Project Monitoring and Control
Project Monitoring, Control and Closing
BeginnerLesson 9 of 9 in Project Management Foundations Course
What you will learn
- Compare actual performance with the approved plan, decide when a variance needs action, and report status clearly and honestly in predictive and adaptive projects.
- Compare actual performance with the planUse the baselines, performance data and agreed thresholds to spot variances early and choose a corrective or preventive action.
- Write clear and honest status reportsDecide what a status report contains, use traffic-light ratings with defined criteria, and match the report to its audience and schedule.
- Track progress in adaptive projectsRead task boards, burndown and burnup charts and velocity to follow progress in iterative and agile work, and combine them with sponsor reporting in hybrid projects.
- Compare actual performance with the plan
- Turn the budget, the schedule and the work completed into planned value, earned value and actual cost, calculate the basic variances and indices, and explain what they say about the project.
- Find planned value, earned value and actual costDefine the three earned value measures, calculate them for a status date, and measure percent complete in a way others can check.
- Calculate schedule and cost variances and indicesApply SV, CV, SPI and CPI, read their signs and sizes correctly, and avoid the classic formula mix-ups.
- Interpret earned value results and decide what to doDiagnose a project's situation from its indices and an earned value chart, compare the results with thresholds, and recognize the limits of the measures.
- Find planned value, earned value and actual cost
- Keep problems and changes under control: log issues and resolve or escalate them, and decide every proposed change through one agreed process before the plans and baselines move.
- Recognize and log project issuesTell issues apart from risks, defects and change requests, and record them in an issue log that makes ownership and progress clear.
- Resolve and escalate issuesAnalyze an issue's impact, choose and track a response, and escalate when the issue goes beyond the project manager's authority.
- Run a change request through integrated change controlFollow the steps from change request to decision, analyze the impact on every part of the project, and update the plans and baselines when a change is approved.
- Keep scope and deliverable versions under controlPrevent scope creep and gold plating, manage the versions of deliverables with configuration management, and handle change in adaptive projects.
- Recognize and log project issues
- Make sure the project's outputs meet their requirements: tell quality assurance from quality control, check deliverables against acceptance criteria, and deal with defects.
- Explain quality, quality assurance and quality controlDefine quality in project terms, separate checking the process from checking the product, and explain why preventing defects costs less than finding and fixing them.
- Inspect and test deliverables and handle defectsCheck deliverables against acceptance criteria with inspections, reviews and tests, record and fix defects, and pass verified work on for acceptance.
- Explain quality, quality assurance and quality control
- Bring a project or phase to a controlled end: confirm acceptance, settle contracts, hand over to the people who will use and support the result, close the administration and record lessons for future projects.
- Confirm acceptance and close contractsCheck the closure criteria, obtain formal sign-off for the deliverables, close supplier contracts and close a project that ends early.
- Hand over the result and complete administrative closureTransfer the deliverables to operations with what users and support staff need, release the team, close the finances and write the final project report.
- Capture and apply lessons learnedGather lessons throughout the project, write them so that others can act on them, and make sure future projects use them.
- Confirm acceptance and close contracts
Project Monitoring and Control study guide
1Find out where the project stands
A useful progress check connects evidence to a decision. You need to know what the approved plan required, what work is actually complete, and whether a difference needs action. Reports then make that comparison clear to the people who can help. In adaptive work, boards and burn charts provide a closer view of the same question: how much usable work is moving through the team, and what is blocking it?
1.1 Compare evidence with the approved plan
Monitoring starts with a practical question: what has changed since the last check? Collect evidence, compare it with the approved plan, and investigate the differences. Controlling is the decision and action that follow. Both continue throughout delivery and closure.
Keep a stable reference
A baseline is an approved plan used for comparison. The scope baseline contains the scope statement, work breakdown structure and WBS dictionary. The schedule baseline fixes the approved dates; the cost baseline assigns the approved budget over time. Together they form the performance measurement baseline.
Update working plans and forecasts as new information arrives. Change a baseline only through approved change control. Moving a milestone in the baseline simply because the team is late removes the evidence of the delay. An updated forecast can show a later finish while the approved baseline still shows the original commitment.
Turn observations into decisions
Work performance data are raw facts, such as “testing started May 6.” Work performance information puts them against the plan: “testing started two days late.” A work performance report presents that information for a decision, perhaps on a dashboard.
Follow a repeating cycle: measure, compare, analyze, decide, act, and report. For a task planned evenly over 10 days, six days should produce 60% completion. If only 40% is complete, the gap is 20 percentage points, equivalent to two planned days of work. Investigation finds that a tester is absent. Borrowing a tester for three days is a possible response; first check availability, cost and the effect on other work.
Use the agreed limits
A variance is a difference from the plan. Tolerance sets the amount the project manager can handle without a higher decision. A sponsor might allow cost to vary by 5% and a milestone by one week. Check both the current variance and the forecast. Escalate as soon as a forecast threatens to exceed the authorized limit.
This is management by exception. It gives the project manager room to manage while bringing larger decisions to the sponsor or steering group. Chasing every tiny difference wastes effort; waiting until a limit is actually exceeded loses recovery time.
Match the action to the problem
| Action | Purpose | Example |
|---|---|---|
| Corrective action | Bring performance back into line | Add a shift after falling behind |
| Preventive action | Reduce a future variance | Book an inspector before demand rises |
| Defect repair | Fix unmet requirements | Replace an incorrectly labeled panel |
An action that changes a baseline needs change approval first. A sensible recovery idea does not create authority to increase the budget or change the agreed scope.
Measure completed work
Check scope, quality, risks, issues, resources and stakeholder engagement alongside time and cost. Use evidence such as accepted deliverables, milestones reached, tests passed or meters of cable installed. Split large tasks into smaller pieces with clear completion criteria. “90% complete” reported for several weeks gives little help in deciding what remains. Spending half the budget is evidence of cost, not proof that half the work is finished.
Key Takeaways
- Baselines change only through approved change control.
- Compare objective evidence with the plan before choosing an action.
- Escalate when a forecast threatens the agreed tolerance.
- Corrective action, preventive action and defect repair serve different purposes.
- Money spent does not measure work completed.
1.2 Write a report people can act on
A status report should help its reader make a decision. State what is happening, how it compares with the plan, and what happens next. An honest warning with an owner and an action is more useful than a reassuring color without evidence.
Separate three views
Status describes the position at a particular date. Progress describes results achieved during a period. A forecast estimates the position ahead, such as the expected finish date. One regular report often combines all three. Include the reporting date and period so readers know how current the evidence is.
Give the status of scope, schedule, cost and quality against the baselines. Add accomplishments, next-period work, upcoming milestones, the main risks and issues with owners, and decisions or help needed. Lead with the point the reader must act on. “Held 12 meetings” reports effort; “two of five milestones met” reports results.
