Project Stakeholders and Communication
Stakeholders, Communication, and the Project Team
BeginnerLesson 8 of 9 in Project Management Foundations Course
What you will learn
- Find everyone who can affect or is affected by a project, record what matters about them, and judge how much attention each one needs.
- Identify stakeholders and keep a stakeholder registerDefine who counts as a stakeholder, find stakeholders systematically from the start of the project, and record them in a stakeholder register that stays current.
- Map stakeholders on a power–interest gridRate each stakeholder's power and interest, place them in the four quadrants of the grid, and choose the level of attention each quadrant calls for.
- Assess stakeholder attitudes and engagement levelsDescribe how engaged each stakeholder is now, decide the level the project needs, and use the gap to set priorities.
- Identify stakeholders and keep a stakeholder register
- Turn the stakeholder analysis into concrete engagement actions and a communication plan that gets the right information to the right people at the right time, in a form they can use.
- Plan engagement actions for each stakeholderWrite a stakeholder engagement plan that sets out how the project will close the gap between each key stakeholder's current and desired engagement and keep expectations realistic.
- Choose how to communicate: the communication model, methods and channelsExplain how a message travels from sender to receiver, compare communication methods and media, and calculate how team size changes the number of communication channels.
- Build a communication planAnalyze stakeholders' information needs and set out who receives what information, why, when, how and from whom, including feedback and escalation routes.
- Plan engagement actions for each stakeholder
- Report the project's status honestly and clearly, make progress visible with simple visual tools, and run the meetings and logs that keep information, actions and decisions on track.
- Write a clear status reportProduce a status report that shows where the project stands against the plan, what comes next, and which decisions or help are needed from the reader.
- Make progress visible with dashboards and agile reportingUse dashboards, information radiators, burndown and burnup charts and iteration reviews to show status at a glance, and read them correctly.
- Run status meetings and keep action, issue and decision logsPlan and run focused project meetings, record what was agreed, and use logs and feedback to check whether stakeholders stay engaged.
- Write a clear status report
- Agree how the team will work together through a team charter and ground rules, make roles clear, and support the team as it moves through its stages of development.
- Write a team charterCreate a team charter together with the team that records its purpose, values, working agreements and decision rules, and tell it apart from the project charter.
- Set ground rules and clarify roles and responsibilitiesAgree specific ground rules for team behavior and apply them consistently, and use a responsibility assignment matrix so everyone knows who does, approves, advises on and is told about each piece of work.
- Recognize the stages of team developmentDescribe the forming, storming, norming, performing and adjourning stages, recognize each from the team's behavior, and explain why teams can move back to an earlier stage.
- Support the team through each stageAdjust the project manager's actions to the team's stage of development, use recognition, training and team-role models to raise performance, and handle the particular challenges of temporary and dispersed project teams.
- Write a team charter
- Recognize where project conflict comes from, tell useful disagreement from harmful conflict, and choose a resolution approach that fits the situation.
- Understand the sources and effects of project conflictIdentify the typical sources of conflict in projects, distinguish task conflict from relationship conflict, spot conflict early, and prevent avoidable conflict.
- Choose and apply a conflict-resolution approachCompare the five common approaches to conflict, choose one that fits the situation, and work through a conflict step by step.
- Understand the sources and effects of project conflict
Project Stakeholders and Communication study guide
1Find stakeholders and understand their needs
A project depends on people who fund it, approve its work, supply resources, and use its results. Some are easy to see; others become visible only when a decision affects them. Start with a broad search, then assess each person’s power, interest, and engagement. These are different questions: who matters, how they can affect the work, and what support the project needs from them. Together, the answers help you decide where to spend your time.
1.1 Who belongs in the stakeholder register
A stakeholder is a person, group, or organization that can affect the project, is affected by it, or believes it will be affected. A belief matters because it can change behavior. Staff who fear that new software will remove jobs need to be heard even when no job cuts are planned.
Search beyond the project team
Internal stakeholders work within the organization: the sponsor, project manager, team, functional managers who lend staff, user departments, and steering committee. External stakeholders include customers, suppliers, contractors, regulators, communities, and the media. One person can hold several roles. A department head may both sponsor a project and use its results.
Begin during initiation with the project charter and business case. Read contracts and organization charts, ask the sponsor and team, and check lessons from similar projects. Trace the result from design and delivery through everyday use and ongoing support. At each point ask who will use, pay for, approve, supply, support, or be disrupted by it. Ask each person you interview, “Who else should we speak to?” This often reveals people outside your usual contacts.
Missed stakeholders can bring late requirements or block acceptance. For example, overlooking a fire inspector during a building project can lead to changes after rooms are finished. Early identification gives the team time to include approval needs in its work.
Record information you can act on
The stakeholder register records who the stakeholders are and what the project needs to know about them. The project manager owns and updates it. Useful fields include name and role, organization, contact details, expectations, requirements, power, interest, current attitude, relevant phases, and communication preferences. Later analysis can add a grid classification.
Consider an online retailer replacing the software used by 40 customer-support agents:
| Stakeholder | What matters to them | What to record or check |
|---|---|---|
| Head of Customer Support | Faster responses to customers | Sponsor influence and success expectations |
| Support agents | Workload and learning the system | Daily-use needs and training concerns |
| IT security manager | Safe handling of customer data | Approval role and review dates |
| Software vendor | Delivering the contracted system | Configuration responsibilities and contacts |
| Customers | Response speed and service quality | Feedback from satisfaction surveys |
Customers can be represented through survey data; you do not need to interview each one. A large group needs separate entries when its members have different interests. Agents and team leads, for example, may face different changes to their work.
Keep the register useful and current
Review the register at each phase start, when people join or leave, and when scope or circumstances change. An approval contact may change even when the project itself stays the same. Replace vague judgments such as “difficult person” with factual observations about requirements or behavior. Keep sensitive assessments available only to people who need them; the full analysis does not belong on a general project noticeboard.
Key Takeaways
- A stakeholder can affect the project, be affected by it, or believe they will be affected.
- Search across the full life of the result, including approval, daily use, and support.
- The project manager maintains a register of roles, needs, influence, and communication preferences.
- Split groups when their interests differ and keep sensitive assessments restricted.
1.2 The power–interest grid
A stakeholder’s job title alone cannot tell you how to engage them. Power is their ability to influence the project’s decisions or outcome. Interest is how much they care about the project or are affected by it. Judge both in relation to this project.
Power can come from budget authority, control of staff, expert knowledge, or a required approval. People without senior titles can also influence adoption. A chief executive may have high authority but little interest in a small project; a user group may have little individual authority but care deeply about the result.
