Project Monitoring and Control

Project Monitoring, Control and Closing

Learn how to keep a project on track once the work starts and how to bring it to a clean finish. You will compare progress with the approved plan and write clear, honest status reports, follow progress on agile boards and burn charts, and measure performance with planned value, earned value and actual cost and the schedule and cost indices built from them. You will also log and escalate issues, take every change through one controlled process, check deliverables against their acceptance criteria, and close a project with formal acceptance, a proper handover and lessons the next project can use.

BeginnerLesson 9 of 9 in Project Management Foundations Course

What you will learn

  1. Compare actual performance with the approved plan, decide when a variance needs action, and report status clearly and honestly in predictive and adaptive projects.
    • Compare actual performance with the plan
      Use the baselines, performance data and agreed thresholds to spot variances early and choose a corrective or preventive action.
    • Write clear and honest status reports
      Decide what a status report contains, use traffic-light ratings with defined criteria, and match the report to its audience and schedule.
    • Track progress in adaptive projects
      Read task boards, burndown and burnup charts and velocity to follow progress in iterative and agile work, and combine them with sponsor reporting in hybrid projects.
  2. Turn the budget, the schedule and the work completed into planned value, earned value and actual cost, calculate the basic variances and indices, and explain what they say about the project.
    • Find planned value, earned value and actual cost
      Define the three earned value measures, calculate them for a status date, and measure percent complete in a way others can check.
    • Calculate schedule and cost variances and indices
      Apply SV, CV, SPI and CPI, read their signs and sizes correctly, and avoid the classic formula mix-ups.
    • Interpret earned value results and decide what to do
      Diagnose a project's situation from its indices and an earned value chart, compare the results with thresholds, and recognize the limits of the measures.
  3. Keep problems and changes under control: log issues and resolve or escalate them, and decide every proposed change through one agreed process before the plans and baselines move.
    • Recognize and log project issues
      Tell issues apart from risks, defects and change requests, and record them in an issue log that makes ownership and progress clear.
    • Resolve and escalate issues
      Analyze an issue's impact, choose and track a response, and escalate when the issue goes beyond the project manager's authority.
    • Run a change request through integrated change control
      Follow the steps from change request to decision, analyze the impact on every part of the project, and update the plans and baselines when a change is approved.
    • Keep scope and deliverable versions under control
      Prevent scope creep and gold plating, manage the versions of deliverables with configuration management, and handle change in adaptive projects.
  4. Make sure the project's outputs meet their requirements: tell quality assurance from quality control, check deliverables against acceptance criteria, and deal with defects.
    • Explain quality, quality assurance and quality control
      Define quality in project terms, separate checking the process from checking the product, and explain why preventing defects costs less than finding and fixing them.
    • Inspect and test deliverables and handle defects
      Check deliverables against acceptance criteria with inspections, reviews and tests, record and fix defects, and pass verified work on for acceptance.
  5. Bring a project or phase to a controlled end: confirm acceptance, settle contracts, hand over to the people who will use and support the result, close the administration and record lessons for future projects.
    • Confirm acceptance and close contracts
      Check the closure criteria, obtain formal sign-off for the deliverables, close supplier contracts and close a project that ends early.
    • Hand over the result and complete administrative closure
      Transfer the deliverables to operations with what users and support staff need, release the team, close the finances and write the final project report.
    • Capture and apply lessons learned
      Gather lessons throughout the project, write them so that others can act on them, and make sure future projects use them.

Project Monitoring and Control study guide

5 chapters

1

Find out where the project stands

A useful progress check connects evidence to a decision. You need to know what the approved plan required, what work is actually complete, and whether a difference needs action. Reports then make that comparison clear to the people who can help. In adaptive work, boards and burn charts provide a closer view of the same question: how much usable work is moving through the team, and what is blocking it?

1.1 Compare evidence with the approved plan

Monitoring starts with a practical question: what has changed since the last check? Collect evidence, compare it with the approved plan, and investigate the differences. Controlling is the decision and action that follow. Both continue throughout delivery and closure.

Keep a stable reference

A baseline is an approved plan used for comparison. The scope baseline contains the scope statement, work breakdown structure and WBS dictionary. The schedule baseline fixes the approved dates; the cost baseline assigns the approved budget over time. Together they form the performance measurement baseline.

Update working plans and forecasts as new information arrives. Change a baseline only through approved change control. Moving a milestone in the baseline simply because the team is late removes the evidence of the delay. An updated forecast can show a later finish while the approved baseline still shows the original commitment.

Turn observations into decisions

Work performance data are raw facts, such as “testing started May 6.” Work performance information puts them against the plan: “testing started two days late.” A work performance report presents that information for a decision, perhaps on a dashboard.

Follow a repeating cycle: measure, compare, analyze, decide, act, and report. For a task planned evenly over 10 days, six days should produce 60% completion. If only 40% is complete, the gap is 20 percentage points, equivalent to two planned days of work. Investigation finds that a tester is absent. Borrowing a tester for three days is a possible response; first check availability, cost and the effect on other work.

Use the agreed limits

A variance is a difference from the plan. Tolerance sets the amount the project manager can handle without a higher decision. A sponsor might allow cost to vary by 5% and a milestone by one week. Check both the current variance and the forecast. Escalate as soon as a forecast threatens to exceed the authorized limit.

This is management by exception. It gives the project manager room to manage while bringing larger decisions to the sponsor or steering group. Chasing every tiny difference wastes effort; waiting until a limit is actually exceeded loses recovery time.

Match the action to the problem
ActionPurposeExample
Corrective actionBring performance back into lineAdd a shift after falling behind
Preventive actionReduce a future varianceBook an inspector before demand rises
Defect repairFix unmet requirementsReplace an incorrectly labeled panel

An action that changes a baseline needs change approval first. A sensible recovery idea does not create authority to increase the budget or change the agreed scope.

Measure completed work

Check scope, quality, risks, issues, resources and stakeholder engagement alongside time and cost. Use evidence such as accepted deliverables, milestones reached, tests passed or meters of cable installed. Split large tasks into smaller pieces with clear completion criteria. “90% complete” reported for several weeks gives little help in deciding what remains. Spending half the budget is evidence of cost, not proof that half the work is finished.

Key Takeaways

  • Baselines change only through approved change control.
  • Compare objective evidence with the plan before choosing an action.
  • Escalate when a forecast threatens the agreed tolerance.
  • Corrective action, preventive action and defect repair serve different purposes.
  • Money spent does not measure work completed.

1.2 Write a report people can act on

A status report should help its reader make a decision. State what is happening, how it compares with the plan, and what happens next. An honest warning with an owner and an action is more useful than a reassuring color without evidence.

Separate three views

Status describes the position at a particular date. Progress describes results achieved during a period. A forecast estimates the position ahead, such as the expected finish date. One regular report often combines all three. Include the reporting date and period so readers know how current the evidence is.

Give the status of scope, schedule, cost and quality against the baselines. Add accomplishments, next-period work, upcoming milestones, the main risks and issues with owners, and decisions or help needed. Lead with the point the reader must act on. “Held 12 meetings” reports effort; “two of five milestones met” reports results.

Give colors a shared meaning

Traffic-light ratings are often called RAG status. Green means on track and within thresholds. Yellow, also called amber, signals risk or a small drift with recovery action. Red signals a tolerance breach or a need for a higher decision. Define the boundaries before reporting starts.

For example, a team agrees that a milestone forecast less than one week late is yellow and one week or more late is red. A seven-day forecast delay is red under that rule. The team also needs a rule for the overall color; many organizations use the worst area. Do not quietly average away a red schedule with green cost and quality.

Write a complete status line

Use fact against plan, cause, action, and request:

“Schedule: Yellow. Course design is 75% complete against 100% planned at week 8. The subject expert was unavailable for two weeks. A second designer will join in weeks 9 and 10 to protect the week 12 pilot. Approval of $3,000 is needed by Friday.”

The line makes the shortfall visible and gives the sponsor a specific decision and deadline. If a cause is still being investigated, say what is known and assign that investigation; a confident guess can send recovery work in the wrong direction.

Choose the right detail

Sponsors need exceptions, decisions and a short overall view, often monthly or at phase ends. A forecast tolerance breach needs an exception report immediately. Team members need detailed task information more often, usually daily or weekly. Customers need milestone and acceptance information. The communication plan states who receives each report, when and in what form.

A milestone chart can compare approved and forecast dates. A Gantt chart can show task progress; a trend chart can show whether variance is growing. Add a short explanation of causes and actions so the visual supports a decision. Send reports before status meetings and use the meeting to resolve red and yellow items, with owners and dates for agreed actions.

Report trouble while help can work

Watermelon reporting means green reports conceal a troubled project. It often grows where bad news is punished or people hope to recover quietly. Rate the evidence honestly and give the recovery plan. A vague “mostly on track” leaves readers unable to judge whether they need to intervene.

Key Takeaways

  • Report status, recent progress and the forecast with a clear date.
  • Define traffic-light criteria and the overall-rating rule in advance.
  • A useful status line gives the fact, cause, action and request.
  • Match detail and timing to the reader.
  • Use meetings for decisions and problem solving.
  • Report yellow or red when evidence supports it.

1.3 Read boards and burn charts

Adaptive teams deliver usable work in short iterations, often one to four weeks long. Progress is visible in working increments and completed work items. A board shows flow; burn charts show how completion relates to time and scope.

Watch where work waits

A task board moves cards through columns such as “To do,” “In progress,” “Testing” and “Done.” Work-in-progress limits cap the cards allowed in a column. If cards build up in Testing, testing is a bottleneck. Starting more work may enlarge the queue while leaving the bottleneck untouched. The visible board acts as an information radiator, giving people a shared view without needing a separate report each time.

The daily stand-up coordinates the day and exposes blockers. The iteration review lets stakeholders inspect the product and give feedback. The retrospective examines the team's way of working and chooses improvements. A product problem and a process problem need different conversations, even when one reveals the other.

Read remaining work

A burndown chart places time on the horizontal axis and remaining work on the vertical axis. The ideal line falls to zero. In a 10-day iteration with 60 points, it falls by six points per day. At day 5, the ideal remaining work is 30 points. If 36 remain, the team has six more points remaining than the ideal line.

A line above the ideal indicates that work is behind that planned pace; a line below indicates that it is ahead. Ask about blockers and changes in scope before deciding why the lines differ. A burndown shows the amount remaining but does not separate new work from slow completion.

Separate completion from scope growth

A burnup chart shows completed work rising toward a separate total-scope line. If release scope rises from 200 to 220 points, the scope line moves up by 20. The completed line still shows what the team delivered. This helps explain why steady delivery can coexist with a finish that keeps moving away.

Use velocity for one team

Velocity is work completed in an iteration, usually measured in story points. Three iterations completing 18, 22 and 20 points average 20 points. If 220 points are in scope and 120 are complete, 100 remain. At that pace, they need about five more iterations. This is a planning estimate; it depends on the team's future pace and the remaining scope.

Count only work meeting the definition of done, the shared completion standard. A story that is 90% finished at iteration end earns no completed points yet. Partial credit hides work still needing tests or other finishing steps. Each team sizes its own points, so comparing team velocities is misleading. Inflating estimates changes the number without increasing delivery.