Give colors a shared meaning
Traffic-light ratings are often called RAG status. Green means on track and within thresholds. Yellow, also called amber, signals risk or a small drift with recovery action. Red signals a tolerance breach or a need for a higher decision. Define the boundaries before reporting starts.
For example, a team agrees that a milestone forecast less than one week late is yellow and one week or more late is red. A seven-day forecast delay is red under that rule. The team also needs a rule for the overall color; many organizations use the worst area. Do not quietly average away a red schedule with green cost and quality.
Write a complete status line
Use fact against plan, cause, action, and request:
“Schedule: Yellow. Course design is 75% complete against 100% planned at week 8. The subject expert was unavailable for two weeks. A second designer will join in weeks 9 and 10 to protect the week 12 pilot. Approval of $3,000 is needed by Friday.”
The line makes the shortfall visible and gives the sponsor a specific decision and deadline. If a cause is still being investigated, say what is known and assign that investigation; a confident guess can send recovery work in the wrong direction.
Choose the right detail
Sponsors need exceptions, decisions and a short overall view, often monthly or at phase ends. A forecast tolerance breach needs an exception report immediately. Team members need detailed task information more often, usually daily or weekly. Customers need milestone and acceptance information. The communication plan states who receives each report, when and in what form.
A milestone chart can compare approved and forecast dates. A Gantt chart can show task progress; a trend chart can show whether variance is growing. Add a short explanation of causes and actions so the visual supports a decision. Send reports before status meetings and use the meeting to resolve red and yellow items, with owners and dates for agreed actions.
Report trouble while help can work
Watermelon reporting means green reports conceal a troubled project. It often grows where bad news is punished or people hope to recover quietly. Rate the evidence honestly and give the recovery plan. A vague “mostly on track” leaves readers unable to judge whether they need to intervene.
Key Takeaways
- Report status, recent progress and the forecast with a clear date.
- Define traffic-light criteria and the overall-rating rule in advance.
- A useful status line gives the fact, cause, action and request.
- Match detail and timing to the reader.
- Use meetings for decisions and problem solving.
- Report yellow or red when evidence supports it.
1.3 Read boards and burn charts
Adaptive teams deliver usable work in short iterations, often one to four weeks long. Progress is visible in working increments and completed work items. A board shows flow; burn charts show how completion relates to time and scope.
Watch where work waits
A task board moves cards through columns such as “To do,” “In progress,” “Testing” and “Done.” Work-in-progress limits cap the cards allowed in a column. If cards build up in Testing, testing is a bottleneck. Starting more work may enlarge the queue while leaving the bottleneck untouched. The visible board acts as an information radiator, giving people a shared view without needing a separate report each time.
The daily stand-up coordinates the day and exposes blockers. The iteration review lets stakeholders inspect the product and give feedback. The retrospective examines the team's way of working and chooses improvements. A product problem and a process problem need different conversations, even when one reveals the other.
Read remaining work
A burndown chart places time on the horizontal axis and remaining work on the vertical axis. The ideal line falls to zero. In a 10-day iteration with 60 points, it falls by six points per day. At day 5, the ideal remaining work is 30 points. If 36 remain, the team has six more points remaining than the ideal line.
A line above the ideal indicates that work is behind that planned pace; a line below indicates that it is ahead. Ask about blockers and changes in scope before deciding why the lines differ. A burndown shows the amount remaining but does not separate new work from slow completion.
Separate completion from scope growth
A burnup chart shows completed work rising toward a separate total-scope line. If release scope rises from 200 to 220 points, the scope line moves up by 20. The completed line still shows what the team delivered. This helps explain why steady delivery can coexist with a finish that keeps moving away.
Use velocity for one team
Velocity is work completed in an iteration, usually measured in story points. Three iterations completing 18, 22 and 20 points average 20 points. If 220 points are in scope and 120 are complete, 100 remain. At that pace, they need about five more iterations. This is a planning estimate; it depends on the team's future pace and the remaining scope.
Count only work meeting the definition of done, the shared completion standard. A story that is 90% finished at iteration end earns no completed points yet. Partial credit hides work still needing tests or other finishing steps. Each team sizes its own points, so comparing team velocities is misleading. Inflating estimates changes the number without increasing delivery.
Connect team and sponsor views
A hybrid project can use a board for development and still report milestone, budget and risk information to its sponsor. Translate the team's measures into an understandable delivery outlook: “120 of 220 points are done. At 20 points per two-week iteration, about five iterations remain, matching the release planned ten weeks from now.” Keep the scope and pace behind that outlook visible when reporting changes.
Key Takeaways
- A board shows flow and queues; WIP limits constrain simultaneous work.
- Burndown tracks remaining work; burnup separates completed work from total scope.
- Velocity is a planning measure for the same team.
- Only work meeting the definition of done earns completed points.
2Measure work against its budget
A spending total cannot tell you whether a project is doing well. You also need the budgeted value of the work that should be complete and the work that actually is complete. Earned value brings those quantities together at one status date. The calculations show schedule and cost performance, while the dates, quality checks and underlying records help you decide what the numbers mean and where action is needed.
2.1 Build planned value, earned value and actual cost
Earned value management combines scope, schedule and cost. It gives completed work a value based on its approved budget, so you can compare achievement with both the plan and the actual cost. Choose a status date and measure everything up to that date.
Ask three different questions
| Measure | Question it answers | Where it comes from |
|---|---|---|
| Planned value, PV | What work should be done by now? | Time-phased budget |
| Earned value, EV | What work is actually done? | Completion evidence valued at budget |
| Actual cost, AC | What has the work cost? | Costs incurred |
Budget at completion (BAC) is the budget for all planned work in the cost baseline. Management reserve is outside it. The training rollout has budgets of $8,000 for needs analysis, $12,000 for course design, $10,000 for materials and $20,000 for delivery. BAC is $50,000.
PV accumulates as work is scheduled. Its cumulative graph is often an S-curve: slow at the start, steeper during delivery, then flatter near completion. At the planned finish, cumulative PV equals BAC. Older records may call PV, EV and AC “BCWS,” “BCWP” and “ACWP.” They name the same three measures.
Work through the week 8 position
| Work package | Budget | PV | Complete | EV | AC |
|---|---|---|---|---|---|
| Needs analysis | $8,000 | $8,000 | 100% | $8,000 | $9,000 |
| Course design | $12,000 | $12,000 | 75% | $9,000 | $8,500 |
| Materials | $10,000 | $4,000 | 20% | $2,000 | $2,500 |
| Delivery | $20,000 | $0 | 0% | $0 | $0 |
| Total | $50,000 | $24,000 | — | $19,000 | $20,000 |
Course design earns 75% of its $12,000 budget, or $9,000. Materials earn 20% of $10,000, or $2,000. Add earned amounts, not completion percentages: the packages have different budgets. The total EV of $19,000 is below PV of $24,000 and below AC of $20,000.