Match attention to the quadrant
The power–interest grid combines the two ratings into four starting strategies.
| Power | Interest | Strategy | What it means in practice |
|---|---|---|---|
| High | High | Manage closely | Involve in decisions and consult often |
| High | Low | Keep satisfied | Give focused updates and consult on specific concerns |
| Low | High | Keep informed | Share regular information and listen to concerns |
| Low | Low | Monitor | Provide general information and watch for change |
“Keep satisfied” and “keep informed” are easy to confuse. The first protects the support of a powerful person who wants limited detail. The second gives interested people enough information and a voice even when they have little formal authority. Every quadrant still calls for respectful, honest communication.
Build and use the grid
- Take the stakeholders from the register.
- Agree a rating scale and define what counts as high or low.
- Rate power and interest with the sponsor or team to reduce personal bias.
- Place each stakeholder in a quadrant and choose an initial strategy.
- Record the result, tailor the actions, and set review points.
For the support-software project, use scores of 1–5 and count 4 or 5 as high. The Head of Customer Support scores 5 for both: manage closely. The Head of Finance scores power 5 and interest 2: keep satisfied. Support agents score power 2 and interest 5: keep informed. The facilities team scores 1 and 2: monitor. The vendor’s account manager, at 3 and 4, also falls in keep informed under this scale.
These ratings guide different actions. Finance may need a one-page monthly cost update. Agents may need demonstrations, a newsletter every two weeks, and an FAQ. A quadrant selects an initial level of attention; the person’s particular concern determines the useful detail.
Reassess as the project changes
The security manager’s interest may rise sharply as approval approaches. Agents may gain power by organizing through representatives or refusing to adopt the tool. Review the grid at phase changes and after major events. Low formal power never makes user adoption unimportant.
Other mapping tools emphasize different attributes. A power–influence grid considers active involvement in shaping the project; an influence–impact grid considers the ability to change the plan or its execution. The salience model combines power, legitimacy, and urgency. Stakeholders with all three usually need particular attention. These tools help direct engagement effort, and their candid assessments need limited distribution.
Key Takeaways
- Assess power and interest for the particular project, using evidence and a shared scale.
- High power and high interest call for close management.
- Keep high-power, low-interest stakeholders satisfied; keep low-power, high-interest stakeholders informed.
- Monitor low-power, low-interest stakeholders for changes.
- Review positions as approval needs, circumstances, or collective influence change.
1.3 Current and desired engagement
The grid shows how much attention a stakeholder needs, but it does not show whether they support the project. A powerful, highly interested stakeholder might be a strong supporter or a determined opponent. Assess attitude and engagement alongside power and interest.
Describe the current position
A common engagement scale has five categories:
| Level | Meaning |
|---|---|
| Unaware | Does not know about the project or its effects |
| Resistant | Knows about the change and opposes it |
| Neutral | Knows about it and neither supports nor opposes it |
| Supportive | Supports the change |
| Leading | Actively works to make the project succeed |
Use conversations, interviews, short surveys, meeting behavior, and team observations as evidence. Record what you saw or heard, such as “asked for training to move outside peak season.” Silence alone does not show support. Ask a quiet stakeholder how the change will affect their work before assigning a level.
Mark the gap the project needs to close
A stakeholder engagement assessment matrix puts stakeholders in rows and the five levels in columns. Mark C for current engagement and D for desired engagement. The desired level reflects the contribution needed from that stakeholder. Making everyone Leading would create work without a clear purpose.
In the support-software project, the Head of Customer Support is currently Supportive but needs to be Leading: agents need visible backing from their own director. Finance is Neutral and needs to be Supportive for the next year’s subscription approval. Agents are Resistant and need to become Supportive because successful use depends on them. Security is Unaware and needs to be Supportive before approving the design.
The categories are not equally spaced numerical steps. A move from Unaware to Supportive cannot be treated as a precise quantity of effort. Look at what the change requires: a briefing may resolve lack of awareness, while resistance caused by workload may need a change to the training plan.
Set priorities from impact and timing
The security manager is a priority because they have high power, have not been briefed, and control an approval needed before go-live. Agents also need early attention because adoption determines whether the expected service benefits appear. A large apparent gap for a remote, low-interest stakeholder may be less urgent than a smaller gap around an imminent decision.
Resistance gives you information. Someone may fear job loss, remember a failed earlier project, or see a real flaw in the design. Listen for the reason before choosing an action. Repeated objections to training dates may reveal a staffing problem that affects delivery, not simply dislike of change.
Repeat the assessment during the project. Record new evidence, compare C with D, and use movement or lack of movement to review engagement actions. If someone attends a demonstration but still refuses to use the result, attendance alone is not enough evidence to mark them Supportive.
Key Takeaways
- Attitude is separate from power and interest.
- The five levels are Unaware, Resistant, Neutral, Supportive, and Leading.
- Mark current and desired engagement with C and D; set D to the level the project needs.
- Prioritize gaps using power, timing, and consequences, not arithmetic on category positions.
- Listen for the reason behind resistance and reassess using evidence.
2Plan engagement and communication
Stakeholder analysis becomes useful when it changes what people do together. Engagement actions address the reasons for missing support, while communication makes sure people receive and understand information they can use. A plan connects these needs to named owners, suitable methods, and clear timing. The same project facts reach different audiences at different levels of detail, with feedback and escalation routes to keep decisions moving.
2.1 Actions that build useful involvement
A stakeholder engagement plan sets out how stakeholders will be involved in the project’s decisions and work. It belongs within the project management plan. For each key person or group, it identifies the engagement needed, the actions to build it, an owner, and timing.
Communication shares information. Engagement involves people through consultation, decisions, collaboration, and agreement. An email announcing training shares information; inviting users to test the software and shape the training plan involves them. The communication plan helps carry out engagement actions, but a list of messages alone cannot do the whole job.
Turn an assessment into an action
Start with the register, power–interest grid, and C/D assessment. For each priority gap:
- Identify the reason for the current attitude or level.
- Choose an action that addresses that reason.
- Name the person who will carry it out.
- Set a date or trigger.
- Define evidence that will show whether it worked.
The best owner may be a team lead or trusted colleague with a strong relationship. Assigning every action to the project manager can ignore those relationships and create a bottleneck.
Work through the support-software example
The 40 agents resist training during the November–December peak. Their desired level is Supportive. Sending more promotional emails leaves the workload concern untouched. The support team lead instead moves training outside the peak, invites four agents into a pilot, and publishes answers to workload and job-security questions. Pilot agents report back to colleagues.
The plan names the team lead as owner and schedules the pilot before wider training. Signs of success include pilot agents recommending the tool and at least 90% of agents attending training. Attendance is one useful measure; conversations and later use help establish whether support has actually improved.
Security needs a different action. The manager is Unaware, and approval is required before go-live. The project manager arranges a week-2 briefing, shares the data-flow design, and agrees review dates. Written approval criteria agreed by week 4 provide evidence that security is involved early enough to influence the design.
