Project Cost and Resources

Learn how to work out what a project will cost and what it needs to get done. Identify the kinds of cost a project incurs and estimate them with analogous, parametric, bottom-up and three-point techniques, stating how accurate each estimate is. Set aside contingency and management reserves, build a time-phased budget and cost baseline that fits the schedule and the funding, and plan the people, equipment and materials the work requires, including leveling and smoothing when demand is too high. Finish by assigning clear responsibilities with a RACI matrix and deciding which goods and services to buy from outside suppliers.

BeginnerLesson 6 of 9 in Project Management Foundations Course

What you will learn

  1. Identify every kind of cost a project incurs and turn the planned work into cost estimates, choosing a technique that fits the information available and stating how accurate the result is.
    • Identify the costs a project incurs
      Recognize the kinds of cost a project spends money on, from labor and materials to overheads, and the distinctions that change how each one is estimated.
    • Plan estimates and judge their accuracy
      Explain why early estimates are ranges, describe how accuracy improves as the project is defined, and choose an estimating technique that fits the information available.
    • Estimate top-down with analogous and parametric techniques
      Produce quick whole-project or large-item estimates from past projects and from cost rates, and recognize when these top-down figures can be trusted.
    • Estimate bottom-up and with three-point ranges
      Build a detailed estimate by costing each work package from its resources and quantities, and express uncertain costs with optimistic, most likely and pessimistic values.
  2. Separate the money set aside for identified risks from the money held for the unforeseen, size each reserve with a clear method, and control how reserves are used.
    • Distinguish contingency reserves from management reserves
      Define the two kinds of reserve, show how they combine with the work estimates into the cost baseline and the project budget, and know who controls each one.
    • Size reserves and control their use
      Calculate a contingency reserve from risk data, set a management reserve, and follow the right steps when a risk occurs or an unforeseen problem appears.
  3. Combine the estimates into an approved budget, spread it over time to match the schedule and the available funding, and protect the resulting cost baseline with change control.
    • Aggregate estimates into a project budget
      Roll the cost estimates up through the work breakdown structure, add reserves at the right levels, and check that the budget is complete before it is approved.
    • Time-phase the budget and plan funding
      Spread the budget over the schedule, read the resulting S-curve, and adjust the timing of work so that spending stays within the funding available in each period.
    • Approve and protect the cost baseline
      Explain what the cost baseline is, how it differs from the budget and from actual spending, and how approved changes, not overruns, are what change it.
  4. Determine which resources each part of the work needs and when they are available, and adjust the plan so that no resource is asked to do more than it can.
    • Identify and plan the resources the work needs
      List the people, equipment and materials each activity requires, with their skills, quantities and availability, and plan how they will be obtained and managed.
    • Balance resource demand with leveling and smoothing
      Read a resource histogram, find overallocations, and resolve them by smoothing within float or by leveling, understanding how each affects the end date and the budget.
  5. Make clear who does, decides, advises and is informed for each piece of work, and decide which goods and services the project needs from outside suppliers.
    • Assign responsibilities with a RACI matrix
      Build a RACI matrix from the project's deliverables and roles, check it for gaps and conflicts, and use it to prevent confusion about who does and who decides.
    • Identify procurement needs and make-or-buy decisions
      Decide which goods and services the project should obtain from outside, compare making with buying or renting, and describe what is needed clearly and early enough for the schedule and budget.

Project Cost and Resources study guide

5 chapters

1

Estimate what a project will cost

Cost planning turns the work a project promises into a reasoned forecast of money needed. Start by identifying the kinds of cost, then match the estimating method to how much is known about the work. Quantities, rates, comparable projects and realistic ranges each provide different evidence. Worked calculations show how to keep effort separate from duration and how to carry uncertainty into an estimate without hiding it.

1.1 Identify the costs a project incurs

A project estimate starts with the resources the work will consume. People, materials and equipment are obvious costs; licenses, insurance, training, travel and project management time are easier to miss. Classifying costs helps you choose the right calculation for each one.

Classify costs in two ways

Direct costs can be charged to this project, such as its contractor fees or staff hours. Indirect costs, such as shared IT support and accounting, reach the project through an overhead allocation. State whether that allocation is included. If overhead is already in a labor rate, adding it again as a separate charge counts it twice.

Fixed and variable describe a different feature: how a cost changes with quantity. A venue fee of $6,000 is fixed across the planned attendance range. Catering at $45 per attendee is variable. For 120 people, catering is $5,400 and the total is $11,400. For 200, catering is $9,000 and the total is $15,000. A cost can be both direct and fixed; these labels answer different questions.

Price the effort, then check the duration

Labor cost equals person-hours multiplied by the burdened rate, which includes the employer's extra costs. Base pay of $40 per hour with a 35% load gives $40 × 1.35 = $54 per hour. A 120-person-hour task therefore costs $6,480.

If three people each work eight hours per day, they provide 24 person-hours daily. The task takes 120 ÷ 24 = 5 working days. One person takes 15 days but still supplies 120 hours. This comparison assumes the work can be shared without changing total effort. Equipment rented by the day behaves differently: a longer duration means more rental days.

Look beyond the purchase

A one-time installation cost and recurring support fees belong to different periods. Life-cycle cost adds the initial cost, operation, maintenance, replacement and disposal over the period being evaluated, then subtracts residual value.

For five years, system A costs $50,000 plus $8,000 a year: $90,000. System B costs $35,000 plus $14,000 a year: $105,000. Neither has replacement, disposal or residual value in this comparison. B has the lower initial cost but the higher five-year cost.

Keep decision figures distinct

A supplier's price becomes the buying project's cost. If the supplier spends $20,000 and adds a 15% markup on cost, the price is $23,000. A 15% profit margin on the selling price needs $20,000 ÷ 0.85, or about $23,529.41. Markup and margin use different denominators.

A sunk cost is already spent and unrecoverable. After spending $30,000 on a design, a team can finish it for another $25,000 or obtain the same result through a new approach for $18,000. The forward-looking comparison is $25,000 against $18,000; the past $30,000 cannot be saved by either choice.

Finally, attach a currency and price date to the estimate. Escalation allows for expected price increases: materials worth $100,000 today become $104,000 after an expected 4% increase over one year.

Key Takeaways

  • Direct and indirect describe how costs are charged; fixed and variable describe how they change.
  • Labor cost follows effort at the burdened rate; daily rental follows duration.
  • Compare life-cycle costs over the same period.
  • Markup is a share of cost; margin is a share of price.
  • Exclude unrecoverable past spending from future choices.
  • State currency and price date, including expected escalation.

1.2 Plan estimates and judge their accuracy

An estimate expresses what the project is likely to cost with the information available now. Its usefulness depends on showing both the figure and the uncertainty around it. A detailed-looking number can still rest on very rough knowledge.

Let the range follow the scope

Early requirements leave many choices open. As the design and work breakdown structure become clearer, more quantities and rates can be checked. The estimating funnel pictures this narrowing range. Progressive elaboration means refining the plan as knowledge grows; it does not mean quietly replacing earlier figures without a record.

Common estimate classes illustrate the change:

ClassTypical stageCommon illustrative range
Rough order of magnitude (ROM)Initiation−25% to +75%
BudgetMain deliverables known−10% to +25%
DefinitiveDetailed work packages−5% to +10%

Organizations and industries define their own ranges; some use ±50% for ROM. Read the range attached to the estimate you are reviewing. For a $200,000 ROM at −25% to +75%, the lower value is $200,000 × 0.75 = $150,000. The upper value is $200,000 × 1.75 = $350,000. Using 1.25 for the upper multiplier would misread the asymmetric range.

A $240,000 definitive estimate at −5% to +10% spans $228,000 to $264,000. The narrower band reflects greater scope definition, not just a later date on the calendar.

Choose a method the evidence can support

With little detail, analogous estimating uses a similar completed project, while parametric estimating uses a measurable quantity and a reliable cost rate. With detailed work packages, bottom-up estimating prices their resources and adds the results. Three-point estimating examines an uncertain item through optimistic, most likely and pessimistic values. Supplier quotes support purchased items. Comparing two suitable methods can expose a missing cost or a poor assumption.

Ask the people who know or will do the work to help. Past actual costs, expert judgment and supplier information provide different kinds of evidence. Rolling-wave planning keeps near-term work detailed and later work broader until enough is known to price it properly.

Record the basis and keep the estimate honest

The basis of estimate records the method, data sources, assumptions, exclusions and expected range. For example: "Current supplier quotes; installation included; annual support excluded; prices valid through November." That record lets someone update a rate without having to guess what the old total contained.

An estimate is different from a target, which is the desired figure, and a commitment, which the team agrees to deliver. If analysis gives $180,000 and the sponsor wants $150,000, investigate a smaller scope or a different approach. Editing the estimate down by $30,000 removes useful information.

Counter optimism with past results and realistic ranges. Check the work breakdown structure for testing, training and handover. Keep risk allowances visible instead of hiding padding in every task. In adaptive work, story points compare relative work size; the money estimate commonly comes from the stable team's cost over the planned iterations.

Key Takeaways

  • Estimate ranges narrow as scope becomes better defined.
  • Choose the technique from the available evidence.
  • Document methods, assumptions, sources, exclusions and range.
  • Keep the estimate separate from the desired target and agreed commitment.
  • Detail near-term work and refine later work through rolling-wave planning.

1.3 Estimate top-down with analogous and parametric techniques

You can estimate before every activity has been defined, provided the comparison or cost model is credible. Two top-down techniques use different starting points: a similar project's actual result, or a measured quantity with a supported unit rate.

Adjust a genuinely similar project

Analogous estimating starts with the actual final cost of a past project. Ask what makes it comparable: scope, technology, location, team experience and complexity. Then adjust for known differences. A budget that the old project exceeded is weaker evidence than what that project actually cost.