Choose a completion rule before work starts
Subjective guesses make progress easy to overstate. Use an agreed rule consistently:
- 0/100: earn nothing until completion; useful for short tasks.
- 50/50: earn half at the start and half at completion.
- 20/80: earn 20% at the start and 80% at completion.
- Weighted milestones: earn a set share when each milestone is met.
- Physical measurement: use counted units of completed work.
A started but unfinished $6,000 package earns $0 under 0/100, $3,000 under 50/50 or $1,200 under 20/80. A $10,000 document with weights of 30% for draft, 20% for review and 50% for approval earns $5,000 after draft and review. Laying 120 of 400 meters of cable gives 30% physical completion.
Keep the comparison consistent
Use the same status date, unit and cost basis for all three measures. Cumulative EV needs cumulative AC, not just this month's cost. If the budget includes labor and materials, AC must include both. Hours can replace money when all three measures use hours consistently. EV cannot exceed BAC. Money spent and work scheduled are neither proof of completion nor substitutes for EV.
Key Takeaways
- PV values scheduled work; EV values completed work; AC records cost incurred.
- BAC is the total cost baseline and excludes management reserve.
- Value each package using its own budget and completion rule.
- Choose completion rules during planning and apply them consistently.
- Match the status date, units, cost basis and reporting period.
2.2 Calculate variances and performance indices
Start each basic performance formula with earned value. Then choose whether you are comparing completed work with the plan or with its actual cost. Variances subtract; indices divide. This keeps the four measures distinct.
Choose the comparison
| Measure | Formula | Meaning of an unfavorable result |
|---|---|---|
| Schedule variance, SV | Negative: less work done than planned | |
| Cost variance, CV | Negative: work cost more than its budget | |
| Schedule performance index, SPI | Below 1: behind the planned work | |
| Cost performance index, CPI | Below 1: over cost for completed work |
Zero variance means on plan; a positive variance is favorable. An index of 1 means on plan; above 1 is favorable. The indices have no unit. Variances use the earned value unit, usually money, so SV does not tell you the number of days late.
Calculate a complete example
A project has BAC of $80,000. Half the work was scheduled by month 4, giving PV of $40,000. Actual completion is 35%, giving EV of $28,000. AC is $32,000.
- Subtract planned value from earned value: SV is $28,000 minus $40,000, or −$12,000.
- Subtract actual cost from earned value: CV is $28,000 minus $32,000, or −$4,000.
- Divide earned value by planned value: SPI is or 0.70.
- Divide earned value by actual cost: CPI is or 0.875, rounded to 0.88.
The project has completed 70% of the budgeted work scheduled by this date. It earns 87.5 cents of budgeted work per dollar spent. It is behind schedule and over cost, even though it has spent less than the $40,000 scheduled budget.
Apply the same method to the rollout
At week 8, PV is $24,000, EV is $19,000 and AC is $20,000. SV is −$5,000, CV is −$1,000, SPI is about 0.79 and CPI is 0.95. The work shortfall against the plan is greater than the cost shortfall against the budget for completed work.
Express a variance as a percentage
Divide SV by PV for the schedule variance percentage. Divide CV by EV for the cost variance percentage. Multiply each ratio by 100 to express it as a percentage.
For the month 4 example, − gives −30% schedule variance. For cost, − gives about −14.3%. These percentages help compare projects of different sizes and apply a rule such as escalating a cost variance worse than −10%.
Avoid the tempting shortcuts
Comparing AC with PV mixes spending with scheduled work. If PV is $50,000, EV is $36,000 and AC is $45,000, the project is not $5,000 under cost. It spent $45,000 on work budgeted at $36,000, so CV is −$9,000 and CPI is 0.80. SPI is 0.72.
Reversing either division also reverses the signal: AC divided by EV looks greater than 1 when cost performance is poor. Keep EV first, select PV for schedule or AC for cost, and round indices only after calculating from the full values.
Key Takeaways
- All four measures begin with EV.
- SV and SPI compare EV with PV; CV and CPI compare EV with AC.
- Negative variances and indices below 1 are unfavorable.
- SV is a budget-value gap, not a delay in days.
- SV% uses PV as its denominator; CV% uses EV.
- Round at the end and never judge cost from AC against PV.
2.3 Turn earned value results into action
The numbers identify a performance pattern. They do not identify its cause by themselves. Read schedule and cost together, compare them with the agreed thresholds, and then check the detailed evidence before selecting a response.
Read the two indices together
| SPI | CPI | Interpretation |
|---|---|---|
| At least 1 | At least 1 | On or ahead of planned work; on or under cost |
| Above 1 | Below 1 | Ahead of planned work but over cost |
| Below 1 | Above 1 | Behind planned work but under cost for what is complete |
| Below 1 | Below 1 | Behind planned work and over cost |
Overtime or extra staff may buy speed at a higher cost. A delayed activity may explain a low SPI, but it does not explain a high CPI: that separate result could reflect lower rates, cheaper materials or generous estimates. Investigate the schedule and cost findings separately. Favorable figures still need checks for padded estimates or reduced quality.
Read the chart at one date
An earned value chart plots cumulative PV, EV and AC against time. Locate the status date and compare the lines vertically. EV below PV shows less work completed than scheduled. AC above EV shows that the completed work cost more than its budget. The gaps correspond to SV and CV; the horizontal axis does not turn a vertical money gap into days of delay.
Suppose the rules are green at 0.95 or higher, yellow from 0.90 to below 0.95, and red below 0.90. The rollout's CPI of 0.95 is green, while SPI of about 0.79 is red. Schedule recovery needs attention. Options include changing the sequence, adding people to critical work or proposing a scope reduction. A baseline change still needs approval.
Look beneath the total
An overall CPI of 0.95 can hide uneven performance. Needs analysis has CPI of about 0.89. Course design has about 1.06. Materials have or 0.80. Investigating materials may reveal a problem that the overall figure makes look modest.
Watch trends too. A CPI moving from 0.98 to 0.95 to 0.91 is deteriorating. Each report should explain what action is being taken and who owns it. Waiting for the last number to become severe loses time.
Keep dates and quality beside the indices
SPI weighs work by budget. It does not show whether the critical path is on time. Ahead-of-plan noncritical work can offset a late critical activity in the total. Check the schedule network, critical activities and milestone forecasts.
At completion, EV equals BAC. Once the planned finish has passed, PV also equals BAC. A $50,000 project planned for week 10 but finished in week 13 therefore ends with SPI of 1 and SV of zero. Its three-week delay remains visible in the dates.
Check the inputs before diagnosing
Late invoices can make AC appear too low. Optimistic completion estimates can make EV too high. A system still using the old baseline after a change gives an outdated PV comparison. Check costs incurred, completion evidence and approved baseline versions. EVM does not measure quality: work later found defective may overstate achievement and create rework. Review test and acceptance evidence alongside the financial measures.
