Aggregate Planning, MRP and ERP
IntermediateLesson 7 of 9 in Operations Management Course
What you will learn
- Place aggregate planning in a company's planning hierarchy and follow the monthly sales and operations planning (S&OP) cycle that turns forecasts, capacity and financial targets into one agreed plan.
- Place aggregate planning in the planning hierarchyDefine aggregate planning and S&OP, describe the planning horizons, and show how an aggregate plan for product families is broken down into detailed schedules.
- Follow the monthly S&OP cycleDescribe the steps of a monthly S&OP cycle, read an S&OP family plan, reconcile volumes with the financial plan, and recognize what makes the process fail.
- Place aggregate planning in the planning hierarchy
- Choose among the ways to match capacity and demand, cost chase, level and mixed plans in a planning table, and pick a plan using both cost and judgment.
- Choose options for matching capacity and demandCompare the capacity options and demand options available in the intermediate term, define chase, level and mixed strategies, and judge when each fits, including in services.
- Set up a planning table and cost a chase planOrganize the data an aggregate plan needs, apply the inventory and workforce balances, and work out the full cost of a chase plan.
- Cost level plans with inventory, backorders and subcontractingCalculate a level production rate, track the inventory or backorders it creates, and cost level plans that use inventory alone or a smaller workforce plus subcontracting.
- Compare plans and choose a mixed strategyCost a mixed plan, compare all plans side by side, test how sensitive the choice is to the cost figures, and weigh the factors a cost table leaves out.
- Choose options for matching capacity and demand
- Turn the aggregate plan into a master production schedule that can be promised to customers, and use the bill of materials to see what each end item is made of and when its parts are needed.
- Build a master production schedule and promise ordersDisaggregate the plan into an MPS, calculate projected available balance and available-to-promise, and protect the schedule with time fences.
- Read and use a bill of materialsDistinguish dependent from independent demand, read a product structure, explode requirements level by level with inventory, and use lead times and special bill types.
- Build a master production schedule and promise orders
- Use MRP records to net requirements, offset lead times and explode plans down the product structure, size orders with standard lot-sizing rules, and keep the plan reliable in practice.
- Apply MRP gross-to-net logicName the inputs and outputs of MRP, complete an MRP record step by step, and pass planned orders down to the next level.
- Choose a lot-sizing techniqueSize MRP orders with lot-for-lot, EOQ, period order quantity and other rules, compare their costs on the same requirements, and know when each fits.
- Keep MRP plans reliable and extend MRP logicMaintain accurate data, choose how MRP replans, use pegging, action notices and firm planned orders, recognize system nervousness, and extend time-phased logic to services and distribution.
- Apply MRP gross-to-net logic
- Check whether the MPS and MRP plans fit the capacity of key resources and work centers, and explain how closed-loop MRP, MRP II and ERP systems link planning with the rest of the business.
- Check plans with rough-cut capacity planning and CRPPlace capacity checks at each planning level, calculate rated capacity and work-center load, and choose remedies for overloads and underloads.
- Explain MRP II and ERP systemsTrace the path from MRP to ERP, describe what an ERP system integrates, and weigh its benefits and drawbacks for manufacturers and service organizations.
- Check plans with rough-cut capacity planning and CRP
Aggregate Planning study guide
1Balance demand, supply, and business targets
Planning connects decisions made years ahead with work done today. A company first chooses its basic capacity, then decides how to use it, and finally assigns specific jobs. Sales and operations planning brings the departments together around the middle of that chain. Learn to read a family plan, connect units with financial targets, and distinguish the decisions executives make from the detail that planners handle afterward.
1.1 Connect business plans with daily work
Aggregate planning decides how much to produce over the coming months and how to supply it. It groups products that use common resources, so the plan can balance demand with workforce, inventory, and other capacity options.
Choose the right planning level
| Horizon | Main decision | Example |
|---|---|---|
| Long range, usually more than a year | Choose basic capacity | Open a plant or buy major equipment |
| Intermediate, often 3–18 months | Use existing capacity | Set monthly output, staffing, and inventory |
| Short range, often up to 3 months | Assign specific work | Put an order on a machine next Tuesday |
The boundaries vary by company. The useful distinction is the decision each plan controls. An aggregate planner can add overtime within a plant; a new building usually needs an earlier, longer-range decision.