A previous intranet cost $120,000. The new one is judged 25% more complex, and relevant prices have risen 6% since the earlier work:

  1. Adjust complexity: $120,000 × 1.25 = $150,000.
  2. Adjust prices: $150,000 × 1.06 = $159,000.

The second percentage applies to the adjusted amount. Adding 25% and 6% and applying 31% once gives a different result. Record why the 25% adjustment is reasonable; the arithmetic cannot establish similarity by itself.

Analogous estimating is quick and inexpensive, which makes it useful during initiation. Its weakness is reliance on judgment and a small comparison base. An experienced team can still choose a misleading comparison if the new technology changes the work substantially.

Use a measurable cost driver

Parametric estimating uses a relationship between quantity and cost. A simple model is:

C=F+qr

Here, the fixed amount is F, quantity is q and cost per unit is r. Keep quantities and rates in matching units. An office fit-out of 300 m² at $900 per m² costs $270,000. The area units cancel in the calculation, leaving money.

A training rollout has an $8,000 fixed design cost plus $1,200 per participant. For 45 participants, the variable cost is $54,000 and the total is $62,000. Multiplying the whole total by attendance would make the fixed design cost grow incorrectly.

A rate is useful when its historical data are accurate, the parameter is measurable and the cost relationship holds across the range used. A cost per user from 50-user projects may be unreliable for 5,000 users. Large projects may introduce new coordination costs or economies of scale. A formula does not remove the need to examine its data.

Cross-check before choosing a figure

A similar office fit-out cost $250,000 for 280 m². Its implied rate is about $892.86 per m². That is close to the $900 rate, so it supports the order of magnitude of the $270,000 estimate for 300 m².

If the two methods differ widely, investigate scope, inclusions, location, price dates and data quality before averaging them. One estimate might include furniture while the other includes only building work. Averaging incompatible totals hides the reason for the gap.

Key Takeaways

  • Analogous estimates adjust actual costs from comparable completed projects.
  • Apply successive percentage adjustments to the updated amount.
  • Parametric estimates use measured quantities and supported unit rates.
  • Check that rates remain valid at the new scale.
  • Investigate large differences between estimates before selecting a figure.

1.4 Estimate bottom-up and with three-point ranges

Detailed scope lets you build costs from the work itself. Uncertain items still need a range, even inside a detailed estimate. Bottom-up and three-point estimating therefore often work together.

Cost each work package

Bottom-up, or analytical, estimating prices the resources for activities or work packages, then adds them through the work breakdown structure. For "Install office network":

ResourceCalculationCost
Technicians3 × 40 hours × $65/hour$7,800
Switches4 × $1,150$4,600
Cable400 m × $2.55/m$1,020
Test equipment5 days × $90/day$450
Total$13,870

Three technicians each work 40 hours, so effort is 120 person-hours. Applying the rate to only 40 hours would omit two people's work. The equipment uses a daily rate, so its quantity is rental days, not labor hours.

This method is strongest when the scope and resource quantities are well defined. It takes time, and detail cannot rescue an incomplete work breakdown structure. Check project management, testing, integration, training and handover. Assign each cost once so it is neither omitted nor included in two packages. Keep risk allowances visible.

Describe an uncertain item with three values

The optimistic value O assumes things go well. The most likely value M describes the most plausible outcome. The pessimistic value P allows for realistic problems. All three describe the same work and scope; a smaller deliverable is not an optimistic cost for the original deliverable.

A triangular average gives equal weight to all three:

E=O+M+P3

The PERT, or beta, average gives four times as much weight to the most likely value:

E=O+4M+P6

For an interface with O = $18,000, M = $24,000 and P = $42,000:

  • Triangular: ($18,000 + $24,000 + $42,000) ÷ 3 = $28,000.
  • PERT: ($18,000 + $96,000 + $42,000) ÷ 6 = $26,000.

Use a divisor of 3 for three equal weights and 6 for the PERT weights of 1, 4 and 1. Dividing the weighted PERT total by 3 would double the intended answer.

Read the spread as well as the average

A rough PERT standard deviation is:

σ≈P−O6

Here, ($42,000 − $18,000) ÷ 6 = $4,000. The long pessimistic side pulls both averages above the $24,000 most likely value. Using M alone would leave a $2,000 gap against the PERT expectation.

A wider spread points to work worth investigating in the risk register and reserve analysis. The expected value is a planning figure, not a guaranteed final invoice. When adding contingency for an uncertain item, check whether its expected-cost allowance is already included in the base estimate, so the same uncertainty is not counted twice.

Key Takeaways

  • Bottom-up estimates price resources and aggregate through the work breakdown structure.
  • Detailed estimates still need complete scope and checks for double counting.
  • Three-point values describe the same work under different outcomes.
  • Triangular averages use equal weights; PERT weights the most likely value four times.
  • The PERT spread estimate is (P − O) ÷ 6.
  • Avoid counting the same uncertainty in both an expected estimate and an added reserve.
2

Plan reserves for uncertainty

A project can plan the work carefully and still face uncertain costs. Visible reserves show how much money protects against those risks and who may authorize its use. Separate identified risks from unforeseen work within scope, then size and track the reserves with a clear method. The office move connects risk probabilities to a contingency amount and shows how a management reserve transfer changes the budget's internal split.

2.1 Distinguish contingency reserves from management reserves

Reserves make uncertainty visible in the budget. They let the team discuss likely risk costs without quietly increasing every task estimate. The two main reserves differ in purpose, position and control.

Put each reserve in the right place
ReserveWhat it coversWhere it sitsWho normally controls it
ContingencyIdentified risksInside the cost baselineProject manager, within agreed rules
ManagementUnforeseen work within scopeOutside the baseline, inside the project budgetSponsor or senior management

An identified supplier delay is a known-unknown: the team knows the event is possible but does not know whether it will occur. A contingency reserve provides for that kind of uncertainty. Management reserve covers an unforeseen in-scope problem, often called an unknown-unknown. Using it requires management approval and a change to the cost baseline.

For the office move, planned work costs $120,000. Add $8,000 contingency to obtain a $128,000 cost baseline. Add $6,000 management reserve to obtain the $134,000 project budget:

120,000+8,000=128,000 128,000+6,000=134,000

The $6,000 is authorized funding held outside the performance reference. Putting it inside the baseline at the start would blur that distinction.

Separate uncertainty from extra scope

A customer requesting an additional deliverable has changed the scope. Neither reserve is a general fund for extras. Record the request and assess its effects before approval. The change authority decides how to fund it: existing authorized funds, a trade-off that removes other work, a separate change budget or additional funding.

Some methods call money for planned risk responses a risk budget, and hold a change budget for approved changes. These names serve different purposes; a change budget does not replace the decision to approve the scope change.

Connect money and time

A supplier delay can require both extra rental payments and extra days. Plan the cost allowance with the schedule reserve, or time buffer, for identified schedule risks. A cash allowance alone cannot recover days lost from the schedule.

A tolerance defines how far performance may deviate before the next management level must decide. A $50,000 stage budget with ±10% cost tolerance has limits of $45,000 and $55,000. A $57,000 forecast exceeds the upper limit and must be escalated. The tolerance describes authority; it does not add $5,000 to the budget or establish a reserve.

Keep reserve amounts and ownership explicit. If every task owner adds an unexplained allowance, the total risk provision becomes hard to see and may be repeated. A visible reserve lets decision makers review how much protection the project has and who can authorize its use.

Key Takeaways

  • Contingency covers identified risks and belongs inside the cost baseline.
  • Management reserve covers unforeseen in-scope work and sits outside the baseline.
  • Work estimates plus contingency form the baseline; management reserve completes the budget.
  • Extra scope needs change control and a funding decision.
  • Tolerance sets an escalation limit; it is not extra money.

2.2 Size reserves and control their use

A reserve needs a reason for its size and a rule for its use. Start with the uncertainty being covered, then choose a method that makes that uncertainty visible to the people approving the budget.

Calculate a risk-based contingency

A percentage allowance is quick: 10% of $120,000 gives $12,000. It does not show which risks produced that amount. Expected monetary value (EMV) ties the calculation to the risk register:

EMV=probability×cost impact

Treat threats as cost additions and opportunities as reductions. For the office move:

EventProbability and impactContribution
Supplier delay30% × $20,000$6,000
Fit-out rework20% × $15,000$3,000
Bulk discount25% × $4,000 saving−$1,000

The net contingency is $6,000 + $3,000 − $1,000 = $8,000. The discount reduces expected cost, so adding its $1,000 contribution would reverse its effect.

EMV is a pooled planning amount. If the supplier delay happens, its cost is $20,000, not $6,000. Probability weights the planning calculation; it does not reduce the invoice after the event occurs. The $8,000 total is not a guarantee that every combination of events can be paid for. The desired confidence and the remaining exposure matter when judging adequacy.

Use other evidence without double counting

Three-point analysis can show an allowance above a base estimate. For an item with M = $24,000 and PERT expectation $26,000, a plan can hold $24,000 for the work and $2,000 in contingency. If $26,000 is already in the base, do not add that same $2,000 again. Larger projects may use simulation, such as Monte Carlo analysis, to examine combined uncertainty and select a confidence level.

Management reserve is often set by organizational policy, with larger allowances for unfamiliar or complex work. Record the percentage, amount and reasoning. No single percentage fits every project.

Record transfers and remaining exposure

When an identified risk occurs, follow the agreed authorization rules, transfer the approved contingency amount to the affected work and log it. This allocates money already inside the cost baseline. Review whether risks have expired and whether unused amounts should be retained or released under the plan.

For a separate unforeseen in-scope problem costing $4,500, the office move's sponsor approves a transfer from management reserve. The baseline rises from $128,000 to $132,500. Management reserve falls from $6,000 to $1,500. The project budget remains $134,000 because this is a transfer within existing funding.

Reserve analysis compares what remains with the risks still ahead. Using half the reserve when only a small part of the risk has passed is a reason to investigate. Cutting reserves merely to secure approval hides exposure, and using contingency to cover poor performance without reporting it hides the cause of the extra cost.