Make expectations explicit
Managing expectations means confirming what the project will deliver, what it will not deliver, and when. A manager may assume a reporting module is included even though the charter excludes it. Discuss the gap early, refer to the scope and constraints, and confirm the understanding in writing. Warn people promptly when a change affects an earlier expectation.
Engagement continues in adaptive projects. A product owner represents customer and business needs. An iteration review, also called a sprint review or demo, lets stakeholders inspect working results and give feedback at the end of a short cycle. A lighter written plan can work alongside this frequent contact.
Review engagement actions when phases, stakeholders, or attitudes change. Share useful arrangements widely, but limit access to sensitive assessments. If an action produces no movement toward the desired level, ask whether it addressed the real concern before repeating it.
Key Takeaways
- Engagement involves people in decisions and work; communication shares information.
- Each engagement action needs a reason, owner, timing, and evidence of success.
- Choose actions that address the cause of resistance, including valid flaws in the plan.
- Confirm scope and timing expectations and review actions as the project changes.
2.2 Messages, methods, and communication channels
Communication works when the receiver understands the meaning the sender intended. Sending a message is only one part of that process. A delivered email can still leave its reader unsure what to do.
Check the meaning received
In the sender–receiver model, the sender encodes an idea into words, figures, or images and transmits it through a medium. The receiver decodes it. Noise can interfere anywhere: jargon, distractions, strong emotions, language differences, a weak connection, or too many competing messages. An acknowledgment confirms receipt; feedback shows understanding. “Received” is different from “We will finish the review by Thursday.”
Use active listening to check meaning: give full attention, paraphrase the concern, ask clarifying questions, and avoid interrupting. A written message should state its purpose first and identify the required action, owner, and deadline.
Choose a method for the job
| Method | How it works | Useful application |
|---|---|---|
| Interactive | Real-time exchange | Complex decisions, sensitive news, checking understanding |
| Push | Sent to named recipients | Reports, email confirmations, notices |
| Pull | Stored for people to access | FAQs, shared files, dashboards, reference material |
When go-live slips by two weeks, call the sponsor first so questions can be answered. Confirm the date and reason by email to create a record. Update the agents’ FAQ as a reference, then ask team leads to announce the update and check understanding. Posting information does not ensure that people look for it.
The method is different from the medium. A virtual tool can support an interactive video call, a pushed email, or a pulled wiki. Face-to-face discussion offers tone, body language, and immediate feedback, but needs shared space and separate notes. Physical documents provide a lasting record but are slower to update. Virtual media reach dispersed people quickly and can be searchable, but face connection problems, message overload, missing tone, and time-zone gaps.
Choose for urgency, complexity, sensitivity, audience size and location, stakeholder preferences, language, culture, and the need for a record. Important informal agreements need written confirmation. Communication may be upward to the sponsor, downward to the team, horizontal to peers, or external to customers and suppliers; formal written records suit approvals, contracts, and change decisions.
Calculate possible one-to-one channels
For a group of people, count every pair once:
Six people give person-to-person counts, but each pair appears twice. Dividing by 2 gives 15 channels. With nine people, channels: 21 more after adding only three people. Include the project manager in the head count. The formula counts possible pairs, not messages actually sent, and shows why growing teams need structure.
Tone and expression matter, but the claim that 93% of all communication is nonverbal misuses Mehrabian’s findings. Those experiments concerned judgments of feelings when words, tone, and facial expression conflicted. They do not assign those percentages to project reports or technical instructions.
Key Takeaways
- Feedback checks understanding; acknowledgment only confirms receipt.
- Interactive communication allows exchange, push sends information, and pull makes it available.
- Choose the medium for the message, audience, urgency, sensitivity, and record needed.
- Count possible one-to-one channels with n(n − 1)/2, including the project manager.
- Active listening checks meaning through attention, paraphrasing, and clarifying questions.
- The 7–38–55 findings do not describe communication in general.
2.3 A communication plan people can use
A communication plan, also called a communications management plan, describes how project information is created, shared, collected, and stored. It answers who needs what information, why, when, how, and from whom. It turns stakeholder needs into arrangements people can follow.
Find the requirements first
Ask each audience what it needs to decide, do, or understand. Establish detail, frequency, format, language, confidentiality, and access needs. Use the register, grid, engagement plan, organization charts, contracts, and reporting duties. Starting with a favorite tool can leave the real information need unresolved: a dashboard is useful only when it shows what its readers need.
The plan records the audience, information, purpose, method and medium, frequency or trigger, and sender. It also identifies approvals needed before confidential information is released, feedback arrangements, escalation routes and time limits, templates, a glossary, storage locations, constraints, and review arrangements. This prevents gaps in ownership as well as gaps in the recipient list.
Build the communication matrix
For the support-software project, the main rows could be:
| Audience | Information and purpose | Timing and medium | Owner |
|---|---|---|---|
| Sponsor | Status, decisions, early warning | Friday report and 30-minute call | Project manager |
| Finance | Budget and forecast | One-page monthly email | Project manager |
| Support agents | Changes, training, questions | Newsletter every two weeks, FAQ, demos | Support team lead |
| IT security manager | Design and approval evidence | Reviews at agreed milestones | Technical lead |
| Project team | Tasks, priorities, blockers | Daily 15-minute stand-up, weekly planning, chat | Project manager |
| Vendor | Delivery dependencies | Weekly call; contract changes in writing | Project manager |
A scheduled report provides routine visibility. A trigger handles events that cannot wait for that schedule, such as a critical approval delay. Build a way to ask questions into each important arrangement. For a confidential design review, record both the authorized audience and the person who approves release.
State how problems move upward
An escalation path names who handles a problem beyond the current level’s authority and how quickly to raise it. For example, a team member raises a blocker with the project manager within one working day. The project manager goes to the sponsor when the effect exceeds agreed cost or schedule limits. The sponsor takes decisions beyond their own authority to the steering committee. Clear routes prevent a problem from sitting between people who each expect someone else to act.
Tailor the detail while keeping the facts consistent. Senior managers need overall status, decisions, and top risks; the team needs task-level information. A short summary cannot call the project on track while the detailed plan shows a two-week delay. Review the communication plan at each phase start and when the register changes. Feedback about missed messages, overload, or inaccessible information tells you which arrangements need adjustment.
Key Takeaways
- Analyze information needs before selecting formats and tools.
- Record audience, content, purpose, timing, method, and sender.
- Include confidentiality, feedback, storage, escalation, and review arrangements.
- Tailor detail to the audience while keeping project facts consistent.
- Review the plan when phases or stakeholder needs change.
