Short-Term Scheduling

Learn how operations turn plans into the day-to-day schedules of a shop floor or a service. Load jobs onto work centers with input–output reports, Gantt charts and the assignment method; sequence them with priority rules, the critical ratio and Johnson's rule, and compare the results with standard measures. See how finite capacity scheduling keeps a schedule within real capacity, and plan service staff to match demand, including weekly schedules with two consecutive days off.

IntermediateLesson 8 of 9 in Operations Management Course

What you will learn

  1. Place short-term scheduling within operations planning, name the decisions it makes and the criteria used to judge a schedule, and choose a scheduling direction and loading approach.
    • Place short-term scheduling in operations planning
      Describe how capacity, aggregate, master and material plans lead to day-to-day schedules, and name the scheduling decisions and criteria in different kinds of operations.
    • Choose forward or backward scheduling and finite or infinite loading
      Schedule a job forward from today or backward from its due date, and explain how loading with or without capacity limits changes the schedule.
  2. Assign work to work centers and keep their loads under control with input–output reports, Gantt charts and the assignment method.
    • Control work-center loads with input–output reports
      Compare planned and actual input and output at a work center, track cumulative deviations and the backlog, and decide how to respond.
    • Read and build Gantt load and schedule charts
      Use Gantt load charts to show how busy each work center is and Gantt schedule charts to track whether jobs are on time.
    • Assign jobs to resources with the assignment method
      Use the assignment (Hungarian) method to match jobs to machines, workers or sites one to one at the lowest total cost or time, including maximization and unequal numbers.
  3. Order the jobs waiting at one work center with priority rules, compare the resulting schedules with standard measures and use the critical ratio to keep priorities up to date.
    • Apply the basic priority rules
      Sequence waiting jobs by first come, first served, shortest processing time, earliest due date and longest processing time.
    • Compare sequences with performance measures
      Compute flow time, average completion time, the utilization metric, the average number of jobs in the system and lateness for a sequence, and explain which rule does best on which measure.
    • Sequence dynamically with the critical ratio
      Calculate and interpret critical ratios, sequence jobs by them, and explain why the ratio is recalculated as work progresses.
  4. Sequence jobs through two work centers with Johnson's rule, check the schedule's makespan and idle time, and use finite capacity scheduling when simple rules are not enough.
    • Sequence two-stage jobs with Johnson's rule
      Apply Johnson's rule step by step to order jobs that pass through the same two work centers.
    • Check a two-machine schedule for makespan and idle time
      Calculate start and finish times, the makespan and idle time for a two-work-center sequence, compare sequences and know where Johnson's rule stops applying.
    • Use finite capacity scheduling
      Explain the limits of simple priority rules and how finite capacity scheduling systems build feasible schedules from real capacity and shop-floor data.
  5. Choose how a service schedules its customers, convert demand forecasts into staffing requirements and shift plans, and build weekly schedules that give employees consecutive days off.
    • Choose a scheduling approach for a service
      Explain how service scheduling differs from manufacturing and choose between appointments, reservations, first come, first served, priority and demand management.
    • Turn demand forecasts into staffing plans
      Convert forecast demand per period into the number of staff needed, cover it with full-time and part-time shifts, and check the plan for shortages and surplus.
    • Build weekly schedules with consecutive days off
      Use the cyclical scheduling method to cover daily staffing requirements in a seven-day operation while giving each full-time employee two consecutive days off.

Short-Term Scheduling study guide

5 chapters

1

Make daily scheduling decisions

Every daily schedule sits inside decisions already made about facilities, output and materials. Learn how those plans become assignments to specific people and machines, and how delivery, waiting, WIP and utilization shape the choice. Then use forward and backward scheduling to find completion and start dates, and distinguish the direction of scheduling from the decision to enforce resource capacity.

1.1 From operations plans to daily assignments

A production plan says what an operation needs to deliver. A short-term schedule turns that plan into named jobs, resources, people and times over hours, days or a few weeks. A print shop might assign order 418 to press 2 from 08:00 to 11:30 on Monday, then run order 421.

Follow the planning hierarchy

Longer-range decisions establish the space within which a scheduler works.

Planning levelMain decisionTypical horizon
CapacityFacilities and major equipmentYears
Aggregate planOutput, workforce and inventory for product familiesRoughly 3–18 months
Master production scheduleSpecific products and production weeksWeeks
Material requirements planning (MRP)Dated component ordersLinked to the master schedule
Short-term scheduleSpecific resources, sequences and time slotsHours to a few weeks

A scheduler can change a sequence, arrange overtime, add a shift or subcontract work. A new building or major machine needs a higher-level capacity decision. Repeated overloads therefore need feedback to the plans above the daily schedule.

Separate the scheduling decisions

Loading assigns work to centers. Sequencing orders the waiting jobs at each center. Detailed scheduling adds start and finish times. Dispatching releases work through instructions such as a dispatch list. Expediting follows urgent or late jobs and helps them move through the operation. A dispatch list contains a sequence, which is why priority rules are also called dispatching rules.

These decisions need reliable data. The item master identifies products and parts. A routing lists their operations in order, with work centers and standard setup and run times. The work-center master records capacity, efficiency and queues. Actual completion records show whether the schedule is being achieved.

Decide what a good schedule means

Four common aims are short average completion time, high resource utilization, low work-in-process inventory (WIP) and short customer waits. They can conflict: a queue that keeps an expensive machine busy also keeps jobs waiting. Choose measures that fit the operation's service promise and cost structure.

Flow time records the time a job spends waiting and being processed. Delivery performance compares completion with the due date. A job can wait several days and still finish early, so queue waiting and lateness measure different things.

Match the process

A job shop handles varied jobs with different routings. It needs order-by-order schedules and close attention to delivery dates. A repetitive assembly operation coordinates modules, final assembly and frequent parts deliveries. A continuous operation, such as a paper mill, concentrates on production runs and changeovers within established capacity.

Aggregate planning works with product families months ahead. Project scheduling coordinates the linked activities of a unique project. Confusing either with daily operations scheduling leads to decisions at the wrong level: changing tomorrow's dispatch list cannot resolve a permanent capacity shortage.

Key Takeaways

  • Short-term schedules assign specific work, resources and times.
  • Loading, sequencing, detailed scheduling, dispatching and expediting make different decisions.
  • Routes, capacity records and actual progress must agree with shop-floor conditions.
  • Select performance measures that reflect the operation’s priorities.

1.2 Choose a direction and respect capacity

A job can be scheduled from its release date or from its due date. Separately, its resource load can be placed with or without a capacity limit. Scheduling direction and loading approach answer different questions.

Start now or work back from delivery

Forward scheduling places operations as early as possible from the time requirements are known. It finds the earliest completion and helps answer a customer asking for the soonest delivery. Early completion can build WIP or finished inventory.

Backward scheduling places the last operation to finish on the due date, then works backward through the routing. It finds the latest start and suits a fixed event or an MRP-driven order. Starting at that latest time leaves no slack to absorb a delay.

Use a shop calendar of consecutively numbered working days. A nonworking weekend does not consume two numbered days. Also distinguish the beginning from the end of a day when counting a job that occupies full days.

A job needs cutting for 2 days, machining for 3 days and painting for 1 day, and is due at the end of day 20:

OperationBackward scheduleForward from day 10
CuttingDays 15–16Days 10–11
MachiningDays 17–19Days 12–14
PaintingDay 20Day 15

Backward scheduling gives a latest start at the beginning of day 15. Forward scheduling gives earliest completion at the end of day 15. The gap from that completion to the end of day 20 is 5 working days of slack. The gap between the earliest and latest starts is also 5 days.

Load work with or without a ceiling

Infinite loading assigns the required work to periods without enforcing resource capacity. It makes overloads visible for a later capacity check. Finite loading places work only in available capacity, accounting for setup and run times. Work that cannot fit must move or receive extra capacity.

A center has 8 hours per day. Jobs J1, J2 and J3 are released Monday, in that priority order, requiring 5, 4 and 6 hours. They may continue the next day. Infinite loading puts 15 hours on Monday:

Load percentage=158×100=187.5%

Finite loading places J1 and 3 hours of J2 on Monday. Tuesday holds the remaining hour of J2 and all 6 hours of J3, leaving 1 hour free. Every scheduled hour now fits the center's calendar.

Check both feasibility and delivery

A finite schedule can be feasible and still miss a due date. If J3 was promised for Monday, moving it to Tuesday solves the overload but misses that promise. Infinite loading can retain planned dates while hiding a conflict; it also cannot make a late release overcome an insufficient processing window.

Planners often use both directions: forward to establish an achievable promise, backward to establish a latest start. Either direction can use finite capacity. For example, backward finite scheduling moves an operation earlier when its preferred resource slot is already full.

Key Takeaways

  • Forward scheduling finds early completion; backward scheduling finds the latest start.
  • Slack is the gap between earliest completion and the due date.
  • Infinite loading reveals required load without enforcing capacity.
  • Finite loading respects capacity but can move completion beyond a due date.
  • Direction and loading can be combined independently.
2

Load and assign work

Loading decisions connect available resources with the work waiting to be done. Compare planned releases and completions to understand queues, use Gantt charts to see workload and progress, and solve one-to-one assignments with the Hungarian method. Each view answers a different practical question: whether work is accumulating, when a resource is occupied, or which combination of job–resource matches gives the smallest total.

2.1 Track releases, output and the queue

A work center needs enough incoming work to stay productive, but releasing work faster than it can finish only builds a queue. Input–output control compares planned and actual releases and completions, period by period. Standard hours let jobs of different sizes be added on one common basis.

Keep a running balance

Input is work released to the center; output is work completed. The backlog changes according to:

Ending backlog=Starting backlog+Actual input−Actual output

For each input and output row, calculate deviation as actual minus planned. Add each new deviation to the previous cumulative deviation. A single weak week may be temporary; a growing cumulative shortfall needs investigation.

A welding cell starts with 60 standard hours of backlog:

WeekPlanned inputActual inputPlanned outputActual outputEnding backlog
120019021020050
220021021019565
322020022021550
422023022022555

Week 1 ends with 60+190−200=50 hours. Week 2 starts with those 50 hours, so its balance is 50+210−195=65. Always carry the latest backlog forward.

Input deviations are −10, +10, −20 and +10 hours; their running totals are −10, 0, −20 and −10. Output deviations are −10, −15, −5 and +5, with running totals −10, −25, −30 and −25.

