Project Risk Management
BeginnerLesson 7 of 9 in Project Management Foundations Course
What you will learn
- Explain what a project risk is, tell risks apart from issues, assumptions and constraints, and describe how a project sets up its risk management.
- Tell risks apart from issuesDefine risk as uncertainty that matters to project objectives, recognize threats and opportunities, and separate risks from issues that have already happened.
- Find the risks behind assumptions and constraintsDefine assumptions and constraints, keep them in an assumption log, and test each assumption to reveal the risks it hides.
- Plan how the project will manage riskDescribe the steps of the risk management cycle, the decisions recorded in a risk management plan, and how risk appetite and thresholds set the limits the project works to.
- Tell risks apart from issues
- Use a range of techniques to find threats and opportunities, and write each risk as a clear statement of cause, event and effect.
- Use techniques to identify risksChoose and run identification techniques that find threats and opportunities from many angles, and keep identifying risks throughout the project.
- Write clear risk statements and group themDescribe each risk by its cause, uncertain event and effect, and group risks by category to spot clusters and gaps.
- Use techniques to identify risks
- Rate risks on agreed scales, rank them with a probability and impact matrix, and refine the ranking with urgency and escalation rules so that effort goes where it matters most.
- Rate probability and impact on agreed scalesUse the project's scales to rate how likely each risk is and how strongly it would affect each objective, and judge how reliable each rating is.
- Rank risks with a probability and impact matrixCombine probability and impact ratings in a matrix, read the priority bands, and apply the project's rules for threats and opportunities.
- Weigh urgency and decide what to escalateRefine priorities with proximity, urgency and other factors, judge the project's overall risk, and decide which risks belong above the project.
- Rate probability and impact on agreed scales
- Choose fitting responses for threats and opportunities, prepare contingency plans with clear triggers, and check what risk remains or newly appears.
- Choose responses to threatsSelect among avoid, mitigate, transfer, accept and escalate, and match each response to the threat it is meant to handle.
- Choose responses to opportunitiesUse exploit, enhance, share, accept and escalate to make positive risks more likely or more valuable.
- Prepare contingency plans and check what remainsSet triggers, write contingency and fallback plans, build responses into the plan, and identify the residual and secondary risks of each response.
- Choose responses to threats
- Keep a complete and current risk register, give every risk a responsible owner, and monitor risks so that responses keep working as the project moves on.
- Build and maintain a risk registerRecord each risk with the fields a team needs, write a complete entry, and keep the register current from the first risk to project closure.
- Assign risk owners and action ownersChoose the right owner for each risk, separate owning a risk from carrying out its actions, and know who decides when a risk goes beyond the project.
- Monitor risks and keep responses workingReview risks regularly, watch triggers, track response actions, and update, close or convert risks into issues as the project moves on.
- Build and maintain a risk register
Project Risk Management study guide
1Understand project risk and what shapes it
Projects depend on events that nobody can fully control: deliveries, approvals, weather, and people. Some uncertainty threatens the plan; some offers a benefit. Before choosing a response, you need to know what is still uncertain, what has already happened, and what the plan takes for granted. A clear risk approach then gives everyone shared rules for deciding which uncertainties deserve attention and who can authorize action.
1.1 Tell risks apart from issues
A risk deserves attention because something uncertain could change a project objective. That objective might concern scope, schedule, cost, quality, or the benefits people expect. Ask two questions: could the event happen, and would it matter if it did?
See both directions of risk
A threat could harm an objective. An opportunity could help one. In a 12-week office move with a budget of $250,000 and 60 staff, late desk delivery is a threat to readiness. A possible 10% discount on a large furniture order is an opportunity to spend less. Both belong in risk management: one needs protection, the other may deserve effort to capture it.
A vague concern such as "the weather" does not explain a risk. "Heavy snow on the moving weekend may stop the trucks and delay the move by a week" identifies the uncertain event and its effect. A certainty such as "the software needs testing" belongs in the work plan.
Decide whether it has happened
| Statement | Classification | Reason |
|---|---|---|
| "The city may close the street during move week." | Threat | Access might be lost. |
| "The movers’ quote is $4,000 over its budget line." | Issue | The cost problem exists now. |
| "The landlord may allow an early exit from the old lease." | Opportunity | A possible agreement could save money. |
| "The new office must pass a fire inspection." | Requirement | It states a condition the project must meet. |
An issue is a current condition or an event that has happened and needs action. "The lead developer may resign before launch" is a risk; "the lead developer has resigned" is an issue. The possible failure of the fire inspection is a risk, even though the inspection requirement itself is certain.
Move from prevention to action
Keep uncertain events in the risk register and current problems in the issue log. If a recorded risk occurs, carry out its planned response, log the issue, and update the risk’s status to show that it occurred. Keep the link between the records so the history remains clear.
Resolve an issue through a short sequence:
- Capture it in the issue log.
- Assess its effect and urgency.
- Decide on action; escalate if the decision exceeds the project manager’s authority.
- Carry out the action.
- Check the result, close the issue, and record useful lessons.
An issue can create a new risk. After the developer resigns, the departure is certain, but whether a replacement will learn the system before launch remains uncertain.
Look beyond single entries
Individual risks are the separate uncertainties recorded in the register. Overall project risk concerns all uncertainty affecting the project, including how risks combine. Several modest threats to the same deadline can make the overall delivery date doubtful.
Methods use "issue" with different breadth. PMI includes current conditions affecting objectives; APM emphasizes problems breaching or about to breach delegated tolerances and needing sponsor support. PRINCE2 also includes change requests and work that misses its specification. The practical distinction remains useful: current matters need action now; uncertain events need forward planning.
Key Takeaways
- A project risk combines uncertainty with an effect on an objective.
- Threats can harm objectives; opportunities can improve them.
- An occurred risk is handled as an issue, with both records updated.
- Overall project risk includes how separate uncertainties combine.
1.2 Find the risks behind assumptions and constraints
Every plan rests on things believed to be true and limits that must be respected. Writing them down makes it easier to see where the plan could break and which responses are possible.
Separate a belief from a limit
An assumption is something treated as true for planning without proof. "The landlord will hand over the keys at the start of week 4" lets the team schedule work, but the handover still needs checking.