Key Takeaways

  • EMV multiplies probability by cost impact; savings reduce the total.
  • An event that occurs costs its full impact, not its probability-weighted amount.
  • Check whether expected-cost uplifts are already in the base estimate.
  • Management reserve transfers raise the baseline but leave total funding unchanged.
  • Review reserve remaining against remaining risk.
  • Log reserve use and follow its authorization rules.
3

Build the budget and cost baseline

A budget must be complete, authorized and available at the right time. Combine the work estimates, place costs against the schedule and check when cash will be needed. The office move shows why a month can exceed its funding limit even when the total budget is sufficient. Keeping the approved baseline separate from actual cost and the latest forecast makes changes visible and preserves a useful reference for decisions.

3.1 Aggregate estimates into a project budget

Estimates describe the cost of pieces of work. Determining the budget joins those pieces, adds the reserves in the right places and establishes an amount that the organization can authorize. The work breakdown structure provides the route for adding costs without losing their origin.

Roll costs upward

Activity estimates add to work packages. Related work packages add to control accounts, and the accounts add to the project total. A control account joins scope, schedule and budget under a responsible manager so performance can be reviewed at a useful level.

Add contingency where the relevant risk is managed: at a work package, a control account or project level. Check whether a lower-level total already contains it before adding a project allowance. The resulting total is the cost baseline. Management reserve is added outside it to reach the project budget.

The office move has four work estimates:

WorkEstimate
Plan and design the layout$12,000
Fit out the office$64,000
Install IT network and equipment$28,000
Move and set up$16,000
Planned work total$120,000

The first two packages total $76,000. Adding IT gives $104,000; adding the move gives $120,000. Contingency of $8,000 produces a $128,000 baseline. Management reserve of $6,000 brings the authorized project budget to $134,000.

Use the right breakdown for the question
StructureWhat it organizes
Work breakdown structure (WBS)Deliverables and work
Cost breakdown structure (CBS)Costs by work element or cost type
Organizational breakdown structure (OBS)Organizational units and roles
Resource breakdown structure (RBS)Resource categories and types

The CBS can connect project costs to accounting codes, such as labor, equipment and services. A WBS view answers "What result does this money buy?" A cost-type view answers "How much are we spending on labor?" These are views of the same costs, not totals to add together.

Check the whole budget before approval

Use the estimates and their basis, schedule, risk register, resource calendars and supplier agreements together. Check that every work package has a cost and that project management, quality checks, training and handover are included. Align currency and price dates, confirm the reserve treatment and explain major differences from earlier top-down estimates.

Sponsor or governance approval authorizes the budget. Cash may still be released in tranches, such as one phase at a time after a review. Approval of the total and release of the next phase's money are separate decisions.

Budget for a stable adaptive team

An adaptive team costing $54,000 per two-week iteration needs $540,000 for ten iterations. That funds a period of team capacity. The team prioritizes scope to fit the time and money available and reviews its forecast after each iteration. Multiplying team cost by iterations does not guarantee that every requested feature fits those iterations.

Key Takeaways

  • Aggregate activity costs through work packages and control accounts.
  • Add each reserve once, at the level where it is managed.
  • WBS, CBS, OBS and RBS organize different views of the project.
  • Check completeness, price dates and consistency before approval.
  • A stable adaptive team budget follows cost per iteration × iterations.

3.2 Time-phase the budget and plan funding

A total budget cannot show whether money will be available on the day a payment is due. Time-phasing connects cost to the schedule, and the funding plan connects that timing to the cash the project can use.

Place costs where work happens

A time-phased budget allocates planned cost by week, month or quarter. Use the schedule and each cost's actual pattern. Staff effort may be spread across an activity, while materials may be charged on delivery and a final supplier payment may wait for acceptance.

For the office move, design costs $12,000 in month 1. Fit-out costs $64,000 evenly across months 2 and 3. IT costs $28,000 in month 3, and moving costs $16,000 in month 4.

MonthPlanned work costCumulative work cost
1$12,000$12,000
2$32,000$44,000
3$60,000$104,000
4$16,000$120,000

These figures phase the work estimates. The full $128,000 baseline also includes $8,000 contingency, allocated according to the risk plan. Dividing $120,000 equally into four months would produce neat figures but would ignore when the work occurs.

Cumulative planned cost often forms an S-curve: slow growth during early planning, faster growth when work overlaps, then slower growth during finishing. The exact shape follows the plan; it need not be a perfect S. The endpoint is the total planned cost represented by the curve.

Separate incurred cost from cash paid

Cost is incurred when work is performed or goods are received. Cash leaves when payment is due. Equipment received in month 2 and paid 30 days later creates month 2 incurred cost and month 3 cash outflow. Performance reporting and funding planning therefore need different timing views.

Funding requirements show both the amount and timing of needed cash, based on the baseline and expected management reserve use. Funding released at phase gates creates a staircase-shaped cumulative line. Available cumulative funding must cover cumulative cash outflows when payments are due.

Reconcile a period that exceeds its limit

Suppose payments in the office example occur in the same months as the displayed costs, and each month has a $50,000 limit. Month 3 is $10,000 too high. The schedule allows a $10,000 IT equipment purchase in month 2: its predecessors are complete and the supplier can deliver early.

Move that purchase forward. The new monthly totals are $12,000, $42,000, $50,000 and $16,000. Their sum is still $120,000; their cumulative totals are $12,000, $54,000, $104,000 and $120,000. Timing has changed, not the amount of work.

This is funding limit reconciliation. Before moving work earlier, check dependencies and earlier resource availability. Before delaying it, check float and the critical path. Float describes allowable delay; it does not establish that earlier work is possible. Update both the schedule and the time-phased cost and cash views after an agreed timing change.

Key Takeaways

  • Time-phase costs from the schedule and the actual cost pattern.
  • Cumulative amounts add each period to all previous periods.
  • Funding plans follow cash payments; cost reports follow incurred costs.
  • Reconcile period limits while respecting dependencies, float and availability.
  • The work-cost total excludes the separate contingency allocation shown in the full baseline.

3.3 Approve and protect the cost baseline

The approved cost plan gives the project a stable reference for judging what changes during delivery. Keeping that reference separate from forecasts makes both the original agreement and the current outlook visible.

Know which figure answers which question
FigureQuestion it answers
Cost baselineWhat spending plan was approved, including contingency?
Project budgetWhat total funding is authorized, including management reserve?
FundingHow much money has actually been made available?
Actual costWhat cost has been incurred for work performed so far?
ForecastWhat do we now expect the final total to be?

The cost baseline is approved and time-phased. It includes contingency and excludes management reserve. For the office move, it is $128,000, while the project budget is $134,000. An unpaid invoice for work already performed contributes to actual cost; the payment belongs to the cash plan when due.

The scope, schedule and cost baselines together form the performance measurement baseline. A new deliverable can affect all three. Updating the cost alone may leave a schedule that has no time for the extra work.

Change the baseline through an authorized decision

Suppose the client requests an extra meeting room costing $9,500. The project manager records the request and assesses scope, cost, schedule and risk effects. The change authority approves it with new funding. The cost baseline becomes $128,000 + $9,500 = $137,500. The project budget becomes $134,000 + $9,500 = $143,500, with the $6,000 management reserve unchanged.

Record the approval, revised amounts, affected work and effective version, then communicate the change. A baseline changes only through formal change control. An informal email saying "we will probably need more" updates neither authority nor the agreed reference.

This scope-change example starts from the original office budget. It is a different decision from transferring existing management reserve into the baseline: a transfer changes the split within the budget, while newly approved funding increases the total.

Update forecasts without hiding performance

A forecast changes when new information changes the expected outcome. If costs rise, report the forecast and investigate the cause while preserving the approved baseline. Moving the baseline to the latest actual or forecast amount simply to remove an overrun erases the comparison. A formally approved scope change or replan can establish a revised baseline, with the decision and earlier reference retained.

After the office move's timing adjustment, planned cumulative work cost at month 2 is $54,000. Actual cost of $51,000 alone cannot establish a saving. The team may have completed the planned work more cheaply, or it may have completed less work. Look at progress as well as spending before interpreting the difference.

An unused budget balance does not require spending. The baseline authorizes and measures the planned work; it is not a target to exhaust by buying unnecessary items.

Key Takeaways

  • The cost baseline is the approved time-phased plan, including contingency.
  • Keep baseline, total budget, available funding, actual cost and forecast distinct.
  • Assess scope, schedule, cost and risk before approving a change.
  • New funding raises the total budget; a reserve transfer reallocates existing funds.
  • An updated forecast does not by itself change the baseline.
  • Interpret spending together with work completed.
4

Plan the people, equipment and materials

People, equipment and materials need to be available when scheduled work calls for them. Resource planning turns activities into quantities, skill requirements and calendar commitments. Comparing total demand with real capacity reveals conflicts that are hidden when tasks are checked separately. The choice between smoothing and leveling then connects those conflicts to the finish date, the critical path and time-dependent costs.

4.1 Identify and plan the resources the work needs

A resource plan connects each activity to the people, equipment, materials and facilities it needs. A cost estimate may contain enough money for a technician but still fail if the right technician is unavailable when the work must happen.

Specify what the activity needs

Start with the activity list or work breakdown structure. For each activity, record resource type, skill or specification, quantity, timing and source. "Two people" is less useful than "two network technicians with the required certification, available for three days." Those requirements feed both the duration estimate and the cost estimate.

A resource breakdown structure (RBS) groups resources by category and type. Labor might contain painters and technicians; equipment might contain lifts and test meters; materials might contain paint and cable. This checks for omissions and supports totals by resource type. It does not show when those resources will be free.

Turn output into quantities

Suppose 450 m² of office walls need two coats of paint. Coverage is 10 m² per liter per coat. The coverage requirement is 450 × 2 = 900 m²-coats. Divide by 10 to obtain 90 liters. Add a 10% waste allowance: 90 × 1.10 = 99 liters. With whole-liter ordering, order 99 liters. Round upward only after applying all allowances when a fractional amount remains.

