Project Cost and Resources
BeginnerLesson 6 of 9 in Project Management Foundations Course
What you will learn
- Identify every kind of cost a project incurs and turn the planned work into cost estimates, choosing a technique that fits the information available and stating how accurate the result is.
- Identify the costs a project incursRecognize the kinds of cost a project spends money on, from labor and materials to overheads, and the distinctions that change how each one is estimated.
- Plan estimates and judge their accuracyExplain why early estimates are ranges, describe how accuracy improves as the project is defined, and choose an estimating technique that fits the information available.
- Estimate top-down with analogous and parametric techniquesProduce quick whole-project or large-item estimates from past projects and from cost rates, and recognize when these top-down figures can be trusted.
- Estimate bottom-up and with three-point rangesBuild a detailed estimate by costing each work package from its resources and quantities, and express uncertain costs with optimistic, most likely and pessimistic values.
- Identify the costs a project incurs
- Separate the money set aside for identified risks from the money held for the unforeseen, size each reserve with a clear method, and control how reserves are used.
- Distinguish contingency reserves from management reservesDefine the two kinds of reserve, show how they combine with the work estimates into the cost baseline and the project budget, and know who controls each one.
- Size reserves and control their useCalculate a contingency reserve from risk data, set a management reserve, and follow the right steps when a risk occurs or an unforeseen problem appears.
- Distinguish contingency reserves from management reserves
- Combine the estimates into an approved budget, spread it over time to match the schedule and the available funding, and protect the resulting cost baseline with change control.
- Aggregate estimates into a project budgetRoll the cost estimates up through the work breakdown structure, add reserves at the right levels, and check that the budget is complete before it is approved.
- Time-phase the budget and plan fundingSpread the budget over the schedule, read the resulting S-curve, and adjust the timing of work so that spending stays within the funding available in each period.
- Approve and protect the cost baselineExplain what the cost baseline is, how it differs from the budget and from actual spending, and how approved changes, not overruns, are what change it.
- Aggregate estimates into a project budget
- Determine which resources each part of the work needs and when they are available, and adjust the plan so that no resource is asked to do more than it can.
- Identify and plan the resources the work needsList the people, equipment and materials each activity requires, with their skills, quantities and availability, and plan how they will be obtained and managed.
- Balance resource demand with leveling and smoothingRead a resource histogram, find overallocations, and resolve them by smoothing within float or by leveling, understanding how each affects the end date and the budget.
- Identify and plan the resources the work needs
- Make clear who does, decides, advises and is informed for each piece of work, and decide which goods and services the project needs from outside suppliers.
- Assign responsibilities with a RACI matrixBuild a RACI matrix from the project's deliverables and roles, check it for gaps and conflicts, and use it to prevent confusion about who does and who decides.
- Identify procurement needs and make-or-buy decisionsDecide which goods and services the project should obtain from outside, compare making with buying or renting, and describe what is needed clearly and early enough for the schedule and budget.
- Assign responsibilities with a RACI matrix
Project Cost and Resources study guide
1Estimate what a project will cost
Cost planning turns the work a project promises into a reasoned forecast of money needed. Start by identifying the kinds of cost, then match the estimating method to how much is known about the work. Quantities, rates, comparable projects and realistic ranges each provide different evidence. Worked calculations show how to keep effort separate from duration and how to carry uncertainty into an estimate without hiding it.
1.1 Identify the costs a project incurs
A project estimate starts with the resources the work will consume. People, materials and equipment are obvious costs; licenses, insurance, training, travel and project management time are easier to miss. Classifying costs helps you choose the right calculation for each one.
Classify costs in two ways
Direct costs can be charged to this project, such as its contractor fees or staff hours. Indirect costs, such as shared IT support and accounting, reach the project through an overhead allocation. State whether that allocation is included. If overhead is already in a labor rate, adding it again as a separate charge counts it twice.
Fixed and variable describe a different feature: how a cost changes with quantity. A venue fee of $6,000 is fixed across the planned attendance range. Catering at $45 per attendee is variable. For 120 people, catering is $5,400 and the total is $11,400. For 200, catering is $9,000 and the total is $15,000. A cost can be both direct and fixed; these labels answer different questions.
Price the effort, then check the duration
Labor cost equals person-hours multiplied by the burdened rate, which includes the employer's extra costs. Base pay of $40 per hour with a 35% load gives $40 × 1.35 = $54 per hour. A 120-person-hour task therefore costs $6,480.
If three people each work eight hours per day, they provide 24 person-hours daily. The task takes 120 ÷ 24 = 5 working days. One person takes 15 days but still supplies 120 hours. This comparison assumes the work can be shared without changing total effort. Equipment rented by the day behaves differently: a longer duration means more rental days.
Look beyond the purchase
A one-time installation cost and recurring support fees belong to different periods. Life-cycle cost adds the initial cost, operation, maintenance, replacement and disposal over the period being evaluated, then subtracts residual value.
For five years, system A costs $50,000 plus $8,000 a year: $90,000. System B costs $35,000 plus $14,000 a year: $105,000. Neither has replacement, disposal or residual value in this comparison. B has the lower initial cost but the higher five-year cost.
Keep decision figures distinct
A supplier's price becomes the buying project's cost. If the supplier spends $20,000 and adds a 15% markup on cost, the price is $23,000. A 15% profit margin on the selling price needs $20,000 ÷ 0.85, or about $23,529.41. Markup and margin use different denominators.
A sunk cost is already spent and unrecoverable. After spending $30,000 on a design, a team can finish it for another $25,000 or obtain the same result through a new approach for $18,000. The forward-looking comparison is $25,000 against $18,000; the past $30,000 cannot be saved by either choice.
Finally, attach a currency and price date to the estimate. Escalation allows for expected price increases: materials worth $100,000 today become $104,000 after an expected 4% increase over one year.
Key Takeaways
- Direct and indirect describe how costs are charged; fixed and variable describe how they change.
- Labor cost follows effort at the burdened rate; daily rental follows duration.
- Compare life-cycle costs over the same period.
- Markup is a share of cost; margin is a share of price.
- Exclude unrecoverable past spending from future choices.
- State currency and price date, including expected escalation.
1.2 Plan estimates and judge their accuracy
An estimate expresses what the project is likely to cost with the information available now. Its usefulness depends on showing both the figure and the uncertainty around it. A detailed-looking number can still rest on very rough knowledge.
