Aggregate Planning, MRP and ERP

Learn how companies decide how much to produce over the coming months and how that plan becomes orders for every part. Follow the monthly sales and operations planning cycle, build and cost chase, level and mixed aggregate plans, and break the plan down into a master production schedule. Use bills of materials and MRP records to calculate what to order and when, compare lot-sizing rules, check plans against work-center capacity, and see how ERP systems connect planning with the rest of the business.

IntermediateLesson 7 of 9 in Operations Management Course

What you will learn

  1. Place aggregate planning in a company's planning hierarchy and follow the monthly sales and operations planning (S&OP) cycle that turns forecasts, capacity and financial targets into one agreed plan.
    • Place aggregate planning in the planning hierarchy
      Define aggregate planning and S&OP, describe the planning horizons, and show how an aggregate plan for product families is broken down into detailed schedules.
    • Follow the monthly S&OP cycle
      Describe the steps of a monthly S&OP cycle, read an S&OP family plan, reconcile volumes with the financial plan, and recognize what makes the process fail.
  2. Choose among the ways to match capacity and demand, cost chase, level and mixed plans in a planning table, and pick a plan using both cost and judgment.
    • Choose options for matching capacity and demand
      Compare the capacity options and demand options available in the intermediate term, define chase, level and mixed strategies, and judge when each fits, including in services.
    • Set up a planning table and cost a chase plan
      Organize the data an aggregate plan needs, apply the inventory and workforce balances, and work out the full cost of a chase plan.
    • Cost level plans with inventory, backorders and subcontracting
      Calculate a level production rate, track the inventory or backorders it creates, and cost level plans that use inventory alone or a smaller workforce plus subcontracting.
    • Compare plans and choose a mixed strategy
      Cost a mixed plan, compare all plans side by side, test how sensitive the choice is to the cost figures, and weigh the factors a cost table leaves out.
  3. Turn the aggregate plan into a master production schedule that can be promised to customers, and use the bill of materials to see what each end item is made of and when its parts are needed.
    • Build a master production schedule and promise orders
      Disaggregate the plan into an MPS, calculate projected available balance and available-to-promise, and protect the schedule with time fences.
    • Read and use a bill of materials
      Distinguish dependent from independent demand, read a product structure, explode requirements level by level with inventory, and use lead times and special bill types.
  4. Use MRP records to net requirements, offset lead times and explode plans down the product structure, size orders with standard lot-sizing rules, and keep the plan reliable in practice.
    • Apply MRP gross-to-net logic
      Name the inputs and outputs of MRP, complete an MRP record step by step, and pass planned orders down to the next level.
    • Choose a lot-sizing technique
      Size MRP orders with lot-for-lot, EOQ, period order quantity and other rules, compare their costs on the same requirements, and know when each fits.
    • Keep MRP plans reliable and extend MRP logic
      Maintain accurate data, choose how MRP replans, use pegging, action notices and firm planned orders, recognize system nervousness, and extend time-phased logic to services and distribution.
  5. Check whether the MPS and MRP plans fit the capacity of key resources and work centers, and explain how closed-loop MRP, MRP II and ERP systems link planning with the rest of the business.
    • Check plans with rough-cut capacity planning and CRP
      Place capacity checks at each planning level, calculate rated capacity and work-center load, and choose remedies for overloads and underloads.
    • Explain MRP II and ERP systems
      Trace the path from MRP to ERP, describe what an ERP system integrates, and weigh its benefits and drawbacks for manufacturers and service organizations.

Aggregate Planning study guide

5 chapters

1

Balance demand, supply, and business targets

Planning connects decisions made years ahead with work done today. A company first chooses its basic capacity, then decides how to use it, and finally assigns specific jobs. Sales and operations planning brings the departments together around the middle of that chain. Learn to read a family plan, connect units with financial targets, and distinguish the decisions executives make from the detail that planners handle afterward.

1.1 Connect business plans with daily work

Aggregate planning decides how much to produce over the coming months and how to supply it. It groups products that use common resources, so the plan can balance demand with workforce, inventory, and other capacity options.

Choose the right planning level
HorizonMain decisionExample
Long range, usually more than a yearChoose basic capacityOpen a plant or buy major equipment
Intermediate, often 3–18 monthsUse existing capacitySet monthly output, staffing, and inventory
Short range, often up to 3 monthsAssign specific workPut an order on a machine next Tuesday

The boundaries vary by company. The useful distinction is the decision each plan controls. An aggregate planner can add overtime within a plant; a new building usually needs an earlier, longer-range decision.

Plan a common unit

A product family groups items that share processes and resources. A bicycle maker might plan 1,200 road bikes for March before choosing frame sizes and colors. Other useful aggregate units include labor-hours, machine-hours, or kilograms of material. The unit must represent the resources the plan needs.

Family demand is generally more predictable than individual-item demand because some item-level variation cancels when totals are combined. Shared equipment and labor also make a family total useful for capacity decisions. A family plan still needs enough detail to avoid hiding a scarce resource used by only some items.

The inputs are forecasts by period, starting workforce and inventory, available capacity, and cost rates. Policies matter too: a limit on overtime, a target service level, or a commitment to stable employment can rule out an otherwise cheap plan.

Break the family plan into detail

Disaggregation translates the family total into specific end items and dates. The sequence is aggregate plan → master production schedule (MPS) → material requirements planning (MRP) → short-term job schedules.

For 1,200 road bikes, the MPS might specify 300 small, 500 medium, and 400 large bikes across four weeks. These quantities total 1,200. MRP then calculates the frames, wheels, and other parts needed for the planned builds. The daily schedule assigns actual jobs to resources. A monthly quantity alone cannot say which customer order runs on Tuesday.

Agree across departments

Sales and operations planning (S&OP) is the monthly decision process that aligns family demand, supply, financial targets, and business strategy. Senior management leads it. Sales contributes market knowledge and customer commitments; operations and purchasing contribute capacity and supplier limits; finance connects volumes with revenue, cost, and cash. Product development explains launches and phase-outs, while human resources supplies hiring and training information.

The aggregate plan is the operations side of the agreed S&OP plan. S&OP needs decisions that all these functions can carry out. A sales forecast without a supply response leaves that work unfinished.

Services use the same hierarchy. A call center can convert forecast calls into monthly agent-hours, then into weekly staffing and shifts. Unused service time cannot be stored as finished inventory, so staffing flexibility carries more of the adjustment.

Key Takeaways

  • Aggregate planning sets family output and resource use over the intermediate horizon.
  • Disaggregation must preserve family totals while adding item quantities and dates.
  • S&OP aligns sales, operations, finance, and other functions around one operating plan.
  • Service plans often use staff-hours because unused service capacity cannot be stored.

1.2 Turn the monthly review into an agreed plan

The S&OP cycle replaces separate departmental plans with one set of decisions. It looks far enough ahead for the company to respond before a shortage, excess inventory, or financial gap becomes urgent.

Follow a rolling cycle

A typical cycle begins after month-end:

  1. Gather data: update actual sales, output, inventory, and the statistical forecast.
  2. Review demand: add market knowledge, promotions, launches, and customer commitments.
  3. Review supply: check capacity, materials, and suppliers; develop responses to constraints.
  4. Reconcile: compare demand, supply, and finance; prepare scenarios and recommendations.
  5. Decide: executives approve the plan and settle unresolved trade-offs.

Some companies include a separate product review. The names and number of meetings vary, but the demand, supply, financial, and executive decisions still need owners.

The horizon is rolling, often 12–18 months. Each month, actual results replace the completed month, the remaining periods are updated, and a new month is added at the far end. S&OP decides family volume. The MPS later decides item mix, such as individual sizes and models.

Read the family balances

For a make-to-stock family, production builds inventory before sales draw it down:

ending inventory=beginning inventory+production−sales

Beginning stock of 500 units, production of 1,100, and sales of 1,250 leave 350 units. Against a target of 400, the projected gap is 50 units. The team must choose more supply or a lower inventory position.

For a make-to-order family, track orders waiting to ship:

ending backlog=beginning backlog+new orders−shipments

A family starting with 180 units of backlog, taking 900 units of new orders, and shipping 950 ends with 130. A growing backlog can lengthen customer lead times; a sustained decline can signal that capacity will soon lack work.

Translate volume into money

At an average selling price of $250, sales of 1,200 units produce $300,000 of revenue. A financial target of $330,000 therefore has a $30,000 gap. More production alone cannot close it: revenue needs sales. Options include finding additional demand that supply can meet, changing the product plan, or revising the financial forecast.

Track plan attainment as actual output divided by planned output. Producing 1,140 of 1,200 planned units gives 95%. Review forecast accuracy, inventory or backlog against target, and on-time delivery alongside it. Strong attainment of the wrong plan can still leave poor customer service or too much stock.

Keep decisions honest

S&OP weakens when departments retain different numbers, change forecasts to fit targets, or use the executive meeting only to read reports. A forecast describes expected demand; a target describes desired performance. Reconciliation makes their gap visible so leaders can decide what to do.

Integrated business planning (IBP) usually means a broader connection with strategy and financial planning, often over 24 months or more. Usage varies, so judge the process by its decisions and links, not its name. Keep attention on later months too: that is where hiring, supplier, and product decisions still have time to work.

Key Takeaways

  • The cycle moves from updated data through demand, supply, reconciliation, and executive decisions.
  • A rolling horizon adds a future period whenever a completed period drops out.
  • Make-to-stock plans track inventory; make-to-order plans track backlog.
  • Convert planned sales into money to expose gaps with financial targets.
  • Forecasts and targets serve different purposes; preserve the gap for decision-making.
2

Build and compare aggregate plans

A demand peak can be met by building inventory early, hiring more people, adding overtime, or buying output from another producer. Each choice moves costs and risks to a different place. Follow a pump plant through chase, level, and mixed plans, keeping its inventory and workforce balances visible. Then compare the full costs and test whether the apparent saving survives a change in demand, cost, or customer-service requirements.

2.1 Choose how to match supply with demand

An aggregate plan can change supply, change demand, or combine both. Start with the product and workforce: storage life, skill requirements, customer patience, and supplier flexibility determine which options are usable.

Compare capacity options
OptionWhat it helps withMain cost or risk
Build inventory earlySmooth output before a peakHolding cost, damage, or obsolescence
Hire or lay off workersMatch regular output to demandTraining, severance, skill loss, and morale
Use overtime or paid idle timeAdjust hours with the same staffPremium pay, fatigue, or paid unused time
SubcontractBuy output beyond internal capacityHigher unit cost and less control
Use temporary or part-time staffAdd flexible laborTraining, turnover, and quality consistency

Overtime rates depend on the employment arrangement; a common teaching example is 1.5 times regular pay. Hiring also takes time before new staff reach full productivity. Employment rules and agreements can constrain workforce changes.

