Process Design and Capacity

Learn how operations choose and design the processes that make products and deliver services, and how much they can produce. Match process types from job shop to continuous flow to volume and variety, design service processes around customer contact, and map processes with flowcharts and service blueprints. Then calculate capacity, utilization and capacity needs, find bottlenecks and manage them with the theory of constraints, use break-even and crossover analysis, apply Little’s law, and model waiting lines to choose how many servers a service needs.

IntermediateLesson 3 of 9 in Operations Management Course

What you will learn

  1. Match manufacturing and service processes to the volume and variety they must handle, and explain the cost, flexibility and customer-contact trade-offs of each choice.
    • Match a manufacturing process type to volume and variety
      Describe the process types from project and job shop to continuous flow, place them on the product-process matrix, and explain why a good fit between product and process matters.
    • Design service processes around customer contact
      Classify service processes by labor intensity, customization and customer contact, and decide which parts of a service to run like a factory and which to design around the customer.
  2. Draw process maps and service blueprints that expose delays, handoffs and fail points, and measure flow with throughput rate, cycle time, throughput time, work in process and Little’s law.
    • Draw flowcharts, process charts and time-function maps
      Use standard mapping symbols to describe a process as it really runs, separate value-adding steps from delays and movements, and show where elapsed time goes.
    • Blueprint a service and design out fail points
      Build a service blueprint that separates what customers see from what happens behind the scenes, and use it to find and prevent the steps where the service is likely to fail.
    • Measure flow with throughput time, cycle time and Little’s law
      Calculate throughput rate, cycle time, throughput time, work in process and throughput efficiency, and use Little’s law to connect them.
  3. Measure capacity, utilization and efficiency, work out the resources a demand forecast requires, and choose how much capacity to add, and when, under uncertain demand.
    • Measure capacity, utilization and efficiency
      Distinguish design capacity, effective capacity and actual output, calculate utilization, efficiency and overall equipment effectiveness, and interpret the results.
    • Calculate capacity requirements and choose a capacity strategy
      Translate a demand forecast into the number of machines or staff needed, set a capacity cushion, and choose the size and timing of capacity changes.
    • Evaluate capacity options under uncertain demand
      Use expected monetary value and decision trees to compare capacity alternatives when future demand is uncertain, and interpret the result with its limits.
  4. Identify the step that limits a process, calculate process capacity and throughput time, and use the theory of constraints to raise output by managing that step.
    • Find the bottleneck and calculate process capacity
      Calculate the capacity of each step, including steps with parallel resources, to find the bottleneck, the process capacity, the cycle time and the throughput time with no waiting.
    • Manage a constraint with the theory of constraints
      Apply the five focusing steps, drum-buffer-rope and throughput accounting to raise the output and profit of a constrained process, including choosing the best product mix.
  5. Find the volume at which an operation covers its costs, for one product and for a product mix, and use cost crossover points to choose between processes.
    • Find the break-even point for one product
      Separate fixed and variable costs, calculate break-even volume and sales, find the volume for a target profit, and state the assumptions behind the model.
    • Extend break-even to product mixes and process choice
      Calculate the break-even sales of a multiproduct operation from its sales mix, and use crossover points between cost lines to choose the cheapest process for an expected volume.
  6. Describe a waiting-line system, calculate its performance with single-server and multi-server models, and choose the number of servers that balances service cost against the cost of waiting.
    • Describe a waiting-line system and its costs
      Identify the arrival pattern, queue rules and service structure of a waiting line, name it in Kendall notation, and explain the trade-off between service cost and waiting cost.
    • Calculate single-server waiting-line measures
      Apply the M/M/1 and M/D/1 models to calculate utilization, line length and waiting time, check the results with Little’s law, and explain why waits grow rapidly as utilization approaches 100%.
    • Compare multi-server options and choose a service level
      Use the M/M/s model to calculate waits with several servers, compare the total cost of different staffing levels, and apply pooling and the psychology of waiting to service design.

Process Design and Capacity study guide

6 chapters

1

Choose a process type that fits volume and variety

Choosing a process shapes cost, speed and flexibility long after the first order is filled. A workshop needs room for different jobs; a dedicated line needs enough repeated demand to justify its equipment. Service processes add another question: where does customer contact help, and where does it disrupt routine work? Compare manufacturing and service choices, then connect the design to the volume, variety and experience customers need.

1.1 Choose how products will be made

A process turns inputs into outputs through a set of activities. Choosing its basic design commits an operation to equipment, skills and ways of working that may be costly to change. Start with what customers need: how much of each product, and how different the orders are.

Match volume and variety

Volume is output per period; variety is the range of products or differences between orders. Five process types span the usual range:

ProcessTypical demandExample
ProjectOne large, unique outputBuilding a bridge
Jobbing or job shopLow volume, highly different ordersA custom tailor
BatchRepeated groups with changeoversA bakery changing bread types
MassHigh volume, narrow varietyAppliance assembly
ContinuousVery high volume of flowing outputA paper mill

A batch need not be small. Its defining feature is production in separate groups, with a changeover between products. In a project, the product commonly stays in place while people and equipment come to it.

Heizer's process focus describes a flexible job shop with resources grouped by function. Repetitive focus assembles standard modules on a line. Product focus uses specialized resources for high-volume, low-variety output. Mass customization combines high volume with customer choice through modules, flexible equipment, fast changeovers and late customization. Configuring a laptop from standard components is different from designing every component afresh.

Understand the cost of a mismatch

The product-process matrix compares product structure with process structure: jumbled job-shop flow, disconnected batch flow, connected assembly-line flow and continuous flow. Its diagonal represents a good match. As a product becomes standardized and demand grows, a move toward line production can make sense.

Moving toward continuous flow generally raises fixed costs and equipment specialization, lowers variable cost per unit, makes work more repetitive and reduces flexibility. Flow becomes more regular; work in process and elapsed time usually fall. The low variable cost pays off only at enough volume to spread the fixed investment.

A standard high-volume part made in a job shop carries avoidable handling and labor costs. A dedicated line handling many custom orders loses time to changeovers and disruptions. The most automated process is therefore not the best choice for every product.

Work through a product range

A furniture maker builds 40 made-to-measure kitchens each year, 30 cabinet models in runs of 500, and 4,000 identical flat-pack bookshelves per day. Kitchens fit jobbing: shared tools and skilled workers accommodate each design. Cabinets fit batch production: repeat a model, then change the setup. Bookshelves fit mass production: repeated steps justify a dedicated line.

The workshop that makes kitchens would give the bookshelf needless flexibility and a high unit cost. The bookshelf line would need constant changes to build kitchens. Functional equipment groupings support the workshop; equipment arranged in task order supports the line. Check expected volume, cost and the flexibility customers value before committing to either design.

Key Takeaways

  • Choose the process from volume per product and the variety of orders.
  • Batch production makes separate groups; batch size can be large.
  • More specialized processes usually have higher fixed costs and lower variable costs.
  • Mass customization keeps standard modules while allowing customer choice.
  • The product-process matrix shows the cost of mismatching products and processes.

1.2 Design contact that customers value

A service often needs the customer to take part while it is delivered. A consultation hour left unused today cannot be stored for tomorrow. Process design must therefore consider both the work and when customers need it.

Classify the service with clear axes

Slack's volume–variety classification runs from professional services, with few customized transactions and much staff discretion, through service shops, which combine front-office and back-office work, to mass services, with many standardized transactions. A consultant, a hotel and a supermarket illustrate this range.

Schmenner's service process matrix asks two different questions: how large is labor cost relative to facilities and equipment, and how much interaction and customization does the service involve?

Labor intensityLow interaction/customizationHigh interaction/customization
LowService factory: airline, hotelService shop: hospital, auto repair
HighMass service: retailing, schoolsProfessional service: law, accounting

Here, labor intensity is a cost ratio, not a count of employees. A large airline employs many people but also uses expensive aircraft. Also, Slack's service shops and Schmenner's service shop are different categories; name the framework when classifying an operation.

Low labor intensity puts emphasis on capital, technology and smoothing demand. High labor intensity puts emphasis on hiring, training and staff schedules. Customization makes cost, quality and expectations harder to control. Standardization makes consistency easier but can leave customers feeling that their needs are ignored.

Separate customer contact from supporting work

The customer contact model links greater time spent by the customer in the system with more variation and less freedom to organize work efficiently. Customers arrive at different times, ask questions and bring different needs.

Decoupling separates the high-contact front office from the low-contact back office. The front office supports the customer experience; the back office can use standard procedures, scheduled work and batching. In a bank, an adviser meets customers while check clearing takes place backstage.

Consider an accounting firm where every client initially meets a senior accountant. Clients can upload documents through a questionnaire. Junior staff and software prepare standard returns in the back office. Senior accountants meet clients who need complex advice. This saves scarce specialist time while preserving contact where judgment matters.

Choose a redesign deliberately

Options include moving unseen work backstage, automating routine steps, offering standard service packages, using customer self-service, or postponing customization. A sandwich shop prepares standard ingredients and assembles each order when requested.

Self-service uses the customer's time and effort, so test whether customers accept it and can complete it easily. Removing contact that customers value can damage perceived quality even if staff cost falls. Keep diagnosis, advice or reassurance where they improve the experience; organize routine work around reliable flow. A service blueprint makes these contact decisions visible and shows which backstage steps each encounter depends on.

Key Takeaways

  • Service capacity must be available when customers need it; unused time cannot be stored.
  • Name the classification framework because service-shop labels differ.
  • Schmenner uses labor intensity and interaction/customization as separate axes.
  • Decouple customer-facing work from routine supporting work where it improves the service.
  • Self-service has a cost in customer effort.
  • Preserve contact that customers value.
2

Map and measure how work flows through a process

A process can look fast when each task is timed separately and still make a customer wait for days. Maps show the path, ownership and delays that task times miss. Service blueprints add the customer’s experience and the hidden work behind it. Flow measures then connect the map to numbers: how often units finish, how long they stay, and how many are inside. Use the same process boundary to make those measures fit together.

2.1 Make delays and handoffs visible

A process map shows what work happens, in what order, and how materials, information or customers move. Observe the as-is process before drawing a to-be process. The official procedure may leave out queues, exceptions and workarounds that explain poor performance.

Choose a map that answers the question

A flowchart shows sequence and decisions. Use an oval or rounded rectangle for the start and end, rectangles for activities, diamonds for decisions and arrows for flow. Label each decision exit. For “Form complete?”, show both “yes” and “no,” including where an incomplete form goes.

A process chart records each step, its time and distance, using five categories:

  • Operation, a circle: something is made or changed.
  • Transport, an arrow: the item moves.
  • Inspection, a square: the item is checked.
  • Delay, a D shape: the item waits for the next step.
  • Storage, a triangle: the item is kept in a controlled place.

Checking a finished part is inspection; correcting it is an operation. Controlled storage differs from an item simply waiting because the next worker is busy.

A swim-lane map gives each role or department its own lane. A crossing arrow is a handoff. For an order, lanes might be customer, sales, credit, warehouse and delivery. Follow the information that must cross each boundary: missing details or unclear ownership can stop an otherwise fast process.

A time-function map adds a horizontal time scale to the lanes. Long bars reveal whether elapsed time comes from active work or waiting. An order that takes 12 days but needs only about 2 days of activity has substantial delay between tasks.

