condition. Its cost being below $25,000 does not cancel that result. The threshold uses "or," so the team does not need both limits to be crossed.

  12. 12
    ChallengeConnect the belief to the decision

    A key handover assumed for week 4 is now uncertain. A late handover could breach the sponsor’s time threshold. What should the team connect in its records and decisions?

    ---reveal---

    Update and check the assumption, describe the possible late handover as a risk, and assess its effect. Apply the threshold and report through the agreed route. If the handover has already been missed and affects the work, also handle the current issue.

  13. 13
    RecapUse the right record for the next action

    A useful decision starts with the status of the matter: uncertain event, current problem, unproved belief, or fixed limit. Its effect on objectives explains why it matters.

    The shared approach gives the team a consistent way to assess that effect and decide who can authorize a response. As evidence changes, update the record that supports the decision.

2

Find risks and turn them into clear entries

12 steps
Choose identification techniques, build a cause–event–effect statement, and use categories to find patterns and gaps.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMake concerns usable
  2. 2
    ExplanationBring different knowledge into the search
  3. 3
    ConnectionChoose privacy or anonymity when useful
  4. 4
    TipCombine experience with current evidence
  5. 5
    ExplanationFind causes and overlooked possibilities
  6. 6
    ChallengeChoose a second method
  7. 7
    ExampleIdentify what exists now
  8. 8
    ExampleAdd the uncertain event
  9. 9
    ExampleShow why the event matters
  10. 10
    Key InsightUse categories to ask better questions
  11. 11
    ChallengeRepair an effect-only entry
  12. 12
    RecapCarry a clear entry into analysis
3

Rate the cabling threat and refine its priority

15 steps
Work through probability, separate impacts, matrix rules, response timing, and escalation using the office-move risks.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionBuild a priority you can explain
  2. 2
    ExplanationRate likelihood on its own
  3. 3
    ExampleRate the schedule consequence
  4. 4
    ExampleSelect the impact required by the plan
  5. 5
    ChallengeCheck the basis for a lower rating
  6. 6
    ExampleMultiply and read the band
  7. 7
    ExampleApply an impact override
  8. 8
    ChallengeDo equal products settle priority?
  9. 9
    TipKeep benefits and low risks visible
  10. 10
    ExplanationRead the action deadline
  11. 11
    ConnectionLook for warning and chain effects
  12. 12
    ExplanationSend the decision to the right level
  13. 13
    ChallengeChoose between two equal scores
  14. 14
    ChallengeCombine priority and overall exposure
  15. 15
    RecapKeep the reasoning behind the rank
4

Choose responses and prepare the backup plan

17 steps
Compare threat and opportunity responses, then build a triggered contingency and check residual and secondary risk.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionTurn the rating into work
  2. 2
    ExplanationRemove a threat or reduce it
  3. 3
    ExampleKnow what insurance covers
  4. 4
    ExplanationPrepare while accepting uncertainty
  5. 5
    ExampleCombine the desk responses
  6. 6
    ChallengeMatch the response to the result
  7. 7
    ExplanationSecure a benefit or improve its chance
  8. 8
    ExampleShare a benefit with a capable partner
  9. 9
    ChallengeCheck whether the discount is secure
  10. 10
    ExplanationDefine an observable trigger
  11. 11
    ExampleUse the contingency and fallback
  12. 12
    ExampleRe-rate the risk after action
  13. 13
    ConnectionLook for a new risk caused by the response
  14. 14
    ExplanationPut resources in the right place
  15. 15
    ChallengeName the risk that remains and the new one
  16. 16
    ChallengeJoin the strategy to the monitoring decision
  17. 17
    RecapMake the response ready to use
5

Keep the risk record connected to action

13 steps
Build an accountable register entry, distinguish risk and action ownership, and work through a live review and closure decision.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionUse the register during delivery
  2. 2
    ExplanationBuild an entry that supports a decision
  3. 3
    ExampleRead the late-desks entry
  4. 4
    ChallengeKeep a closed entry useful
  5. 5
    ExplanationAgree one accountable risk owner
  6. 6
    ExampleDelegate a task without losing accountability
  7. 7
    ChallengeDecide who owns the next decision
  8. 8
    ExampleUse the week 6 delivery evidence
  9. 9
    ExampleAct when the inspection trigger appears
  10. 10
    ConnectionReview the process as well as the entries
  11. 11
    ChallengeCheck whether a date really closes a risk
  12. 12
    ChallengePrepare the next status discussion
  13. 13
    RecapKeep decisions current and traceable

Project Risk Management practice questions

50 Practice Questions in 5 sets

Set 1: Recognize risks and choose a first response10 Practice Questions

Question 1 of 10

A venue has canceled its booking for a staff training event. How should the team classify the cancellation?
  1. A threat because the event date is still in the future.
  2. An issue because the cancellation has already happened.
  3. An assumption because another venue has not been found.
  4. A constraint because every booking sets a limit on planning.
Show answerHide answer
Answer: B
The cancellation is a current fact that needs action, so it is an issue. Record it in the issue log and assess its effect on the training event. The fact that the event date is still ahead does not make the cancellation uncertain; a possible failure to find a replacement venue would be a separate risk.