Change the demand pattern

A promotion or lower off-peak price can move demand toward quieter periods. Backordering accepts an order now for later delivery, provided the customer accepts the delay. Otherwise the unmet demand can become a lost sale. Counterseasonal mixing combines products with different peaks, such as heaters and air conditioners, to spread shared-resource demand across the year.

Demand measures need a supply check. A promotion that creates demand during an existing bottleneck can make delivery performance worse.

Select a strategy

A chase strategy adjusts production to demand period by period, often through workforce changes, overtime, or subcontracting. It suits output that cannot be stored and work for which capacity can change quickly.

A level strategy keeps output or the core workforce steady. Inventory absorbs differences between output and demand; accepted backorders can absorb temporary shortages. It suits storable products and skilled teams that are costly to rebuild. A constant workforce can still vary output through overtime or idle time.

A mixed strategy combines options, such as a stable core workforce, some inventory built early, and overtime during a short peak. A pure strategy changes only one planning variable.

Chase avoids inventory holding but can create large workforce-change costs. Level avoids repeated workforce changes but can create large stocks. The demand pattern and cost rates decide their relative cost; the strategy name cannot settle that comparison.

Apply the ideas to services

Services often adjust staffing through part-time work, flexible shifts, overtime, and cross-training. A restaurant needs capacity during the dinner rush; unused staff time from lunchtime cannot be carried forward as stock.

Revenue management, also called yield management, varies prices and access across customer segments and booking times. It is useful when capacity is fixed, can be sold in advance, expires unused, and has a low extra cost per customer served. A hotel room tonight loses its selling opportunity once the night passes. Selling every room cheaply very early can also displace customers willing to pay more later, so the decision concerns timing and revenue as well as occupancy.

Key Takeaways

  • Capacity options change supply; demand options influence when or how much customers buy.
  • Chase follows demand; level stabilizes output or workforce; mixed plans combine options.
  • Backorders require customers who accept delayed delivery.
  • Service capacity expires, so staffing and demand timing are central.
  • Revenue management balances prices and booking opportunities for perishable capacity.
  • Cost every usable strategy before choosing one.

2.2 Build and cost a chase plan

A planning table keeps quantities, workers, and money separate until the quantities are correct. For each period, first calculate the workforce and inventory movement. Then apply the appropriate cost rate to each movement or balance.

Set up the balances

Record demand by period, beginning stock and workforce, output per worker, and all cost rates. Include capacity limits, ending-stock targets, and backorder policies.

It=It−1+Pt−Dt

Here, ending inventory equals the previous balance plus all output received minus demand. Output includes regular production, overtime, and subcontracted supply. A negative net inventory balance represents a backorder. Workforce follows a separate balance: current workers equal previous workers plus hires minus layoffs.

Match the pump plant's monthly demand

The plant starts with 25 workers and no stock. Each worker produces 40 pumps per month and earns $3,200 per month. Hiring costs $1,000 per worker, layoffs $1,500, and inventory holding $10 per pump per month on ending stock. Demand totals 7,200 pumps.

MonthDemandWorkers neededHiresLayoffs
Jan8002005
Feb1,0002550
Mar1,2003050
Apr1,60040100
May1,4003505
Jun1,2003005

Divide each month's demand by 40 to obtain its workforce. Then compare that workforce with the previous month's workforce. January needs five layoffs because the starting workforce is 25; starting the calculation from zero would miss this cost. Production equals demand in each month, so every ending inventory is zero.

Calculate the full cost

The workforce totals 180 worker-months. Regular labor is therefore 180 × $3,200 = $576,000. The 20 hires cost $20,000; the 15 layoffs cost $22,500. With no ending stock or backorders, the total is $618,500.

Regular labor is paid for workers employed, including paid idle time. The shortcut 7,200 pumps × $80 gives the same $576,000 here because all 180 worker-months are fully productive. It would understate cost if workers were paid while idle. It also needs revision when overtime or subcontracted output replaces regular-time production at another rate.

Check practical details

Whole workers cannot be rounded down when that leaves demand uncovered. If 30.5 workers are calculated, 30 workers do not provide enough output. An extra worker, overtime, inventory, or subcontracting must close the gap; show the resulting stock or cost.

Different working-day counts also change the interpretation of monthly demand. Demand of 1,320 over 22 days and 1,200 over 20 days both require 60 pumps daily. Compare capacity on a consistent time basis.

Holding conventions must stay fixed across plans. Ending-inventory costing charges every period's positive ending balance. Average-inventory costing uses a different base and can produce a different ranking. Backorder cost applies to the magnitude of a negative balance, not as a negative holding cost.

Key Takeaways

  • Calculate workforce needs before hiring and layoff costs.
  • Include the starting workforce in the first period comparison.
  • Charge regular labor for paid worker-periods, including paid idle time.
  • Carry each ending inventory balance into the next period.
  • Use consistent time units and inventory-cost conventions.

2.3 Follow inventory through a level plan

A level plan spreads production across the horizon. Its average output can meet total demand while still missing an early peak, so calculate both the overall rate and every period's inventory balance.

Find the constant rate
level rate=total demand+target ending stock−beginning stocknumber of periods

For six months of pump demand totaling 7,200, with zero beginning and target ending inventory, the rate is 1,200 pumps per month. At 40 pumps per worker, this requires 30 workers. Hire five in January from the starting workforce of 25.

Beginning stock reduces required production. With 300 pumps initially available and no ending target, total production would be 6,900 and the rate 1,150. Using 1,200 would leave an unplanned 300 pumps at the end.

Carry the stock forward
MonthDemandProductionEnding inventory
Jan8001,200400
Feb1,0001,200600
Mar1,2001,200600
Apr1,6001,200200
May1,4001,2000
Jun1,2001,2000

February starts with January's 400: add 1,200 and subtract 1,000 to obtain 600. Do not restart each month at zero. April's peak uses 400 pumps from stock; May uses the remaining 200.

Regular labor costs 30 workers × 6 months × $3,200 = $576,000. Hiring costs $5,000. Sum the ending stocks: 1,800 pump-months, costing $18,000 at $10 each. Total cost is $599,000, which is $19,500 below the chase plan.

Check every cumulative position

A plan avoids backorders only if beginning inventory plus cumulative production covers cumulative demand in every period. A zero final balance checks the horizon total but says nothing about earlier shortages.

If January demand were 1,600 with no starting stock, output of 1,200 would leave a 400-unit backlog immediately. Customers must accept that delay for backordering to be usable. On a cumulative graph, inventory equals beginning stock plus cumulative production minus cumulative demand. Start the supply line at beginning stock if you want the vertical gap to show the inventory directly.

Test a smaller workforce

Keep 28 workers, producing 1,120 monthly, and subcontract 240 pumps in each of April and May. Ending stocks become 320, 440, 360, 120, 80, and zero. This needs three initial hires and buys 480 pumps externally.

The cost is $537,600 regular labor + $3,000 hiring + $13,200 holding + $52,800 subcontracting = $606,600. The external price is $110 per pump, compared with $80 regular labor per fully productive pump. Lower payroll alone therefore does not make this plan cheaper. A level workforce with subcontracting is a mixed use of options, even though its internal staffing stays level.

Key Takeaways

  • Beginning inventory reduces the production needed over the horizon.
  • A level rate that balances total demand can still create early shortages.
  • Sum all positive ending stocks to calculate ending-inventory holding cost.
  • Check subcontracting cost alongside the payroll it replaces.

2.4 Compare cost, feasibility, and risk

A mixed plan can delay hiring, carry less inventory, and accept a limited backlog. Evaluate these changes together: a saving in one row can create a larger cost or an unacceptable service result elsewhere.

Cost a mixed pump plan

Keep 25 workers in January, hire two in February, then five in March. Hold 32 workers from March through June. Output is 1,000, 1,080, 1,280, 1,280, 1,280, and 1,280 pumps, totaling 7,200.

Against demand of 800, 1,000, 1,200, 1,600, 1,400, and 1,200, ending balances are 200, 280, 360, 40, −80, and zero. May's negative 80 means customers wait for 80 pumps delivered in June. June production must serve that backlog as well as June demand.

The 180 worker-months cost $576,000. Seven hires cost $7,000. Positive ending stocks total 880 pump-months, costing $8,800. The 80 pump-months backordered cost $2,000 at $25 each. Total cost is $593,800.

PlanTotal cost
Mixed$593,800
Level, 30 workers$599,000
Level workforce of 28 plus subcontracting$606,600
Chase$618,500

The mixed plan is cheapest among these candidates under these costs. It is acceptable only if the planned May delay is allowed. Spreadsheet comparison proves which tested candidate costs least; it does not prove that no better plan exists.

Test a cost change

Suppose holding falls from $10 to $4 per pump per month. Recalculate only the affected row while keeping the other costs intact.

The 30-worker level plan becomes $576,000 + $5,000 + 1,800 × $4 = $588,200. The mixed plan becomes $576,000 + $7,000 + 880 × $4 + $2,000 = $588,520. Level is now cheaper by $320. Lower holding cost favors the plan carrying more inventory.

Sensitivity analysis shows how robust a decision is. A narrow cost advantage deserves close attention to forecast error, supplier reliability, customer patience, and the availability of trained workers. Repeated layoffs can damage skills and morale; more inventory can become obsolete if demand falls. These effects help define the cheapest acceptable plan.

Understand what models decide

A linear program can choose output, inventories, backorders, and workforce changes together when costs and constraints are linear. Its minimum is conditional on that model's costs and constraints.

A transportation model has a narrower role. Regular-time, overtime, and subcontract capacities are fixed sources; period demands are destinations. Producing early adds holding cost for each period the unit waits. The model allocates supply within those capacities. It does not choose how many people to hire or lay off.

Review the chosen plan in the monthly S&OP cycle. Updated demand and actual performance can change the best response, while the near periods move into item-level master scheduling.

Key Takeaways

  • Cost positive stock and negative backlog separately.
  • Compare plans with the same demand, starting conditions, and cost conventions.
  • Sensitivity analysis changes one input and follows its effect on the ranking.
  • The cheapest acceptable plan must meet service, workforce, and supply constraints.
  • A transportation model allocates fixed capacities; a general linear program can choose workforce changes.
  • A spreadsheet comparison finds the best tested candidate, not a guaranteed overall optimum.
3

Schedule end items and calculate their parts

A monthly family total leaves several questions unanswered: which products will be ready, when customers can receive them, and which parts production needs. The master production schedule supplies the item quantities and dates. The bill of materials supplies the product structure. Together they turn an aggregate commitment into a plan that can support order promises and component calculations without losing track of existing stock.