Three painters working five days at eight hours per day provide 120 person-hours. At $38 per hour, labor costs $4,560. Paint quantity follows area, coats and coverage; labor follows estimated effort. These quantities use different units and cannot substitute for each other.

Check real availability

A resource calendar records working days, holidays, part-time hours, other project commitments and equipment maintenance. A person assigned 50% of a 40-hour week supplies 20 hours. A 60-person-hour task takes three weeks at that availability, not the one and a half weeks implied by a full-time assumption.

Check skill as well as hours. A free painter cannot take over work that needs a qualified electrician. More people may also create extra coordination or training work, so doubling headcount need not halve duration.

Plan acquisition, care and release

Internal staff assignments usually need agreement with functional managers. External hiring, rental and purchases create procurement needs. Work backward from the required date using selection, approval and delivery lead times; money in the budget does not make a scarce item arrive sooner.

The resource management plan describes how resources are identified, acquired, managed and released. Include responsibilities, training, delivery, storage and logistics. An early materials delivery may require secure storage. Just-in-time delivery reduces storage needs but makes a late delivery more disruptive to scheduled work.

Review availability across the whole project and other commitments before confirming assignments. A calendar with no allowance for meetings or operational support can overstate the capacity the team can actually contribute.

Key Takeaways

  • Activity resource estimates specify type, skill, quantity and timing.
  • Resource quantities feed both duration and cost estimates.
  • Use calendars to calculate actual available capacity.
  • Include material allowances and round purchase quantities at the end.
  • Plan acquisition, training, logistics and release with the relevant managers.

4.2 Balance resource demand with leveling and smoothing

Resource problems often appear only when activities are viewed together. A schedule can give every task a sensible individual assignment and still demand more people on the same day than the organization has.

Find the peak demand

A resource histogram shows demand per period as bars, usually against an availability line. Add demand for the same resource across every concurrent activity, including commitments to other projects. Overallocation occurs when total demand exceeds available capacity.

Three electricians are available. Task A needs two on days 1–3 and is on the critical path. Task B needs two on days 1–2. Demand on days 1 and 2 is four, exceeding capacity by one. The project cannot carry out both tasks as scheduled with those three electricians.

Smooth within float

Resource smoothing moves activities within their float, preserving the end date. If B has three days of total float, delay its start from day 1 to day 4. It now runs on days 4–5, after A ends. Its start moved three days, using all its float. Demand becomes two electricians on each day from 1 through 5.

Smoothing cannot always remove every overload: some tasks have too little float to avoid a busy period.

Level to respect a fixed resource limit

Resource leveling changes dates to respect availability, even when that changes the end date. Now suppose B has only one day of total float. The earliest feasible slot is still days 4–5. Its three-day delay exceeds float by two days, so the project finishes two days later in this network, with B now critical.

ApproachMain constraintDate effect
SmoothingPreserve the finish dateStay within float
LevelingRespect resource limitsFinish may move; critical path may change

These are also called time-limited and resource-limited scheduling. Leveling can finish without a delay if enough room exists; the distinction is that it permits the resource limit to drive the dates.

Compare alternatives and their costs

If the end date cannot move, consider borrowing or hiring capacity, overtime, splitting work where feasible, changing the skill mix or an approved scope reduction. Each option needs a cost, quality and risk check.

An electrician at $60 per hour earns $90 at time-and-a-half. Sixteen overtime hours cost $1,440, compared with $960 at the ordinary rate: an extra $480. Compare that premium with the costs of a longer project, such as additional daily rental. The cheapest hourly option may not produce the cheapest overall plan.

After any timing adjustment, recalculate resource demand, check the critical path and update the time-phased budget and funding plan. Moving an activity to another week moves its costs; extending the project can also increase time-dependent costs.

Key Takeaways

  • Add demand across concurrent work before comparing it with capacity.
  • Smoothing stays within float and protects the end date.
  • Leveling respects resource limits and may change the finish or critical path.
  • Compare overtime and added capacity with the full cost of delay.
  • Update resource, schedule, cost and cash views after moving work.
5

Assign responsibilities and identify what to buy

A workable project plan makes both responsibility and outside supply clear. A RACI matrix identifies who performs work, who approves it and who needs input or updates. Procurement planning identifies what the organization must buy or rent, how it compares with internal delivery and how early the process must start. Together, these decisions connect deliverables to people with authority and suppliers with clear acceptance requirements.

5.1 Assign responsibilities with a RACI matrix

Clear responsibilities prevent a deliverable from waiting while several people assume someone else will decide. A responsibility matrix links work to roles so the team can agree who acts and who has the authority to approve the result.

Read the four RACI letters

A responsibility assignment matrix (RAM) places deliverables, work packages or activities in rows and people or roles in columns. RACI is a common form:

LetterRole in the work
R — ResponsiblePerforms the work
A — AccountableOwns the result, makes the final decision and signs off
C — ConsultedGives input through two-way communication
I — InformedReceives updates through one-way communication

Each row needs exactly one A and at least one R. One person may hold both A and R. Assign A to a single person or role with real decision authority; "the team" leaves approval ownership unclear.

For the office move's "Approved floor plan," the sponsor is A and the facilities manager is R. The IT lead and department heads are C because their input affects the plan. All staff are I. Being informed about the approved layout does not make every staff member a design reviewer.

For "Network installed and tested," the IT lead is A, the contractor is R, the facilities manager is C and the project manager is I. An outside supplier can perform the work while an internal person remains answerable for acceptance.

Build the matrix with the people involved

Take the deliverables or work packages from the work breakdown structure. List the roles involved, agree the letters with the team and relevant managers, then check rows and columns before sharing the matrix. A high-level RAM can connect work packages with organizational units from the OBS; a detailed matrix can name the individuals carrying out activities.

Use roles when the matrix needs to remain useful after staffing changes. Make sure each role still points to an identified decision maker in the current project. Update the matrix when scope or responsibilities change.

Check across and down

Read across a row to find a missing A, competing As, missing R or too many Cs. No A leaves the decision unowned; two As can create conflicting approvals; no R leaves the work undone. Every consulted role creates a two-way communication demand, so include people whose input is needed.

Read down a column to spot a possible workload or decision bottleneck. Many Rs suggest a person may have too much to do; many As suggest approvals may queue behind one person. Check the resource calendar to establish whether the assignments actually overlap. RACI does not contain workload timing.

C and I assignments also inform the communication plan: consulted people need opportunities to respond, while informed people need appropriate updates. A variant, RASCI, adds S for Support: people who help the responsible person. Agree the legend so everyone reads the same letter in the same way.

Key Takeaways

  • Each RACI row has exactly one A and at least one R.
  • R performs the work; A owns and approves the result.
  • C requires two-way input; I receives one-way updates.
  • Check rows for gaps and conflicts, and columns for possible bottlenecks.
  • Use resource calendars to check workload timing; keep the matrix current.

5.2 Identify procurement needs and make-or-buy decisions

Some resources come from inside the organization; others require an outside supplier. Identifying those needs early gives the project time to decide what to obtain, compare the alternatives and describe a result a seller can price.

Find the procurement needs

Review the work breakdown structure, resource requirements and missing skills. Equipment rental, specialist installation and bought materials are procurement needs. Check purchasing policies, including which purchases must go through a central team. Supplier selection, approval and delivery all need time in the schedule.

Make-or-buy analysis compares internal work with outside supply, or buying with renting. Include labor at burdened rates, equipment, maintenance and supervision for in-house work. On the supplier side, include the price, delivery, setup and management effort. Compare equivalent quality, quantities and timing.

Cost is only part of the decision. Available skills and capacity, quality control, confidentiality, delivery risk and long-term ownership may change the choice. An apparently cheaper internal option is not feasible if the required team is already fully committed.

Work out buying and renting

A machine is needed for 14 months. Buying costs $24,000 plus $200 monthly maintenance. Renting costs $1,400 per month. Ignoring resale for this first comparison:

  • Buy: $24,000 + 14 × $200 = $26,800.
  • Rent: 14 × $1,400 = $19,600.

Renting costs $7,200 less. To find the duration at which the costs are equal, let m be months:

24,000+200m=1,400m 24,000=1,200m m=20

Before 20 months, renting is cheaper under these assumptions; after 20, buying is cheaper. At 20 months the two totals match.

Now include an $8,000 resale value after the 14-month project. Buying's net cost becomes $26,800 − $8,000 = $18,800, which is $800 less than renting. State resale assumptions clearly because this one changes the decision. Include only future relevant costs; unrecoverable past spending does not change which option is better from now on.

Define the result and its timing

A procurement statement of work (SOW) tells potential sellers what to supply. Include quantities, specifications or performance needs, quality standards, required date and location, acceptance criteria and reporting. "Provide suitable desks" is vague. "Supply 20 desks to the new office by May 6, assembled, with dimensions and finish matching the approved specification" gives the seller a basis for pricing and acceptance.

Lead time includes selection and approval as well as production and delivery. Furniture requiring three weeks for selection and approval, then ten weeks for manufacture and delivery, needs the process to start at least 13 weeks before use. Include purchase, delivery, applicable taxes and supplier-management costs in the estimate.

A procurement strategy sets the high-level approach: one supplier or several, selection approach, timing of payments and delivery arrangements. Agree it with purchasing and legal specialists under organizational policy. Even when a supplier performs the work, an internal accountable person oversees acceptance.

Key Takeaways

  • Compare complete relevant costs and non-cost constraints in make-or-buy decisions.
  • Resale value can reverse a buy-versus-rent decision.
  • A procurement SOW defines deliverables, timing, quality and acceptance.
  • Lead time includes selection, approval, production and delivery.
  • External delivery still needs internal accountability.

Project Cost and Resources examples

5 Walkthroughs

1

Build and test a cost estimate

18 steps
Move from resource costs and estimate ranges to top-down, bottom-up and three-point calculations.
  1. 1
    IntroductionStart with the work, then choose the evidence

    An estimate answers two linked questions: "What resources will the work consume?" and "How well can we price them now?"