Question 2 of 10

A translation project schedules work on the belief that reviewers will return comments within two days, but nobody has confirmed this. What is that belief?
  1. A constraint on the reviewers’ agreed review time.
  2. An issue needing correction before planning begins.
  3. A risk event past its planned response window.
  4. An assumption used to build the review schedule.
Show answerHide answer
Answer: D
The two-day turnaround is being treated as true without proof, which makes it an assumption. Give it an owner and check it with the reviewers. It is not a constraint merely because it appears in the schedule: no firm requirement or agreed limit on review time has been established.

Question 3 of 10

A sponsor requires escalation of any risk that could add more than 6 working days to a project. What does the 6-day limit represent?
  1. A measurable risk threshold.
  2. A statement of risk appetite.
  3. A probability scale for delays.
  4. A contingency time allowance.
Show answerHide answer
Answer: A
The limit is a risk threshold because it sets a measurable boundary for an escalation decision. Appetite is the broader willingness to accept uncertainty in pursuit of value. A statement about a specific number of working days makes that general direction usable when the team assesses a particular threat.

Question 4 of 10

In a risk workshop, two senior staff members dominate the discussion. The facilitator wants everyone to write ideas alone, share in turn, and then rank them. What technique fits?
  1. Delphi questionnaires over repeated anonymous rounds.
  2. Individual interviews followed by a facilitator’s report.
  3. Nominal group technique with structured participation.
  4. Document review using a common project checklist.
Show answerHide answer
Answer: C
The nominal group technique starts with individual ideas, then sharing in turn and ranking. This gives quieter members a defined opportunity to contribute. Delphi also reduces the influence of status, but it does so through anonymous expert questionnaires over repeated rounds, not through the workshop sequence described.

Question 5 of 10

An event team depends on one printer that is running at full capacity. Printed badges might arrive after registration opens, delaying attendee entry. What is the cause in this risk?
  1. Attendees entering the event later than planned.
  2. Badges arriving after registration has opened.
  3. The need to prepare badges before the event.
  4. Dependence on a printer already at full capacity.
Show answerHide answer
Answer: D
The printer’s full workload and the team’s dependence on it are conditions that exist now, so they form the cause. Late badge arrival is the uncertain event, and delayed attendee entry is the effect on the event. Calling the late arrival the cause mixes the current condition with what may happen next.

Question 6 of 10

A project’s probability scale rates 20–39% as 2 and 40–59% as 3. The team estimates a 35% chance of a test failure. What probability rating applies?
  1. 1, because the event is less likely than not.
  2. 2, because 35% is within the defined range.
  3. 3, because failure could severely affect quality.
  4. 4, because uncertainty calls for a cautious rating.
Show answerHide answer
Answer: B
The estimate of 35% lies in the project’s 20–39% interval, so the probability rating is 2. Use the written scale rather than a personal sense of caution. A severe quality effect belongs in the impact rating and does not move a 35% likelihood into a higher probability band.

Question 7 of 10

A project multiplies probability and impact ratings. Scores 1–4 are low, 5–12 medium, and 15–25 high, with no overrides. A threat has probability 3 and impact 3. What is its score and band?
  1. 6, medium.
  2. 9, high.
  3. 9, medium.
  4. 6, low.
Show answerHide answer
Answer: C
Multiplying the two ratings gives 9, which lies in the defined medium band. Adding them would give 6, but that is not the project’s scoring rule. The band follows the stated boundaries; a score of 9 does not become high simply because both inputs are in the middle of the scale.

Question 8 of 10

A project buys insurance covering repair costs if equipment is damaged in transit. What response does this use for those costs?
  1. Transfer the covered financial effect.
  2. Avoid the transit-damage event entirely.
  3. Mitigate the likelihood of transit damage.
  4. Accept the repair cost without preparation.
Show answerHide answer
Answer: A
Insurance transfers the specified repair-cost consequence to the insurer under the agreement. It does not, by itself, change how likely damage is or prevent the equipment from being damaged. The team still needs to consider effects such as delay and disruption that the stated repair-cost cover does not address.

Question 9 of 10

A test team adds an extra specialist to improve the chance of finishing early. External approvals could still prevent the early finish. What opportunity response is this?
  1. Exploit, because extra effort secures the outcome.
  2. Share, because another person contributes to it.
  3. Enhance, because the chance improves but is uncertain.
  4. Accept, because early completion remains possible.
Show answerHide answer
Answer: C
The specialist increases the chance of an early finish, so this enhances the opportunity. The remaining approval uncertainty means the benefit has not been secured. Exploitation requires action that makes the opportunity certain; assigning more resources does not meet that test when another uncertain dependency remains.

