Short-Term Scheduling
IntermediateLesson 8 of 9 in Operations Management Course
What you will learn
- Place short-term scheduling within operations planning, name the decisions it makes and the criteria used to judge a schedule, and choose a scheduling direction and loading approach.
- Place short-term scheduling in operations planningDescribe how capacity, aggregate, master and material plans lead to day-to-day schedules, and name the scheduling decisions and criteria in different kinds of operations.
- Choose forward or backward scheduling and finite or infinite loadingSchedule a job forward from today or backward from its due date, and explain how loading with or without capacity limits changes the schedule.
- Place short-term scheduling in operations planning
- Assign work to work centers and keep their loads under control with input–output reports, Gantt charts and the assignment method.
- Control work-center loads with input–output reportsCompare planned and actual input and output at a work center, track cumulative deviations and the backlog, and decide how to respond.
- Read and build Gantt load and schedule chartsUse Gantt load charts to show how busy each work center is and Gantt schedule charts to track whether jobs are on time.
- Assign jobs to resources with the assignment methodUse the assignment (Hungarian) method to match jobs to machines, workers or sites one to one at the lowest total cost or time, including maximization and unequal numbers.
- Control work-center loads with input–output reports
- Order the jobs waiting at one work center with priority rules, compare the resulting schedules with standard measures and use the critical ratio to keep priorities up to date.
- Apply the basic priority rulesSequence waiting jobs by first come, first served, shortest processing time, earliest due date and longest processing time.
- Compare sequences with performance measuresCompute flow time, average completion time, the utilization metric, the average number of jobs in the system and lateness for a sequence, and explain which rule does best on which measure.
- Sequence dynamically with the critical ratioCalculate and interpret critical ratios, sequence jobs by them, and explain why the ratio is recalculated as work progresses.
- Apply the basic priority rules
- Sequence jobs through two work centers with Johnson's rule, check the schedule's makespan and idle time, and use finite capacity scheduling when simple rules are not enough.
- Sequence two-stage jobs with Johnson's ruleApply Johnson's rule step by step to order jobs that pass through the same two work centers.
- Check a two-machine schedule for makespan and idle timeCalculate start and finish times, the makespan and idle time for a two-work-center sequence, compare sequences and know where Johnson's rule stops applying.
- Use finite capacity schedulingExplain the limits of simple priority rules and how finite capacity scheduling systems build feasible schedules from real capacity and shop-floor data.
- Sequence two-stage jobs with Johnson's rule
- Choose how a service schedules its customers, convert demand forecasts into staffing requirements and shift plans, and build weekly schedules that give employees consecutive days off.
- Choose a scheduling approach for a serviceExplain how service scheduling differs from manufacturing and choose between appointments, reservations, first come, first served, priority and demand management.
- Turn demand forecasts into staffing plansConvert forecast demand per period into the number of staff needed, cover it with full-time and part-time shifts, and check the plan for shortages and surplus.
- Build weekly schedules with consecutive days offUse the cyclical scheduling method to cover daily staffing requirements in a seven-day operation while giving each full-time employee two consecutive days off.
- Choose a scheduling approach for a service
Short-Term Scheduling study guide
1Make daily scheduling decisions
Every daily schedule sits inside decisions already made about facilities, output and materials. Learn how those plans become assignments to specific people and machines, and how delivery, waiting, WIP and utilization shape the choice. Then use forward and backward scheduling to find completion and start dates, and distinguish the direction of scheduling from the decision to enforce resource capacity.
1.1 From operations plans to daily assignments
A production plan says what an operation needs to deliver. A short-term schedule turns that plan into named jobs, resources, people and times over hours, days or a few weeks. A print shop might assign order 418 to press 2 from 08:00 to 11:30 on Monday, then run order 421.
Follow the planning hierarchy
Longer-range decisions establish the space within which a scheduler works.
| Planning level | Main decision | Typical horizon |
|---|---|---|
| Capacity | Facilities and major equipment | Years |
| Aggregate plan | Output, workforce and inventory for product families | Roughly 3–18 months |
| Master production schedule | Specific products and production weeks | Weeks |
| Material requirements planning (MRP) | Dated component orders | Linked to the master schedule |
| Short-term schedule | Specific resources, sequences and time slots | Hours to a few weeks |
A scheduler can change a sequence, arrange overtime, add a shift or subcontract work. A new building or major machine needs a higher-level capacity decision. Repeated overloads therefore need feedback to the plans above the daily schedule.
Separate the scheduling decisions
Loading assigns work to centers. Sequencing orders the waiting jobs at each center. Detailed scheduling adds start and finish times. Dispatching releases work through instructions such as a dispatch list. Expediting follows urgent or late jobs and helps them move through the operation. A dispatch list contains a sequence, which is why priority rules are also called dispatching rules.
These decisions need reliable data. The item master identifies products and parts. A routing lists their operations in order, with work centers and standard setup and run times. The work-center master records capacity, efficiency and queues. Actual completion records show whether the schedule is being achieved.
Decide what a good schedule means
Four common aims are short average completion time, high resource utilization, low work-in-process inventory (WIP) and short customer waits. They can conflict: a queue that keeps an expensive machine busy also keeps jobs waiting. Choose measures that fit the operation's service promise and cost structure.
Flow time records the time a job spends waiting and being processed. Delivery performance compares completion with the due date. A job can wait several days and still finish early, so queue waiting and lateness measure different things.
Match the process
A job shop handles varied jobs with different routings. It needs order-by-order schedules and close attention to delivery dates. A repetitive assembly operation coordinates modules, final assembly and frequent parts deliveries. A continuous operation, such as a paper mill, concentrates on production runs and changeovers within established capacity.
Aggregate planning works with product families months ahead. Project scheduling coordinates the linked activities of a unique project. Confusing either with daily operations scheduling leads to decisions at the wrong level: changing tomorrow's dispatch list cannot resolve a permanent capacity shortage.
Key Takeaways
- Short-term schedules assign specific work, resources and times.
- Loading, sequencing, detailed scheduling, dispatching and expediting make different decisions.
- Routes, capacity records and actual progress must agree with shop-floor conditions.
- Select performance measures that reflect the operation’s priorities.
1.2 Choose a direction and respect capacity
A job can be scheduled from its release date or from its due date. Separately, its resource load can be placed with or without a capacity limit. Scheduling direction and loading approach answer different questions.
Start now or work back from delivery
Forward scheduling places operations as early as possible from the time requirements are known. It finds the earliest completion and helps answer a customer asking for the soonest delivery. Early completion can build WIP or finished inventory.