A constraint is a limit the project must work within. In the office move, the old lease ends at the end of week 12, the budget is $250,000, and staff must move over a weekend to keep the business running. These limits restrict the plan. A fixed deadline leaves less room to absorb a delay and may rule out a response that simply moves the finish date.
High-level assumptions and constraints appear in the charter and scope statement. An assumption log tracks the assumptions in detail: the statement, owner, date raised, status, and follow-up action. Status might be open, confirmed, or proven false. Some teams also record constraints there.
Test what the plan depends on
Assumption analysis asks how likely an assumption is to be wrong and what would change if it were. Consider both harm and benefit. If the team assumes a permit is needed but learns that it is unnecessary, work could start sooner.
For the office move, work through the cabling assumption:
- State the belief: "The contractor will finish the network cabling by the end of week 8."
- Examine the evidence: the contractor missed deadlines on two earlier jobs.
- Trace the dependency: staff need a network to work in the new office.
- Describe the risk: "Because the contractor has missed earlier deadlines, the cabling may finish after week 8, delaying the move and possibly pushing it beyond the old lease in week 12."
- Enter the risk in the register and link it to the assumption that needs checking.
The belief is both uncertain and important, so it deserves a risk entry. The assumption that staff will keep their current monitors is much less important in this example and stays in the assumption log.
Find assumptions hidden inside estimates
An estimate may quietly depend on a specialist working full time or on an approval taking one week. Ask, "What must be true for this estimate to hold?" Check the answer with the people who supply the resource or make the decision. An estimate based on a person’s availability is weak if their manager has not agreed to release them.
A constraint is certain as a planning limit. A possible change to it is a separate uncertainty: "The board may cut the budget by 10% at the mid-year review." Record that possible decision as a risk, with its effect on the work.
Revisit the log as evidence arrives. A confirmed assumption becomes a fact. A false assumption may require replanning or may already be an issue if it is affecting the project. Keeping an old assumption marked open after it has been disproved hides the need for action.
Key Takeaways
- An assumption is an unproved planning belief; a constraint is a limit.
- Test how uncertain and how important each assumption is.
- A false assumption can reveal a threat or an opportunity.
- Ask what must be true for important estimates to hold.
- Update the assumption log when evidence confirms or disproves a belief.
1.3 Plan how the project will manage risk
Risk management helps a team make decisions with uncertainty in view. Its aim is to reduce threats and make the most of opportunities so the project is more likely to meet its objectives. Some uncertainty remains because a project creates something new.
Set up a repeating cycle
The work follows a cycle: plan the approach, identify risks, analyze them, plan responses, carry out those responses, and monitor results. Monitoring can uncover new risks or show that a rating needs to change, so the team returns to earlier steps throughout the project.
Communication runs through the cycle. A well-rated risk has little value if the person able to act never hears about it. Short review cycles in agile projects serve the same purpose: feedback on small increments reduces the risk of building the wrong thing, and stand-ups, reviews, and retrospectives reveal new uncertainty. A spike is a short, time-boxed experiment that explores technical uncertainty early; resulting response work goes into the backlog.
Agree how decisions will be made
The risk management plan records the project’s working rules. It is called a risk management approach in PRINCE2. It sets out:
- Methods, tools, categories, and the format of the register.
- Probability and impact definitions, the matrix, and priority rules.
- Roles, review frequency, reporting, and escalation routes.
- The time and budget allowed for risk work.
- Appetite and measurable thresholds for decisions.
Scale this approach to the project. A two-week internal job may need one page and a short register. A large infrastructure project needs a more formal approach, regular reviews, and independent checks. The work needed to manage risk should fit the decisions at stake.
Turn appetite into limits
Risk appetite is the amount of uncertainty a person or organization is willing to accept in pursuit of a reward. "Low appetite for safety and legal risk; moderate appetite for schedule risk on internal projects" gives a broad direction.
A risk threshold, also called a tolerance in some methods, turns that direction into a measurable limit. For the office move, the sponsor might require any risk that could delay the move by more than 10 working days or add more than $25,000 to be reported within two working days.
Apply each part of that rule. A possible $30,000 extra cost crosses the cost limit even if the schedule effect is small. A possible 12-working-day delay crosses the time limit even if the response is inexpensive. The word "or" means either breach is enough.
Give the rules clear owners
The sponsor sets appetite, approves thresholds, and decides on escalated risks. The project manager leads the process and keeps the register. Team members and stakeholders identify risks and take on agreed ownership and actions.
People’s personal comfort with uncertainty differs. Optimism may make one person dismiss a threat that another person rates highly. Written scales and thresholds give them a shared basis for discussing evidence and authority instead of treating confidence as a rating method.
Key Takeaways
- Plan, identify, analyze, respond, implement, and monitor throughout the project.
- The risk management plan sets shared methods, responsibilities, and decision rules.
- Appetite gives broad direction; thresholds make limits measurable.
- Agile feedback and spikes help reduce uncertainty early.
- Risk work is scaled to the project’s size and stakes.
- The sponsor approves limits and handles decisions beyond project authority.
2Identify and describe project risks
Useful risk identification draws on several views of the work. A supplier may see a problem that the project team misses, while an experienced user may see an opportunity. Different techniques help people bring those views forward. Clear descriptions then turn a collection of concerns into risks that can be rated, assigned, and acted on. Categories help reveal shared causes and areas the team has not yet examined.
2.1 Use techniques to identify risks
Risk identification finds and records threats and opportunities while there is time to act. Bring in people who understand different parts of the work: team members, users, the sponsor, suppliers, and subject experts. Their different knowledge helps expose blind spots.
Choose a way to hear the right people
| Technique | How it works | When it helps |
|---|---|---|
| Brainstorming | Gather ideas without judging them, then group and refine them. | A mixed group needs to explore widely. |
| Nominal group technique | People write alone, share in turn, then rank ideas. | Senior or outspoken people might dominate. |
| Interviews | Ask experienced people individually about uncertainty. | A concern is sensitive or needs specialist discussion. |
| Delphi technique | Collect anonymous expert views, summarize them, and repeat rounds. | Independent judgment matters and status could sway opinions. |
For example, a workshop about the office move might quickly focus on furniture because the procurement lead speaks first. Individual writing before discussion gives the IT and facilities staff room to raise network readiness and building access. A private supplier interview can then explore a concern that would be difficult to discuss openly.