Use time to locate the opportunity

A laptop repair chart records 14 minutes of operations, 4 minutes of inspections, 8 minutes of transport and 54 minutes of delay. Total elapsed time is:

14+4+8+54=80 minutes

If the operations are the value-adding work, the value-added ratio is:

1480=0.175=17.5%

Waiting consumes 54 of the 80 minutes. Reducing those waits is the main opportunity to shorten the customer's experience. Making the 14 minutes of repair slightly faster would leave most of the delay intact.

Value-added analysis asks whether a step changes the output in a way the customer would pay for. Transport, inspection, delay and storage usually do not add value, but some remain necessary. A required safety inspection should be assessed for how well it works, not removed just because it does not transform the item.

Set the right boundary and detail

Use a high-level map to find the major stages and handoffs, then expand the stage that needs investigation. Record the same beginning and end when comparing current and proposed times. Include failed checks, returns for missing information and repeated work. A map of only the smooth route can hide the very delays it is meant to explain.

Key Takeaways

  • Map actual work before proposing a new process.
  • Label decision exits and include rework loops.
  • Process charts distinguish operation, transport, inspection, delay and storage.
  • Swim lanes show ownership and handoffs; time-function maps show elapsed time.
  • Value-added time divided by elapsed time identifies how much time changes the output.

2.2 Protect the service at its fail points

A customer sees only part of a service. A service blueprint connects that experience to the employees and systems that make it possible. It helps explain why a pleasant interaction can still end in a late, incomplete or incorrect result.

Build the layers around the customer

Choose one service and customer group, then trace the customer's actions from beginning to end. Put the provider's actions under the customer step they support. Read the layers from top to bottom:

  1. Physical evidence: the website, room, signs, confirmation or invoice the customer encounters.
  2. Customer actions: what the customer does.
  3. The line of interaction, separating customers from visible employee actions.
  4. Onstage actions: employee work the customer sees.
  5. The line of visibility, separating visible and hidden employee work.
  6. Backstage actions: employee work out of sight.
  7. The line of internal interaction, separating contact employees from supporting functions.
  8. Support processes: IT, purchasing and other departments.

An arrow crossing the line of interaction represents a service encounter. The line of visibility is a design choice: selected backstage work can be shown to build trust, while complex routine work can remain hidden.

Mark failures and waits

Add activity times, waits and the limits customers can tolerate. Mark a likely harmful error or delay as a fail point, often with F, and a customer wait with W. A handoff that depends on copying details manually deserves attention because information may be lost or changed.

For an auto repair service, customers book, drop off the car, approve extra work and collect it. The adviser receives the car, confirms the complaint, asks for approval and explains the bill. The technician diagnoses, repairs and road-tests backstage. Booking software and parts ordering support these actions.

Three fail points suggest different protections. If the complaint can be recorded wrongly, the adviser reads it back for confirmation. If a needed part may be missing, stock for common jobs is checked at booking. If the promised completion time will be missed, the adviser contacts the customer before that time. Each protection is attached to a named failure, so staff know when and why to act.

Prevent errors at the step

Fail-safing, also called poka-yoke, prevents an error or catches it immediately. A required-field check can stop an incomplete booking from entering the process. An appointment reminder reduces missed appointments. A checklist completed with a patient helps catch omissions before treatment.

A customer journey alone is not a full blueprint: it omits the hidden work that supports each encounter. Physical evidence also matters because customers use it to judge service quality. After marking a fail point, specify a prevention or recovery action and who owns it; an F on the page does not protect the customer by itself.

Key Takeaways

  • Blueprints connect customer actions to onstage, backstage and support work.
  • The line of visibility separates work customers see from work they do not see.
  • Mark waits and fail points, then attach a protection and an owner.
  • Fail-safing prevents errors or catches them before they reach the customer.

2.3 Connect inventory, output and time

A busy process can finish units frequently while each unit spends a long time inside it. Separate the pace of completion from the journey of one unit before calculating flow performance.

Define the measures

Throughput rate is average completed units per period. Cycle time is the average interval between successive completions, the reciprocal of throughput rate. At 50 claims per working day, cycle time is 1/50 of a working day. Throughput time is the elapsed time for one unit, including waiting. Work in process (WIP) counts units that have entered but not yet left.

Textbooks and workplaces use “cycle time” and “throughput time” differently. Here, throughput time includes waits. Work content adds all activity time; throughput time with no waiting measures elapsed activity time. For a chair, a frame takes 10 minutes and a seat 6 minutes in parallel, followed by 8 minutes of assembly. Work content is 24 worker-minutes; elapsed time with no waiting is:

max⁡(10,6)+8=18 minutes

The parallel workers reduce elapsed time, not the amount of work needed.

Apply Little's law

For stable long-run averages:

WIP=throughput rate×throughput time

Use one boundary and compatible time units. Stable means average inflow equals average outflow; a queue that grows continually has no stable average WIP. The relation does not require a particular arrival or service-time distribution.

An office completes 50 claims per working day and holds 400 claims on average. Average throughput time is:

40050=8 working days

At the same completion rate, reducing WIP to 200 claims reduces the average time to 4 days. The condition that output stays at 50 matters: releasing so little work that the bottleneck goes idle could lower output too.

For a clinic receiving 20 patients per hour with an average visit of 30 minutes, convert the time to 0.5 hour. Average occupancy is 10 patients, including those waiting and being treated. This helps plan space with room for busier periods; it is not a count of staff required.

Measure how much of the journey is work

Throughput efficiency is work content divided by throughput time, expressed as a percentage. If each claim needs 2 hours of work and the office uses 8-hour working days, the 8-day journey is 64 working hours:

264×100%≈3.1%

Do not replace work content with elapsed parallel activity time in this definition. At another boundary, such as just the waiting line, Little's law uses only waiting customers and their time in line. In queue notation, the whole system uses L=λW, while the line uses Lq=λWq. Count people or items, rate and time over that same boundary throughout.

Key Takeaways

  • Cycle time is the interval between completions; throughput time is one unit’s full journey.
  • Work content sums activity time; elapsed parallel activity time counts the longest branch.
  • Little’s law connects stable long-run averages over one boundary.
  • Convert rates and times to compatible units before multiplying.
  • At unchanged throughput rate, less WIP means shorter throughput time.
  • Average occupancy does not determine staffing by itself.
3

Measure capacity and plan how much is needed

A capacity figure is useful only when its operating conditions and time period are clear. Ideal output, planned output and actual output tell different stories about losses. Demand forecasts must also be translated into resource hours, including setups and spare capacity. After sizing the resources, compare when to add them and what each option earns under uncertain demand, keeping expected payoff and financial risk distinct.

3.1 Read capacity figures correctly

Capacity describes how much an operation can deliver in a stated period. “300 units” is incomplete; “300 units per shift” is usable. Where products need very different amounts of work, measure capacity in machine hours or standard hours, or state the product mix.

Separate three output levels

Design capacity is the theoretical maximum under ideal conditions. Effective capacity allows for the planned way the operation runs: product mix, maintenance, cleaning, breaks, changeovers and quality standards. Actual output is what it really delivers after unplanned losses such as breakdowns, shortages and absence.

Two ratios answer different questions:

Utilization=actual outputdesign capacity Efficiency=actual outputeffective capacity

A sandwich line makes up to 150 sandwiches per hour. Two 8-hour shifts on 5 days give design capacity of 12,000 per week. Effective capacity is 10,000 after planned stops; actual output is 9,000. Utilization is 75%, while efficiency is 90%.

The 3,000-unit total gap has two parts: 2,000 from planned losses and 1,000 from unplanned losses. Faster changeovers could raise effective capacity; fewer breakdowns could raise efficiency. Investigate which losses are avoidable before choosing an action. A new line with effective capacity of 10,000 and expected efficiency of 85% should deliver 8,500 per week, not 10,000.

Break equipment losses into parts

Overall equipment effectiveness (OEE) combines availability, performance and quality:

OEE=availability×performance×quality

Suppose planned production time is 480 minutes, with 48 minutes of breakdowns. Running time is 432 minutes, so availability is 0.90. The ideal cycle time is 1 minute per unit, and the machine makes 400 units: performance is 400/432, about 0.926. Of these, 380 are good, so quality is 0.95.

Multiplying the unrounded factors gives OEE of about 79%. Check it directly: 380 good units at 1 ideal minute each use 380 of the 480 planned minutes. The factors locate different losses; a machine may be available but slow, or fast while making defects.

Choose the measure for the decision

Services often use input measures such as staff hours, beds or seats because their outputs differ. Manufacturing with a changing mix also needs workload measures: 100 simple units and 100 complex units can use very different capacity.

Long-range decisions concern facilities and major equipment more than about a year ahead. Intermediate decisions, roughly 3–18 months, concern staffing, subcontracting and inventory. Short-range decisions, up to about 3 months, concern schedules, overtime and assignments. High utilization alone does not show good performance: a nonbottleneck running faster can build unwanted inventory, while a variable service operating near full utilization develops long waits.

Key Takeaways

  • Capacity needs both an output or resource measure and a time period.
  • Utilization uses design capacity; efficiency uses effective capacity.
  • Separate planned losses from unplanned losses before choosing an improvement.
  • OEE multiplies availability, performance and quality.
  • High utilization can create inventory or waiting when it is pursued in the wrong place.

3.2 Plan enough resources and choose when to add them

Capacity planning connects a demand forecast to the resources needed to deliver it. Convert units into processing and setup time, compare that load with usable time, then evaluate the cost and risk of closing any gap.

Include processing, setups and a cushion

For one product, required machines or staff are:

M=Dp+(D/Q)sN(1−C)

Demand per year is D, processing time per unit is p, lot size is Q, setup time per lot is s, available annual time per resource is N, and the desired capacity cushion is C as a fraction. Use the same time unit for p, s and N, then round the resource count up.

Demand of 120,000 units at 3 minutes each needs 360,000 processing minutes. Lots of 500 require 240 setups; at 60 minutes each, setups add 14,400 minutes. Total load is 374,400 minutes.

One machine working 250 days, two 8-hour shifts per day, provides 4,000 hours or 240,000 minutes. A 15% cushion leaves 204,000 minutes planned for workload. The requirement is about 1.84 machines, so install 2. Their combined 480,000 minutes give planned utilization of 78%; rounding up leaves a larger actual cushion than the minimum.

A capacity cushion is capacity above expected load, measured here as 100% minus average utilization. Uncertain demand, costly lost sales and services without storable output favor larger cushions. Stable demand and expensive equipment favor smaller ones. Ignoring setup time or rounding down can leave a facility unable to meet its plan.

Decide size and timing

Economies of scale lower average cost as fixed costs spread across more units and specialization becomes worthwhile. Beyond a certain size, coordination, complexity and congestion create diseconomies of scale. The best operating level is the output with the lowest average unit cost.

A lead strategy adds capacity before demand arrives, protecting sales but risking idle resources. A lag strategy waits until growth appears, using existing capacity more fully but risking lost sales or costly overtime. An average or straddle strategy alternates between capacity above and below demand. Small increments preserve flexibility; one large addition can gain scale economies but creates a period of spare capacity.

With capacity of 10,000 and annual demand forecasts of 9,000, 11,000 and 13,000, 2,000-unit modules added before years 2 and 3 give capacity of 12,000 and 14,000. A lagging addition after year 2 leaves 1,000 unserved that year, then another 1,000 in year 3 with capacity at 12,000.