Interpret the gap against the plan

Total planned input is 840 hours and planned output is 860. The planned final backlog is 60+840−860=40 hours. Actual input totals 830 and actual output 835, leaving 55 hours. The actual backlog is 15 hours above plan even though it has fallen from its initial 60 hours.

Input is only 10 hours below plan, while output is 25 below. Check lost capacity first: breakdowns, absence or poor efficiency may explain the shortfall. Also inspect when work arrived and whether its mix suited the cell. Weekly totals can conceal a shortage early in the week followed by a late surge.

Responses should follow the cause. Repair a recurring failure, add effective capacity or hold back new releases when the center is overloaded. When input is too low, check upstream centers for missing work. Sending more jobs into a center already above capacity does not increase what it can complete.

Connect backlog to waiting

At an output rate of about 220 standard hours per week, a 55-hour queue represents roughly 55÷220=0.25 week, or 1.25 working days in a five-day week. This is a rough waiting estimate based on the output rate; individual jobs also depend on their priority.

ConWIP, constant work in process, controls releases with a fixed number of cards. A job needs a free card to enter, and finishing a job frees its card. The circulating cards cap the number of jobs in the system and help limit queues and lead times.

Key Takeaways

  • Update backlog using actual input and output.
  • Cumulative deviations reveal a continuing gap against the plan.
  • Compare actual backlog with planned backlog before judging performance.
  • Investigate timing and job mix as well as lost capacity.
  • ConWIP ties new releases to completed work.

2.2 Use Gantt charts to see load and progress

A Gantt chart places bars against a time scale. Henry Gantt developed these charts in the 1910s. In operations, their value is immediate: a supervisor can see the jobs occupying a resource or compare an order's progress with its plan.

Give the rows the right meaning
ChartOne row representsMain question
Load chartA machine, department or work centerWhat occupies this resource, and when is it free?
Schedule chartA job or orderIs this job progressing as planned?

For a load chart, list the work centers and available capacity. Place each operation with its setup and processing time, following the routing. A job's second operation cannot start before its first ends. Mark maintenance and other unavailable periods before filling the remaining slots.

A weekly load chart might show:

ResourceMondayTuesdayWednesdayThursdayFriday
CuttingJob 101Job 101Job 102Job 102Job 102
WeldingFreeFreeJob 101Job 101Job 101
PaintingMaintenanceFreeFreeFreeFree

Welding waits for cut parts early in the week. Painting has capacity after maintenance. A free cell identifies an available resource period, although a job still needs the correct routing, skills and materials to use it. Overlapping demands on one machine reveal a conflict that a feasible detailed schedule must resolve.

Compare actual work with the review point

A schedule chart records planned starts and finishes, actual progress and a vertical current-date line. For an unfinished job, compare actual work with the amount planned by that date. Comparing only the end of the actual bar with the date line can mislead: some completed jobs should already lie entirely to its left.

At the end of Wednesday, consider three orders. A was planned Monday through Thursday, but only Monday's and Tuesday's work is complete: it is one day behind. B was planned Tuesday through Wednesday and is finished: it is on schedule. C was planned Wednesday through Friday, with one day of work expected by now; it has completed one and a half days, so it is half a day ahead.

For a finished job, compare its actual finish with the planned finish. For a partially finished job, shading should represent the work completed on a consistent scale; elapsed calendar time alone is not completed work.

Keep the chart useful

A chart displays a chosen schedule. It does not calculate the best assignment or sequence. Update it when work finishes, a machine fails or priorities change. With many jobs, electronic charts are easier to revise and inspect than a crowded paper chart.

Operations charts show recurring jobs sharing resources. A project chart shows linked activities of a particular project. The same bar format can serve both settings, but the scheduling decisions behind the bars differ.

Key Takeaways

  • Load-chart rows represent resources; schedule-chart rows represent jobs.
  • Respect routing order and unavailable time when placing operations.
  • Judge unfinished jobs against planned progress at the review date.
  • Judge finished jobs by actual versus planned finish.

2.3 Find the best one-to-one assignment

The assignment problem matches each job to one resource and each resource to one job. The aim is the smallest total time or cost, or the largest total benefit. Four jobs already have 24 possible assignments; ten have more than 3.6 million. The Hungarian method finds an optimum without listing all of them. Harold Kuhn published it in 1955, building on work by Dénes Kőnig and Jenő Egerváry.

Reduce the table without changing the best match

Subtracting a constant from every cell of one row changes every complete assignment total by that same constant. The same holds for a column. The ranking of complete assignments therefore stays unchanged. Reduced cells represent opportunity costs; a zero offers no extra cost in that reduced table.

For minimization:

  1. Subtract each row's minimum from its cells.
  2. Subtract each resulting column's minimum from its cells.
  3. Cover every zero with the fewest horizontal and vertical lines.
  4. If fewer lines than rows suffice, subtract the smallest uncovered value from all uncovered cells. Add it only at crossings of two lines; leave singly covered cells unchanged. Repeat the cover test.
  5. Once the minimum cover needs as many lines as rows, choose independent zeros: one per row and column. Start with a forced single zero. If a choice leaves a later row with no available zero, undo it and choose another; no row or column may be reused. Total the selected original values.
Work through a conflict

Four jobs can run on four machines. Times are hours:

JobM1M2M3M4
J16101215
J2125157
J3591312
J45695

Row minima are 6, 5, 5 and 5. After row reduction, only column M3 has a positive minimum, 4. Subtracting it gives:

JobM1M2M3M4
J10429
J27062
J30447
J40100

M1 and rows J2 and J4 cover all zeros with three lines. J1 and J3 compete for their only zero, M1, so four assignments are not yet possible. The smallest uncovered value is 2. After adjustment:

JobM1M2M3M4
J10207
J29062
J30225
J42100

Choose J3–M1, J1–M3, J2–M2 and J4–M4. Original times total 5+12+5+5=27 hours. Assigning every row its cheapest original cell would have given M1 to several jobs, violating the one-to-one rule.

Adapt the table

For maximization, subtract every value from the table's largest value, then minimize these opportunity losses. Each complete assignment selects the same number of cells, so minimizing total loss maximizes total benefit.

Add zero-valued dummy rows or columns to make an unequal table square. A dummy job leaves a resource unused; a dummy resource leaves a job unassigned this period. This zero treatment fits a model with no penalty for that idle or deferred assignment.

Mark an impossible pairing with a penalty large enough to make any allowed complete assignment preferable. Check that the final solution contains no forbidden cell: if none of the allowed complete assignments is feasible, a penalty cannot create one.

Key Takeaways

  • A complete assignment uses each row and column once.
  • Row and column reductions preserve the best complete assignment.
  • The cover test uses the minimum number of lines.
  • Adjust uncovered cells and line crossings differently.
  • Calculate the final total from original values.
  • Convert maximization and balance unequal tables before solving.
3

Sequence jobs at one work center

The order of waiting jobs changes how long customers and materials remain in the system. Apply common priority rules to a shared job list, turn their sequences into completion and delivery measures, and choose a rule that fits the objective. Critical ratio and slack then add a changing view of urgency as due dates approach and work progresses; a job’s priority must reflect what still needs to be done.

3.1 Order a queue with priority rules

When several jobs are ready for one work center, a priority rule decides which runs next. A rule makes the dispatch list consistent, but different rules protect different goals. Choose the rule before sorting the jobs.

State the comparison conditions

The standard comparison uses one work center with all jobs available at time 0. Processing times are known, include setup and do not change with the sequence. The center handles one job at a time and finishes a started job without interruption. These conditions matter when comparing the rules' performance.

RuleSort byMain emphasis
First come, first served (FCFS)Arrival, earliest firstArrival-order fairness
Shortest processing time (SPT)Processing time, smallest firstShort average flow time
Earliest due date (EDD)Due date, earliest firstDelivery dates
Longest processing time (LPT)Processing time, largest firstStarting long jobs early

FCFS is easy to explain when customers see the queue. SPT clears many small jobs quickly, although long jobs can wait. EDD gives priority to the earliest delivery promise. LPT sometimes starts large or important work early, but performs poorly on many single-center time measures.

Sort the same jobs four ways

Jobs arrived A, B, C, D, E and are all waiting at day 0:

JobProcessing daysDue day
A214
B77
C610
D918
E58

FCFS keeps A–B–C–D–E. The labels happen to be alphabetical, but arrival order is the reason. SPT sorts processing days 2, 5, 6, 7, 9, giving A–E–C–B–D. EDD sorts due days 7, 8, 10, 14, 18, giving B–E–C–A–D. LPT sorts processing days 9, 7, 6, 5, 2, giving D–B–C–E–A.

Check the column you are sorting. The earliest due job need not be the shortest job: B is due first but requires 7 days. Reversing EDD would sort late due dates first; it would not produce LPT, which ignores due dates.

Handle ties and changing queues

State a tiebreaker before applying a rule. If two jobs take 3 hours under SPT, FCFS can decide between them. A clear tiebreaker keeps the rule reproducible without pretending that it ranks information it never considers.

Other priorities may use critical ratio, smallest slack, customer importance or a shared setup with the previous job. These use different job attributes and can produce different lists. Record any change in the rule so that supervisors understand why a job moved.

Use one time basis throughout. A due day on a working-day calendar cannot be compared directly with a calendar date that includes closures. In a live shop, new arrivals and changes in remaining work require a fresh dispatch decision; a sequence chosen at the start is not a permanent plan for every future job.

Key Takeaways

  • FCFS sorts arrivals; SPT and LPT sort processing times; EDD sorts due dates.
  • Use the same working-time basis for every job.
  • State how tied priorities will be resolved.
  • Choose the rule to fit the performance objective.

3.2 Measure flow time, WIP and delivery

An ordered list becomes useful when its consequences are measured. Flow time runs from a job's availability to its completion, including waiting and processing. When all jobs are ready at time 0, flow time equals completion time. Makespan is the time when the last job finishes.

Build completion times first

For the five jobs A–E, processing days are 2, 7, 6, 9 and 5; due days are 14, 7, 10, 18 and 8. FCFS gives:

JobCompletion / flow timeLatenessTardiness
A2−120
B922
C1555
D2466
E292121

Each completion adds the next processing time to the previous completion. Total flow time is 79 job-days, while actual processing totals 29 days. Waiting accounts for the difference.