Let the range follow the scope
Early requirements leave many choices open. As the design and work breakdown structure become clearer, more quantities and rates can be checked. The estimating funnel pictures this narrowing range. Progressive elaboration means refining the plan as knowledge grows; it does not mean quietly replacing earlier figures without a record.
Common estimate classes illustrate the change:
| Class | Typical stage | Common illustrative range |
|---|---|---|
| Rough order of magnitude (ROM) | Initiation | −25% to +75% |
| Budget | Main deliverables known | −10% to +25% |
| Definitive | Detailed work packages | −5% to +10% |
Organizations and industries define their own ranges; some use ±50% for ROM. Read the range attached to the estimate you are reviewing. For a $200,000 ROM at −25% to +75%, the lower value is $200,000 × 0.75 = $150,000. The upper value is $200,000 × 1.75 = $350,000. Using 1.25 for the upper multiplier would misread the asymmetric range.
A $240,000 definitive estimate at −5% to +10% spans $228,000 to $264,000. The narrower band reflects greater scope definition, not just a later date on the calendar.
Choose a method the evidence can support
With little detail, analogous estimating uses a similar completed project, while parametric estimating uses a measurable quantity and a reliable cost rate. With detailed work packages, bottom-up estimating prices their resources and adds the results. Three-point estimating examines an uncertain item through optimistic, most likely and pessimistic values. Supplier quotes support purchased items. Comparing two suitable methods can expose a missing cost or a poor assumption.
Ask the people who know or will do the work to help. Past actual costs, expert judgment and supplier information provide different kinds of evidence. Rolling-wave planning keeps near-term work detailed and later work broader until enough is known to price it properly.
Record the basis and keep the estimate honest
The basis of estimate records the method, data sources, assumptions, exclusions and expected range. For example: "Current supplier quotes; installation included; annual support excluded; prices valid through November." That record lets someone update a rate without having to guess what the old total contained.
An estimate is different from a target, which is the desired figure, and a commitment, which the team agrees to deliver. If analysis gives $180,000 and the sponsor wants $150,000, investigate a smaller scope or a different approach. Editing the estimate down by $30,000 removes useful information.
Counter optimism with past results and realistic ranges. Check the work breakdown structure for testing, training and handover. Keep risk allowances visible instead of hiding padding in every task. In adaptive work, story points compare relative work size; the money estimate commonly comes from the stable team's cost over the planned iterations.
Key Takeaways
- Estimate ranges narrow as scope becomes better defined.
- Choose the technique from the available evidence.
- Document methods, assumptions, sources, exclusions and range.
- Keep the estimate separate from the desired target and agreed commitment.
- Detail near-term work and refine later work through rolling-wave planning.
1.3 Estimate top-down with analogous and parametric techniques
You can estimate before every activity has been defined, provided the comparison or cost model is credible. Two top-down techniques use different starting points: a similar project's actual result, or a measured quantity with a supported unit rate.
Adjust a genuinely similar project
Analogous estimating starts with the actual final cost of a past project. Ask what makes it comparable: scope, technology, location, team experience and complexity. Then adjust for known differences. A budget that the old project exceeded is weaker evidence than what that project actually cost.
A previous intranet cost $120,000. The new one is judged 25% more complex, and relevant prices have risen 6% since the earlier work:
- Adjust complexity: $120,000 × 1.25 = $150,000.
- Adjust prices: $150,000 × 1.06 = $159,000.
The second percentage applies to the adjusted amount. Adding 25% and 6% and applying 31% once gives a different result. Record why the 25% adjustment is reasonable; the arithmetic cannot establish similarity by itself.
Analogous estimating is quick and inexpensive, which makes it useful during initiation. Its weakness is reliance on judgment and a small comparison base. An experienced team can still choose a misleading comparison if the new technology changes the work substantially.
Use a measurable cost driver
Parametric estimating uses a relationship between quantity and cost. A simple model is:
Here, the fixed amount is , quantity is and cost per unit is . Keep quantities and rates in matching units. An office fit-out of 300 m² at $900 per m² costs $270,000. The area units cancel in the calculation, leaving money.
A training rollout has an $8,000 fixed design cost plus $1,200 per participant. For 45 participants, the variable cost is $54,000 and the total is $62,000. Multiplying the whole total by attendance would make the fixed design cost grow incorrectly.
A rate is useful when its historical data are accurate, the parameter is measurable and the cost relationship holds across the range used. A cost per user from 50-user projects may be unreliable for 5,000 users. Large projects may introduce new coordination costs or economies of scale. A formula does not remove the need to examine its data.
Cross-check before choosing a figure
A similar office fit-out cost $250,000 for 280 m². Its implied rate is about $892.86 per m². That is close to the $900 rate, so it supports the order of magnitude of the $270,000 estimate for 300 m².
If the two methods differ widely, investigate scope, inclusions, location, price dates and data quality before averaging them. One estimate might include furniture while the other includes only building work. Averaging incompatible totals hides the reason for the gap.
Key Takeaways
- Analogous estimates adjust actual costs from comparable completed projects.
- Apply successive percentage adjustments to the updated amount.
- Parametric estimates use measured quantities and supported unit rates.
- Check that rates remain valid at the new scale.
- Investigate large differences between estimates before selecting a figure.
1.4 Estimate bottom-up and with three-point ranges
Detailed scope lets you build costs from the work itself. Uncertain items still need a range, even inside a detailed estimate. Bottom-up and three-point estimating therefore often work together.
Cost each work package
Bottom-up, or analytical, estimating prices the resources for activities or work packages, then adds them through the work breakdown structure. For "Install office network":
| Resource | Calculation | Cost |
|---|---|---|
| Technicians | 3 × 40 hours × $65/hour | $7,800 |
| Switches | 4 × $1,150 | $4,600 |
| Cable | 400 m × $2.55/m | $1,020 |
| Test equipment | 5 days × $90/day | $450 |
| Total | $13,870 |
Three technicians each work 40 hours, so effort is 120 person-hours. Applying the rate to only 40 hours would omit two people's work. The equipment uses a daily rate, so its quantity is rental days, not labor hours.
This method is strongest when the scope and resource quantities are well defined. It takes time, and detail cannot rescue an incomplete work breakdown structure. Check project management, testing, integration, training and handover. Assign each cost once so it is neither omitted nor included in two packages. Keep risk allowances visible.