3Report progress and keep decisions moving
Useful reporting lets people see what has happened, where the project stands, and what help it needs next. A clear report connects evidence to a decision; a dashboard makes selected facts easy to scan. Meetings and logs then turn those facts into agreed action. Keep the reporting cycle linked to stakeholder needs, so that a sponsor can make timely decisions and the team can coordinate work without spending its week producing updates.
3.1 An honest, useful status report
A status report compares the project’s current position with its baseline for scope, schedule, cost, and quality. A progress report describes accomplishments during a period. A forecast predicts future results, such as the finish date or final cost. One regular report often combines all three, but each answers a different question.
Put decisions near the top
Begin with a header naming the project, reporting period, author, and date. Give the overall status and a short summary, then show accomplishments, next period’s work, milestones, costs, risks, issues, changes, and decisions needed. Compare planned milestone dates with forecasts, and show budget, spending so far, and expected final cost separately.
For each important problem, give its cause, impact, and action. “Three of five interfaces tested” provides evidence; “good progress” leaves the reader guessing. Report completed results against the plan, not just activities such as the number of meetings held. A task described as “90% done” for weeks needs better evidence from finished work and accepted milestones.
Apply agreed RAG thresholds
RAG stands for red, amber, green; many US organizations use yellow for amber. Agree thresholds in advance. Green usually means within agreed limits, amber signals deviation or risk that is recoverable with current plans or limited help, and red signals that sponsor help or a decision is needed because agreed limits are or will be exceeded. The precise thresholds belong to the organization or project.
For the support-software project, the budget is $120,000 and forecast final cost is $129,000. First find the overrun, then compare it with the budget:
The forecast is $9,000, or 7.5%, above budget. With green up to 5% over, amber above 5% through 10%, and red above 10%, cost is amber. Using the amount spent so far would answer a different question from the expected final overrun.
Training was planned for November 13 and is now forecast for November 20, five working days late in this schedule. With green on time, amber up to 10 working days late, and red beyond that, schedule is also amber.
Turn facts into a request
A useful opening could read: “Overall status: Amber. Migration finished on schedule, but training moved to November 20 because the vendor’s training environment was late. Forecast cost is $129,000 against a $120,000 budget. By October 30, approve an additional $9,000 through the budget change process or approve a revised training plan within budget.”
The summary gives a conclusion, cause, impact, and dated decision. It does not treat an existing contingency reserve inside the budget as extra money above that budget.
Use a consistent format and the frequency agreed in the communication plan. Keep the main report short, with supporting detail in attachments. A watermelon report looks green while serious problems remain hidden. Report problems early with recovery actions; change a rating back to green only when evidence supports it.
Key Takeaways
- Status compares the present with the baseline; progress describes accomplishments; a forecast predicts the future.
- Lead with the conclusion and decisions needed, backed by results and numbers.
- Use RAG thresholds agreed in advance and calculate variances against the correct baseline.
- Give each major problem a cause, impact, action, and owner.
- Report bad news early and change ratings only when evidence supports the change.
3.2 Dashboards, boards, and progress charts
A dashboard is a compact visual summary of selected project measures. It may show milestone dates, budget against forecast, RAG ratings, top risks, and open issues. It helps readers spot where attention is needed, but each indicator still needs reliable data and a short explanation.
An information radiator is a visible display people can read without asking for an update. A wall task board, shared online board, or blocker list can serve this purpose. A task board with To do, In progress, and Done columns shows the flow of work. These displays are pull communication: information is available when someone looks at it.
Read a burndown chart
A burndown chart shows remaining work on the vertical axis and time on the horizontal axis. The unit might be hours, tasks, or story points. An ideal line falls from the starting total to zero at the planned end. The actual line shows what remains according to the latest data. Above the ideal means more work remains than planned; below it means less remains.
A 10-day iteration starts with 60 hours of work. A straight ideal line assumes the same planned reduction each day:
The ideal reduction is 6 hours per day. At the end of day 4:
The ideal remaining work is 36 hours. Actual remaining work is 42 hours, so the difference is:
There are 6 more hours remaining than planned. The team investigates blockers and decides what can be completed or moved to a later iteration. The chart prompts that conversation; it does not identify the cause by itself.
A flat line can mean work is not being finished or the chart is not being updated. A rising line can mean work was added or underestimated. Ask about the work and data before choosing a response.
Separate completed work from changing scope
A burnup chart shows completed work rising toward a separate total-scope line. When scope increases, the total line rises. Keeping the two lines separate helps readers see both delivered work and a changing target. On a burndown, new work and slower completion can both increase the amount remaining, so the reason needs investigation.
An iteration review lets stakeholders see and try working results and provide feedback. It gives evidence beyond a claimed completion percentage. A daily stand-up, often 15 minutes, helps the team coordinate what comes next and remove blockers. It serves the team’s planning needs; it is not a round of individual status reports to the manager.
Choose measures that help decisions
Too many dashboard measures hide the important ones. Choose a small set that supports action, and check how each is calculated and updated. Spending half the budget does not establish that half the work is complete. Use evidence of delivered and accepted work when describing progress, and use cost information to describe spending and forecasts.
Key Takeaways
- A dashboard summarizes selected measures; check the evidence behind its indicators.
- An information radiator makes current work visible through pull communication.
- A burndown shows remaining work; above the ideal line means more remains than planned.
- A burnup separates completed work from the total-scope target.
- Iteration reviews show working results; stand-ups help the team coordinate.
- Money spent is not a measure of work completed.
3.3 Focused meetings and clear follow-up
A project meeting earns its time when it creates shared understanding, resolves a decision, or coordinates action. Give it a clear purpose and invite the people needed for that purpose. Send an agenda in advance, assign time to each item, and identify a facilitator and note-taker.
A kickoff meeting brings the team and key stakeholders together at project start or the start of the main execution phase. It establishes objectives, scope, plan, roles, communication arrangements, and ground rules. A later status meeting uses that shared understanding to compare current work with the plan.
Run a short status meeting
A 30-minute weekly agenda might allow 5 minutes for previous actions, 10 for milestone progress, 10 for new risks and issues, and 5 for decisions and new actions. Start and finish on time. Move detailed technical problem-solving into a separate discussion with the people involved, so the full group is not waiting through work it cannot contribute to.
Meeting time adds up across the whole team. Eight people in a weekly one-hour meeting use 8 person-hours per week. Over 20 weeks:
That is 160 person-hours. At 30 minutes per meeting, the same group uses 80 person-hours, saving 80. A shorter meeting is useful when the agenda still achieves its purpose.