Lateness is completion minus due date and can be negative. Tardiness counts late time only:

L=C−d,T=max⁡(0,C−d)

The priority-rule measure called “average job lateness” uses tardiness. An early job contributes zero; it cannot cancel another job's delay.

Calculate the comparison measures

For a continuously busy center with all jobs available at time 0:

Average completion time=Sum of flow timesNumber of jobs Utilization metric=Total processing timeSum of flow times Average jobs in system=Sum of flow timesTotal processing time Average job lateness=Total tardinessNumber of jobs

FCFS gives 15.8 days average completion, a 36.7% utilization metric, 2.72 average jobs and 6.8 days average tardiness. The largest lateness is 21 days.

The utilization metric above is a textbook flow-efficiency measure. It is reciprocal to average jobs in the system. Machine busy time is a different measure: this machine works all 29 days under every sequence, even though the utilization metric changes.

Compare the rules
RuleSum of flow timesAverage completionUtilization metricAverage jobsAverage tardinessMaximum lateness
FCFS7915.836.7%2.726.821
SPT7114.240.8%2.455.413
EDD8617.233.7%2.975.811
LPT10320.628.2%3.5511.019

Times are working days. SPT wins the average-flow measures; EDD gives the smallest worst delay. Under the comparison conditions, SPT minimizes average flow time, waiting time and average jobs. EDD minimizes maximum lateness.

Neither guarantees minimum total tardiness. Here B–E–A–C–D has 25 late days, fewer than SPT's 27. Every nonidle sequence still has a 29-day makespan. Changing the order changes who waits, not the total single-machine processing requirement.

SPT can repeatedly delay long work when short jobs keep arriving, so a waiting-time limit can protect those jobs. Select the criterion first, then compare the appropriate results.

Key Takeaways

  • Flow time includes waiting as well as processing.
  • Lateness can be negative; tardiness cannot.
  • “Average job lateness” in these comparisons means average tardiness.
  • The utilization metric is not machine busy-time percentage.
  • SPT minimizes average flow measures; EDD minimizes maximum lateness under the comparison conditions.
  • Neither SPT nor EDD guarantees minimum total tardiness.

3.3 Update urgency with critical ratio and slack

A job due soon may need little work; another due later may need much more. The critical ratio (CR) compares the time available with the work remaining, putting both on a common scale.

Calculate and interpret the ratio
CR=Due date−Today’s dateWork time remaining

Use the same time unit in the numerator and denominator. Subtract today before dividing, and use remaining work, not the job's original processing requirement.

Critical ratioMeaning
Greater than 1More time than work remains; ahead of schedule
Equal to 1Time and work are equal; exactly on schedule
Between 0 and 1Insufficient time remains at the planned rate; behind schedule
Equal to 0Due today
NegativeDue date has passed

The rule gives the lowest ratio first. A high ratio indicates more time relative to remaining work, so it gives lower urgency under this rule.

Rank four jobs

Today is day 30:

JobDue dayWork remainingCRSlack
P364 days1.52 days
Q335 days0.6−2 days
R388 days1.00 days
S292 days−0.5−3 days

For P, CR=(36−30)÷4=1.5. For S, CR=(29−30)÷2=−0.5. The priority order is S–Q–R–P: overdue S, then behind-schedule Q, exactly-on-schedule R and ahead-of-schedule P.

Recalculate when the next decision is made

CR is dynamic. When a center is ready for its next job, update both the date and remaining work. A job that waited has less time available but the same work; its ratio falls. A job that progressed can have a higher ratio because its denominator shrank.

For example, at day 31, P with no progress has 5÷4=1.25. If it instead has only 3 days of work remaining, its ratio is 5÷3≈1.67. The date alone does not tell you its new status. Updated due dates from MRP can also change the ranking.

Compare CR with slack
Slack=(Due date−Today)−Work remaining

Slack measures spare time in days or hours; CR is a ratio with no unit. The example gives the same order under smallest slack, but the rules can disagree. A 1-day job with 2 spare days has CR 3; a 20-day job with the same 2 spare days has CR 1.1. Equal slack is a much thinner proportional margin on the long job. A related rule divides slack by the number of operations still required.

CR helps compare make-to-stock and make-to-order jobs and track changes in urgency. It still looks at each job's due date and remaining work. Congestion at a later center and customer importance require additional information in the overall schedule.

Key Takeaways

  • Compute CR as time until due divided by remaining work.
  • Process the lowest critical ratio first.
  • Recalculate both date and remaining work at each dispatch decision.
  • Slack is spare time; critical ratio measures the proportional margin.
  • CR does not account for downstream congestion or customer importance.
4

Coordinate machines within capacity

Jobs that visit several machines need more than a ranked queue. Their operations must fit together in time and stay within available capacity. Use Johnson’s rule to build a two-stage sequence, calculate its makespan and idle time, and check a lower bound. Then see how finite capacity scheduling responds to breakdowns, shared resource limits and bottlenecks that a local dispatch rule cannot fully capture.

4.1 Build a two-machine sequence with Johnson’s rule

Jobs passing through two work centers can overlap: while one job uses the second center, another uses the first. Their order controls how much the second center must wait. Johnson's rule, published by S. M. Johnson in 1954, finds a sequence with minimum makespan, from the first start to the final finish.

Check the operating conditions

Every job must visit center 1 and then center 2 in that order. All jobs are available at the start. Processing times are known and constant; setup is included and does not depend on the sequence. Each center processes one job at a time without interrupting it, and each job must finish its first operation before starting its second. Jobs can wait between centers.

The objective is to finish the whole set as early as possible. Due dates do not enter the rule. A sequence with minimum makespan may still deliver a particular job late.

Fill positions from both ends
  1. List both processing times for every unscheduled job.
  2. Find the smallest individual time anywhere in that list.
  3. If it belongs to center 1, put its job in the earliest open position.
  4. If it belongs to center 2, put its job in the latest open position.
  5. Remove the entire job and repeat until all positions are filled.

The last position may be filled before the middle positions. “Choose next” means the next placement decision, not necessarily the next job to run.

Work a five-job example

A print shop prints and then binds each job. Times are hours:

JobPrintingBinding
A49
B76
C75
D98
E24

The smallest time is E's 2 hours at printing, so place E first. Remove E, including its binding time. The smallest remaining time is A's 4 hours at printing, so place A second.

C's 5 hours at binding is now smallest, so place C last. B's 6 hours at binding is next, so put B in the latest open position, immediately before C. D occupies the remaining middle position. The completed sequence is E–A–D–B–C.

A short first operation near the front feeds the second center early. A short second operation near the back helps that center finish soon after the first center finishes its work. Sorting the sum of each job's two times would lose this distinction between the stages.

Resolve ties without changing the objective

When different jobs share the smallest time, either can be selected first; the resulting Johnson sequences have the same minimum makespan. If a job's minimum is tied across its two centers, either end is allowed. Write down the chosen placement so later timing follows the same sequence.

Do not schedule a selected job twice by leaving its other time in the candidate list. Also check routings before using the rule: a job that visits binding before printing belongs to a different scheduling problem.

Key Takeaways

  • Johnson’s rule minimizes makespan for the two-stage flow-shop conditions.
  • Choose the smallest individual remaining processing time.
  • A first-center minimum goes at the front; a second-center minimum goes at the back.
  • Remove a job completely after placing it.
  • Johnson ties can produce different optimal sequences.

4.2 Time the sequence and verify its makespan

A sequence says which job comes next. To find its makespan, calculate when each operation can actually start. The second work center needs both a free machine and a job that has completed its first operation.

Respect both release conditions

Run center 1 back to back from time 0. For each job at center 2:

S2=max⁡(C1,C2,previous)

Here S2 is its second-center start, C1 its first-center completion and C2,previous the preceding job's second-center finish. Add its second processing time to find its finish. Any gap between the previous finish and the new start is idle time.

For the print shop's Johnson sequence E–A–D–B–C:

JobPrintingBinding
E0–22–6
A2–66–15
D6–1515–23
B15–2223–29
C22–2929–34

B finishes printing at 22 but waits until binding becomes free at 23. D starts binding at 15 because both the job and the machine become available then. The makespan is 34 hours.

Account for idle time over the same horizon

Binding performs 32 hours of work. Over the 34-hour schedule, its idle time is 34−32=2 hours, all before E arrives. Printing performs 29 hours, leaving 5 hours of idle time at the end if it is measured over that same 34-hour horizon.

Arrival order A–B–C–D–E has printing completions 4, 11, 18, 27 and 29. Binding runs 4–13, 13–19, 19–24, 27–35 and 35–39. It waits 4 hours initially and 3 hours before D, totaling 7 idle hours. Johnson's order saves 5 hours of makespan, about 12.8% of 39.

Starting every second operation as early as possible does not eliminate these gaps. A different sequence changes when work reaches the second center; drawing the existing bars earlier cannot make unfinished parts available.

Use a lower bound

Any schedule must allow all 32 hours of binding after at least the smallest printing time, 2 hours. It also needs all 29 hours of printing followed by at least the smallest binding time, 4 hours. Thus:

Makespan≥max⁡(32+2,29+4)=34

The Johnson schedule reaches 34, so the lower bound proves that it cannot be improved. A bound below a schedule's makespan would not establish optimality by itself.

Know the three-center special case

For three centers visited in order, the method gives an optimum when the smallest time at center 1 is at least the largest at center 2, or the smallest time at center 3 is at least the largest at center 2. For each job, add its first and second operation times for one virtual time, and its second and third for the other. Apply the two-center rule to those paired virtual times.

Use the resulting order on the three real centers and time their real operations. The virtual centers are a sequencing device, not two physical machines. Beyond this restricted case, use other heuristics or scheduling software. Due dates and average flow time still need separate checks.

For example, three jobs H, J and K have times H (8, 2, 7), J (7, 3, 4) and K (6, 1, 9) hours across the three centers. The smallest first-center time is 6, above the largest middle time of 3. Virtual times are H (10, 9), J (10, 7) and K (7, 10). K's first virtual time puts K first; J's second virtual time puts J last. H fills the middle, giving K–H–J. Either order of selecting the tied minima gives that sequence.