Key Takeaways
- Read cost and schedule as separate findings before explaining their causes.
- Apply agreed thresholds and investigate work-package results and trends.
- Check critical-path and milestone dates alongside SPI.
- At completion, SPI can equal 1 even after a late finish.
- Reliable indices need reliable costs, completion evidence and baseline versions.
3Resolve problems and control changes
Projects encounter problems and useful new ideas while work is underway. An issue needs a clear owner and a response; a proposed change needs an informed decision by someone with authority. These controls connect when resolving a problem would alter the approved plan. Keeping the logs linked and deliverable versions clear lets people act on the decision without losing track of what was agreed or why it changed.
3.1 Make an issue visible and owned
A concern becomes manageable when people can see what happened, why it matters and who will take it forward. An issue is a current condition or event that affects, or is certain to affect, project objectives and needs action. A risk is still uncertain.
Decide what you are recording
“The supplier might deliver late” is a risk. “The supplier confirms delivery will be eight working days late” is an issue. You do not need to wait eight days to log it: the confirmed delay already needs action.
When a risk occurs, update or close its risk entry and open an issue. Carry out the planned response if one exists. An unplanned response to a problem that has occurred is a workaround. Keeping the link to the risk record helps people see which preparation worked and what was missing.
Recognize related records
| Record or type | What it deals with |
|---|---|
| Problem or concern | A current difficulty, such as a resource conflict |
| Request for change | A proposal for something new or different |
| Off-specification | An actual or expected departure from specification |
| Question needing a decision | A matter that cannot progress without an answer |
| Defect | A deliverable that fails a requirement |
Many organizations use the issue log to capture several of these types, then route change requests to change control. Individual defects normally belong in the defect log through quality control. Repeated defective supplier parts may also need a project issue when they threaten the delivery date. The logs serve different purposes and can refer to the same underlying event.
Write enough for someone else to act
An issue log, also called an issue register, needs an ID, a specific description, the date and person raising it, type, impact, priority, one owner, actions and target dates, status, and the eventual resolution.
For example: “I-014. Supplier email of May 12 confirms servers will arrive eight working days late. Installation and go-live are affected. High priority. Owner: J. Rivera. Assess response options by May 14. Status: open.” This tells a new reader more than “IT problem.” Record evidence and the effect on objectives, not just a broad topic.
A log can be a shared table or a tool with assigned records. What matters is that the team can find the current entry and review it. Personal email alone hides actions from people who need to coordinate them.
Set priority using two questions
Impact asks how much scope, schedule, cost, quality or benefits are affected. Urgency asks how soon action is needed. A payroll error one week before go-live combines high impact and urgency. A small spelling error in an internal guide has a different priority. A quiet but severe issue can deserve attention before a frequently discussed minor one.
Assign one accountable person
Every issue needs one named owner. A department cannot personally chase an action, bring options to a meeting or confirm that a response worked. The owner coordinates that work and reports progress; other people may perform the technical tasks. Review the log regularly so priorities and dates remain useful as the project changes.
Key Takeaways
- An issue is current or certain; a risk remains uncertain.
- Link a realized risk to its issue and carry out the planned response.
- Record the event, impact, owner, action and date clearly.
- Set priority using both impact and urgency.
- One named person drives each issue to resolution.
3.2 Choose a response and escalate in time
Logging a problem starts the work; it does not resolve it. The owner needs to assess the impact, compare responses, obtain any higher decision, and track the action until its result is confirmed.
Work through the response
Capture the issue, assess priority, assign an owner, identify options, decide within authority, act and monitor, then close and communicate the resolution. If the decision exceeds the project manager's authority, escalation belongs before the action requiring that authority.
Begin with the effect on objectives. A supplier delay does not automatically move the end date by its full length. Total float is the delay an activity can absorb without moving the project's end date.
In the training rollout, installation is delayed eight working days and has three days of total float. The first three days use the available float; the remaining five move the end date if nothing else changes. Installation then has no float left. Check the schedule network when assessing options, because another task may also depend on the delivery.
Compare workable options
For the late servers, the team might accept the five-day delay, rent temporary servers for $1,500, re-sequence installation and testing using existing test servers, or request a later go-live date. Compare cost, time saved and risk. Check that rental equipment meets the technical need and that re-sequenced work respects dependencies.
Give the chosen response’s actions owners and dates, then track whether it saves the expected time.
Take the right decision upward
Suppose the project manager can handle an end-date movement of up to three working days. The five-day forecast slip exceeds that tolerance. Escalate now, even though go-live is still in the future. The agreed path might be team member to project manager, then sponsor, then steering group.
A useful escalation gives the issue, measured impact, options and recommendation. “Servers are late; please help” transfers an unexplained problem. “Eight days late, three days float, five-day end-date effect; recommend temporary servers for $1,500” gives the decision maker something concrete to assess. Include the decision deadline if waiting would remove a viable option.
Connect the logs when the plan must change
Moving go-live, adding budget or removing scope changes a baseline and needs a change request. Keep the issue entry for the problem and the change entry for the proposed plan change and its decision. Cross-reference their IDs. Escalation itself is not approval to alter a baseline.
Close the loop
At regular reviews, follow up overdue actions, update status and reassess priority. Close the issue after resolution is confirmed and recorded, and tell affected people. Age alone is no reason to close an unresolved issue. At project end, transfer remaining issues to named people in the receiving organization.
Investigate the cause as well as the symptom. The server delay began with an order placed without checking stock. Confirming stock before future orders addresses that cause; renting servers only treats this occurrence.
Key Takeaways
- Use float when assessing the effect on the end date.
- Compare response cost, time saved and risk.
- Escalate a forecast tolerance breach before it occurs.
- A baseline change needs a linked change request.
- Confirm and communicate resolution before closing an issue.
- Address the cause to reduce repeat problems.
3.3 Decide changes before changing the plan
A small scope addition can need more design time, testing, money and support. Integrated change control considers those effects together and puts the decision with the authorized person or group. Its purpose is to make change deliberate and informed.
Capture a complete proposal
Anyone involved can raise a change request. Write it down and enter it in the change log. Requests can concern new requirements, changed documents or deliverables, baseline-changing corrective or preventive action, or repairs to items under formal control. A conversation with a stakeholder does not authorize a team member to start the work.
Describe the proposed change and why it is needed. Analyze effects on scope, schedule, cost, quality, risk, resources and benefits. Identify alternatives, including what happens if the request is rejected or deferred. An analysis limited to purchase cost can miss testing time or a new operational risk.
Follow the decision through
- Raise and log the request.
- Analyze the full impact and options.
- Obtain an approve, reject or defer decision from the authorized person or group.
- Communicate the decision to everyone affected.
- For approval, update plans, baselines and affected documents, then implement.
- Verify the result and close the entry.