Question 10 of 10

A festival’s outdoor setup has ended without wind disruption. A badge shipment is now late, and a staffing shortage remains possible for tomorrow. What status sequence fits the wind, shipment, and staffing entries?
  1. Closed, closed, open; retain the three entries with dated updates.
  2. Closed, occurred, open; retain history and link the shipment to an issue.
  3. Open, occurred, open; retain each until the entire festival closes.
  4. Closed, open, occurred; use the issue log for the staffing possibility.
Show answerHide answer
Answer: B
The wind risk can no longer occur during the completed setup, so close it with a reason and date. Late shipment has occurred and needs linked issue handling, while the staffing shortage is still uncertain and open. The shipment should not stay merely open once its event has happened.
Set 2: Turn risk descriptions into practical decisions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A supplier may offer a free upgrade that would improve a project’s output without extra cost. How is this uncertainty classified?
  1. An issue because the upgrade changes the planned output.
  2. A constraint because the supplier controls the decision.
  3. An opportunity because it could improve an objective.
  4. An assumption because every offer must be treated as true.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A project has a fixed spending cap. The board may reduce that cap next month. What should the team record about the possible reduction?
  1. A risk about a possible change to the constraint.
  2. An issue showing the budget has already fallen.
  3. A confirmed assumption about next month’s budget.
  4. A new constraint replacing the existing cap now.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

An analyst wants to find risks in unclear requirements, single-supplier dependencies, and tasks with no slack. What identification technique directly examines those sources?
  1. A pre-mortem based on an imagined project failure.
  2. A Delphi exercise with anonymous expert feedback.
  3. A SWOT review of internal and external factors.
  4. Document review of the project’s plans and agreements.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A risk has schedule impact 2, cost impact 4, and quality impact 3. The plan uses the highest objective rating. What impact should be used in the matrix?
  1. 2, because the schedule is the first affected objective.
  2. 3, because the middle rating balances the consequences.
  3. 9, because all affected objectives must be added.
  4. 4, because cost has the highest individual rating.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Two threats have equal priority scores. One could occur in month 5 but needs an order this week; the other could occur next month and can be handled with an action started in three weeks. What should drive the earlier response?
  1. The second threat’s closer occurrence date.
  2. The first threat’s earlier response deadline.
  3. The second threat’s shorter remaining duration.
  4. The first threat’s later period of possible impact.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A project replaces an untested installation method with an established method that removes the identified failure threat. What strategy does that change illustrate?
  1. Mitigation by reducing the impact of failure.
  2. Transfer by assigning the failure to a supplier.
  3. Avoidance by removing the identified threat.
  4. Acceptance by preparing for a possible failure.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A plan says, "If fewer than 80% of reviewers have access by Tuesday, activate the prepared support session." What is the access condition?
  1. A trigger for the contingency plan.
  2. A fallback plan if the session fails.
  3. A workaround after the session.
  4. A schedule reserve for late access.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A risk entry says, "Owner: operations; action: discuss supplier." What change would make follow-up more accountable?
  1. Add a higher score and keep the department as owner.
  2. Name an agreed person and a specific, dated action.
  3. Move the discussion to the issue log without changes.
  4. Replace the description with the next meeting’s date.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Ravi owns a supplier risk. Mei completes an assigned backup-capacity check, finding that the contingency is possible but needs funding beyond project authority. Who must coordinate the next risk decision?
  1. Mei must accept the remaining exposure because she completed the check.
  2. The project manager must become risk owner because funding is required.
  3. The whole purchasing team must approve funding and share ownership.
  4. Ravi must work with the project manager to escalate the funding decision.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A trigger was checked only monthly despite a daily-check requirement. Its warning was missed, but the team could also have used a contingency prepared for the event. The event has now occurred. What correction addresses both the live problem and the process gap?
  1. Use the applicable contingency, log the issue, and restore daily trigger checks.
  2. Use the applicable contingency, retain open status, and wait for the monthly review.
  3. Log the issue, improvise a new response, and replace daily checks with reports.
  4. Restore daily checks, lower the rating, and defer action until the next warning.
Show answerHide answer

Save this lesson to see this answer.

Set 3: Connect ratings, responses, and ownership10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