Key Takeaways

  • Start a second operation only when both the job and center are available.
  • Makespan is the final finish; idle time depends on the measurement horizon.
  • Reaching a valid lower bound proves the makespan is optimal.
  • The three-center reduction needs its dominance condition.
  • Johnson’s objective is makespan, so check due dates separately.

4.3 Build a feasible schedule from current capacity

A priority rule chooses the next job using a few attributes. It does not see the entire shop. Finite capacity scheduling (FCS) builds detailed schedules within the capacity actually available across resources and periods.

Use more than a local ranking

Simple rules have three limits. They need revision as equipment, processes and product mix change. They see one work center at a time, so they can miss congestion downstream or idle capacity upstream. Each uses only selected attributes, such as arrival, processing time or due date, unless other priorities are built in.

Two orders due on the same day may have different customer importance or lateness penalties. EDD treats them alike. Running the shortest local job first can also delay work needed at a system bottleneck. A locally attractive dispatch choice need not improve the whole operation.

FCS uses routings, setup and run times, shift calendars, maintenance, tooling and skilled labor availability. Orders and standard data usually come from MRP or ERP; live shop-floor information can update machine status and progress. Software combines rules, optimization methods and simulation, then shows a detailed electronic Gantt chart.

Replan after a disruption

A center has 8 hours per day. J1, J2 and J3 need 5, 4 and 6 hours and may continue the next day. Monday holds J1 plus 3 hours of J2. The original Tuesday schedule contains the last hour of J2 and all 6 hours of J3.

A Tuesday breakdown removes 2 hours, leaving 6. After the last hour of J2, only 5 hours remain for J3. Its final hour moves to Wednesday. If J3 is due Tuesday evening, the schedule exposes a one-hour shortfall against its promised completion.

The planner can compare 1 hour of Tuesday overtime, a qualified alternative machine for part of the work, or a revised promise. Interactive changes show the effects on other jobs immediately. Adding overtime only helps when the required people, tools and supporting resources are available too.

Protect the limiting resource

A bottleneck has less capacity than the demand placed on it and limits system output. Schedule it first and arrange supporting work so it has what it needs. Lost bottleneck time reduces output when it cannot be recovered; extra speed elsewhere does not raise output while the bottleneck remains the limit.

Drum-buffer-rope links three controls. The bottleneck sets the pace, the drum. A time buffer protects it from starvation. The rope releases new material at that pace, preventing uncontrolled WIP buildup at other centers.

Keep the inputs credible

An MRP capacity check compares aggregate load with capacity per period and reports overloads. FCS places operations into feasible detailed slots. Neither creates a new machine or makes inaccurate processing times reliable.

Check changed routings, realistic standard times, maintenance and skill availability when an apparently precise schedule cannot be followed. Software can evaluate alternatives quickly, but its feasibility depends on the resource data and constraints it receives.

Key Takeaways

  • Local priority rules do not optimize the whole operation.
  • FCS places detailed operations within actual resource availability.
  • Interactive replanning shows the consequences of disruptions and alternatives.
  • Plan the bottleneck first and control releases to its pace.
5

Schedule customers and staff

Services match capacity to customers whose needs change throughout the day and week. Choose how bookings and queues organize demand, translate forecasts into whole-person staffing requirements, and fit shifts to the periods that need cover. A repeating weekly schedule adds another constraint: employees work five days with two consecutive days off, while the service still covers every day’s demand.

5.1 Match the service schedule to the customer need

Service capacity often disappears when its time passes. An unused appointment or an empty room for tonight cannot be stored for tomorrow. Services mainly schedule people; demand varies across hours and seasons, and customers often experience waiting directly. Labor is usually the largest cost.

Choose how customers enter
ApproachWhat it controlsExample
AppointmentsService slots with a providerAn adviser at 10:00
ReservationsCapacity set aside for a date, time or periodA table at 19:00 or a car for a weekend
FCFSService order by arrivalA counter queue
PriorityOrder by urgency or another stated needEmergency triage

Appointments help control the timing of arrivals. Reservations make future capacity needs visible. Both can specify a time; the difference is the commitment being scheduled, not whether a clock time appears.

A clinic has a 4-hour session with 15-minute appointments, giving 16 slots. If 10% of booked patients typically do not arrive, 16 bookings bring an expected 16×0.9=14.4 arrivals. That is an average across sessions, not a possible head count on one day. Overbooking can reduce unused capacity but raises waits when more patients attend.

FCFS is simple and often feels fair when needs are similar. It does not smooth demand. A priority system serves the most urgent case first even when that customer arrived later. In emergency care, triage makes medical urgency the scheduling priority. An express checkout applies the SPT idea to short transactions.

Change demand or change capacity

Demand management moves customers toward quieter periods using off-peak prices, promotions, appointments or reservations. Capacity management changes the resources available: part-time staff, flexible shifts, cross-trained employees or self-service.

For example, inviting customers to book a quiet morning slot changes when demand arrives. Moving a trained employee from an idle desk to a busy queue changes where capacity is supplied. The two actions can support the same service target through different mechanisms.

Fit the setting

Hospitals coordinate operating rooms with fixed surgery times and continuous nursing cover. Retailers convert forecast customer traffic into shifts. Banks can add part-time workers at peaks and move cross-trained staff between tasks. Airlines must coordinate aircraft and crew schedules, including duty and rest constraints. Around-the-clock services use rotating shifts.

The practical choice balances staffing cost against waiting, lost business and service quality. Because arrivals vary, staffing exactly to average workload can still produce queues during surges. Additional capacity can shorten waits but costs more.

FCFS is not the best fairness rule for every setting. Equal arrival-order treatment can overlook urgent need. Choose the service priority explicitly, then align bookings, queue rules and staffing with it.

Key Takeaways

  • Service capacity cannot be stored after its time passes.
  • Appointments schedule service slots; reservations set aside capacity.
  • FCFS suits arrival-order fairness; priority can protect urgent needs.
  • Demand management shifts arrivals; capacity management shifts resources.
  • No-show averages do not guarantee spare slots on a particular day.

5.2 Convert forecast demand into shift coverage

A staffing plan must cover demand when it occurs. A daily average can hide a midday shortage even when total staff-hours look generous. Start with short periods, then fit shifts to their requirements.

Find the requirement in each period

Forecast arrivals, convert them into workload and divide by one employee's output for the same period. Round up to a whole number. If demand is stated per hour, use output per employee per hour; using daily output would mix time bases.

A desk opens 08:00–20:00. Each employee serves 15 customers per hour:

BlockCustomers per hourCalculationStaff required
08:00–12:004545 ÷ 153
12:00–16:008484 ÷ 156
16:00–20:005252 ÷ 154

Midday needs 5.6 employees' worth of output, so schedule 6 people. Five can serve only 75 customers per hour. The evening calculation is about 3.47, requiring 4 people. Across three 4-hour blocks, the rounded requirement is 4(3+6+4)=52 staff-hours.

Build shifts and check their overlap

Full-time workers can take 08:00–16:00 or 12:00–20:00. The overlap makes midday coverage the sum of both groups.

PlanEarly full-timeLate full-timeEvening part-timeCoverage by blockStaff-hours
A3403, 7, 456
B3313, 6, 452

Plan A covers every block but has one surplus person for four midday hours. Plan B adds a part-time worker only from 16:00 to 20:00 and removes that surplus. Its hours are 6×8+1×4=52.

Check each period for shortage and surplus, not just the day's total. The average hourly demand is about 60.3, suggesting 5 staff all day after rounding up. That leaves two surplus in the morning, one too few at midday and one surplus in the evening. Extra morning hours cannot be saved and used to serve the midday queue.

Add availability and service constraints

Breaks reduce the number actually serving. Cover them through relief staff or an allowance; count coverage after unavailable time is removed. Also check skills, certifications, contracts, employee preferences and fair allocation of unpopular shifts. A shift with enough people can still lack the required skill mix.

Random arrivals make 100% planned occupancy a poor service target: there is no spare ability to absorb a surge. A call center might plan around 85% busy time, but its exact target comes from the waiting-time goal. Distinguish the basic workload calculation from the extra capacity needed for service quality.

With many shift types and constraints, integer programming or scheduling software can select start times and staff numbers. The plan still needs a period-by-period check against forecast demand and actual availability.

Key Takeaways

  • Calculate staff from matching demand and output time units, then round up.
  • Check shift coverage in each demand block.
  • Overlapping shifts can create surplus even when every block is covered.
  • Breaks and skills affect effective availability.
  • Plan spare capacity to meet waiting-time goals under variable arrivals.

5.3 Give consecutive days off while covering the week

A seven-day service can give each full-time employee five working days and two consecutive days off. Cyclical scheduling builds a repeating week by assigning one employee at a time to the days still needing cover.

Apply the days-off heuristic

Write the daily staffing requirements Monday through Sunday. Find the consecutive pair with the smallest combined requirement and give the next employee those days off. Sunday and Monday form a pair because the schedule repeats. Subtract 1 from each of that employee's five working days, then repeat using the updated requirements.

Keep negative residuals: they show surplus already created. Stop when every residual is zero or negative. If pairs tie, any tied pair can be selected, but the choice can change the final staffing total. This is a heuristic, not a general guarantee of the smallest workforce.

Follow the updates

A store needs 3, 6, 5, 4, 7, 6, 3 people from Monday to Sunday. Adjacent pair totals are 9, 11, 9, 11, 13, 9 and 6, with Sun–Mon lowest.

EmployeeDays offRemaining requirement, Mon–Sun
Start—3, 6, 5, 4, 7, 6, 3
1Sun–Mon3, 5, 4, 3, 6, 5, 3
2Sun–Mon3, 4, 3, 2, 5, 4, 3
3Wed–Thu2, 3, 3, 2, 4, 3, 2
4Sun–Mon2, 2, 2, 1, 3, 2, 2
5Wed–Thu1, 1, 2, 1, 2, 1, 1
6Mon–Tue1, 1, 1, 0, 1, 0, 0
7Sat–Sun0, 0, 0, −1, 0, 0, 0

For employee 6, Mon–Tue, Sat–Sun and Sun–Mon tie at 2. Choosing Mon–Tue allows employee 7 to cover every positive residual while taking Sat–Sun off.

Count the resulting cover independently: 3, 6, 5, 5, 7, 6, 3. Every day is covered; Thursday has one extra person. Weekly demand totals 34 staff-days and seven employees supply 35, leaving one surplus staff-day.