Connect team and sponsor views

A hybrid project can use a board for development and still report milestone, budget and risk information to its sponsor. Translate the team's measures into an understandable delivery outlook: “120 of 220 points are done. At 20 points per two-week iteration, about five iterations remain, matching the release planned ten weeks from now.” Keep the scope and pace behind that outlook visible when reporting changes.

Key Takeaways

  • A board shows flow and queues; WIP limits constrain simultaneous work.
  • Burndown tracks remaining work; burnup separates completed work from total scope.
  • Velocity is a planning measure for the same team.
  • Only work meeting the definition of done earns completed points.
2

Measure work against its budget

A spending total cannot tell you whether a project is doing well. You also need the budgeted value of the work that should be complete and the work that actually is complete. Earned value brings those quantities together at one status date. The calculations show schedule and cost performance, while the dates, quality checks and underlying records help you decide what the numbers mean and where action is needed.

2.1 Build planned value, earned value and actual cost

Earned value management combines scope, schedule and cost. It gives completed work a value based on its approved budget, so you can compare achievement with both the plan and the actual cost. Choose a status date and measure everything up to that date.

Ask three different questions
MeasureQuestion it answersWhere it comes from
Planned value, PVWhat work should be done by now?Time-phased budget
Earned value, EVWhat work is actually done?Completion evidence valued at budget
Actual cost, ACWhat has the work cost?Costs incurred

Budget at completion (BAC) is the budget for all planned work in the cost baseline. Management reserve is outside it. The training rollout has budgets of $8,000 for needs analysis, $12,000 for course design, $10,000 for materials and $20,000 for delivery. BAC is $50,000.

PV accumulates as work is scheduled. Its cumulative graph is often an S-curve: slow at the start, steeper during delivery, then flatter near completion. At the planned finish, cumulative PV equals BAC. Older records may call PV, EV and AC “BCWS,” “BCWP” and “ACWP.” They name the same three measures.

Work through the week 8 position
Work packageBudgetPVCompleteEVAC
Needs analysis$8,000$8,000100%$8,000$9,000
Course design$12,000$12,00075%$9,000$8,500
Materials$10,000$4,00020%$2,000$2,500
Delivery$20,000$00%$0$0
Total$50,000$24,000—$19,000$20,000

Course design earns 75% of its $12,000 budget, or $9,000. Materials earn 20% of $10,000, or $2,000. Add earned amounts, not completion percentages: the packages have different budgets. The total EV of $19,000 is below PV of $24,000 and below AC of $20,000.

Choose a completion rule before work starts

Subjective guesses make progress easy to overstate. Use an agreed rule consistently:

  • 0/100: earn nothing until completion; useful for short tasks.
  • 50/50: earn half at the start and half at completion.
  • 20/80: earn 20% at the start and 80% at completion.
  • Weighted milestones: earn a set share when each milestone is met.
  • Physical measurement: use counted units of completed work.

A started but unfinished $6,000 package earns $0 under 0/100, $3,000 under 50/50 or $1,200 under 20/80. A $10,000 document with weights of 30% for draft, 20% for review and 50% for approval earns $5,000 after draft and review. Laying 120 of 400 meters of cable gives 30% physical completion.

Keep the comparison consistent

Use the same status date, unit and cost basis for all three measures. Cumulative EV needs cumulative AC, not just this month's cost. If the budget includes labor and materials, AC must include both. Hours can replace money when all three measures use hours consistently. EV cannot exceed BAC. Money spent and work scheduled are neither proof of completion nor substitutes for EV.

Key Takeaways

  • PV values scheduled work; EV values completed work; AC records cost incurred.
  • BAC is the total cost baseline and excludes management reserve.
  • Value each package using its own budget and completion rule.
  • Choose completion rules during planning and apply them consistently.
  • Match the status date, units, cost basis and reporting period.

2.2 Calculate variances and performance indices

Start each basic performance formula with earned value. Then choose whether you are comparing completed work with the plan or with its actual cost. Variances subtract; indices divide. This keeps the four measures distinct.

Choose the comparison
MeasureFormulaMeaning of an unfavorable result
Schedule variance, SVEV−PVNegative: less work done than planned
Cost variance, CVEV−ACNegative: work cost more than its budget
Schedule performance index, SPIEV/PVBelow 1: behind the planned work
Cost performance index, CPIEV/ACBelow 1: over cost for completed work

Zero variance means on plan; a positive variance is favorable. An index of 1 means on plan; above 1 is favorable. The indices have no unit. Variances use the earned value unit, usually money, so SV does not tell you the number of days late.

Calculate a complete example

A project has BAC of $80,000. Half the work was scheduled by month 4, giving PV of $40,000. Actual completion is 35%, giving EV of $28,000. AC is $32,000.

  1. Subtract planned value from earned value: SV is $28,000 minus $40,000, or −$12,000.
  2. Subtract actual cost from earned value: CV is $28,000 minus $32,000, or −$4,000.
  3. Divide earned value by planned value: SPI is 28,000÷40,000, or 0.70.
  4. Divide earned value by actual cost: CPI is 28,000÷32,000, or 0.875, rounded to 0.88.

The project has completed 70% of the budgeted work scheduled by this date. It earns 87.5 cents of budgeted work per dollar spent. It is behind schedule and over cost, even though it has spent less than the $40,000 scheduled budget.

Apply the same method to the rollout

At week 8, PV is $24,000, EV is $19,000 and AC is $20,000. SV is −$5,000, CV is −$1,000, SPI is about 0.79 and CPI is 0.95. The work shortfall against the plan is greater than the cost shortfall against the budget for completed work.

Express a variance as a percentage

Divide SV by PV for the schedule variance percentage. Divide CV by EV for the cost variance percentage. Multiply each ratio by 100 to express it as a percentage.

For the month 4 example, −12,000÷40,000 gives −30% schedule variance. For cost, −4,000÷28,000 gives about −14.3%. These percentages help compare projects of different sizes and apply a rule such as escalating a cost variance worse than −10%.

Avoid the tempting shortcuts

Comparing AC with PV mixes spending with scheduled work. If PV is $50,000, EV is $36,000 and AC is $45,000, the project is not $5,000 under cost. It spent $45,000 on work budgeted at $36,000, so CV is −$9,000 and CPI is 0.80. SPI is 0.72.

Reversing either division also reverses the signal: AC divided by EV looks greater than 1 when cost performance is poor. Keep EV first, select PV for schedule or AC for cost, and round indices only after calculating from the full values.

Key Takeaways

  • All four measures begin with EV.
  • SV and SPI compare EV with PV; CV and CPI compare EV with AC.
  • Negative variances and indices below 1 are unfavorable.
  • SV is a budget-value gap, not a delay in days.
  • SV% uses PV as its denominator; CV% uses EV.
  • Round at the end and never judge cost from AC against PV.

2.3 Turn earned value results into action

The numbers identify a performance pattern. They do not identify its cause by themselves. Read schedule and cost together, compare them with the agreed thresholds, and then check the detailed evidence before selecting a response.

Read the two indices together
SPICPIInterpretation
At least 1At least 1On or ahead of planned work; on or under cost
Above 1Below 1Ahead of planned work but over cost
Below 1Above 1Behind planned work but under cost for what is complete
Below 1Below 1Behind planned work and over cost

Overtime or extra staff may buy speed at a higher cost. A delayed activity may explain a low SPI, but it does not explain a high CPI: that separate result could reflect lower rates, cheaper materials or generous estimates. Investigate the schedule and cost findings separately. Favorable figures still need checks for padded estimates or reduced quality.

Read the chart at one date

An earned value chart plots cumulative PV, EV and AC against time. Locate the status date and compare the lines vertically. EV below PV shows less work completed than scheduled. AC above EV shows that the completed work cost more than its budget. The gaps correspond to SV and CV; the horizontal axis does not turn a vertical money gap into days of delay.

Suppose the rules are green at 0.95 or higher, yellow from 0.90 to below 0.95, and red below 0.90. The rollout's CPI of 0.95 is green, while SPI of about 0.79 is red. Schedule recovery needs attention. Options include changing the sequence, adding people to critical work or proposing a scope reduction. A baseline change still needs approval.

Look beneath the total

An overall CPI of 0.95 can hide uneven performance. Needs analysis has CPI of 8,000÷9,000, about 0.89. Course design has 9,000÷8,500, about 1.06. Materials have 2,000÷2,500, or 0.80. Investigating materials may reveal a problem that the overall figure makes look modest.

Watch trends too. A CPI moving from 0.98 to 0.95 to 0.91 is deteriorating. Each report should explain what action is being taken and who owns it. Waiting for the last number to become severe loses time.

Keep dates and quality beside the indices

SPI weighs work by budget. It does not show whether the critical path is on time. Ahead-of-plan noncritical work can offset a late critical activity in the total. Check the schedule network, critical activities and milestone forecasts.

At completion, EV equals BAC. Once the planned finish has passed, PV also equals BAC. A $50,000 project planned for week 10 but finished in week 13 therefore ends with SPI of 1 and SV of zero. Its three-week delay remains visible in the dates.

Check the inputs before diagnosing

Late invoices can make AC appear too low. Optimistic completion estimates can make EV too high. A system still using the old baseline after a change gives an outdated PV comparison. Check costs incurred, completion evidence and approved baseline versions. EVM does not measure quality: work later found defective may overstate achievement and create rework. Review test and acceptance evidence alongside the financial measures.

Key Takeaways

  • Read cost and schedule as separate findings before explaining their causes.
  • Apply agreed thresholds and investigate work-package results and trends.
  • Check critical-path and milestone dates alongside SPI.
  • At completion, SPI can equal 1 even after a late finish.
  • Reliable indices need reliable costs, completion evidence and baseline versions.
3

Resolve problems and control changes

Projects encounter problems and useful new ideas while work is underway. An issue needs a clear owner and a response; a proposed change needs an informed decision by someone with authority. These controls connect when resolving a problem would alter the approved plan. Keeping the logs linked and deliverable versions clear lets people act on the decision without losing track of what was agreed or why it changed.

3.1 Make an issue visible and owned

A concern becomes manageable when people can see what happened, why it matters and who will take it forward. An issue is a current condition or event that affects, or is certain to affect, project objectives and needs action. A risk is still uncertain.

Decide what you are recording

“The supplier might deliver late” is a risk. “The supplier confirms delivery will be eight working days late” is an issue. You do not need to wait eight days to log it: the confirmed delay already needs action.

When a risk occurs, update or close its risk entry and open an issue. Carry out the planned response if one exists. An unplanned response to a problem that has occurred is a workaround. Keeping the link to the risk record helps people see which preparation worked and what was missing.

Recognize related records
Record or typeWhat it deals with
Problem or concernA current difficulty, such as a resource conflict
Request for changeA proposal for something new or different
Off-specificationAn actual or expected departure from specification
Question needing a decisionA matter that cannot progress without an answer
DefectA deliverable that fails a requirement

Many organizations use the issue log to capture several of these types, then route change requests to change control. Individual defects normally belong in the defect log through quality control. Repeated defective supplier parts may also need a project issue when they threaten the delivery date. The logs serve different purposes and can refer to the same underlying event.