Record agreements in the right place
Minutes summarize attendees, decisions, actions, and open questions. They are not a transcript. Send them promptly, for example within one working day. An action should name both an owner and a due date: “Agree customer-data access approval criteria. Owner: Priya Shah. Due: October 9.”
| Record | What belongs in it | Useful fields |
|---|---|---|
| Action log | Agreed tasks to carry out | Task, owner, due date, status |
| Issue log | Problems that already exist | Description, impact, priority, owner, target date, status |
| Decision log | Decisions already made | Decision, authority, date, reason |
An uncertain future event belongs in the risk register. If a training environment might arrive late, it is a risk. Once its delivery is late, the delay is an issue. The response can also create actions, such as arranging an alternative environment. Recording a decision’s reason helps a new member understand why the team chose it and reduces repeated debate.
Check whether people remain engaged
The reporting cycle also gives evidence about engagement. Compare current and desired levels using feedback, attendance, complaints, surveys, and adoption. If training attendance is 60% against a 90% target, investigate before assuming the agents are simply uncooperative. In the software project, moving sessions to quieter hours and asking team leads to promote them may address the barrier.
Update the register, grid, and plans when the evidence changes. Review previous actions at the next meeting. A list of unfinished actions with no owner or due date cannot tell the team who should act next.
Key Takeaways
- Give meetings a purpose, timed agenda, needed attendees, and recorded outcomes.
- Minutes record decisions and actions without reproducing every spoken word.
- Action logs track tasks; issue logs track current problems; decision logs preserve choices and reasons.
- A risk is uncertain; an issue already exists.
- Use engagement evidence to update assessments and plans.
4Agree how the team works and support its development
A project team needs agreements about decisions, responsibilities, and everyday behavior as well as a task plan. These agreements help people coordinate and settle misunderstandings. Team needs also change: a new group may need clear direction, while an experienced group can solve many problems itself. Recognizing those changes helps a project manager provide useful support, welcome new members, and bring temporary teams to a proper close.
4.1 The team charter and decision rules
A team charter records how team members agree to work together. It includes purpose, shared values, communication, meetings, decisions, conflict handling, and other working agreements. Agile teams often use the term working agreement for similar arrangements.
Separate the two charters
| Document | Main purpose | Who creates or issues it |
|---|---|---|
| Project charter | Authorizes the project and the project manager; sets objectives, high-level scope, and success criteria | Sponsor |
| Team charter | Records how members work and behave together | Team, with facilitation |
A team charter authorizes nothing. Its value is shared expectations. When a problem appears, members have an agreed reference point; new members can also learn the team’s practices quickly.
The project manager facilitates a session in which the team writes the charter together. Invite practical suggestions, agree what members can follow, and have everyone acknowledge the result. Agreements people helped create are easier to own than rules delivered without discussion. Keep the document short, usually one or two pages, and revisit it when membership changes or an agreement stops working.
Write observable agreements
“Communicate well” gives little guidance. “Reply to direct questions in team chat within four working hours” identifies a behavior others can observe. For the support-software team, the purpose might be “Deliver the new support system by March 1 so agents can resolve customer requests faster.” Other entries can specify the chat channel, written records, daily stand-up time, and when unresolved disagreements reach the project manager.
Virtual and hybrid teams need agreements about overlapping hours, tools, response times, and written decision records. “Four working hours” needs a shared understanding of each member’s working schedule; otherwise people in different time zones may expect replies while colleagues are asleep.
Agree how decisions are made
| Rule | What agreement means |
|---|---|
| Unanimity | Everyone agrees |
| Majority | More than half agree |
| Consensus | Everyone can accept and support the decision, even if it is not their first choice |
| Leader decides after consulting | The leader hears input and makes the decision |
Choose rules for particular kinds of decisions. Consensus does not require everyone to prefer the same option. A member can support a workable choice while believing another choice would have been better. Majority voting can produce a decision without that shared acceptance.
A practical charter entry could say, “Developers seek consensus on technical choices. If there is no agreement within two working days, the technical lead decides.” The time limit and fallback prevent an urgent choice from remaining open indefinitely. Explain the rule before the dispute, so the team is not trying to agree on a process while defending competing proposals.
Use the charter in everyday work and review it in retrospectives. When a rule repeatedly fails, discuss whether the rule, the conditions, or members’ behavior needs to change.
Key Takeaways
- The project charter authorizes the project; the team charter records working agreements.
- The team creates and acknowledges its charter with the project manager facilitating.
- Specific agreements guide behavior better than vague intentions.
- Consensus means everyone can support a decision; unanimity means everyone agrees.
- Decision rules can include a time limit and an agreed fallback.
4.2 Ground rules and responsibility assignment
Ground rules set expectations for acceptable team behavior. They usually sit in the team charter. Keep them few, specific, observable, and agreed by the people who will follow them. Every member, including the project manager, shares responsibility for maintaining them.
Useful examples include “Update the task board before stand-up,” “Criticize ideas, not people,” and “Tell the task owner as soon as you know a deadline is at risk.” Raise breaches early and first in private. Refer to the agreement: “We agreed to update the board before stand-up.” Apply rules consistently; repeated exceptions for one person weaken their credibility. A rule repeatedly broken by many members may need revision.
Make the work responsibilities clear
Unclear roles create duplicated tasks, missed work, and conflict. A role description states authority, the decisions the person can make; responsibility, the work expected of them; and competence, the knowledge and skills needed.
A responsibility assignment matrix links activities to people. The common RACI format distinguishes four relationships:
| Letter | Role | Meaning |
|---|---|---|
| R | Responsible | Does the work |
| A | Accountable | Owns the result and approves it |
| C | Consulted | Provides input through two-way communication |
| I | Informed | Receives updates through one-way communication |
Each activity has exactly one accountable person and at least one responsible person. The same person can hold A and R.
Check the software project’s rows
For “Define ticket categories,” the support team lead is R, the Head of Customer Support is A, pilot agents are C, and security is I. The agents help shape a system they will use, but the department head owns the result.
For “Approve customer-data access settings,” the IT security manager is both A and R, the technical lead is C, and the project manager is I. Combining A and R is valid because one person performs and owns that activity.
For “Run agent training,” the vendor trainer is R, the project manager is A, the support team lead is C, and the Head of Customer Support is I. The person delivering a session is different from the person accountable for the activity’s outcome.
Review the matrix with the named people
Check every row for a missing R or more than one A. Two accountable people leave ownership unclear; no responsible person leaves the work unassigned. Too many consulted people can also slow work, so identify whose input actually changes it.
Share and confirm the matrix with the people named. A chart they have never seen cannot establish shared expectations. Use its I entries to help build the communication plan, put agreed roles into the team charter, and review rows when responsibilities change.
Key Takeaways
- Ground rules are shared, observable agreements that apply to the project manager too.
- R does the work; A owns and approves its result; C gives input; I receives updates.
- Each activity needs exactly one A and at least one R.
- A person can hold both A and R for the same activity.