Backward scheduling places the last operation to finish on the due date, then works backward through the routing. It finds the latest start and suits a fixed event or an MRP-driven order. Starting at that latest time leaves no slack to absorb a delay.
Use a shop calendar of consecutively numbered working days. A nonworking weekend does not consume two numbered days. Also distinguish the beginning from the end of a day when counting a job that occupies full days.
A job needs cutting for 2 days, machining for 3 days and painting for 1 day, and is due at the end of day 20:
| Operation | Backward schedule | Forward from day 10 |
|---|---|---|
| Cutting | Days 15–16 | Days 10–11 |
| Machining | Days 17–19 | Days 12–14 |
| Painting | Day 20 | Day 15 |
Backward scheduling gives a latest start at the beginning of day 15. Forward scheduling gives earliest completion at the end of day 15. The gap from that completion to the end of day 20 is 5 working days of slack. The gap between the earliest and latest starts is also 5 days.
Load work with or without a ceiling
Infinite loading assigns the required work to periods without enforcing resource capacity. It makes overloads visible for a later capacity check. Finite loading places work only in available capacity, accounting for setup and run times. Work that cannot fit must move or receive extra capacity.
A center has 8 hours per day. Jobs J1, J2 and J3 are released Monday, in that priority order, requiring 5, 4 and 6 hours. They may continue the next day. Infinite loading puts 15 hours on Monday:
Finite loading places J1 and 3 hours of J2 on Monday. Tuesday holds the remaining hour of J2 and all 6 hours of J3, leaving 1 hour free. Every scheduled hour now fits the center's calendar.
Check both feasibility and delivery
A finite schedule can be feasible and still miss a due date. If J3 was promised for Monday, moving it to Tuesday solves the overload but misses that promise. Infinite loading can retain planned dates while hiding a conflict; it also cannot make a late release overcome an insufficient processing window.
Planners often use both directions: forward to establish an achievable promise, backward to establish a latest start. Either direction can use finite capacity. For example, backward finite scheduling moves an operation earlier when its preferred resource slot is already full.
Key Takeaways
- Forward scheduling finds early completion; backward scheduling finds the latest start.
- Slack is the gap between earliest completion and the due date.
- Infinite loading reveals required load without enforcing capacity.
- Finite loading respects capacity but can move completion beyond a due date.
- Direction and loading can be combined independently.
2Load and assign work
Loading decisions connect available resources with the work waiting to be done. Compare planned releases and completions to understand queues, use Gantt charts to see workload and progress, and solve one-to-one assignments with the Hungarian method. Each view answers a different practical question: whether work is accumulating, when a resource is occupied, or which combination of job–resource matches gives the smallest total.
2.1 Track releases, output and the queue
A work center needs enough incoming work to stay productive, but releasing work faster than it can finish only builds a queue. Input–output control compares planned and actual releases and completions, period by period. Standard hours let jobs of different sizes be added on one common basis.
Keep a running balance
Input is work released to the center; output is work completed. The backlog changes according to:
For each input and output row, calculate deviation as actual minus planned. Add each new deviation to the previous cumulative deviation. A single weak week may be temporary; a growing cumulative shortfall needs investigation.
A welding cell starts with 60 standard hours of backlog:
| Week | Planned input | Actual input | Planned output | Actual output | Ending backlog |
|---|---|---|---|---|---|
| 1 | 200 | 190 | 210 | 200 | 50 |
| 2 | 200 | 210 | 210 | 195 | 65 |
| 3 | 220 | 200 | 220 | 215 | 50 |
| 4 | 220 | 230 | 220 | 225 | 55 |
Week 1 ends with hours. Week 2 starts with those 50 hours, so its balance is . Always carry the latest backlog forward.
Input deviations are −10, +10, −20 and +10 hours; their running totals are −10, 0, −20 and −10. Output deviations are −10, −15, −5 and +5, with running totals −10, −25, −30 and −25.
Interpret the gap against the plan
Total planned input is 840 hours and planned output is 860. The planned final backlog is hours. Actual input totals 830 and actual output 835, leaving 55 hours. The actual backlog is 15 hours above plan even though it has fallen from its initial 60 hours.
Input is only 10 hours below plan, while output is 25 below. Check lost capacity first: breakdowns, absence or poor efficiency may explain the shortfall. Also inspect when work arrived and whether its mix suited the cell. Weekly totals can conceal a shortage early in the week followed by a late surge.
Responses should follow the cause. Repair a recurring failure, add effective capacity or hold back new releases when the center is overloaded. When input is too low, check upstream centers for missing work. Sending more jobs into a center already above capacity does not increase what it can complete.
Connect backlog to waiting
At an output rate of about 220 standard hours per week, a 55-hour queue represents roughly week, or 1.25 working days in a five-day week. This is a rough waiting estimate based on the output rate; individual jobs also depend on their priority.
ConWIP, constant work in process, controls releases with a fixed number of cards. A job needs a free card to enter, and finishing a job frees its card. The circulating cards cap the number of jobs in the system and help limit queues and lead times.
Key Takeaways
- Update backlog using actual input and output.
- Cumulative deviations reveal a continuing gap against the plan.
- Compare actual backlog with planned backlog before judging performance.
- Investigate timing and job mix as well as lost capacity.
- ConWIP ties new releases to completed work.
2.2 Use Gantt charts to see load and progress
A Gantt chart places bars against a time scale. Henry Gantt developed these charts in the 1910s. In operations, their value is immediate: a supervisor can see the jobs occupying a resource or compare an order's progress with its plan.
Give the rows the right meaning
| Chart | One row represents | Main question |
|---|---|---|
| Load chart | A machine, department or work center | What occupies this resource, and when is it free? |
| Schedule chart | A job or order | Is this job progressing as planned? |
For a load chart, list the work centers and available capacity. Place each operation with its setup and processing time, following the routing. A job's second operation cannot start before its first ends. Mark maintenance and other unavailable periods before filling the remaining slots.
A weekly load chart might show:
| Resource | Monday | Tuesday | Wednesday | Thursday | Friday |
|---|---|---|---|---|---|
| Cutting | Job 101 | Job 101 | Job 102 | Job 102 | Job 102 |
| Welding | Free | Free | Job 101 | Job 101 | Job 101 |
| Painting | Maintenance | Free | Free | Free | Free |
Welding waits for cut parts early in the week. Painting has capacity after maintenance. A free cell identifies an available resource period, although a job still needs the correct routing, skills and materials to use it. Overlapping demands on one machine reveal a conflict that a feasible detailed schedule must resolve.