    A clear scope supports detailed quantities, priced bottom-up. A rough concept needs broader comparisons, such as analogous estimating and parametric estimating, and wider ranges, so the method fits the evidence. Work through both kinds of evidence, then examine an uncertain item with three-point estimating, without pretending its most likely cost is certain.

  2. 2
    ExplanationAsk how each cost behaves

    Classify each expense in two ways. Direct or indirect describes how it is charged to the project. Fixed or variable describes how it changes with quantity.

    A contractor's setup fee can be direct and fixed. Cable charged per meter is direct and variable. Shared accounting support is indirect. State whether the estimate includes that overhead, and check whether it is already included in the labor rate.

  3. 3
    ExampleTurn base pay into a usable rate

    A technician earns $40 per hour. The employer adds a 35% load for its extra costs, giving $40 × 1.35 = $54 per hour.

    A 120-person-hour task costs 120 × $54 = $6,480. If three people each supply eight hours daily, they provide 24 person-hours a day, so duration is 120 ÷ 24 = 5 working days. The cost follows effort; the duration follows how that effort is scheduled.

  4. 4
    ChallengeSeparate labor effort from rental days

    A task needs 64 person-hours at $50 per hour. Two people each work eight hours daily, and a test device is rented for the whole task at $80 per day. What is the combined cost?

    ---reveal---

    Two people provide 16 hours daily, so duration is four days. Labor costs $3,200 and rental costs $320, giving $3,520. Charging the device for 64 days would confuse person-hours with elapsed rental days.

  5. 5
    Key InsightCompare costs over the same period

    Purchase price can point in the wrong direction when later costs differ. System A costs $50,000 plus $8,000 yearly support; B costs $35,000 plus $14,000 yearly support. Over five years they cost $90,000 and $105,000, with no other ownership costs or residual values.

    Include operation, maintenance, replacement and disposal where relevant, then subtract residual value. Unrecoverable past spending does not change which future option costs less.

  6. 6
    ExplanationMake the range visible

    The estimating funnel narrows as scope and design become clearer. Early ROM estimates commonly illustrate a −25%/+75% range; detailed definitive estimates may use −5%/+10%. Organizations define their own bands.

    Record the method, data, assumptions, exclusions and range in the basis of estimate. A precise-looking total without that record can hide rough quantities or an expired supplier price.

  7. 7
    ExampleCalculate both ends separately

    For a $200,000 ROM with −25%/+75%, calculate the lower endpoint as $200,000 × 0.75 = $150,000. Calculate the upper endpoint as $200,000 × 1.75 = $350,000.

    The band is asymmetric. Subtracting and adding 25% would turn the upper value into $250,000 and discard the stated overrun allowance. Use the two percentages attached to this estimate, not a remembered symmetric range.

  8. 8
    ChallengeRespond to an unaffordable estimate

    A supported estimate is $96,000, but the sponsor's target is $80,000. No scope or rate has changed. Should the estimate become $80,000?

    ---reveal---

    Keep $96,000 as the estimate and discuss a smaller scope, a different approach or more funding. The $80,000 is a target. Replacing the estimate with that target hides the $16,000 gap without changing the work that creates it.

  9. 9
    ExampleAdjust a comparable actual cost

    A completed intranet cost $120,000. The new one is judged 25% more complex, with prices now 6% higher.

    First calculate $120,000 × 1.25 = $150,000. Then calculate $150,000 × 1.06 = $159,000. This is analogous estimating. Its credibility depends on whether the old project's scope and delivery conditions are comparable, not just on multiplying correctly.

  10. 10
    ExampleAdd fixed and per-unit costs

    A training program has a fixed design fee of $8,000 and a cost of $1,200 per participant. For 45 people, the variable cost is $54,000. Add the design fee once to get $62,000.

    This is parametric estimating because participant count drives cost through a supported rate. Check the rate's inclusions and scale: a model drawn from small sessions may need adjustment for a much larger rollout.

  11. 11
    ChallengeInvestigate a large gap

    An analogous estimate for a refurbishment is $70,000. A parametric estimate is $100,000. The methods use the same currency and price date, but their included work has not been compared. What should happen before a figure is selected?

    ---reveal---

    Compare scope and inclusions, then the data and adjustments behind each method. One may include furniture or specialist installation that the other omits. Averaging to $85,000 would conceal that unresolved difference.

  12. 12
    ExplanationPrice the resources in each work package

    A bottom-up estimate builds from the resources needed for defined work. For an office network:

    • Technician effort: 3 × 40 hours × $65 = $7,800.
    • Switches: 4 × $1,150 = $4,600.
    • Cable: 400 m × $2.55 = $1,020.
    • Rental: 5 days × $90 = $450.

    These add to $13,870. Check testing, handover and management effort, and count each expense in only one work package.

  13. 13
    ExplanationDefine three realistic outcomes

    Three-point estimating uses optimistic O, most likely M and pessimistic P costs for the same scope. The pessimistic value reflects realistic problems, not an unlimited disaster.

    For a software interface, O is $18,000, M is $24,000 and P is $42,000. The longer side above M expresses greater exposure to overruns. Changing the deliverable between the three values would mix scope choices with uncertainty.

  14. 14
    ExampleGive each value equal weight

    The triangular average is:

    E=O+M+P3

    For the interface, add $18,000 + $24,000 + $42,000 = $84,000. Divide by three to get $28,000.

    Each value receives equal weight. The result sits above the most likely cost because the pessimistic side extends $18,000 above M, while the optimistic side is only $6,000 below it.

  15. 15
    ExampleGive the most likely cost more weight

    PERT uses:

    E=O+4M+P6

    Four times $24,000 is $96,000. Add $18,000 and $42,000 to get $156,000, then divide by six to obtain $26,000.

    A rough PERT standard deviation is (P − O) ÷ 6, so ($42,000 − $18,000) ÷ 6 = $4,000. The weighting and spread describe different features: central expectation and uncertainty.

  16. 16
    ChallengeCheck the weighting

    A work item has O = $4,000, M = $7,000 and P = $16,000. What is its PERT expected cost?

    ---reveal---

    Four times $7,000 is $28,000. Adding the extremes gives $48,000; dividing by six gives $8,000. The equal-weight average would be $9,000. Using M alone gives $7,000 and misses the expected-cost effect of the long pessimistic side.

  17. 17
    ChallengeChoose detail without losing uncertainty

    The WBS and resource quantities are complete, but one integration item has a wide range. The sponsor asks for a defensible total. How can the estimating methods work together?

    ---reveal---

    Build the defined work bottom-up and examine the uncertain integration item with three-point values. Record the assumptions and range in the basis of estimate. Detail in most packages does not remove the uncertainty concentrated in this one item.

  18. 18
    RecapCheck the estimate before sharing it

    Before presenting an estimate, check four things:

    • Resource quantities and rates describe the full work.
    • The technique fits the available evidence.
    • The range and basis are visible.
    • The total does not count the same work or allowance twice.

    Then compare the supported figure with the target. Any gap is a decision about the work or funding, not a reason to erase the evidence.

2

Build and use visible reserves

10 steps
Calculate a pooled contingency and follow separate rules for identified and unforeseen in-scope risks.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionGive uncertainty a visible place
  2. 2
    ExplanationDistinguish identified from unforeseen risks
  3. 3
    ExampleBuild the two totals
  4. 4
    ChallengeHandle an extra deliverable
  5. 5
    ExplanationWeight impacts before pooling them
  6. 6
    Key InsightAn expected amount is not a discounted invoice
  7. 7
    ChallengeRecalculate a net allowance
  8. 8
    ExampleMove existing funding into the baseline
  9. 9
    ChallengeApply authority and reserve rules together
  10. 10
    RecapReview what is left and what lies ahead
3

Turn the office estimates into a controlled budget

13 steps
Aggregate costs, resolve a monthly funding limit and distinguish approved changes from forecast updates.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionConnect amount, timing and approval
  2. 2
    ExplanationAdd costs through the work structure
  3. 3
    ExampleBuild the office move total
  4. 4
    ChallengeCount an embedded reserve once
  5. 5
    ExamplePlace work costs in their months
  6. 6
    ExampleRead the cumulative profile
  7. 7
    Key InsightCash can move after the cost occurs
  8. 8
    ExampleMove a feasible purchase
  9. 9
    ChallengeTest a proposed earlier start
  10. 10
    ExplanationKeep the reference and outlook separate
  11. 11
    ExampleApprove extra scope and new funding
  12. 12
    ChallengeInterpret low spending carefully
  13. 13
    RecapKeep the budget useful for decisions
4

Fit resource demand to real capacity

11 steps
Calculate resource quantities, find an overlap and compare smoothing, leveling and overtime.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionAsk who and what is available when
  2. 2
    ExampleCalculate paint with an allowance
  3. 3
    ExplanationRead the resource calendar
  4. 4
    ChallengePlan a feasible specialist assignment
  5. 5
    ExplanationAdd the overlapping demands
  6. 6
    ExampleUse three days of float
  7. 7
    ChallengeFind the limit of smoothing
  8. 8
    ExamplePrice the overtime premium
  9. 9
    ChallengeConnect delivery timing with resource planning
  10. 10
    ConnectionMove the cost plan with the schedule
  11. 11
    RecapConfirm capacity before committing dates
5

Agree ownership and an outside supply plan

12 steps
Repair a RACI row, compare buying with renting and turn resource needs into clear procurement requirements.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionConnect work to people and suppliers
  2. 2
    ExplanationRead the four roles
  3. 3
    ExampleAssign the office network
  4. 4
    ChallengeRepair competing approvals
  5. 5
    TipUse rows and columns for different checks
  6. 6
    ExplanationCompare feasible supply options
  7. 7
    ExampleCalculate the 14-month totals
  8. 8
    ExampleFind the equal-cost duration
  9. 9
    ExampleInclude value recovered at the end
  10. 10
    ChallengeWork back from the needed date
  11. 11
    ChallengePlan acceptance of outside work
  12. 12
    RecapMake agreements usable for delivery

Project Cost and Resources practice questions

40 Practice Questions in 4 sets

Set 1: Apply estimates, ownership and resource limits10 Practice Questions

Question 1 of 10

A scanner costs $15,000 to buy plus $150 per month to maintain. Rental costs $900 per month. With no resale or other costs, after how many months are total costs equal?
  1. 20 months
  2. 16.7 months
  3. 25 months
  4. 17.5 months
Show answerHide answer
Answer: A
At equality, $15,000 + $150m = $900m, leaving $15,000 = $750m and m = 20 months. Dividing purchase price by $900 gives about 16.7 months but ignores maintenance during ownership. The monthly saving from buying is $750, not the full rental charge.