Test whether fewer employees are possible

Two lower bounds apply. The workforce must be at least the largest daily requirement, and at least total required staff-days divided by five, rounded up:

N≥max⁡(Largest daily requirement,⌈Weekly staff-days5⌉)

Here Friday requires 7 and 34÷5=6.8 rounds up to 7. The seven-person schedule reaches that bound, proving it uses the fewest employees possible.

Choosing Sun–Mon for employee 6 instead leaves positive residuals on Mon, Wed, Fri and Sun. No employee with consecutive days off can cover all four, so that tie choice needs an eighth employee. A result above the lower bound deserves another look at ties; the bound alone does not promise that a schedule attaining it exists.

In practice, rotate days off over successive weeks for fairness and check contracts, rest requirements and preferences. Surplus can support training or maintenance; part-time shifts can fill small remaining gaps.

Key Takeaways

  • Treat Sun–Mon as consecutive in a repeating week.
  • Subtract cover from working days and recalculate the pair totals.
  • Stop only when all residual requirements are nonpositive.
  • Tie choices can change the workforce needed.
  • Reaching the daily and weekly lower bound proves minimum staffing.
  • Check final daily cover independently of the residual table.

Short-Term Scheduling examples

5 Walkthroughs

1

Turn a plan into a feasible daily schedule

11 steps
Move from planning decisions to start dates, delivery promises and capacity limits.
  1. 1
    IntroductionGive work a resource and a time

    A monthly output plan still leaves tomorrow’s practical questions open: which job should use each machine, and when? A short-term schedule resolves those assignments. We will follow a print-shop order from the planning hierarchy to its start and finish dates, then check whether the work fits the machine’s available hours.

  2. 2
    ExplanationLocate the daily decision

    Capacity plans establish facilities and equipment. Aggregate plans set output, workforce and inventory for product families. The master production schedule names products and weeks, and MRP dates component orders. Short-term scheduling places those orders on particular resources. Buying a new press belongs to capacity planning; reserving press 2 for an order on Monday is a daily scheduling decision.

  3. 3
    ExampleSeparate assignment from order

    Suppose orders 418 and 421 both need printing. Assigning both to press 2 is loading. Choosing 418 before 421 is sequencing. Giving order 418 the slot 08:00–11:30 adds detailed timing. A dispatch list authorizes the chosen work to run; expediting follows urgent or delayed orders. The job’s routing supplies the required operations and their standard times.

  4. 4
    Key InsightA busy machine can still mean long waits

    A queue helps keep a press occupied, but every order waiting there contributes to WIP and flow time. Utilization and customer waiting can therefore pull in different directions. Choose the objective that reflects the operation’s promise. Reliable due-date delivery, a short average lead time and keeping an expensive press busy are different measures of success.

  5. 5
    ChallengeChoose the planning level

    A shop’s dispatch list is revised every morning, but every week the same machine has more work than it can complete. Should the planner keep solving the problem only through daily sequencing?

    ---reveal---

    No. Daily sequencing can reorder work and short-term capacity changes can help, but a lasting shortage must feed back to higher-level capacity or output plans. The daily schedule exposes the persistent mismatch; changing the order alone does not remove it.

  6. 6
    ExplanationCount working days consistently

    A shop calendar numbers working days consecutively. A weekend closure does not consume two working-day numbers. For a job occupying full days, keep the boundary clear: starting a two-day operation at the beginning of day 10 finishes it at the end of day 11. This prevents a one-day error when working backward from an end-of-day promise.

  7. 7
    ExampleSchedule back from day 20

    An order needs cutting for 2 days, machining for 3 and painting for 1, due at the end of day 20. Place painting on day 20. Machining occupies days 17–19, so cutting occupies 15–16. The latest start is the beginning of day 15. Starting then leaves no spare working time between these operations and the delivery deadline.

  8. 8
    ExampleFind the earliest finish

    Release the same order at the beginning of day 10 and schedule forward. Cutting runs days 10–11, machining 12–14 and painting day 15. Earliest completion is the end of day 15, giving five working days before the day-20 deadline. The same five-day gap separates earliest start on day 10 from latest start on day 15.

  9. 9
    ExplanationPut a ceiling on the load

    A separate center has 8 hours per day. Monday releases, in order, need 5, 4 and 6 hours, and may continue the next day. Infinite loading places 15 hours on Monday, or 187.5% of capacity. Finite loading places 5 plus 3 hours Monday, then the remaining 1 plus 6 Tuesday. It respects available hours, but the last job may finish after its promised date.

  10. 10
    ChallengeCombine direction and capacity

    A customer wants the last of those three jobs by Monday evening. The planner keeps all 15 hours on Monday and calls the plan backward scheduled. Has the scheduling direction resolved the problem?

    ---reveal---

    No. Monday has only 8 hours, leaving a 7-hour capacity gap. Working back from a due date does not add capacity. The planner needs earlier available slots, added effective capacity or a later promise. The capacity choice and scheduling direction must both be checked.

  11. 11
    RecapRead the finished plan

    For a proposed daily schedule, identify the named work, its resource, its sequence and its timing. Then check the working-day calendar and the resource’s available slots. Forward scheduling supports an early completion promise; backward scheduling identifies a latest start. A due date and a feasible capacity plan must agree before that promise is dependable.

2

Control the load and solve an assignment

17 steps
Track a work center’s queue, read its Gantt charts and work through a four-job assignment.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionUse three views of work
  2. 2
    ExplanationBalance the queue
  3. 3
    ExampleAccumulate the deviations
  4. 4
    ChallengeInterpret a smaller queue
  5. 5
    ConnectionLet completions authorize releases
  6. 6
    ExplanationRead resource rows
  7. 7
    ExampleCompare work done by Wednesday
  8. 8
    ChallengeCheck a finished order
  9. 9
    ExplanationPreserve one job per machine
  10. 10
    ExampleStart with original times
  11. 11
    ExampleReduce columns after rows
  12. 12
    ExampleFind the smallest zero cover
  13. 13
    ExampleChoose independent zeros
  14. 14
    TipPrepare variants before solving
  15. 15
    ChallengeChange the optimization direction
  16. 16
    ChallengeConnect assignment to the schedule
  17. 17
    RecapFollow work from release to resource
3

Compare job sequences and update urgency

15 steps
Build completion times, separate waiting from delivery delay, and recalculate critical ratios.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionDecide what the sequence should improve
  2. 2
    ExplanationSet a fair basis for comparison
  3. 3
    ExampleSort the jobs by the right column
  4. 4
    ChallengePick a rule for a waiting list
  5. 5
    ExampleAccumulate completion times
  6. 6
    ExplanationKeep two meanings of lateness separate
  7. 7
    Key InsightInterpret the utilization metric
  8. 8
    ExampleCompare averages with worst delays
  9. 9
    ChallengeCheck what optimization really claims
  10. 10
    ExplanationCompare time left with work left
  11. 11
    ExampleRank four current jobs
  12. 12
    ExampleUpdate date and progress together
  13. 13
    ConnectionCompare slack with proportional margin
  14. 14
    ChallengeDiagnose a high-ratio priority
  15. 15
    RecapChoose the measure before the rule
4

Sequence two machines and replan within capacity

16 steps
Apply Johnson’s placements, time the result and respond to a capacity disruption.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMake operations fit together
  2. 2
    ExplanationCheck the shared route
  3. 3
    ExamplePlace the first two jobs
  4. 4
    ExampleFill the back before the middle
  5. 5
    ChallengeReject a total-time shortcut
  6. 6
    ExampleRun the first center back to back
  7. 7
    ExampleTime binding from both constraints
  8. 8
    Key InsightLocate the idle hours
  9. 9
    ExampleProve a lower limit
  10. 10
    ChallengeRead what the bound proves
  11. 11
    ConnectionReduce three centers only when qualified
  12. 12
    ExplanationSchedule the resources actually available
  13. 13
    ExampleReplan after Tuesday loses capacity
  14. 14
    ChallengeCompare a feasible response
  15. 15
    Key InsightProtect the resource that limits output
  16. 16
    RecapCheck the sequence and the calendar
5

Cover service demand through the day and week

17 steps
Choose customer scheduling rules, fit shifts to demand and build a repeating days-off plan.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMatch capacity to the time of need
  2. 2
    ExplanationChoose what gets booked
  3. 3
    ExampleInterpret no-shows as an average
  4. 4
    ChallengeShift arrivals or shift resources
  5. 5
    ExampleConvert hourly demand to staff
  6. 6
    ExampleCheck overlapping full-time shifts
  7. 7
    ExampleUse a short shift where it helps
  8. 8
    ChallengeTest the average-demand shortcut
  9. 9
    TipCount staff who are actually available
  10. 10
    ExplanationBuild the repeating week one employee at a time
  11. 11
    ExampleAssign the first two employees
  12. 12
    ExampleUpdate the pair totals after each choice
  13. 13
    ExampleChoose a tie and finish the plan
  14. 14
    Key InsightUse a bound to check the workforce
  15. 15
    ChallengeCheck the effect of a tie
  16. 16
    ChallengeCheck both calendars
  17. 17
    RecapVerify cover where customers need it

Short-Term Scheduling practice questions

50 Practice Questions in 5 sets

Set 1: Daily scheduling decisions10 Practice Questions

Question 1 of 10

Jobs all visit cutting and then coating under Johnson’s conditions. Their hours are T (6, 4), U (3, 8) and V (7, 5). What sequence does Johnson’s rule give?
  1. T–U–V.
  2. U–T–V.
  3. V–U–T.
  4. U–V–T.
Show answerHide answer
Answer: D
The smallest time is U’s 3 hours at cutting, placing U first. T’s 4 hours at coating then places T last, leaving V in the middle. Putting T immediately after U confuses the next placement decision with the next open position at the front.

Question 2 of 10

A repair shop has approved next month’s workforce level. What decision turns that plan into a short-term schedule?
  1. Set the total technician head count for next month.
  2. Assign repair 62 to a technician from 09:00 to 11:00.
  3. Choose next year’s investment in workshop equipment.
  4. Set quarterly output targets for all repair families.
Show answerHide answer
Answer: B
Assigning a named repair to a technician and time slot specifies the work to be carried out. Setting next month’s head count belongs to the higher-level workforce plan.