- Confirm the matrix with the people named and connect it to communication arrangements.
4.3 How a project team develops
People do not become an effective team simply because their names appear on the same plan. They need to learn their roles, work through differences, and build ways of coordinating. Tuckman’s model names common patterns in this development.
Bruce Tuckman described forming, storming, norming, and performing in 1965. Tuckman and Mary Ann Jensen added adjourning in 1977. The model helps project managers recognize team needs; it does not set a timetable that every team follows.
Recognize the five stages
| Stage | Typical behavior | What you may notice |
|---|---|---|
| Forming | Polite, uncertain, looking for direction | Questions about purpose, roles, and where to begin |
| Storming | Challenging ideas, priorities, roles, or leadership | Tension and repeated disagreement about the approach |
| Norming | Agreeing methods and building trust | Clearer roles, shared rules, helpful feedback |
| Performing | Working interdependently and solving problems | Members coordinate and adapt without constant direction |
| Adjourning | Completing work and leaving the temporary team | Closure, recognition, uncertainty about next assignments |
During forming, output is often low because people are still learning how the team works. During storming, productivity can dip as competing ideas become visible. Norming brings more reliable coordination, and performing brings high productivity and the ability to solve many problems within the team. Adjourning can bring a sense of loss as well as satisfaction.
Follow the evidence in a project
In week 1 of the software project, members keep asking who decides what: forming. In week 3, developers repeatedly argue about database design and challenge the project manager’s approach: storming. By week 6, the team agrees a code-review rule and settles disagreements through it: norming. In week 10, members reorganize tasks to absorb a vendor delay without waiting for instructions: performing.
The useful evidence is the behavior. A quiet team may be polite and uncertain, or it may be skilled and coordinated; quietness alone cannot distinguish forming from performing. Look at whether members understand their roles and handle dependencies themselves.
Expect changes and setbacks
Teams can move quickly through a stage, stay in storming, or return to earlier patterns. New members, a new leader, changed goals, or rising pressure can disturb established agreements. Two specialists joining a norming team may bring back questions about roles or arguments about methods. A short project may finish before the team reaches performing.
A good team can disagree. Storming can expose differences that need to be settled, while suppressing them can leave the same conflict waiting to return. Keep disagreements focused on work and help members build agreements they can use. Recognizing a stage helps explain what support is useful; it should not become a label used to dismiss a real problem.
Key Takeaways
- The five stages are forming, storming, norming, performing, and adjourning.
- Identify stages from team behavior, not from the week number or quietness alone.
- Handled well, storming brings differences into the open.
- Membership, leadership, goals, or pressure can move a team back to earlier patterns.
4.4 Support that fits the team’s needs
A project manager helps the team by matching support to what members currently need. Clear goals, suitable skills, resources, fair workloads, feedback, and working tools all affect performance. Personally following the ground rules makes the manager’s expectations credible.
Adjust support as the team develops
| Stage | Useful project-manager actions |
|---|---|
| Forming | Clarify objectives and roles; introduce people; hold a kickoff; agree the charter |
| Storming | Facilitate disagreements, clarify responsibilities, and use the charter |
| Norming | Encourage decisions, offer feedback, and reinforce working agreements |
| Performing | Delegate, remove obstacles, protect focus, and recognize results |
| Adjourning | Recognize contributions, capture lessons, and support next assignments |
A performing team does not need the manager to approve every small task. A forming team still needs enough direction to begin. Reassess when membership or conditions change; past independence does not mean a reorganized team needs no support.
Develop skills and recognize contributions
Training closes skill gaps needed for the work. Team building develops trust and working relationships through activities such as introductions and joint planning. Tying it to real work gives members practice in coordinating the tasks they actually face.
Recognition acknowledges a contribution; a reward is tangible, such as time off or a bonus. Make either specific, timely, fair, and connected to useful behavior. Thanking members for a successful cross-team handover encourages collaboration. A single prize that only one member can win may work against it. Ask about preferences: some people welcome public praise, while others prefer private thanks.
Notice the team’s mix of behaviors
Belbin’s nine team roles describe behavioral contributions:
- Plant: develops creative ideas.
- Resource Investigator: finds outside contacts and opportunities.
- Coordinator: clarifies goals and delegates.
- Shaper: drives progress through obstacles.
- Monitor Evaluator: weighs options logically.
- Teamworker: supports cooperation.
- Implementer: turns ideas into practical plans.
- Completer Finisher: checks details and deadlines.
- Specialist: contributes deep expertise.
People usually show several roles. These are behavioral preferences, not fixed personality types or a requirement for nine separate people. A team with many idea generators may need stronger checking and follow-through. Use the model to consider missing contributions, then connect that observation to the work.
Handle temporary and dispersed working
In a matrix organization, a member reports to both a functional manager and a project manager. Competing priorities can reduce availability. Agree commitments with functional managers, clarify priorities, and give useful feedback to line managers, especially when you do not control pay or appraisals.
Dispersed teams offer wider access to skills and less travel, but have time-zone gaps, less informal contact, and technology problems. Agree overlapping hours, use video for important conversations, record decisions, and rotate inconvenient meeting times fairly.
When a newcomer joins, explain the charter, roles, tools, and current status, then pair them with an experienced colleague. Expect a short productivity dip while members adjust. At the end, make time for lessons, thanks, and transition to new assignments.
Key Takeaways
- Match direction, facilitation, support, and delegation to the team’s current needs.
- Training builds needed skills; team building develops trust and working relationships.
- Recognition and rewards work best when specific, timely, fair, and suited to the person.
- Belbin roles describe contributions people can combine, not fixed personality types.
- Agree availability with functional managers when people serve two reporting lines.
- Dispersed teams need explicit communication agreements and fair meeting arrangements.
- Onboard new members and support closure when the team disbands.
5Understand conflict and choose a response
Project work brings together people with different priorities and limited time and resources. Disagreement can expose a weak plan or improve a decision, but personal attacks damage trust. Start by finding what the conflict is about and what each person needs. Then choose an approach that fits the importance, urgency, authority, and relationships involved, and follow the agreement through into the work.
5.1 What project conflict is really about
Conflict arises when people see their goals, interests, values, or needs as incompatible. Projects create many opportunities for this: teams are temporary, deadlines are tight, resources are shared, and people face change. Managing conflict is part of coordinating the work.
Look for the source
A classic project-management study by Thamhain and Wilemon identified seven sources: schedules, project priorities, staffing and resources, technical opinions and trade-offs, administrative procedures, cost, and personality. Across the life cycle, schedules, priorities, and staffing were the three most intense sources in that study. The ranking changed between phases, with priorities leading early in a project.