Compare actual work with the review point
A schedule chart records planned starts and finishes, actual progress and a vertical current-date line. For an unfinished job, compare actual work with the amount planned by that date. Comparing only the end of the actual bar with the date line can mislead: some completed jobs should already lie entirely to its left.
At the end of Wednesday, consider three orders. A was planned Monday through Thursday, but only Monday's and Tuesday's work is complete: it is one day behind. B was planned Tuesday through Wednesday and is finished: it is on schedule. C was planned Wednesday through Friday, with one day of work expected by now; it has completed one and a half days, so it is half a day ahead.
For a finished job, compare its actual finish with the planned finish. For a partially finished job, shading should represent the work completed on a consistent scale; elapsed calendar time alone is not completed work.
Keep the chart useful
A chart displays a chosen schedule. It does not calculate the best assignment or sequence. Update it when work finishes, a machine fails or priorities change. With many jobs, electronic charts are easier to revise and inspect than a crowded paper chart.
Operations charts show recurring jobs sharing resources. A project chart shows linked activities of a particular project. The same bar format can serve both settings, but the scheduling decisions behind the bars differ.
Key Takeaways
- Load-chart rows represent resources; schedule-chart rows represent jobs.
- Respect routing order and unavailable time when placing operations.
- Judge unfinished jobs against planned progress at the review date.
- Judge finished jobs by actual versus planned finish.
2.3 Find the best one-to-one assignment
The assignment problem matches each job to one resource and each resource to one job. The aim is the smallest total time or cost, or the largest total benefit. Four jobs already have 24 possible assignments; ten have more than 3.6 million. The Hungarian method finds an optimum without listing all of them. Harold Kuhn published it in 1955, building on work by Dénes Kőnig and Jenő Egerváry.
Reduce the table without changing the best match
Subtracting a constant from every cell of one row changes every complete assignment total by that same constant. The same holds for a column. The ranking of complete assignments therefore stays unchanged. Reduced cells represent opportunity costs; a zero offers no extra cost in that reduced table.
For minimization:
- Subtract each row's minimum from its cells.
- Subtract each resulting column's minimum from its cells.
- Cover every zero with the fewest horizontal and vertical lines.
- If fewer lines than rows suffice, subtract the smallest uncovered value from all uncovered cells. Add it only at crossings of two lines; leave singly covered cells unchanged. Repeat the cover test.
- Once the minimum cover needs as many lines as rows, choose independent zeros: one per row and column. Start with a forced single zero. If a choice leaves a later row with no available zero, undo it and choose another; no row or column may be reused. Total the selected original values.
Work through a conflict
Four jobs can run on four machines. Times are hours:
| Job | M1 | M2 | M3 | M4 |
|---|---|---|---|---|
| J1 | 6 | 10 | 12 | 15 |
| J2 | 12 | 5 | 15 | 7 |
| J3 | 5 | 9 | 13 | 12 |
| J4 | 5 | 6 | 9 | 5 |
Row minima are 6, 5, 5 and 5. After row reduction, only column M3 has a positive minimum, 4. Subtracting it gives:
| Job | M1 | M2 | M3 | M4 |
|---|---|---|---|---|
| J1 | 0 | 4 | 2 | 9 |
| J2 | 7 | 0 | 6 | 2 |
| J3 | 0 | 4 | 4 | 7 |
| J4 | 0 | 1 | 0 | 0 |
M1 and rows J2 and J4 cover all zeros with three lines. J1 and J3 compete for their only zero, M1, so four assignments are not yet possible. The smallest uncovered value is 2. After adjustment:
| Job | M1 | M2 | M3 | M4 |
|---|---|---|---|---|
| J1 | 0 | 2 | 0 | 7 |
| J2 | 9 | 0 | 6 | 2 |
| J3 | 0 | 2 | 2 | 5 |
| J4 | 2 | 1 | 0 | 0 |
Choose J3–M1, J1–M3, J2–M2 and J4–M4. Original times total hours. Assigning every row its cheapest original cell would have given M1 to several jobs, violating the one-to-one rule.
Adapt the table
For maximization, subtract every value from the table's largest value, then minimize these opportunity losses. Each complete assignment selects the same number of cells, so minimizing total loss maximizes total benefit.
Add zero-valued dummy rows or columns to make an unequal table square. A dummy job leaves a resource unused; a dummy resource leaves a job unassigned this period. This zero treatment fits a model with no penalty for that idle or deferred assignment.
Mark an impossible pairing with a penalty large enough to make any allowed complete assignment preferable. Check that the final solution contains no forbidden cell: if none of the allowed complete assignments is feasible, a penalty cannot create one.
Key Takeaways
- A complete assignment uses each row and column once.
- Row and column reductions preserve the best complete assignment.
- The cover test uses the minimum number of lines.
- Adjust uncovered cells and line crossings differently.
- Calculate the final total from original values.
- Convert maximization and balance unequal tables before solving.
3Sequence jobs at one work center
The order of waiting jobs changes how long customers and materials remain in the system. Apply common priority rules to a shared job list, turn their sequences into completion and delivery measures, and choose a rule that fits the objective. Critical ratio and slack then add a changing view of urgency as due dates approach and work progresses; a job’s priority must reflect what still needs to be done.
3.1 Order a queue with priority rules
When several jobs are ready for one work center, a priority rule decides which runs next. A rule makes the dispatch list consistent, but different rules protect different goals. Choose the rule before sorting the jobs.
State the comparison conditions
The standard comparison uses one work center with all jobs available at time 0. Processing times are known, include setup and do not change with the sequence. The center handles one job at a time and finishes a started job without interruption. These conditions matter when comparing the rules' performance.
| Rule | Sort by | Main emphasis |
|---|---|---|
| First come, first served (FCFS) | Arrival, earliest first | Arrival-order fairness |
| Shortest processing time (SPT) | Processing time, smallest first | Short average flow time |
| Earliest due date (EDD) | Due date, earliest first | Delivery dates |
| Longest processing time (LPT) | Processing time, largest first | Starting long jobs early |
FCFS is easy to explain when customers see the queue. SPT clears many small jobs quickly, although long jobs can wait. EDD gives priority to the earliest delivery promise. LPT sometimes starts large or important work early, but performs poorly on many single-center time measures.
Sort the same jobs four ways
Jobs arrived A, B, C, D, E and are all waiting at day 0:
| Job | Processing days | Due day |
|---|---|---|
| A | 2 | 14 |
| B | 7 | 7 |
| C | 6 | 10 |
| D | 9 | 18 |
| E | 5 | 8 |
FCFS keeps A–B–C–D–E. The labels happen to be alphabetical, but arrival order is the reason. SPT sorts processing days 2, 5, 6, 7, 9, giving A–E–C–B–D. EDD sorts due days 7, 8, 10, 14, 18, giving B–E–C–A–D. LPT sorts processing days 9, 7, 6, 5, 2, giving D–B–C–E–A.