Question 3 of 10

A planner has chosen the machine for an order. What decision is sequencing?
  1. Decide which machine receives the order.
  2. Decide how many machines to buy.
  3. Decide the monthly workforce level.
  4. Decide which waiting order runs first.
Show answerHide answer
Answer: D
Sequencing orders the jobs waiting for a resource. Selecting the machine is loading, even though it happens close to the sequencing decision.

Question 4 of 10

A cell starts the week with 36 standard hours waiting, receives 114 hours and completes 123 hours. What backlog remains?
  1. 27 standard hours.
  2. 45 standard hours.
  3. 9 standard hours.
  4. 159 standard hours.
Show answerHide answer
Answer: A
The ending backlog is the initial 36 hours plus 114 received, less 123 completed, leaving 27 hours. Using output minus input as an addition would give 45 hours and reverse the queue movement.

Question 5 of 10

A Gantt chart has one row for each packaging machine and shows jobs placed along a time scale. What type of operations chart is it?
  1. A job-progress schedule chart.
  2. An input–output report.
  3. A load chart.
  4. A one-to-one assignment table.
Show answerHide answer
Answer: C
A load chart gives resources their own rows and shows when each is occupied or free. A schedule chart that tracks job progress gives jobs their own rows.

Question 6 of 10

Two jobs need different machines. Their times on machines R and S are J1: 3 and 5 hours; J2: 4 and 9 hours. What is the minimum-total one-to-one assignment?
  1. J1–R and J2–S: 12 hours.
  2. J1–R and J2–R: 7 hours.
  3. J1–S and J2–R: 9 hours.
  4. J1–S and J2–S: 14 hours.
Show answerHide answer
Answer: C
The two valid one-to-one assignments total 3+9=12 hours and 5+4=9 hours. Giving both jobs machine R totals only 7 hours but violates the assignment restriction. Choosing each job’s cheapest machine independently is therefore not a valid solution.

Question 7 of 10

Three jobs are ready. K needs 6 hours and is due at hour 7; L needs 2 hours and is due at hour 12; M needs 4 hours and is due at hour 9. What sequence does SPT give?
  1. K–M–L.
  2. L–M–K.
  3. M–L–K.
  4. L–K–M.
Show answerHide answer
Answer: B
Shortest processing time sorts the required hours from smallest to largest: 2, 4 and 6. This gives L, then M, then K. K–M–L follows due dates instead and would answer an EDD question, not an SPT question.

Question 8 of 10

Two jobs are ready at time 0 and run in order on one center without idle time. The first takes 4 hours and the second 7 hours. What is their average flow time?
  1. 7.5 hours.
  2. 5.5 hours.
  3. 11 hours.
  4. 3.5 hours.
Show answerHide answer
Answer: A
The first job finishes at hour 4 and the second at hour 11, so their flow times total 15 hours. Dividing by two jobs gives 7.5 hours. Averaging only the processing times gives 5.5 hours and leaves out the second job’s four-hour wait.

Question 9 of 10

A rental service promises to hold a particular capacity category for a customer from Friday to Monday. What scheduling approach is it using?
  1. A reservation for a stated period.
  2. An appointment with a named provider.
  3. A first-come service queue.
  4. A priority based on urgency.
Show answerHide answer
Answer: A
The service is setting aside rental capacity in advance for the requested period, which is a reservation. An appointment would schedule the service itself in a provider’s time slot. Reservations can specify dates and times, so a timed commitment alone does not make it an appointment.

Question 10 of 10

A help desk needs 2, 5 and 3 employees in the blocks 08:00–12:00, 12:00–16:00 and 16:00–20:00. Available shifts are 08:00–16:00, 12:00–20:00 and a part-time 16:00–20:00 shift. What combination covers demand with the fewest staff-hours?
  1. 2 early, 2 late, 1 part-timer: 36 hours.
  2. 2 early, 3 late, no part-timers: 40 hours.
  3. 3 early, 2 late, 1 part-timer: 44 hours.
  4. 2 early, 4 late, no part-timers: 48 hours.
Show answerHide answer
Answer: B
Two early and three late employees cover 2, 5 and 3, using 40 staff-hours. The block requirements themselves total 40 hours, so a feasible plan at that total is minimum. The 36-hour plan leaves midday one employee short because its part-timer arrives only at 16:00.
Set 2: Read schedules and set priorities10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

Customers with urgent needs are served before earlier arrivals with routine needs. What rule organizes that service queue?
  1. A first-come rule.
  2. A reservation rule.
  3. A priority rule.
  4. A backward-loading rule.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A job needs 3 working days of preparation followed by 2 of finishing. It is due at the end of day 17. What is its latest start under backward scheduling?
  1. Beginning of day 12.
  2. Beginning of day 14.
  3. Beginning of day 13.
  4. Beginning of day 15.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Over three weeks, actual input minus planned input is +6, −4 and −7 standard hours. What is the final cumulative input deviation?
  1. −5 standard hours.
  2. −7 standard hours.
  3. +5 standard hours.
  4. −17 standard hours.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A lab assigns jobs A, B and C to three different instruments. Times on I1, I2, I3 are A: 4, 6, 8; B: 5, 9, 7; C: 6, 3, 5 hours. What assignment gives the smallest total time?
  1. A–I2, B–I1, C–I3: 16 hours.
  2. A–I3, B–I1, C–I2: 16 hours.
  3. A–I1, B–I2, C–I3: 18 hours.
  4. A–I1, B–I3, C–I2: 14 hours.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Two jobs are waiting at day 20. P is due day 26 with 3 days of work left; Q is due day 25 with 4 days left. What order does the critical-ratio rule give?
  1. P then Q.
  2. Q then P.
  3. Equal priority without a tiebreaker.
  4. Either order because both ratios exceed 1.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

At working day 12, an unfinished job is due at day 18 and has 8 days of work remaining. What is its critical ratio and status?
  1. 1.33; ahead of schedule.
  2. 2.25; ahead of schedule.
  3. 0.75; ahead of schedule.
  4. 0.75; behind schedule.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

In a Johnson placement step, the unique smallest remaining time belongs to job H at the second work center. Where does H go?
  1. The latest open position.
  2. The earliest open position.
  3. After the last front job.
  4. Before the first front job.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A job finishes center 1 at hour 13. Center 2 finishes its preceding job at hour 16, and this job needs 5 hours there. When does it finish center 2?
  1. Hour 18.
  2. Hour 21.
  3. Hour 16.
  4. Hour 29.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A finite schedule uses a machine for all 7 available hours on Thursday. An extra 2-hour repair is then scheduled that day. What must the planner do to keep the schedule feasible?
  1. Keep all work in Thursday’s 5 productive hours.
  2. Record 9 productive hours within the existing shift.
  3. Move work or provide 2 hours of effective capacity.
  4. Raise release quantities while retaining every slot.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A seven-day service needs 2, 4, 4, 4, 4, 2, 1 staff from Monday to Sunday. Each employee works five days with two consecutive days off. The heuristic first assigns Sun–Mon off. What pair is lowest for the next employee, and what is the workforce lower bound?
  1. Sat–Sun; at least 5 employees.
  2. Sun–Mon; at least 5 employees.
  3. Sat–Sun; at least 4 employees.
  4. Fri–Sat; at least 5 employees.
Show answerHide answer

Save this lesson to see this answer.

Set 3: Compare schedules and coverage10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A center has 6 hours per day. Jobs requiring 4 and 5 hours are released Monday and processed in that order; a job can continue Tuesday. How does finite loading place the work?
  1. 4 hours of the first and 5 of the second on Monday; none Tuesday.
  2. 4 hours of the first on Monday; all 5 of the second on Tuesday.
  3. 5 hours of the second and 1 of the first on Monday; 3 Tuesday.
  4. 4 hours of the first and 2 of the second on Monday; 3 Tuesday.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

At the end of working day 4, order R was planned to have completed 3 days of work but has completed 2. Order S was planned to finish on day 3 and actually finished then. How should their progress be reported?
  1. R is two workdays behind; S finished on schedule.
  2. R is one workday behind; S is one day late.
  3. R is one workday behind; S finished on schedule.
  4. R is on schedule; S is one day ahead.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Three crews each take one distinct maintenance task. Expected hours of capacity restored on tasks 1, 2, 3 are A: 9, 6, 7; B: 10, 5, 9; C: 6, 8, 4. What assignment restores the greatest total capacity?
  1. A–1, B–3, C–2: 26 hours.
  2. A–3, B–1, C–2: 25 hours.
  3. A–2, B–1, C–3: 20 hours.
  4. A–1, B–2, C–3: 18 hours.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Three jobs are ready at time 0 at one work center and run without interruption or idle time. Their processing times and due hours are R (3, 12), S (6, 6), T (2, 5). Compare SPT and EDD on average flow time and maximum lateness.
  1. SPT: 6 hours and 2 late; EDD: 7 hours and 5 late.
  2. SPT: 6 hours and 5 late; EDD: 7 hours and 2 late.
  3. SPT: 7 hours and 5 late; EDD: 6 hours and 2 late.
  4. SPT: 6 hours and 5 late; EDD: 7 hours and 3 late.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Jobs arrive in the order N, J, L. Their processing times are 2, 7 and 4 hours. What sequence does FCFS give?
  1. N–J–L.
  2. J–L–N.
  3. N–L–J.
  4. J–N–L.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A two-center shop has jobs available from the start with known processing times. Some jobs visit center 1 then 2, while others visit center 2 then 1. What routing condition prevents a direct use of Johnson’s two-center rule?
  1. The jobs do not have equal total processing times.
  2. The centers do not have equal workloads.
  3. The jobs do not visit both centers in the same order.
  4. The jobs do not have matching due dates.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Three jobs all visit centers 1 then 2 under Johnson’s conditions: J (2, 6), K (5, 3), L (4, 5) hours. A planner proposes J–L–K. What makespan results, and is it minimum?
  1. 15 hours; it reaches a valid lower bound.
  2. 16 hours; it exceeds the lower bound by 2.
  3. 18 hours; it exceeds the lower bound by 2.
  4. 16 hours; it reaches a valid lower bound.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A sports center offers quieter-time bookings at a lower price to move some customers away from the evening peak. What scheduling response is this?
  1. Capacity management.
  2. Demand management.
  3. Priority dispatching.
  4. Finite resource loading.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A desk needs 4, 7 and 3 staff in three four-hour blocks. Four employees work 08:00–16:00 and three work 12:00–20:00. What is the shortage or surplus in these blocks?
  1. No shortage and no surplus in any block.
  2. One surplus at midday; no shortage elsewhere.
  3. One shortage at midday; no surplus elsewhere.
  4. One surplus in the morning; one shortage late.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A clinic has 20 appointment slots. Its historical no-show rate is 15%. What does that rate imply for 20 bookings?
  1. Exactly 17 patients will attend every session.
  2. Expected attendance is 23, with actual attendance varying.
  3. Three slots are guaranteed free for walk-ins every session.
  4. Expected attendance is 17, with actual attendance varying.
Show answerHide answer

Save this lesson to see this answer.