Where should a team find the agreed probability scale, review frequency, and escalation route?
  1. In the risk management plan.
  2. In the current issue log.
  3. In the latest assumption entry.
  4. In the project’s lessons archive.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A risk entry says, "The installer may arrive late and material prices may rise." How should the entry be improved for rating and response planning?
  1. Keep one entry and use the higher of the two probability ratings.
  2. Keep one entry and list the two effects under one shared score.
  3. Split the events so each can receive its own rating and response.
  4. Replace both events with the combined effect, "higher cost."
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A project uses low 1–4, medium 5–12, and high 15–25, with an override making any impact-5 threat high. Threat X is rated 1 by 5; threat Y is rated 3 by 3. What priorities apply?
  1. X medium and Y medium, using the calculated scores.
  2. X high and Y medium, after applying the override.
  3. X low and Y medium, using probability as the priority.
  4. X high and Y high, because both could affect delivery.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A product team discovers a possible company-wide license agreement that could cut costs across several departments. Only executives can authorize it. What should the team do with the opportunity?
  1. Escalate it with an assessment and recommendation.
  2. Exploit it by committing all departments to the agreement.
  3. Accept it by waiting for executives to discover it.
  4. Transfer it by adding the supplier as the project owner.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A minor threat is within thresholds. The team chooses no preventive action but reserves funds and prepares steps to use if it occurs. What response is this?
  1. Passive acceptance because the event remains possible.
  2. Mitigation because the planned funds reduce its probability.
  3. Transfer because a reserve pays the financial consequence.
  4. Active acceptance because the team prepares for the event.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A supplier has made a firm offer of a discount for a qualifying order received by Friday. The team places and confirms that order on Thursday, securing the discount. What response is this?
  1. Enhance the opportunity.
  2. Exploit the opportunity.
  3. Accept the opportunity.
  4. Share the opportunity.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A response lowers a delivery threat’s probability from 4 to 2; its impact stays 3. What is the residual score?
  1. 12, because the original rating remains the risk history.
  2. 9, because the old and new probabilities are combined.
  3. 5, because the two remaining ratings are added.
  4. 6, because the new probability is multiplied by impact.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A junior designer identifies a contract risk but has no authority over the supplier. Who is the best risk owner?
  1. The designer automatically, because they raised the risk.
  2. The whole team, because everyone benefits from delivery.
  3. An agreed individual able to manage the supplier risk.
  4. The project manager automatically, because it is a risk.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A preventive action is complete, but probability remains 4 and impact 4. Bands are low 1–4, medium 5–12, high 15–25. The owner’s fallback needs funding above project authority. How should the owner report the position and seek action?
  1. Report medium residual risk and implement the fallback using existing authority.
  2. Report high residual risk and escalate the fallback funding with a recommendation.
  3. Report high original risk and close the entry because prevention is complete.
  4. Report medium residual risk and wait for the event before requesting a decision.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A backup courier reduces a delivery threat from probability 4 to 2, with impact still 3. It also creates a possible handling-damage event rated 2 by 4. How should the owner record the two exposures?
  1. Delivery residual score 6; a separate secondary damage risk with score 8.
  2. Delivery residual score 8; a separate secondary damage risk with score 6.
  3. One delivery residual risk with score 14 covering both uncertain events.
  4. One damage issue with score 8 replacing the original delivery risk.
Show answerHide answer

Save this lesson to see this answer.

Set 4: Judge the evidence behind a risk decision10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A deployment has already failed its acceptance test. The team also fears the repair may delay training. How should these two matters be classified?
  1. Two risks, because both affect the future schedule.
  2. Two issues, because both arise from the failed test.
  3. A failed-test risk and a confirmed training constraint.
  4. A failed-test issue and a possible training-delay risk.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A schedule assumes a specialist will work full time, but their manager has promised only half-time availability. What should the team do?
  1. Keep the assumption open until the final project review.
  2. Update the log and replan using the confirmed availability.
  3. Convert the whole schedule into one high-priority risk.
  4. Treat full-time availability as a fixed project constraint.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A sponsor requires escalation for possible delay above 7 working days or extra cost above $18,000. Completed responses leave risk X at 7 days and $18,000, and risk Y at 9 days and $16,000. Neither has another escalation condition. What follows?
  1. Escalate X only, because meeting either boundary crosses the limit.
  2. Escalate neither, because neither exceeds both limits together.
  3. Escalate Y only, because its residual delay exceeds the time limit.
  4. Escalate both, because any remaining exposure needs sponsor ownership.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A team uses a checklist from similar projects and finds no risks involving a new technology it has never used. What is the best next step?
  1. Conclude that the technology has no relevant risk history.
  2. Add expert discussion and review of the current design.
  3. Copy a past technical risk so that the category is filled.
  4. Exclude the technology until an actual failure supplies evidence.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Late-order risks, missed-discount risks, and contract-error risks appear in separate entries. Document review shows their purchase requests all wait for the same approver, whose queue is growing. What should the team investigate while keeping the analysis useful?
  1. The shared approval bottleneck, while retaining separate event entries.
  2. The highest-scoring event alone, while closing the related risk entries.
  3. A single combined event, while replacing its ratings with the largest score.
  4. Three independent causes, while excluding the approval queue from the review.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A team rates an unfamiliar supplier using one optimistic guess. Another rating uses records from comparable deliveries. What difference should the risk review recognize?
  1. The optimistic rating must have the lower impact score.
  2. The recorded estimate must be treated as a certain event.
  3. Both have equal reliability because each produces a number.
  4. The guess has weaker data quality and needs investigation.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Project A rates a threat 4 by 3: its probability band is 20–39% and its impact band is 1–2 days. Project B rates a threat 2 by 4: its probability band is 40–59% and impact band is 6–10 days. What can a director conclude from scores 12 and 8?
  1. The larger score in A does not establish greater underlying exposure.
  2. The threats must be equally serious because both ratings are ordinal.
  3. A is definitely more serious because 12 is larger than 8 on any scale.
  4. B’s impact is lower because its probability rating is smaller than A’s.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A landlord and team each contribute to re-letting a space if it is vacated early. They will split the saved rent equally. A possible three-week early exit would save $2,400 per week, but the finish date remains uncertain. How should the project describe its response and potential share?
  1. Exploitation with a certain $7,200 benefit to the project.
  2. Sharing with a certain $3,600 benefit to the project.
  3. Sharing with a possible $3,600 benefit to the project.
  4. Enhancement with a possible $7,200 benefit to the project.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A supplier threat has been accepted by an executive owner because its response is beyond project authority. How should the project’s register represent it?
  1. Delete it because the executive now maintains the risk history.
  2. Mark it escalated and keep its ownership and status visible.
  3. Mark it closed because the project manager cannot authorize action.
  4. Mark it occurred because the decision has moved to another level.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