Describe an uncertain item with three values
The optimistic value assumes things go well. The most likely value describes the most plausible outcome. The pessimistic value allows for realistic problems. All three describe the same work and scope; a smaller deliverable is not an optimistic cost for the original deliverable.
A triangular average gives equal weight to all three:
The PERT, or beta, average gives four times as much weight to the most likely value:
For an interface with O = $18,000, M = $24,000 and P = $42,000:
- Triangular: ($18,000 + $24,000 + $42,000) ÷ 3 = $28,000.
- PERT: ($18,000 + $96,000 + $42,000) ÷ 6 = $26,000.
Use a divisor of 3 for three equal weights and 6 for the PERT weights of 1, 4 and 1. Dividing the weighted PERT total by 3 would double the intended answer.
Read the spread as well as the average
A rough PERT standard deviation is:
Here, ($42,000 − $18,000) ÷ 6 = $4,000. The long pessimistic side pulls both averages above the $24,000 most likely value. Using M alone would leave a $2,000 gap against the PERT expectation.
A wider spread points to work worth investigating in the risk register and reserve analysis. The expected value is a planning figure, not a guaranteed final invoice. When adding contingency for an uncertain item, check whether its expected-cost allowance is already included in the base estimate, so the same uncertainty is not counted twice.
Key Takeaways
- Bottom-up estimates price resources and aggregate through the work breakdown structure.
- Detailed estimates still need complete scope and checks for double counting.
- Three-point values describe the same work under different outcomes.
- Triangular averages use equal weights; PERT weights the most likely value four times.
- The PERT spread estimate is (P − O) ÷ 6.
- Avoid counting the same uncertainty in both an expected estimate and an added reserve.
2Plan reserves for uncertainty
A project can plan the work carefully and still face uncertain costs. Visible reserves show how much money protects against those risks and who may authorize its use. Separate identified risks from unforeseen work within scope, then size and track the reserves with a clear method. The office move connects risk probabilities to a contingency amount and shows how a management reserve transfer changes the budget's internal split.
2.1 Distinguish contingency reserves from management reserves
Reserves make uncertainty visible in the budget. They let the team discuss likely risk costs without quietly increasing every task estimate. The two main reserves differ in purpose, position and control.
Put each reserve in the right place
| Reserve | What it covers | Where it sits | Who normally controls it |
|---|---|---|---|
| Contingency | Identified risks | Inside the cost baseline | Project manager, within agreed rules |
| Management | Unforeseen work within scope | Outside the baseline, inside the project budget | Sponsor or senior management |
An identified supplier delay is a known-unknown: the team knows the event is possible but does not know whether it will occur. A contingency reserve provides for that kind of uncertainty. Management reserve covers an unforeseen in-scope problem, often called an unknown-unknown. Using it requires management approval and a change to the cost baseline.
For the office move, planned work costs $120,000. Add $8,000 contingency to obtain a $128,000 cost baseline. Add $6,000 management reserve to obtain the $134,000 project budget:
The $6,000 is authorized funding held outside the performance reference. Putting it inside the baseline at the start would blur that distinction.
Separate uncertainty from extra scope
A customer requesting an additional deliverable has changed the scope. Neither reserve is a general fund for extras. Record the request and assess its effects before approval. The change authority decides how to fund it: existing authorized funds, a trade-off that removes other work, a separate change budget or additional funding.
Some methods call money for planned risk responses a risk budget, and hold a change budget for approved changes. These names serve different purposes; a change budget does not replace the decision to approve the scope change.
Connect money and time
A supplier delay can require both extra rental payments and extra days. Plan the cost allowance with the schedule reserve, or time buffer, for identified schedule risks. A cash allowance alone cannot recover days lost from the schedule.
A tolerance defines how far performance may deviate before the next management level must decide. A $50,000 stage budget with ±10% cost tolerance has limits of $45,000 and $55,000. A $57,000 forecast exceeds the upper limit and must be escalated. The tolerance describes authority; it does not add $5,000 to the budget or establish a reserve.
Keep reserve amounts and ownership explicit. If every task owner adds an unexplained allowance, the total risk provision becomes hard to see and may be repeated. A visible reserve lets decision makers review how much protection the project has and who can authorize its use.
Key Takeaways
- Contingency covers identified risks and belongs inside the cost baseline.
- Management reserve covers unforeseen in-scope work and sits outside the baseline.
- Work estimates plus contingency form the baseline; management reserve completes the budget.
- Extra scope needs change control and a funding decision.
- Tolerance sets an escalation limit; it is not extra money.
2.2 Size reserves and control their use
A reserve needs a reason for its size and a rule for its use. Start with the uncertainty being covered, then choose a method that makes that uncertainty visible to the people approving the budget.
Calculate a risk-based contingency
A percentage allowance is quick: 10% of $120,000 gives $12,000. It does not show which risks produced that amount. Expected monetary value (EMV) ties the calculation to the risk register:
Treat threats as cost additions and opportunities as reductions. For the office move:
| Event | Probability and impact | Contribution |
|---|---|---|
| Supplier delay | 30% × $20,000 | $6,000 |
| Fit-out rework | 20% × $15,000 | $3,000 |
| Bulk discount | 25% × $4,000 saving | −$1,000 |
The net contingency is $6,000 + $3,000 − $1,000 = $8,000. The discount reduces expected cost, so adding its $1,000 contribution would reverse its effect.
EMV is a pooled planning amount. If the supplier delay happens, its cost is $20,000, not $6,000. Probability weights the planning calculation; it does not reduce the invoice after the event occurs. The $8,000 total is not a guarantee that every combination of events can be paid for. The desired confidence and the remaining exposure matter when judging adequacy.
Use other evidence without double counting
Three-point analysis can show an allowance above a base estimate. For an item with M = $24,000 and PERT expectation $26,000, a plan can hold $24,000 for the work and $2,000 in contingency. If $26,000 is already in the base, do not add that same $2,000 again. Larger projects may use simulation, such as Monte Carlo analysis, to examine combined uncertainty and select a confidence level.
Management reserve is often set by organizational policy, with larger allowances for unfamiliar or complex work. Record the percentage, amount and reasoning. No single percentage fits every project.