Write enough for someone else to act

An issue log, also called an issue register, needs an ID, a specific description, the date and person raising it, type, impact, priority, one owner, actions and target dates, status, and the eventual resolution.

For example: “I-014. Supplier email of May 12 confirms servers will arrive eight working days late. Installation and go-live are affected. High priority. Owner: J. Rivera. Assess response options by May 14. Status: open.” This tells a new reader more than “IT problem.” Record evidence and the effect on objectives, not just a broad topic.

A log can be a shared table or a tool with assigned records. What matters is that the team can find the current entry and review it. Personal email alone hides actions from people who need to coordinate them.

Set priority using two questions

Impact asks how much scope, schedule, cost, quality or benefits are affected. Urgency asks how soon action is needed. A payroll error one week before go-live combines high impact and urgency. A small spelling error in an internal guide has a different priority. A quiet but severe issue can deserve attention before a frequently discussed minor one.

Assign one accountable person

Every issue needs one named owner. A department cannot personally chase an action, bring options to a meeting or confirm that a response worked. The owner coordinates that work and reports progress; other people may perform the technical tasks. Review the log regularly so priorities and dates remain useful as the project changes.

Key Takeaways

  • An issue is current or certain; a risk remains uncertain.
  • Link a realized risk to its issue and carry out the planned response.
  • Record the event, impact, owner, action and date clearly.
  • Set priority using both impact and urgency.
  • One named person drives each issue to resolution.

3.2 Choose a response and escalate in time

Logging a problem starts the work; it does not resolve it. The owner needs to assess the impact, compare responses, obtain any higher decision, and track the action until its result is confirmed.

Work through the response

Capture the issue, assess priority, assign an owner, identify options, decide within authority, act and monitor, then close and communicate the resolution. If the decision exceeds the project manager's authority, escalation belongs before the action requiring that authority.

Begin with the effect on objectives. A supplier delay does not automatically move the end date by its full length. Total float is the delay an activity can absorb without moving the project's end date.

In the training rollout, installation is delayed eight working days and has three days of total float. The first three days use the available float; the remaining five move the end date if nothing else changes. Installation then has no float left. Check the schedule network when assessing options, because another task may also depend on the delivery.

Compare workable options

For the late servers, the team might accept the five-day delay, rent temporary servers for $1,500, re-sequence installation and testing using existing test servers, or request a later go-live date. Compare cost, time saved and risk. Check that rental equipment meets the technical need and that re-sequenced work respects dependencies.

Give the chosen response’s actions owners and dates, then track whether it saves the expected time.

Take the right decision upward

Suppose the project manager can handle an end-date movement of up to three working days. The five-day forecast slip exceeds that tolerance. Escalate now, even though go-live is still in the future. The agreed path might be team member to project manager, then sponsor, then steering group.

A useful escalation gives the issue, measured impact, options and recommendation. “Servers are late; please help” transfers an unexplained problem. “Eight days late, three days float, five-day end-date effect; recommend temporary servers for $1,500” gives the decision maker something concrete to assess. Include the decision deadline if waiting would remove a viable option.

Connect the logs when the plan must change

Moving go-live, adding budget or removing scope changes a baseline and needs a change request. Keep the issue entry for the problem and the change entry for the proposed plan change and its decision. Cross-reference their IDs. Escalation itself is not approval to alter a baseline.

Close the loop

At regular reviews, follow up overdue actions, update status and reassess priority. Close the issue after resolution is confirmed and recorded, and tell affected people. Age alone is no reason to close an unresolved issue. At project end, transfer remaining issues to named people in the receiving organization.

Investigate the cause as well as the symptom. The server delay began with an order placed without checking stock. Confirming stock before future orders addresses that cause; renting servers only treats this occurrence.

Key Takeaways

  • Use float when assessing the effect on the end date.
  • Compare response cost, time saved and risk.
  • Escalate a forecast tolerance breach before it occurs.
  • A baseline change needs a linked change request.
  • Confirm and communicate resolution before closing an issue.
  • Address the cause to reduce repeat problems.

3.3 Decide changes before changing the plan

A small scope addition can need more design time, testing, money and support. Integrated change control considers those effects together and puts the decision with the authorized person or group. Its purpose is to make change deliberate and informed.

Capture a complete proposal

Anyone involved can raise a change request. Write it down and enter it in the change log. Requests can concern new requirements, changed documents or deliverables, baseline-changing corrective or preventive action, or repairs to items under formal control. A conversation with a stakeholder does not authorize a team member to start the work.

Describe the proposed change and why it is needed. Analyze effects on scope, schedule, cost, quality, risk, resources and benefits. Identify alternatives, including what happens if the request is rejected or deferred. An analysis limited to purchase cost can miss testing time or a new operational risk.

Follow the decision through
  1. Raise and log the request.
  2. Analyze the full impact and options.
  3. Obtain an approve, reject or defer decision from the authorized person or group.
  4. Communicate the decision to everyone affected.
  5. For approval, update plans, baselines and affected documents, then implement.
  6. Verify the result and close the entry.

Rejected and deferred requests remain in the log with reasons. A change control board (CCB) is a formally selected group that decides requests within its authority. Delegation can make small decisions quicker. For example, a project manager may approve costs up to $2,000 and delays up to three days; a request must meet both limits to stay within that delegation.

Trace one approved addition

HR asks for an extra e-learning module in the training rollout. Sixty design hours at $100 per hour add $6,000. The end moves from week 20 to week 22; the week 12 pilot stays unchanged. The new platform also adds a risk because the team has not used it before.

The request exceeds the project manager's limit. The board approves the module and $6,000 of additional funding. BAC rises from $50,000 to $56,000. The scope baseline gains the module, the schedule baseline records week 22, and the cost baseline and PV curve are updated. Communicate the decision so designers, testers and the sponsor work from the same approved plan. Verify the new module against its agreed requirements when complete.

Know where reserves belong

Contingency reserve is already inside the cost baseline for identified risks, used as the risk plan describes. Management reserve sits outside it for unforeseen work within approved scope. Its use needs approval and increases the cost baseline. A new requirement needs authorized funding for the expanded scope; it is not unforeseen work within the original scope.

After a change is approved, measure performance against the updated baseline. Keep the change history so people can explain how commitments moved. An approval with an unchanged budget system or old schedule circulating is incomplete control.

Keep problems and decisions connected

The issue log tracks problems and resolutions. The change log tracks proposals and decisions. A problem can prompt a request, and an approved change can create risks or issues. Link entries so readers can trace the cause, decision and implementation without merging their different jobs into a vague action list.

Key Takeaways

  • Log and analyze requests before implementation.
  • Assess schedule, quality, risk and resources as well as cost.
  • Obtain the decision from the authorized person or board.
  • Communicate approval and update every affected baseline and document.
  • Use reserves according to their purpose; fund new scope through approval.
  • Verify implementation before closing the change entry.

3.4 Protect scope and use the right version

Changes become difficult to control when people start extra work informally or use different versions of the same deliverable. Scope control decides what the project will deliver. Configuration management keeps the approved characteristics and versions clear.

Spot uncontrolled additions

Scope creep is uncontrolled growth without matching adjustments to time, cost or resources. Three extra reports that each seem to need only one day still add three days of unplanned work. Record the requests and assess their combined effect.

Gold plating is an extra feature the team adds on its own, beyond the agreed requirements. It uses resources and adds risk even if the team thinks the customer will like it. Propose useful ideas through the change process so the customer and authorized decision maker can judge their value.

Clear scope and measurable acceptance criteria give requests a reference point. Use one request channel, supported by the sponsor. A useful response is: “Thanks, I'll log that as a change request so we can look at its effect on the dates and budget.” It acknowledges the idea and starts an assessment without making an unauthorized promise.

Control the delivered version

A configuration item is a deliverable or component whose characteristics and versions are controlled. Change control decides whether a change should happen; configuration management records exactly what each version contains and how it changed.

Its activities are:

  • Planning which items are controlled and how.
  • Identification with a unique ID and version number.
  • Control of changes to baselined items, including check-out and check-in.
  • Status accounting: current versions and change histories.
  • Verification and audit: checking delivered items against records and requirements.

For example: “Manual v1.2, approved May 3. Manual v1.3 is a draft adding the e-learning section authorized by CR-07.” The draft is not the approved version. The change reference explains why the new version exists; the version number identifies the exact content being reviewed or printed.

Keep one master repository. If two trainers edit separate slide decks and a printer combines both, learners may receive conflicting instructions. Version labels, controlled access and a change history help the team find the approved set and prevent accidental mixing.

Handle adaptive change through the backlog

Adaptive projects expect requirements to evolve. The product owner orders new and changed items in the product backlog by value. New work normally waits for the next iteration planning. During an iteration, the product owner and team can clarify and renegotiate selected work as they learn, while protecting the iteration goal. Urgency does not let one person add work unilaterally.

Time and cost are often fixed while the selected scope flexes. A change to the overall budget, contract or release date still needs formal approval. Backlog control and formal authority can therefore operate together in the same project.

The control method fits the work: a predictive baseline uses formal requests; an adaptive team controls selection and ordering through the backlog and iteration boundaries. In both, people need to know what was agreed, who may change it, and which version is current.

Key Takeaways

  • Scope creep is uncontrolled addition; gold plating is an unrequested team addition.
  • A request channel and measurable scope help prevent informal promises.
  • Configuration management identifies and tracks controlled versions.
  • Backlog ordering controls adaptive changes while protecting the iteration goal.
4

Check that deliverables meet requirements

Quality depends on clear requirements and work that meets them. Planning defines the checks, quality assurance examines how the work is done, and quality control examines the deliverables. These activities help the team prevent repeated mistakes, find defects early and supply evidence for customer acceptance. A high pass rate still needs careful reading when the acceptance rules also prohibit critical failures.

4.1 Build quality into the work

A deliverable has high quality when its characteristics meet the agreed requirements and it is fit for its intended use. A high price or a long feature list cannot substitute for that fit. Quality starts with planning and remains everyone's responsibility during delivery.

Separate quality from grade

Grade groups products with the same use but different technical characteristics. Basic and premium laptops have different grades. A basic model that meets its requirements can have high quality; a premium model with a faulty battery has a quality problem.

This distinction helps teams judge the right thing. Adding premium features does not repair a failed requirement. A clean, working basic hotel room can meet its intended standard even though it offers fewer services than a luxury room.

Plan the evidence early

Quality planning defines applicable standards, metrics, acceptance criteria, responsibilities and timing. Record these in the quality management plan. A quality metric is a measure, such as page-load time or the percentage of trainees passing an assessment. A criterion sets the required result, such as pages loading in under three seconds or no open critical defects at release.

Agree these requirements before producing the deliverable. Otherwise, a team can spend heavily on an output and discover at the end that its customer expects a different standard. Give each check a responsible person and a suitable point in the work.

Check process and product
ActivityMain focusExample
Quality assurance (QA)Processes and standards used to prevent defectsAudit whether regression tests are performed
Quality control (QC)Deliverables against requirements and criteriaRun a checkout test and record failure

QA gives confidence that the way of working can produce the required result. QC finds defects and confirms that repairs work, producing verified deliverables. They inform each other: repeated checkout failures may point to a weak review or test process that needs QA attention.