Check the column you are sorting. The earliest due job need not be the shortest job: B is due first but requires 7 days. Reversing EDD would sort late due dates first; it would not produce LPT, which ignores due dates.
Handle ties and changing queues
State a tiebreaker before applying a rule. If two jobs take 3 hours under SPT, FCFS can decide between them. A clear tiebreaker keeps the rule reproducible without pretending that it ranks information it never considers.
Other priorities may use critical ratio, smallest slack, customer importance or a shared setup with the previous job. These use different job attributes and can produce different lists. Record any change in the rule so that supervisors understand why a job moved.
Use one time basis throughout. A due day on a working-day calendar cannot be compared directly with a calendar date that includes closures. In a live shop, new arrivals and changes in remaining work require a fresh dispatch decision; a sequence chosen at the start is not a permanent plan for every future job.
Key Takeaways
- FCFS sorts arrivals; SPT and LPT sort processing times; EDD sorts due dates.
- Use the same working-time basis for every job.
- State how tied priorities will be resolved.
- Choose the rule to fit the performance objective.
3.2 Measure flow time, WIP and delivery
An ordered list becomes useful when its consequences are measured. Flow time runs from a job's availability to its completion, including waiting and processing. When all jobs are ready at time 0, flow time equals completion time. Makespan is the time when the last job finishes.
Build completion times first
For the five jobs A–E, processing days are 2, 7, 6, 9 and 5; due days are 14, 7, 10, 18 and 8. FCFS gives:
| Job | Completion / flow time | Lateness | Tardiness |
|---|---|---|---|
| A | 2 | −12 | 0 |
| B | 9 | 2 | 2 |
| C | 15 | 5 | 5 |
| D | 24 | 6 | 6 |
| E | 29 | 21 | 21 |
Each completion adds the next processing time to the previous completion. Total flow time is 79 job-days, while actual processing totals 29 days. Waiting accounts for the difference.
Lateness is completion minus due date and can be negative. Tardiness counts late time only:
The priority-rule measure called “average job lateness” uses tardiness. An early job contributes zero; it cannot cancel another job's delay.
Calculate the comparison measures
For a continuously busy center with all jobs available at time 0:
FCFS gives 15.8 days average completion, a 36.7% utilization metric, 2.72 average jobs and 6.8 days average tardiness. The largest lateness is 21 days.
The utilization metric above is a textbook flow-efficiency measure. It is reciprocal to average jobs in the system. Machine busy time is a different measure: this machine works all 29 days under every sequence, even though the utilization metric changes.
Compare the rules
| Rule | Sum of flow times | Average completion | Utilization metric | Average jobs | Average tardiness | Maximum lateness |
|---|---|---|---|---|---|---|
| FCFS | 79 | 15.8 | 36.7% | 2.72 | 6.8 | 21 |
| SPT | 71 | 14.2 | 40.8% | 2.45 | 5.4 | 13 |
| EDD | 86 | 17.2 | 33.7% | 2.97 | 5.8 | 11 |
| LPT | 103 | 20.6 | 28.2% | 3.55 | 11.0 | 19 |
Times are working days. SPT wins the average-flow measures; EDD gives the smallest worst delay. Under the comparison conditions, SPT minimizes average flow time, waiting time and average jobs. EDD minimizes maximum lateness.
Neither guarantees minimum total tardiness. Here B–E–A–C–D has 25 late days, fewer than SPT's 27. Every nonidle sequence still has a 29-day makespan. Changing the order changes who waits, not the total single-machine processing requirement.
SPT can repeatedly delay long work when short jobs keep arriving, so a waiting-time limit can protect those jobs. Select the criterion first, then compare the appropriate results.
Key Takeaways
- Flow time includes waiting as well as processing.
- Lateness can be negative; tardiness cannot.
- “Average job lateness” in these comparisons means average tardiness.
- The utilization metric is not machine busy-time percentage.
- SPT minimizes average flow measures; EDD minimizes maximum lateness under the comparison conditions.
- Neither SPT nor EDD guarantees minimum total tardiness.
3.3 Update urgency with critical ratio and slack
A job due soon may need little work; another due later may need much more. The critical ratio (CR) compares the time available with the work remaining, putting both on a common scale.
Calculate and interpret the ratio
Use the same time unit in the numerator and denominator. Subtract today before dividing, and use remaining work, not the job's original processing requirement.
| Critical ratio | Meaning |
|---|---|
| Greater than 1 | More time than work remains; ahead of schedule |
| Equal to 1 | Time and work are equal; exactly on schedule |
| Between 0 and 1 | Insufficient time remains at the planned rate; behind schedule |
| Equal to 0 | Due today |
| Negative | Due date has passed |
The rule gives the lowest ratio first. A high ratio indicates more time relative to remaining work, so it gives lower urgency under this rule.
Rank four jobs
Today is day 30:
| Job | Due day | Work remaining | CR | Slack |
|---|---|---|---|---|
| P | 36 | 4 days | 1.5 | 2 days |
| Q | 33 | 5 days | 0.6 | −2 days |
| R | 38 | 8 days | 1.0 | 0 days |
| S | 29 | 2 days | −0.5 | −3 days |
For P, . For S, . The priority order is S–Q–R–P: overdue S, then behind-schedule Q, exactly-on-schedule R and ahead-of-schedule P.
Recalculate when the next decision is made
CR is dynamic. When a center is ready for its next job, update both the date and remaining work. A job that waited has less time available but the same work; its ratio falls. A job that progressed can have a higher ratio because its denominator shrank.
For example, at day 31, P with no progress has . If it instead has only 3 days of work remaining, its ratio is . The date alone does not tell you its new status. Updated due dates from MRP can also change the ranking.
Compare CR with slack
Slack measures spare time in days or hours; CR is a ratio with no unit. The example gives the same order under smallest slack, but the rules can disagree. A 1-day job with 2 spare days has CR 3; a 20-day job with the same 2 spare days has CR 1.1. Equal slack is a much thinner proportional margin on the long job. A related rule divides slack by the number of operations still required.
CR helps compare make-to-stock and make-to-order jobs and track changes in urgency. It still looks at each job's due date and remaining work. Congestion at a later center and customer importance require additional information in the overall schedule.
Key Takeaways
- Compute CR as time until due divided by remaining work.