Question 2 of 10

A research task needs 75 person-hours. Base pay is $32 per hour and the employer adds a 25% load. What labor cost belongs in the estimate?
  1. $2,400
  2. $2,475
  3. $3,200
  4. $3,000
Show answerHide answer
Answer: D
The burdened rate is $32 × 1.25 = $40 per hour, so 75 hours cost $3,000. Using $2,400 includes base pay only and omits employer costs. The percentage applies to the hourly rate or its full labor subtotal, not once as a $25 addition to the project.

Question 3 of 10

A planner starts with the actual final cost of a similar archive digitization project and adjusts for different scope and current prices. What estimating technique is being used?
  1. Bottom-up estimating
  2. Analogous estimating
  3. Three-point estimating
  4. Parametric estimating
Show answerHide answer
Answer: B
This is analogous estimating because one comparable completed project supplies the starting cost and judgment-based adjustments. Parametric estimating instead applies a supported relationship such as cost per document. Referring to history alone does not make every estimate parametric; the way the evidence is used matters.

Question 4 of 10

An equipment setup requires two specialists for 18 hours each at $70 per hour, six sensors at $240 each and three rental days at $160 per day. An uncertain calibration item is additional: O = $900, M = $1,200, P = $2,700. What is the total using the calibration item's PERT expectation?
  1. $5,640
  2. $5,940
  3. $4,680
  4. $5,840
Show answerHide answer
Answer: D
The certain items total $2,520 labor + $1,440 sensors + $480 rental = $4,440. Calibration adds ($900 + 4 × $1,200 + $2,700) ÷ 6 = $1,400, so the total is $5,840. Using the $1,200 most likely calibration cost alone would produce $5,640 and omit the expected-cost uplift.

Question 5 of 10

A stage has a $36,000 budget and an upper cost tolerance of 8%. Its latest forecast is $39,200. What should the project manager do?
  1. Continue because the forecast is within tolerance
  2. Add the tolerance amount to the authorized budget
  3. Escalate because the forecast exceeds tolerance
  4. Transfer the excess from management reserve directly
Show answerHide answer
Answer: C
The upper tolerance is $36,000 × 1.08 = $38,880, so a $39,200 forecast must be escalated. Tolerance sets the project manager's decision limit; it does not authorize an automatic budget increase. A reserve transfer would still need the rules and approval appropriate to that reserve.

Question 6 of 10

A training event pays $1,800 for a room and $24 for each participant. What is the total cost for 35 participants?
  1. $2,640
  2. $2,400
  3. $840
  4. $1,824
Show answerHide answer
Answer: A
The room contributes $1,800 once, and 35 participants add 35 × $24 = $840, giving $2,640. Counting only $840 leaves out the fixed room fee; adding just one $24 charge would miss the fact that catering varies with every participant.

Question 7 of 10

A clinic project has a $91,000 baseline, a $98,000 total budget and a new $95,000 forecast. No baseline change is approved. What baseline should the next report show?
  1. $95,000
  2. $98,000
  3. $91,000
  4. $102,000
Show answerHide answer
Answer: C
The baseline remains the approved $91,000 until formal change control revises it. The report should also show the $95,000 forecast so the expected overrun is visible. Replacing the baseline with the forecast would hide the gap between the authorized reference and the current expectation.

Question 8 of 10

An exhibit has 360 m² of panels to paint with two coats. Coverage is 9 m² per liter per coat, with 15% added for waste. Paint is ordered in whole liters. How much is needed?
  1. 80 liters
  2. 92 liters
  3. 46 liters
  4. 83 liters
Show answerHide answer
Answer: B
Two coats require 360 × 2 ÷ 9 = 80 liters before waste. Adding 15% gives 80 × 1.15 = 92 liters, already a whole-liter quantity. Ordering 80 liters omits waste, while 46 liters applies the allowance to only one coat and misses half the coverage requirement.

Question 9 of 10

Two technicians are available. Critical task A needs both on days 1–4. Task B also needs both for two days, was scheduled on days 2–3 and has two days of total float. No other constraints apply. What happens when B moves to its earliest feasible slot?
  1. It runs on days 4–5; the finish is unchanged
  2. It runs on days 5–6; the finish is unchanged
  3. It runs on days 6–7; the finish slips two days
  4. It runs on days 5–6; the finish slips one day
Show answerHide answer
Answer: D
B cannot overlap A because A uses both technicians through day 4, so its first feasible slot is days 5–6. That moves its start three days later, exceeding its two days of float by one day. Calling this smoothing with no finish effect would overlook the delay beyond the available float.

Question 10 of 10

A RACI row has two Responsible roles and no Accountable role. What correction is required?
  1. Remove one R to leave a single worker
  2. Give A to every Responsible role
  3. Assign one authorized Accountable role
  4. Mark all managers as Informed roles
Show answerHide answer
Answer: C
The row needs exactly one Accountable role with authority to own and approve the result. Two Responsible roles can be valid because more than one person may perform the work. Removing one worker does not solve the missing decision ownership, and assigning two As would create a different conflict.
Set 2: Build a sound cost and resource plan10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A technical specialist can give a project 12 hours per week. How many weeks are needed for a 48-person-hour task performed by that specialist?
  1. 2 weeks
  2. 6 weeks
  3. 4 weeks
  4. 3 weeks
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

One report groups project expenses into labor, materials, equipment and services using accounting codes. What structure does this describe?
  1. Cost breakdown structure
  2. Work breakdown structure
  3. Organizational breakdown structure
  4. Resource calendar
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A team has a rough concept for a new service but no defined work packages. How should it present its early cost estimate?
  1. A precise figure tied to the desired target
  2. A broad range with its basis and assumptions
  3. A narrow range supported by the planned end date
  4. A fixed commitment based on the concept alone
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A support-center rollout costs $4,500 to design plus $320 per agent trained. What should be estimated for 28 agents?
  1. $8,960
  2. $13,140
  3. $134,960
  4. $13,460
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A data-cleaning task has optimistic cost $6,000, most likely cost $9,000 and pessimistic cost $18,000. What is its PERT expected cost?
  1. $9,000
  2. $11,000
  3. $10,000
  4. $20,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A project holds money for a supplier delay already listed in its risk register. Where does this reserve belong?
  1. Inside the baseline as management reserve
  2. Outside the baseline as contingency reserve
  3. Inside the baseline as contingency reserve
  4. Outside the baseline as management reserve
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A warehouse project lists a 40% chance of $7,000 rework and a 20% chance of a $3,000 discount. What net EMV do these events contribute?
  1. $3,400
  2. $2,200
  3. $4,000
  4. $2,800
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Work packages total $73,000 before reserves. Contingency is $5,500 and management reserve is $4,500. What total project budget should be authorized?
  1. $83,000
  2. $78,500
  3. $77,500
  4. $73,000
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A project plans payments of $18,000 in June and $47,000 in July, with a $40,000 limit each month. A $9,000 July purchase has no unfinished predecessors, can arrive in June and is paid on delivery. What feasible revised monthly payments solve the limit problem without changing total cost?
  1. $18,000 in June; $40,000 in July
  2. $32,500 in June; $32,500 in July
  3. $9,000 in June; $56,000 in July
  4. $27,000 in June; $38,000 in July
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A RACI row assigns the team lead A, a technician R, and a compliance adviser I. The adviser must review the design and discuss concerns before approval. What change fits that communication need?
  1. Change the adviser from I to C
  2. Change the adviser from I to A
  3. Change the adviser from I to R
  4. Change the team lead from A to C
Show answerHide answer

Save this lesson to see this answer.

Set 3: Connect risks, schedules and buying decisions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

An equipment program has a $160,000 estimate with a stated range of −10% to +25%. What lower and upper values should be reported?
  1. $150,000 and $185,000
  2. $144,000 and $176,000
  3. $144,000 and $200,000
  4. $120,000 and $200,000
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A comparable help-desk project actually cost $84,000. The new work is judged 20% larger, then needs a 5% price adjustment. A supplier model estimates $4,000 setup plus $200 per user for 500 users, covering the same scope. What are the two estimates?
  1. Analogous $105,840; parametric $104,000
  2. Analogous $105,000; parametric $104,000
  3. Analogous $100,800; parametric $100,000
  4. Analogous $105,840; parametric $100,000
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A team wants each of its optimistic, most likely and pessimistic cost values to have equal weight. Which average fits that choice?
  1. PERT average
  2. Triangular average
  3. Most likely value
  4. Pessimistic value
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A project's work estimates of $210,000 already include a PERT uplift of $3,000 for data migration. The team proposes adding that same $3,000 again, plus EMVs for a separate 25% chance of $12,000 rework and a 10% chance of a $5,000 saving. What baseline avoids duplicate allowance?
  1. $216,500
  2. $215,500
  3. $213,000
  4. $212,500
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A museum receives $16,000 of equipment in September and pays the invoice in October. Other incurred costs are $10,000 in September and $12,000 in October, all paid in the month incurred. What cost and cash totals apply in September?
  1. Incurred $10,000; cash $26,000
  2. Incurred $26,000; cash $10,000
  3. Incurred $26,000; cash $26,000
  4. Incurred $10,000; cash $10,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A project has incurred $42,000 against $46,000 planned by the reporting date. What additional evidence is needed before calling the $4,000 difference a saving?
  1. The amount of management reserve initially approved
  2. The number of suppliers with outstanding invoices
  3. The current phase's original funding release date
  4. The work completed compared with the work planned
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A testing activity needs 72 person-hours from one qualified analyst. The resource calendar allows 18 project hours per week; another available employee lacks the required qualification. What duration should be planned with the stated resources?
  1. 2 weeks
  2. 3 weeks
  3. 4 weeks
  4. 6 weeks
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A resource limit would extend a project by three days. Site equipment costs $260 per extra day. Twelve overtime hours at a regular rate of $48, paid at time-and-a-half, would avoid the extension. Those hours are already included at regular pay in the base. All other costs and effects are equal. What is the cheaper extra-cost choice?
  1. Overtime, saving $492
  2. Overtime, saving $84
  3. Extension, saving $492
  4. Extension, saving $84
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