Search the records and the surroundings
Checklists draw on risks identified on earlier projects, lessons learned, and expert knowledge. They make experience easy to reuse, including risks that were spotted but never occurred. They need other techniques alongside them because a new project can face unfamiliar risks.
Document review examines the scope, WBS, schedule, estimates, requirements, and contracts. Look for single suppliers, tasks with no slack, vague requirements, and unclear contract terms. Ask what assumptions make important estimates possible and what constraints leave the project little room to recover.
A prompt list gives broad sources to consider. PESTLE covers political, economic, social, technological, legal, and environmental factors. In the office move, those prompts can reveal material-price increases, staff concerns about commuting, delayed permits, and snow. TECOP uses technical, environmental, commercial, operational, and political categories. A category is a starting question; it still needs a specific risk statement.
Examine causes and positive possibilities
SWOT analysis separates internal strengths and weaknesses from external opportunities and threats. An experienced installation team is a strength that may support an early finish. Limited purchasing capacity is a weakness that may contribute to missed orders.
Root cause analysis works backward from a possible problem to its causes, often using a fishbone diagram. An overloaded procurement team might cause late orders, missed discounts, and contract errors. Finding that shared cause can support one useful response across several risks.
In a pre-mortem, imagine the project has already failed and ask why. Treating failure as the starting situation can make it easier to voice doubts that sound too negative during ordinary planning.
Identification continues after kickoff. A scope change, a replacement supplier, or new information from completed work can create fresh risks. Ask about both threats and opportunities during status meetings and iteration reviews, then record new risks before detailed rating begins.
Key Takeaways
- Use several perspectives and techniques to reduce blind spots.
- Nominal groups and Delphi reduce different forms of group influence.
- Checklists reuse experience; document review tests the current plan.
- Prompt lists and SWOT widen the search for threats and opportunities.
- Root cause analysis can reveal a cause shared by several risks.
- A pre-mortem starts by imagining failure and asking what caused it.
- Keep identifying risks when the work or its setting changes.
2.2 Write clear risk statements and group them
A risk statement should let someone outside the workshop understand what might happen and why it matters. Separate the conditions that exist now from the uncertain event and the effect it would have.
Build cause, event, and effect
The cause is a current fact or condition. The event is uncertain. The effect is the change to an objective if the event occurs. A useful sentence pattern is:
"Because of [cause], [uncertain event] may occur, which would lead to [effect on objectives]."
Start with the vague office-move entry "Supplier problems."
- Identify the cause: the only furniture supplier is fitting out two other offices this spring.
- Name the event: it may deliver the desks after week 10.
- Explain the effect: 60 staff would have no workstations during their first week in the new office.
- Join the parts: "Because our only furniture supplier is fitting out two other offices this spring, it may deliver our desks after week 10, leaving 60 staff without workstations in their first week."
The cause suggests where to investigate or intervene. The effect shows what the project needs to protect. A shorter "If [event], then [effect]" form works too when the cause is recorded separately.
Describe benefits with the same care
An opportunity also has a cause, event, and effect. "Because the supplier offers volume pricing above 50 desks, ordering for both floors together may earn a 10% discount, saving about $8,000 on the $80,000 furniture budget."
The saving follows from the size of the order and discount: 10% of $80,000 is $8,000. Recording the benefit makes it possible to judge whether coordinating the orders deserves effort.
Avoid four weak descriptions. "We have a new team" gives a fact without an uncertain event. "The project will be late" gives an effect without the uncertainty that could cause it. A certain task belongs in the plan. "The supplier may be late and prices may rise" combines two risks that need separate ratings and responses.
Group entries to reveal patterns
A risk category groups similar sources. A risk breakdown structure (RBS) arranges these categories in levels. For example:
- Technical: requirements, technology, quality.
- Management: estimates, resources, communication.
- Commercial: contracts and suppliers.
- External: regulation, markets, weather.
Risks can also be grouped by the WBS area or objective they affect. Several supplier risks may point to overloaded purchasing staff or dependence on one supplier. An empty external category deserves another look: the team may have missed it during the workshop.
Record each new risk promptly with a unique ID, description, category, date, and the person who raised it. Detailed rating and response planning can follow. Keeping one risk per entry allows its owner to update it without mixing several different events into one status.
Key Takeaways
- Cause is present; the event is uncertain; effect concerns objectives.
- Describe one specific risk per entry, including opportunities.
- Categories and an RBS help reveal clusters and blind spots.
- Record a new risk promptly before completing its analysis.
3Analyze and prioritize risks
A long risk list gives little guidance about where to act first. Shared scales turn judgments about likelihood and consequences into a consistent starting point for priority. The project’s matrix, the time available to respond, and the limits of the project manager’s authority then shape the decision. You will work through those judgments separately, so that a striking consequence does not quietly inflate the probability rating.
3.1 Rate probability and impact on agreed scales
Qualitative analysis rates each risk so the team can decide where to focus. Probability describes the chance of the event. Impact describes the effect on an objective if it happens. Judge these separately: a frightening consequence does not make an event more likely.
Use written scales
A project can use these probability levels:
| Rating | Description | Chance |
|---|---|---|
| 1 | Very low | Below 10% |
| 2 | Low | 10% to 29% |
| 3 | Medium | 30% to 49% |
| 4 | High | 50% to 69% |
| 5 | Very high | 70% or more |
A certain event is a fact to plan for. The scale describes uncertainty; its top category does not turn certainty into a risk.
Impact definitions depend on the objective and the project’s size. For the 12-week office move with a $250,000 budget, use:
| Rating | Schedule delay | Extra cost |
|---|---|---|
| 1 | Up to 1 day | Up to $2,500 (1%) |
| 2 | More than 1 day, up to 1 week | More than $2,500, up to $12,500 (5%) |
| 3 | More than 1 week, up to 2 weeks | More than $12,500, up to $25,000 (10%) |
| 4 | More than 2 weeks, up to 4 weeks | More than $25,000, up to $50,000 (20%) |
| 5 | More than 4 weeks | More than $50,000 |
Read endpoints carefully. An extra cost of exactly $25,000 is impact 3; a larger cost up to $50,000 is impact 4. The percentages relate these amounts to this project’s budget.