3.1 Build the master schedule and promise deliveries

The master production schedule (MPS) names the end items or modules to make, their quantities, and their completion periods. Its totals must agree with the family plan, and key-resource capacity must support it.

Choose what to schedule

Make-to-stock firms schedule finished products. Assemble-to-order firms schedule modules and options, then use a final assembly schedule for each customer's combination. Make-to-order and engineer-to-order firms schedule work against actual orders. The MPS is a supply decision built from demand and constraints; it is not simply a copy of the forecast.

Calculate projected stock

Outside a demand time fence, a common rule uses the larger of forecast and booked orders:

PABt=PABt−1+MPSt−max⁡(forecastt,orderst)

Projected available balance (PAB) is expected ending stock after planned demand. Add a production lot when the balance would otherwise fall below zero or the safety-stock target.

Start with 50 pumps, no safety stock, and a fixed MPS lot of 100. Forecasts are 40 in weeks 1–4 and 60 in weeks 5–8. Orders are 45, 30, 20, 10, 5, 0, 0, and 0.

WeekPlanning demandMPS receiptPAB
14505
24010065
340025
44010085
560025
66010065
76005
86010045

Week 2 would end at −35 without a receipt, so the 100-unit lot raises its balance to 65. Adding forecast and orders would count overlapping demand twice.

Calculate what sales can promise

Available-to-promise (ATP) counts supply not committed to booked orders. It excludes forecast demand. Discrete ATP is calculated initially and in each MPS receipt period, covering orders until just before the next MPS receipt.

Week 1 ATP is 50 − 45 = 5. Week 2 ATP is 100 − (30 + 20) = 50. Week 4 ATP is 100 − (10 + 5) = 85. Weeks 6 and 8 each have 100 uncommitted units.

A new request for 60 pumps by week 3 has only 5 + 50 = 55 units of ATP available by then. Promise 55 by week 3 and five from week 4, or review the production plan. Later supply cannot satisfy an earlier delivery date. If a later ATP bucket is negative, reduce an earlier uncommitted balance to cover it before promising more.

Protect the near schedule

The frozen zone permits exceptional changes with senior approval; the slushy zone permits scheduler-managed trade-offs; the liquid zone is more flexible. Inside the demand time fence, planning usually considers booked orders without the remaining forecast. Inside the planning time fence, the master scheduler controls changes that the system would otherwise make automatically.

These controls address different issues: demand recognition and supply-plan stability. Rough-cut capacity planning checks whether key resources can produce the MPS before it drives the component plan.

Key Takeaways

  • The MPS converts family volume into specific supply quantities and dates.
  • PAB commonly covers the larger of forecast and orders, subject to the demand time fence.
  • ATP subtracts booked orders, not forecast demand.
  • Only ATP available by the requested date supports that delivery promise.
  • Time fences control demand recognition and schedule changes.
  • Check key-resource capacity before relying on the MPS.

3.2 Calculate parts from a bill of materials

A bill of materials (BOM) lists what one parent item requires and the quantity of each component. Demand for those components follows the parent's plan, which lets the planner calculate it instead of forecasting it separately.

Read the structure

Independent demand comes from forecasts, customer orders, or both, without being derived from another item's production requirements. Spare parts sold to customers can have independent demand. Dependent demand comes from a parent plan: 200 chairs needing five casters each create a requirement for 1,000 casters.

A product structure tree puts the end item at level 0, its direct components at level 1, and their components at level 2. One office chair needs:

  • One seat assembly, one base, and four direct-assembly bolts.
  • Each seat assembly needs one cushion, one seat frame, and six bolts.
  • Each base needs five casters and one star frame.
Explode, then net at each level

With no inventory, 200 chairs need 200 seats and bases, 200 cushions and seat frames, 1,000 casters, 200 star frames, and 2,000 bolts. The bolts combine two branches: 800 for final chair assembly and 1,200 for seat assembly.

Now put 50 completed seat assemblies in stock. Only 150 seats need making. Cushion and seat-frame requirements drop to 150 each. Bolts become 800 + 150 × 6 = 1,700. The stocked seats already contain their cushions, frames, and bolts. Exploding all 200 gross seats before subtracting stock would buy parts for work that is already done.

An item's low-level code is the deepest level where it appears anywhere in the structure. Bolts appear at levels 1 and 2, so their code is 2. Processing by that code gathers both branches' requirements before netting bolt stock once.

Choose a useful BOM form
FormPurpose
Single-levelList one parent's direct components
IndentedDisplay all product levels
ModularPlan standard options before final configuration
PlanningSplit family demand using expected percentages
PhantomPass requirements through a subassembly built and used immediately

Four seat colors and three base types give 12 final combinations but seven option modules. A planning BOM might split seat demand 60% black and 40% gray. Those percentages plan expected mix; actual order configuration still determines the final build.

Work backward through lead times

Cumulative lead time is the longest dependent path to the finished product. Chair assembly takes one week, seat assembly two, and cushion purchasing three. That path takes six weeks; parallel branches are not added together.

For shipment at the end of week 8, chair assembly occupies week 8, seat assembly weeks 6–7, and cushion procurement weeks 3–5. Release the cushion order at the start of week 3 for availability at the start of week 6. Labeling period starts and ends avoids an extra week's error.

Engineering changes must update quantities and versions, while inventory and lead-time records must reflect reality. The same structure applies to a meal recipe or a surgical kit: a planned service creates requirements for its ingredients or supplies.

Key Takeaways

  • Dependent demand is calculated from parent plans; independent demand has its own demand source.
  • Net intermediate stock before exploding the work still required.
  • Add requirements from every branch before netting a shared component.
  • Low-level codes delay processing until all parent requirements are known.
  • Cumulative lead time follows the longest dependent path.
  • BOM forms support different planning tasks, including options and immediate-use subassemblies.
4

Plan materials and choose order sizes

Component demand arrives in bursts because it follows the work scheduled for parent products. Material requirements planning turns those bursts into dated order proposals. Work through the inventory arithmetic first, then examine how order sizes change setup and holding costs. The final step is keeping the plan useful as orders, deliveries, and inventory records change, including when the same logic is used in distribution or services.

4.1 Turn requirements into dated orders

Material requirements planning (MRP) combines the MPS, BOM, inventory, open orders, and lead times. For each item it calculates quantities and dates, then proposes orders and messages for planners to act on.

Read the six rows
RowMeaning
Gross requirementsTotal demand in the period
Scheduled receiptsOrders already released and due to arrive
Projected on handExpected inventory after the period's activity
Net requirementsShortfall after stock, receipts, and safety stock
Planned order receiptsSuggested future arrivals
Planned order releasesSuggested starts or placements, offset by lead time

Scheduled receipts are existing commitments. Planned receipts remain proposals until released. Counting both as if they were separate deliveries would overstate supply.

Net one period at a time

Available supply before a new planned receipt equals previous projected stock plus scheduled receipts. Then calculate:

net requirement=max⁡(0,gross requirement+safety stock−available)

Apply the lot-sizing rule to obtain the planned receipt. Ending projected stock equals available plus that receipt minus gross requirements. Move the receipt backward by the lead time to place its planned release.

Safety stock belongs inside the maximum. If available stock already covers demand and the safety target, there is no net requirement. Adding the safety target after reducing a negative shortage to zero would create an unnecessary order.

Complete a chair-base record

Start with 40 bases, a scheduled receipt of 60 in week 2, one-week lead time, lot-for-lot ordering, and no safety stock. All receipts are available at the start of their week.

WeekGross requirementsScheduled receiptsNet requirementsPlanned receiptsEnding stock
13000010
250600020
3000020
480060600
520020200
670070700

Week 2 has 10 carried forward plus 60 arriving: after 50 are used, 20 remain. Week 4 needs 80 but has only 20, so its planned receipt is 60. Release that order in week 3. Releases for the following receipts are 20 in week 4 and 70 in week 5.

Pass the right dates to components

Each base requires five casters. The base releases create caster gross requirements of 300 in week 3, 100 in week 4, and 350 in week 5. Use parent releases: casters must be available when base work starts, not when the completed bases arrive.

MRP repeats this logic down the structure in low-level-code order. With base safety stock of 10, week 4's requirement becomes 80 + 10 − 20 = 70. Safety lead time offers a different buffer by planning an earlier arrival. If a release date falls in the past, normal lead time is no longer achievable; the planner must expedite, change supply, or revise the parent schedule.

Key Takeaways

  • Available supply includes previous projected stock and scheduled receipts.
  • Net requirements include the safety target before applying the zero floor.
  • Lot sizing sets receipt quantities; lead-time offsetting sets release dates.
  • Parent planned releases generate component gross requirements.
  • A past-due planned release needs action, not silent acceptance.

4.2 Compare order sizes and their costs

Lot sizing trades the cost of starting another order against the cost of carrying units early. Compare rules on the same dated requirements; a low purchase quantity alone does not measure the planning cost.

Keep the cost basis fixed

Weekly requirements are 50, 0, 60, 70, 0, 40, 80, and 20 units. Setup costs $90 per order; holding costs $0.50 per unit per week on ending inventory. There is no starting stock, and receipts arrive at the start of a week.

Lot-for-lot (L4L) orders exactly each nonzero requirement: six orders and no carried inventory. Cost is 6 × $90 = $540. It fits expensive-to-hold items or inexpensive setups.

Apply EOQ and POQ

Economic order quantity (EOQ) gives a fixed quantity using average demand:

Q∗=2DSH

Average weekly demand is 40, so annual demand is 2,080. Annual holding is $26 per unit. With setup cost $90, EOQ is 120 units. Use the same time basis for demand and holding.

Ordering 120 in weeks 1, 4, and 7 gives ending stocks of 70, 70, 10, 60, 60, 20, 60, and 40. Their sum is 390 unit-weeks. Cost is $270 setup + $195 holding = $465, with 40 units left after week 8. Fixed lots can leave units waiting through gaps in requirements.

Period order quantity (POQ) uses EOQ to choose a time interval: 120 ÷ 40 = three weeks. Each order covers the actual requirements of its interval. Order 110 in week 1 for weeks 1–3, 110 in week 4 for weeks 4–6, and 100 in week 7 for weeks 7–8. Ending stocks total 220 unit-weeks, so cost is $270 + $110 = $380, with no ending remnant.