Understand the cost of quality

The cost of quality includes the effort to prevent and check defects and the losses when defects occur.

GroupCategoryExample
ConformancePreventionTraining, standards, design reviews
ConformanceAppraisalInspection and testing
NonconformanceInternal failureScrap and rework before delivery
NonconformanceExternal failureComplaints, recalls and warranty claims after delivery

Suppose prevention costs $2,000, appraisal $3,000, internal failure $5,000 and external failure $12,000. Total quality cost is $22,000. Only $5,000 is conformance cost; the remaining $17,000 arises from failures. Counting only test spending misses most of the picture.

A requirement error caught in review may take minutes to fix. After delivery it can require rework, customer support and damage repair. Investing in prevention and appraisal usually reduces failure costs. Inspection can reveal poor work, but it cannot build quality into work already done.

Team members are responsible for their own work. The project manager makes sure the quality activities happen, and independent reviewers or auditors may examine processes. Leaving quality entirely to testers at the end removes opportunities to prevent errors earlier.

Key Takeaways

  • Quality means meeting agreed requirements and intended use.
  • Grade describes different technical categories, not whether requirements are met.
  • QA checks processes; QC checks deliverables.
  • Conformance costs cover prevention and appraisal.
  • Nonconformance costs cover failures before and after delivery.

4.2 Test, repair and verify deliverables

Quality control compares an actual deliverable with measurable requirements. Choose a method that fits the output, record the results and follow defects through repair and retest. The evidence supports acceptance but does not replace the customer's acceptance decision.

Choose a suitable check

Inspect physical work directly, such as a room's measurements. Use peer reviews or walkthroughs for documents, designs and code. Run planned test cases for software or equipment. A checklist helps reviewers perform all required checks consistently.

Acceptance criteria state the conditions needed for acceptance and are agreed with the customer before the work. “Works in the current versions of four named browsers” can be tested. “User-friendly” needs a clearer measure. Adaptive teams use item-specific criteria together with a shared definition of done, which may require review, passed tests and updated user help.

Apply every acceptance condition

A website release has 40 test cases. Its rule requires no critical failures and at least 95% of cases passing. The first run passes 37 cases and fails three, including card payments, a critical case.

The pass rate is 37 out of 40, or 92.5%. It fails the percentage requirement and the no-critical-failure rule. Fixing enough minor cases to reach 95% would not make the release ready while the critical payment failure remained.

After repair and retest, 39 pass. That is 97.5%, and the one remaining failure is cosmetic. The release now meets the stated criteria. Record the remaining item and its agreed treatment so it is not lost.

Track defects to a checked result

A defect log needs an ID, description, severity, finder and date, owner, status, repair and retest result. Severity describes how serious the failure is and drives the order of repair. A clear record lets testers reproduce the problem and lets the owner show that it is resolved.

Possible treatments are repair, replacement, rejection, or a concession: a formal customer decision to accept the item as it is, sometimes with a later fix or price adjustment. The team cannot grant itself a concession. A repair that changes an approved baseline needs change control.

Retest every repair. Also run related tests: regression testing checks that the change has not broken behavior that worked before. A payment repair might affect related checkout steps, so repeating only the originally failed test is incomplete evidence.

Separate verification and validation
CheckQuestionTypical outcome
VerificationDoes it meet the specification?Verified deliverable from QC
ValidationDoes it meet the customer's needs?Customer or sponsor acceptance

In a predictive project, internal QC usually precedes customer acceptance. Passing internal tests does not itself provide sign-off.

When checking every item is too costly or destructive, inspect a planned sample, such as 20 of 500 manuals. Missing pages in the sample prompt a wider batch check. Repeated similar defects also call for process investigation through QA. Keep failed work out of completion claims until it meets the applicable quality checks; premature earned value credit hides rework.

Key Takeaways

  • Agree measurable acceptance criteria before delivery.
  • Meet each acceptance condition, including critical-failure rules.
  • Log defects, assign owners and retest repairs.
  • Regression testing checks related behavior after a change.
  • Verification supplies QC evidence; validation addresses customer needs and acceptance.
  • Use sampling deliberately and investigate recurring defect patterns.
5

Finish with acceptance and a usable handover

Finishing the last task leaves several responsibilities to settle. The customer needs to accept the result, suppliers need their contracts closed, and operations needs the people, information and access to run what was delivered. Closure also records actual performance and transfers remaining actions. Lessons become useful when later teams can find them and someone turns the recommendations into a changed process or habit.

5.1 Confirm acceptance and settle contracts

Closing formally completes a project or phase. It happens after objectives are met or after an authorized decision to end early. A clear closure process prevents work from drifting on with no settled responsibility, budget or end point.

Check readiness to close

Closure criteria belong in the plan. They normally require deliverables to be accepted, contracts settled, remaining issues and risks transferred to owners, records archived and resources released. Use a closure checklist to coordinate the sequence and confirm completion.

Phase closure applies the same controls to a smaller part of the work and ends with a decision about continuing. Completing a phase does not automatically authorize the next one. A review may show that further work no longer offers enough value.

Obtain written acceptance

Formal acceptance, or sign-off, is written confirmation from the customer or sponsor that deliverables meet their acceptance criteria. Identify the deliverable and version, the evidence, the accepting person and the date. For example: “E-learning module v2.0: 12 of 12 criteria met; accepted by the HR director on June 28.”

Individual outputs are often accepted during delivery; final acceptance confirms the whole. Silence is weak evidence because it does not show which version or criteria someone approved. Written acceptance supports closure and payments linked to acceptance. Operational responsibility follows the handover arrangements, and outstanding claims are settled separately.

Manage minor open items

Conditional acceptance records acceptance with minor items still to finish. A punch list, also called a snag list, gives each item an owner and date. An office fit-out might be accepted with four finishing items due within ten working days. Track them until complete.

The list is an active record, not a way to make outstanding work disappear. The acceptance decision needs to state the conditions so the customer, team and receiving staff share the same understanding of what remains.

Close each supplier contract

Contract closure can occur before the overall project ends. For each contract:

  1. Confirm that contracted work was delivered and accepted.
  2. Settle final invoices, payments and any retained amounts.
  3. Resolve open claims, using negotiation where possible.
  4. Notify the supplier formally that the contract is complete.
  5. Archive the contract records and record supplier performance.

Acceptance of the product does not settle a disputed invoice by itself. Keep enough people and financial access available to complete the final transactions. Close cost accounts after the final costs have been handled; closing them too early can prevent invoices from being recorded properly.

Close an early termination properly

A project may end because its business case no longer works, funding is withdrawn or the need disappears. Record the decision and reason. Document the state of each deliverable, hand over usable work, settle contracts under their termination terms, release resources and capture lessons.

An early stop still creates records and responsibilities. Abandoning the administration leaves a “zombie” project consuming effort with no clear purpose. Plan the team's release around the closure tasks so the people who know the work can finish the evidence and handover.

Key Takeaways

  • Use planned closure criteria for project and phase closure.
  • Formal acceptance identifies what was accepted, by whom and when.
  • Conditional acceptance needs a tracked punch list with owners and dates.
  • Settle contracts and final costs before closing the related administration.
  • Early termination still requires controlled closure.

5.2 Prepare operations and complete the records

A finished deliverable needs people who can run, maintain and support it. Handover, or transition, transfers it into normal business with those arrangements in place. Involve the receiving staff early and agree what readiness means with them.

Assemble a usable handover

The package includes deliverables and their approved configuration, user guides, operating and maintenance instructions, relevant drawings, training, support contacts and service levels. Include warranties, supplier contacts, open risks and issues with new owners, and the access rights and licenses needed to operate the result. Transfer access securely.

Check the package with the people who will use it. A manual in a folder is little help if the service team cannot locate it or has no access to the system it describes. Schedule training and practice before responsibility changes hands.

Operational acceptance confirms that the receiving organization is ready to run the deliverable. This differs from customer sign-off against product criteria: it concerns readiness to operate. Agree the handover point and responsibilities explicitly.

Give early support an end point

Extra help after go-live is often called early life support or hypercare. Agree who provides it, how long it lasts and its exit criteria. Otherwise, the project team may remain the informal support service long after closure. Open actions and risks need named receiving owners who understand what they are accepting.

A warranty expiry date is certain information to record. The risk is that equipment fails after expiry and causes unplanned repair cost. Record both the date in the documentation and the risk with its new owner.

Separate outputs from later benefits

The project delivers outputs; the sponsor or business owner remains responsible for realizing and measuring benefits afterward. A new onboarding system may be live at closure while its effect on onboarding time is measured six months later.

A post-project review evaluates delivery performance at closure. A later benefits review checks whether expected improvements arrived. Agree who will measure the benefit and when, so ending the project does not end accountability for value.

Finish the administration

Record final scope, schedule, cost and quality results. Settle final costs, close cost accounts and work orders, archive plans and baselines, logs, decisions, acceptance evidence and contracts. Update templates and estimating information that future teams can use.

The final project report compares objectives with actual results. Include main variances and causes, quality results, benefits outlook, open items with owners and key lessons. In the rollout, the approved budget after change is $56,000 and actual cost is $58,800. The $2,800 overrun is 5% of that budget. Final CPI is 56,000÷58,800, about 0.95. Finish in week 23 against baseline week 22 is one week late. Use the approved post-change baseline and explain its history.

Release people and equipment in time

Tell functional managers when people will be available, provide performance feedback, return equipment and facilities, and recognize the team's work. Keep the people needed for closure until their handover and record tasks are done. A resource-release plan makes the finish orderly for both the project and the next assignment.

Key Takeaways

  • Operational acceptance confirms readiness to run and support the result.
  • Transfer documentation, training, support, access and open responsibilities.
  • Agree early support exit criteria.
  • The business owner or sponsor tracks benefits after handover.
  • The final report compares actual results with approved baselines.
  • Complete closure tasks before releasing the people needed for them.

5.3 Turn experience into a useful lesson

Lessons learned record what a project teaches about successful and unsuccessful ways of working. Their value comes from a practical change that helps the next team repeat a success or avoid a problem. A complaint without a recommendation gives that team little to use.

Capture experience while it is fresh

Record lessons throughout delivery: at phase ends, after major events and in iteration retrospectives. At the end, people may have left and details may be forgotten. Keep a lessons learned register during the project, then place reusable lessons in the organization's searchable repository at closure.

Gather several views. Use a workshop or post-project review, short surveys, and evidence from issue and change logs, the risk register and variance data. A retrospective asks what went well, what could improve and what the team will do differently. Include effective practices, such as a review that prevented a costly error, as well as failures.

Make discussion safe enough to be useful

Focus on processes and conditions. If people expect personal blame, they may hide the information needed to prevent a repeat. Ask what enabled an error, which checks were missing and what would make the next decision better. A facilitator who was not directly involved can help the group hear different accounts fairly.

Blameless discussion still produces clear actions. An action owner takes responsibility for an improvement; naming that owner is different from blaming someone for the original event. Record the evidence supporting a cause so the group does not turn a suspicion into a permanent rule.

Write a lesson someone can apply

Include the situation, what happened, its measured effect, root cause and a specific recommendation. “Communication with the supplier was poor” gives neither evidence nor a usable next step.