Set 4: Diagnose scheduling mistakes10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A center is fully occupied, but jobs spend most of their time waiting in its queue. Why can high resource utilization coexist with slow customer delivery?
  1. A large queue reduces the time each job waits before processing.
  2. A large queue keeps the resource fed while increasing job flow time.
  3. A busy resource makes its job completion times equal to processing times.
  4. A busy resource removes due dates as a scheduling criterion.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A job released at the beginning of day 5 needs two successive operations, each needing two uninterrupted working days. It is due at the end of day 10. The first center is unavailable on days 7 and 8, and both centers are otherwise free. What schedule meets the due date, and how much delay can its first operation absorb?
  1. First operation days 5–6; second 7–8; zero delay before the first.
  2. First operation days 5–6; second 7–8; two days before the first.
  3. First operation days 7–8; second 9–10; zero delay before the first.
  4. First operation days 9–10; second 11–12; two days before the first.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A center starts with 40 standard hours of backlog. Across two weeks, planned input/output are 100/110 and 120/120; actual input/output are 95/100 and 115/110. How far is the final backlog above or below plan, and what comparison explains it?
  1. 10 hours below; output fell 20 below plan while input fell 10.
  2. 20 hours above; output fell 20 below plan while input fell 10.
  3. 10 hours above; output fell 20 below plan while input fell 10.
  4. 10 hours above; input rose 10 above plan while output matched it.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

An unfinished job’s chart shows 18 standard hours completed at a review point when 24 were planned. Its planned finish is tomorrow. What status does the progress record show?
  1. On schedule because the due date has not passed.
  2. 6 standard hours ahead of planned progress.
  3. Late by one calendar day.
  4. 6 standard hours behind planned progress.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Two waiting jobs have the same processing time, and the shop uses SPT with FCFS as its tiebreaker. How is their order decided?
  1. The earlier arrival runs first.
  2. The later due date runs first.
  3. The earlier due date runs first.
  4. The alphabetically first label runs first.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A machine runs without idle time for 20 hours, finishing all jobs that were ready at time 0. Their flow times total 60 job-hours. What are the textbook utilization metric and average number of jobs in the system?
  1. 100% and 3 jobs.
  2. 33.3% and 3 jobs.
  3. 33.3% and one-third of a job.
  4. 300% and one-third of a job.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

At day 10, job A is due day 16 with 5 days of work remaining; B is due day 21 with 9 days remaining. Both wait one day without progress. How does their critical-ratio priority change?
  1. B leads initially; they tie at day 11.
  2. A leads initially; they tie at day 11.
  3. They tie initially; B leads at day 11.
  4. A leads initially and still leads at day 11.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

One work center limits system output. Another center has spare capacity and can reduce its own processing time by an hour without changing the bottleneck’s work. What immediate throughput change follows while the bottleneck remains the limit?
  1. One extra hour of system output becomes available.
  2. The bottleneck gains one hour of usable capacity.
  3. No increase in system output from that hour alone.
  4. The improved center becomes the new system bottleneck.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A service needs 3, 3, 4, 4, 3, 2, 1 staff Monday–Sunday. Each employee works five days with two consecutive days off. An off-pair plan has one employee off Mon–Tue, two off Fri–Sat and one off Sun–Mon. What is its coverage verdict?
  1. It covers every day with no surplus.
  2. It fails Friday despite supplying 20 staff-days.
  3. It fails Monday despite supplying 20 staff-days.
  4. It covers every day with one surplus staff-day.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A service needs 2 employees every day. Four repeating five-day employees have consecutive days off Mon–Tue, Wed–Thu, Fri–Sat and Sun–Mon. Does this plan cover demand, and does the weekly lower bound prove four are necessary?
  1. It covers demand, but the lower bound is only three.
  2. It covers demand, and the lower bound proves four.
  3. It misses Monday, and the lower bound is only three.
  4. It misses Sunday, and the lower bound proves four.
Show answerHide answer

Save this lesson to see this answer.

Set 5: Evaluate feasible alternatives10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

An infinite-loading plan assigns 26 standard hours to a center with 16 hours available before the due date. All work must use that center. What shortfall must a revised feasible plan address?
  1. 10 hours through added effective capacity or later completion.
  2. 26 hours through added effective capacity or later completion.
  3. 16 hours through added effective capacity or later completion.
  4. 42 hours through added effective capacity or later completion.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A reduced 3-by-3 assignment table has rows A: 0, 2, 5; B: 0, 3, 4; C: 6, 0, 0. All zeros are minimally covered by column 1 and row C. After the Hungarian adjustment, what independent zero assignment becomes available?
  1. A–1, B–2, C–3.
  2. A–3, B–1, C–2.
  3. A–2, B–1, C–3.
  4. A–2, B–3, C–1.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Three jobs are ready at time 0 at one work center and run without interruption or idle time. Their processing hours and due hours are A (2, 20), B (5, 6), C (4, 9). Compare SPT with EDD on average tardiness and maximum lateness.
  1. SPT: −16/3 hours and 5 hours; EDD: −10/3 and 0.
  2. SPT: 5/3 hours and 5 hours; EDD: 3 and 9.
  3. SPT: 0 and 0; EDD: 5/3 hours and 5 hours.
  4. SPT: 5/3 hours and 5 hours; EDD: 0 and 0.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Today is day 40. X is due day 44 with 2 days of work left; Y is due day 50 with 7 days left; Z is due day 46 with 4 days left. How do lowest-CR and smallest-slack priorities compare?
  1. CR puts X first; slack puts Z alone first.
  2. CR puts Y first; slack ties Z with X first.
  3. CR puts Y first; slack ties X with Y first.
  4. CR ties X with Z first; slack puts X alone first.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Jobs A (4, 8), B (7, 2), C (3, 6), D (5, 9) all meet Johnson’s two-center conditions. After applying the rule, which jobs immediately precede and follow D?
  1. C precedes D; A follows D.
  2. B precedes D; A follows D.
  3. A precedes D; B follows D.
  4. A precedes D; C follows D.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Three jobs visit centers 1, 2 and 3 in order. Their times are A (6, 2, 7), B (7, 4, 2), C (5, 1, 8) hours. All meet the standard flow-shop conditions. Use the three-center Johnson reduction if its time condition holds. What job sequence results?
  1. A–C–B.
  2. C–A–B.
  3. C–B–A.
  4. B–A–C.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A finite schedule repeatedly shows jobs finishing later than its calendar bars predict. The recorded run times are shorter than the times actually observed, and staff and machines follow the listed calendars. What input should the planner correct first?
  1. The standard run times used for loading.
  2. The capacity recorded in shift calendars.
  3. The standard setup times used for loading.
  4. The due dates used to rank the waiting jobs.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Forecast demand is 73 requests per hour and one employee handles 12 per hour. Ignoring breaks and arrival variation for this workload calculation, how many employees are required?
  1. 6 employees.
  2. 8 employees.
  3. 12 employees.
  4. 7 employees.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A desk needs 3, 6 and 4 staff in three four-hour blocks, 08:00–12:00, 12:00–16:00 and 16:00–20:00. It has 3 early 08:00–16:00 staff and 3 late 12:00–20:00 staff. Part-time four-hour staff may cover any one block. An early worker takes a full hour off at 12:00; all other breaks are already covered. What extra part-time cover is needed?
  1. One evening worker and no midday worker.
  2. One midday worker and one evening worker.
  3. One midday worker and no evening worker.
  4. Two evening workers and no midday worker.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A seven-day service needs one employee on Mon, Wed, Fri and Sun, and none on other days. All employees work five days with two consecutive days off. What is the minimum full-time workforce?
  1. 1 employee.
  2. 3 employees.
  3. 4 employees.
  4. 2 employees.
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

68 Key Terms, each with its definition

A

Appointment
An appointment reserves a time slot for a customer’s service with a provider, helping organize when service demand arrives.
A customer books a technician for a repair assessment at 14:00 on Thursday.
Assignment problem
An assignment problem matches jobs and resources one to one to minimize their total cost or time, or maximize total benefit.
Three inspectors each receive one task, with no task assigned twice in the matching.
Average completion time
Average completion time is the mean completion point; it equals average flow time when every job is available at time zero.
Finishes at hours 2, 5 and 11 average six hours for three initially available jobs.
Average jobs in the system
The average jobs in the system measures mean WIP; in a nonidle time-zero comparison it is summed flow time divided by processing time.
Thirty job-hours of flow time over a ten-hour schedule represent an average of three jobs.

B

Backlog
A backlog is work waiting to be completed at a resource, measured in jobs or a common workload unit such as standard hours.
A cell that ends Friday with 48 standard hours still waiting carries them into Monday’s plan.
Backward scheduling
Backward scheduling works from the due date through preceding operations to establish the latest start that meets the deadline.
A banquet team works back from the serving time to place preparation and cooking tasks.
Bottleneck
A bottleneck has less capacity than the workload placed on it and limits the output achievable by the operation.
Speeding up packing does not raise output while the slower coating stage remains the limit.

C

Capacity management
Capacity management changes the resources available to serve demand, using measures such as flexible shifts and cross-trained staff.
Two trained staff move from a quiet counter to the busy desk during the lunch peak.
ConWIP
ConWIP is a release-control system with a fixed number of circulating cards that caps the number of jobs in process.
Completing one job frees a card that permits the next waiting order to enter the system.
Critical ratio (CR)
The critical ratio divides the time until a job is due by its work time remaining, measuring its proportional schedule margin.
With six days until due and three days of work left, a job has a critical ratio of two.
Cumulative deviation
A cumulative deviation is the running total of actual minus planned work, showing the accumulated input or output gap.
Weekly output deviations of −3 and −5 hours leave a cumulative shortfall of 8 hours.
Cyclical scheduling
Cyclical scheduling builds a repeating staffing pattern, such as a seven-day service week with five working days per employee.
The same days-off pattern repeats next week, making Sunday and Monday adjacent.