Rate the cabling risk step by step
The team estimates a 40% chance of late cabling, a delay of about 3 weeks, and extra costs of about $20,000.
- A 40% chance sits in the 30% to 49% band: probability 3.
- A 3-week delay sits above 2 and up to 4 weeks: schedule impact 4.
- An extra $20,000 sits above $12,500 and up to $25,000: cost impact 3.
- The plan uses the highest impact across objectives, so the risk’s impact is 4.
Keep the separate impact ratings in the record so the reason for choosing 4 is visible. Opportunities use the same method with impact measuring benefit: an $8,000 discount is cost impact 2, and its probability rating is 3.
Check the evidence behind the numbers
Bring together people who know the work and record why each rating was chosen. A supplier’s delivery record supports a stronger estimate than a guess about an unfamiliar supplier. Risk data quality describes that reliability. Mark weak evidence and gather more before a major decision depends on it.
Rate the risk as it stands now. An early-order action that has merely been proposed has not yet reduced the current probability; judge the residual risk after the response is carried out.
The ratings are ranks. A probability rating of 4 is not twice the chance of 2, and impact 4 is not twice the cost of impact 2. Quantitative analysis estimates effects in units such as money or days; multiplying scale ranks does not perform that analysis.
Key Takeaways
- Rate probability separately from the severity of the consequence.
- Use the same written definitions for every risk on the project.
- Rate all affected objectives and apply the plan’s impact-selection rule.
- An opportunity’s impact measures the benefit.
- Record evidence quality and improve weak estimates.
- Current ratings cannot assume that proposed responses have worked.
3.2 Rank risks with a probability and impact matrix
A probability and impact matrix turns ratings into priority bands. Probability runs along one axis and impact along the other. Each cell has a defined priority, often shown as high, medium, or low with red, amber, or green shading.
Calculate a score
A common starting rule is:
With whole-number ratings from 1 to 5, the possible scores run from 1 to 25. The office-move example uses low for 1–4, medium for 5–12, and high for 15–25. Scores 13 and 14 do not occur because no two whole numbers from 1 to 5 multiply to make them.
Apply the rule to the move:
| Risk | Probability | Impact | Score | Initial band |
|---|---|---|---|---|
| Desks delivered late | 4 | 4 | 16 | High |
| Cabling finished late | 3 | 4 | 12 | Medium |
| Servers damaged in transit | 2 | 5 | 10 | Medium |
| Bulk-order discount | 3 | 2 | 6 | Medium opportunity |
| Snowstorm during the move | 1 | 3 | 3 | Low |
For the desks, multiply 4 by 4 to get 16, then locate 16 in the high band. For cabling, 3 times 4 gives 12, the upper end of medium. Keep the threat or opportunity label visible so a high benefit is not read as a large problem.
Apply the project’s special rules
The raw score is a starting point. A project may make every threat with impact 5 high priority, whatever its probability. With that rule, the server risk is high even though its score of 10 lies in the medium numerical band.
Equal products also hide different profiles. A risk rated 4 by 2 and one rated 2 by 4 both score 8. The second has a less likely but more severe outcome. The plan may give that profile greater priority, so read the actual matrix and any override rules before choosing an action.
A score of 12 is not a precise measurement of how much worse a risk is than one scoring 10. Both depend on judgments and broad bands. Scores from projects with different scales are not directly comparable.
Connect a band to action
High risks need response planning now, a named owner, and sponsor reporting. Medium risks need responses and regular review. Low risks go on a watch list with set review intervals; they can become more serious as circumstances change.
Rank opportunities too. A double matrix can put threats on one side and opportunities on a mirrored side. A high-priority opportunity deserves attention to capture its value.
A heat map places each risk’s ID in its probability-impact cell. At the next review, moving an ID to a different cell shows a change in exposure. It also helps the sponsor notice clusters of risks with severe consequences, even when their individual probabilities are low.
Key Takeaways
- Multiply probability and impact ratings to find the score.
- Use the project’s bands and override rules to set priority.
- Equal scores can represent very different risk profiles.
- Keep low risks on a watch list and rank opportunities too.
- A heat map shows where risks sit and how their ratings move.
3.3 Weigh urgency and decide what to escalate
A priority score does not tell you when the team must act or who can authorize the response. Timing, connections between risks, and decision limits refine the initial ranking.
Compare occurrence time with action time
Proximity is when a risk could occur. Urgency is how soon a response must start to work. A late occurrence can demand an early decision if resources or approvals take time.
The desks cannot arrive late before week 10, but the supplier needs the order confirmed by week 3. Waiting until week 9 would leave little useful response time. The action is urgent even though the possible event is distant.
Now compare two risks scoring 12. Cabling could be late in week 8; weekly inspections must be agreed before work starts in week 4. A second risk concerns returning the old keys in week 12. The cabling response goes first because its useful action window closes sooner. This refines the order without pretending the cabling score has changed.
Consider how a risk behaves
Three further questions help explain priority:
- Manageability: how far can the team influence the event or its effect?
- Detectability: how much early warning would the team receive?
- Connectivity: could this event set off other risks?
A supplier problem that affects furniture, equipment, and training readiness can matter more than its isolated entry suggests. A risk with no warning may need preparation that cannot wait for a trigger. These judgments supplement the matrix; record the reasons so another reviewer can follow the decision.
Escalate through the agreed route
A risk needs escalation if it affects matters beyond the project, needs authority the project manager lacks, or exceeds a sponsor-set threshold. Send it to the sponsor or other level able to decide. A possible company acquisition that could cancel the move belongs with the executive team.
A useful escalation contains the risk description, current rating, the limit or authority problem, response options with costs, and a recommendation. Send it while there is still time for a decision. The person who accepts ownership at the higher level owns the risk; the project marks it escalated and keeps it visible in its records.
Judge whether the project is still acceptable
Overall project risk asks whether combined uncertainty threatens the project as a whole. Look at the number of high risks, clusters around the same objective, and whether exposure is rising or falling. Compare that picture with the sponsor’s appetite.
The sponsor weighs the overall picture and any single intolerable risk when deciding to continue, change, or stop. Several medium risks can together threaten delivery; one unacceptable risk can also be enough to require a different course. Revisit this judgment when evidence improves, responses take effect, or the period in which a risk could occur passes.