- Process the lowest critical ratio first.
- Recalculate both date and remaining work at each dispatch decision.
- Slack is spare time; critical ratio measures the proportional margin.
- CR does not account for downstream congestion or customer importance.
4Coordinate machines within capacity
Jobs that visit several machines need more than a ranked queue. Their operations must fit together in time and stay within available capacity. Use Johnson’s rule to build a two-stage sequence, calculate its makespan and idle time, and check a lower bound. Then see how finite capacity scheduling responds to breakdowns, shared resource limits and bottlenecks that a local dispatch rule cannot fully capture.
4.1 Build a two-machine sequence with Johnson’s rule
Jobs passing through two work centers can overlap: while one job uses the second center, another uses the first. Their order controls how much the second center must wait. Johnson's rule, published by S. M. Johnson in 1954, finds a sequence with minimum makespan, from the first start to the final finish.
Check the operating conditions
Every job must visit center 1 and then center 2 in that order. All jobs are available at the start. Processing times are known and constant; setup is included and does not depend on the sequence. Each center processes one job at a time without interrupting it, and each job must finish its first operation before starting its second. Jobs can wait between centers.
The objective is to finish the whole set as early as possible. Due dates do not enter the rule. A sequence with minimum makespan may still deliver a particular job late.
Fill positions from both ends
- List both processing times for every unscheduled job.
- Find the smallest individual time anywhere in that list.
- If it belongs to center 1, put its job in the earliest open position.
- If it belongs to center 2, put its job in the latest open position.
- Remove the entire job and repeat until all positions are filled.
The last position may be filled before the middle positions. “Choose next” means the next placement decision, not necessarily the next job to run.
Work a five-job example
A print shop prints and then binds each job. Times are hours:
| Job | Printing | Binding |
|---|---|---|
| A | 4 | 9 |
| B | 7 | 6 |
| C | 7 | 5 |
| D | 9 | 8 |
| E | 2 | 4 |
The smallest time is E's 2 hours at printing, so place E first. Remove E, including its binding time. The smallest remaining time is A's 4 hours at printing, so place A second.
C's 5 hours at binding is now smallest, so place C last. B's 6 hours at binding is next, so put B in the latest open position, immediately before C. D occupies the remaining middle position. The completed sequence is E–A–D–B–C.
A short first operation near the front feeds the second center early. A short second operation near the back helps that center finish soon after the first center finishes its work. Sorting the sum of each job's two times would lose this distinction between the stages.
Resolve ties without changing the objective
When different jobs share the smallest time, either can be selected first; the resulting Johnson sequences have the same minimum makespan. If a job's minimum is tied across its two centers, either end is allowed. Write down the chosen placement so later timing follows the same sequence.
Do not schedule a selected job twice by leaving its other time in the candidate list. Also check routings before using the rule: a job that visits binding before printing belongs to a different scheduling problem.
Key Takeaways
- Johnson’s rule minimizes makespan for the two-stage flow-shop conditions.
- Choose the smallest individual remaining processing time.
- A first-center minimum goes at the front; a second-center minimum goes at the back.
- Remove a job completely after placing it.
- Johnson ties can produce different optimal sequences.
4.2 Time the sequence and verify its makespan
A sequence says which job comes next. To find its makespan, calculate when each operation can actually start. The second work center needs both a free machine and a job that has completed its first operation.
Respect both release conditions
Run center 1 back to back from time 0. For each job at center 2:
Here is its second-center start, its first-center completion and the preceding job's second-center finish. Add its second processing time to find its finish. Any gap between the previous finish and the new start is idle time.
For the print shop's Johnson sequence E–A–D–B–C:
| Job | Printing | Binding |
|---|---|---|
| E | 0–2 | 2–6 |
| A | 2–6 | 6–15 |
| D | 6–15 | 15–23 |
| B | 15–22 | 23–29 |
| C | 22–29 | 29–34 |
B finishes printing at 22 but waits until binding becomes free at 23. D starts binding at 15 because both the job and the machine become available then. The makespan is 34 hours.
Account for idle time over the same horizon
Binding performs 32 hours of work. Over the 34-hour schedule, its idle time is hours, all before E arrives. Printing performs 29 hours, leaving 5 hours of idle time at the end if it is measured over that same 34-hour horizon.
Arrival order A–B–C–D–E has printing completions 4, 11, 18, 27 and 29. Binding runs 4–13, 13–19, 19–24, 27–35 and 35–39. It waits 4 hours initially and 3 hours before D, totaling 7 idle hours. Johnson's order saves 5 hours of makespan, about 12.8% of 39.
Starting every second operation as early as possible does not eliminate these gaps. A different sequence changes when work reaches the second center; drawing the existing bars earlier cannot make unfinished parts available.
Use a lower bound
Any schedule must allow all 32 hours of binding after at least the smallest printing time, 2 hours. It also needs all 29 hours of printing followed by at least the smallest binding time, 4 hours. Thus:
The Johnson schedule reaches 34, so the lower bound proves that it cannot be improved. A bound below a schedule's makespan would not establish optimality by itself.
Know the three-center special case
For three centers visited in order, the method gives an optimum when the smallest time at center 1 is at least the largest at center 2, or the smallest time at center 3 is at least the largest at center 2. For each job, add its first and second operation times for one virtual time, and its second and third for the other. Apply the two-center rule to those paired virtual times.
Use the resulting order on the three real centers and time their real operations. The virtual centers are a sequencing device, not two physical machines. Beyond this restricted case, use other heuristics or scheduling software. Due dates and average flow time still need separate checks.
For example, three jobs H, J and K have times H (8, 2, 7), J (7, 3, 4) and K (6, 1, 9) hours across the three centers. The smallest first-center time is 6, above the largest middle time of 3. Virtual times are H (10, 9), J (10, 7) and K (7, 10). K's first virtual time puts K first; J's second virtual time puts J last. H fills the middle, giving K–H–J. Either order of selecting the tied minima gives that sequence.
Key Takeaways
- Start a second operation only when both the job and center are available.
- Makespan is the final finish; idle time depends on the measurement horizon.
- Reaching a valid lower bound proves the makespan is optimal.
- The three-center reduction needs its dominance condition.
- Johnson’s objective is makespan, so check due dates separately.
4.3 Build a feasible schedule from current capacity
A priority rule chooses the next job using a few attributes. It does not see the entire shop. Finite capacity scheduling (FCS) builds detailed schedules within the capacity actually available across resources and periods.
Use more than a local ranking
Simple rules have three limits. They need revision as equipment, processes and product mix change. They see one work center at a time, so they can miss congestion downstream or idle capacity upstream. Each uses only selected attributes, such as arrival, processing time or due date, unless other priorities are built in.