An independent reviewer checks whether risks are identified, rated consistently, assigned owners, and acted on. What activity is this?
  1. A risk review focused on one entry’s current score.
  2. A contingency activation after a warning sign appears.
  3. A risk report summarizing exposure for the sponsor.
  4. A risk audit assessing the management process.
Show answerHide answer

Save this lesson to see this answer.

Set 5: Make integrated risk decisions as a project changes10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

An agile team is unsure whether a new interface can meet its needs. What planned action best investigates the uncertainty before committing to a full build?
  1. Add a permanent contingency allowance without further investigation.
  2. Treat the interface as proven because development uses iterations.
  3. Run a short, time-boxed technical experiment and use its findings.
  4. Wait for final acceptance testing before examining the interface.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A facilitator asks the team to imagine that a project has failed and then list reasons for that failure. What technique is being used?
  1. Root cause analysis of an observed current defect.
  2. Delphi rounds seeking anonymous expert agreement.
  3. SWOT classification of internal and external factors.
  4. A pre-mortem to surface possible causes of failure.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A threat currently has probability 4, schedule impact 2, and cost impact 3. The plan uses the highest impact. An unstarted action is expected to reduce probability to 2. What current score should the owner report?
  1. 6, using the expected probability and the highest impact.
  2. 12, using the current probability and the highest impact.
  3. 8, using the current probability and schedule impact alone.
  4. 9, using an average of current and expected probabilities.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A project uses bands low 1–4, medium 5–12, high 15–25 and makes every impact-5 threat high. A completed response changes a threat from 4 by 5 to 1 by 5. How should the residual be reported?
  1. Score 5, high priority under the impact override.
  2. Score 5, medium priority under the numerical band.
  3. Score 1, low priority from the new probability.
  4. Score 20, high priority kept from the original rating.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A sponsor sees several medium threats clustered around one launch dependency and one rare threat whose effect exceeds appetite on its own. What should inform the continue-or-change decision?
  1. Only the highest product, because scores combine every relevant factor.
  2. Only the medium-risk cluster, because rare events should be excluded.
  3. Combined exposure and the individually unacceptable threat.
  4. The number of entries alone, because each entry has an equal weight.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A transport project buys protective packaging and also insures covered damage costs. How do these responses work together?
  1. Packaging transfers the cost; insurance removes the damage event.
  2. Packaging mitigates damage; insurance transfers covered cost.
  3. Both avoid damage because each requires spending in advance.
  4. Both actively accept damage because a loss remains possible.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A firm offer gives a discount only for at least 100 units ordered together by Monday. A team confirms 70 units for Monday and another 40 in a separate Tuesday order. Has it exploited that discount opportunity?
  1. Yes; the combined 110 units satisfy every discount condition.
  2. Yes; confirming 70 units by Monday secures the qualifying rate.
  3. No; exploitation requires the supplier to share ownership of the gain.
  4. No; the quantity across two orders does not meet the offer’s conditions.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A project funds a prepared rental response for an identified, accepted risk. Later, an unidentified risk causes unforeseen work within approved scope. How should the team distinguish the reserve routes for these needs?
  1. Use baseline contingency for the identified risk; seek management-controlled reserve outside it for the unforeseen work.
  2. Use management reserve outside the baseline for the identified risk; put unforeseen work directly against contingency.
  3. Use baseline contingency for both needs; approved scope makes the distinction between known and unforeseen work unnecessary.
  4. Use management reserve outside the baseline for both needs; any conditional expenditure belongs outside the approved baseline.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A threat exceeds the project manager’s authority. The risk owner has prepared the description, rating, and recommended response. What should the owner and project manager do?
  1. Let the risk owner authorize and fund the response.
  2. Refer it to the sponsor and mark the risk closed.
  3. Escalate promptly through the agreed decision route.
  4. Keep the decision local until a risk action is overdue.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A pilot project’s risk count falls because several entries are deleted, but its remaining high risks and overdue response actions increase. What conclusion should the sponsor draw?
  1. Report improvement from the smaller count, while listing overdue actions separately.
  2. Report only current high risks, because closed-entry history has no decision value.
  3. Report the old total, deferring judgment until every remaining risk can be re-rated.
  4. Examine exposure and overdue actions, and restore the missing closure history.
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