Key Takeaways
- Proximity concerns occurrence; urgency concerns the response deadline.
- Manageability, warning time, and risk connections can refine priority.
- Escalate beyond project authority or thresholds, with a recommendation.
- Judge overall exposure alongside any individually unacceptable risk.
4Plan responses to threats and opportunities
A response turns a risk judgment into a decision about the work. Threats may call for a change of plan, preventive action, or an agreed way to absorb the consequences. Opportunities call for action that secures or increases a benefit. Choosing a strategy is only the start: someone must carry it out, resources must be available, and the team must know when to use a prepared backup plan and how to judge the risk that remains.
4.1 Choose responses to threats
A threat response changes the work or prepares the team to handle harm. Choose an affordable, realistic action that can work in time, and agree it with the person who will own it. The aim is to bring exposure within the project’s thresholds.
Match the strategy to the change
| Strategy | What changes | Office-move example |
|---|---|---|
| Avoid | Remove the threat or its effect on the objective. | Use existing, tested cabling instead of installing new cabling. |
| Mitigate | Reduce probability, impact, or both in advance. | Order desks early and seek regular delivery updates. |
| Transfer | Shift specified financial consequences and response responsibility to a third party. | Buy transit insurance for server repairs. |
| Accept | Acknowledge the threat and decide how to live with it. | Prepare an alternative moving weekend for snow. |
| Escalate | Move the decision to the level with authority to act. | Refer possible cancellation after an acquisition to executives. |
Avoidance may require a different solution or less scope. If tested existing cabling meets the project’s needs, using it removes the particular threat associated with finishing new cabling late. That choice still needs agreement about the changed approach.
Mitigation, called reduction in some methods, acts before the event. Specialist IT movers can lower the chance of damage; backups can reduce the harm if damage occurs. These actions can be combined because they address different parts of the threat.
Know what a contract changes
Insurance, fixed-price contracts, warranties, and performance bonds can transfer specified financial effects. Check which effects are actually covered. Transit insurance can pay server repair costs, but damaged servers may still delay work and disrupt staff. The project must manage those consequences.
Some methods also list sharing a threat. Two parties might agree to split a fit-out cost overrun 50/50, giving both a reason to control it. Sharing divides an agreed consequence; transferring assigns a specified consequence to another party.
Make acceptance an explicit decision
Passive acceptance means taking no preventive action, reviewing the risk, and handling it if it occurs. Active acceptance prepares a contingency plan or sets aside time or money. An agreed alternative move weekend is active acceptance of the snow threat.
Acceptance can suit a low-priority threat or one whose possible effect is smaller than the cost of a useful response. Simply writing "monitor it" for a high threat leaves the team with passive acceptance unless a further action is agreed.
Combine responses where needed
The desks risk scores 16, high. The team orders in week 2 and obtains weekly updates: mitigation. A late-delivery penalty transfers part of the financial effect to the supplier. The team prepares to rent 60 temporary desks at $50 each for one week: active acceptance of what remains. The rental total is $3,000.
Each action needs an owner, a due date, and funding. "Be careful" gives none of those and cannot be checked at review. Put the agreed actions into the schedule and budget so the response can actually be carried out.
Key Takeaways
- Avoid removes the threat; mitigation reduces its probability or impact.
- Transfer covers specified consequences while other effects can remain.
- Active acceptance prepares resources or a plan; passive acceptance does not.
- Sharing divides an agreed threat consequence between parties.
- Responses can be combined to address different parts of a threat.
- Actions need agreement, ownership, dates, and resources.
4.2 Choose responses to opportunities
An opportunity is uncertain good news worth considering deliberately. A response can secure the benefit, improve its chance or value, or put it with a partner who can capture it. Give it an owner and review it just as you would a threat.
Decide whether to secure or improve the benefit
Exploit means taking action that makes the opportunity certain. Suppose the furniture supplier has made a firm offer: an order above 50 desks placed before the deadline earns the discount. Combining both floors into one qualifying order secures the $8,000 saving. The response removes the uncertainty about receiving that discount.
Enhance means increasing the chance or size of the benefit while uncertainty remains. An extra fit-out crew can raise the chance of leaving the old office early, but other delays could still prevent an early finish. The action improves the prospect without guaranteeing the result.
The distinction turns on the outcome, not on how hard people work. Giving a task to experienced staff is exploitation when it secures the benefit; if an early finish still depends on uncertain approvals or deliveries, the action enhances the opportunity.
Work with someone better placed to capture it
Share gives part of the opportunity’s ownership to a third party and divides the gain. The partner should contribute something that helps realize the benefit.
In the office move, the landlord can re-let the old space if the team leaves two weeks early. The parties agree to split the rent saving. At $3,000 per week, the two-week saving is $6,000; each receives $3,000. The project contributes early access to the space, and the landlord contributes the ability to find a new tenant.
An ordinary supplier payment does not by itself make a response sharing. The agreement must connect the parties to capturing and dividing the opportunity’s gain.
Accept or escalate deliberately
Accept means being ready to benefit if the opportunity arises without actively pursuing it. Some methods also use reject for a recorded decision not to pursue an opportunity, for example when the effort or added threats outweigh its value.
Escalate moves an opportunity beyond project scope or authority to people who can act. The move team might discover a spare floor suitable for a regional training center. That investment decision belongs to senior management, even if project staff first noticed it.
Pursuit can introduce extra work and new threats. Adding a crew costs money; combining orders may create coordination work. Record the response actions and check their effects. Any change to approved scope goes through change control, so a promising benefit does not quietly turn the move into a larger project.
Key Takeaways
- Exploit secures a benefit; enhance improves its chance or size.
- Sharing combines a partner’s contribution with an agreed split of the gain.
- Accepted opportunities remain visible without active pursuit.
- Escalate opportunities beyond project scope or authority.
- Opportunity responses need owners, review, and scope control.
4.3 Prepare contingency plans and check what remains
A response plan needs a clear point for action and a way to handle what remains. Prepare those details before the team is under pressure to recover from a problem.
Set a trigger and a prepared response
A contingency plan is prepared in advance and used if the risk occurs or warning signs appear. A trigger is the observable condition that starts it. A useful trigger is specific, measurable, and checked on a schedule.