Record transfers and remaining exposure
When an identified risk occurs, follow the agreed authorization rules, transfer the approved contingency amount to the affected work and log it. This allocates money already inside the cost baseline. Review whether risks have expired and whether unused amounts should be retained or released under the plan.
For a separate unforeseen in-scope problem costing $4,500, the office move's sponsor approves a transfer from management reserve. The baseline rises from $128,000 to $132,500. Management reserve falls from $6,000 to $1,500. The project budget remains $134,000 because this is a transfer within existing funding.
Reserve analysis compares what remains with the risks still ahead. Using half the reserve when only a small part of the risk has passed is a reason to investigate. Cutting reserves merely to secure approval hides exposure, and using contingency to cover poor performance without reporting it hides the cause of the extra cost.
Key Takeaways
- EMV multiplies probability by cost impact; savings reduce the total.
- An event that occurs costs its full impact, not its probability-weighted amount.
- Check whether expected-cost uplifts are already in the base estimate.
- Management reserve transfers raise the baseline but leave total funding unchanged.
- Review reserve remaining against remaining risk.
- Log reserve use and follow its authorization rules.
3Build the budget and cost baseline
A budget must be complete, authorized and available at the right time. Combine the work estimates, place costs against the schedule and check when cash will be needed. The office move shows why a month can exceed its funding limit even when the total budget is sufficient. Keeping the approved baseline separate from actual cost and the latest forecast makes changes visible and preserves a useful reference for decisions.
3.1 Aggregate estimates into a project budget
Estimates describe the cost of pieces of work. Determining the budget joins those pieces, adds the reserves in the right places and establishes an amount that the organization can authorize. The work breakdown structure provides the route for adding costs without losing their origin.
Roll costs upward
Activity estimates add to work packages. Related work packages add to control accounts, and the accounts add to the project total. A control account joins scope, schedule and budget under a responsible manager so performance can be reviewed at a useful level.
Add contingency where the relevant risk is managed: at a work package, a control account or project level. Check whether a lower-level total already contains it before adding a project allowance. The resulting total is the cost baseline. Management reserve is added outside it to reach the project budget.
The office move has four work estimates:
| Work | Estimate |
|---|---|
| Plan and design the layout | $12,000 |
| Fit out the office | $64,000 |
| Install IT network and equipment | $28,000 |
| Move and set up | $16,000 |
| Planned work total | $120,000 |
The first two packages total $76,000. Adding IT gives $104,000; adding the move gives $120,000. Contingency of $8,000 produces a $128,000 baseline. Management reserve of $6,000 brings the authorized project budget to $134,000.
Use the right breakdown for the question
| Structure | What it organizes |
|---|---|
| Work breakdown structure (WBS) | Deliverables and work |
| Cost breakdown structure (CBS) | Costs by work element or cost type |
| Organizational breakdown structure (OBS) | Organizational units and roles |
| Resource breakdown structure (RBS) | Resource categories and types |
The CBS can connect project costs to accounting codes, such as labor, equipment and services. A WBS view answers "What result does this money buy?" A cost-type view answers "How much are we spending on labor?" These are views of the same costs, not totals to add together.
Check the whole budget before approval
Use the estimates and their basis, schedule, risk register, resource calendars and supplier agreements together. Check that every work package has a cost and that project management, quality checks, training and handover are included. Align currency and price dates, confirm the reserve treatment and explain major differences from earlier top-down estimates.
Sponsor or governance approval authorizes the budget. Cash may still be released in tranches, such as one phase at a time after a review. Approval of the total and release of the next phase's money are separate decisions.
Budget for a stable adaptive team
An adaptive team costing $54,000 per two-week iteration needs $540,000 for ten iterations. That funds a period of team capacity. The team prioritizes scope to fit the time and money available and reviews its forecast after each iteration. Multiplying team cost by iterations does not guarantee that every requested feature fits those iterations.
Key Takeaways
- Aggregate activity costs through work packages and control accounts.
- Add each reserve once, at the level where it is managed.
- WBS, CBS, OBS and RBS organize different views of the project.
- Check completeness, price dates and consistency before approval.
- A stable adaptive team budget follows cost per iteration × iterations.
3.2 Time-phase the budget and plan funding
A total budget cannot show whether money will be available on the day a payment is due. Time-phasing connects cost to the schedule, and the funding plan connects that timing to the cash the project can use.
Place costs where work happens
A time-phased budget allocates planned cost by week, month or quarter. Use the schedule and each cost's actual pattern. Staff effort may be spread across an activity, while materials may be charged on delivery and a final supplier payment may wait for acceptance.
For the office move, design costs $12,000 in month 1. Fit-out costs $64,000 evenly across months 2 and 3. IT costs $28,000 in month 3, and moving costs $16,000 in month 4.
| Month | Planned work cost | Cumulative work cost |
|---|---|---|
| 1 | $12,000 | $12,000 |
| 2 | $32,000 | $44,000 |
| 3 | $60,000 | $104,000 |
| 4 | $16,000 | $120,000 |
These figures phase the work estimates. The full $128,000 baseline also includes $8,000 contingency, allocated according to the risk plan. Dividing $120,000 equally into four months would produce neat figures but would ignore when the work occurs.
Cumulative planned cost often forms an S-curve: slow growth during early planning, faster growth when work overlaps, then slower growth during finishing. The exact shape follows the plan; it need not be a perfect S. The endpoint is the total planned cost represented by the curve.
Separate incurred cost from cash paid
Cost is incurred when work is performed or goods are received. Cash leaves when payment is due. Equipment received in month 2 and paid 30 days later creates month 2 incurred cost and month 3 cash outflow. Performance reporting and funding planning therefore need different timing views.
Funding requirements show both the amount and timing of needed cash, based on the baseline and expected management reserve use. Funding released at phase gates creates a staircase-shaped cumulative line. Available cumulative funding must cover cumulative cash outflows when payments are due.
Reconcile a period that exceeds its limit
Suppose payments in the office example occur in the same months as the displayed costs, and each month has a $50,000 limit. Month 3 is $10,000 too high. The schedule allows a $10,000 IT equipment purchase in month 2: its predecessors are complete and the supplier can deliver early.
Move that purchase forward. The new monthly totals are $12,000, $42,000, $50,000 and $16,000. Their sum is still $120,000; their cumulative totals are $12,000, $54,000, $104,000 and $120,000. Timing has changed, not the amount of work.