Balance part-periods

A part-period is one unit held for one period. Part period balancing (PPB) groups future requirements to bring carrying cost close to one setup cost. The economic part period is 90 ÷ 0.50 = 180 unit-weeks.

From week 1, including week 3 creates 60 × 2 = 120 part-periods. Adding week 4 would create another 70 × 3 = 210, making 330 in total. The 120 total is closer to 180 than 330, so stop at week 3. Continue from the next uncovered requirement. Here PPB matches POQ at $380; another pattern can give different results.

Recognize the minimum for the model

Wagner–Whitin uses dynamic programming to compare ordering intervals over a finite horizon. For these requirements it orders 50 in week 1, 130 in week 3, and 140 in week 6. Setup costs $270. Holding is 190 unit-weeks, costing $95, for a minimum of $365.

It is optimal for the stated single-item model with known requirements and no capacity limit. It can tie a simpler rule, and its plan can change substantially when requirements change. Real systems also apply minimum quantities, maximum quantities, and pack multiples. Large parent lots create lumpy component requirements, so lot-for-lot is often useful lower in the BOM.

Key Takeaways

  • Compare setup plus holding cost using the same requirements and horizon.
  • EOQ fixes quantity; POQ fixes a coverage interval and varies quantity.
  • PPB chooses coverage by comparing part-periods with setup cost divided by holding cost.
  • Wagner–Whitin finds a minimum under its single-item finite-horizon model.
  • Order modifiers can change the quantity proposed by a lot-sizing rule.
  • Large parent lots can amplify lumpiness in component demand.

4.3 Keep the material plan useful as things change

An MRP run is a calculation based on records. Accurate records, controlled replanning, and prompt action on exceptions turn that calculation into a useful operating plan.

Maintain the inputs

Inventory errors change net requirements. A wrong BOM quantity multiplies the error across every parent order. An unrealistic lead time can produce a date that looks valid but cannot be met. Open-order records must also show quantities, dates, and actual status.

Cycle counting checks selected items throughout the year and investigates differences. Firms often target inventory accuracy of 95% or higher. Counting alone is not enough: the cause may be a missed receipt, an unrecorded issue, scrap, or the wrong item code. Correct the transaction process as well as the stock number.

Replan and trace changes

Regenerative MRP recalculates the whole plan at intervals. Net-change MRP recalculates affected items when something changes, such as a late delivery or a revised customer order. More frequent calculation gives quicker information, but planners still need to decide which changes deserve action.

Pegging traces a component requirement back to the parent orders that created it. A shortage of 350 casters in week 5 can be traced to 70 base starts, then to chairs and the customer orders they support. That trace helps prioritize the shortage by its consequences.

An action notice asks the planner to release, expedite, postpone, or cancel an order. Expedite brings supply earlier; de-expedite moves it later. A proposed date change is not the same as a confirmed supplier commitment.

Control nervousness

System nervousness occurs when small changes in higher-level plans trigger large, frequent changes below. Changing a parent lot can shift both the quantity and date of several component orders. Suppliers and production teams can spend more time chasing changes than completing stable work.

Time fences and firm planned orders protect selected quantities and dates from automatic revision. Ignoring immaterial changes and choosing less sensitive lot rules can also help. Firming an order does not make a shortage disappear: it leaves a protected decision that a planner must review when conditions change.

Check the resources separately

Standard MRP assumes unlimited capacity and fixed lead times. It may propose more work than a center can perform. Capacity planning checks that resource requirement, while shop-floor kanban signals can control actual replenishment. These tools can work together: MRP plans material timing, capacity planning tests resources, and pull signals manage local execution.

Some systems plan with exact dates instead of weekly buckets. This bucketless detail changes the time representation; it does not remove the need for accurate lead times or feasible capacity.

Extend the logic

A caterer calculates ingredient needs from meals and recipes. A hospital calculates supplies from scheduled procedures and standard kits. Distribution requirements planning (DRP) applies time-phased netting through a warehouse network. Regional warehouses calculate replenishment orders, and those requirements flow to the central warehouse or plant. Combine all downstream requirements before netting central stock, just as shared-component requirements are combined in a BOM.

Key Takeaways

  • Accurate stock, BOM, lead-time, and open-order data are essential to reliable MRP.
  • Regeneration recalculates everything; net change recalculates affected items.
  • Pegging connects a shortage with the orders it threatens.
  • Action notices need planner action and confirmation where appropriate.
  • Firm orders and time fences reduce nervousness without removing genuine shortages.
  • MRP, capacity checks, and kanban serve complementary planning and execution roles.
  • DRP passes downstream replenishment needs upstream through a distribution network.
5

Check resources and connect the business

A materials plan can be arithmetically correct and still ask a work center to do too much. Capacity checks compare the plan with the hours people and equipment can supply, then feed changes back into planning. Follow those checks from the master schedule to detailed orders, and see how closed-loop MRP, MRP II, and ERP connect operational information with purchasing, sales, staffing, and finance.

5.1 Compare work-center load with capacity

A capacity check asks whether the resources can perform the planned work in time. Keep the level of detail appropriate: key resources for the master schedule, then individual work centers for the material plan.

Match the check to the plan

Resource requirements planning checks aggregate plans against major resources. Rough-cut capacity planning (RCCP) checks the MPS at bottlenecks or other key resources. A bill of resources gives the standard hours required per end item. If 200 chairs need 0.4 standard hours each, assembly load is 80 standard hours. Against 70 available, the MPS needs a 10-hour remedy before it can be relied on.

Capacity requirements planning (CRP) checks detailed MRP orders using their routings: the centers visited, setup time, and run time per unit. Include work from planned orders and existing released orders, placed in the periods when that work is due.

Use comparable hours
rated capacity=available clock hours×utilization×efficiency

Utilization is the share of available time spent working on production. Efficiency compares standard hours earned with actual worked hours. Two welders, eight hours a day for five days, provide 80 labor-hours. At 90% utilization, 72 are worked. At 95% efficiency, rated output is 68.4 standard hours. Compare that with loads stated in standard hours, not directly with clock hours.

For one order:

load=setup time+run time per unit×quantity

Setup is charged once per batch visiting the center. Run time rises with quantity.

Read a load report

Base orders of 60, 20, and 70 units are released in weeks 3, 4, and 5. Each batch needs 1.5 standard setup hours plus 0.6 standard hours per unit. Other items contribute 30, 25, and 40 standard hours.

WeekBase loadOther loadTotalPercent of 68.4
337.53067.598.7%
413.52538.556.3%
543.54083.5122.1%

Week 5 is 15.1 standard hours over capacity; week 4 has 29.9 spare. Average load across the weeks would hide the overload.

Change capacity or move work

Overtime, another shift, an alternate center, or subcontracting can add capacity. Releasing earlier, splitting lots, changing lot sizes, or revising the MPS can move or reduce load.

Split the week-5 base batch into 30 extra bases in week 4 and 40 in week 5. Week 4 now has its original 20-base batch plus a separate 30-base batch: 13.5 + 19.5 + 25 = 58.0 standard hours. Week 5 needs 1.5 + 0.6 × 40 + 40 = 65.5. Both fit, at the cost of one extra setup and a week of holding 30 bases.

A load profile displays these period loads against capacity. CRP reports overloads using infinite loading; it does not automatically resolve them or sequence jobs. Feedback must lead to a revised, checked plan.

Key Takeaways

  • RCCP checks key MPS resources; CRP checks detailed MRP work-center loads.
  • Convert available clock hours to standard-hour capacity using utilization and efficiency.
  • Order load includes a setup plus run time for every unit.
  • Check each period, since spare hours later do not resolve an earlier overload.
  • Splitting or moving work can add setups and inventory costs.
  • CRP identifies overloads; planners must choose and check remedies.

5.2 Connect planning through MRP II and ERP

Planning systems widened as companies needed to connect material calculations with resources, money, and execution. The distinction between the systems is the scope of the decisions and information they connect.

Follow the widening scope
SystemMain addition
MRPCalculate material quantities and dates
Closed-loop MRPAdd capacity checks and feedback from execution
MRP IIIntegrate manufacturing resources, finance, S&OP, and what-if planning
ERPConnect processes across the enterprise

MRP developed in the 1960s and spread widely in the 1970s. The term ERP came into use around 1990. MRP II means manufacturing resource planning; it connects labor and other manufacturing resources with financial consequences. In a closed loop, actual receipts, output, and capacity performance feed back so the plan can be corrected.

Follow one transaction

An enterprise resource planning (ERP) suite links modules through a shared database. Core areas include sales and order management, purchasing, inventory, manufacturing planning, distribution, finance, and human resources.

A customer orders 50 chairs. Order entry checks ATP and confirms the date. Inventory is reserved; planning updates requirements; purchasing acts on proposed supply orders. Production releases work, the warehouse records shipment, and accounting issues the invoice and updates receivables and the general ledger. The same order identity and quantities remain visible through the process.

This integration reduces separate re-entry. A receipt entered by the warehouse can update purchasing's open quantity and inventory's stock position, giving finance the same transaction basis. A common database reduces conflicting records, but an incorrect entry can still spread incorrect information.

Weigh benefits and drawbacks

Shared data improves order and inventory visibility, reduces re-keying errors, supports consistent processes, and can speed financial closing. It gives S&OP more timely information about actual demand, supply, and costs.

The drawbacks include high cost, long and risky projects, process changes required by standard software, difficult upgrades after extensive customization, and continued dependence on data quality. Integration cannot compensate for unrecorded scrap or an unrealistic supplier lead time.

ERP also supports service organizations. A university can connect purchasing, supplies, staffing, and finance. A hospital can link scheduling information with staffing and supply needs. Manufacturing modules are relevant only where the organization's processes need them.

Distinguish software from decisions

An on-premises system runs on company-managed servers. Cloud ERP delivered as software-as-a-service (SaaS) is subscription software operated and updated by the vendor. ERP may also connect with customer relationship management, supply chain management, and e-commerce systems.

ERP contains MRP as one planning function; its enterprise scope is broader. It calculates and shares information, while people agree on the S&OP plan, set commitments, review the master schedule, and act on exceptions. A proposed purchase order becomes an actual commitment through the organization's release process.

Key Takeaways

  • Closed-loop MRP adds capacity and execution feedback to materials planning.
  • MRP II connects manufacturing resources and their financial consequences.
  • ERP links enterprise processes through shared data.
  • Integration reduces duplicate entry but still depends on accurate transactions.
  • People retain planning choices and responsibility for acting on exceptions.