Manage demand as well as supply

Compare adding capacity with subcontracting, changing hours, or changing demand timing. Reservations, appointments, higher peak prices and longer quoted lead times can ease overload. Promotions, off-peak prices or products with opposite seasonal peaks can use spare capacity. A service needs capacity for arrival peaks; an acceptable daily average can still hide a severely overloaded hour.

Key Takeaways

  • Convert demand into processing time plus setup time.
  • Divide workload by resource time after allowing for the desired cushion.
  • Round required resources up and recheck the resulting utilization.
  • Lead, lag and average strategies trade service risk against spare capacity.
  • Scale economies can reverse when coordination and congestion grow.
  • Demand timing can be changed as well as capacity.

3.3 Compare uncertain capacity investments

A forecast can leave several plausible demand outcomes. A capacity decision should show what each option earns in each outcome and how likely those outcomes are. This makes the trade-off between upside, downside and flexibility visible.

Calculate expected monetary value

A state of nature is an outcome the manager does not control, such as high or low demand. Give the states probabilities that sum to 1. For each alternative, multiply every payoff by its probability and add:

EMV=∑ipi×payoffi

For profit payoffs, choose the highest EMV; for costs, choose the lowest expected cost. Use payoffs on the same basis: investment costs must be included consistently, and amounts from different years need a comparable present-value basis.

Suppose high demand has probability 0.4 and low demand 0.6. Payoffs below are thousands of dollars, net of investment:

AlternativeHigh demandLow demandEMV
Large expansion800−200200
Small expansion400100220
Do nothing000

For the large option, 320 from the high-demand branch plus −120 from the low-demand branch gives 200. For the small option, 160 plus 60 gives 220. The small expansion has the higher EMV even though the large expansion has the greatest possible gain.

EMV is a probability-weighted average across repeated comparable decisions. The small expansion will pay either 400 or 100 in this decision, not 220. A firm unable to survive the large option's loss must also consider that downside; EMV alone does not represent its tolerance for risk.

Read and solve a decision tree

Draw decisions as squares and uncertain outcomes as circles. Branches from a chance node carry their probabilities; terminal paths show payoffs. Draw from left to right, then solve from right to left. Calculate a chance node's EMV before choosing the best branch at the preceding decision.

A later decision, such as expanding a small facility only after high demand appears, belongs after the demand outcome. Evaluate that decision separately in the branch where it is available. This shows how staged capacity can preserve useful options.

Test whether the choice is fragile

Let p be the probability of high demand in the table. Large and small expansions tie when:

800p−200(1−p)=400p+100(1−p)

This simplifies to 1000p−200=300p+100, giving p=3/7≈0.43. Above about 43%, the large option has the higher EMV. The current estimate of 40% is close to that cutoff, so better demand information could change the recommendation. Do not select an option just because it wins in the most favorable state or because its single best payoff is largest.

Key Takeaways

  • EMV weights each payoff by the probability of its state.
  • Fold decision trees back from outcomes toward the first decision.
  • An expected payoff is not the payoff guaranteed in one decision.
  • Test probability cutoffs and consider whether the downside is affordable.
4

Find bottlenecks and manage the constraint

A process succeeds at the pace of its limiting resource. Faster work elsewhere can leave the same output and more unfinished items. Find the constraint by comparing each resource group’s capacity with its workload, including parallel workers and product mix. Then decide how to protect its time, control releases and allocate scarce minutes to products that earn the most from them. Recalculate when an improvement moves the constraint.

4.1 Find what limits the whole process

The slowest task does not necessarily limit output: several people may perform it in parallel. Find each resource group's capacity relative to its workload, then identify the group that constrains the complete process.

Convert task times into capacity

For identical resources serving separate units in parallel:

capacity per hour=number of resources×60minutes per unit

The equivalent time per completed unit is task time divided by the resource count. The bottleneck has the lowest effective capacity relative to demand. Its capacity is the process capacity; its effective time is the process cycle time at full output.

A phone repair process has diagnosis at 4 minutes with one technician, repair at 6 minutes with two technicians, and test-and-clean at 5 minutes with one person. Capacities are 15, 20 and 12 phones per hour. Test-and-clean is the bottleneck, despite repair having the longest individual task time. The process can deliver 12 per hour, one completion every 5 minutes.

One phone still needs 4+6+5=15 minutes with no waiting. Parallel repair technicians each handle a different phone; they do not reduce one phone's 6-minute repair. At 12 completions per hour, diagnosis uses 80% of its capacity, repair 60%, and test-and-clean 100%. Idle time at a nonbottleneck is part of running at the system's pace.

Distinguish parallel resources from parallel tasks

When different parts of the same unit are prepared simultaneously, use the longest branch for elapsed time before joining them. A chair frame taking 10 minutes and a seat taking 6, followed by 8-minute assembly, takes 18 minutes with no waiting. With one worker at each task, capacities are 6 frames, 10 seats and 7.5 assemblies per hour. Frames limit complete chairs to 6 per hour.

Adding capacity changes the comparison. In the phone shop, a second test-and-clean worker raises that stage to 24 per hour, but diagnosis then limits output to 15. The improvement raises process output from 12 to 15, not to 24. A third repair technician would leave output unchanged because repair already has spare capacity.

Check a changing product mix

For several products, add the minutes each product needs at each resource. A press has 2,400 minutes per week. Demand of 200 X at 6 minutes and 150 Y at 10 minutes requires:

200×6+150×10=2700 minutes

Load is 112.5% of available time, so the mix cannot be supplied by that press. Repeat the calculation for every resource; another product mix may move the bottleneck. When all resources can meet demand, the market limits sales.

Do not average stage capacities or add task times to obtain an output rate. Those calculations describe neither the slowest resource group nor the process's sustainable completion rate.

Key Takeaways

  • Compare capacity after allowing for parallel resources.
  • Process capacity is the bottleneck capacity, not an average of stage capacities.
  • Cycle time at full output differs from one unit’s elapsed processing time.
  • Improving a bottleneck can move the limit to another step.
  • For a product mix, compare each resource’s total workload with available time.

4.2 Use the constraint to guide decisions

The theory of constraints (TOC) directs improvement toward whatever limits the system's goal. A constraint can be physical, such as a machine or scarce skill, a market with insufficient demand, or a policy such as rewarding every department for maximum local output.

Follow the focusing cycle
  1. Identify the system's constraint.
  2. Exploit it: use existing capacity well, prevent starvation and defective input, and work on output customers need.
  3. Subordinate other work to it: release and process work at the pace the constraint needs.
  4. Elevate it if needed, using more capacity, another shift or outsourcing.
  5. Return to identification when it moves; prevent old rules from becoming the next constraint.

An hour lost at an active bottleneck loses an hour of system output. An hour saved at a nonbottleneck does not increase output while the same constraint remains. Protecting the bottleneck therefore comes before trying to keep every resource busy.

In the phone shop, test-and-clean takes 5 minutes and limits output to 12 per hour. Move 1 minute of packing to repair. Repair now takes 7 minutes with two technicians, or 3.5 effective minutes per unit; test-and-clean takes 4 minutes. Diagnosis also takes 4 minutes, so output rises to 15 per hour without extra staff. Diagnosis and test-and-clean now tie, and both must be considered in the next improvement.

Control release with drum-buffer-rope

The drum is the constraint's schedule. A buffer of work protects it from upstream disruptions. The rope signals when to release new work, linking release to the constraint's consumption. Too much release creates WIP and long throughput times without creating more sales. Too little can starve the constraint.

Rank products by scarce time

In throughput accounting, throughput (T) is sales revenue minus totally variable costs, usually materials. Inventory (I) is money tied up in things intended for sale. Operating expense (OE) is money spent turning inventory into throughput. Net profit is T minus OE. Here, throughput is money from sales, not a count of finished units.

Product P sells for 90 dollars with 45 of materials and uses 15 bottleneck minutes. Its throughput is 45 dollars, or 3 per constraint minute. Product Q sells for 100, uses 40 of materials and 30 minutes: 60 dollars per unit, but only 2 per constraint minute.

With 2,400 minutes and demand for 100 P and 50 Q, make P first: 100 P use 1,500 minutes, leaving 900 for 30 Q. Total throughput is 6,300 dollars. With OE of 5,000, profit is 1,300. Making Q first yields 5,700 throughput and 700 profit. Ranking by the larger unit margin would lose 600 dollars. The ranking uses a single active constraint and the stated demand limits; allocate its minutes until demand is met, then use any remainder for the next product.

Key Takeaways

  • Exploit existing constraint capacity before paying to elevate it.
  • Subordinate other work to the system’s constraint.
  • Drum-buffer-rope protects the constraint while controlling WIP.
  • TOC throughput is money from sales minus totally variable costs.
  • Rank products by throughput per constraint minute, subject to demand limits.
  • Recheck the system when the constraint moves.
5

Use break-even analysis for volume and process decisions

Capacity decisions commit money before sales are certain. Contribution shows how each sale helps cover that commitment, and break-even shows the volume needed to avoid a loss. A product mix changes the contribution earned per sales dollar; a process choice changes fixed and variable costs. Use these relationships to compare feasible volumes, check profit targets and identify where a different process becomes cheaper.

5.1 Calculate break-even and target output

Sales first pay for the variable costs of making each unit. What remains contributes toward fixed costs and then profit. Break-even analysis finds the sales volume at which that contribution exactly covers fixed costs.

Build the profit equation

Let F be fixed cost per period, V variable cost per unit, P selling price per unit and x units sold in that period. Within the relevant operating range, F stays fixed and V stays constant per unit. Total variable cost, Vx, rises with volume.

Profit=Px−(F+Vx)=(P−V)x−F

The contribution per unit is P−V. At break-even, profit is zero:

BEPunits=FP−V

The contribution margin ratio is 1−V/P, the fraction of each sales dollar available for fixed costs and profit. Break-even sales value is:

BEPsales=F1−V/P

Dividing fixed cost by selling price would ignore the cost of making the units. Allocated overhead per unit is also not a variable cost simply because it has been expressed “per unit.”

Work from contribution to profit

A bakery has monthly fixed costs of 12,000 dollars, a price of 4.00 per loaf and variable cost of 1.60. Contribution is 2.40 per loaf. Break-even volume is 5,000 loaves, and break-even sales are 20,000 dollars. Check: 5,000 contributions of 2.40 exactly cover 12,000.

At 6,500 loaves, contribution is 15,600 and profit is 3,600. For a target profit of 6,000, the required volume is:

x=F+target profitP−V=12000+60002.40=7500

If units are indivisible, round a fractional requirement up. Fixed cost of 10,000 and contribution of 3 gives 3,333.3 units, so 3,334 are needed to avoid a loss.

Read the chart and test feasibility

On a break-even chart, total cost starts at fixed cost on the vertical axis and rises with slope V. Revenue starts at zero and rises with slope P. Their crossing is break-even; their vertical difference is profit or loss. Lower fixed cost, lower variable cost or a higher selling price lowers break-even volume.

Compare the requirement with demand and capacity. If the bakery can produce only 6,000 loaves per month, it can reach break-even but not the 7,500-loaf profit target. Its maximum monthly profit is 2,400 dollars. A break-even point above capacity cannot be achieved at that capacity.

The linear model assumes stable price, stable variable cost per unit, fixed cost unchanged within the range, and all output sold. A second shift or extra machine may raise fixed cost in a step; recalculate for that operating range. Keep cost and sales periods aligned. Monthly fixed costs and annual sales do not belong in the same calculation.