An external engineer performs a deliverable while an internal operations lead owns its final acceptance. What RACI assignment fits those duties?
  1. Engineer A; operations lead R
  2. Engineer R; operations lead A
  3. Engineer C; operations lead I
  4. Engineer I; operations lead C
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A unit needs a device for eight months. Buying costs $9,600, maintenance is $100 monthly and resale at the end is $3,000. Rental is $1,000 monthly, with no other costs. What is the cheaper option and its net cost?
  1. Rent for $8,000
  2. Buy for $10,400
  3. Rent for $5,000
  4. Buy for $7,400
Show answerHide answer

Save this lesson to see this answer.

Set 4: Resolve combined cost and resource decisions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A team has already spent an unrecoverable $11,000 on a design. Finishing it costs another $17,000 and then $4,000 yearly support for three years. A replacement costs $20,000 now and $2,000 yearly support for three years. Both meet the same need and have no other costs or residual values. What is the cheaper choice from now on?
  1. Finish the design; $29,000
  2. Replace the design; $37,000
  3. Replace the design; $26,000
  4. Finish the design; $40,000
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

The sponsor wants a $125,000 project, but the supported estimate is $148,000. What action preserves useful cost information?
  1. Reduce the estimate to target after sponsor review
  2. Keep $148,000 and examine scope or approach
  3. Use $125,000 and track the $23,000 difference later
  4. Average the target and estimate to get $136,500
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A restoration package has O = $12,000, M = $18,000 and P = $36,000. The plan holds M as the work estimate and the difference to PERT expectation as contingency. What contingency and rough PERT standard deviation follow?
  1. Contingency $4,000; spread $4,000
  2. Contingency $2,000; spread $6,000
  3. Contingency $4,000; spread $6,000
  4. Contingency $2,000; spread $4,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A customer requests a new training module that was not in the agreed scope. Both contingency and management reserve have unused balances. What process should handle the request?
  1. Management reserve release without scope review
  2. Contingency release because the module is new
  3. Change control with an explicit funding decision
  4. Routine spending because the total budget has room
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A project has a $156,000 baseline and $9,000 management reserve. A $4,000 identified risk is funded from existing contingency inside the baseline. Separately, the sponsor approves $6,000 of unforeseen in-scope work from management reserve. What baseline and total budget result?
  1. Baseline $162,000; budget $165,000
  2. Baseline $160,000; budget $165,000
  3. Baseline $166,000; budget $175,000
  4. Baseline $162,000; budget $171,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Two control-account totals are $48,000 and $37,000. The first already includes $3,000 contingency and the second includes $2,000. Another $4,000 contingency is held at project level, with $6,000 management reserve. What baseline and project budget should be reported?
  1. Baseline $94,000; budget $100,000
  2. Baseline $89,000; budget $95,000
  3. Baseline $85,000; budget $91,000
  4. Baseline $89,000; budget $100,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

November cash payments total $68,000 against a $60,000 limit. A $12,000 delivery is scheduled for November with a fixed December payment date even if it arrives earlier. An $8,000 noncritical task is paid when done and can move to December within float. What change resolves November's cash limit?
  1. Receive the $12,000 delivery in October
  2. Split the November total evenly across months
  3. Move the $8,000 task and keep its payment in November
  4. Move the $8,000 task and its payment to December
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A new deliverable is formally approved with $7,500 additional funding. The baseline was $112,000 and the total budget $120,000; management reserve is unchanged. What are the revised figures?
  1. Baseline $119,500; budget $127,500
  2. Baseline $119,500; budget $120,000
  3. Baseline $112,000; budget $127,500
  4. Baseline $127,500; budget $127,500
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Four installers are available. Task A needs three on days 1–3. Task B needs two for two days, originally days 2–3, and has one day of total float. Neither can be split, and no extra installers are available. What is B's earliest feasible timing and project finish effect?
  1. Days 3–4; no delay
  2. Days 4–5; two days late
  3. Days 4–5; one day late
  4. Days 3–4; one day late
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A supplier needs two weeks for selection and approval, five for manufacture and one for delivery, all sequential. Equipment must be ready at the start of week 12. In-house delivery meets quality needs but requires a specialist already fully committed until week 12. What feasible plan follows?
  1. Use in-house work starting in week 12
  2. Start outside procurement at the start of week 4
  3. Start outside procurement at the start of week 6
  4. Start manufacturing before supplier approval
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

75 Key Terms, each with its definition

A

Accountable
An Accountable role in RACI owns the result and its final approval; each row has exactly one person or role with this authority.
The facilities manager is Accountable for accepting the completed office fit-out and resolving final decisions.
Activity resource estimate
An activity resource estimate specifies the resource types, skills or specifications, quantities and timing needed to perform an activity.
The activity resource estimate calls for two qualified technicians and test equipment for three days.
Actual cost
Actual cost is the cost incurred for work performed so far, including completed work owed to suppliers that has not yet been paid.
Actual cost includes the contractor's completed installation even though its invoice is due next month.
Analogous estimating
Analogous estimating uses the actual cost of a similar completed project and adjusts it for known scope, complexity or price differences.
Analogous estimating starts with the final cost of a portal built last year and adjusts it for a new portal's requirements.

B

Basis of estimate
A basis of estimate is the record of methods, assumptions, data sources, exclusions and expected range supporting a cost forecast.
The basis of estimate records that support fees are excluded and supplier prices expire in November.
Bottom-up estimating
Bottom-up estimating prices individual activities or work packages from resources and rates, then aggregates them through the work structure.
Bottom-up estimating adds technician hours, switches, cable and rental to price the network work package.
Budget estimate
A budget estimate is a cost forecast made when major deliverables are known, with more definition than an early rough estimate.
The budget estimate prices the agreed service areas while their detailed work packages are still being developed.
Burdened labor rate
A burdened labor rate includes base pay and the employer's additional costs, such as benefits, payroll taxes and allocated overhead.
Using the burdened labor rate puts benefits into the estimate for the team's 200 project hours.

C

Change budget
A change budget is a separate amount some methods hold for approved changes, used under the project's change-control rules.
An approved extra training session draws on the change budget after its scope and funding are agreed.
Consulted
A Consulted role in RACI provides input before or during work through two-way communication, allowing advice and questions to be exchanged.
The security lead is Consulted about access controls before the new office floor plan is approved.
Contingency reserve
A contingency reserve is money for identified risks, included in the cost baseline and normally controlled by the project manager.
The contingency reserve provides for a recorded risk that rented equipment may need extra operating days.
Control account
A control account is a management point joining scope, schedule and budget under a responsible manager to support performance review.
The office fit-out control account brings several work packages together for the facilities manager's review.
Cost aggregation
Cost aggregation adds activity estimates into work packages, control accounts and project totals while preserving each cost's origin.
Cost aggregation rolls the installation and testing packages into the IT manager's control account.
Cost baseline
A cost baseline is the approved time-phased cost plan, including contingency reserve but excluding management reserve, used to measure performance.
For an office move, the cost baseline remains $128,000 until an authorized change revises the approved plan.
Cost breakdown structure
A cost breakdown structure organizes costs by work element or cost type, often linking project totals to organizational accounting codes.
The cost breakdown structure shows the labor, equipment and service shares of the installation budget.
Cost driver
A cost driver is a measurable quantity with a supported relationship to cost, such as area, participant count or number of users.
Participant count is the cost driver for catering when every attendee receives the same meal package.
Cost estimate
A cost estimate is a reasoned forecast of the money needed to complete project work before its actual costs are known.
The cost estimate includes installation, training and the team's time for the new scheduling system.
Cumulative planned cost
Cumulative planned cost is the total planned cost from project start through a chosen reporting date, including all earlier periods.
Cumulative planned cost reaches $54,000 after months planned at $12,000 and $42,000 have been added.

D

Definitive estimate
A definitive estimate is a detailed cost forecast based on well-defined work packages and supported resource quantities and rates.
The definitive estimate uses approved drawings, measured material quantities and current supplier quotes.
Direct cost
A direct cost is an expense caused by and charged to a particular project, such as its materials or assigned staff hours.
The contractor's fee is a direct cost of fitting out the organization's new customer service center.
Duration
Duration is the calendar time an activity takes, given its work pattern, available resources and schedule constraints.
A technician's part-time availability increases the duration of the task without reducing its effort.

E

Effort
Effort is the total person-hours of work required for an activity, regardless of how those hours are spread across working days.
The configuration task needs 48 person-hours of effort even if two people share its completion.
Escalation
Escalation is an allowance for expected changes in prices between the estimate's price date and the time resources will be purchased.
The team includes 4% escalation for materials it expects to buy one year after receiving today's quote.
Estimating funnel
The estimating funnel is a model showing cost uncertainty narrowing as scope, requirements and work packages become better defined.
The estimating funnel narrows after design approval makes quantities and installation work clearer.
Expected monetary value
Expected monetary value is probability multiplied by cost impact, used to combine threat costs and opportunity savings into a planning amount.
Expected monetary value contributes $2,400 for a 30% chance of an event with an $8,000 cost impact.