71 Key Terms, each with its definition

A

Action owner
An action owner carries out a specific risk response task and reports progress to the risk owner, who retains overall accountability.
The action owner must confirm the backup supplier’s capacity by Thursday and report the result to the risk owner.
Active acceptance
Active acceptance acknowledges a threat while preparing a contingency plan or reserving time or money to handle it if it occurs.
Preparing an alternative event date is active acceptance of a weather threat that the team cannot prevent.
Assumption
An assumption is a factor treated as true for planning without proof, allowing work to be planned while information is incomplete.
The schedule uses the assumption that reviewers will return comments within two working days.
Assumption analysis
Assumption analysis examines how likely a planning belief is to be wrong and what that would mean for project objectives.
Assumption analysis reveals that an unconfirmed reviewer’s availability could delay the approval milestone.
Assumption log
An assumption log is a record of planning beliefs, their owners, dates, confirmation status, and the actions taken to check them.
After a supplier confirms capacity, the owner updates the status of the belief about that capacity in the assumption log.
Avoidance
Avoidance changes the project plan so an identified threat can no longer occur or can no longer affect the objective being protected.
Using tested existing cabling is avoidance of the threat that a new cabling installation finishes late.

B

Brainstorming
Brainstorming is a facilitated group technique that gathers possible risks without judging them first, then groups and refines the ideas.
The facilitator collects all brainstorming ideas before the team discusses which ones need clearer descriptions.

C

Connectivity
Connectivity describes links between risks through which one event could trigger others, increasing the importance of the shared exposure.
A supplier threat that could delay installation, testing, and staff training has high connectivity.
Constraint
A constraint is a limit the project must work within, such as a fixed finish date, spending cap, mandatory standard, or resource limit.
The venue’s fixed reopening date is a constraint that restricts how the team can recover from delays.
Contingency plan
A contingency plan is a response prepared in advance and carried out if a risk occurs or specified warning signs appear.
A contingency plan starts temporary network installation when an inspection in week 6 meets the trigger the plan names.
Contingency reserve
A contingency reserve is time or money included in the baseline for identified risks that the project has accepted and prepared to handle.
The schedule’s contingency reserve allows time for an identified delay if its agreed trigger appears.

D

Delphi technique
The Delphi technique collects anonymous expert views over repeated rounds, using summarized feedback to help judgments move closer together.
The Delphi technique lets specialists revise estimates without being swayed by the most senior person’s view.
Detectability
Detectability describes how early warning signs of a risk can be noticed, affecting how much time the team may have to respond.
Poor detectability of a service problem leads the team to prepare backups before the problem gives any visible warning.
Document review
Document review examines project records such as plans, estimates, requirements, and contracts to identify uncertainty and weak points.
Document review shows that the schedule relies on one supplier and allows no recovery time before handover.

E

Enhancement
Enhancement is an opportunity response that increases the chance or size of a benefit while leaving the outcome uncertain.
An extra installation crew provides enhancement when other uncertain approvals can still prevent an early finish.
Escalation
Escalation passes a risk decision to a level able to act when its effects, response authority, or threshold lie beyond the project.
The manager uses escalation when a possible company acquisition could cancel the project altogether.
Exploitation
Exploitation is an opportunity response that removes uncertainty and secures the benefit through an action that makes it certain.
A confirmed order meeting every condition of a firm discount offer achieves exploitation of that opportunity.

F

Fallback plan
A fallback plan is a prepared second course of action used if the main risk response or its contingency plan does not work.
Working from home is the fallback plan if a temporary network set up during a move cannot support the team’s work.

H

Heat map
A heat map places risk identifiers in probability–impact cells to show exposure patterns and movements in ratings between reviews.
The sponsor uses the heat map to see several risks clustering in cells with severe consequences.

I

Impact
Impact is the size of an event’s effect on a project objective if it occurs, measured as harm for threats or benefit for opportunities.
The possible saving from a discount determines the opportunity’s cost impact on the project’s scale.
Issue
An issue is a current condition or an event that has already happened and needs action because it affects the project.
A failed acceptance test is an issue; the team now needs a decision about repairs and another test.
Issue log
An issue log records current matters that need action and tracks their assessment, decisions, responsibility, progress, and closure.
After a delivery threat occurs, the team uses the issue log to coordinate recovery and link back to the original risk.