This is funding limit reconciliation. Before moving work earlier, check dependencies and earlier resource availability. Before delaying it, check float and the critical path. Float describes allowable delay; it does not establish that earlier work is possible. Update both the schedule and the time-phased cost and cash views after an agreed timing change.
Key Takeaways
- Time-phase costs from the schedule and the actual cost pattern.
- Cumulative amounts add each period to all previous periods.
- Funding plans follow cash payments; cost reports follow incurred costs.
- Reconcile period limits while respecting dependencies, float and availability.
- The work-cost total excludes the separate contingency allocation shown in the full baseline.
3.3 Approve and protect the cost baseline
The approved cost plan gives the project a stable reference for judging what changes during delivery. Keeping that reference separate from forecasts makes both the original agreement and the current outlook visible.
Know which figure answers which question
| Figure | Question it answers |
|---|---|
| Cost baseline | What spending plan was approved, including contingency? |
| Project budget | What total funding is authorized, including management reserve? |
| Funding | How much money has actually been made available? |
| Actual cost | What cost has been incurred for work performed so far? |
| Forecast | What do we now expect the final total to be? |
The cost baseline is approved and time-phased. It includes contingency and excludes management reserve. For the office move, it is $128,000, while the project budget is $134,000. An unpaid invoice for work already performed contributes to actual cost; the payment belongs to the cash plan when due.
The scope, schedule and cost baselines together form the performance measurement baseline. A new deliverable can affect all three. Updating the cost alone may leave a schedule that has no time for the extra work.
Change the baseline through an authorized decision
Suppose the client requests an extra meeting room costing $9,500. The project manager records the request and assesses scope, cost, schedule and risk effects. The change authority approves it with new funding. The cost baseline becomes $128,000 + $9,500 = $137,500. The project budget becomes $134,000 + $9,500 = $143,500, with the $6,000 management reserve unchanged.
Record the approval, revised amounts, affected work and effective version, then communicate the change. A baseline changes only through formal change control. An informal email saying "we will probably need more" updates neither authority nor the agreed reference.
This scope-change example starts from the original office budget. It is a different decision from transferring existing management reserve into the baseline: a transfer changes the split within the budget, while newly approved funding increases the total.
Update forecasts without hiding performance
A forecast changes when new information changes the expected outcome. If costs rise, report the forecast and investigate the cause while preserving the approved baseline. Moving the baseline to the latest actual or forecast amount simply to remove an overrun erases the comparison. A formally approved scope change or replan can establish a revised baseline, with the decision and earlier reference retained.
After the office move's timing adjustment, planned cumulative work cost at month 2 is $54,000. Actual cost of $51,000 alone cannot establish a saving. The team may have completed the planned work more cheaply, or it may have completed less work. Look at progress as well as spending before interpreting the difference.
An unused budget balance does not require spending. The baseline authorizes and measures the planned work; it is not a target to exhaust by buying unnecessary items.
Key Takeaways
- The cost baseline is the approved time-phased plan, including contingency.
- Keep baseline, total budget, available funding, actual cost and forecast distinct.
- Assess scope, schedule, cost and risk before approving a change.
- New funding raises the total budget; a reserve transfer reallocates existing funds.
- An updated forecast does not by itself change the baseline.
- Interpret spending together with work completed.
4Plan the people, equipment and materials
People, equipment and materials need to be available when scheduled work calls for them. Resource planning turns activities into quantities, skill requirements and calendar commitments. Comparing total demand with real capacity reveals conflicts that are hidden when tasks are checked separately. The choice between smoothing and leveling then connects those conflicts to the finish date, the critical path and time-dependent costs.
4.1 Identify and plan the resources the work needs
A resource plan connects each activity to the people, equipment, materials and facilities it needs. A cost estimate may contain enough money for a technician but still fail if the right technician is unavailable when the work must happen.
Specify what the activity needs
Start with the activity list or work breakdown structure. For each activity, record resource type, skill or specification, quantity, timing and source. "Two people" is less useful than "two network technicians with the required certification, available for three days." Those requirements feed both the duration estimate and the cost estimate.
A resource breakdown structure (RBS) groups resources by category and type. Labor might contain painters and technicians; equipment might contain lifts and test meters; materials might contain paint and cable. This checks for omissions and supports totals by resource type. It does not show when those resources will be free.
Turn output into quantities
Suppose 450 m² of office walls need two coats of paint. Coverage is 10 m² per liter per coat. The coverage requirement is 450 × 2 = 900 m²-coats. Divide by 10 to obtain 90 liters. Add a 10% waste allowance: 90 × 1.10 = 99 liters. With whole-liter ordering, order 99 liters. Round upward only after applying all allowances when a fractional amount remains.
Three painters working five days at eight hours per day provide 120 person-hours. At $38 per hour, labor costs $4,560. Paint quantity follows area, coats and coverage; labor follows estimated effort. These quantities use different units and cannot substitute for each other.
Check real availability
A resource calendar records working days, holidays, part-time hours, other project commitments and equipment maintenance. A person assigned 50% of a 40-hour week supplies 20 hours. A 60-person-hour task takes three weeks at that availability, not the one and a half weeks implied by a full-time assumption.
Check skill as well as hours. A free painter cannot take over work that needs a qualified electrician. More people may also create extra coordination or training work, so doubling headcount need not halve duration.
Plan acquisition, care and release
Internal staff assignments usually need agreement with functional managers. External hiring, rental and purchases create procurement needs. Work backward from the required date using selection, approval and delivery lead times; money in the budget does not make a scarce item arrive sooner.
The resource management plan describes how resources are identified, acquired, managed and released. Include responsibilities, training, delivery, storage and logistics. An early materials delivery may require secure storage. Just-in-time delivery reduces storage needs but makes a late delivery more disruptive to scheduled work.
Review availability across the whole project and other commitments before confirming assignments. A calendar with no allowance for meetings or operational support can overstate the capacity the team can actually contribute.
Key Takeaways
- Activity resource estimates specify type, skill, quantity and timing.
- Resource quantities feed both duration and cost estimates.
- Use calendars to calculate actual available capacity.
- Include material allowances and round purchase quantities at the end.
- Plan acquisition, training, logistics and release with the relevant managers.