Rejected and deferred requests remain in the log with reasons. A change control board (CCB) is a formally selected group that decides requests within its authority. Delegation can make small decisions quicker. For example, a project manager may approve costs up to $2,000 and delays up to three days; a request must meet both limits to stay within that delegation.
Trace one approved addition
HR asks for an extra e-learning module in the training rollout. Sixty design hours at $100 per hour add $6,000. The end moves from week 20 to week 22; the week 12 pilot stays unchanged. The new platform also adds a risk because the team has not used it before.
The request exceeds the project manager's limit. The board approves the module and $6,000 of additional funding. BAC rises from $50,000 to $56,000. The scope baseline gains the module, the schedule baseline records week 22, and the cost baseline and PV curve are updated. Communicate the decision so designers, testers and the sponsor work from the same approved plan. Verify the new module against its agreed requirements when complete.
Know where reserves belong
Contingency reserve is already inside the cost baseline for identified risks, used as the risk plan describes. Management reserve sits outside it for unforeseen work within approved scope. Its use needs approval and increases the cost baseline. A new requirement needs authorized funding for the expanded scope; it is not unforeseen work within the original scope.
After a change is approved, measure performance against the updated baseline. Keep the change history so people can explain how commitments moved. An approval with an unchanged budget system or old schedule circulating is incomplete control.
Keep problems and decisions connected
The issue log tracks problems and resolutions. The change log tracks proposals and decisions. A problem can prompt a request, and an approved change can create risks or issues. Link entries so readers can trace the cause, decision and implementation without merging their different jobs into a vague action list.
Key Takeaways
- Log and analyze requests before implementation.
- Assess schedule, quality, risk and resources as well as cost.
- Obtain the decision from the authorized person or board.
- Communicate approval and update every affected baseline and document.
- Use reserves according to their purpose; fund new scope through approval.
- Verify implementation before closing the change entry.
3.4 Protect scope and use the right version
Changes become difficult to control when people start extra work informally or use different versions of the same deliverable. Scope control decides what the project will deliver. Configuration management keeps the approved characteristics and versions clear.
Spot uncontrolled additions
Scope creep is uncontrolled growth without matching adjustments to time, cost or resources. Three extra reports that each seem to need only one day still add three days of unplanned work. Record the requests and assess their combined effect.
Gold plating is an extra feature the team adds on its own, beyond the agreed requirements. It uses resources and adds risk even if the team thinks the customer will like it. Propose useful ideas through the change process so the customer and authorized decision maker can judge their value.
Clear scope and measurable acceptance criteria give requests a reference point. Use one request channel, supported by the sponsor. A useful response is: “Thanks, I'll log that as a change request so we can look at its effect on the dates and budget.” It acknowledges the idea and starts an assessment without making an unauthorized promise.
Control the delivered version
A configuration item is a deliverable or component whose characteristics and versions are controlled. Change control decides whether a change should happen; configuration management records exactly what each version contains and how it changed.
Its activities are:
- Planning which items are controlled and how.
- Identification with a unique ID and version number.
- Control of changes to baselined items, including check-out and check-in.
- Status accounting: current versions and change histories.
- Verification and audit: checking delivered items against records and requirements.
For example: “Manual v1.2, approved May 3. Manual v1.3 is a draft adding the e-learning section authorized by CR-07.” The draft is not the approved version. The change reference explains why the new version exists; the version number identifies the exact content being reviewed or printed.
Keep one master repository. If two trainers edit separate slide decks and a printer combines both, learners may receive conflicting instructions. Version labels, controlled access and a change history help the team find the approved set and prevent accidental mixing.
Handle adaptive change through the backlog
Adaptive projects expect requirements to evolve. The product owner orders new and changed items in the product backlog by value. New work normally waits for the next iteration planning. During an iteration, the product owner and team can clarify and renegotiate selected work as they learn, while protecting the iteration goal. Urgency does not let one person add work unilaterally.
Time and cost are often fixed while the selected scope flexes. A change to the overall budget, contract or release date still needs formal approval. Backlog control and formal authority can therefore operate together in the same project.
The control method fits the work: a predictive baseline uses formal requests; an adaptive team controls selection and ordering through the backlog and iteration boundaries. In both, people need to know what was agreed, who may change it, and which version is current.
Key Takeaways
- Scope creep is uncontrolled addition; gold plating is an unrequested team addition.
- A request channel and measurable scope help prevent informal promises.
- Configuration management identifies and tracks controlled versions.
- Backlog ordering controls adaptive changes while protecting the iteration goal.
4Check that deliverables meet requirements
Quality depends on clear requirements and work that meets them. Planning defines the checks, quality assurance examines how the work is done, and quality control examines the deliverables. These activities help the team prevent repeated mistakes, find defects early and supply evidence for customer acceptance. A high pass rate still needs careful reading when the acceptance rules also prohibit critical failures.
4.1 Build quality into the work
A deliverable has high quality when its characteristics meet the agreed requirements and it is fit for its intended use. A high price or a long feature list cannot substitute for that fit. Quality starts with planning and remains everyone's responsibility during delivery.
Separate quality from grade
Grade groups products with the same use but different technical characteristics. Basic and premium laptops have different grades. A basic model that meets its requirements can have high quality; a premium model with a faulty battery has a quality problem.
This distinction helps teams judge the right thing. Adding premium features does not repair a failed requirement. A clean, working basic hotel room can meet its intended standard even though it offers fewer services than a luxury room.
Plan the evidence early
Quality planning defines applicable standards, metrics, acceptance criteria, responsibilities and timing. Record these in the quality management plan. A quality metric is a measure, such as page-load time or the percentage of trainees passing an assessment. A criterion sets the required result, such as pages loading in under three seconds or no open critical defects at release.
Agree these requirements before producing the deliverable. Otherwise, a team can spend heavily on an output and discover at the end that its customer expects a different standard. Give each check a responsible person and a suitable point in the work.
Check process and product
| Activity | Main focus | Example |
|---|---|---|
| Quality assurance (QA) | Processes and standards used to prevent defects | Audit whether regression tests are performed |
| Quality control (QC) | Deliverables against requirements and criteria | Run a checkout test and record failure |
QA gives confidence that the way of working can produce the required result. QC finds defects and confirms that repairs work, producing verified deliverables. They inform each other: repeated checkout failures may point to a weak review or test process that needs QA attention.
Understand the cost of quality
The cost of quality includes the effort to prevent and check defects and the losses when defects occur.
| Group | Category | Example |
|---|---|---|
| Conformance | Prevention | Training, standards, design reviews |
| Conformance | Appraisal | Inspection and testing |
| Nonconformance | Internal failure | Scrap and rework before delivery |
| Nonconformance | External failure | Complaints, recalls and warranty claims after delivery |
Suppose prevention costs $2,000, appraisal $3,000, internal failure $5,000 and external failure $12,000. Total quality cost is $22,000. Only $5,000 is conformance cost; the remaining $17,000 arises from failures. Counting only test spending misses most of the picture.