Aggregate Planning examples

5 Walkthroughs

1

Agree on one demand and supply plan

11 steps
Connect planning horizons, family volumes, and the monthly S&OP decisions that align operations with finance.
  1. 1
    IntroductionStart with a decision that needs several teams

    Sales expects a peak in four months. Operations can meet it with overtime or an earlier inventory build, while finance wants less cash tied up in stock. Each team sees part of the decision.

    Follow how the planning hierarchy places that choice, then use S&OP to turn the competing views into a common operating plan.

  2. 2
    ExplanationPlace the decision on the right horizon

    Long-range planning chooses basic capacity, such as facilities and major equipment, usually more than a year ahead. Intermediate planning, often 3–18 months, chooses how to use that capacity. Short-range planning assigns specific jobs and people in the coming weeks and days.

    A four-month choice between overtime and stored output belongs to aggregate planning. Building a new plant belongs to a longer-range decision.

  3. 3
    ExampleUse a family total before choosing each model

    A maker plans 1,200 road bikes in March. The family shares assembly resources, so its combined volume helps estimate the workforce and hours required.

    The MPS later splits that total into 300 small, 500 medium, and 400 large bikes by week. Those quantities reconcile to 1,200. MRP then calculates their parts, and short-term schedules assign the jobs.

  4. 4
    ChallengeSort out an overloaded planning meeting

    A monthly meeting spends most of its time deciding which customer order will run first on a machine tomorrow. Its family demand and staffing gaps remain unresolved. What planning levels have become confused?

    ---reveal---

    Tomorrow’s job assignment is short-range scheduling. The S&OP meeting needs to resolve family volume, supply, and financial trade-offs, leaving detailed job sequencing to the appropriate scheduling process.

  5. 5
    ExplanationBuild the monthly decision sequence

    Start with updated actual sales, production, inventory, and forecasts. Demand review adds market knowledge; supply review checks resources and develops responses. Reconciliation compares those responses with the financial plan.

    The executive meeting chooses among unresolved trade-offs and approves one plan. Meeting names vary, but the work must end in decisions with owners, not only a refreshed report.

  6. 6
    ExampleRead a make-to-stock gap

    A family starts with 500 units, plans to make 1,100, and expects sales of 1,250. Projected ending inventory is 500 + 1,100 − 1,250 = 350 units.

    The target is 400, leaving a 50-unit gap. Supply review can test 50 more units of production; reconciliation can compare that response with accepting lower stock. The target is not extra customer demand.

  7. 7
    ConnectionTrack waiting orders in make-to-order

    A make-to-order operation tracks backlog: beginning orders waiting + new orders − shipments. Beginning backlog of 180, new orders of 900, and shipments of 950 leave 130 units waiting.

    A growing backlog can extend delivery times. A sustained decline can leave future capacity idle. Reading backlog alongside available capacity helps the team see both customer delay and the approaching workload.

  8. 8
    ExampleTranslate sales into a financial gap

    A plan to sell 1,200 units at an average price of $250 produces $300,000 revenue. The budget expects $330,000, so the gap is $30,000.

    Producing more stock does not itself create revenue. The team needs additional sales that supply can support, another commercial response, or a revised financial forecast. This is why finance participates before the plan is approved.

  9. 9
    ChallengeConnect the stock target with the revenue target

    A family expects sales of 1,000 units at $90, against a $99,000 revenue target. Supply can make 1,100 units, but demand review still supports only 1,000 sales. Does producing all 1,100 close the revenue gap?

    ---reveal---

    No. Sales still produce $90,000 revenue, leaving $9,000 short. The extra 100 units increase inventory. Reconciliation must address the demand or financial gap as well as the feasible output volume.

  10. 10
    TipKeep the horizon useful

    Roll the plan forward each month: replace the completed period with actuals, update future assumptions, and add a new far period. Review forecast accuracy, plan attainment, stock or backlog, and delivery performance.

    Keep forecasts distinct from targets. If actual output is 1,140 against 1,200 planned, attainment is 95%; the next question is what caused the gap and which future decisions need to change.

  11. 11
    RecapCarry the agreed volume into detailed planning

    The family plan now has a demand view, a supply response, and a financial interpretation. Leaders can approve a common volume plan, while planners turn it into products and dates.

    That handoff works when the MPS reconciles with family totals and returns material or capacity constraints for review before they become delivery failures.

2

Build chase, level, and mixed plans

20 steps
Work through a pump plant’s staffing and inventory balances, compare costs, and test the choice against a changed holding rate.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionFollow one demand peak through several plans
  2. 2
    ExplanationChoose where flexibility will come from
  3. 3
    ExplanationDistinguish the three strategies
  4. 4
    ExampleUse booking times as a demand lever
  5. 5
    ChallengeChoose a response for nonstorable output
  6. 6
    ExampleOrganize the pump data
  7. 7
    ExampleFind the chase workforce
  8. 8
    ExampleAdd paid labor and workforce-change costs
  9. 9
    ChallengeNotice the first workforce change
  10. 10
    ExplanationFind a level rate that meets the ending target
  11. 11
    ExampleCarry level inventory through the peak
  12. 12
    ExampleCost the level plan
  13. 13
    ChallengeCheck the early months as well as the total
  14. 14
    ExampleTest a smaller core team
  15. 15
    ExampleBuild a mixed workforce plan
  16. 16
    ExamplePrice the mixed plan
  17. 17
    ChallengeDecide whether the cheapest plan is usable
  18. 18
    ExampleChange the holding rate
  19. 19
    ConnectionKnow what the comparison proves
  20. 20
    RecapCarry a defensible plan into S&OP
3

Turn family volume into products and parts

14 steps
Build a master schedule, calculate customer promise quantities, and explode a product structure after allowing for inventory.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionAdd the detail customers and production need
  2. 2
    ExplanationSchedule the right item for the business
  3. 3
    ExampleBuild the first projected balances
  4. 4
    ExampleContinue the schedule through higher demand
  5. 5
    ExplanationCalculate uncommitted supply
  6. 6
    ChallengeMake a promise that respects the date
  7. 7
    TipProtect the schedule without confusing the fences
  8. 8
    ExplanationRead one chair’s structure
  9. 9
    ExampleAllow for completed assemblies before multiplying
  10. 10
    Key InsightGather shared-part demand before netting
  11. 11
    ChallengeNet a different product structure
  12. 12
    ExampleWork backward along the longest path
  13. 13
    ChallengeConnect the promise with the product lead time
  14. 14
    RecapPass a dated and netted plan to MRP
4

Calculate MRP orders and compare lot rules

19 steps
Net stock and receipts, offset lead times, compare setup and holding costs, and respond when the material plan changes.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionSeparate the shortage from the proposed order
  2. 2
    ExplanationRead the record in order
  3. 3
    ExampleCarry stock through weeks with existing supply
  4. 4
    ExamplePlan the receipts and move their releases back
  5. 5
    ChallengeMake the safety-stock target part of netting
  6. 6
    ConnectionCreate component demand at the production start
  7. 7
    ExplanationChoose what an order should cover
  8. 8
    ExampleCalculate a fixed EOQ
  9. 9
    ExampleUse the EOQ to choose an interval
  10. 10
    ExampleBalance carrying exposure against one setup
  11. 11
    ChallengeCount every period a unit waits
  12. 12
    Key InsightRecognize the optimal model and its limits
  13. 13
    ExplanationMaintain the facts behind the calculation
  14. 14
    ExampleUse pegging to prioritize a shortage
  15. 15
    TipStabilize what needs to stay committed
  16. 16
    ChallengeRespond to an early requirement
  17. 17
    ConnectionCarry time-phased logic beyond the factory
  18. 18
    ChallengeFollow a parent change all the way down
  19. 19
    RecapTake a checked proposal to execution
5

Check the hours and connect the systems

13 steps
Calculate capacity and work-center loads, revise an overload, and connect planning feedback with enterprise data.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionTest whether the plan can actually be done
  2. 2
    ExplanationChoose the capacity check for the plan
  3. 3
    ExampleConvert available time into rated output
  4. 4
    ExampleAdd batch setup and run time
  5. 5
    ExampleMove work and include the extra setup
  6. 6
    ChallengeTest a proposed capacity remedy
  7. 7
    Key InsightTreat the load report as a signal to act
  8. 8
    ExplanationFollow the expanding scope of planning systems
  9. 9
    ExampleFollow an order through shared records
  10. 10
    ChallengeFind the limit of integration
  11. 11
    ConnectionApply enterprise integration in services
  12. 12
    ChallengeConnect a shop-floor delay with the business promise
  13. 13
    RecapClose the loop with a revised commitment

Aggregate Planning practice questions

40 Practice Questions in 4 sets

Set 1: Practice 1: Read the plan and calculate the next step10 Practice Questions

Question 1 of 10

An MRP item has gross requirements of 95, safety stock of 15, prior projected stock of 40, and a scheduled receipt of 30. What is its net requirement?
  1. 25 units
  2. 55 units
  3. 40 units
  4. 110 units
Show answerHide answer
Answer: C
Available supply is 40 + 30 = 70 units. Keeping 15 after meeting demand requires 95 + 15 − 70 = 40 new units. A 25-unit receipt would cover demand but leave zero stock, missing the safety-stock target.

Question 2 of 10

A manufacturer decides its monthly family output, staffing, and inventory for the next nine months. What planning level is it using?
  1. Long-range capacity planning
  2. Intermediate aggregate planning
  3. Daily production scheduling
  4. Item-level master scheduling
Show answerHide answer
Answer: B
Aggregate planning sets family output and resource use over the intermediate horizon. A nine-month staffing and inventory plan fits that purpose. Master scheduling would add specific end items and dates; the scenario still concerns family totals.

Question 3 of 10

A make-to-order family begins a month with a backlog of 160 units, receives 740 units of new orders, and ships 690. What is its ending backlog?
  1. 110 units
  2. 50 units
  3. 900 units
  4. 210 units
Show answerHide answer
Answer: D
Ending backlog is beginning backlog plus new orders minus shipments: 160 + 740 − 690 = 210 units. The backlog grows by 50, but that increase is not the ending total. The original 160 units waiting must also remain in the balance until shipped.

Question 4 of 10

A firm combines irrigation equipment with winter heating equipment because they use the same resources and sell most strongly in different seasons. What demand option is it using?
  1. Counterseasonal product mixing
  2. Backordering peak demand
  3. Temporary workforce expansion
  4. Subcontracting peak production
Show answerHide answer
Answer: A
Counterseasonal mixing combines products whose demand peaks occur at different times, spreading demand for shared resources. Temporary staff change supply capacity instead. Nothing in this scenario changes staffing or transfers production to another firm.