4.2 Balance resource demand with leveling and smoothing
Resource problems often appear only when activities are viewed together. A schedule can give every task a sensible individual assignment and still demand more people on the same day than the organization has.
Find the peak demand
A resource histogram shows demand per period as bars, usually against an availability line. Add demand for the same resource across every concurrent activity, including commitments to other projects. Overallocation occurs when total demand exceeds available capacity.
Three electricians are available. Task A needs two on days 1–3 and is on the critical path. Task B needs two on days 1–2. Demand on days 1 and 2 is four, exceeding capacity by one. The project cannot carry out both tasks as scheduled with those three electricians.
Smooth within float
Resource smoothing moves activities within their float, preserving the end date. If B has three days of total float, delay its start from day 1 to day 4. It now runs on days 4–5, after A ends. Its start moved three days, using all its float. Demand becomes two electricians on each day from 1 through 5.
Smoothing cannot always remove every overload: some tasks have too little float to avoid a busy period.
Level to respect a fixed resource limit
Resource leveling changes dates to respect availability, even when that changes the end date. Now suppose B has only one day of total float. The earliest feasible slot is still days 4–5. Its three-day delay exceeds float by two days, so the project finishes two days later in this network, with B now critical.
| Approach | Main constraint | Date effect |
|---|---|---|
| Smoothing | Preserve the finish date | Stay within float |
| Leveling | Respect resource limits | Finish may move; critical path may change |
These are also called time-limited and resource-limited scheduling. Leveling can finish without a delay if enough room exists; the distinction is that it permits the resource limit to drive the dates.
Compare alternatives and their costs
If the end date cannot move, consider borrowing or hiring capacity, overtime, splitting work where feasible, changing the skill mix or an approved scope reduction. Each option needs a cost, quality and risk check.
An electrician at $60 per hour earns $90 at time-and-a-half. Sixteen overtime hours cost $1,440, compared with $960 at the ordinary rate: an extra $480. Compare that premium with the costs of a longer project, such as additional daily rental. The cheapest hourly option may not produce the cheapest overall plan.
After any timing adjustment, recalculate resource demand, check the critical path and update the time-phased budget and funding plan. Moving an activity to another week moves its costs; extending the project can also increase time-dependent costs.
Key Takeaways
- Add demand across concurrent work before comparing it with capacity.
- Smoothing stays within float and protects the end date.
- Leveling respects resource limits and may change the finish or critical path.
- Compare overtime and added capacity with the full cost of delay.
- Update resource, schedule, cost and cash views after moving work.
5Assign responsibilities and identify what to buy
A workable project plan makes both responsibility and outside supply clear. A RACI matrix identifies who performs work, who approves it and who needs input or updates. Procurement planning identifies what the organization must buy or rent, how it compares with internal delivery and how early the process must start. Together, these decisions connect deliverables to people with authority and suppliers with clear acceptance requirements.
5.1 Assign responsibilities with a RACI matrix
Clear responsibilities prevent a deliverable from waiting while several people assume someone else will decide. A responsibility matrix links work to roles so the team can agree who acts and who has the authority to approve the result.
Read the four RACI letters
A responsibility assignment matrix (RAM) places deliverables, work packages or activities in rows and people or roles in columns. RACI is a common form:
| Letter | Role in the work |
|---|---|
| R — Responsible | Performs the work |
| A — Accountable | Owns the result, makes the final decision and signs off |
| C — Consulted | Gives input through two-way communication |
| I — Informed | Receives updates through one-way communication |
Each row needs exactly one A and at least one R. One person may hold both A and R. Assign A to a single person or role with real decision authority; "the team" leaves approval ownership unclear.
For the office move's "Approved floor plan," the sponsor is A and the facilities manager is R. The IT lead and department heads are C because their input affects the plan. All staff are I. Being informed about the approved layout does not make every staff member a design reviewer.
For "Network installed and tested," the IT lead is A, the contractor is R, the facilities manager is C and the project manager is I. An outside supplier can perform the work while an internal person remains answerable for acceptance.
Build the matrix with the people involved
Take the deliverables or work packages from the work breakdown structure. List the roles involved, agree the letters with the team and relevant managers, then check rows and columns before sharing the matrix. A high-level RAM can connect work packages with organizational units from the OBS; a detailed matrix can name the individuals carrying out activities.
Use roles when the matrix needs to remain useful after staffing changes. Make sure each role still points to an identified decision maker in the current project. Update the matrix when scope or responsibilities change.
Check across and down
Read across a row to find a missing A, competing As, missing R or too many Cs. No A leaves the decision unowned; two As can create conflicting approvals; no R leaves the work undone. Every consulted role creates a two-way communication demand, so include people whose input is needed.
Read down a column to spot a possible workload or decision bottleneck. Many Rs suggest a person may have too much to do; many As suggest approvals may queue behind one person. Check the resource calendar to establish whether the assignments actually overlap. RACI does not contain workload timing.
C and I assignments also inform the communication plan: consulted people need opportunities to respond, while informed people need appropriate updates. A variant, RASCI, adds S for Support: people who help the responsible person. Agree the legend so everyone reads the same letter in the same way.
Key Takeaways
- Each RACI row has exactly one A and at least one R.
- R performs the work; A owns and approves the result.
- C requires two-way input; I receives one-way updates.
- Check rows for gaps and conflicts, and columns for possible bottlenecks.
- Use resource calendars to check workload timing; keep the matrix current.
5.2 Identify procurement needs and make-or-buy decisions
Some resources come from inside the organization; others require an outside supplier. Identifying those needs early gives the project time to decide what to obtain, compare the alternatives and describe a result a seller can price.
Find the procurement needs
Review the work breakdown structure, resource requirements and missing skills. Equipment rental, specialist installation and bought materials are procurement needs. Check purchasing policies, including which purchases must go through a central team. Supplier selection, approval and delivery all need time in the schedule.
Make-or-buy analysis compares internal work with outside supply, or buying with renting. Include labor at burdened rates, equipment, maintenance and supervision for in-house work. On the supplier side, include the price, delivery, setup and management effort. Compare equivalent quality, quantities and timing.
Cost is only part of the decision. Available skills and capacity, quality control, confidentiality, delivery risk and long-term ownership may change the choice. An apparently cheaper internal option is not feasible if the required team is already fully committed.