Plan a common unit
A product family groups items that share processes and resources. A bicycle maker might plan 1,200 road bikes for March before choosing frame sizes and colors. Other useful aggregate units include labor-hours, machine-hours, or kilograms of material. The unit must represent the resources the plan needs.
Family demand is generally more predictable than individual-item demand because some item-level variation cancels when totals are combined. Shared equipment and labor also make a family total useful for capacity decisions. A family plan still needs enough detail to avoid hiding a scarce resource used by only some items.
The inputs are forecasts by period, starting workforce and inventory, available capacity, and cost rates. Policies matter too: a limit on overtime, a target service level, or a commitment to stable employment can rule out an otherwise cheap plan.
Break the family plan into detail
Disaggregation translates the family total into specific end items and dates. The sequence is aggregate plan → master production schedule (MPS) → material requirements planning (MRP) → short-term job schedules.
For 1,200 road bikes, the MPS might specify 300 small, 500 medium, and 400 large bikes across four weeks. These quantities total 1,200. MRP then calculates the frames, wheels, and other parts needed for the planned builds. The daily schedule assigns actual jobs to resources. A monthly quantity alone cannot say which customer order runs on Tuesday.
Agree across departments
Sales and operations planning (S&OP) is the monthly decision process that aligns family demand, supply, financial targets, and business strategy. Senior management leads it. Sales contributes market knowledge and customer commitments; operations and purchasing contribute capacity and supplier limits; finance connects volumes with revenue, cost, and cash. Product development explains launches and phase-outs, while human resources supplies hiring and training information.
The aggregate plan is the operations side of the agreed S&OP plan. S&OP needs decisions that all these functions can carry out. A sales forecast without a supply response leaves that work unfinished.
Services use the same hierarchy. A call center can convert forecast calls into monthly agent-hours, then into weekly staffing and shifts. Unused service time cannot be stored as finished inventory, so staffing flexibility carries more of the adjustment.
Key Takeaways
- Aggregate planning sets family output and resource use over the intermediate horizon.
- Disaggregation must preserve family totals while adding item quantities and dates.
- S&OP aligns sales, operations, finance, and other functions around one operating plan.
- Service plans often use staff-hours because unused service capacity cannot be stored.
1.2 Turn the monthly review into an agreed plan
The S&OP cycle replaces separate departmental plans with one set of decisions. It looks far enough ahead for the company to respond before a shortage, excess inventory, or financial gap becomes urgent.
Follow a rolling cycle
A typical cycle begins after month-end:
- Gather data: update actual sales, output, inventory, and the statistical forecast.
- Review demand: add market knowledge, promotions, launches, and customer commitments.
- Review supply: check capacity, materials, and suppliers; develop responses to constraints.
- Reconcile: compare demand, supply, and finance; prepare scenarios and recommendations.
- Decide: executives approve the plan and settle unresolved trade-offs.
Some companies include a separate product review. The names and number of meetings vary, but the demand, supply, financial, and executive decisions still need owners.
The horizon is rolling, often 12–18 months. Each month, actual results replace the completed month, the remaining periods are updated, and a new month is added at the far end. S&OP decides family volume. The MPS later decides item mix, such as individual sizes and models.
Read the family balances
For a make-to-stock family, production builds inventory before sales draw it down:
Beginning stock of 500 units, production of 1,100, and sales of 1,250 leave 350 units. Against a target of 400, the projected gap is 50 units. The team must choose more supply or a lower inventory position.
For a make-to-order family, track orders waiting to ship:
A family starting with 180 units of backlog, taking 900 units of new orders, and shipping 950 ends with 130. A growing backlog can lengthen customer lead times; a sustained decline can signal that capacity will soon lack work.
Translate volume into money
At an average selling price of $250, sales of 1,200 units produce $300,000 of revenue. A financial target of $330,000 therefore has a $30,000 gap. More production alone cannot close it: revenue needs sales. Options include finding additional demand that supply can meet, changing the product plan, or revising the financial forecast.
Track plan attainment as actual output divided by planned output. Producing 1,140 of 1,200 planned units gives 95%. Review forecast accuracy, inventory or backlog against target, and on-time delivery alongside it. Strong attainment of the wrong plan can still leave poor customer service or too much stock.