A stronger record is: “The server order was placed without stock confirmation. Delivery was eight working days late, using three days of float and moving go-live five days. For long-lead hardware, confirm stock and delivery dates in writing before ordering, and show delivery as a separate schedule activity.”

The effect is measurable, the cause explains why the problem arose, and the recommendation changes a decision before the next order. Someone planning a hardware purchase can find the lesson and act on it without asking the original team to reconstruct the story.

Make the change happen

A recorded recommendation is a lesson identified. It becomes a lesson learned when behavior or a process actually changes. Give the improvement an owner. Update a procurement checklist, planning template or estimating record, and review relevant lessons when starting the next project.

For the supplier lesson, a new order form could require written stock confirmation and a scheduled delivery activity. The owner checks that future orders use those fields. This turns the lesson into a working control, with evidence that it is being used.

A long folder of unsearched reports does not achieve that transfer. Store lessons where new teams look during initiation and planning, with clear titles and context. Hold the closure review while the team is still available and complete the improvement handover before everyone disperses.

Key Takeaways

  • Capture lessons throughout delivery and include successes.
  • Use evidence and keep the discussion focused on processes and conditions.
  • Write the situation, event, effect, cause and recommendation.
  • Give improvements owners and put them into working processes.

Project Monitoring and Control examples

5 Walkthroughs

1

From progress evidence to an honest report

12 steps
Compare a plan with real progress, choose a reporting response and read adaptive delivery evidence.
  1. 1
    IntroductionA number needs a reference

    A team says its design work is “nearly done.” Before reporting that to a sponsor, you need evidence, the planned completion level and the likely effect on the next milestone. The planned level comes from the approved baseline; a tolerance tells you when a gap needs a higher decision.

    Follow a progress check through to a useful status line, then see how boards and burn charts answer similar questions in an adaptive team.

  2. 2
    ExplanationHold the approved plan steady

    A baseline is the approved reference for scope, dates or cost. Actual performance is compared with it so the difference remains visible.

    The forecast can show what the team now expects. It can move without silently rewriting the commitment. A baseline changes only through approved change control; otherwise a late task could appear on time simply because its target was moved.

  3. 3
    ExampleWork out the progress gap

    A task is planned evenly over ten days. At the end of day six, the plan calls for 60% complete, but checked work shows 40%.

    The gap is 20 percentage points, equal to two planned days of work. Investigation finds a tester is absent. Borrowing a tester is a possible corrective response. The spending total alone would not have revealed how much usable work was complete.

  4. 4
    ChallengeDoes this need a higher decision?

    The project manager can handle an end-date delay of up to two days. A new forecast shows four days late. Should the manager wait for the date to be missed?

    ---reveal---

    No. The forecast already exceeds tolerance, so escalate with the impact, options and recommendation. Management by exception uses a threatened limit to trigger the higher decision while action may still protect the outcome.

  5. 5
    ConnectionBuild a status line from the gap

    The sponsor needs to know what decision would help, not just that design is late. A useful line has four parts: fact against plan, cause, action and request.

    For the rollout: design is 75% complete against 100% planned at week eight; the expert was unavailable; a second designer is proposed; approval of $3,000 is needed by Friday. Each part answers a different practical question.

  6. 6
    ExplanationMake the color mean something

    Traffic-light rules must be agreed before use. Green means within thresholds; yellow or amber signals risk or recoverable drift; red signals a tolerance breach or a higher decision.

    Also agree how the overall color is chosen. A worst-area rule would make a red schedule determine the overall red. Counting green areas against it would apply a different rule and could hide the exception.

  7. 7
    ChallengeChoose an honest status

    A report uses red for a milestone forecast at least one week late. The latest forecast is eight days late, but the team hopes to recover. What should the report show?

    ---reveal---

    Red, with the evidence and recovery action. Hope does not change the forecast or the agreed boundary. Keeping the rating green would conceal a known problem and delay the sponsor’s opportunity to help.

  8. 8
    ExplanationRead the queue before starting more

    Cards move across a board from To do through active stages to Done. A buildup in Testing shows where work is waiting. Work-in-progress limits cap simultaneous cards so the team can focus on finishing.

    Use the daily stand-up to expose blockers. An iteration review gathers feedback on the product, while a retrospective examines how the team works. A queue problem is useful evidence for both daily coordination and process improvement.

  9. 9
    ExampleLocate the burndown position

    A ten-day iteration starts with 60 points. Its ideal remaining-work line falls by six points per day. At day five it should show 30 remaining.

    If 36 remain, the actual line is six points above the ideal. The team has more work left than planned at this point. Investigate blockers and scope changes before choosing a response; the chart shows the gap without proving its cause.

  10. 10
    Key InsightSeparate a moving target from delivery

    A burnup has a completed-work line and a separate total-scope line. If scope grows from 200 to 220 points, the target steps up by 20. That change can be seen even if completion continues steadily.

    Count only work meeting the definition of done. A story still needing tests is unfinished, so giving it partial completed-point credit would make the completion line overstate delivery.

  11. 11
    ChallengeConnect team pace to the sponsor’s date

    A hybrid release has 72 points left. The same team has averaged 18 completed points per two-week iteration, and release is planned eight weeks away. What outlook should be reported?

    ---reveal---

    About four more iterations, or eight weeks, at that pace. The current outlook matches the planned date. State the remaining scope and pace behind it, and review the forecast if either changes. Do not compare this team’s velocity with another team’s points.

  12. 12
    RecapCheck the evidence, then the decision

    A useful report preserves the approved reference, shows actual achievement and explains the response to a gap. Tolerances determine when the decision must go higher.

    Adaptive tools give a closer view of flow, completion and scope. Translate those measures into the milestone, cost and risk information the sponsor needs, with enough context to judge the delivery outlook.

2

Build and read an earned value result

17 steps
Calculate PV, EV, AC, variances and indices, then test the interpretation against dates and data quality.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionHas spending bought the planned work?
  2. 2
    ExplanationGive each measure its own job
  3. 3
    ExampleAdd the scheduled value
  4. 4
    ExampleValue the completed work
  5. 5
    ExampleBring in costs on the same basis
  6. 6
    ChallengeUse the agreed earning rule
  7. 7
    ExplanationChoose subtraction or division
  8. 8
    ExampleCalculate the two gaps
  9. 9
    ExampleCalculate the two ratios
  10. 10
    TipUse the right percentage denominator
  11. 11
    ChallengeDoes low spending prove good cost control?
  12. 12
    ExampleApply the reporting thresholds
  13. 13
    Key InsightA favorable cost result does not explain delay
  14. 14
    ChallengeCan an index erase a late finish?
  15. 15
    ConnectionCheck what the index cannot see
  16. 16
    ChallengeCombine the signals before acting
  17. 17
    RecapKeep value, cost and dates distinct
3

From a confirmed issue to a controlled change

16 steps
Log a problem, assess its delay, obtain a decision and keep scope and versions clear.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionA late delivery starts several decisions
  2. 2
    ExplanationRecognize an issue now
  3. 3
    ExampleGive the record a working purpose
  4. 4
    ChallengeSet priority from the effect
  5. 5
    ExampleUse the available float
  6. 6
    ExampleCompare responses before choosing
  7. 7
    ChallengeKnow when authority ends
  8. 8
    ExplanationAnalyze all effects of a new request
  9. 9
    ExampleTrace approval into the plan
  10. 10
    ChallengeChoose the proper funding decision
  11. 11
    Key InsightSpot informal additions early
  12. 12
    ExplanationKnow exactly which copy is approved
  13. 13
    ChallengeRelease the right document
  14. 14
    ConnectionKeep adaptive changes deliberate
  15. 15
    ChallengeLink a problem, request and version
  16. 16
    RecapKeep the decision trail clear
4

Check a release against every acceptance rule

12 steps
Distinguish process assurance from product control, then handle a test failure through repair and retest.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionWhat would make this ready?
  2. 2
    ExplanationQuality starts with requirements
  3. 3
    ExampleCheck the process or the product
  4. 4
    ExplanationCount failures as quality cost too
  5. 5
    ChallengeClassify the work by purpose
  6. 6
    ExampleApply the percentage condition
  7. 7
    Key InsightTwo conditions need two checks
  8. 8
    ExampleRepair and check for side effects
  9. 9
    ChallengeWho may accept a defect as it is?
  10. 10
    ConnectionTake verified work to acceptance
  11. 11
    ChallengeConnect process, evidence and acceptance
  12. 12
    RecapMake readiness traceable
5

Close the work and transfer responsibility

13 steps
Follow sign-off, contract settlement, operational handover, final reporting and applied lessons.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionFinish the responsibilities as well as the work
  2. 2
    ExplanationCheck the planned closure conditions
  3. 3
    ExampleGet a specific acceptance record
  4. 4
    ChallengeDoes sign-off close the supplier file?
  5. 5
    ExplanationMake the receiving team ready
  6. 6
    TipPut an end point on extra support
  7. 7
    ExampleReport the final result against the approved plan
  8. 8
    ChallengeWho measures a benefit after closure?
  9. 9
    ExplanationCapture evidence before people disperse
  10. 10
    ExampleWrite a lesson with a usable action
  11. 11
    ChallengeHas the lesson been learned yet?
  12. 12
    ChallengeClose with open actions under control
  13. 13
    RecapLeave a usable result and a clear record

Project Monitoring and Control practice questions

60 Practice Questions in 6 sets

Set 1: Read the evidence and report status10 Practice Questions

Question 1 of 10

One team completed 14, 18 and 16 points in its last three iterations. It has 80 points remaining and expects a similar pace. About how many more iterations should it plan for?
  1. Four iterations
  2. Five iterations
  3. Six iterations
  4. Eight iterations
Show answerHide answer
Answer: B
The average is 48 points across three iterations, or 16 per iteration. Dividing 80 remaining points by 16 gives about five iterations at that pace. Four uses the best recent result too optimistically and still would not cover 80 points; the estimate also needs review if scope or pace changes.

Question 2 of 10

A coordinator records that equipment arrived on June 9. What kind of performance record is this?
  1. Work performance information
  2. Work performance data
  3. A work performance report
  4. A schedule baseline
Show answerHide answer
Answer: B
The arrival date is a raw observation, so it is work performance data. It becomes performance information when someone compares it with the planned arrival date and explains the difference. A report then presents that comparison for a reader who needs to decide or act.

Question 3 of 10

A task was planned evenly over 12 days. After 6 days, objective checks show 25% complete. How far behind the planned work is it?
  1. 75 percentage points
  2. 50 percentage points
  3. 3 percentage points
  4. 25 percentage points
Show answerHide answer
Answer: D
At the halfway point, the plan calls for 50% completion. Actual completion of 25% leaves a gap of 25 percentage points, equivalent to three planned days of work. Reporting 50 percentage points confuses the planned completion level with the difference from the actual result.

Question 4 of 10

What should a sponsor report put first when an approval is needed tomorrow?
  1. The decision needed and its deadline
  2. The full list of team assignments
  3. The history of earlier approvals
  4. Every completed task this month
Show answerHide answer
Answer: A
The sponsor needs to see the action that cannot wait, including when the decision is required. Detailed achievements can follow as supporting information. Starting with the full task history may make the report look thorough while hiding the approval that determines whether work can continue.