Key Takeaways

  • Contribution per unit is price minus variable cost per unit.
  • Break-even units equal fixed cost divided by contribution.
  • Add target profit to fixed cost before dividing by contribution.
  • Round fractional whole-unit requirements up.
  • Check demand, capacity and the relevant cost range.

5.2 Compare sales mixes and process costs

A business selling several products cannot use one product's contribution ratio for all its sales. A process choice also needs more than the lowest variable cost: fixed investment matters at the expected volume.

Weight a mix by sales value

For a stable sales mix, find each product's dollar sales and its share W of total dollar sales. Multiply each contribution margin ratio by that share, then add:

r=∑i(1−Vi/Pi)Wi Break-even sales=F/r

A café forecasts 10,000 coffees at 3 dollars, 5,000 sandwiches at 6, and 4,000 muffins at 2.50. Sales values are 30,000, 30,000 and 10,000, so weights are 3/7, 3/7 and 1/7. With variable costs of 1.20, 3.60 and 1.00, contribution ratios are 0.60, 0.40 and 0.60.

The weighted ratio is 18/35, about 0.514. Fixed cost of 18,000 dollars gives break-even sales of 35,000. Allocate these sales by the weights, then divide by prices: 5,000 coffees, 2,500 sandwiches and 2,000 muffins. Their contributions total 18,000, confirming the result.

Unit shares would give the wrong weighted ratio because products have different prices. A shift toward lower-contribution-ratio products raises break-even sales. If the café sold only sandwiches, a 0.40 ratio would require 45,000 dollars in sales. The original result depends on the original mix.

Find cost crossovers

For process j, total cost is fixed cost plus variable cost times volume. To compare processes 1 and 2, set their total costs equal:

F1+V1x=F2+V2x x=F2−F1V1−V2

Consider annual costs, all in dollars:

ProcessFixed costVariable cost per unit
A: general equipment10,00020
B: batch equipment40,0008
C: dedicated line100,0003

A and B cross at 2,500 units. B and C cross at 12,000. A is cheapest below 2,500, B between 2,500 and 12,000, and C above 12,000; adjacent choices tie at the boundaries. At 5,000 units their costs are 110,000, 80,000 and 115,000, confirming B's advantage.

A and C also cross, near 5,294 units, but B is cheaper than both there. A pairwise crossing is not necessarily a point where the best choice changes. Compare all lines in every candidate range.

Connect cost to process design

Flexible processes with lower fixed costs fit small volumes; specialized processes with lower variable costs become attractive at larger volumes. Also check capacity, quality, flexibility and forecast uncertainty. Near a crossover, a small forecast change can reverse the cost ranking. Crossover compares process costs, while break-even compares revenue with cost; a cheap process can still be unprofitable.

Key Takeaways

  • Weight contribution ratios by dollar sales shares, not unit shares.
  • Multiproduct break-even depends on the assumed sales mix.
  • Crossover analysis sets two process total costs equal.
  • Compare all alternatives; some pairwise crossings never change the best choice.
  • Check volume uncertainty, capacity and flexibility alongside cost.
  • Break-even and crossover answer different questions.
6

Analyze waiting lines and choose a service level

Customers can wait even when average capacity exceeds demand because arrivals and service times vary. Waiting-line models connect that variation to average line lengths, time and staffing cost. Start by identifying the system, then work from one server to a shared line with several servers. Compare service options using compatible rates, the right waiting-cost boundary and peak demand, while also considering how customers experience a wait.

6.1 Describe arrivals, service and waiting costs

A waiting line can form even when average service capacity exceeds average demand. Arrivals may cluster and some services may take longer than others. A model must describe this variation and the way customers move through the system.

Describe the system before choosing a formula

Start with the arriving population. It may be effectively unlimited, as for shoppers at a large store, or limited, as for six machines maintained by one technician. Describe line capacity and customer behavior: balking means not joining, reneging means leaving before service, and jockeying means switching lines.

The queue discipline decides who is served next. First-in, first-out (FIFO) follows arrival order; priority systems and appointments use different rules. A channel is a server working in parallel with others. A phase is a sequential service step. Several tellers sharing one line are multiple channels in one phase; an order window followed by a collection window has multiple phases.

Turn times into rates

The arrival rate is λ customers per period. Poisson arrivals mean random arrival counts with exponential times between arrivals; the mean interval is 1/λ. The service rate μ is one busy server's completions per period. A mean service time of 4 minutes gives μ=15 per hour, not 4 per hour.

Kendall notation A/B/s describes the arrival distribution, service-time distribution and number of servers. M denotes Poisson arrivals or exponential service times, D constant service time and G a general distribution. M/M/1 is one server with Poisson arrivals and exponential service times. M/D/1 keeps the arrivals but fixes service duration. M/M/s has s parallel servers.

Keep line and system measures separate

Use L for average customers in the system and Lq for those waiting. W is average time from arrival to departure; Wq is time in line. Server utilization is ρ, and P0 is the probability the whole system is empty.

L=λW,Lq=λWq W=Wq+1/μ

Time in service is included in W but excluded from Wq. The number being served averages less than the number of installed servers when they are sometimes idle.

Price the waiting you mean

Total cost per period combines server cost and waiting cost. For s servers at Cs dollars each per hour, service cost is sCs. If each customer-hour in line costs Cw, waiting cost per hour is CwLq. Use L instead if the cost also applies during service.

For example, 2 customers waiting on average with a cost of 18 dollars per customer-hour generate 36 dollars of waiting cost per hour. Multiplying by Wq alone would omit how many customers experience the wait. Adding servers raises service cost but usually lowers waiting cost. For customers, waiting costs can include lost goodwill; for a firm's own employees or equipment, they can be directly measured lost productive time.

Key Takeaways

  • Random variation can create waits despite spare average capacity.
  • Channels are parallel servers; phases are sequential steps.
  • Convert mean service duration into a per-server service rate.
  • L and W count the system; Lq and Wq count only the line.
  • Waiting cost per hour uses average customers waiting, not waiting time alone.

6.2 Calculate a single-server queue

Single-server models show why a small rise in demand can produce a large rise in waiting. First check that the model fits, then keep rates, customer counts and times distinct.

Fit the M/M/1 model

M/M/1 assumes Poisson arrivals from an unlimited population, exponential service times, one server, FIFO service, unlimited waiting room and no balking or reneging. A steady state requires λ<μ. At or above full average capacity there is no finite steady-state mean; the following formulas cannot describe it.

ρ=λμ,P0=1−ρ L=λμ−λ,W=1μ−λ Lq=λ2μ(μ−λ),Wq=λμ(μ−λ)

The probability of more than k customers in the system is Pn>k=ρk+1. This counts the customer being served as well as anyone in line.

Work through the pharmacy

Customers arrive at 12 per hour. A 4-minute mean service gives μ=15 per hour. Utilization is 0.8 and P0 is 0.2. The capacity gap μ−λ is 3 per hour, so W is 1/3 hour, or 20 minutes. L is 12/3=4 customers.

For the line, Lq is 144/45=3.2 customers and Wq is 12/45 hour, or 16 minutes. Check that 16 minutes of waiting plus 4 of service gives the 20-minute total. Little's law also checks both counts: 12 arrivals per hour times 1/3 hour gives 4 in the system.

More than 3 customers are present with probability 0.84=0.4096, about 41%. Using the third power would count 3 or more, a different event.

If arrivals rise to 14 per hour while service stays at 15, W becomes 1 hour and L becomes 14. Arrivals rose by about 17%, yet system time tripled. As utilization nears 100%, the spare capacity needed to clear bursts disappears.

Change the service-time pattern

M/D/1 has the same Poisson arrivals but a constant service duration. Its line measures are:

Lq=λ22μ(μ−λ),Wq=λ2μ(μ−λ)

Add λ/μ to Lq for L, and 1/μ to Wq for W. At 12 arrivals and 15 services per hour, Lq is 1.6, Wq is 8 minutes, L is 2.4 and W is 12 minutes. Fixing service duration halves waiting in line compared with M/M/1 at the same rates. It does not halve total time because service time is still 4 minutes.

A small population, such as eight machines needing repair, requires a limited-population model: each machine already down reduces the number still able to fail. Do not treat its arrival rate as independent of how many are already waiting.

Key Takeaways

  • Check M/M/1 assumptions and λ<μ before calculating steady-state measures.
  • Use rates in one time unit, then convert the resulting times.
  • Check W=Wq + mean service time and both forms of Little’s law.
  • M/M/1 waits rise sharply near full utilization.
  • At equal rates, M/D/1 halves line waiting, not total system time.
  • Tail probabilities count everyone in the system.

6.3 Choose servers using waits and cost

Adding servers changes both the cost of providing service and the cost of delay. Compare feasible staffing levels using the same arrival pattern, cost boundary and service target.

Model one line with parallel servers

M/M/s has Poisson arrivals, exponential service times, one FIFO line and s identical parallel servers. Use an unlimited population and line, with no balking or reneging. Stability requires λ<sμ, and utilization per server is λ/(sμ). The arrival rate belongs to the whole line; μ remains the rate of one server.

For spreadsheet calculation, set a=λ/μ and ρ=λ/(sμ). The empty-system probability and queue length are:

P0=[∑n=0s−1ann!+ass!(1−ρ)]−1 Lq=P0asρs!(1−ρ)2

Then L=Lq+a, Wq=Lq/λ and W=Wq+1/μ. These are the same M/M/s relations expressed with shorter intermediate variables. Use unrounded values until the final result.

Compare help-desk staffing

A help desk receives 12 calls per hour; each agent serves 8 per hour. One agent is insufficient. With two agents, utilization is 75%, P0 is 1/7, Lq is 27/14 and Wq is about 9.6 minutes. Total time is about 17.1 minutes after adding 7.5 minutes of service.

With three agents, utilization is 50%, P0 is 4/19, Lq is 9/38 and Wq is about 1.2 minutes. Total time is about 8.7 minutes. A 50% increase in capacity cuts the line wait by much more than 50%; waiting changes nonlinearly with utilization.

Agents cost 20 dollars per hour and waiting in line costs 30 per caller-hour. Two agents cost about 97.86 dollars per hour including waiting; three cost about 67.11. The third agent's wage is outweighed by lower waiting cost. If service time also carries the waiting cost, use L in both alternatives: totals become about 142.86 and 112.11, leaving the same choice.

Pool demand and manage the experience

Two separate M/M/1 lines, each receiving 6 calls per hour with μ=8, have a 22.5-minute average line wait. Pooling them into the two-agent shared line cuts that to about 9.6 minutes. Sharing lets an available agent serve the next caller even when arrivals are unevenly split. A common line also supports arrival-order fairness.

Evaluate busy periods with their own arrival rates. Faster service, less variation, appointments and off-peak demand shifts are alternatives to extra servers. Meet a stated waiting target as well as comparing costs.

Customers also experience a wait psychologically. Maister's proposals suggest that occupied, explained, predictable and fair waits can feel shorter; anxiety, isolation and waiting before service can feel longer. People may accept more delay for a valued service. Test useful responses such as estimated wait displays, menus or forms during the wait, and a shared line; these change the experience without replacing adequate capacity.