Question 5 of 10

A plant starts with 18 workers. Next month it must make 600 units, and each worker can make 30 units. Hiring costs $700 per worker. What hiring cost does a chase plan incur for that month?
  1. $1,260
  2. $14,000
  3. $1,400
  4. $12,600
Show answerHide answer
Answer: C
The plan needs 600 ÷ 30 = 20 workers, two more than the starting 18. Hiring those two costs 2 × $700 = $1,400. Charging for all 20 workers would confuse the required workforce with the number newly hired.

Question 6 of 10

A four-month plan has demand totaling 4,500 units, beginning inventory of 300, and target ending inventory of 200. What constant monthly output meets the target?
  1. 1,100 units
  2. 1,175 units
  3. 1,125 units
  4. 1,250 units
Show answerHide answer
Answer: A
Total required production is 4,500 + 200 − 300 = 4,400 units, or 1,100 per month. Beginning inventory supplies part of demand, so subtract it. Adding the beginning stock would overstate production and leave excess inventory at the end.

Question 7 of 10

An item has 35 units of prior projected stock, a forecast of 50, booked orders of 65, and an MPS receipt of 80 for the week. The week is outside the demand time fence. What is its ending PAB?
  1. 65 units
  2. 0 units
  3. 15 units
  4. 50 units
Show answerHide answer
Answer: D
Planning demand is the larger of forecast and booked orders, which is 65. PAB is 35 + 80 − 65 = 50 units. Subtracting both demand figures would give zero, but would count overlapping forecast and orders twice under this rule.

Question 8 of 10

A table needs two leg assemblies. Each leg assembly needs three brackets. An order calls for 90 tables, and 30 complete leg assemblies are already available. With no other stock, how many brackets are needed for the remaining assembly work?
  1. 540 brackets
  2. 450 brackets
  3. 510 brackets
  4. 180 brackets
Show answerHide answer
Answer: B
The tables need 90 × 2 = 180 leg assemblies, but only 150 must be made after using the 30 in stock. Those 150 need 450 brackets. Exploding all 180 assemblies would give 540 and buy brackets already contained in the stocked assemblies.

Question 9 of 10

A component has requirements of 30, 50, and 20 units in weeks 1–3. Setup costs $60; holding costs $1 per unit per week on ending inventory. No stock is available, and receipts arrive at the start of a week. What is the lowest-cost way to group these requirements into orders?
  1. One order for all three weeks
  2. An order for weeks 1–2, then week 3
  3. An order in every required week
  4. An order for week 1, then weeks 2–3
Show answerHide answer
Answer: D
Ordering 30 in week 1 and 70 in week 2 costs $120 in setups and $20 to carry week-3 demand, totaling $140. Covering weeks 1–2 together costs $170; one order for all three costs $150. Comparing every grouping makes the $140 plan the minimum.

Question 10 of 10

In a closed-loop planning system, a supplier reports a delayed delivery. What makes the response a closed loop?
  1. The original release date stays fixed
  2. A larger BOM quantity replaces the delay
  3. The delay feeds back into revised plans
  4. Finance records the original forecast
Show answerHide answer
Answer: C
A closed loop brings execution information back into planning so quantities, dates, or resources can be revised. The supplier delay is new supply information that needs evaluation. Keeping the original release date without checking its consequences would leave the feedback unused.
Set 2: Practice 2: Trace quantities, costs, and commitments10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A plant retains 16 workers at $2,400 per month. Each can make 25 units, but only 360 units are produced. What regular labor cost belongs in the plan for that month?
  1. $34,560
  2. $3,840
  3. $38,400
  4. $40,000
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A call center forecasts 12,000 calls next month, averaging four minutes of direct handling per call. How much direct call-handling work should its aggregate plan allow?
  1. 800 agent-hours
  2. 3,000 agent-hours
  3. 200 agent-hours
  4. 12,000 agent-hours
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Two feasible plans have equal labor and hiring costs. Plan L carries 500 unit-months of inventory and no backlog. Plan M carries 200 unit-months and 40 unit-months of backlog. Holding costs $3 and backlog costs $18 per unit-month. At what holding rate would their total costs be equal?
  1. $1.44 per unit-month
  2. $3.60 per unit-month
  3. $2.00 per unit-month
  4. $2.40 per unit-month
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

An MPS receipt of 150 units is due in week 4. Booked orders are 50 in week 4 and 35 in week 5; the next MPS receipt is in week 6. Forecast is 70 in each of weeks 4 and 5. What is the discrete ATP for the week-4 receipt?
  1. 10 units
  2. 65 units
  3. 100 units
  4. 80 units
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A purchased fastener appears directly under one end item at level 1 and under a subassembly at level 3. What low-level code does it receive?
  1. Code 3
  2. Code 1
  3. Code 2
  4. Code 4
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A housing has gross requirements of 60 in week 3 and 70 in week 4, with no earlier demand. It starts with 20 on hand and has a scheduled receipt of 30 in week 3. Safety stock is 10, lot sizing is lot-for-lot, and lead time is two weeks. Each housing needs two seals at its production start. With no other parents, what seal gross requirements follow from the planned housing orders?
  1. 120 in week 3 and 140 in week 4
  2. 40 in week 3 and 140 in week 4
  3. 40 in week 1 and 140 in week 2
  4. 20 in week 1 and 140 in week 2
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A customer order falls by five units, but the next MRP run shifts many component orders by large quantities and several weeks. What planning problem should be investigated?
  1. Inventory inaccuracy
  2. No demand time fence
  3. Network imbalance
  4. System nervousness
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A center has 120 available clock hours, 80% utilization, and 110% efficiency measured as standard hours earned per worked hour. What is its rated capacity?
  1. 96 standard hours
  2. 105.6 standard hours
  3. 132 standard hours
  4. 87.3 standard hours
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A university wants one transaction record to support purchasing, supplies, human resources, and finance. What type of system has that enterprise-wide scope?
  1. A material requirements plan
  2. A master production schedule
  3. An enterprise resource planning suite
  4. A capacity requirements report
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

An item has 90 units available before a planned receipt, gross requirements of 50, and safety stock of 20. What net requirement should MRP report?
  1. 0 units
  2. 20 units
  3. 40 units
  4. 70 units
Show answerHide answer

Save this lesson to see this answer.

Set 3: Practice 3: Diagnose the constraint and revise the plan10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

S&OP projects sales of 2,400 units at an average price of $75, with enough supply for at most 2,500 units. The revenue target is $195,000. A manager proposes closing the gap entirely through extra unit sales at the same price. How much of the revenue gap remains even if all available supply sells?
  1. $7,500
  2. $15,000
  3. $5,000
  4. $0
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A hotel discounts every remaining room for tonight, even though it expects some later bookings at full price. What revenue-management trade-off needs evaluation?
  1. Whether stock can move into tomorrow
  2. Whether labor should track each booking
  3. Whether setup cost exceeds holding cost
  4. Whether early discounts displace higher-price bookings
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A three-month plan has demand of 500, 900, and 700 units, beginning stock of 150, and a target ending stock of 150. A constant output rate meets the final target. What is its lowest projected inventory balance, and does the plan require backorders?
  1. −50 units; backorders are required
  2. 0 units; backorders are avoided
  3. 150 units; backorders are avoided
  4. 350 units; backorders are avoided
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A transportation model allocates regular-time, overtime, and subcontract output among future demand periods. Its source capacities have already been fixed. What decision needs a broader model if it must also be optimized?
  1. How much early output to hold
  2. How many workers to hire each month
  3. Which demand receives subcontract output
  4. Which period uses regular-time supply
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Discrete ATP is 12 initially, 48 for a receipt in week 3, and 90 for a receipt in week 5. The figures already cover all booked orders, and no additional orders have been accepted. A new customer requests 75 units by week 4. Without changing production, what delivery split is supported?
  1. 48 by week 4 and 27 in week 5
  2. 75 by week 4 and none afterward
  3. 12 by week 4 and 63 in week 5
  4. 60 by week 4 and 15 in week 5
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A lot-sizing comparison uses requirements of 40, 0, 30, and 50 in weeks 1–4, setup $80, and holding $1 per unit per week on ending inventory. No stock is available. A fixed-quantity plan receives 60 in weeks 1 and 3. A three-week POQ plan receives 70 in week 1 and 50 in week 4. How do their setup-plus-holding costs compare?
  1. POQ costs $30 less
  2. POQ costs $10 less
  3. POQ costs $30 more
  4. Both plans cost the same
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Part period balancing starts with a week-1 requirement of 40 units. Later requirements are 30 in week 2 and 50 in week 3. Setup costs $100 and holding costs $1 per unit per week. Using the closest-part-period rule, how much should the first order cover?
  1. 40 units through week 1
  2. 70 units through week 2
  3. 120 units through week 3
  4. 100 units through part of week 3
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A regional warehouse plans a replenishment order of 140 units for dispatch from the central warehouse in week 6. How should DRP represent that upstream?
  1. As a central receipt in week 6
  2. As central gross requirements in week 6
  3. As central safety stock in week 6
  4. As a regional sale in week 6
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A center has 60 standard hours of weekly capacity. Week 2 contains 24 hours of other work and a 100-unit batch; week 1 has 30 hours of other work. Each batch needs two setup hours plus 0.4 hours per unit. Moving units to week 1 creates a separate batch. What is the smallest transfer that makes both weeks feasible?
  1. 10 units
  2. 20 units
  3. 25 units
  4. 15 units
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A company buys cloud ERP as a subscription service operated and updated by the vendor. What delivery model is this?
  1. Closed-loop planning
  2. On-premises software
  3. Software-as-a-service
  4. Standalone MRP system
Show answerHide answer

Save this lesson to see this answer.