Question 5 of 10

A board has a growing queue in Review while new cards keep entering In progress. What response best addresses the visible flow problem?
  1. Increase the number of cards started
  2. Move queued cards directly to Done
  3. Help clear work waiting for review
  4. Raise every story-point estimate
Show answerHide answer
Answer: C
The buildup identifies Review as the bottleneck, so helping that step finish existing work addresses the queue. Starting more cards feeds work into the same blocked stage and can increase waiting. Moving items to Done would also misstate progress unless they had met the completion standard.

Question 6 of 10

A team defines yellow as a milestone forecast 1–4 days late and red as 5 or more days late. A milestone is forecast 5 days late, with recovery under discussion. What rating applies?
  1. Green until the date is missed
  2. Yellow while recovery is open
  3. Red under the agreed criteria
  4. Yellow until recovery fails
Show answerHide answer
Answer: C
Five days lies in the defined red range, so the report should show red now. Discussing recovery is useful but does not change the measured forecast or the rating rule. Waiting until the date is missed hides an exception that the sponsor could help address while options remain.

Question 7 of 10

What does the rising completed-work line on a burnup chart show?
  1. Work remaining over time
  2. Work finished over time
  3. Actual spending over time
  4. Unfinished work in testing
Show answerHide answer
Answer: B
The completed-work line accumulates the work finished over time. A separate total-scope line lets the reader see whether the target has grown. Remaining work is the main quantity on a burndown chart, so reading a burnup completion line that way reverses the meaning of its movement.

Question 8 of 10

A project manager may absorb up to 2 working days of end-date delay. A confirmed supply delay is 7 days; the affected activity has 4 days of total float. No recovery is agreed. What should the manager do?
  1. Keep the issue within team authority
  2. Wait until the end date is missed
  3. Escalate a seven-day end-date slip
  4. Escalate a three-day end-date slip
Show answerHide answer
Answer: D
Four days of float absorb part of the seven-day activity delay, leaving a three-day end-date effect. That forecast exceeds the two-day tolerance and needs escalation now. Escalating seven days ignores float, while keeping it within team authority ignores the remaining breach after float is used.

Question 9 of 10

A milestone dashboard shows a four-day forecast delay but no commentary. What addition makes it most useful for a decision?
  1. Cause, recovery action and help needed
  2. More colors for the same milestone
  3. A longer list of completed meetings
  4. The original schedule without forecasts
Show answerHide answer
Answer: A
A decision maker needs to understand why the milestone is late, what response is planned and what help is needed. The four-day figure supplies the size of the variance but not the action. Adding more visual detail without those points still leaves the reader to guess what to do.

Question 10 of 10

A release burnup shows completed points rising steadily while the total-scope line rises faster. The team velocity is stable. What best explains the widening gap?
  1. The scope line measures actual spending
  2. Completed stories are earning fewer points
  3. The team has stopped finishing work
  4. Scope is growing faster than delivery
Show answerHide answer
Answer: D
The two lines show delivery continuing while the target expands even faster. Stable velocity is consistent with that pattern: it measures completed points per iteration, not control of new scope. Blaming slower completion would conflict with the stated steady completion line and stable team pace.
Set 2: Calculate and interpret earned value10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A $9,000 work package uses the 20/80 rule. It has started but is unfinished. What EV should be recorded?
  1. $7,200
  2. $4,500
  3. $0
  4. $1,800
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A project has PV $30,000, EV $24,000 and AC $27,000. What are SV and CV?
  1. SV −$3,000; CV −$6,000
  2. SV −$6,000; CV −$3,000
  3. SV +$6,000; CV +$3,000
  4. SV −$6,000; CV +$3,000
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A project has two packages. A $16,000 package is 50% complete; a $4,000 package is 100% complete. What is total EV?
  1. $12,000
  2. $15,000
  3. $10,000
  4. $20,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

What does a CPI of 0.75 mean?
  1. 75% of all project work is complete
  2. The project finishes 25% later
  3. $0.75 of budgeted work per $1 spent
  4. $1 of budgeted work per $0.75 spent
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

SPI is 0.85 and CPI is 1.10. How should the manager describe the position?
  1. Ahead of planned work and over cost
  2. Behind planned work and over cost
  3. Ahead of planned work and under cost
  4. Behind planned work and under cost
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

EV is $18,000 and AC is $20,000. What is CV as a percentage of EV, to one decimal place?
  1. −11.1%
  2. −10.0%
  3. +11.1%
  4. +10.0%
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A project planned to finish in week 9 ends in week 12. All authorized scope is complete and PV and EV both equal BAC. What should its final schedule statement say?
  1. SPI 0.75 proves a three-week delay
  2. SPI 1.00 and a three-week delay
  3. SPI 1.00 proves an on-time finish
  4. SV equals three weeks at completion
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

The budget includes labor and materials. At month end, EV is cumulative but AC includes only this month’s labor. What must happen before interpreting CPI?
  1. Remove materials from EV only
  2. Divide current labor cost by EV
  3. Align AC with EV’s period and cost basis
  4. Replace EV with cumulative invoices
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

PV is $48,000, EV is $36,000 and AC is $40,000. What are SPI and CPI?
  1. SPI 1.33; CPI 1.11
  2. SPI 0.90; CPI 0.75
  3. SPI 1.20; CPI 0.90
  4. SPI 0.75; CPI 0.90
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Overall CPI is 1.02, but a critical package has CPI 0.72 and a late forecast. What is the most useful next investigation?
  1. Check that package’s costs and schedule
  2. Close the cost concern using overall CPI
  3. Rebaseline the package to its actual cost
  4. Infer its finish date from overall CPI
Show answerHide answer

Save this lesson to see this answer.

Set 3: Resolve issues and authorize changes10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A supplier confirms today that a required part will miss its delivery date. How should the project record this condition?
  1. Only as a possible future risk
  2. As a completed preventive action
  3. As an issue needing an owner
  4. Only as a proposed scope change
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

Two issues compete for attention: a billing error before tomorrow’s launch and a minor guide typo with no near deadline. What should determine priority?
  1. The time each issue was first logged
  2. The impact and urgency together
  3. The number of people copied on email
  4. The ease of closing the record
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A 9-day activity delay affects an activity with 5 days of total float. Without recovery or other schedule changes, what is the end-date effect?
  1. Five working days late
  2. Nine working days late
  3. Fourteen working days late
  4. Four working days late
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A stakeholder asks a developer to add a new feature to approved scope. What should happen first?
  1. Record a change request for assessment
  2. Implement it and record it after testing
  3. Update the baseline to include it
  4. Use management reserve to begin it
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A designer adds an unrequested premium animation to the approved product. What does this illustrate?
  1. Approved scope elaboration
  2. Customer conditional acceptance
  3. Team-initiated gold plating
  4. Planned contingency response
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A manager can approve changes up to $2,500 and no more than 2 days. A request costs $1,800 and adds 4 days. What decision route is needed?
  1. Manager approval because cost is within limit
  2. Manager approval after splitting the request
  3. Implementation followed by board review
  4. A higher decision because time exceeds authority
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A confirmed issue would move the finish 6 days beyond a 3-day tolerance. The preferred response reduces approved scope. What should the manager do before implementing it?
  1. Escalate and obtain the scope-change decision
  2. Record the smaller scope only in the issue log
  3. Implement it within the original cost budget
  4. Wait for the six-day delay to occur
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A manual has approved v2.1 and a draft v2.2 linked to a change request. Which copy should be released as the approved manual?
  1. The newer v2.2 draft copy
  2. The approved v2.1 copy
  3. Either labeled copy
  4. A mix of the newest pages
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A new module is approved with $4,800 extra funding. Original BAC is $72,000. The sponsor keeps a separate management reserve. What should the updated cost baseline show?
  1. BAC $72,000; reserve reduced $4,800
  2. BAC $72,000; added work excluded
  3. BAC $76,800; scope and PV updated
  4. BAC $76,800; scope left unchanged
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

During an iteration, a customer requests an urgent item. It can fit only by changing selected work, and the iteration goal can still be protected. How should the team handle it?
  1. The customer adds it directly to the board
  2. The product owner assigns it unilaterally
  3. The team accepts it without backlog review
  4. The team and product owner renegotiate scope
Show answerHide answer

Save this lesson to see this answer.

Set 4: Check quality and finish the project10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

An auditor checks whether the team follows its agreed test process. What activity is this?
  1. Quality control of the finished product
  2. Quality assurance of the process
  3. Customer validation of the result
  4. Conditional acceptance of defects
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A release needs at least 96% of 50 tests to pass and no critical failures. It passes 49 tests, but the remaining failure is critical. What is its readiness?
  1. Not ready because the critical rule fails
  2. Ready because 98% exceeds the target
  3. Ready if its owner promises a repair
  4. Not ready because all tests must pass
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

What provides formal acceptance of a deliverable?
  1. A team message saying work has ended
  2. A customer’s silence after the demo
  3. An internal test report with no failures
  4. Written customer or sponsor sign-off
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A team spends $1,200 on training, $2,300 on testing and $4,100 on rework before delivery. What is its conformance cost?
  1. $6,400
  2. $5,300
  3. $3,500
  4. $7,600
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

The product meets its criteria, but support staff lack access and training. Which readiness is still missing?
  1. Technical grade selection
  2. Operational acceptance
  3. Customer requirements
  4. Change-request capture
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A lesson says “Testing coordination was poor.” What addition would make it useful to a future team?
  1. Situation, measured effect, cause and action
  2. More names of the people attending meetings
  3. A longer account of how frustrating it felt
  4. A statement that every project should test
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A repair makes a failed login test pass. Related account-recovery behavior worked before, but has not been checked since the repair. What is the best next quality action?
  1. Grant acceptance using the login result
  2. Close testing because the defect is repaired
  3. Run related regression tests and record results
  4. Rewrite the criteria to cover login only
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A sponsor ends a project when its need disappears. Some outputs are usable and a supplier invoice remains unsettled. What is the appropriate closure approach?
  1. Release everyone and leave accounts open
  2. Record success and omit unfinished outputs
  3. Close accounts before considering the invoice
  4. Document the stop, hand over value and settle obligations
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Approved budget after change is $84,000. Final cost is $88,200, with all authorized work complete. What should the final report show?
  1. $4,200 over; CPI about 0.95
  2. $4,200 under; CPI about 1.05
  3. $4,200 over; CPI about 1.05
  4. $4,200 under; CPI about 0.95
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A review recommends a new supplier checklist. It is archived, but nobody updates the ordering process. What is the lesson’s status and the needed next step?
  1. Learned; repeat the review next year
  2. Identified; assign and implement the improvement
  3. Learned; increase the report distribution
  4. Identified; remove it from the repository
Show answerHide answer

Save this lesson to see this answer.