Key Takeaways

  • M/M/s uses total arrivals and a per-server service rate.
  • Check stability, then compare total service and waiting costs.
  • Pooling lets shared capacity respond to uneven arrivals.
  • Adding servers changes waiting nonlinearly.
  • Analyze peak periods and a stated service target.
  • Improve information and fairness as well as actual waiting.

Process Design and Capacity examples

6 Walkthroughs

1

Choose a process for products and customers

11 steps
Match a lamp maker’s production and support service to volume, variety and customer contact.
  1. 1
    IntroductionStart with the demand

    A lamp maker sells bespoke installations, recurring design ranges and one standard desk lamp. Its support team also handles routine replacement orders and complex lighting advice. Choosing one process for all this work would make some tasks expensive and others inflexible. Start by separating what repeats from what changes, which is the volume and variety of demand and what points to the right process for each kind of work, then decide where customers need direct contact.

  2. 2
    ExplanationRead volume and variety

    Volume asks how much of each product is needed per period. Variety asks how much the orders differ. Bespoke installations have low volume and high variety; a standard desk lamp has high volume and low variety. Process choice follows this demand pattern because flexible skills and dedicated equipment solve different production problems.

  3. 3
    ExampleAssign the production work

    The company builds 60 bespoke installations per year, eight lamp designs in recurring runs, and 2000 identical desk lamps per day. Use jobbing for the bespoke work, batch production for the recurring design runs, and mass production for the desk lamp. A batch is defined by a group followed by a changeover, so even a large run can still be a batch.

  4. 4
    Key InsightSee the cost behind the choice

    A job shop shares general-purpose resources and skilled people across varied orders. A dedicated line commits more fixed cost to specialized equipment but lowers variable cost per unit at sufficient volume. The product-process matrix places suitable matches near its diagonal. Growing demand can justify a move toward more connected, specialized flow as a product becomes standardized.

  5. 5
    ChallengeDiagnose a mismatch

    The manager proposes putting every bespoke installation through the desk-lamp line because that line has the lowest variable cost. What problem would this create?

    ---reveal---

    The line’s rigidity conflicts with the different installation designs. Frequent changes and disruption can erase its low unit-cost advantage. The workshop’s flexibility serves the bespoke orders even though each unit uses more labor.

  6. 6
    ConnectionOffer choice through modules

    The desk lamp could offer customer-selected bases, colors and controls without returning to fully bespoke manufacture. Mass customization keeps standard modules and combines them late in the process. Fast changeovers and flexible equipment support this design. The finished choices vary, while much of the underlying work still repeats at high volume.

  7. 7
    ExplanationClassify service work carefully

    Slack’s service types run from professional services through service shops to mass services as transactions become more standardized. Schmenner instead compares labor intensity with interaction and customization. Its categories are service factory, service shop, mass service and professional service. State the framework: the same “service shop” label does not identify the same category in both.

  8. 8
    ExampleSeparate support tasks

    Routine replacement orders require an item number, delivery details and a standard payment. Complex lighting advice requires questions and expert judgment. Move routine entry into a simple online flow and back-office processing; keep advice in the front office. This decoupling lets the team schedule predictable work while keeping personal contact where it adds value.

  9. 9
    TipCount customer effort

    Self-service transfers work to the customer. Check that people can identify the part, enter the details and recover from an error without repeating everything by phone. A lower staff-time figure can hide greater customer effort. Also plan service capacity for when requests arrive: unused adviser time today cannot be stored to handle tomorrow’s peak.

  10. 10
    ChallengeConnect the product and service design

    The configurable lamp range grows. Buyers can choose standard modules easily, but some need advice about unusual spaces. How can the company keep efficient production and useful customer contact?

    ---reveal---

    Assemble standard modules late for customer configurations, and offer expert front-office advice for unusual needs. Process ordinary orders backstage. Standardize repeatable work while preserving the interaction that helps customers choose.

  11. 11
    RecapMatch each kind of work

    Use volume and variety to choose the production flow, and compare its flexibility with its fixed and variable cost. Modular design can add choice without making every task unique. For service, identify the classification framework and separate valued customer contact from routine support. A useful process design fits both the work customers request and the experience they need.

2

Trace an equipment return from arrival to completion

14 steps
Build a map, protect service handoffs and calculate flow measures for a rental-return process.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionStart with the demand
  2. 2
    ExplanationMap the actual route
  3. 3
    ExampleAdd the elapsed time
  4. 4
    ChallengeLocate the main delay
  5. 5
    ExplanationAdd what the customer sees
  6. 6
    ExampleConnect the visible handoff to support
  7. 7
    ChallengeChoose protection for the failure
  8. 8
    ExplanationSeparate pace from journey
  9. 9
    ExampleUse the unfinished returns
  10. 10
    ExampleMeasure the share spent working
  11. 11
    Key InsightHandle parallel work correctly
  12. 12
    ChallengeSet an inventory target
  13. 13
    ChallengeConnect the map to the numbers
  14. 14
    RecapRead the path and the averages together
3

Size capacity and compare uncertain expansions

15 steps
Calculate capacity performance, resource needs and the expected payoffs from expansion.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionStart with the demand
  2. 2
    ExplanationRead the capacity benchmarks
  3. 3
    ExampleCompute both ratios
  4. 4
    ChallengePredict output from effective capacity
  5. 5
    ConnectionLocate equipment losses
  6. 6
    ExampleCalculate next year’s workload
  7. 7
    ExampleAllow for the cushion
  8. 8
    Key InsightCheck the capacity after rounding
  9. 9
    ChallengeCompare timing choices
  10. 10
    TipCheck scale and demand timing
  11. 11
    ExplanationPut the outcomes on one basis
  12. 12
    ExampleCalculate expected payoffs
  13. 13
    ChallengeFind where the recommendation changes
  14. 14
    ChallengeCheck more than the average
  15. 15
    RecapBuild a feasible, affordable plan
4

Improve a diagnostic shop at its constraint

12 steps
Find the limiting stage, test a work transfer and choose products using scarce minutes.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionStart with the demand
  2. 2
    ExampleCalculate the three capacities
  3. 3
    Key InsightKeep the unit’s journey separate
  4. 4
    ChallengeAdd a checker
  5. 5
    ExplanationUse the existing limit well
  6. 6
    ExampleMove work before buying capacity
  7. 7
    ChallengeControl the work entering the shop
  8. 8
    ExplanationMeasure the money from scarce time
  9. 9
    ExampleAllocate the constraint minutes
  10. 10
    ChallengeTest a competing product priority
  11. 11
    ConnectionRecheck the limit after a mix change
  12. 12
    RecapFollow the system’s scarce time
5

Use contribution to choose a feasible process

12 steps
Find break-even, test a profit target and compare product mixes and process cost lines.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionStart with the demand
  2. 2
    ExplanationFind what each sale contributes
  3. 3
    ExampleFind the zero-profit point
  4. 4
    ExampleAdd a profit target
  5. 5
    ChallengeCheck the capacity limit
  6. 6
    TipKeep the cost range valid
  7. 7
    ExplanationWeight a product mix by revenue
  8. 8
    ExampleCalculate the mixed break-even
  9. 9
    ChallengePredict the effect of a mix shift
  10. 10
    ExampleSet two process costs equal
  11. 11
    ChallengeChoose at a forecast volume
  12. 12
    RecapIdentify which comparison you need
6

Choose service capacity for a busy counter

18 steps
Calculate single-server waits, compare constant service and evaluate a pooled multi-server expansion.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionStart with the demand
  2. 2
    ExplanationIdentify the system and the rates
  3. 3
    ChallengeCount steps and servers
  4. 4
    ExampleCalculate total system time
  5. 5
    ExampleExtract the line wait
  6. 6
    ChallengeCheck a tail probability
  7. 7
    ExampleRemove service-duration variation
  8. 8
    Key InsightNotice the cost of high utilization
  9. 9
    ExplanationPlan a shared two-server line
  10. 10
    ExampleCalculate the empty probability
  11. 11
    ExampleTurn queue count into waiting time
  12. 12
    ChallengeCompare pooling with separate lines
  13. 13
    ConnectionPrice only the time that costs money
  14. 14
    ExampleCompare a third agent
  15. 15
    ChallengeAdd a service target
  16. 16
    TipAnalyze the busy hour
  17. 17
    ConnectionImprove the waiting experience
  18. 18
    RecapChoose from a complete service comparison

Process Design and Capacity practice questions

50 Practice Questions in 5 sets

Set 1: Read processes and calculate their limits10 Practice Questions

Question 1 of 10

A ceramics producer makes 800 bowls of one design, changes molds, then makes 600 plates. What process type does this describe?
  1. Job-shop production
  2. Batch production
  3. Mass production
  4. Continuous production
Show answerHide answer
Answer: B
The producer makes separate groups and changes the setup between products, which defines batch production. The group sizes can be large. Mass production emphasizes a repeated connected flow of standardized units; high output alone does not make these separate runs mass production.

Question 2 of 10

An insurance office uses expert meetings to assess unusual claims, but staff also enter routine documents during each meeting. How could it preserve valuable contact while organizing routine work more efficiently?
  1. Move expert assessment backstage and keep routine entry in every meeting.
  2. Keep all entry in expert meetings and standardize every unusual decision.
  3. Replace expert meetings with self-entry and give all claims one fixed answer.
  4. Move routine entry backstage and keep expert meetings for unusual claims.
Show answerHide answer
Answer: D
Decoupling lets predictable document work be standardized away from the meeting while preserving expert contact for unusual cases. Moving the assessment itself out of customer contact can remove the interaction needed to understand those cases. Lower staff contact is useful where it improves the service, not as a goal by itself.

Question 3 of 10

A process chart records a finished sensor being measured without being changed. What activity type is this?
  1. Inspection
  2. Operation
  3. Transport
  4. Storage
Show answerHide answer
Answer: A
Measuring checks whether the sensor meets a requirement, so it is an inspection. An operation changes the item or produces something. If staff adjusted the sensor after the measurement, that adjustment would be a separate operation; the stated step only checks it.

Question 4 of 10

A stable permit office completes 36 permits per working day and holds 180 permits on average. What is the average throughput time?
  1. 0.2 working day
  2. 5 working days
  3. 36 working days
  4. 180 working days
Show answerHide answer
Answer: B
Little’s law gives average throughput time as WIP divided by throughput rate: 180/36=5 working days. Dividing 36 by 180 instead gives the inverse quantity, not a journey time. Both the inventory and completion rate refer to the same stable office boundary.

Question 5 of 10

A line has design capacity of 960 units per day, effective capacity of 800, and actual output of 720. What are utilization and efficiency, respectively?
  1. 90% and 75%
  2. 83.3% and 90%
  3. 75% and 90%
  4. 75% and 83.3%
Show answerHide answer
Answer: C
Utilization compares actual output with design capacity, giving 720/960=75%. Efficiency compares the same output with effective capacity, giving 720/800=90%. Swapping these denominators reverses the two measures and hides which capacity benchmark each one assesses.

Question 6 of 10

A packaging facility expects to use 84% of its total capacity on average. What capacity cushion does it plan?
  1. 16%
  2. 19%
  3. 84%
  4. 116%
Show answerHide answer
Answer: A
The cushion is the unused share of total capacity, so 100%−84%=16%. Dividing the spare 16 by the used 84 gives about 19%, but that uses demand as the denominator. The capacity-cushion convention here uses total capacity, consistent with 100% minus utilization.