Set 4: Practice 4: Test decisions across the planning chain10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A monthly family plan of 900 units becomes weekly plans for 250 compact, 400 standard, and 250 large units. What planning activity does this illustrate?
  1. Capacity requirements planning
  2. Disaggregation of the family plan
  3. Netting of component inventory
  4. Regeneration of material orders
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A make-to-stock family starts with 260 units, plans production of 1,100, and expects sales of 1,240. The inventory target is 200. Demand review confirms sales; supply review finds room for 60 additional units, with no other supply changes available. What minimum shortfall against the inventory target remains?
  1. 20 units
  2. 60 units
  3. 80 units
  4. 0 units
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A repair service has sharply varying weekly demand, cannot store unused service time, and can train temporary staff quickly. What staffing approach best matches those conditions?
  1. A fixed output rate with finished-service stock
  2. A smaller core team with permanent backlogs
  3. A chase approach using flexible staffing
  4. A level approach building service inventory
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A plant starts with 40 units and 13 workers. Monthly demand is 1,000; each worker makes three units per day over 22 days. Workers must be whole people and fully productive. Pay is $2,400 per worker, hiring $700 per worker, and holding $3 per ending unit. No other supply is used. What is the minimum labor-plus-hiring-plus-holding cost that meets demand?
  1. $37,400
  2. $38,190
  3. $36,090
  4. $37,490
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A two-month plan starts with 50 units and must end with none. Demand is 700 then 400, and backorders are prohibited. Month-1 regular output is fixed at 525; month-2 regular output is currently 525 and can be reduced. Subcontracting is available in month 1. What smallest change meets these conditions?
  1. Subcontract 125, then cut month-2 output by 125
  2. Subcontract 175, then keep month-2 output at 525
  3. Subcontract 125, then keep month-2 output at 525
  4. Subcontract 175, then cut month-2 output by 175
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Plan A costs $48,000 including 600 unit-months of holding at $5 each. Plan B costs $47,400 including 200 unit-months at that rate. All other costs stay fixed, and both are feasible. What happens if holding falls to $3?
  1. B remains cheaper by $600
  2. A becomes cheaper by $800
  3. B becomes cheaper by $200
  4. A becomes cheaper by $200
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A kit needs two modules and three direct-use clips. Each module needs four clips. There are orders for 80 kits, 30 complete modules in stock, and 100 loose clips available. No kits or other receipts are available. How many additional clips are required?
  1. 780 clips
  2. 660 clips
  3. 540 clips
  4. 420 clips
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A component has a net requirement of 68 units. Its supplier accepts orders only in multiples of 25, with no other restriction. What is the smallest permitted planned receipt that covers the requirement?
  1. 50 units
  2. 68 units
  3. 75 units
  4. 100 units
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A component has 70 units on record but only 25 physically available. MRP shows no shortage for a 60-unit requirement due before any receipt. The related planned order is firm. What immediate planning response addresses the actual problem?
  1. Correct stock and arrange coverage for 35 missing units
  2. Keep the firm plan because the recorded stock covers demand
  3. Raise the forecast by 45 units and regenerate every item
  4. Delay counting until the firm order becomes changeable
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A center has 80 available clock hours, 85% utilization, and 100% efficiency. This week has 20 standard hours of other work and a 100-unit batch needing three setup hours plus 0.5 standard hours per unit. The prior week has seven standard hours spare. A split batch needs its own three-hour setup. If the fewest units needed to remove this week’s overload move earlier, how much extra capacity does the prior week still need?
  1. 0 standard hours
  2. 3 standard hours
  3. 5 standard hours
  4. 1 standard hour
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

96 Key Terms, each with its definition

A

Action notice
An action notice is a planning message requesting an order release, earlier delivery, postponement, or cancellation to align supply with requirements.
A planner contacts the supplier after a message requests that an existing receipt arrive earlier.
Aggregate planning
Aggregate planning sets the quantities and timing of family output and the resources used to meet intermediate-term demand.
A pump plant compares staffing and inventory plans for the next six months before scheduling models.
Available-to-promise (ATP)
Available-to-promise is inventory and scheduled end-item supply remaining after booked orders, available for additional customer commitments.
Sales checks uncommitted supply due by week four before promising a new order for that week.

B

Backorder
A backorder is accepted demand that cannot be supplied when due and remains to be delivered later with the customer’s agreement.
A customer accepts delivery next month, so the missing quantity remains in the plan as backlog.
Backorder cost
Backorder cost is the cost assigned to accepted demand waiting for delivery, often charged per unit for each period of delay.
A 50-unit backlog carried one month at $8 per unit-month contributes $400 to the plan.
Bill of materials (BOM)
A bill of materials lists the components, materials, or ingredients needed for one parent item, including the quantity of each input.
The chair bill records its seat, base, and direct fasteners before their lower-level parts are considered.
BOM explosion
BOM explosion multiplies parent production quantities through product levels to calculate the component requirements created by that work.
The planner nets stocked seats before exploding only the seats that still need to be made.
Bucketless planning
Bucketless planning represents requirements and orders by exact dates instead of collecting them only into weekly or monthly time buckets.
Two component deliveries within the same week can appear on different dates in the material plan.

C

Capacity requirements planning (CRP)
Capacity requirements planning calculates detailed work-center loads from planned and existing orders, using routings and operation times.
A detailed load report reveals a machining overload that an earlier check, focused only on final assembly, missed.
Chase strategy
A chase strategy adjusts production to each period’s demand, using changes in workforce, hours, or purchased capacity to follow the demand pattern.
A service firm adds temporary capacity for its busy weeks instead of building finished inventory.
Closed-loop MRP
Closed-loop MRP links materials planning with capacity checks and feedback from purchasing and production so plans can be corrected against actuals.
A late receipt feeds back into the material plan and a revised production commitment.
Counterseasonal mixing
Counterseasonal mixing combines products or services with demand peaks at different times to smooth the use of shared resources.
A maker balances winter heating products with cooling products that sell strongly in summer.
Cross-training
Cross-training prepares employees to perform more than one task, letting an operation move available staff toward the work that needs capacity.
Service staff switch between customer intake and processing when the queue pattern changes.
Cumulative demand
Cumulative demand is the total demand from the start of the horizon through a selected period, used to check whether supply stays ahead.
By month three, the planner compares all demand so far with beginning stock plus all output so far.
Cumulative lead time
Cumulative lead time is the total time along the longest dependent path of procurement and production needed to complete an end item.
Three weeks for a part, two for its assembly, and one for final assembly create a six-week path.
Cumulative supply
Cumulative supply is beginning inventory plus production received through a selected period, compared with cumulative demand to detect shortages.
A positive final balance can hide an earlier month when cumulative demand exceeded available supply.
Cycle counting
Cycle counting checks selected inventory items throughout the year and investigates differences to maintain accurate stock records and transactions.
A daily count uncovers an unrecorded material issue before the next plan relies on overstated stock.

D

Demand review
A demand review combines the statistical forecast with market knowledge, promotions, launches, and customer commitments to build a demand plan.
Sales adds the expected effect of a product launch before operations tests the required supply.
Demand time fence
A demand time fence marks the near-term boundary inside which planning usually counts customer orders and ignores remaining forecast demand.
A near-term week may be planned from actual bookings even when its forecast is larger.
Dependent demand
Dependent demand is demand calculated from the planned production of parent items, using the quantity of the component required by each parent.
Starting 100 bases with five casters each creates a gross requirement for 500 casters.
Disaggregation
Disaggregation breaks a family plan into specific products and dates while keeping their totals consistent with the aggregate plan.
A monthly total for a bicycle family becomes weekly quantities for each frame size and model.
Distribution requirements planning (DRP)
Distribution requirements planning applies time-phased netting through a warehouse network, passing replenishment needs to supplying locations.
Regional warehouse orders become gross requirements for the central warehouse that dispatches the stock.

E

Economic order quantity (EOQ)
Economic order quantity is a fixed order size calculated from average demand, setup cost, and holding cost using consistent time units.
Lumpy requirements can leave inventory remnants even when the fixed order size follows the EOQ formula.
Economic part period
The economic part period is setup cost divided by holding cost per unit per period, measuring the carrying exposure equivalent to one setup.
A $90 setup and $0.50 weekly holding rate create a target of 180 unit-weeks.
Efficiency
Efficiency compares standard hours of output produced with actual hours worked, converting worked clock hours into standard-hour capacity.
At 110% efficiency, 80 worked hours produce output equivalent to 88 standard hours.
Enterprise resource planning (ERP)
Enterprise resource planning is an integrated software suite that shares data across major processes such as finance, HR, sales, and operations.
One customer order remains visible as it moves from order entry through shipment and invoicing.

F

Feasible plan
A feasible plan satisfies the model’s demand, inventory, capacity, and policy constraints throughout the horizon, not only at its end.
A cheap plan with a backlog is rejected when the customer-service policy prohibits delayed delivery.
Final assembly schedule
A final assembly schedule sets the work needed to combine planned modules or options into the particular finished configurations customers order.
A desk order chooses a top and frame from modules already covered by the master schedule.
Firm planned order
A firm planned order is a proposed order whose date and quantity a planner protects from automatic changes during replanning.
A stable supplier commitment is protected while the planner reviews whether changed demand needs action.
Frozen zone
A frozen zone is the nearest part of a schedule, protected from routine changes and altered only exceptionally with senior approval.
A late request triggers an approval decision because materials and work are already committed.

G

Gross requirements
Gross requirements are the total demand for an item in a time period before available inventory and existing receipts are deducted.
A shared component combines requirements from several parents before its stock is netted.

H

Holding cost
Holding cost is the cost of carrying inventory through time, expressed per unit per period; ending-inventory costing uses each ending balance.
Keeping 100 units through one month at a rate of $2 per unit creates $200 of holding cost.

I

Independent demand
Independent demand is demand not derived from a parent’s production requirements, planned from customer orders, forecasts, or both.
A replacement caster sold directly to a customer creates independent demand for that spare part.
Integrated business planning (IBP)
Integrated business planning usually describes S&OP with a fuller connection to financial planning and strategy over a longer horizon.
A business reviews the financial effects of future product changes alongside its supply scenarios.
Inventory balance
An inventory balance carries beginning stock forward, adds receipts or output, and subtracts demand to calculate the ending position.
Stock built in a quiet month supplies part of the following month’s demand peak.

L

Lead-time offsetting
Lead-time offsetting places an order’s start earlier than its required receipt by the procurement or production time needed to complete it.
Component demand follows the parent’s start date, so its own supply must be offset still earlier.
Level production rate
A level production rate is constant output per period calculated to cover total demand while moving from beginning stock to the ending-stock target.
Starting stock reduces the number of new units that must be produced over the horizon.
Level strategy
A level strategy keeps output or the core workforce constant while inventory, accepted backlog, or flexible hours absorb demand changes.
A skilled assembly team stays employed while early production builds stock for the peak month.
Linear programming
Linear programming finds the minimum or maximum of a linear objective within linear constraints, allowing linked planning quantities to be chosen together.
A planning model chooses workforce changes and production while enforcing inventory balances.
Liquid zone
A liquid zone is the farther part of a schedule where plans can change more freely because fewer near-term resources and orders are committed.
A future product mix is revised before materials and production starts are firmly committed.
Load profile
A load profile displays planned resource load against capacity by period, making overloads and underloads visible for corrective decisions.
A weekly chart reveals a peak that would disappear if the same loads were shown only as an average.
Long-range planning
Long-range planning decides the basic capacity of the operation, such as facilities, locations, and major equipment, usually more than a year ahead.
A new production building must be planned before monthly staffing can make use of it.
Lot sizing
Lot sizing chooses how much to procure or produce at each order event, balancing setup or ordering costs with inventory carrying costs.
Grouping several weeks into one order saves setups but holds later requirements in stock early.
Lot-for-lot (L4L)
Lot-for-lot is a lot-sizing rule that orders exactly the net requirement of each period, without deliberately grouping future requirements.
Separate weekly shortages become separate receipts when no minimum-order modifier applies.
Low-level code
A low-level code identifies the deepest level where an item appears, allowing all its parent requirements to be gathered before netting its stock.
Bolts used at levels one and two are processed at level two, after both demand branches are known.