For cabling, use "less than 60% complete at the week 6 inspection." If the inspection finds 45% complete, the condition has been met. The team starts the planned temporary wireless network, costing about $4,000. It does not wait until staff arrive and find no connection.
A fallback plan is the second plan if the main response or contingency fails. If the temporary wireless network cannot support work, staff will work from home for up to one week. Agree the resources and authority for that step before it is needed.
A workaround is different: it is an unplanned response devised after an issue or threat has occurred. The timing of the preparation distinguishes it from contingency planning.
Re-rate the remaining risk
Residual risk is what remains after the response has been carried out. Early desk ordering reduces probability from 4 to 2 while impact remains 4:
The score falls from high to medium under the example bands. Check the residual against the project’s thresholds. If it is still unacceptable, add further responses or obtain the sponsor’s informed acceptance.
A secondary risk is a new risk directly caused by a response. The temporary wireless network might expose client data if it is less secure than the wired network. Give this new threat its own entry, rating, owner, and response. It is a different event from the late cabling that prompted the network.
Provide resources and schedule the work
A contingency reserve is time or money in the baseline for identified, accepted risks. A management reserve is held outside the baseline under management control for unforeseen work within approved scope, including risks that were not identified. Neither term means an unrestricted fund for extra scope.
Put response actions into the schedule, budget, and work assignments, or into the agile backlog. Name the action owner and due date. A backup system that has not been ordered or funded cannot be relied on simply because its name appears in the register.
Key Takeaways
- A measurable trigger tells the team when to start a contingency plan.
- A fallback is a prepared second plan; a workaround is improvised afterward.
- Residual risk remains after a response; secondary risk is created by it.
- Re-rate residual risk and check whether it is acceptable.
- Contingency reserve sits in the baseline; management reserve sits outside it.
- Build response work into the project’s schedule, budget, and assignments.
5Own, monitor and update risks
Risk information changes as the work moves forward. A delivery date is confirmed, a warning sign appears, or an action misses its deadline. The team needs a record that shows those changes and a person who is accountable for each risk. Regular reviews connect that record to decisions, while reporting gives the sponsor a view of the project’s exposure. At closure, the same history helps future teams learn what worked and what was missed.
5.1 Build and maintain a risk register
The risk register is the central record of individual risks and how the project is handling them. Start it when the first risk is identified, update it throughout delivery, and archive it at closure. Its format can be simple, provided it supports decisions and follow-up.
Record enough to act
A complete entry needs several groups of information:
- Identity: unique ID, date raised, date updated, description, threat or opportunity, and category.
- Analysis: probability, impact, score, proximity, and the reasons for ratings.
- Response: strategy, actions, action owners, due dates, trigger, contingency, and fallback.
- Accountability and review: named risk owner, residual rating, secondary risks, and status.
Use one risk per entry and consistent scales. Keep IDs unique and never reuse them. Date updates so the team can distinguish a new judgment from an old one.
Read a complete entry
The office-move desks entry has ID R2, raised in week 1, and a commercial/supplier category. Its description explains the supplier’s workload, possible delivery after week 10, and the effect on 60 staff. Probability 4 and impact 4 give a score of 16, high. The event’s proximity is week 10, but the order is needed by week 3.
The strategy combines mitigation and active acceptance. The procurement lead places the order in week 2 with a late-delivery penalty and requests weekly updates from week 6. The trigger is no confirmed delivery date by week 6. The contingency is to rent 60 temporary desks for $3,000. Once early ordering has taken effect, the residual rating is probability 2 and impact 4, giving score 8, medium.
In a working register, replace the role title with the agreed individual’s name, such as "Jordan Lee, procurement lead." The person must know that they own the risk. The entry is open while late delivery remains possible.
Keep the status and history clear
Open means active. Occurred means the event is now handled as an issue. Escalated means ownership has passed above the project. Closed means the risk can no longer occur or has been dealt with.
Retain closed entries with their closure dates and reasons. Deleting a risk erases evidence of what the team anticipated, which response it used, and whether it worked. An occurred event also needs an issue-log entry, with the risk record updated to show the change.
Connect the register to other records
The risk management plan sets the method; the register records actual risks. The assumption log holds planning beliefs, and the issue log tracks current matters. A risk report summarizes the top risks, overall status, trends, and changes for stakeholders.
Agile teams may track risks on a board or in the backlog. The location changes, but the record still needs the risk, seriousness, owner, and response. A dated response task can link to the risk entry so its completion is visible during review.
Key Takeaways
- The register records individual risks, analysis, responses, and accountability.
- Use unique IDs, consistent scales, and dated updates.
- Keep closed entries with reasons and dates.
- Link risk records to issues, assumptions, and scheduled response work.
5.2 Assign risk owners and action owners
A risk needs one named person who makes sure it is managed. That person may ask others to do specific tasks, but accountability for the risk must remain clear.
Choose someone able to act
The risk owner makes sure responses are planned and carried out, watches triggers, and reports changes. Choose a person with knowledge of the risk, authority to influence it, and enough time to manage it. They must agree to take the role.
The person who first spots the risk is not always the best owner. A junior team member might identify a supplier problem but lack authority to change a purchase order. Put the risk with the person able to manage the supplier, and acknowledge the team member’s contribution without assigning authority they do not have.
Separate accountability from a task
An action owner, also called a risk actionee in some methods, carries out a particular response task and reports progress to the risk owner. One person may fill both roles, but delegating a task does not transfer accountability for the whole risk.
For example, Jordan Lee, the procurement lead, owns the late-desks risk. A purchasing assistant sends delivery-update requests, while Jordan decides whether the reply is satisfactory and whether to activate the rental contingency. The assistant reports completion and concerns to Jordan. Jordan remains accountable even when the assistant has finished sending the messages.
Know the supporting roles
| Role | Responsibility |
|---|---|
| Sponsor | Sets appetite and thresholds, decides on escalated risks, and approves responses beyond project authority. |
| Project manager | Leads the process, facilitates identification, keeps the register, and checks that every risk has an owner. |
| Risk owner | Manages one risk and its responses, triggers, and reporting. |
| Action owner | Completes a specific response action. |
| Team member | Identifies uncertainty, reports warning signs, and carries out agreed work. |
For the move, the procurement lead owns the desks risk, the IT manager owns server damage, and the facilities manager owns snow and cabling risks. The project manager checks these entries at reviews without taking ownership of every one.