Two orders due on the same day may have different customer importance or lateness penalties. EDD treats them alike. Running the shortest local job first can also delay work needed at a system bottleneck. A locally attractive dispatch choice need not improve the whole operation.
FCS uses routings, setup and run times, shift calendars, maintenance, tooling and skilled labor availability. Orders and standard data usually come from MRP or ERP; live shop-floor information can update machine status and progress. Software combines rules, optimization methods and simulation, then shows a detailed electronic Gantt chart.
Replan after a disruption
A center has 8 hours per day. J1, J2 and J3 need 5, 4 and 6 hours and may continue the next day. Monday holds J1 plus 3 hours of J2. The original Tuesday schedule contains the last hour of J2 and all 6 hours of J3.
A Tuesday breakdown removes 2 hours, leaving 6. After the last hour of J2, only 5 hours remain for J3. Its final hour moves to Wednesday. If J3 is due Tuesday evening, the schedule exposes a one-hour shortfall against its promised completion.
The planner can compare 1 hour of Tuesday overtime, a qualified alternative machine for part of the work, or a revised promise. Interactive changes show the effects on other jobs immediately. Adding overtime only helps when the required people, tools and supporting resources are available too.
Protect the limiting resource
A bottleneck has less capacity than the demand placed on it and limits system output. Schedule it first and arrange supporting work so it has what it needs. Lost bottleneck time reduces output when it cannot be recovered; extra speed elsewhere does not raise output while the bottleneck remains the limit.
Drum-buffer-rope links three controls. The bottleneck sets the pace, the drum. A time buffer protects it from starvation. The rope releases new material at that pace, preventing uncontrolled WIP buildup at other centers.
Keep the inputs credible
An MRP capacity check compares aggregate load with capacity per period and reports overloads. FCS places operations into feasible detailed slots. Neither creates a new machine or makes inaccurate processing times reliable.
Check changed routings, realistic standard times, maintenance and skill availability when an apparently precise schedule cannot be followed. Software can evaluate alternatives quickly, but its feasibility depends on the resource data and constraints it receives.
Key Takeaways
- Local priority rules do not optimize the whole operation.
- FCS places detailed operations within actual resource availability.
- Interactive replanning shows the consequences of disruptions and alternatives.
- Plan the bottleneck first and control releases to its pace.
5Schedule customers and staff
Services match capacity to customers whose needs change throughout the day and week. Choose how bookings and queues organize demand, translate forecasts into whole-person staffing requirements, and fit shifts to the periods that need cover. A repeating weekly schedule adds another constraint: employees work five days with two consecutive days off, while the service still covers every day’s demand.
5.1 Match the service schedule to the customer need
Service capacity often disappears when its time passes. An unused appointment or an empty room for tonight cannot be stored for tomorrow. Services mainly schedule people; demand varies across hours and seasons, and customers often experience waiting directly. Labor is usually the largest cost.
Choose how customers enter
| Approach | What it controls | Example |
|---|---|---|
| Appointments | Service slots with a provider | An adviser at 10:00 |
| Reservations | Capacity set aside for a date, time or period | A table at 19:00 or a car for a weekend |
| FCFS | Service order by arrival | A counter queue |
| Priority | Order by urgency or another stated need | Emergency triage |
Appointments help control the timing of arrivals. Reservations make future capacity needs visible. Both can specify a time; the difference is the commitment being scheduled, not whether a clock time appears.
A clinic has a 4-hour session with 15-minute appointments, giving 16 slots. If 10% of booked patients typically do not arrive, 16 bookings bring an expected arrivals. That is an average across sessions, not a possible head count on one day. Overbooking can reduce unused capacity but raises waits when more patients attend.
FCFS is simple and often feels fair when needs are similar. It does not smooth demand. A priority system serves the most urgent case first even when that customer arrived later. In emergency care, triage makes medical urgency the scheduling priority. An express checkout applies the SPT idea to short transactions.
Change demand or change capacity
Demand management moves customers toward quieter periods using off-peak prices, promotions, appointments or reservations. Capacity management changes the resources available: part-time staff, flexible shifts, cross-trained employees or self-service.
For example, inviting customers to book a quiet morning slot changes when demand arrives. Moving a trained employee from an idle desk to a busy queue changes where capacity is supplied. The two actions can support the same service target through different mechanisms.
Fit the setting
Hospitals coordinate operating rooms with fixed surgery times and continuous nursing cover. Retailers convert forecast customer traffic into shifts. Banks can add part-time workers at peaks and move cross-trained staff between tasks. Airlines must coordinate aircraft and crew schedules, including duty and rest constraints. Around-the-clock services use rotating shifts.
The practical choice balances staffing cost against waiting, lost business and service quality. Because arrivals vary, staffing exactly to average workload can still produce queues during surges. Additional capacity can shorten waits but costs more.
FCFS is not the best fairness rule for every setting. Equal arrival-order treatment can overlook urgent need. Choose the service priority explicitly, then align bookings, queue rules and staffing with it.
Key Takeaways
- Service capacity cannot be stored after its time passes.
- Appointments schedule service slots; reservations set aside capacity.
- FCFS suits arrival-order fairness; priority can protect urgent needs.
- Demand management shifts arrivals; capacity management shifts resources.
- No-show averages do not guarantee spare slots on a particular day.
5.2 Convert forecast demand into shift coverage
A staffing plan must cover demand when it occurs. A daily average can hide a midday shortage even when total staff-hours look generous. Start with short periods, then fit shifts to their requirements.
Find the requirement in each period
Forecast arrivals, convert them into workload and divide by one employee's output for the same period. Round up to a whole number. If demand is stated per hour, use output per employee per hour; using daily output would mix time bases.
A desk opens 08:00–20:00. Each employee serves 15 customers per hour:
| Block | Customers per hour | Calculation | Staff required |
|---|---|---|---|
| 08:00–12:00 | 45 | 45 ÷ 15 | 3 |
| 12:00–16:00 | 84 | 84 ÷ 15 | 6 |
| 16:00–20:00 | 52 | 52 ÷ 15 | 4 |
Midday needs 5.6 employees' worth of output, so schedule 6 people. Five can serve only 75 customers per hour. The evening calculation is about 3.47, requiring 4 people. Across three 4-hour blocks, the rounded requirement is staff-hours.