A requirement error caught in review may take minutes to fix. After delivery it can require rework, customer support and damage repair. Investing in prevention and appraisal usually reduces failure costs. Inspection can reveal poor work, but it cannot build quality into work already done.
Team members are responsible for their own work. The project manager makes sure the quality activities happen, and independent reviewers or auditors may examine processes. Leaving quality entirely to testers at the end removes opportunities to prevent errors earlier.
Key Takeaways
- Quality means meeting agreed requirements and intended use.
- Grade describes different technical categories, not whether requirements are met.
- QA checks processes; QC checks deliverables.
- Conformance costs cover prevention and appraisal.
- Nonconformance costs cover failures before and after delivery.
4.2 Test, repair and verify deliverables
Quality control compares an actual deliverable with measurable requirements. Choose a method that fits the output, record the results and follow defects through repair and retest. The evidence supports acceptance but does not replace the customer's acceptance decision.
Choose a suitable check
Inspect physical work directly, such as a room's measurements. Use peer reviews or walkthroughs for documents, designs and code. Run planned test cases for software or equipment. A checklist helps reviewers perform all required checks consistently.
Acceptance criteria state the conditions needed for acceptance and are agreed with the customer before the work. “Works in the current versions of four named browsers” can be tested. “User-friendly” needs a clearer measure. Adaptive teams use item-specific criteria together with a shared definition of done, which may require review, passed tests and updated user help.
Apply every acceptance condition
A website release has 40 test cases. Its rule requires no critical failures and at least 95% of cases passing. The first run passes 37 cases and fails three, including card payments, a critical case.
The pass rate is 37 out of 40, or 92.5%. It fails the percentage requirement and the no-critical-failure rule. Fixing enough minor cases to reach 95% would not make the release ready while the critical payment failure remained.
After repair and retest, 39 pass. That is 97.5%, and the one remaining failure is cosmetic. The release now meets the stated criteria. Record the remaining item and its agreed treatment so it is not lost.
Track defects to a checked result
A defect log needs an ID, description, severity, finder and date, owner, status, repair and retest result. Severity describes how serious the failure is and drives the order of repair. A clear record lets testers reproduce the problem and lets the owner show that it is resolved.
Possible treatments are repair, replacement, rejection, or a concession: a formal customer decision to accept the item as it is, sometimes with a later fix or price adjustment. The team cannot grant itself a concession. A repair that changes an approved baseline needs change control.
Retest every repair. Also run related tests: regression testing checks that the change has not broken behavior that worked before. A payment repair might affect related checkout steps, so repeating only the originally failed test is incomplete evidence.
Separate verification and validation
| Check | Question | Typical outcome |
|---|---|---|
| Verification | Does it meet the specification? | Verified deliverable from QC |
| Validation | Does it meet the customer's needs? | Customer or sponsor acceptance |
In a predictive project, internal QC usually precedes customer acceptance. Passing internal tests does not itself provide sign-off.
When checking every item is too costly or destructive, inspect a planned sample, such as 20 of 500 manuals. Missing pages in the sample prompt a wider batch check. Repeated similar defects also call for process investigation through QA. Keep failed work out of completion claims until it meets the applicable quality checks; premature earned value credit hides rework.
Key Takeaways
- Agree measurable acceptance criteria before delivery.
- Meet each acceptance condition, including critical-failure rules.
- Log defects, assign owners and retest repairs.
- Regression testing checks related behavior after a change.
- Verification supplies QC evidence; validation addresses customer needs and acceptance.
- Use sampling deliberately and investigate recurring defect patterns.
5Finish with acceptance and a usable handover
Finishing the last task leaves several responsibilities to settle. The customer needs to accept the result, suppliers need their contracts closed, and operations needs the people, information and access to run what was delivered. Closure also records actual performance and transfers remaining actions. Lessons become useful when later teams can find them and someone turns the recommendations into a changed process or habit.
5.1 Confirm acceptance and settle contracts
Closing formally completes a project or phase. It happens after objectives are met or after an authorized decision to end early. A clear closure process prevents work from drifting on with no settled responsibility, budget or end point.
Check readiness to close
Closure criteria belong in the plan. They normally require deliverables to be accepted, contracts settled, remaining issues and risks transferred to owners, records archived and resources released. Use a closure checklist to coordinate the sequence and confirm completion.
Phase closure applies the same controls to a smaller part of the work and ends with a decision about continuing. Completing a phase does not automatically authorize the next one. A review may show that further work no longer offers enough value.
Obtain written acceptance
Formal acceptance, or sign-off, is written confirmation from the customer or sponsor that deliverables meet their acceptance criteria. Identify the deliverable and version, the evidence, the accepting person and the date. For example: “E-learning module v2.0: 12 of 12 criteria met; accepted by the HR director on June 28.”
Individual outputs are often accepted during delivery; final acceptance confirms the whole. Silence is weak evidence because it does not show which version or criteria someone approved. Written acceptance supports closure and payments linked to acceptance. Operational responsibility follows the handover arrangements, and outstanding claims are settled separately.
Manage minor open items
Conditional acceptance records acceptance with minor items still to finish. A punch list, also called a snag list, gives each item an owner and date. An office fit-out might be accepted with four finishing items due within ten working days. Track them until complete.
The list is an active record, not a way to make outstanding work disappear. The acceptance decision needs to state the conditions so the customer, team and receiving staff share the same understanding of what remains.
Close each supplier contract
Contract closure can occur before the overall project ends. For each contract:
- Confirm that contracted work was delivered and accepted.
- Settle final invoices, payments and any retained amounts.
- Resolve open claims, using negotiation where possible.
- Notify the supplier formally that the contract is complete.
- Archive the contract records and record supplier performance.
Acceptance of the product does not settle a disputed invoice by itself. Keep enough people and financial access available to complete the final transactions. Close cost accounts after the final costs have been handled; closing them too early can prevent invoices from being recorded properly.
Close an early termination properly
A project may end because its business case no longer works, funding is withdrawn or the need disappears. Record the decision and reason. Document the state of each deliverable, hand over usable work, settle contracts under their termination terms, release resources and capture lessons.
An early stop still creates records and responsibilities. Abandoning the administration leaves a “zombie” project consuming effort with no clear purpose. Plan the team's release around the closure tasks so the people who know the work can finish the evidence and handover.
Key Takeaways
- Use planned closure criteria for project and phase closure.
- Formal acceptance identifies what was accepted, by whom and when.
- Conditional acceptance needs a tracked punch list with owners and dates.
- Settle contracts and final costs before closing the related administration.
- Early termination still requires controlled closure.
5.2 Prepare operations and complete the records
A finished deliverable needs people who can run, maintain and support it. Handover, or transition, transfers it into normal business with those arrangements in place. Involve the receiving staff early and agree what readiness means with them.