Make escalation actionable
If the risk crosses a threshold or needs a decision beyond the project manager’s authority, the risk owner and project manager escalate promptly through the agreed route. Include the description, current rating, and recommended response. Identify the higher-level person who accepts ownership so the entry does not disappear into a general referral.
"IT" or "everyone" is too vague for a named owner. Recording a department leaves reviewers unsure whom to contact, and actions can stall while people assume someone else will act. Record the individual and check acceptance of the role when responsibilities change.
Key Takeaways
- Choose an agreed individual with knowledge, authority, and time.
- The risk owner stays accountable when an action is delegated.
- The project manager leads the process without owning every risk.
- The sponsor handles decisions beyond the project’s authority.
- Escalation needs a recommendation and an accepted owner at the higher level.
5.3 Monitor risks and keep responses working
Monitoring keeps the risk record aligned with the project as it is today. It tracks triggers and actions, checks whether responses work, updates ratings, and finds new risks. A completed response task is evidence to examine, not a reason to stop reviewing the risk.
Review on a useful schedule
Make risks a standing item in regular status meetings and review them in more depth at stage or phase boundaries. The frequency must allow triggers to be noticed in time. A weekly meeting alone is insufficient for a trigger that needs checking every day.
At each review, ask:
- What new risks have appeared?
- Have evidence, ratings, or response deadlines changed?
- Are response actions complete and effective?
- Has a trigger appeared?
- Does anything need escalation, issue handling, or closure?
Record the date and reason for each change. If an action is late, find out whether the delay has reduced the response’s usefulness and decide what must happen next.
Work through the week 6 review
The desks were ordered in week 2. At week 6, the supplier confirms delivery for week 9. The procurement lead now judges probability 2 instead of 4. With impact still 4, the score falls from 16 to 8. Record the evidence behind the reduction, while keeping the risk open because delivery has not yet occurred.
The cabling inspection finds 45% complete, below the 60% trigger. The facilities manager starts the prepared temporary wireless-network plan. The register records the trigger, decision, dated action, and follow-up. The team also checks the new network’s security risk and whether the response is ready when needed.
Update, close, or handle an issue
When a risk occurs, use the prepared contingency if one exists, log the event as an issue, and mark the risk as occurred. If there is no prepared response, the team develops a workaround. If the main response or contingency fails, use the fallback or propose a new response.
Close a risk when it can no longer happen or its response has removed it. After the moving weekend passes without snow disruption, close the snowstorm risk with the date and reason. Retain the entry. A passed date supports closure only when the relevant event can no longer occur; an unresolved delayed delivery still needs handling.
Report the picture and improve the process
Risk reporting shows top risks, exposure trends, open high risks, overdue actions, and overall exposure compared with appetite. In agile work, a risk burndown chart plots total remaining exposure across iterations; a falling line indicates reduced exposure.
A risk audit examines whether the process works: consistent identification and rating, real ownership, and action on responses. It often involves someone outside the team. This differs from a review of an individual risk’s current rating.
At project closure, record which risks occurred, which responses worked, and which risks were missed. Use those lessons to improve future checklists and estimates.
Key Takeaways
- Review triggers, actions, evidence, and new risks throughout delivery.
- Record why ratings change, not just the new number.
- Start agreed contingency actions when their trigger appears.
- An occurred risk needs issue handling and an updated risk status.
- Close risks when they can no longer occur and retain their history.
- Report overall trends and overdue actions as well as top risks.
- Audits assess the process; lessons learned improve future projects.
Project Risk Management examples
1Separate uncertainty from current problems
13 steps
- 1IntroductionStart with what the project needs
A team is moving 60 staff to a new office over 12 weeks with a budget of $250,000. Deliveries, access, and network readiness all matter to its objectives.
You will sort what might happen from what already needs action (a risk versus an issue, so each gets the right response), examine what the plan assumes (an assumption, unlike a fixed constraint), and see how the team agrees limits for risk decisions.
- 2ExplanationApply the two risk tests
A risk is uncertain and would affect an objective if it occurred. Ask: "Could this happen?" and "What would it change?"
Late desk delivery could delay staff readiness, so it is a threat. A possible supplier discount could reduce spending, so it is an opportunity. The direction of the effect changes, but both need a decision about uncertainty.
- 3ExampleDecide whether it has happened
"The movers’ quote is $4,000 above its budget line" describes a problem that exists now. It is an issue, even though the move is weeks away.
The team logs it, assesses its effect, decides on action or escalation, carries out the decision, and checks the result. "The movers may increase their quote" would instead describe an uncertain event to assess as a risk.
- 4ChallengeClassify the resignation
The lead developer has resigned. The team is unsure whether a replacement can learn the system before launch. Which part is an issue, and which is a risk?
---reveal---
The resignation is an issue because it has happened. The replacement’s possible lack of readiness is a risk because its effect on launch is still uncertain. Handle the departure now and assess the new uncertainty separately.
- 5ExplanationSeparate a belief from a limit
"Keys will be available at the start of week 4" is an assumption if it has not been confirmed. Planning can use it, but someone must check it.
"The old lease ends at the end of week 12" is a constraint. It limits the plan and the responses available. Record assumptions with owners and status in the assumption log; high-level assumptions and constraints also appear in planning documents.
- 6ExampleTest the cabling assumption
The schedule assumes the cabling contractor will finish by week 8. The contractor missed deadlines on two earlier jobs, and staff cannot work in the new office without a network.
The belief is uncertain and important. It creates a threat: cabling may finish after week 8, delaying the move and possibly pushing it beyond the week 12 lease deadline. Record the risk and keep checking the assumption.
- 7ChallengeFollow a possible budget change
The budget cap is $250,000. The board may cut it by 10% at its next review. Is the possible cut another fixed constraint or a risk?
---reveal---
The existing cap is a constraint. The cut is a risk because the decision is uncertain and could affect the work. A future decision should not replace the current approved limit before it has been made.