M

Manufacturing resource planning (MRP II)
Manufacturing resource planning integrates material plans with manufacturing resources, S&OP, financial consequences, and what-if analysis.
A proposed overtime plan is compared in both production units and its effect on the financial plan.
Master production schedule (MPS)
A master production schedule states the quantities and completion periods of specific end items or modules within the aggregate family plan.
A monthly total for a pump family becomes weekly supply lots for the individual models customers order.
Material requirements planning (MRP)
Material requirements planning calculates dependent material quantities and dates by combining the MPS, BOM, inventory, open orders, and lead times.
The plan proposes component receipts and works backward to the dates their orders must start.
Mixed strategy
A mixed strategy combines two or more planning options to balance demand and supply, such as stable staffing, inventory, and overtime.
The plant keeps its trained core team and buys some peak output from a subcontractor.
Modular BOM
A modular BOM organizes a configurable product around reusable modules or options that can be planned before the final combination is selected.
Four seat choices and three bases can support twelve finished chair combinations from seven modules.

N

Net requirements
Net requirements are the remaining shortage after available stock and scheduled receipts are compared with demand plus the safety-stock target.
Stock covering both demand and the safety target gives a zero net requirement, not another safety order.
Net-change MRP
Net-change MRP recalculates the items affected by a new demand or supply event, allowing targeted updates between complete planning runs.
A delayed purchase order triggers recalculation for its item and the related parent requirements.

O

On-premises ERP
On-premises ERP runs on servers managed by the organization, giving it responsibility for operating the infrastructure that hosts the software.
The company’s own IT team manages the servers used for its purchasing and finance modules.
Order backlog
An order backlog is the quantity of accepted customer orders still waiting to be shipped, carried forward until deliveries reduce it.
A make-to-order workshop adds new orders to backlog and subtracts each month’s shipments.
Order modifier
An order modifier is a quantity restriction, such as a minimum, maximum, or pack multiple, applied to the lot proposed by a planning rule.
A supplier’s 25-unit pack rule increases a 68-unit requirement to a planned receipt of 75.

P

Paid idle time
Paid idle time is time for which employees are paid although they are not producing, so payroll can exceed output times a fully productive unit rate.
A retained team has capacity for 500 units but makes 450; its full payroll still enters the plan.
Part period balancing (PPB)
Part period balancing groups future requirements so the resulting unit-periods of holding are close to the economic part-period target.
The planner compares carrying totals just below and above the target before choosing the lot coverage.
Pegging
Pegging traces a component requirement back to the parent orders that created it, helping identify end items and customers affected by a shortage.
A caster shortage is traced through base starts to the chair orders needing those bases.
Period order quantity (POQ)
Period order quantity converts EOQ into a fixed coverage interval and orders the actual requirements of the periods within that interval.
A three-week rule creates different-sized orders when each group of three weeks has different demand.
Phantom BOM
A phantom BOM describes a subassembly made and used immediately without being held in stock, so requirements pass through to its components.
An immediate-use assembly does not create a separate stocked buffer between its parts and parent.
Plan attainment
Plan attainment is actual production divided by planned production for the same scope and period, commonly shown as a percentage.
Making 950 units against a 1,000-unit plan gives 95% attainment, prompting a review of the shortfall.
Planned order receipt
A planned order receipt is a proposed supply quantity due in a future period, sized to cover net requirements under the item’s lot rule.
A 70-unit shortage may produce a 75-unit planned receipt when the supplier packs in multiples of 25.
Planned order release
A planned order release is the proposed start or placement of an order, dated earlier than its receipt by the required lead time.
A receipt needed in week seven with two weeks of lead time requires release in week five.
Planning BOM
A planning BOM allocates a product family across expected options or variants using percentages to support forecasting and supply planning.
A family plan assigns 60% of expected seat demand to black and 40% to gray.
Planning horizon
A planning horizon is the future span covered by a plan, chosen to match the lead times and decisions the organization needs to manage.
A long hiring lead time requires planners to look beyond the immediate month’s demand.
Planning time fence
A planning time fence marks the near-term boundary within which the scheduler controls supply changes that the system would otherwise make automatically.
A proposed near-term MPS move waits for scheduler review instead of being adopted automatically.
Product family
A product family is a group of items that share processes and resources and can be planned together in a common aggregate unit.
Several pump models use the same assembly line, so planners first set their combined monthly output.
Projected available balance (PAB)
Projected available balance is expected end-item stock after prior stock, scheduled production, and the period’s planning demand are combined.
A negative projected balance signals that the master schedule needs additional supply or revision.

Q

Quantity per
Quantity per is the amount of a component needed to make one unit of its parent, used to multiply parent production into component requirements.
Two modules per kit turn 80 planned kits into a gross requirement for 160 modules.

R

Rated capacity
Rated capacity is the standard output a resource can provide from its available time after utilization and efficiency are applied.
Eighty available labor-hours at 90% utilization and 95% efficiency yield 68.4 standard hours.
Reconciliation
Reconciliation compares demand, supply, and financial plans and prepares the trade-offs and recommendations that need a decision.
The team compares overtime with later delivery and shows the cost of each response to executives.
Regenerative MRP
Regenerative MRP recalculates the complete material plan for all items at selected intervals, using the latest planning data and requirements.
A weekend run rebuilds the full plan after the week’s recorded orders, receipts, and issues.
Regular-time production
Regular-time production is output made within the normal paid working schedule, distinguished from overtime and subcontracted supply.
A plant uses its regular team for base demand and separately records output bought during the peak.
Revenue management
Revenue management varies prices and booking access across segments and times to earn revenue from fixed service capacity that expires unused.
A hotel weighs discounted early bookings against the chance of higher-price bookings later.
Rolling horizon
A rolling horizon moves forward as time passes, replacing completed periods with actual results and adding new periods at the end.
After April closes, the team updates May onward and adds a new April at the far end of its year plan.
Rough-cut capacity planning (RCCP)
Rough-cut capacity planning checks the master production schedule against selected key resources using standard hours required by end items.
A proposed master schedule for pumps is tested against final-assembly hours before its component plan is accepted.
Routing
A routing records the work centers an item visits and the setup and run times used to translate its orders into resource loads.
A batch visits cutting before welding, with its load placed in each center’s planned work period.

S

Safety lead time
Safety lead time schedules supply earlier than the normal required date to provide a time buffer against uncertain or late delivery.
A planner brings an expected delivery forward while leaving the planned consumption date unchanged.
Sales and operations planning (S&OP)
Sales and operations planning is a senior-led process that aligns family demand, supply, financial targets, and business strategy.
Sales, operations, and finance agree how to cover a demand peak that exceeds regular capacity.
Scenario
A scenario is a consistent set of planning inputs and responses used to compare possible outcomes before choosing an operating plan.
The team costs one response to high demand and another to demand falling below forecast.
Scheduled receipt
A scheduled receipt is supply from an order already released and expected to arrive in a specified period, included in available supply.
A supplier’s open order due next week reduces the new quantity the planner needs to propose.
Sensitivity analysis
Sensitivity analysis changes a planning input and recomputes the result to see how strongly a decision depends on that input.
A lower holding rate reverses the ranking of a low-inventory mixed plan and a level plan.
Setup cost
Setup cost is the cost incurred each time production is prepared for a batch, treated as a cost per order in the lot-sizing comparison.
Two batches each incur a setup even when their combined output equals one larger batch.
Shared database
A shared database stores common transaction and planning records used by several modules, reducing conflicting data and repeated entry.
Recording a receipt updates stock availability and the purchasing order position from the same event.
Short-range planning
Short-range planning assigns specific jobs, machines, and people over the near term, often from daily work up to about three months.
A planner assigns next week’s customer orders to available production resources.
Slushy zone
A slushy zone is the part of a schedule where the master scheduler can allow changes through managed trade-offs among products and resources.
One model’s quantity can rise if another is reduced without exceeding the available resource load.
Software-as-a-service (SaaS)
Software-as-a-service provides subscription access to software operated and updated by the vendor, including cloud-delivered ERP suites.
A business subscribes to ERP modules while the vendor manages their hosted operation and updates.
Standard hour
A standard hour is a unit of work content based on the operation’s standard time, allowing planned loads and rated output to be compared.
A 40-unit batch at 0.5 standard hours each creates 20 standard run hours before its setup is added.
Subcontracting
Subcontracting buys work or output from another organization to supplement internal capacity, with trade-offs in price, quality, and timing.
An external assembler covers a short peak while the plant retains its normal workforce.
Supply review
A supply review checks the demand plan against production, materials, and supplier limits and develops responses to expected constraints.
Purchasing warns that a supplier cannot support the peak volume without earlier orders.
System nervousness
System nervousness is frequent, large change in lower-level plans caused by small changes to higher-level quantities, dates, or lot groupings.
A small MPS revision causes many component purchase dates to move, disrupting supplier plans.

T

Transportation model
A transportation model allocates fixed production capacities to period demands, including holding cost when earlier output serves later demand.
The model assigns available overtime output to future demand but does not decide how many workers to hire.

U

Utilization
Utilization is the share of available clock hours actually worked on production, excluding time lost to breaks, maintenance, and similar causes.
At 80% utilization, a resource with 100 available hours spends 80 hours working on production.

W

Wagner–Whitin algorithm
The Wagner–Whitin algorithm finds a minimum-cost lot plan for a single item with known finite-horizon requirements and no capacity constraint.
The optimal order intervals can change when revised future requirements alter the cost comparison.
Worker-month
A worker-month is one worker employed for one month, used to total labor resources and payroll across a monthly planning horizon.
Ten workers retained for three months represent 30 worker-months even if some hours are idle.
Workforce balance
A workforce balance calculates the current workforce as the previous workforce plus hires minus layoffs for the planning period.
Starting with 20 staff and needing 23 means three hires, not 23 new hires.

About this lesson

By StudeliReport a mistake

Make your own Study Materials