Work out buying and renting
A machine is needed for 14 months. Buying costs $24,000 plus $200 monthly maintenance. Renting costs $1,400 per month. Ignoring resale for this first comparison:
- Buy: $24,000 + 14 × $200 = $26,800.
- Rent: 14 × $1,400 = $19,600.
Renting costs $7,200 less. To find the duration at which the costs are equal, let be months:
Before 20 months, renting is cheaper under these assumptions; after 20, buying is cheaper. At 20 months the two totals match.
Now include an $8,000 resale value after the 14-month project. Buying's net cost becomes $26,800 − $8,000 = $18,800, which is $800 less than renting. State resale assumptions clearly because this one changes the decision. Include only future relevant costs; unrecoverable past spending does not change which option is better from now on.
Define the result and its timing
A procurement statement of work (SOW) tells potential sellers what to supply. Include quantities, specifications or performance needs, quality standards, required date and location, acceptance criteria and reporting. "Provide suitable desks" is vague. "Supply 20 desks to the new office by May 6, assembled, with dimensions and finish matching the approved specification" gives the seller a basis for pricing and acceptance.
Lead time includes selection and approval as well as production and delivery. Furniture requiring three weeks for selection and approval, then ten weeks for manufacture and delivery, needs the process to start at least 13 weeks before use. Include purchase, delivery, applicable taxes and supplier-management costs in the estimate.
A procurement strategy sets the high-level approach: one supplier or several, selection approach, timing of payments and delivery arrangements. Agree it with purchasing and legal specialists under organizational policy. Even when a supplier performs the work, an internal accountable person oversees acceptance.
Key Takeaways
- Compare complete relevant costs and non-cost constraints in make-or-buy decisions.
- Resale value can reverse a buy-versus-rent decision.
- A procurement SOW defines deliverables, timing, quality and acceptance.
- Lead time includes selection, approval, production and delivery.
- External delivery still needs internal accountability.
Project Cost and Resources examples
1Build and test a cost estimate
18 steps
- 1IntroductionStart with the work, then choose the evidence
An estimate answers two linked questions: "What resources will the work consume?" and "How well can we price them now?"
A clear scope supports detailed quantities, priced bottom-up. A rough concept needs broader comparisons, such as analogous estimating and parametric estimating, and wider ranges, so the method fits the evidence. Work through both kinds of evidence, then examine an uncertain item with three-point estimating, without pretending its most likely cost is certain.
- 2ExplanationAsk how each cost behaves
Classify each expense in two ways. Direct or indirect describes how it is charged to the project. Fixed or variable describes how it changes with quantity.
A contractor's setup fee can be direct and fixed. Cable charged per meter is direct and variable. Shared accounting support is indirect. State whether the estimate includes that overhead, and check whether it is already included in the labor rate.
- 3ExampleTurn base pay into a usable rate
A technician earns $40 per hour. The employer adds a 35% load for its extra costs, giving $40 × 1.35 = $54 per hour.
A 120-person-hour task costs 120 × $54 = $6,480. If three people each supply eight hours daily, they provide 24 person-hours a day, so duration is 120 ÷ 24 = 5 working days. The cost follows effort; the duration follows how that effort is scheduled.
- 4ChallengeSeparate labor effort from rental days
A task needs 64 person-hours at $50 per hour. Two people each work eight hours daily, and a test device is rented for the whole task at $80 per day. What is the combined cost?
---reveal---
Two people provide 16 hours daily, so duration is four days. Labor costs $3,200 and rental costs $320, giving $3,520. Charging the device for 64 days would confuse person-hours with elapsed rental days.
- 5Key InsightCompare costs over the same period
Purchase price can point in the wrong direction when later costs differ. System A costs $50,000 plus $8,000 yearly support; B costs $35,000 plus $14,000 yearly support. Over five years they cost $90,000 and $105,000, with no other ownership costs or residual values.
Include operation, maintenance, replacement and disposal where relevant, then subtract residual value. Unrecoverable past spending does not change which future option costs less.
- 6ExplanationMake the range visible
The estimating funnel narrows as scope and design become clearer. Early ROM estimates commonly illustrate a −25%/+75% range; detailed definitive estimates may use −5%/+10%. Organizations define their own bands.
Record the method, data, assumptions, exclusions and range in the basis of estimate. A precise-looking total without that record can hide rough quantities or an expired supplier price.
- 7ExampleCalculate both ends separately
For a $200,000 ROM with −25%/+75%, calculate the lower endpoint as $200,000 × 0.75 = $150,000. Calculate the upper endpoint as $200,000 × 1.75 = $350,000.
The band is asymmetric. Subtracting and adding 25% would turn the upper value into $250,000 and discard the stated overrun allowance. Use the two percentages attached to this estimate, not a remembered symmetric range.
- 8ChallengeRespond to an unaffordable estimate
A supported estimate is $96,000, but the sponsor's target is $80,000. No scope or rate has changed. Should the estimate become $80,000?
---reveal---
Keep $96,000 as the estimate and discuss a smaller scope, a different approach or more funding. The $80,000 is a target. Replacing the estimate with that target hides the $16,000 gap without changing the work that creates it.
- 9ExampleAdjust a comparable actual cost
A completed intranet cost $120,000. The new one is judged 25% more complex, with prices now 6% higher.
First calculate $120,000 × 1.25 = $150,000. Then calculate $150,000 × 1.06 = $159,000. This is analogous estimating. Its credibility depends on whether the old project's scope and delivery conditions are comparable, not just on multiplying correctly.
- 10ExampleAdd fixed and per-unit costs
A training program has a fixed design fee of $8,000 and a cost of $1,200 per participant. For 45 people, the variable cost is $54,000. Add the design fee once to get $62,000.
This is parametric estimating because participant count drives cost through a supported rate. Check the rate's inclusions and scale: a model drawn from small sessions may need adjustment for a much larger rollout.
- 11ChallengeInvestigate a large gap
An analogous estimate for a refurbishment is $70,000. A parametric estimate is $100,000. The methods use the same currency and price date, but their included work has not been compared. What should happen before a figure is selected?
---reveal---
Compare scope and inclusions, then the data and adjustments behind each method. One may include furniture or specialist installation that the other omits. Averaging to $85,000 would conceal that unresolved difference.
- 12ExplanationPrice the resources in each work package
A bottom-up estimate builds from the resources needed for defined work. For an office network:
- Technician effort: 3 × 40 hours × $65 = $7,800.