Set 5: Choose the next control action10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

Who should be named as the owner of an issue?
  1. The whole delivery department
  2. Everyone who raised a concern
  3. A person who drives its resolution
  4. Only the person doing every task
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A $25,000 design package earns 20% at draft, 30% at review and 50% at approval. Draft and review are complete. What EV has it earned?
  1. $25,000
  2. $7,500
  3. $5,000
  4. $12,500
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

The agreed overall-rating rule uses the worst area. Cost and scope are green; schedule is red. What should the overall status and explanation show?
  1. Green with schedule in the appendix
  2. Red with schedule impact and action
  3. Green until actual finish is delayed
  4. Yellow because two areas are green
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A basic projector meets every agreed performance requirement. A premium model fails its brightness requirement. How do their quality and grade compare?
  1. The basic one meets quality despite lower grade
  2. Both have low quality because one is basic
  3. The premium one has higher quality by price
  4. Both meet quality because they share a use
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A project delivers a new booking system today. Reduced booking time will be measured in four months. Who should own that later benefit measurement?
  1. The supplier’s invoice approver
  2. The project’s former test coordinator
  3. The whole released project team
  4. The sponsor or business owner
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

BAC is $90,000. By today, 60% was scheduled and 45% is complete. AC is $45,000. What are SPI and CPI?
  1. SPI 1.33; CPI 1.11
  2. SPI 0.90; CPI 0.75
  3. SPI 0.75; CPI 0.90
  4. SPI 0.75; CPI 1.11
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A board approves a change, but the schedule and cost system still use the old baseline. A team proposes measuring the next report against it. What should happen?
  1. Update affected baselines and communicate them
  2. Implement first and keep the old comparison
  3. Report the old baseline as the approved one
  4. Delay all reporting until project closure
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A customer formally accepts a minor cosmetic defect as it is. The performance requirements are unchanged. What treatment should the defect record show?
  1. Repair verified by regression testing
  2. Replacement approved by the project team
  3. Concession authorized by the customer
  4. Rejection pending a new specification
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A contract’s work is accepted, but a final claim is unresolved. The customer asks whether sign-off means the contract is closed. What is the best answer?
  1. Yes; acceptance settles every remaining claim
  2. No; resolve the claim and remaining closure tasks
  3. Yes; archive the claim with the acceptance
  4. No; repeat all technical tests before negotiation
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A project’s hardware order was seven working days late, consuming two days of total float. No recovery occurred. Stock was not checked before ordering, a problem also recorded on earlier projects. What lesson and follow-through best address this evidence?
  1. Record a five-day end effect; assign and use stock checks.
  2. Record a seven-day end effect; assign and use stock checks.
  3. Record a five-day end effect; increase final product testing.
  4. Record a two-day end effect; assign and use stock checks.
Show answerHide answer

Save this lesson to see this answer.

Set 6: Judge a project’s full position10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

What kind of quality cost is rework performed before delivery?
  1. Internal failure cost
  2. Appraisal cost
  3. External failure cost
  4. Prevention cost
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

An iteration ends with 22 points meeting the definition of done and 8 points still in testing. What velocity should be recorded?
  1. 30 points
  2. 26 points
  3. 22 points
  4. 8 points
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

An accepted facility has three minor finishing items, each assigned to a person with a due date. What arrangement does this describe?
  1. A rejected deliverable awaiting inspection
  2. Conditional acceptance with a punch list
  3. An issue closed because it is minor
  4. Contract closure with no remaining actions
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

An issue response fixes the immediate delay, but the purchasing process still permits orders without stock checks. What action addresses the root cause?
  1. Close the issue without reviewing the cause
  2. Rent temporary equipment on this occasion
  3. Move the delayed milestone in the baseline
  4. Require stock confirmation before ordering
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

SPI is 1.04, but the critical installation activity is late and the end-date forecast exceeds tolerance. Noncritical work is ahead. What should the manager do?
  1. Report green because total SPI exceeds 1
  2. Offset the delay with noncritical EV
  3. Escalate the date forecast with schedule evidence
  4. Wait for SPI to fall below the threshold
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

At one status date, PV is $64,000, EV is $48,000 and AC is $60,000. A manager reports $4,000 under cost because AC is below PV. What correction is needed?
  1. CV −$12,000 and CPI 0.80
  2. CV −$16,000 and CPI 0.75
  3. CV +$4,000 and CPI 1.07
  4. CV +$12,000 and CPI 1.25
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A proposed extra reporting feature costs $3,600 and leaves the finish unchanged. Contingency covers identified risks, and no such risk applies. What is the correct funding approach?
  1. Seek approval to fund it from contingency reserve
  2. Seek approval and funding for the new scope
  3. Seek approval to fund it from management reserve
  4. Approve it as corrective work in the existing baseline
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A batch sample reveals missing pages in training manuals. Similar errors occurred in two earlier batches. What combined response fits the evidence?
  1. Widen checking but leave the production process unchanged
  2. Widen checking and investigate the production process
  3. Investigate the process but release the unexamined batch
  4. Repair sampled copies and monitor only the next batch
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A system is handed over with a warranty ending next year. Who handles future equipment failure after expiry is undecided. What should closure establish?
  1. Treat the expiry itself as an uncertain event
  2. Leave future failures with the released team
  3. Omit the risk until the warranty has ended
  4. Record expiry and assign the post-warranty risk
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A review finds that short peer checks prevented repeated design errors. What is the best lesson record and follow-through?
  1. Record evidence and make peer checks reusable
  2. Archive the success without changing future plans
  3. Focus the lesson list only on delivery failures
  4. Increase checks without recording their purpose
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

92 Key Terms, each with its definition

A

Acceptance criteria
Acceptance criteria are measurable conditions, agreed with the customer before delivery, that a deliverable must meet to be accepted.
“The release needs a 95% pass rate and no critical failures, so the team checks both requirements.”
Actual cost
Actual cost is the cost incurred for work performed by the status date, recorded on a basis consistent with the budget.
“Labor and materials are both included so the cost total matches the categories in the cost baseline.”
Administrative closure
Administrative closure completes final performance and financial records, closes accounts and work orders, and archives project information.
“After final costs are handled, the manager closes work orders and files the approved baseline and decision history.”
Appraisal cost
An appraisal cost is spending on evaluating work for conformance, such as inspections and tests, within the total cost of quality.
“Running the planned acceptance tests is appraisal; repairing a defect found by the tests is failure cost.”

B

Baseline
A baseline is an approved version of a plan that provides the reference for measuring actual performance and changes only through approval.
“The report shows the original approved date beside the later forecast, keeping the delay visible.”
Benefits review
A benefits review checks after delivery whether expected business improvements have occurred, under sponsor or business-owner responsibility.
“The business owner measures onboarding time six months after the new learning system is handed over.”
Budget at completion
Budget at completion is the total budget for planned work in the cost baseline, excluding separately held management reserve.
“When a rollout’s four work-package budgets total $50,000, that sum becomes its BAC before approved additions.”
Burndown chart
A burndown chart plots remaining work against time, allowing actual remaining work to be compared with a planned decline.
“At day five, 36 points remain against an ideal 30, placing the actual line above the ideal line.”
Burnup chart
A burnup chart plots completed work and total scope as separate lines so scope growth can be seen apart from delivery.
“The target line rises after new requirements are added, while the completed-work line keeps climbing.”

C

Change control board
A change control board is a formally chosen group authorized to review and decide change requests within the project’s governance.
“The board decides a request that exceeds the manager’s delegated cost and schedule limits.”
Change log
A change log records proposed changes, their assessment and decisions, and the progress and verification of approved implementation.
“A rejected request stays in the log with its reason, preventing later confusion about its status.”
Change request
A change request is a written formal proposal to modify a deliverable, document or baseline, submitted for impact analysis and decision.
“The customer’s new reporting feature is logged before anyone promises to include it in the release.”
Closure criteria
Closure criteria are the planned conditions a project or phase must meet to end formally, covering acceptance and remaining responsibilities.
“The checklist confirms contracts are settled and open actions transferred before the team is released.”
Concession
A concession is a formal customer decision to accept an item with a defect as it is, sometimes with a later repair or price adjustment.
“The customer agrees to accept a minor cosmetic fault and the decision is recorded against the defect.”
Conditional acceptance
Conditional acceptance accepts a deliverable with minor open items that remain tracked with named owners and completion dates.
“The office is accepted with three small finishing items, each assigned to a contractor with a due date.”
Configuration item
A configuration item is a deliverable or component whose characteristics and versions are identified and formally controlled.
“The approved training manual has a unique ID, version number and recorded history of authorized edits.”
Configuration management
Configuration management controls deliverable characteristics and versions so records, approvals and delivered items remain consistent.
“The manual repository distinguishes approved v1.2 from draft v1.3 and links the draft to its change request.”
Contingency reserve
Contingency reserve is budget within the cost baseline for identified risks, used according to the project’s planned risk responses.
“The manager uses the planned allowance for an identified response under the agreed risk arrangements.”
Contract closure
Contract closure confirms accepted supplier work, settles payments and claims, issues completion notice and archives the contract record.
“Product sign-off is complete, but the final invoice is settled before the supplier file is closed.”
Controlling
Controlling is deciding and acting on performance evidence to address variances, prevent problems or repair defective work.
“The team borrows a tester after its progress check reveals a shortfall caused by unavailable staff.”
Corrective action
Corrective action is work intended to bring project performance back into line after a variance has already appeared.
“An additional shift addresses the current production shortfall while the approved dates stay visible.”
Cost of conformance
The cost of conformance is spending on preventing defects and appraising work, including training, reviews, inspection and testing.
“The quality report adds training and test costs separately from the cost of repairing failed work.”
Cost of nonconformance
The cost of nonconformance is loss from defects, including internal failures before delivery and external failures after delivery.
“Scrapped units and warranty claims both contribute to failure costs, even though they occur at different times.”
Cost performance index
The cost performance index is EV divided by AC, a unitless ratio describing budgeted work earned for each unit of actual cost.
“CPI of 0.90 means 90 cents of budgeted achievement per dollar spent on the completed work.”
Cost variance
Cost variance is earned value minus actual cost, showing whether completed work cost more or less than its budgeted value.
“Work budgeted at $24,000 costs $27,000, producing an unfavorable CV of −$3,000 at the status date.”
Cost variance percentage
Cost variance percentage expresses CV relative to EV, multiplied by 100, using completed work’s budget value as the reference.
“The analyst divides the negative cost variance by EV, keeping the agreed percentage basis consistent.”
Critical path
The critical path is the sequence of activities determining the project’s shortest finish, so delays there threaten the end date.
“Early noncritical work improves SPI while a late critical installation still threatens go-live.”

D

Defect
A defect is an imperfection or deficiency that causes a deliverable to fail a requirement and needs an agreed treatment.
“The checkout rejects valid payments, so the tester records a defect with an owner and retest result.”
Defect log
A defect log records failures with their severity, finder, owner, status, treatment and retest evidence so corrections can be tracked.
“A payment failure remains open until its repair is checked and the result is entered in the record.”
Definition of done
A definition of done is the shared standard an item must meet before the team counts it as completed work in an increment.
“A story still waiting for its required tests earns no completed points when the iteration ends.”