F

Fixed cost
A fixed cost stays constant as output changes within the relevant range, such as a venue fee across the planned attendance range.
The training room has a fixed cost of $900 for the day whether 15 or 25 learners attend.
Forecast
A forecast is the current best estimate of a project's eventual cost, updated as new information changes the expected outcome.
The forecast rises after a supplier price increase, while the baseline stays subject to change control.
Funding limit reconciliation
Funding limit reconciliation adjusts feasible work and payment timing to keep planned spending within the funding limits for each period.
Funding limit reconciliation moves an eligible purchase to a month with enough available funding.
Funding requirements
Funding requirements state how much cash a project needs and when, allowing for payment timing and expected reserve use.
Funding requirements reflect a deposit due before production and a final payment due after acceptance.

I

Indirect cost
An indirect cost is a shared expense allocated to a project as overhead, such as part of the organization's accounting support.
An indirect cost allocation adds the project's share of central IT support to its work estimates.
Informed
An Informed role in RACI receives one-way updates about progress or decisions without being assigned to supply input or approve the work.
Staff are Informed about the confirmed moving date after the project team has agreed the arrangements.

J

Just-in-time delivery
Just-in-time delivery schedules resources to arrive close to when they are needed, reducing storage but increasing disruption from late arrival.
Just-in-time delivery avoids storing floor panels for weeks but leaves less time to recover from a late truck.

L

Lead time
Lead time is the elapsed time needed to obtain a resource, including relevant selection, approval, production and delivery activities.
The furniture lead time includes three weeks of selection and approval before manufacturing can begin.
Life-cycle cost
Life-cycle cost is the total cost over an evaluated period, including ownership and disposal costs and subtracting residual value.
A five-year life-cycle cost comparison includes support fees as well as the initial system purchase.

M

Make-or-buy analysis
Make-or-buy analysis compares internal work with external supply, or purchase with rental, using relevant costs and practical constraints.
Make-or-buy analysis checks the staff time, supplier fee and delivery risk for the proposed training package.
Management reserve
A management reserve is money for unforeseen in-scope work, held outside the cost baseline but within the authorized project budget.
The sponsor approves moving $3,000 of management reserve into the baseline for unforeseen in-scope work.
Markup
Markup is profit expressed as a percentage of cost, used to calculate a selling price by adding that percentage to the cost.
A supplier adds a 20% markup to its $5,000 cost and quotes the buying project a $6,000 price.

O

Opportunity
An opportunity is an uncertain event that could improve project objectives; an expected saving reduces a net cost-risk calculation.
A possible bulk discount is an opportunity that reduces the net contingency calculation for materials.
Organizational breakdown structure
An organizational breakdown structure organizes the units and roles involved in delivery and can help link work with responsibility.
The organizational breakdown structure helps assign work packages to facilities, IT and operations.
Overallocation
Overallocation occurs when the total demand for a resource across concurrent work exceeds the capacity available in a given period.
The planner finds an overallocation after adding the technician's hours on two projects for the same week.

P

Parametric estimating
Parametric estimating calculates cost from a measurable driver and a supported rate, adding any fixed cost separately where needed.
Parametric estimating prices the flooring from its measured area in m² and the cost per m².
Performance measurement baseline
A performance measurement baseline joins approved scope, schedule and cost into an integrated reference for assessing project performance.
A new deliverable may require coordinated revisions to the performance measurement baseline after approval.
PERT average
A PERT average is a three-point expected value calculated as (O + 4M + P) ÷ 6, giving extra weight to the most likely value.
When a cost range is skewed, the PERT average stays closer to the most likely cost than an equal-weight average does.
Procurement need
A procurement need is a good, service or result the project must obtain from outside the organization to deliver its planned work.
A missing specialist testing skill creates a procurement need for an external service before acceptance.
Procurement statement of work
A procurement statement of work describes the required supply, quantities, quality, delivery and acceptance so potential sellers can price it.
The procurement statement of work sets the desk quantity, delivery location and checks for acceptance.
Procurement strategy
A procurement strategy sets the high-level approach to external supply, including supplier arrangements, selection, payment and delivery.
The procurement strategy proposes one coordinated installation supplier to manage access and delivery timing.
Profit margin
Profit margin is profit expressed as a percentage of selling price, so it uses a different denominator from a markup on cost.
A $2,000 profit on a $10,000 selling price gives the supplier a 20% profit margin on the sale.
Progressive elaboration
Progressive elaboration is the refinement of plans and estimates as more reliable information about the project's work becomes available.
Progressive elaboration replaces early assumptions with checked quantities after the site survey.
Project budget
A project budget is the total authorized funding for the project, made up of the cost baseline plus the management reserve.
The $134,000 project budget includes a $128,000 baseline and a $6,000 management reserve outside it.

R

RACI matrix
A RACI matrix assigns Responsible, Accountable, Consulted and Informed roles for each item of project work to clarify action and decisions.
The RACI matrix gives the contractor R and the internal IT lead A for the completed network installation.
RASCI
RASCI is a responsibility-matrix variant that adds Support to RACI, identifying people who help the Responsible role carry out the work.
The RASCI legend assigns Support to staff who help the facilities manager prepare the moving labels.
Reserve
A reserve is an amount of money or time kept visible in a plan to cover uncertainty, with rules identifying how it may be used.
The sponsor asks to see each reserve separately from the estimates for the project's planned work.
Reserve analysis
Reserve analysis compares the money or time still available for uncertainty with the risk exposure that remains in the project.
Reserve analysis checks whether $5,000 of remaining reserve is adequate before a project's riskiest installation starts.
Resource breakdown structure
A resource breakdown structure groups resources in a hierarchy by category and type, supporting completeness checks and resource-type totals.
The resource breakdown structure separates labor skills from equipment and materials for the office work.
Resource calendar
A resource calendar records when a person or physical resource is available, including other work, nonworking time and maintenance.
The resource calendar limits the specialist to 20 project hours per week because of another assignment.
Resource histogram
A resource histogram is a bar chart showing resource demand in each period, often against a line marking available resource capacity.
The resource histogram shows a four-technician peak on a day when only three technicians are available.
Resource leveling
Resource leveling adjusts activity dates to respect resource limits and may change the project finish date or its critical path.
Resource leveling postpones installation until the single available specialist finishes the earlier job.
Resource management plan
A resource management plan describes how resources are identified, obtained, managed and released, including roles, training and logistics.
The resource management plan assigns responsibility for storage and for returning hired equipment on time.
Resource smoothing
Resource smoothing adjusts activities only within their available float to reduce resource demand peaks while preserving the project end date.
Resource smoothing moves a noncritical test by two days because the activity has three days of float.
Responsibility assignment matrix
A responsibility assignment matrix links project work in rows to people or organizational roles in columns to show assigned responsibilities.
The responsibility assignment matrix connects the approved work packages with the departments involved.
Responsible
A Responsible role in RACI performs the work needed for a deliverable or activity; each row must have at least one such assignment.
The moving company is Responsible for transporting equipment to the new office on the agreed date.
Rolling-wave planning
Rolling-wave planning details and estimates near-term work while leaving later work at a broader level until more information is available.
Rolling-wave planning keeps next month's installation detailed while later rollout phases remain broader.
Rough order of magnitude
A rough order of magnitude is an early estimate with a broad uncertainty range, used when scope detail is still limited.
A rough order of magnitude helps the sponsor assess affordability before the detailed design exists.

S

S-curve
An S-curve is a cumulative cost plot that often rises slowly at the start, steeply during delivery and more slowly during completion.
The S-curve steepens when construction and installation work overlap during the busiest project months.
Schedule reserve
A schedule reserve is a time buffer planned for identified schedule risks, considered alongside their possible cost effects.
The schedule reserve allows time for a possible retest while the cost plan provides for its labor.
Standard deviation
Standard deviation is a measure of spread; a rough PERT cost estimate uses (pessimistic − optimistic) ÷ 6 to estimate it.
A wider standard deviation flags the work package as a useful focus for closer uncertainty analysis.
Sunk cost
A sunk cost is money already spent that cannot be recovered and therefore cannot be changed by a choice about future work.
The abandoned prototype's sunk cost is excluded when comparing two ways to complete the remaining work.

T

Threat
A threat is an uncertain event that could harm project objectives; in a cost reserve calculation, its expected cost adds to the total.
A possible supplier delay is a threat because additional rental days would increase the project's cost.
Three-point estimating
Three-point estimating describes uncertain cost with optimistic, most likely and pessimistic values for the same work and scope.
Three-point estimating captures the extra cost exposure when a custom interface may need extensive rework.
Time-phased budget
A time-phased budget allocates planned cost across periods according to the schedule and the cost pattern of each work package.
The time-phased budget puts design in month 1 and spreads fit-out costs across months 2 and 3.
Tolerance
A tolerance is the permitted deviation from a target before a decision must be escalated to the next management level.
A forecast above the stage's cost tolerance requires the project manager to seek a sponsor decision.
Tranche
A tranche is a portion of authorized funding released at a particular time or decision point, such as the start of an approved phase.
The sponsor releases the next funding tranche after reviewing the completed design and updated forecast.
Triangular average
A triangular average is a three-point expected value that weights optimistic, most likely and pessimistic costs equally and divides by three.
The triangular average of $10,000, $16,000 and $28,000 is $18,000 for the installation package.

U

Unit rate
A unit rate is a cost per defined unit of quantity, supported by relevant data and valid over the scale where it will be applied.
The unit rate for cable installation is stated per meter, matching the length measured for the project.

V

Variable cost
A variable cost rises or falls with the quantity of work or output, such as materials priced per unit or catering per attendee.
Catering is a variable cost because each additional participant adds $30 to the event's bill.

About this lesson

By StudeliReport a mistake

Make your own Study Materials

Turn your notes, slides and documents into Study Guides, Practice Questions, Flashcards and 6 more tools.

Get Started