L

Lessons learned
Lessons learned are recorded insights from project experience, including risks that occurred or were missed and how well responses worked.
Lessons learned from a supplier delay on one project lead the next project to check capacity before confirming its schedule.

M

Manageability
Manageability is the extent to which the project team can influence a risk’s probability or consequences through its available actions.
The owner judges manageability before choosing between changing a supplier and preparing for a delivery delay.
Management reserve
A management reserve is held outside the baseline under management control for unforeseen work that remains within approved scope.
Management considers use of its management reserve when an unidentified risk creates unforeseen in-scope work.
Mitigation
Mitigation acts in advance to reduce a threat’s probability, impact, or both while some uncertainty can remain after the action.
Backups mitigate the impact of server damage, while specialist movers can reduce its probability.

N

Nominal group technique
The nominal group technique gathers individually written ideas, shares them in turn, and then ranks them to support broad participation.
The nominal group technique gives quieter engineers time to develop their concerns before discussion begins.

O

Opportunity
An opportunity is a project risk whose effect would help an objective if it occurred, such as improving quality or reducing cost.
The possibility of combining two orders at a discount is an opportunity to reduce the project’s spending.
Opportunity acceptance
Opportunity acceptance means being ready to take a benefit if it arises without actively working to increase or secure it.
The team records opportunity acceptance when it will use a free upgrade if offered but will not pursue it.
Opportunity rejection
Opportunity rejection is a recorded decision not to pursue an upside, for example because the effort or added threats outweigh the gain.
The owner records opportunity rejection after comparing a discount with the extra storage risks that taking it would create.
Opportunity sharing
Opportunity sharing gives a capable partner part of an opportunity’s ownership and an agreed share of the benefit it helps capture.
The landlord’s role in finding a new tenant makes a split of early-exit savings opportunity sharing.
Overall project risk
Overall project risk is the effect of all uncertainty on a project as a whole, including the ways individual risks combine.
Several supplier threats make the overall launch date doubtful even though each individual score is medium.

P

Passive acceptance
Passive acceptance acknowledges a threat without advance response preparation, with periodic review and action if the event occurs.
The team chooses passive acceptance for a minor threat whose useful response would cost more than its effect.
Pre-mortem
A pre-mortem asks people to imagine that a project has already failed and identify possible reasons, making doubts easier to raise.
During a pre-mortem, staff explain how an overlooked access agreement could have stopped the launch.
Probability
Probability is the chance that a risk event will occur, assessed separately from the severity of its consequences using an agreed scale.
A supplier’s delivery history informs the probability rating, while the cost of delay informs impact.
Probability and impact matrix
A probability and impact matrix assigns priority to combinations of likelihood and consequence ratings using the project’s agreed rules.
A probability and impact matrix with a rule that every impact-5 threat is high priority ranks it high even if its probability is low.
Project manager
The project manager leads the risk process, maintains the register, and ensures risks have owners without automatically owning every risk.
The project manager checks each risk owner’s updates during the regular status meeting and follows up missing actions.
Project risk
A project risk is an uncertain event or condition that would affect at least one objective, such as schedule, cost, quality, or benefits.
A possible delay to the training-room installation is a project risk because it could postpone staff training.
Project sponsor
The project sponsor sets risk appetite and thresholds, decides escalated risks, and approves responses beyond the project manager’s authority.
The project sponsor decides whether to accept a residual exposure that remains above the agreed threshold.
Prompt list
A prompt list names broad sources of risk that guide a team’s search, helping it consider areas it might otherwise overlook.
An environmental heading in the prompt list leads a team planning a move to investigate seasonal access problems.
Proximity
Proximity is the time when a risk could occur, helping the team relate uncertainty to project activities, milestones, and review dates.
A risk to an equipment shipment that must be ready for installation in week 9 has proximity in week 9.

Q

Qualitative risk analysis
Qualitative risk analysis rates probability and impact using descriptive or numbered categories so individual risks can be prioritized.
The team uses qualitative risk analysis to decide which supplier uncertainties need response planning first.