D

Demand management
Demand management changes the timing or level of customer demand to fit capacity, including quieter-time bookings and off-peak offers.
A service encourages morning bookings to reduce its usual late-afternoon queue.
Detailed scheduling
Detailed scheduling sets the start and finish times of operations after their resources and processing order are chosen.
A cutting operation is placed at 09:00–11:00, followed by welding at 11:30–13:00.
Dispatching
Dispatching authorizes and releases work to be carried out, often through a list telling a center what to process next.
The supervisor releases the next order only after confirming its material is ready.
Drum-buffer-rope
Drum-buffer-rope coordinates bottleneck pace, a protective time buffer and controlled material release to support system flow.
Releases follow the constrained center’s pace so upstream queues do not grow without limit.
Dummy resource
A dummy resource is an added column that balances an assignment table and represents a job left unassigned in the period.
A fourth job matched to the dummy column waits because only three real machines are available.
Dynamic priority
A dynamic priority is a job ranking updated as time, remaining work or other relevant scheduling information changes.
A waiting order’s critical ratio falls as its deadline approaches without progress.

E

Earliest due date (EDD)
Earliest due date orders ready jobs by their delivery deadlines, with the earliest due job processed first.
A job due on day 9 takes priority over one due on day 12 even if it requires more work.
Expediting
Expediting tracks urgent or late work and takes action to help it progress through the operation.
A planner follows a delayed order through cutting and arranges its next available coating slot.

F

Finite capacity scheduling (FCS)
Finite capacity scheduling builds detailed operation slots that respect actual resource capacity, calendars and other availability constraints.
A breakdown removes two machine-hours and the software moves work into a later available slot.
Finite loading
Finite loading places work only within available resource capacity, moving work that does not fit into another feasible period.
A four-hour job uses today’s last two hours and continues for two hours tomorrow.
First come, first served (FCFS)
First come, first served processes jobs or customers in arrival order, giving the earliest arrival the next service position.
A counter serves a customer who arrived at 10:05 before one who arrived at 10:08.
Flow shop
A flow shop processes jobs through work centers in the same route order, such as cutting followed by coating.
Every job visits the printing press before the binding machine in a two-stage flow shop.
Flow time
A job’s flow time is the time from its availability until completion, including all waiting and processing in that interval.
A job waits three hours and runs for two, giving it a five-hour flow time.
Forward scheduling
Forward scheduling places operations as early as possible from the available start and establishes the earliest completion date.
A workshop schedules from today to find the soonest date it can offer for a new repair.

G

Gantt load chart
A Gantt load chart gives each resource a row and displays its planned work against time, exposing occupied and free periods.
On a load chart, a coating row shows maintenance Monday and open slots Tuesday, while the cutting row remains occupied.
Gantt schedule chart
A Gantt schedule chart gives jobs their own rows and compares planned timing with actual progress or completion.
An order’s actual progress bar ends two work-hours short of the planned progress at noon.

H

Heuristic
A heuristic is a practical procedure for finding a useful solution without guaranteeing the best possible result in every case.
In a weekly days-off heuristic, trying a different tied days-off pair can reduce the workforce it produces.
Hungarian method
The Hungarian method finds an optimal one-to-one assignment through row and column reductions and adjustments of reduced costs.
The planner creates independent zero cells before adding the chosen original processing times.

I

Idle time
Idle time is time within a stated observation horizon when a resource is not processing scheduled work.
A second machine waits two hours for the first job to arrive from the first machine.
Independent zeros
Independent zeros are zero cells selected so that no two share a row or column in an assignment table.
Three zeros all in one column cannot assign three jobs to three different machines.
Infinite loading
Infinite loading places required work into periods without enforcing the resource’s capacity limit, leaving overloads for review.
A plan puts 14 standard hours into a day when the center has only 8 available hours.
Input–output control
Input–output control compares planned and actual work releases and completions to monitor a center’s load and queue.
A weekly report shows that releases met plan but completions fell short for three weeks.

J

Johnson’s rule
Johnson’s rule minimizes makespan in the qualifying two-center flow shop by placing small first-stage times early and second-stage times late.
When the smallest time is at a second-stage binding machine, its job takes the last open position of the sequence.

L

Lateness
Lateness is a job’s completion time minus its due date, producing a negative value for early work and a positive value for late work.
Finishing at hour 7 against a due hour of 10 gives signed lateness of −3 hours.
Loading
Loading assigns work to resources or work centers and establishes how much work each must handle in a period.
The planner loads two cutting orders onto the same cell before deciding which runs first.
Longest processing time (LPT)
Longest processing time orders ready jobs from the largest processing requirement to the smallest at a work center.
A nine-hour job is placed before a four-hour job when the shop chooses LPT.
Lower bound
A lower bound is a limit below which an objective cannot fall; a feasible schedule reaching it proves optimality for that objective.
If a valid bound is 25 hours and a feasible plan takes 25, no shorter makespan is possible.

M

Makespan
The makespan is the elapsed time from the first job’s start to the final job’s finish in the schedule being measured.
Printing finishes at hour 18 but binding continues to hour 23, making the makespan 23 hours.

N

No-show rate
A no-show rate is the share of booked customers who do not attend, used to estimate attendance across comparable service periods.
A 10% no-show rate reduces expected attendance but does not guarantee empty slots today.

O

Occupancy
Occupancy is the share of available staff service time spent handling work, with spare time helping absorb variable arrivals.
A service chooses its occupancy target from a waiting-time goal rather than assuming full use.
Opportunity cost
An opportunity cost in a reduced assignment table measures a pairing’s extra cost relative to the reductions already made.
A reduced zero can be selected without extra reduced cost, although its original time is positive.
Opportunity loss
An opportunity loss in a converted benefit table is the largest table value minus a pairing’s benefit, ready for minimization.
A benefit of 9 becomes a loss of 5 when the largest benefit in the table is 14.

P

Priority rule
A priority rule ranks waiting jobs using selected attributes so that a work center can decide which job to process next.
The supervisor applies the same stated rule every time the machine becomes free.

R

Reservation
A reservation sets aside service capacity in advance for a stated date, time or period, such as a seat, room or rental car.
A customer reserves a vehicle for the weekend without booking continuous staff service.
Residual requirement
A residual requirement is daily cover still needed after scheduled employees are counted; a negative value records surplus.
When one more worker is scheduled for Tuesday, a residual of three employees that day falls to two.
Review-date line
A review-date line marks the current time on a Gantt chart so actual progress can be compared with what was planned by then.
At Wednesday’s review line, an unfinished job has completed less work than expected.
Routing
A routing lists an item’s operations in order, with the work centers and standard setup and run times they require.
A part’s routing sends it through cutting, drilling and finishing before inspection.

S

Sequence-independent setup
A sequence-independent setup takes the same time for a job regardless of which job was processed immediately before it.
Including a fixed setup in each job’s processing time preserves the Johnson comparison conditions.
Sequencing
Sequencing chooses the order in which waiting jobs or customers are processed by a resource.
A dispatch list places the shortest repair ahead of a longer one waiting at the same bench.
Shift coverage
Shift coverage is the number of available employees supplied by overlapping shifts in each demand period.
Two early and three late employees give five at midday, before subtracting breaks.
Shop calendar
A shop calendar numbers working days consecutively so that scheduling arithmetic skips weekends, holidays and other nonworking days.
Day 12 follows day 11 in the plan even when a weekend separates them on the civil calendar.
Short-term scheduling
Short-term scheduling assigns specific jobs, customers or staff to resources, sequences and times over hours, days or a few weeks.
A print shop reserves press 2 for a named order from 08:00 to 11:30 on Monday.
Shortest processing time (SPT)
Shortest processing time orders ready jobs from the shortest processing requirement to the longest at a work center.
A two-hour task runs before a five-hour task when both are ready and SPT applies.
Slack
Slack is the time available beyond the work needed: time until due minus remaining work, measured on a consistent calendar.
A job due in eight working days with six days of work remaining has two days of slack.
Staff-day
A staff-day is one employee’s cover for one working day, used to compare total weekly staffing supply with daily requirements.
Seven five-day employees provide 35 staff-days, which must also fall on the required days.
Staff-hour
A staff-hour is one employee’s scheduled work for one hour, used to total staffing across employees and shift durations.
Four staff working a three-hour block supply twelve staff-hours in that period.
Staffing requirement
A staffing requirement is the whole-person cover needed in a period, calculated from workload and employee output and rounded up.
A forecast of 61 customers per hour at 15 per employee requires five employees.
Staffing surplus
A staffing surplus is available cover above a period’s requirement; it may provide relief, training time or other useful work.
Six available staff against a requirement of five leave one surplus for that block.
Standard hour
A standard hour measures workload using the expected work content at standard performance, allowing different jobs to be added.
Ten standard hours may be spread across several small orders or concentrated in one large order.

T

Tardiness
Tardiness counts only late time: it is completion minus due date when positive, and zero for a job that is early or on time.
A job that finishes three days early contributes zero to a total of late days.
Time buffer
A time buffer protects the bottleneck by arranging work ahead of its scheduled need, reducing the chance that it waits for input.
Parts are ready before the constrained machine needs them, absorbing a short upstream delay.

U

Utilization metric
The utilization metric in priority-rule comparisons divides total processing time by summed flow time, measuring flow efficiency.
A busy machine can have a low utilization metric when several jobs wait a long time for it.

V

Virtual work center
A virtual work center combines real processing times for a qualifying scheduling reduction and does not represent a physical resource.
Reducing a three-center flow shop to two centers adds adjoining operation times to create two virtual times for each job.

W

What-if scheduling
What-if scheduling compares the effects of proposed resource, timing or priority changes before a revised schedule is adopted.
A planner tests Tuesday overtime and checks which customer orders would then finish on time.
Work center
A work center is a resource or group of resources to which operations are assigned and for which capacity is recorded.
The welding cell has its own shift calendar, available standard hours and queue of jobs.
Work-in-process (WIP)
Work-in-process is work that has entered the production system but is not yet finished, including jobs waiting between operations.
Cut parts waiting for welding remain in WIP even while no machine is processing them.

About this lesson