Question 7 of 10

A serial process has cutting at 5 minutes with one worker, drilling at 9 minutes with two parallel workers, and checking at 6 minutes with one worker. Demand exceeds current capacity. One identical worker can be added to one stage. Where should the worker go, and what will process capacity become?
  1. Drilling; 10 units per hour
  2. Checking; 20 units per hour
  3. Cutting; 13.3 units per hour
  4. Checking; 12 units per hour
Show answerHide answer
Answer: D
Current capacities are 12, about 13.3 and 10 units per hour, so checking limits output. A second checker raises checking to 20, leaving cutting as the new limit at 12. Reporting 20 uses the improved stage alone; adding to drilling leaves the original 10-unit checking limit unchanged.

Question 8 of 10

A repair kit sells for 32 dollars and costs 20 dollars per unit to supply. Monthly fixed costs are 8400 dollars. How many kits must be sold to break even?
  1. 263 kits
  2. 420 kits
  3. 700 kits
  4. 2625 kits
Show answerHide answer
Answer: C
Each kit contributes 32−20=12 dollars toward fixed cost. Dividing 8400 by 12 gives 700 kits, whose total contribution exactly covers the monthly commitment. Dividing by the 32-dollar selling price gives about 263 and ignores the variable cost of supplying those kits.

Question 9 of 10

A visitor joins a reception line but leaves before reaching the desk. What waiting-line behavior is this?
  1. Balking
  2. Reneging
  3. Jockeying
  4. Priority service
Show answerHide answer
Answer: B
The visitor entered the line and then abandoned it, which is reneging. Balking would mean deciding not to join in the first place. Jockeying requires switching to another line, something this scenario does not describe; the distinction depends on what the customer actually did.

Question 10 of 10

A stable M/M/1 desk receives 9 requests per hour and serves 12 per hour. What is the average total time a request spends in the system?
  1. 15 minutes
  2. 5 minutes
  3. 6.7 minutes
  4. 20 minutes
Show answerHide answer
Answer: D
For M/M/1, total system time is 1/(12−9) hour, or 20 minutes. The mean service time is 5 minutes, leaving 15 minutes waiting in line. Choosing 15 minutes would report Wq and omit service; the question asks for the full time from arrival to departure.
Set 2: Connect flow, money and service decisions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A firm assembles large volumes of configurable lamps from standard bases, shades and controls after each order arrives. What process strategy best describes this design?
  1. Process-focused jobbing
  2. Continuous processing
  3. Mass customization
  4. One-off project work
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A service blueprint places a technician’s hidden preparation below a horizontal boundary and the visible adviser interaction above it. What is this boundary called?
  1. The line of visibility
  2. The line of interaction
  3. The line of internal interaction
  4. The physical evidence row
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A stable office completes 24 reviews per day. Management reduces average WIP from 144 to 96 while keeping that output rate. How does average throughput time change?
  1. It falls from 6 days to 2 days.
  2. It falls from 6 days to 4 days.
  3. It falls from 4 days to 2 days.
  4. It rises from 4 days to 6 days.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

An expansion has high- and low-demand net payoffs in thousands of dollars. Large pays 600 or −180; small pays 300 or 60. Above what probability of high demand does large have the higher EMV?
  1. 2/7, about 28.6%
  2. 1/3, about 33.3%
  3. 3/5, exactly 60%
  4. 4/9, about 44.4%
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

One product requires a 12-minute component A and a 7-minute component B made simultaneously by different workers, followed by 5 minutes of assembly. What is its elapsed activity time without waiting?
  1. 24 minutes
  2. 12 minutes
  3. 10 minutes
  4. 17 minutes
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A single constrained machine has 1800 minutes per week. Product A earns 36 dollars of throughput in 6 machine minutes; B earns 50 dollars in 10. Demand is at most 200 A and 100 B, and all other resources have spare capacity. What weekly mix maximizes throughput?
  1. 133 A and 100 B
  2. 200 A and 60 B
  3. 150 A and 90 B
  4. 100 A and 100 B
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A business has monthly fixed cost of 9600 dollars, price of 45 dollars and variable cost of 29 dollars per unit. What volume is needed for a monthly profit of 3200 dollars?
  1. 800 units
  2. 600 units
  3. 200 units
  4. 441 units
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A shop expects to sell equal numbers of items A and B. A sells for 12 dollars with variable cost 6; B sells for 24 with variable cost 18. Fixed cost is 9000 dollars per month. What monthly sales value breaks even at this mix?
  1. 24000 dollars
  2. 18000 dollars
  3. 27000 dollars
  4. 36000 dollars
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A service has an average duration of 2.5 minutes per customer while the employee is busy. What is the employee’s service rate per hour?
  1. 2.5 customers per hour
  2. 24 customers per hour
  3. 0.4 customer per hour
  4. 150 customers per hour
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A service compares two feasible M/M/s staffing levels. Two agents cost 22 dollars each per hour and have Lq=1.8; three have Lq=0.3. Waiting in line costs 28 dollars per customer-hour. What is the lower-cost option and its total hourly cost?
  1. Three agents; 74.40 dollars
  2. Two agents; 44.00 dollars
  3. Two agents; 94.40 dollars
  4. Three agents; 116.40 dollars
Show answerHide answer

Save this lesson to see this answer.

Set 3: Evaluate capacity and service alternatives10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

Using Schmenner’s framework, how should a service with expensive equipment, low labor cost relative to equipment, and highly customized work be classified?
  1. Service factory
  2. Mass service
  3. Professional service
  4. Service shop
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A device-refurbishing chart shows 18 minutes of customer-valued operations, 6 of inspection, 9 of transport and 57 of delay. What is its value-added ratio?
  1. 26.7%
  2. 30%
  3. 20%
  4. 75%
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A booking form refuses submission until the required collection date is entered. What service-design method does this illustrate?
  1. Fail-safing
  2. Demand pooling
  3. Capacity cushioning
  4. Queue prioritization
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A machine has 450 planned production minutes, runs for 405, makes 360 units at an ideal cycle of 1 minute, and produces 342 good units. What is its OEE?
  1. 90%
  2. 76%
  3. 84.4%
  4. 95%
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Annual demand is 48000 units, each requiring 4 processing minutes. Lots contain 400 units and each setup takes 30 minutes. Each machine offers 1800 hours per year. With a required 20% capacity cushion, how many whole machines are needed?
  1. 3 machines
  2. 2 machines
  3. 4 machines
  4. 5 machines
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Demand is high with probability 0.35 and low otherwise. In thousands of dollars, building large pays 500 or −100. Building small pays 200 or 80, with an optional later expansion adding 140 under high demand or −40 under low. All payoffs are comparable and net of investment. What decision has the highest EMV?
  1. Build small, expand in both states; EMV 145.
  2. Build large, make no later change; EMV 110.
  3. Build small, expand only if high; EMV 171.
  4. Build small, never expand later; EMV 122.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A constrained test station is already well supplied and sometimes retests items because defects escape an upstream check. Management can improve that check without buying equipment. What TOC action does this represent?
  1. Elevate the test constraint.
  2. Exploit the test constraint.
  3. Move the constraint to the market.
  4. Maximize all upstream output.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Three processes have annual costs in dollars: A = 8000+18x, B = 28000+8x, and C=70000+4x, where x is units. All can meet demand. Over what volume ranges is each the cheapest?
  1. A below 4429; C above 4429; B is never cheapest.
  2. A below 2000; C from 2000 to 10500; B above 10500.
  3. A below 2000; B from 2000 to 15500; C above 15500.
  4. A below 2000; B from 2000 to 10500; C above 10500.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

An M/M/1 station with λ=8 and μ=10 per hour is replaced by a constant-time service with the same rates, fitting M/D/1. What are its new average line wait and total system time?
  1. 12 minutes waiting; 15 minutes total
  2. 12 minutes waiting; 18 minutes total
  3. 24 minutes waiting; 30 minutes total
  4. 15 minutes waiting; 21 minutes total
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A pooled M/M/s desk receives 15 calls per hour and each agent serves 10 per hour. Calculated Lq is 1.9286 for two agents and 0.2368 for three. Agents cost 25 dollars per hour; line waiting costs 40 dollars per caller-hour. Only these staff levels are available, and average line wait must be below 2 minutes. What should be chosen?
  1. Two agents; about 127.14 dollars per hour
  2. Three agents; about 75.00 dollars per hour
  3. Three agents; about 84.47 dollars per hour
  4. Two agents; about 50.00 dollars per hour
Show answerHide answer

Save this lesson to see this answer.

Set 4: Test the design when demand changes10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A firm makes one standard valve at high volume using shared general-purpose machines and complex routing. Which mismatch is likely raising its cost?
  1. The process supplies more flexibility than the product needs.
  2. The product requires more customization than the machines allow.
  3. The process supplies too little routing choice for the product.
  4. The product has too little standardization for connected flow.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A stable fulfillment process completes 30 orders per hour and holds 45 orders on average. Two tasks for each order take 8 and 5 minutes in parallel, followed by 7 minutes of packing. What are average throughput time and throughput efficiency?
  1. 90 minutes and about 16.7%
  2. 15 minutes and about 22.2%
  3. 90 minutes and about 22.2%
  4. 20 minutes and about 16.7%
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A line’s effective capacity is 1500 units per week and its expected efficiency is 88%. What output should be planned?
  1. 1500 units per week
  2. 1705 units per week
  3. 180 units per week
  4. 1320 units per week
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A product has annual demand of 60000 units and takes 3 minutes to process. Each setup takes 45 minutes. Current lots are 300 units; proposed lots are 150. Each machine offers 100000 minutes annually and a 10% cushion is required. What happens to the minimum machine count?
  1. It rises from 2 to 3 machines.
  2. It stays at 3 machines.
  3. It falls from 3 to 2 machines.
  4. It stays at 2 machines.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A press has 2100 available minutes per week. Product R needs 7 press minutes and S needs 12. Weekly demand is 180 R and 80 S. What does the press-load calculation show?
  1. 2100 minutes required; the press exactly meets the mix.
  2. 2220 minutes required; the mix exceeds press capacity.
  3. 1260 minutes required; the press has 840 spare minutes.
  4. 1920 minutes required; the press has 180 spare minutes.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A constrained resource offers 1500 minutes. U earns 40 dollars of throughput in 8 minutes; V earns 54 in 12. Demand is at most 120 U and 80 V, with other resources unconstrained. Operating expense is 6000 dollars. What mix and profit follow from the best use of constraint time?
  1. 67 U and 80 V; profit 1000 dollars
  2. 120 U and 45 V; profit 7230 dollars
  3. 100 U and 58 V; profit 1132 dollars
  4. 120 U and 45 V; profit 1230 dollars
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A facility sells a product for 50 dollars, variable cost is 30, and monthly fixed cost is 18000. Capacity is 1200 units per month and demand can absorb it all. What is the maximum monthly profit at this capacity?
  1. 6000 dollars
  2. 24000 dollars
  3. 18000 dollars
  4. 3000 dollars
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A business has fixed cost of 12000 dollars and two products with contribution ratios 0.60 and 0.30. The first product’s share of dollar sales falls from two thirds to one third. How does break-even sales value change?
  1. It rises from 24000 to 36000 dollars.
  2. It falls from 30000 to 24000 dollars.
  3. It rises from 24000 to 30000 dollars.
  4. It stays at 26666.67 dollars for both mixes.
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Two independent M/M/1 lines each receive 5 customers per hour and each server handles 8 per hour. For one pooled M/M/2 line with total arrivals of 10, software gives Lq=0.8013. What happens to average time waiting in line when the lines are pooled?
  1. It falls from 20.0 to about 4.8 minutes.
  2. It falls from 12.5 to about 9.6 minutes.
  3. It stays at 12.5 minutes in both designs.
  4. It falls from 12.5 to about 4.8 minutes.
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A desk receives 8 customers per hour off-peak and 25 during the peak; each server handles 10 per hour. Three servers are available. What does the peak rate imply about steady-state capacity?
  1. Three servers are stable at about 83.3% utilization.
  2. Two servers are stable at about 80.0% utilization.
  3. Three servers are stable at about 26.7% utilization.
  4. Two servers are stable at about 125.0% utilization.
Show answerHide answer

Save this lesson to see this answer.