Build shifts and check their overlap
Full-time workers can take 08:00–16:00 or 12:00–20:00. The overlap makes midday coverage the sum of both groups.
| Plan | Early full-time | Late full-time | Evening part-time | Coverage by block | Staff-hours |
|---|---|---|---|---|---|
| A | 3 | 4 | 0 | 3, 7, 4 | 56 |
| B | 3 | 3 | 1 | 3, 6, 4 | 52 |
Plan A covers every block but has one surplus person for four midday hours. Plan B adds a part-time worker only from 16:00 to 20:00 and removes that surplus. Its hours are .
Check each period for shortage and surplus, not just the day's total. The average hourly demand is about 60.3, suggesting 5 staff all day after rounding up. That leaves two surplus in the morning, one too few at midday and one surplus in the evening. Extra morning hours cannot be saved and used to serve the midday queue.
Add availability and service constraints
Breaks reduce the number actually serving. Cover them through relief staff or an allowance; count coverage after unavailable time is removed. Also check skills, certifications, contracts, employee preferences and fair allocation of unpopular shifts. A shift with enough people can still lack the required skill mix.
Random arrivals make 100% planned occupancy a poor service target: there is no spare ability to absorb a surge. A call center might plan around 85% busy time, but its exact target comes from the waiting-time goal. Distinguish the basic workload calculation from the extra capacity needed for service quality.
With many shift types and constraints, integer programming or scheduling software can select start times and staff numbers. The plan still needs a period-by-period check against forecast demand and actual availability.
Key Takeaways
- Calculate staff from matching demand and output time units, then round up.
- Check shift coverage in each demand block.
- Overlapping shifts can create surplus even when every block is covered.
- Breaks and skills affect effective availability.
- Plan spare capacity to meet waiting-time goals under variable arrivals.
5.3 Give consecutive days off while covering the week
A seven-day service can give each full-time employee five working days and two consecutive days off. Cyclical scheduling builds a repeating week by assigning one employee at a time to the days still needing cover.
Apply the days-off heuristic
Write the daily staffing requirements Monday through Sunday. Find the consecutive pair with the smallest combined requirement and give the next employee those days off. Sunday and Monday form a pair because the schedule repeats. Subtract 1 from each of that employee's five working days, then repeat using the updated requirements.
Keep negative residuals: they show surplus already created. Stop when every residual is zero or negative. If pairs tie, any tied pair can be selected, but the choice can change the final staffing total. This is a heuristic, not a general guarantee of the smallest workforce.
Follow the updates
A store needs 3, 6, 5, 4, 7, 6, 3 people from Monday to Sunday. Adjacent pair totals are 9, 11, 9, 11, 13, 9 and 6, with Sun–Mon lowest.
| Employee | Days off | Remaining requirement, Mon–Sun |
|---|---|---|
| Start | — | 3, 6, 5, 4, 7, 6, 3 |
| 1 | Sun–Mon | 3, 5, 4, 3, 6, 5, 3 |
| 2 | Sun–Mon | 3, 4, 3, 2, 5, 4, 3 |
| 3 | Wed–Thu | 2, 3, 3, 2, 4, 3, 2 |
| 4 | Sun–Mon | 2, 2, 2, 1, 3, 2, 2 |
| 5 | Wed–Thu | 1, 1, 2, 1, 2, 1, 1 |
| 6 | Mon–Tue | 1, 1, 1, 0, 1, 0, 0 |
| 7 | Sat–Sun | 0, 0, 0, −1, 0, 0, 0 |
For employee 6, Mon–Tue, Sat–Sun and Sun–Mon tie at 2. Choosing Mon–Tue allows employee 7 to cover every positive residual while taking Sat–Sun off.
Count the resulting cover independently: 3, 6, 5, 5, 7, 6, 3. Every day is covered; Thursday has one extra person. Weekly demand totals 34 staff-days and seven employees supply 35, leaving one surplus staff-day.
Test whether fewer employees are possible
Two lower bounds apply. The workforce must be at least the largest daily requirement, and at least total required staff-days divided by five, rounded up:
Here Friday requires 7 and rounds up to 7. The seven-person schedule reaches that bound, proving it uses the fewest employees possible.
Choosing Sun–Mon for employee 6 instead leaves positive residuals on Mon, Wed, Fri and Sun. No employee with consecutive days off can cover all four, so that tie choice needs an eighth employee. A result above the lower bound deserves another look at ties; the bound alone does not promise that a schedule attaining it exists.
In practice, rotate days off over successive weeks for fairness and check contracts, rest requirements and preferences. Surplus can support training or maintenance; part-time shifts can fill small remaining gaps.
Key Takeaways
- Treat Sun–Mon as consecutive in a repeating week.
- Subtract cover from working days and recalculate the pair totals.
- Stop only when all residual requirements are nonpositive.
- Tie choices can change the workforce needed.
- Reaching the daily and weekly lower bound proves minimum staffing.
- Check final daily cover independently of the residual table.
Short-Term Scheduling examples
1Turn a plan into a feasible daily schedule
11 steps
- 1IntroductionGive work a resource and a time
A monthly output plan still leaves tomorrow’s practical questions open: which job should use each machine, and when? A short-term schedule resolves those assignments. We will follow a print-shop order from the planning hierarchy to its start and finish dates, then check whether the work fits the machine’s available hours.
- 2ExplanationLocate the daily decision
Capacity plans establish facilities and equipment. Aggregate plans set output, workforce and inventory for product families. The master production schedule names products and weeks, and MRP dates component orders. Short-term scheduling places those orders on particular resources. Buying a new press belongs to capacity planning; reserving press 2 for an order on Monday is a daily scheduling decision.
- 3ExampleSeparate assignment from order
Suppose orders 418 and 421 both need printing. Assigning both to press 2 is loading. Choosing 418 before 421 is sequencing. Giving order 418 the slot 08:00–11:30 adds detailed timing. A dispatch list authorizes the chosen work to run; expediting follows urgent or delayed orders. The job’s routing supplies the required operations and their standard times.
- 4Key InsightA busy machine can still mean long waits
A queue helps keep a press occupied, but every order waiting there contributes to WIP and flow time. Utilization and customer waiting can therefore pull in different directions. Choose the objective that reflects the operation’s promise. Reliable due-date delivery, a short average lead time and keeping an expensive press busy are different measures of success.
- 5ChallengeChoose the planning level
A shop’s dispatch list is revised every morning, but every week the same machine has more work than it can complete. Should the planner keep solving the problem only through daily sequencing?
---reveal---
No. Daily sequencing can reorder work and short-term capacity changes can help, but a lasting shortage must feed back to higher-level capacity or output plans. The daily schedule exposes the persistent mismatch; changing the order alone does not remove it.