Use these categories to investigate a dispute. A heated argument between two leads may concern the same specialist’s availability. Calling it a personality clash without checking the work leaves the resource problem in place. Personal friction can also hide behind a technical debate, so ask about both the practical facts and the relationship.
Distinguish task and relationship conflict
| Type | Focus | Likely effect |
|---|---|---|
| Task conflict | Ideas, methods, priorities, or decisions | Can improve decisions when handled respectfully |
| Relationship conflict | Personal friction and attacks | Tends to damage trust and performance |
Two engineers can disagree about a design and still respect each other. Asking for evidence can expose a risk before the team commits to a choice. Calling a colleague careless turns attention toward the person and can make the same debate harmful. Task conflict can become relationship conflict when people feel attacked.
The aim is useful, early resolution, not silence. A team that never questions a proposal may be avoiding concerns. Make room for people to challenge assumptions while keeping discussion specific to the work.
Recognize early warning signs
Watch for the same dispute returning each week, avoidance, unexplained silence, sarcasm, growing email copy lists, missed handovers, and repeated complaints about one colleague. Investigate before the pattern becomes entrenched. A missed handover might be a single oversight, but repeated missed handovers between the same people deserve a conversation.
In the software project, two leads need the only database specialist in the same week. One needs migration scripts before a Thursday test window; the other needs performance tuning before go-live. The visible argument concerns a person’s allocation. The practical causes include resources, priorities, and schedule. Understanding those causes gives the team something it can change.
Prevent avoidable disputes
Clear roles and a RACI chart reduce uncertainty about who owns decisions and work. Agreed priorities and realistic schedules reduce incompatible demands. Ground rules and a conflict process in the team charter give people a way to raise concerns. Open communication lets someone say that two promised tasks cannot both be completed with the available time before the problem becomes personal.
Key Takeaways
- Conflict can come from schedules, priorities, resources, technical choices, procedures, cost, or personality.
- Investigate the work and the relationship before deciding the cause.
- Respectful task disagreement can improve decisions; personal friction tends to damage performance.
- Recurring disputes, avoidance, sarcasm, and missed handovers can signal conflict.
- Clear responsibilities, priorities, schedules, and working agreements prevent avoidable conflict.
5.2 Choose a conflict approach and follow through
A conflict response should fit the situation. The Thomas–Kilmann model uses assertiveness, pursuing your own concerns, and cooperativeness, meeting the other person’s concerns. These dimensions describe five common approaches.
Compare the approaches
| Approach | What happens | When it fits |
|---|---|---|
| Collaborate / problem solve | Seek a solution meeting both sides’ real interests | Important issue, time to explore, trust, lasting commitment needed |
| Compromise / reconcile | Each side gives up something | Moderate stakes, similar power, or a quick temporary settlement |
| Force / direct | Impose a decision through authority | Emergency or an urgent safety, legal, or ethical decision |
| Smooth / accommodate | Give way and emphasize agreement | The issue matters more to the other side or you realize you were wrong |
| Withdraw / avoid | Step back or postpone | Trivial issue, cooling-off time, missing information, or another person better placed |
Collaboration is high in both dimensions. Forcing is high in assertiveness and low in cooperativeness; accommodating is the reverse. Avoiding is low in both, while compromise sits between the extremes. No approach is best in every situation. Collaboration can build a lasting solution but takes time; repeated forcing can damage commitment, and repeated avoidance can let problems grow.
Find interests behind positions
A position is the demand someone states. An interest is the need behind it. “I need the specialist all next week” is a position. “The scripts must be ready before Thursday’s test window” identifies a reason and a timing constraint.
In the support-software dispute, migration scripts need two days before Thursday, while tuning needs three days before go-live after that week. Splitting the week equally might leave neither task complete. The leads instead allocate Monday and Tuesday to scripts and Wednesday through Friday to tuning. The tuning tester prepares data during the first two days. Both underlying needs are met. That is collaboration, not a compromise in which each loses part of the time required.
Work through the conversation
- Address the conflict early, privately, and at a suitable time.
- Let each side explain; listen and keep people separate from the problem.
- Identify interests behind stated positions.
- Agree the facts and a shared goal.
- Generate options together.
- Choose an option and confirm agreement.
- Record the agreement and follow up.
Smoothing can lower tension while leaving the cause unresolved. A pause can help people cool down, but agree when the conversation resumes. In an emergency, use appropriate authority to protect people or meet a mandatory requirement without waiting for lengthy negotiation.
If the decision exceeds the project manager’s authority, follow the escalation route. Two functional managers competing for a shared specialist may need a sponsor or resource owner to decide. Escalation brings the issue to the person with authority; it should include the facts, effects, and decision needed.
Key Takeaways
- Choose a response for the issue’s stakes, urgency, relationships, and available authority.
- Collaboration seeks to meet both interests; compromise leaves each side partly satisfied.
- A position states a demand; an interest explains the need behind it.
- Listen, agree facts, generate options, record an agreement, and follow up.
- Use escalation when the needed priority or resource decision exceeds your authority.
- Avoidance and smoothing can leave the underlying problem unresolved.
Project Stakeholders and Communication examples
1From stakeholder search to engagement priorities
11 steps
- 1IntroductionThree questions about the people involved
An online retailer is replacing the software used by 40 support agents. Delivering the tool is only part of success: people must approve it, learn it, and use it. Those people are its stakeholders, and missing one can sink adoption.
Work through three questions: Who can affect or experience the change? How much power and interest do they have? What engagement does the project need from them? Each answer adds something to the next decision.
- 2ExplanationLook beyond the kickoff list
A stakeholder can affect the project, be affected by it, or believe it will affect them. Begin with the charter, contracts, organization chart, and interviews.
Trace who will use, fund, approve, supply, support, or be disrupted by the system. The agents are visible users, but customers experience response times and security holds an approval. Ask each contact who else needs to be involved.
- 3ExampleCreate a useful register entry
Record the support agents as daily users who worry about learning the system during the busy season. Include their expectations, contact route, interest, current attitude, and training preferences.
Record security separately: its main concern is customer-data handling, and it must approve before go-live. The project manager keeps the register current and limits access to sensitive assessments.
- 4ChallengeFind a missing group
A depot is changing its booking system. Managers and the vendor are listed. Night-shift staff believe the change will remove their jobs, although no cuts are planned. Do they belong in the register, and why?
---reveal---
Yes. People who believe the project will affect them are stakeholders. Record the concern factually and speak with them; the absence of planned cuts does not remove their need for engagement.
- 5ExplanationRate power and interest separately
Power means the ability to influence this project’s decisions or outcome. It may come from an approval, resource control, expertise, or collective action. Interest means how much someone cares or is affected.
Agree a scale with the team or sponsor. On a 1–5 scale with 4–5 high, the software project’s Finance head scores power 5 and interest 2. That combination calls for keep satisfied.