Set 5: Make recommendations from connected evidence10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A clinic offers online self-registration but patients with complex needs often enter incomplete information. Staff then repeat the interview at arrival. What redesign best addresses both customer effort and useful contact?
  1. Require all patients to repeat both forms and interviews.
  2. Keep simple self-entry and offer staff help for complex cases.
  3. Remove all staff contact and reject incomplete registrations.
  4. Move every clinical discussion into the standard online form.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A manager wants to see which department owns each step and whether the longest delays occur between departments. What mapping approach would answer both questions directly?
  1. A flowchart showing only the successful route.
  2. A process chart recording only active work.
  3. A time-function map with department lanes.
  4. A blueprint showing only customer actions.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A collection service sends a customer confirmation before the warehouse confirms that the item is ready. Customers sometimes arrive for unavailable items. What change best protects this fail point?
  1. Release confirmation after a recorded warehouse-ready check.
  2. Keep early confirmation and shorten the confirmation message.
  3. Hide warehouse status and keep the same collection promise.
  4. Send more reminders while retaining the early confirmation rule.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A stable document service completes 16 cases per hour and holds 40 cases on average. It wants average throughput time at most 90 minutes while keeping output unchanged. Each case requires 18 worker-minutes of activity. What maximum average WIP and resulting throughput efficiency correspond to that limit?
  1. 24 cases and 12%
  2. 30 cases and 20%
  3. 40 cases and 12%
  4. 24 cases and 20%
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

One resource type will process annual demand for 24000 A and 18000 B. A takes 2 minutes per unit in lots of 400 with 40-minute setups; B takes 4 minutes in lots of 300 with 50-minute setups. Each resource offers 90000 minutes yearly. With a 25% cushion, how many resources are required?
  1. 2 resources
  2. 1 resource
  3. 3 resources
  4. 4 resources
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Two capacity options have comparable net payoffs in thousands of dollars. Large pays 700 under high demand and −140 under low; flexible pays 350 or 70. A report can only place the high-demand probability between 0.30 and 0.45. What EMV recommendation is supported over that whole interval?
  1. Choose large; its high-demand payoff is higher throughout.
  2. Choose flexible below 0.35 and large above that probability.
  3. Neither wins throughout; the ranking changes at p=0.375.
  4. Choose large below 0.375 and flexible above that probability.
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A serial process has preparation at 4 minutes with one worker, processing at 10 minutes with two parallel workers, and testing at 6 minutes with one worker. Two minutes of testing work can be transferred to processing without affecting quality. Demand is ample. What happens to capacity after the transfer?
  1. It rises to 15 per hour; testing remains the constraint.
  2. It rises to 12 per hour; processing becomes the constraint.
  3. It stays at 10 per hour; preparation becomes the constraint.
  4. It stays at 10 per hour; processing becomes the constraint.
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Process A costs 6000+16x dollars per year and can make 1800 units; B costs 18000+8x and can make 3000. Here x is annual unit volume. Forecast sales are 2200 units and all demand must be met internally. Selling price is 22 dollars. Which process is feasible and what profit does it earn at that volume?
  1. A; 7200 dollars profit
  2. B; 12800 dollars profit
  3. B; 30800 dollars profit
  4. A; 22400 dollars profit
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Visitors first register, then receive a consultation. Two staff register visitors in parallel and three specialists consult in parallel. How many service phases does each visitor pass through?
  1. 3 phases
  2. 5 phases
  3. 2 phases
  4. 6 phases
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A desk receives Poisson arrivals at 10 per hour. It can use either one automated server with constant 4-minute service at 20 dollars per hour, or one human server with exponential 3-minute mean service at 18 dollars per hour. Other standard model assumptions hold. Line waiting costs 30 dollars per customer-hour and must average at most 3.5 minutes. What should it choose?
  1. Automated server; total hourly cost 40 dollars.
  2. Human server; total hourly cost 33 dollars.
  3. Human server; total hourly cost 18 dollars.
  4. Automated server; total hourly cost 20 dollars.
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

96 Key Terms, each with its definition

A

As-is process
The as-is process is the sequence of work as it actually happens today, including waits, rework, exceptions and informal workarounds.
Observation finds that staff copy order details twice, although the official procedure shows one entry.
Average strategy
An average strategy adds capacity so that it runs alternately above and below demand as growth passes each capacity increment.
A facility expands in modules at intervals, accepting both some spare capacity and some temporary overload.

B

Back office
The back office performs low-contact supporting work that can often be standardized, batched or scheduled away from customers.
A bank processes routine payment records away from the counter where customers ask questions.
Balking
Balking occurs when a potential customer sees or expects a wait and decides not to join the service line at all.
A visitor sees a long reception line and leaves without entering it or registering for service.
Batch process
A batch process makes products in separate groups, with resources changed over between one product or group and the next.
A cosmetics plant fills one cream for several hours before cleaning and setting up for another formula.
Best operating level
The best operating level is the volume at which a facility's average cost per unit is lowest for its given size and design.
Running far below the best operating level leaves fixed facility costs spread over too few units.
Bottleneck
A bottleneck is the resource with the lowest effective capacity relative to its workload, limiting the output of the whole process.
Two workers may make a long task faster as a group than a shorter task handled by one worker.
Bottleneck time
Bottleneck time is the limiting stage's effective time per unit after allowing for parallel resources; it sets cycle time at full output.
A ten-minute task with two identical workers has five effective minutes per unit for capacity analysis.
Break-even point
The break-even point is the sales volume or value where total revenue equals total cost, leaving profit equal to zero.
Selling above break-even creates profit only while the assumed prices and cost structure continue to apply.

C

Capacity
Capacity is the maximum output a system can deliver in a stated period, or the resource time available when outputs differ greatly.
A mixed-product workshop compares required machine hours with available machine hours for the week.
Capacity cushion
A capacity cushion is capacity held above expected load, measured here as 100% minus average utilization of total capacity.
An expected utilization of 82% leaves an 18% cushion to help absorb variation in demand or resource needs.
Channel
A channel is a server operating in parallel with other servers, each able to serve a customer at the same service phase.
Three receptionists who can each register the next visitor provide three channels for registration.
Continuous process
A continuous process produces very high volumes of a flowing, standardized output using specialized equipment, often around the clock.
A paper mill runs a connected flow of material instead of treating every sheet as a separate custom job.
Contribution margin ratio
The contribution margin ratio is contribution divided by selling price, showing the fraction of sales value available for fixed costs and profit.
A product with a 40% contribution ratio supplies 40 cents from each sales dollar toward fixed costs and profit.
Contribution per unit
Contribution per unit is selling price minus variable cost per unit, the amount each sale provides for fixed costs and profit.
A service sold for 35 dollars with 14 dollars of variable cost contributes 21 dollars before fixed costs.
Crossover point
A crossover point is the volume at which two alternative processes have equal total cost, including fixed and variable costs.
Above a relevant crossover, a specialized process may repay its higher fixed cost through lower variable cost.
Cycle time
Cycle time is the average interval between successive completed units and is the reciprocal of the throughput rate.
A line completing 20 units per hour has a three-minute cycle time even if each unit stays much longer.

D

Decision tree
A decision tree shows choices, uncertain outcomes and payoffs in a branching structure that is evaluated from right to left.
A small-facility branch can include a later choice to expand only if demand turns out to be high.
Decoupling
Decoupling separates high-contact customer-facing work from low-contact supporting work so each can be organized appropriately.
An adviser handles unusual cases while a separate team processes complete standard applications in batches.
Delay
A delay is time an item spends waiting for the next process step because that step is not yet ready to receive or handle it.
A completed form sits in an inbox until the reviewer becomes available to check its details.
Design capacity
Design capacity is the theoretical maximum output of an operation under ideal conditions during a stated period.
A line's ideal rate multiplied by its scheduled shift hours gives a weekly design-capacity figure.
Diseconomies of scale
Diseconomies of scale occur when greater size raises average unit cost through coordination problems, complexity or congestion.
A very large operation may spend more time coordinating transfers than a smaller, simpler facility.
Drum-buffer-rope
Drum-buffer-rope links the constraint's schedule, a protective work buffer and a release signal to coordinate flow around the constraint.
A release signal admits enough work to protect the bottleneck without filling the whole factory with inventory.

E

Economies of scale
Economies of scale occur when a larger operation lowers average unit cost by spreading fixed costs and using specialization effectively.
A higher-volume facility can justify specialized equipment whose cost would be too high for a small output.
Effective capacity
Effective capacity is output expected under planned operating conditions, allowing for mix, maintenance, changeovers and planned stops.
Planned cleaning reduces the line's usable weekly output below the ideal design-capacity level.
Efficiency
Efficiency is actual output divided by effective capacity for the same period, showing performance against the planned operating level.
Actual output of 630 units against effective capacity of 700 gives efficiency of 90%.
Elevation
Elevation adds capacity to a constraint after existing capacity has been used well, through investment, extra time or outsourcing.
A firm adds another shift at the constrained machine after eliminating avoidable stops and setup losses.
Expected monetary value
Expected monetary value is the sum of each possible monetary payoff multiplied by the probability of that payoff's state.
An expansion's EMV can be positive even though its low-demand branch would create a substantial loss.
Exploiting a constraint
Exploiting a constraint means getting more useful output from its existing capacity by preventing avoidable idle time and wasted work.
Checking input quality before the bottleneck prevents scarce minutes from being spent on unusable items.

F

Fail point
A fail point is a service step where a likely error or delay could damage the customer's experience or the intended outcome.
Copying a customer's collection date by hand is marked as a fail point because an error can cause a wasted trip.
Fail-safing
Fail-safing designs a step to prevent a mistake or catch it immediately, before it moves onward and harms the customer.
A booking form blocks submission when the required contact number is missing, preventing an incomplete record.
Fixed cost
A fixed cost stays unchanged as volume changes within a defined relevant range and period, even though its cost per unit changes.
The monthly facility rent is unchanged when output rises within the same premises and operating range.
Flowchart
A flowchart uses activity shapes, decision shapes and directional arrows to show the sequence and branches of a process.
A “Payment approved?” diamond has labeled exits that lead to dispatch or a request for another payment method.
Front office
The front office is the customer-facing part of a service, designed around direct interaction and the customer's experience.
A service adviser discusses a fault with the customer before sending the job to a technician backstage.

I

Inspection
An inspection is a process-chart step that checks an item without changing it, represented by a square in the standard symbol set.
Measuring the finished hole checks its size; enlarging an undersized hole would be a separate operation.