- 8ExplanationAgree how risk work runs
The risk management plan defines methods, categories, scales, the matrix, roles, reporting, review frequency, resources, and escalation routes.
Risk work repeats: plan, identify, analyze, plan responses, implement, and monitor. Monitoring supplies new evidence and can send the team back to earlier steps. Communication keeps the people who can act informed throughout the cycle.
- 9ExampleTurn appetite into a decision limit
The sponsor accepts some schedule uncertainty but wants large effects raised promptly. The threshold is: possible delay above 10 working days or extra cost above $25,000 must be reported within two working days.
A potential $30,000 cost crosses that limit even if time is unaffected. A potential 12-working-day delay crosses it even if extra cost is small. Either condition is enough.
- 10ConnectionInvestigate uncertainty early
Agile teams apply the same risk ideas in shorter cycles. Feedback on small increments helps discover whether the product meets people’s needs before too much work is committed.
A spike is a short, time-boxed technical experiment. Its findings improve the team’s decisions, while response tasks go into the backlog. Iterations provide review opportunities; they do not remove the need for ownership.
- 11ChallengeUse the threshold as written
A move risk could add $20,000 and delay the move by 11 working days. Does the example threshold require sponsor reporting?
---reveal---
Yes. The possible delay is above 10 working days, so it meets the time condition. Its cost being below $25,000 does not cancel that result. The threshold uses "or," so the team does not need both limits to be crossed.
- 12ChallengeConnect the belief to the decision
A key handover assumed for week 4 is now uncertain. A late handover could breach the sponsor’s time threshold. What should the team connect in its records and decisions?
---reveal---
Update and check the assumption, describe the possible late handover as a risk, and assess its effect. Apply the threshold and report through the agreed route. If the handover has already been missed and affects the work, also handle the current issue.
- 13RecapUse the right record for the next action
A useful decision starts with the status of the matter: uncertain event, current problem, unproved belief, or fixed limit. Its effect on objectives explains why it matters.
The shared approach gives the team a consistent way to assess that effect and decide who can authorize a response. As evidence changes, update the record that supports the decision.
2Find risks and turn them into clear entries
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake concerns usable
- 2ExplanationBring different knowledge into the search
- 3ConnectionChoose privacy or anonymity when useful
- 4TipCombine experience with current evidence
- 5ExplanationFind causes and overlooked possibilities
- 6ChallengeChoose a second method
- 7ExampleIdentify what exists now
- 8ExampleAdd the uncertain event
- 9ExampleShow why the event matters
- 10Key InsightUse categories to ask better questions
- 11ChallengeRepair an effect-only entry
- 12RecapCarry a clear entry into analysis
3Rate the cabling threat and refine its priority
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionBuild a priority you can explain
- 2ExplanationRate likelihood on its own
- 3ExampleRate the schedule consequence
- 4ExampleSelect the impact required by the plan
- 5ChallengeCheck the basis for a lower rating
- 6ExampleMultiply and read the band
- 7ExampleApply an impact override
- 8ChallengeDo equal products settle priority?
- 9TipKeep benefits and low risks visible
- 10ExplanationRead the action deadline
- 11ConnectionLook for warning and chain effects
- 12ExplanationSend the decision to the right level
- 13ChallengeChoose between two equal scores
- 14ChallengeCombine priority and overall exposure
- 15RecapKeep the reasoning behind the rank
4Choose responses and prepare the backup plan
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionTurn the rating into work
- 2ExplanationRemove a threat or reduce it
- 3ExampleKnow what insurance covers
- 4ExplanationPrepare while accepting uncertainty
- 5ExampleCombine the desk responses
- 6ChallengeMatch the response to the result
- 7ExplanationSecure a benefit or improve its chance
- 8ExampleShare a benefit with a capable partner
- 9ChallengeCheck whether the discount is secure
- 10ExplanationDefine an observable trigger
- 11ExampleUse the contingency and fallback
- 12ExampleRe-rate the risk after action
- 13ConnectionLook for a new risk caused by the response
- 14ExplanationPut resources in the right place
- 15ChallengeName the risk that remains and the new one
- 16ChallengeJoin the strategy to the monitoring decision
- 17RecapMake the response ready to use
5Keep the risk record connected to action
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionUse the register during delivery
- 2ExplanationBuild an entry that supports a decision
- 3ExampleRead the late-desks entry
- 4ChallengeKeep a closed entry useful
- 5ExplanationAgree one accountable risk owner
- 6ExampleDelegate a task without losing accountability
- 7ChallengeDecide who owns the next decision
- 8ExampleUse the week 6 delivery evidence
- 9ExampleAct when the inspection trigger appears
- 10ConnectionReview the process as well as the entries
- 11ChallengeCheck whether a date really closes a risk
- 12ChallengePrepare the next status discussion
- 13RecapKeep decisions current and traceable
Project Risk Management practice questions
Set 1: Recognize risks and choose a first response10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Turn risk descriptions into practical decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Connect ratings, responses, and ownership10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Judge the evidence behind a risk decision10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Make integrated risk decisions as a project changes10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Action owner
Active acceptance
Assumption
Assumption analysis
Assumption log
Avoidance
B
Brainstorming
C
Connectivity
Constraint
Contingency plan
Contingency reserve
D
Delphi technique
Detectability
Document review
E
Enhancement
Escalation
Exploitation
F
Fallback plan
H
Heat map
I
Impact
Issue
Issue log
L
Lessons learned
M
Manageability
Management reserve
Mitigation
N
Nominal group technique
O
Opportunity
Opportunity acceptance
Opportunity rejection
Opportunity sharing
Overall project risk
P
Passive acceptance
Pre-mortem
Probability
Probability and impact matrix
Project manager
Project risk
Project sponsor
Prompt list
Proximity
Q
Qualitative risk analysis
R
Residual risk
Risk appetite
Risk audit
Risk breakdown structure
Risk burndown chart
Risk category
Risk cause
Risk checklist
Risk data quality
Risk event
Risk interview
Risk management plan
Risk monitoring
Risk owner
Risk register
Risk report
Risk score
Risk threshold
Risk transfer
Root cause analysis
S
Secondary risk
Spike
SWOT analysis
T
Threat
Threat sharing
Trigger
U
Urgency
W
Watch list
Workaround
About this lesson