E

Early life support
Early life support is an agreed period of extra assistance after go-live, with responsibilities, an end date and exit criteria.
“The project team supports launch for two weeks under agreed conditions before ordinary support takes over.”
Earned value
Earned value is the approved budget value of work actually completed by the status date, using the agreed completion rule.
“A design package that is 75% complete earns $9,000 from its $12,000 budget, regardless of spending.”
Earned value chart
An earned value chart plots cumulative PV, EV and AC over time so the schedule-value and cost gaps can be read at a status date.
“EV below PV and AC above EV reveal both a work shortfall and poor cost performance at the cutoff.”
Earned value management
Earned value management combines scope, schedule and cost by comparing budgeted scheduled work, completed work and actual cost.
“The report distinguishes a low spending total from the smaller amount of work actually completed.”
Escalation
Escalation takes an issue or decision to a higher authority when its impact or response exceeds the current decision maker’s limits.
“The manager sends options and a recommendation to the sponsor when the forecast exceeds tolerance.”

F

Final project report
A final project report compares objectives and approved baselines with actual results, explaining variances, open items and key lessons.
“The report shows the approved budget, actual cost, one-week delay and receiving owners for remaining actions.”
Forecast
A forecast is an estimate of a future project result, such as an expected finish date, based on the current evidence.
“A project’s baseline finish stays June 20, while its latest forecast shows a June 24 finish after a delay.”
Formal acceptance
Formal acceptance is written customer or sponsor confirmation that an identified deliverable meets its agreed acceptance criteria.
“An HR director signs off v2.0 of a training module with its acceptance evidence and date, supporting project closure.”

G

Gold plating
Gold plating is adding features beyond agreed requirements on the team’s initiative, without a customer request and controlled decision.
“A designer builds an unrequested premium feature that adds test work and uses the project budget.”
Grade
Grade is a category for products with the same use but different technical characteristics, separate from whether they meet requirements.
“Basic and premium laptops have different grades, but either can be reliable or defective against its criteria.”

H

Handover
Handover transfers deliverables into normal business with the information, training, support, access and responsibilities needed to operate them.
“Operations receives the guides, licenses and named owners for the remaining service issues before transfer.”

I

Integrated change control
Integrated change control reviews requests across all affected project areas, obtains authorized decisions and manages approved changes.
“An extra module is assessed for design time, testing, cost, risk and benefits before the board decides.”
Issue
An issue is a current condition or event that affects, or is certain to affect, project objectives and requires action.
“The supplier’s confirmed delay is logged now, even though the planned delivery date has not arrived.”
Issue log
An issue log is a shared record of project issues, their impacts, priorities, owners, actions, status and eventual resolutions.
“The owner updates the response deadline and records the evidence before the issue is closed.”
Issue owner
An issue owner is the named person responsible for driving an issue to resolution, coordinating contributors and reporting progress.
“An issue owner asks specialists for options and checks their actions, although she does not perform every task.”
Issue resolution
Issue resolution is the confirmed outcome of actions taken to address an issue, recorded and communicated before closing its entry.
“After temporary equipment ends a delay, the issue owner records the result and tells those affected.”
Iteration
An iteration is a short delivery cycle in adaptive work during which a team develops an increment and reviews its progress.
“The team selects work for a two-week cycle and demonstrates its completed product at the end.”

L

Lesson identified
A lesson identified is a documented insight or recommendation that has not yet been demonstrated through changed behavior or process.
“The review recommends stock checks, but it remains identified until the purchasing process actually changes.”
Lesson learned
A lesson learned is project experience that has been applied through a change in behavior or process, making its recommendation operational.
“The ordering checklist now requires stock confirmation and future teams use it before placing hardware orders.”
Lessons learned register
A lessons learned register records experience during a project, including evidence and recommendations that can improve current or future work.
“The team records a review practice that succeeded while the people and supporting results are still available.”
Lessons learned repository
A lessons learned repository is an organizational knowledge base where reusable project experience can be found during future work.
“The new project manager searches relevant supplier lessons before preparing the next procurement plan.”

M

Management by exception
Management by exception brings higher authorities into decisions when agreed tolerances are threatened, leaving routine control delegated.
“The sponsor considers a threatened cost limit while the manager handles smaller variations locally.”
Management reserve
Management reserve is budget outside the cost baseline for unforeseen work within approved scope, brought into the baseline with approval.
“Authorized reserve use increases the baseline; a new customer requirement needs its own funding decision.”
Monitoring
Monitoring is the collection and comparison of actual project performance with the plan to identify differences needing attention.
“The manager compares accepted units and actual costs with the approved plan at each weekly check.”

O

Off-specification
An off-specification is a delivered or expected result that departs from its agreed specification and needs a recorded decision or response.
“A supplier confirms its planned component will miss the specified capacity, so the project assesses the issue.”
Operational acceptance
Operational acceptance is the receiving organization’s confirmation that it is ready to run, maintain and support the delivered result.
“Support staff demonstrate access and complete their training before accepting the live service.”

P

Performance threshold
A performance threshold is an agreed boundary used to decide a rating or response when a measure reaches a defined level.
“The project rates an index below 0.90 red and investigates the causes with its sponsor.”
Performance trend
A performance trend is the direction of a measure across reporting dates, showing improvement or deterioration over time.
“CPI falls across three reports, prompting investigation before the cost problem grows further.”
Planned value
Planned value is the budget assigned to work scheduled to be completed by the status date, based on the time-phased budget.
“Design was scheduled to be complete, so its entire budget contributes to PV at the week-eight check.”
Post-project review
A post-project review evaluates how a project was run and what it achieved at closure, providing evidence and lessons for future work.
“The team compares final cost and dates with the approved plan and records what helped or hindered delivery.”
Preventive action
Preventive action is work taken to reduce the chance of a future performance variance before that variance appears.
“The team books an inspector early after learning that appointment waiting times are increasing.”
Product backlog
A product backlog is an ordered collection of product work and requirements, managed by the product owner to guide adaptive selection.
“An urgent idea enters the backlog for ordering before the team decides what to select for an iteration.”
Progress report
A progress report describes results achieved during a reporting period, often alongside current status and future work.
“The weekly update lists accepted deliverables completed since Monday and names next week’s work.”
Punch list
A punch list is the recorded set of minor finishing items left under conditional acceptance, with owners and dates for completion.
“The receiving manager checks the final paint repair against the list before marking that item complete.”

Q

Quality
Quality is the degree to which a deliverable’s characteristics meet agreed requirements and make it fit for its intended use.
“A basic projector meets every agreed requirement, so having fewer premium features than premium models does not reduce its quality.”
Quality assurance
Quality assurance checks processes and standards to help prevent defects and give confidence that requirements will be met.
“An audit finds that planned reviews are skipped and recommends a change to the team’s working process.”
Quality control
Quality control inspects and tests deliverables against their requirements, identifies defects and checks that corrections work.
“The tester records a failed payment case, then verifies the repair and related checkout behavior.”
Quality metric
A quality metric is a defined measure used to assess a product or process against the quality expectations established during planning.
“Page-load time is measured against the agreed requirement that pages load in under three seconds.”

R

Regression testing
Regression testing checks previously working related behavior after a change to find unintended failures introduced by the repair.
“After fixing login, the tester also checks account recovery and other affected sign-in behavior.”
Retrospective
A retrospective is a regular team review of how work was done that identifies successes, problems and specific process improvements.
“The team changes its review arrangements after discussing why work repeatedly waited in Testing.”
Risk
A risk is an uncertain event or condition that may occur and affect project objectives, unlike an issue already current or certain.
“Possible transport disruption remains in the risk register until the situation becomes confirmed.”
Root cause
A root cause is an underlying process or condition that produced a problem and can be addressed to help prevent recurrence.
“Missing stock confirmation explains why orders repeatedly arrive later than the installation plan needs.”

S

Schedule performance index
The schedule performance index is EV divided by PV, a unitless ratio comparing completed work with work scheduled by the status date.
“SPI of 0.80 indicates that 80% of the budgeted work scheduled by that date has been completed.”
Schedule variance
Schedule variance is earned value minus planned value, showing the budget-value gap between completed and scheduled work.
“SV of −$6,000 means less work is complete than planned; it does not mean six thousand days late.”
Schedule variance percentage
Schedule variance percentage expresses SV relative to PV, multiplied by 100, so a schedule-value gap can be compared across sizes.
“SV of −$10,000 against PV of $50,000 gives −20%, triggering the agreed reporting threshold.”
Scope creep
Scope creep is uncontrolled growth in project scope without corresponding adjustments to the approved time, cost or resources.
“Several informal extra reports consume three days while the original delivery commitment stays unchanged.”
Status accounting
Status accounting records controlled items’ current versions and change histories so people can identify their exact approved state.
“The record shows which manual version is approved and which change produced its revised section.”
Status date
A status date is the cutoff point for measuring scheduled work, completed work and costs in a project performance comparison.
“All three earned value measures are calculated cumulatively through the same Friday cutoff.”
Status report
A status report presents a project’s position against its baselines at a particular date and identifies action or decisions needed.
“The sponsor receives the cost and milestone position with a request for approval before Friday.”

T

Task board
A task board is a visible arrangement of work-item cards in columns showing their current stage, such as Testing or Done.
“Cards accumulating in Review tell the team where work is waiting before more items can finish.”
Tolerance
A tolerance is an agreed limit of variation that a project manager can handle without seeking a higher-level decision.
“A five-day forecast slip exceeds the manager’s three-day limit, so it is escalated before go-live.”
Total float
Total float is the time an activity can be delayed without delaying the project’s end date, before any recovery or other change.
“Three days of float absorb part of an eight-day installation delay, leaving five days of end-date impact.”
Traffic-light rating
A traffic-light rating summarizes performance as green, yellow or red using agreed criteria for risk, variance and decision needs.
“A five-day forecast delay is rated red because that is the boundary the sponsor agreed in advance.”

V

Validation
Validation checks whether a deliverable meets the customer’s needs and leads to the customer or sponsor’s formal acceptance.
“The customer evaluates the verified workflow against its intended use and records the acceptance decision.”
Variance
A variance is a measurable difference between planned and actual performance, used to assess the size and cause of a departure.
“A milestone is forecast four days later than its baseline date, so the manager investigates the gap.”
Velocity
Velocity is the work a team completes per iteration, usually in its own story points, used to plan that team’s future work.
“Three completed totals average 20 points, giving a rough pace for estimating the remaining iterations.”
Verification
Verification checks whether a deliverable meets its specification, usually through internal inspection and testing in quality control.
“The team confirms every specified field behaves correctly before presenting the result for acceptance.”

W

Watermelon reporting
Watermelon reporting describes green project reports that conceal known trouble, preventing readers from seeing the real position.
“The report stays green despite a known tolerance breach, so the sponsor does not see the need to act.”
Weighted milestones
Weighted milestones assign fixed shares of a package budget to defined achievements, earning value when those achievements are met.
“The document earns 30% for its draft and another 20% after review, with the rest waiting for approval.”
Work performance information
Work performance information is raw project data compared with the plan so its meaning for objectives can be understood.
“The start date becomes information when the analyst reports that installation began two days late.”
Work-in-progress limit
A work-in-progress limit caps the number of work items allowed in a stage at once to help manage flow and reduce queues.
“A limit of three items in Testing prompts the team to finish tests before pulling more work in.”
Workaround
A workaround is an unplanned response to a problem that has already occurred, developed when that response was not prepared in advance.
“The team rents temporary equipment after an unexpected failure stops work and no planned response fits.”