- Switches: 4 × $1,150 = $4,600.
- Cable: 400 m × $2.55 = $1,020.
- Rental: 5 days × $90 = $450.
These add to $13,870. Check testing, handover and management effort, and count each expense in only one work package.
- 13ExplanationDefine three realistic outcomes
Three-point estimating uses optimistic O, most likely M and pessimistic P costs for the same scope. The pessimistic value reflects realistic problems, not an unlimited disaster.
For a software interface, O is $18,000, M is $24,000 and P is $42,000. The longer side above M expresses greater exposure to overruns. Changing the deliverable between the three values would mix scope choices with uncertainty.
- 14ExampleGive each value equal weight
The triangular average is:
For the interface, add $18,000 + $24,000 + $42,000 = $84,000. Divide by three to get $28,000.
Each value receives equal weight. The result sits above the most likely cost because the pessimistic side extends $18,000 above M, while the optimistic side is only $6,000 below it.
- 15ExampleGive the most likely cost more weight
PERT uses:
Four times $24,000 is $96,000. Add $18,000 and $42,000 to get $156,000, then divide by six to obtain $26,000.
A rough PERT standard deviation is (P − O) ÷ 6, so ($42,000 − $18,000) ÷ 6 = $4,000. The weighting and spread describe different features: central expectation and uncertainty.
- 16ChallengeCheck the weighting
A work item has O = $4,000, M = $7,000 and P = $16,000. What is its PERT expected cost?
---reveal---
Four times $7,000 is $28,000. Adding the extremes gives $48,000; dividing by six gives $8,000. The equal-weight average would be $9,000. Using M alone gives $7,000 and misses the expected-cost effect of the long pessimistic side.
- 17ChallengeChoose detail without losing uncertainty
The WBS and resource quantities are complete, but one integration item has a wide range. The sponsor asks for a defensible total. How can the estimating methods work together?
---reveal---
Build the defined work bottom-up and examine the uncertain integration item with three-point values. Record the assumptions and range in the basis of estimate. Detail in most packages does not remove the uncertainty concentrated in this one item.
- 18RecapCheck the estimate before sharing it
Before presenting an estimate, check four things:
- Resource quantities and rates describe the full work.
- The technique fits the available evidence.
- The range and basis are visible.
- The total does not count the same work or allowance twice.
Then compare the supported figure with the target. Any gap is a decision about the work or funding, not a reason to erase the evidence.
2Build and use visible reserves
10 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionGive uncertainty a visible place
- 2ExplanationDistinguish identified from unforeseen risks
- 3ExampleBuild the two totals
- 4ChallengeHandle an extra deliverable
- 5ExplanationWeight impacts before pooling them
- 6Key InsightAn expected amount is not a discounted invoice
- 7ChallengeRecalculate a net allowance
- 8ExampleMove existing funding into the baseline
- 9ChallengeApply authority and reserve rules together
- 10RecapReview what is left and what lies ahead
3Turn the office estimates into a controlled budget
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionConnect amount, timing and approval
- 2ExplanationAdd costs through the work structure
- 3ExampleBuild the office move total
- 4ChallengeCount an embedded reserve once
- 5ExamplePlace work costs in their months
- 6ExampleRead the cumulative profile
- 7Key InsightCash can move after the cost occurs
- 8ExampleMove a feasible purchase
- 9ChallengeTest a proposed earlier start
- 10ExplanationKeep the reference and outlook separate
- 11ExampleApprove extra scope and new funding
- 12ChallengeInterpret low spending carefully
- 13RecapKeep the budget useful for decisions
4Fit resource demand to real capacity
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionAsk who and what is available when
- 2ExampleCalculate paint with an allowance
- 3ExplanationRead the resource calendar
- 4ChallengePlan a feasible specialist assignment
- 5ExplanationAdd the overlapping demands
- 6ExampleUse three days of float
- 7ChallengeFind the limit of smoothing
- 8ExamplePrice the overtime premium
- 9ChallengeConnect delivery timing with resource planning
- 10ConnectionMove the cost plan with the schedule
- 11RecapConfirm capacity before committing dates
5Agree ownership and an outside supply plan
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionConnect work to people and suppliers
- 2ExplanationRead the four roles
- 3ExampleAssign the office network
- 4ChallengeRepair competing approvals
- 5TipUse rows and columns for different checks
- 6ExplanationCompare feasible supply options
- 7ExampleCalculate the 14-month totals
- 8ExampleFind the equal-cost duration
- 9ExampleInclude value recovered at the end
- 10ChallengeWork back from the needed date
- 11ChallengePlan acceptance of outside work
- 12RecapMake agreements usable for delivery
Project Cost and Resources practice questions
Set 1: Apply estimates, ownership and resource limits10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Build a sound cost and resource plan10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Connect risks, schedules and buying decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Resolve combined cost and resource decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Accountable
Activity resource estimate
Actual cost
Analogous estimating
B
Basis of estimate
Bottom-up estimating
Budget estimate
Burdened labor rate
C
Change budget
Consulted
Contingency reserve
Control account
Cost aggregation
Cost baseline
Cost breakdown structure
Cost driver
Cost estimate
Cumulative planned cost
D
Definitive estimate
Direct cost
Duration
E
Effort
Escalation
Estimating funnel
Expected monetary value
F
Fixed cost
Forecast
Funding limit reconciliation
Funding requirements
I
Indirect cost
Informed
J
Just-in-time delivery
L
Lead time
Life-cycle cost
M
Make-or-buy analysis
Management reserve
Markup
O
Opportunity
Organizational breakdown structure
Overallocation
P
Parametric estimating
Performance measurement baseline
PERT average
Procurement need
Procurement statement of work
Procurement strategy
Profit margin
Progressive elaboration
Project budget
R
RACI matrix
RASCI
Reserve
Reserve analysis
Resource breakdown structure
Resource calendar
Resource histogram
Resource leveling
Resource management plan
Resource smoothing
Responsibility assignment matrix
Responsible
Rolling-wave planning
Rough order of magnitude
S
S-curve
Schedule reserve
Standard deviation
Sunk cost
T
Threat
Three-point estimating
Time-phased budget
Tolerance
Tranche
Triangular average
U
Unit rate
V
Variable cost
About this lesson