- 6ExampleChoose the quadrant’s starting strategy
The Head of Customer Support scores 5 for power and 5 for interest: manage closely, including regular consultation on decisions. Agents score 2 and 5: keep informed, with useful updates and listening.
Facilities scores 1 and 2: monitor. Finance needs concise information about cost. Agents need fuller information about workflows and training. A quadrant guides attention; it does not measure a person’s worth.
- 7ChallengeRespond to a change in influence
Users had little individual power and high interest. They now act through a representative who can block adoption, while their interest stays high. How should the engagement strategy change?
---reveal---
Reassess their power as high and manage closely. Keep regular information flowing, but add close consultation on decisions affecting adoption. Keeping the old rating would overlook their new ability to affect the outcome.
- 8ExplanationAdd the engagement assessment
Power and interest do not reveal support. Use Unaware, Resistant, Neutral, Supportive, Leading to describe engagement. Mark C for current and D for desired in an assessment matrix.
Set D to the contribution the project needs. Leading means active work to make the project succeed; Supportive means backing the change. A low-interest observer may need no more than Neutral.
- 9ExampleChoose evidence and a priority
Security is C = Unaware and D = Supportive: nobody has briefed the manager, yet approval is required before go-live. Agents are C = Resistant and D = Supportive because they fear peak-season training.
Security comes first because power and timing make the gap urgent. The levels are categories, so counting columns cannot tell you the effort needed. Ask agents about workload to understand their resistance.
- 10ChallengeCombine attention and engagement
A finance director can block funding next week but has not heard about a change. A small user group supports it and wants optional updates. What engagement gap should receive attention first, and what evidence should be sought?
---reveal---
Brief the finance director first and check the support needed for the funding decision. Their power, lack of awareness, and near deadline create the priority. Use a conversation to assess understanding and attitude, then update the register and C/D assessment.
- 11RecapKeep the analysis alive
Search broadly and keep the register current. Assess power and interest for the project, then assess engagement using evidence of awareness and support.
Use the grid to choose an initial level of attention and the C/D gap to identify missing involvement. Review both when phases, people, or circumstances change; the next step is to turn the priority gaps into owned actions.
2Turn stakeholder needs into a communication plan
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionStart with a need, then choose an action
- 2ExplanationSeparate information from involvement
- 3ExampleAddress the workload concern
- 4ChallengeChoose an action that addresses the cause
- 5ExplanationCheck the meaning received
- 6ExampleUse three methods for a delayed date
- 7ExampleCount the possible channels
- 8ChallengeApply the formula to a new team
- 9TipSelect media for the message
- 10ExampleBuild a row from an information need
- 11ExplanationGive blockers a route to authority
- 12ChallengePlan communication for an approval
- 13RecapConnect actions, understanding, and ownership
3Turn reporting evidence into decisions
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionReport so someone can act
- 2ExplanationSeparate three kinds of information
- 3ExampleCalculate the cost deviation
- 4ExampleApply the agreed threshold
- 5ExampleWrite the request with the impact
- 6ChallengeUse a new report’s numbers
- 7Key InsightRead the display behind the color
- 8ExampleFind the ideal remaining work
- 9ExampleCompare actual with ideal
- 10ChallengeInterpret two rising burnup lines
- 11TipKeep the meeting focused
- 12ExplanationPut each item in its log
- 13ChallengeTurn a meeting outcome into follow-up
- 14ConnectionUse the cycle to check engagement
- 15RecapEvidence, decisions, and follow-through
4Build working agreements and support the team
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionGive the team a way to work together
- 2ExplanationWrite the team’s charter together
- 3ExampleChoose a usable decision rule
- 4ChallengeApply the agreed rule
- 5TipMake ground rules observable
- 6ExplanationSeparate doing from owning
- 7ChallengeRepair an unclear responsibility row
- 8ExplanationRecognize forming and storming
- 9ExplanationLook for coordination and closure
- 10ChallengeRecognize a return to earlier patterns
- 11ExampleMatch support to the current stage
- 12ChallengeChoose help for a performing team
- 13ExplanationRecognize the contribution you need
- 14TipSupport skills and collaboration
- 15ConnectionCoordinate across managers and locations
- 16ChallengeRespond to two linked team problems
- 17RecapUse agreements and behavior together
5Resolve a shared-resource conflict
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionStart with the needs behind the argument
- 2ExplanationIdentify the source before labeling people
- 3Key InsightKeep useful disagreement focused on work
- 4ChallengeDiagnose the immediate cause
- 5ExplanationCompare five responses
- 6ExampleFind the interests behind the positions
- 7ExampleTest a workable schedule
- 8ChallengeApply the reasoning to a new dispute
- 9TipKnow when another response fits
- 10ExplanationRecord the agreement and follow up
- 11ChallengeChoose authority and a useful next step
- 12RecapResolve the work and protect the relationship
Project Stakeholders and Communication practice questions
Set 1: Apply plans and interpret project evidence10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Recognize needs and choose useful first steps10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Connect stakeholder needs with team decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Analyze changing conditions and competing demands10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Make decisions across the whole project10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Accommodation
Accountable
Acknowledgment
Action log
Active listening
Adjourning
Assertiveness
Attitude
Authority
Avoidance
B
Baseline
Belbin team roles
Burndown chart
Burnup chart
C
Collaboration
Communication
Communication channel
Communication plan
Communication requirements analysis
Completer Finisher
Compromise
Conflict
Consensus
Consulted
Cooperativeness
Coordinator
D
Daily stand-up
Dashboard
Decision log
Decoding
Dispersed team
E
Encoding
Engagement
Engagement assessment matrix
Escalation path
External stakeholder
F
Feedback
Forcing
Forecast
Forming
G
Ground rules
I
Ideal line
Implementer
Information radiator
Informed
Interactive communication
Interest
Internal stakeholder
Issue
Issue log
Iteration review
K
Keep informed
Keep satisfied
Kickoff meeting
L
Leading
M
Majority
Manage closely
Managing expectations
Matrix organization
Minutes
Monitor
Monitor Evaluator
N
Neutral
Noise
Norming
O
Onboarding
P
Performing
Plant
Position
Power
Power–interest grid
Product owner
Progress report
Project charter
Pull communication
Push communication
R
RACI chart
RAG status
Recognition
Relationship conflict
Resistant
Resource Investigator
Responsibility
Responsibility assignment matrix
Responsible
Reward
S
Salience model
Shaper
Specialist
Stakeholder
Stakeholder engagement plan
Stakeholder register
Status report
Storming
Supportive
T
Tailoring
Task conflict
Team building
Team charter
Teamworker
Training
Tuckman’s model
U
Unanimity
Unaware
Underlying interest
W
Watermelon report
Working agreement