Assemble a usable handover
The package includes deliverables and their approved configuration, user guides, operating and maintenance instructions, relevant drawings, training, support contacts and service levels. Include warranties, supplier contacts, open risks and issues with new owners, and the access rights and licenses needed to operate the result. Transfer access securely.
Check the package with the people who will use it. A manual in a folder is little help if the service team cannot locate it or has no access to the system it describes. Schedule training and practice before responsibility changes hands.
Operational acceptance confirms that the receiving organization is ready to run the deliverable. This differs from customer sign-off against product criteria: it concerns readiness to operate. Agree the handover point and responsibilities explicitly.
Give early support an end point
Extra help after go-live is often called early life support or hypercare. Agree who provides it, how long it lasts and its exit criteria. Otherwise, the project team may remain the informal support service long after closure. Open actions and risks need named receiving owners who understand what they are accepting.
A warranty expiry date is certain information to record. The risk is that equipment fails after expiry and causes unplanned repair cost. Record both the date in the documentation and the risk with its new owner.
Separate outputs from later benefits
The project delivers outputs; the sponsor or business owner remains responsible for realizing and measuring benefits afterward. A new onboarding system may be live at closure while its effect on onboarding time is measured six months later.
A post-project review evaluates delivery performance at closure. A later benefits review checks whether expected improvements arrived. Agree who will measure the benefit and when, so ending the project does not end accountability for value.
Finish the administration
Record final scope, schedule, cost and quality results. Settle final costs, close cost accounts and work orders, archive plans and baselines, logs, decisions, acceptance evidence and contracts. Update templates and estimating information that future teams can use.
The final project report compares objectives with actual results. Include main variances and causes, quality results, benefits outlook, open items with owners and key lessons. In the rollout, the approved budget after change is $56,000 and actual cost is $58,800. The $2,800 overrun is 5% of that budget. Final CPI is about 0.95. Finish in week 23 against baseline week 22 is one week late. Use the approved post-change baseline and explain its history.
Release people and equipment in time
Tell functional managers when people will be available, provide performance feedback, return equipment and facilities, and recognize the team's work. Keep the people needed for closure until their handover and record tasks are done. A resource-release plan makes the finish orderly for both the project and the next assignment.
Key Takeaways
- Operational acceptance confirms readiness to run and support the result.
- Transfer documentation, training, support, access and open responsibilities.
- Agree early support exit criteria.
- The business owner or sponsor tracks benefits after handover.
- The final report compares actual results with approved baselines.
- Complete closure tasks before releasing the people needed for them.
5.3 Turn experience into a useful lesson
Lessons learned record what a project teaches about successful and unsuccessful ways of working. Their value comes from a practical change that helps the next team repeat a success or avoid a problem. A complaint without a recommendation gives that team little to use.
Capture experience while it is fresh
Record lessons throughout delivery: at phase ends, after major events and in iteration retrospectives. At the end, people may have left and details may be forgotten. Keep a lessons learned register during the project, then place reusable lessons in the organization's searchable repository at closure.
Gather several views. Use a workshop or post-project review, short surveys, and evidence from issue and change logs, the risk register and variance data. A retrospective asks what went well, what could improve and what the team will do differently. Include effective practices, such as a review that prevented a costly error, as well as failures.
Make discussion safe enough to be useful
Focus on processes and conditions. If people expect personal blame, they may hide the information needed to prevent a repeat. Ask what enabled an error, which checks were missing and what would make the next decision better. A facilitator who was not directly involved can help the group hear different accounts fairly.
Blameless discussion still produces clear actions. An action owner takes responsibility for an improvement; naming that owner is different from blaming someone for the original event. Record the evidence supporting a cause so the group does not turn a suspicion into a permanent rule.
Write a lesson someone can apply
Include the situation, what happened, its measured effect, root cause and a specific recommendation. “Communication with the supplier was poor” gives neither evidence nor a usable next step.
A stronger record is: “The server order was placed without stock confirmation. Delivery was eight working days late, using three days of float and moving go-live five days. For long-lead hardware, confirm stock and delivery dates in writing before ordering, and show delivery as a separate schedule activity.”
The effect is measurable, the cause explains why the problem arose, and the recommendation changes a decision before the next order. Someone planning a hardware purchase can find the lesson and act on it without asking the original team to reconstruct the story.
Make the change happen
A recorded recommendation is a lesson identified. It becomes a lesson learned when behavior or a process actually changes. Give the improvement an owner. Update a procurement checklist, planning template or estimating record, and review relevant lessons when starting the next project.
For the supplier lesson, a new order form could require written stock confirmation and a scheduled delivery activity. The owner checks that future orders use those fields. This turns the lesson into a working control, with evidence that it is being used.
A long folder of unsearched reports does not achieve that transfer. Store lessons where new teams look during initiation and planning, with clear titles and context. Hold the closure review while the team is still available and complete the improvement handover before everyone disperses.
Key Takeaways
- Capture lessons throughout delivery and include successes.
- Use evidence and keep the discussion focused on processes and conditions.
- Write the situation, event, effect, cause and recommendation.
- Give improvements owners and put them into working processes.
Project Monitoring and Control examples
1From progress evidence to an honest report
12 steps
- 1IntroductionA number needs a reference
A team says its design work is “nearly done.” Before reporting that to a sponsor, you need evidence, the planned completion level and the likely effect on the next milestone. The planned level comes from the approved baseline; a tolerance tells you when a gap needs a higher decision.
Follow a progress check through to a useful status line, then see how boards and burn charts answer similar questions in an adaptive team.
- 2ExplanationHold the approved plan steady
A baseline is the approved reference for scope, dates or cost. Actual performance is compared with it so the difference remains visible.
The forecast can show what the team now expects. It can move without silently rewriting the commitment. A baseline changes only through approved change control; otherwise a late task could appear on time simply because its target was moved.
- 3ExampleWork out the progress gap
A task is planned evenly over ten days. At the end of day six, the plan calls for 60% complete, but checked work shows 40%.
The gap is 20 percentage points, equal to two planned days of work. Investigation finds a tester is absent. Borrowing a tester is a possible corrective response. The spending total alone would not have revealed how much usable work was complete.
- 4ChallengeDoes this need a higher decision?
The project manager can handle an end-date delay of up to two days. A new forecast shows four days late. Should the manager wait for the date to be missed?
---reveal---
No. The forecast already exceeds tolerance, so escalate with the impact, options and recommendation. Management by exception uses a threatened limit to trigger the higher decision while action may still protect the outcome.
- 5ConnectionBuild a status line from the gap
The sponsor needs to know what decision would help, not just that design is late. A useful line has four parts: fact against plan, cause, action and request.
For the rollout: design is 75% complete against 100% planned at week eight; the expert was unavailable; a second designer is proposed; approval of $3,000 is needed by Friday. Each part answers a different practical question.