J

Job shop
A job shop shares flexible, general-purpose resources among small quantities of highly varied work, often with different routes.
A custom metal shop sends each order to the cutting, drilling and finishing equipment its design needs.
Jockeying
Jockeying occurs when a waiting customer switches from one line to another in an attempt to receive service sooner.
A shopper leaves one checkout queue for another that appears to be moving more quickly.

K

Kendall notation
Kendall notation A/B/s describes the arrival distribution, service-time distribution and number of parallel servers in a queue model.
M/D/1 indicates Poisson arrivals, a constant service time and a single server handling the line.

L

Labor intensity
Labor intensity is the cost of labor relative to the cost of facilities and equipment in the service process matrix.
An airline can employ many people and still have low labor intensity because its aircraft are expensive.
Lag strategy
A lag strategy adds capacity after demand growth appears, reducing spare-capacity risk but allowing interim shortages or overtime.
A producer waits for sustained extra orders before installing a machine, accepting some delayed deliveries.
Lead strategy
A lead strategy adds capacity before forecast demand arrives, protecting availability while risking idle resources if growth falls short.
A service opens extra desks before a forecast seasonal rise so customers can be served when the peak starts.
Line of interaction
The line of interaction separates customer actions from onstage employee actions; a crossing marks a direct service encounter.
Handing a parcel to the counter employee crosses the line of interaction in a collection-service blueprint.
Line of visibility
The line of visibility separates employee actions customers can see from backstage employee work that remains out of their view.
A customer sees an adviser explain the repair, while the technician's earlier diagnosis stays backstage.
Little's law
Little's law links stable long-run averages: inventory inside a boundary equals throughput rate multiplied by time inside that boundary.
A stable flow of 10 cases per day with 50 cases in process implies an average journey of five days.

M

M/D/1 model
The M/D/1 model describes Poisson arrivals at one server with a constant service time, removing service-duration variation from M/M/1.
An automatic wash with a fixed cycle has less service-time variation than a manually handled variable-duration job.
M/M/1 model
The M/M/1 model describes Poisson arrivals and exponential service at one server; its finite steady-state averages require λ<μ.
A single help desk with a variable service duration may fit M/M/1 after the population and line assumptions are checked.
M/M/s model
The M/M/s model describes one FIFO line feeding s identical parallel servers, with Poisson arrivals and exponential service times.
A shared help-desk queue sends each new call to the next free agent instead of assigning a separate line per agent.
Mass customization
Mass customization supplies high volume and many customer choices by combining standard modules with flexible operations and late customization.
A computer maker stocks common components and assembles each order in the configuration the buyer chooses.
Mass production
Mass production makes a high volume of standardized units through a repeated sequence of tasks, commonly on a connected line.
An appliance factory repeats the same assembly sequence for thousands of units of its standard model.
Mass service
A mass service handles many transactions with relatively little customization, using standardized tasks and defined staff roles.
A supermarket organizes a large number of customer transactions around repeatable checkout procedures.

O

Operation
An operation is a process-chart step that changes an item or produces something, represented by a circle in the standard symbol set.
Drilling a mounting hole changes the part, so the chart records that task as an operation.
Overall equipment effectiveness
Overall equipment effectiveness is the product of availability, performance and quality, combining downtime, speed and defect losses.
A machine can run for most of its planned time yet have low OEE because it runs slowly or produces defects.

P

Parallel resources
Parallel resources are equivalent servers, workers or machines that handle separate units at the same process stage at the same time.
Two technicians each repairing a separate device raise repair-stage capacity without shortening either repair.
Perceived waiting
Perceived waiting is the customer's experience of a delay, shaped by uncertainty, fairness, anxiety and how the waiting time is spent.
An honest wait estimate and an explanation can reduce uncertainty while a customer waits for the same service.
Phase
A phase is a sequential stage of service that a customer passes through, potentially with several channels at each stage.
Registration followed by consultation is a two-phase service even if each phase has several staff members.
Physical evidence
Physical evidence is the tangible or visible material customers encounter and use to judge a service, including digital interfaces.
A clear booking confirmation and an accurate invoice help a customer understand what the service delivers.
Poisson arrivals
Poisson arrivals describe random arrivals with a constant mean rate and independent counts in separate intervals; interarrival times are exponential.
A model may use Poisson arrivals for unscheduled calls reaching a desk during a period with a stable mean rate.
Pooling
Pooling combines separate waiting lines into one shared line for parallel servers, allowing available capacity to serve the next waiting customer.
A receptionist who becomes free can take the next visitor even when arrivals were uneven across the former lines.
Process
A process is a linked set of activities that transforms materials, information or customers into a product or service output.
A repair process turns a damaged device and a fault report into a working device ready for collection.
Process chart
A process chart lists steps in order, classifies their activity type, and records the time and distance involved in each step.
A chart separates the minutes spent repairing a device from the minutes spent moving, checking and waiting.
Product-process matrix
The product-process matrix compares product volume and standardization with process flow structure to show suitable or costly mismatches.
A growing standard product may move from shared workshop equipment to batch flow and then a dedicated line.
Professional service
A professional service handles highly customized work using substantial staff judgment and close contact with individual customers.
A consulting team spends time understanding each client's situation before proposing a tailored response.
Project process
A project process organizes resources around a large, complex, one-off output that commonly stays in one place while work proceeds.
Building a bridge requires different teams to bring their skills and equipment to the same fixed site.

Q

Queue discipline
Queue discipline is the rule that selects the next customer for service, such as arrival order, priority or appointments.
An urgent case can go first under a priority rule even though another customer arrived earlier.

R

Relevant range
The relevant range is the output interval within which the assumed fixed cost and constant variable cost per unit remain valid.
Adding a second shift can change fixed staffing costs, so the old break-even calculation must be revisited.
Reneging
Reneging occurs when a customer joins a waiting line but leaves before service begins because the wait is no longer acceptable.
A caller hangs up after spending several minutes waiting for an available service agent.
Resource load
Resource load is the total processing and setup time demanded from a resource by the planned products during a stated period.
A press receiving 900 minutes of one product and 1400 of another needs 2300 minutes for that mix.

S

Sales mix
The sales mix is the relative share of different products sold; a multiproduct break-even result assumes those proportions stay fixed.
A shift from high-contribution accessories to lower-contribution equipment can increase the sales needed to break even.
Sensitivity analysis
Sensitivity analysis checks whether changing an uncertain input, such as a demand probability, changes the preferred alternative.
A probability cutoff close to the current estimate signals that more demand information could change the choice.
Service blueprint
A service blueprint maps customer actions alongside physical evidence, visible employee work, hidden work and supporting processes.
An appointment blueprint links booking and arrival to reception, preparation and the scheduling system.
Service process matrix
Schmenner's service process matrix classifies services by labor intensity and by their degree of interaction and customization.
An auto repair business has equipment-intensive work and customized diagnoses, placing it in the service-shop quadrant.
Service rate
The service rate is the average number of customers one server can complete per time period while busy, the reciprocal of mean service time.
A mean service duration of six minutes corresponds to a rate of ten customers per server-hour.
Service shop
A service shop is a middle category in Slack's volume–variety framework, but a low-labor, high-customization category in Schmenner's matrix.
A hotel is a service shop in Slack's framework and a service factory in Schmenner's classification.
Service-level target
A service-level target states the performance a service aims to meet, such as a maximum acceptable average time waiting in line.
A desk may require an average queue wait below three minutes when comparing affordable staffing options.
Setup time
Setup time is the resource time needed to prepare for a lot or change product, adding workload beyond processing individual units.
Smaller lots require more setups for the same annual demand, increasing the capacity minutes needed.
State of nature
A state of nature is a possible future outcome outside the decision maker's control that changes the payoff from an alternative.
High and low demand are separate states when comparing the payoffs from two possible expansions.
Steady state
A steady state is a stable long-run operating pattern with finite average queue measures, requiring average arrivals below available service capacity.
An M/M/1 arrival rate equal to service rate leaves no finite long-run mean waiting time to calculate.
Subordination
Subordination aligns other activities with the constraint's needs and pace, supporting its output while avoiding unnecessary work in process.
An upstream team releases work when the constrained station needs it instead of maximizing its own output.
Support process
A support process is work by another department or system that enables service employees to complete their customer-facing tasks.
The parts-ordering system supports a repair even though customers do not interact with it directly.
Swim-lane map
A swim-lane map places activities in lanes for their responsible roles or departments, making ownership and handoffs visible.
An order arrow crosses from sales to the warehouse when responsibility for filling the order changes.

T

Theory of constraints
The theory of constraints improves system performance by identifying its limiting constraint and organizing improvement around that limit.
A factory investigates the resource that restricts sales output before buying faster equipment elsewhere.
Throughput accounting
Throughput accounting measures money from sales less totally variable costs, money tied up in inventory, and operating expense.
A product earning more money per bottleneck minute can be preferred over one with a larger unit contribution.
Throughput efficiency
Throughput efficiency is work content divided by total throughput time, multiplied by 100% when expressed as a percentage.
A case requiring one hour of activity during a ten-hour journey has throughput efficiency of 10%.
Throughput per constraint minute
Throughput per constraint minute is sales less totally variable cost per unit divided by the unit's use of the scarce resource.
A product earning 36 dollars in six constrained minutes yields 6 dollars per minute of scarce time.
Throughput rate
Throughput rate is the average number of completed units leaving a defined process per unit of time, such as cases per day.
A team completing 30 applications each working day has a throughput rate of 30 applications per day.
Throughput time
Throughput time is the elapsed time for one unit to enter and leave the defined process, including both activity and waiting.
An application may need 40 minutes of work but spend four working days moving through review queues.
Time-function map
A time-function map lays role lanes against a time scale so the lengths of activities and waits show where elapsed time goes.
A map shows a two-day credit-check queue between a short order entry task and warehouse release.

U

Utilization
Utilization is actual output divided by design capacity for the same period, showing the share of ideal capacity actually delivered.
Weekly output of 600 units against a design capacity of 800 gives utilization of 75%.

V

Value-added ratio
The value-added ratio is time spent making customer-valued changes divided by the total elapsed time through the process.
If a 50-minute journey contains 10 minutes of valued changes, the ratio is 20% despite busy staff.
Variable cost per unit
Variable cost per unit is the cost incurred for each additional unit, assumed constant within the relevant range of the model.
If each package needs 2 dollars of material, making 100 extra packages adds 200 dollars of material cost.
Variety
Variety is the range of products or services offered and the degree to which one customer's order differs from another.
A workshop making a different cabinet design for each customer handles more variety than a standard shelf line.
Volume
Volume is the number of units of a product or transactions of a service delivered during a stated period.
A bottle line producing 20000 identical containers per day has high volume for that particular product.

W

Waiting cost
Waiting cost is the value lost while customers or items wait, calculated per period from the average count within the chosen cost boundary.
If only queue time costs money, multiply the cost per customer-hour by Lq instead of total system occupancy.
Weighted contribution margin ratio
The weighted contribution margin ratio averages product contribution ratios using each product's share of total dollar sales.
Products earning different prices need sales-value weights, so equal unit sales need not receive equal weights.
Work content
Work content is the total activity time required for one unit, added across all tasks even when some tasks run simultaneously.
Two parallel six-minute tasks contain 12 worker-minutes of work, although they can finish in six elapsed minutes.
Work in process
Work in process is the number of units that have entered a defined process but have not yet left it, including units waiting.
Cases in an inbox and cases being actively reviewed both count as work in process for the whole office.