R

Residual risk
Residual risk is the uncertainty remaining after a response has been carried out, requiring a new rating and an acceptability check.
Early ordering lowers the threat that desks arrive late, but the owner still reviews the residual risk of late arrival.
Risk appetite
Risk appetite is the amount of uncertainty a person or organization is willing to accept in pursuit of a reward or benefit.
The sponsor expresses low risk appetite for service disruption during the customer-system changeover.
Risk audit
A risk audit checks whether the risk management process works, including consistent identification, analysis, ownership, and response action.
An independent risk audit finds that several high risks have no agreed owners despite regular rating updates.
Risk breakdown structure
A risk breakdown structure arranges sources of risk in a hierarchy of categories, such as technical, commercial, management, and external.
The risk breakdown structure prompts the team to revisit external risks after a workshop focused on technology.
Risk burndown chart
A risk burndown chart plots total remaining risk exposure across iterations so an agile team can see how exposure changes over time.
The risk burndown chart falls after the team resolves technical uncertainty and completes effective responses.
Risk category
A risk category groups risks by a shared source or area, helping the team recognize clusters and gaps in its identification work.
Several entries in the commercial risk category point to dependence on the same equipment supplier.
Risk cause
A risk cause is a fact or condition that exists now and gives rise to an uncertain event that could affect project objectives.
A supplier’s full workload is the risk cause behind a possible late shipment of equipment.
Risk checklist
A risk checklist is a reusable list based on risks identified on earlier projects, lessons learned, and expert knowledge.
The team adds a design review because its risk checklist has no entries about the unfamiliar installation method.
Risk data quality
Risk data quality describes the reliability of information supporting a rating, including whether it rests on evidence or weak guesses.
Low risk data quality leads the owner to request delivery records before recommending a major response.
Risk event
A risk event is the uncertain occurrence described in a risk statement, separated from its present cause and its possible consequences.
In a risk that printed badges arrive late, late delivery is the risk event and delayed attendee entry is the effect.
Risk interview
A risk interview is an individual discussion with a stakeholder or expert to uncover uncertainty, especially where a concern is sensitive.
A private risk interview lets a buyer explain doubts about a supplier without pressure from the workshop group.
Risk management plan
A risk management plan defines the project’s methods, roles, scales, reviews, reporting, resources, and rules for handling risk.
The team checks the risk management plan before deciding how to classify a severe but unlikely threat.
Risk monitoring
Risk monitoring tracks risks, triggers, action progress, response results, and changing evidence throughout the project to guide further decisions.
Risk monitoring shows that a completed action has not reduced exposure, prompting the owner to revise the response.
Risk owner
A risk owner is the agreed individual accountable for managing one risk, ensuring responses, trigger checks, and reporting stay on track.
The procurement lead remains risk owner when a purchasing assistant sends the supplier’s update requests.
Risk register
A risk register is the central record of individual risks, including descriptions, ratings, responses, ownership, dates, and status.
The risk register links a late-delivery threat to a named owner, an early-order action, and a rental contingency.
Risk report
A risk report summarizes information for stakeholders, including top risks, overall status, trends, and changes since the previous report.
The sponsor’s risk report highlights two overdue responses and a rise in exposure around the launch date.
Risk score
A risk score is a ranking value commonly calculated by multiplying probability and impact ratings; it is not a measured financial loss.
Where a score of 12 counts as medium, a cabling threat with a risk score of 12 sits in the medium band before any special rule is applied.
Risk threshold
A risk threshold is a measurable limit around an objective that determines when exposure is unacceptable or requires escalation.
Where the risk threshold is a delay of five working days, a possible delay above five days crosses it and needs a sponsor decision.
Risk transfer
Risk transfer assigns specified financial consequences and response responsibility to a third party, commonly through a contract or insurance.
Transit insurance provides risk transfer for repair costs, but the project still plans for possible disruption.
Root cause analysis
Root cause analysis traces the conditions behind possible problems, often revealing a common source that drives several separate risks.
Root cause analysis links missed orders and contract errors to the same overloaded purchasing team.

S

Secondary risk
A secondary risk is a new uncertainty caused directly by a risk response, requiring its own identification, analysis, and handling.
A temporary network’s possible security weakness is a secondary risk created by a contingency plan that uses it to cover late cabling.
Spike
A spike is a short, time-boxed experiment in agile work that investigates technical uncertainty before the team commits more effort.
A two-day spike tests whether a new interface can support the expected number of users.
SWOT analysis
SWOT analysis examines internal strengths and weaknesses alongside external opportunities and threats to support decisions and risk discovery.
A SWOT analysis connects experienced staff with an opportunity to complete the installation ahead of schedule.

T

Threat
A threat is a project risk whose effect would harm an objective if it occurred, such as increasing cost or delaying delivery.
The team records a possible shortage of installation parts as a threat to the equipment handover date.
Threat sharing
Threat sharing is an agreement between parties to divide specified losses if a threat occurs, giving both an incentive to control it.
A contract splitting an installation overrun equally between two parties is an example of threat sharing.
Trigger
A trigger is an observable event or condition that warns a risk is occurring or approaching and starts a specified response.
Because a delivery confirmation is the trigger for renting, the owner checks it each week so a rental order can be placed in time.

U

Urgency
Urgency is how soon a response must start to work, taking account of preparation, orders, approvals, and other lead times.
When an event is months away but a backup venue must be booked today, the response that books it has high urgency.

W

Watch list
A watch list holds low-priority risks for scheduled review so the team can detect changes without losing them from the record.
The owner checks the watch list after a supplier change makes a previously minor threat more likely.
Workaround
A workaround is an unplanned response devised after a threat has occurred or an issue has appeared, when no prepared action covers it.
The team develops a workaround after an unexpected equipment failure occurs without a contingency plan.

About this lesson

By StudeliReport a mistake

Make your own Study Materials