- 6ExplanationMake the color mean something
Traffic-light rules must be agreed before use. Green means within thresholds; yellow or amber signals risk or recoverable drift; red signals a tolerance breach or a higher decision.
Also agree how the overall color is chosen. A worst-area rule would make a red schedule determine the overall red. Counting green areas against it would apply a different rule and could hide the exception.
- 7ChallengeChoose an honest status
A report uses red for a milestone forecast at least one week late. The latest forecast is eight days late, but the team hopes to recover. What should the report show?
---reveal---
Red, with the evidence and recovery action. Hope does not change the forecast or the agreed boundary. Keeping the rating green would conceal a known problem and delay the sponsor’s opportunity to help.
- 8ExplanationRead the queue before starting more
Cards move across a board from To do through active stages to Done. A buildup in Testing shows where work is waiting. Work-in-progress limits cap simultaneous cards so the team can focus on finishing.
Use the daily stand-up to expose blockers. An iteration review gathers feedback on the product, while a retrospective examines how the team works. A queue problem is useful evidence for both daily coordination and process improvement.
- 9ExampleLocate the burndown position
A ten-day iteration starts with 60 points. Its ideal remaining-work line falls by six points per day. At day five it should show 30 remaining.
If 36 remain, the actual line is six points above the ideal. The team has more work left than planned at this point. Investigate blockers and scope changes before choosing a response; the chart shows the gap without proving its cause.
- 10Key InsightSeparate a moving target from delivery
A burnup has a completed-work line and a separate total-scope line. If scope grows from 200 to 220 points, the target steps up by 20. That change can be seen even if completion continues steadily.
Count only work meeting the definition of done. A story still needing tests is unfinished, so giving it partial completed-point credit would make the completion line overstate delivery.
- 11ChallengeConnect team pace to the sponsor’s date
A hybrid release has 72 points left. The same team has averaged 18 completed points per two-week iteration, and release is planned eight weeks away. What outlook should be reported?
---reveal---
About four more iterations, or eight weeks, at that pace. The current outlook matches the planned date. State the remaining scope and pace behind it, and review the forecast if either changes. Do not compare this team’s velocity with another team’s points.
- 12RecapCheck the evidence, then the decision
A useful report preserves the approved reference, shows actual achievement and explains the response to a gap. Tolerances determine when the decision must go higher.
Adaptive tools give a closer view of flow, completion and scope. Translate those measures into the milestone, cost and risk information the sponsor needs, with enough context to judge the delivery outlook.
2Build and read an earned value result
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionHas spending bought the planned work?
- 2ExplanationGive each measure its own job
- 3ExampleAdd the scheduled value
- 4ExampleValue the completed work
- 5ExampleBring in costs on the same basis
- 6ChallengeUse the agreed earning rule
- 7ExplanationChoose subtraction or division
- 8ExampleCalculate the two gaps
- 9ExampleCalculate the two ratios
- 10TipUse the right percentage denominator
- 11ChallengeDoes low spending prove good cost control?
- 12ExampleApply the reporting thresholds
- 13Key InsightA favorable cost result does not explain delay
- 14ChallengeCan an index erase a late finish?
- 15ConnectionCheck what the index cannot see
- 16ChallengeCombine the signals before acting
- 17RecapKeep value, cost and dates distinct
3From a confirmed issue to a controlled change
16 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionA late delivery starts several decisions
- 2ExplanationRecognize an issue now
- 3ExampleGive the record a working purpose
- 4ChallengeSet priority from the effect
- 5ExampleUse the available float
- 6ExampleCompare responses before choosing
- 7ChallengeKnow when authority ends
- 8ExplanationAnalyze all effects of a new request
- 9ExampleTrace approval into the plan
- 10ChallengeChoose the proper funding decision
- 11Key InsightSpot informal additions early
- 12ExplanationKnow exactly which copy is approved
- 13ChallengeRelease the right document
- 14ConnectionKeep adaptive changes deliberate
- 15ChallengeLink a problem, request and version
- 16RecapKeep the decision trail clear
4Check a release against every acceptance rule
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionWhat would make this ready?
- 2ExplanationQuality starts with requirements
- 3ExampleCheck the process or the product
- 4ExplanationCount failures as quality cost too
- 5ChallengeClassify the work by purpose
- 6ExampleApply the percentage condition
- 7Key InsightTwo conditions need two checks
- 8ExampleRepair and check for side effects
- 9ChallengeWho may accept a defect as it is?
- 10ConnectionTake verified work to acceptance
- 11ChallengeConnect process, evidence and acceptance
- 12RecapMake readiness traceable
5Close the work and transfer responsibility
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionFinish the responsibilities as well as the work
- 2ExplanationCheck the planned closure conditions
- 3ExampleGet a specific acceptance record
- 4ChallengeDoes sign-off close the supplier file?
- 5ExplanationMake the receiving team ready
- 6TipPut an end point on extra support
- 7ExampleReport the final result against the approved plan
- 8ChallengeWho measures a benefit after closure?
- 9ExplanationCapture evidence before people disperse
- 10ExampleWrite a lesson with a usable action
- 11ChallengeHas the lesson been learned yet?
- 12ChallengeClose with open actions under control
- 13RecapLeave a usable result and a clear record
Project Monitoring and Control practice questions
Set 1: Read the evidence and report status10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Calculate and interpret earned value10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Resolve issues and authorize changes10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Check quality and finish the project10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Choose the next control action10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 6: Judge a project’s full position10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Acceptance criteria
Actual cost
Administrative closure
Appraisal cost
B
Baseline
Benefits review
Budget at completion
Burndown chart
Burnup chart
C
Change control board
Change log
Change request
Closure criteria
Concession
Conditional acceptance
Configuration item
Configuration management
Contingency reserve
Contract closure
Controlling
Corrective action
Cost of conformance
Cost of nonconformance
Cost performance index
Cost variance
Cost variance percentage
Critical path
D
Defect
Defect log
Definition of done
E
Early life support
Earned value
Earned value chart
Earned value management
Escalation
F
Final project report
Forecast
Formal acceptance
G
Gold plating
Grade
H
Handover
I
Integrated change control
Issue
Issue log
Issue owner
Issue resolution
Iteration
L
Lesson identified
Lesson learned
Lessons learned register
Lessons learned repository
M
Management by exception
Management reserve
Monitoring
O
Off-specification
Operational acceptance
P
Performance threshold
Performance trend
Planned value
Post-project review
Preventive action
Product backlog
Progress report
Punch list
Q
Quality
Quality assurance
Quality control
Quality metric
R
Regression testing
Retrospective
Risk
Root cause
S
Schedule performance index
Schedule variance
Schedule variance percentage
Scope creep
Status accounting
Status date
Status report
T
Task board
Tolerance
Total float
Traffic-light rating
V
Validation
Variance
Velocity
Verification
W
Watermelon reporting
Weighted milestones
Work performance information
Work-in-progress limit
Workaround
About this lesson