- 6ExplanationCount working days consistently
A shop calendar numbers working days consecutively. A weekend closure does not consume two working-day numbers. For a job occupying full days, keep the boundary clear: starting a two-day operation at the beginning of day 10 finishes it at the end of day 11. This prevents a one-day error when working backward from an end-of-day promise.
- 7ExampleSchedule back from day 20
An order needs cutting for 2 days, machining for 3 and painting for 1, due at the end of day 20. Place painting on day 20. Machining occupies days 17–19, so cutting occupies 15–16. The latest start is the beginning of day 15. Starting then leaves no spare working time between these operations and the delivery deadline.
- 8ExampleFind the earliest finish
Release the same order at the beginning of day 10 and schedule forward. Cutting runs days 10–11, machining 12–14 and painting day 15. Earliest completion is the end of day 15, giving five working days before the day-20 deadline. The same five-day gap separates earliest start on day 10 from latest start on day 15.
- 9ExplanationPut a ceiling on the load
A separate center has 8 hours per day. Monday releases, in order, need 5, 4 and 6 hours, and may continue the next day. Infinite loading places 15 hours on Monday, or 187.5% of capacity. Finite loading places 5 plus 3 hours Monday, then the remaining 1 plus 6 Tuesday. It respects available hours, but the last job may finish after its promised date.
- 10ChallengeCombine direction and capacity
A customer wants the last of those three jobs by Monday evening. The planner keeps all 15 hours on Monday and calls the plan backward scheduled. Has the scheduling direction resolved the problem?
---reveal---
No. Monday has only 8 hours, leaving a 7-hour capacity gap. Working back from a due date does not add capacity. The planner needs earlier available slots, added effective capacity or a later promise. The capacity choice and scheduling direction must both be checked.
- 11RecapRead the finished plan
For a proposed daily schedule, identify the named work, its resource, its sequence and its timing. Then check the working-day calendar and the resource’s available slots. Forward scheduling supports an early completion promise; backward scheduling identifies a latest start. A due date and a feasible capacity plan must agree before that promise is dependable.
2Control the load and solve an assignment
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionUse three views of work
- 2ExplanationBalance the queue
- 3ExampleAccumulate the deviations
- 4ChallengeInterpret a smaller queue
- 5ConnectionLet completions authorize releases
- 6ExplanationRead resource rows
- 7ExampleCompare work done by Wednesday
- 8ChallengeCheck a finished order
- 9ExplanationPreserve one job per machine
- 10ExampleStart with original times
- 11ExampleReduce columns after rows
- 12ExampleFind the smallest zero cover
- 13ExampleChoose independent zeros
- 14TipPrepare variants before solving
- 15ChallengeChange the optimization direction
- 16ChallengeConnect assignment to the schedule
- 17RecapFollow work from release to resource
3Compare job sequences and update urgency
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionDecide what the sequence should improve
- 2ExplanationSet a fair basis for comparison
- 3ExampleSort the jobs by the right column
- 4ChallengePick a rule for a waiting list
- 5ExampleAccumulate completion times
- 6ExplanationKeep two meanings of lateness separate
- 7Key InsightInterpret the utilization metric
- 8ExampleCompare averages with worst delays
- 9ChallengeCheck what optimization really claims
- 10ExplanationCompare time left with work left
- 11ExampleRank four current jobs
- 12ExampleUpdate date and progress together
- 13ConnectionCompare slack with proportional margin
- 14ChallengeDiagnose a high-ratio priority
- 15RecapChoose the measure before the rule
4Sequence two machines and replan within capacity
16 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake operations fit together
- 2ExplanationCheck the shared route
- 3ExamplePlace the first two jobs
- 4ExampleFill the back before the middle
- 5ChallengeReject a total-time shortcut
- 6ExampleRun the first center back to back
- 7ExampleTime binding from both constraints
- 8Key InsightLocate the idle hours
- 9ExampleProve a lower limit
- 10ChallengeRead what the bound proves
- 11ConnectionReduce three centers only when qualified
- 12ExplanationSchedule the resources actually available
- 13ExampleReplan after Tuesday loses capacity
- 14ChallengeCompare a feasible response
- 15Key InsightProtect the resource that limits output
- 16RecapCheck the sequence and the calendar
5Cover service demand through the day and week
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMatch capacity to the time of need
- 2ExplanationChoose what gets booked
- 3ExampleInterpret no-shows as an average
- 4ChallengeShift arrivals or shift resources
- 5ExampleConvert hourly demand to staff
- 6ExampleCheck overlapping full-time shifts
- 7ExampleUse a short shift where it helps
- 8ChallengeTest the average-demand shortcut
- 9TipCount staff who are actually available
- 10ExplanationBuild the repeating week one employee at a time
- 11ExampleAssign the first two employees
- 12ExampleUpdate the pair totals after each choice
- 13ExampleChoose a tie and finish the plan
- 14Key InsightUse a bound to check the workforce
- 15ChallengeCheck the effect of a tie
- 16ChallengeCheck both calendars
- 17RecapVerify cover where customers need it
Short-Term Scheduling practice questions
Set 1: Daily scheduling decisions10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Read schedules and set priorities10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Compare schedules and coverage10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Diagnose scheduling mistakes10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Evaluate feasible alternatives10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Appointment
Assignment problem
Average completion time
Average jobs in the system
B
Backlog
Backward scheduling
Bottleneck
C
Capacity management
ConWIP
Critical ratio (CR)
Cumulative deviation
Cyclical scheduling
D
Demand management
Detailed scheduling
Dispatching
Drum-buffer-rope
Dummy resource
Dynamic priority
E
Earliest due date (EDD)
Expediting
F
Finite capacity scheduling (FCS)
Finite loading
First come, first served (FCFS)
Flow shop
Flow time
Forward scheduling
G
Gantt load chart
Gantt schedule chart
H
Heuristic
Hungarian method
I
Idle time
Independent zeros
Infinite loading
Input–output control
J
Johnson’s rule
L
Lateness
Loading
Longest processing time (LPT)
Lower bound
M
Makespan
N
No-show rate
O
Occupancy
Opportunity cost
Opportunity loss
P
Priority rule
R
Reservation
Residual requirement
Review-date line
Routing
S
Sequence-independent setup
Sequencing
Shift coverage
Shop calendar
Short-term scheduling
Shortest processing time (SPT)
Slack
Staff-day
Staff-hour
Staffing requirement
Staffing surplus
Standard hour
T
Tardiness
Time buffer
U
Utilization metric
V
Virtual work center
W
What-if scheduling
Work center
Work-in-process (WIP)
About this lesson