Keep decisions honest
S&OP weakens when departments retain different numbers, change forecasts to fit targets, or use the executive meeting only to read reports. A forecast describes expected demand; a target describes desired performance. Reconciliation makes their gap visible so leaders can decide what to do.
Integrated business planning (IBP) usually means a broader connection with strategy and financial planning, often over 24 months or more. Usage varies, so judge the process by its decisions and links, not its name. Keep attention on later months too: that is where hiring, supplier, and product decisions still have time to work.
Key Takeaways
- The cycle moves from updated data through demand, supply, reconciliation, and executive decisions.
- A rolling horizon adds a future period whenever a completed period drops out.
- Make-to-stock plans track inventory; make-to-order plans track backlog.
- Convert planned sales into money to expose gaps with financial targets.
- Forecasts and targets serve different purposes; preserve the gap for decision-making.
2Build and compare aggregate plans
A demand peak can be met by building inventory early, hiring more people, adding overtime, or buying output from another producer. Each choice moves costs and risks to a different place. Follow a pump plant through chase, level, and mixed plans, keeping its inventory and workforce balances visible. Then compare the full costs and test whether the apparent saving survives a change in demand, cost, or customer-service requirements.
2.1 Choose how to match supply with demand
An aggregate plan can change supply, change demand, or combine both. Start with the product and workforce: storage life, skill requirements, customer patience, and supplier flexibility determine which options are usable.
Compare capacity options
| Option | What it helps with | Main cost or risk |
|---|---|---|
| Build inventory early | Smooth output before a peak | Holding cost, damage, or obsolescence |
| Hire or lay off workers | Match regular output to demand | Training, severance, skill loss, and morale |
| Use overtime or paid idle time | Adjust hours with the same staff | Premium pay, fatigue, or paid unused time |
| Subcontract | Buy output beyond internal capacity | Higher unit cost and less control |
| Use temporary or part-time staff | Add flexible labor | Training, turnover, and quality consistency |
Overtime rates depend on the employment arrangement; a common teaching example is 1.5 times regular pay. Hiring also takes time before new staff reach full productivity. Employment rules and agreements can constrain workforce changes.
Change the demand pattern
A promotion or lower off-peak price can move demand toward quieter periods. Backordering accepts an order now for later delivery, provided the customer accepts the delay. Otherwise the unmet demand can become a lost sale. Counterseasonal mixing combines products with different peaks, such as heaters and air conditioners, to spread shared-resource demand across the year.
Demand measures need a supply check. A promotion that creates demand during an existing bottleneck can make delivery performance worse.
Select a strategy
A chase strategy adjusts production to demand period by period, often through workforce changes, overtime, or subcontracting. It suits output that cannot be stored and work for which capacity can change quickly.
A level strategy keeps output or the core workforce steady. Inventory absorbs differences between output and demand; accepted backorders can absorb temporary shortages. It suits storable products and skilled teams that are costly to rebuild. A constant workforce can still vary output through overtime or idle time.
A mixed strategy combines options, such as a stable core workforce, some inventory built early, and overtime during a short peak. A pure strategy changes only one planning variable.
Chase avoids inventory holding but can create large workforce-change costs. Level avoids repeated workforce changes but can create large stocks. The demand pattern and cost rates decide their relative cost; the strategy name cannot settle that comparison.
Apply the ideas to services
Services often adjust staffing through part-time work, flexible shifts, overtime, and cross-training. A restaurant needs capacity during the dinner rush; unused staff time from lunchtime cannot be carried forward as stock.
Revenue management, also called yield management, varies prices and access across customer segments and booking times. It is useful when capacity is fixed, can be sold in advance, expires unused, and has a low extra cost per customer served. A hotel room tonight loses its selling opportunity once the night passes. Selling every room cheaply very early can also displace customers willing to pay more later, so the decision concerns timing and revenue as well as occupancy.
Key Takeaways
- Capacity options change supply; demand options influence when or how much customers buy.
- Chase follows demand; level stabilizes output or workforce; mixed plans combine options.
- Backorders require customers who accept delayed delivery.
- Service capacity expires, so staffing and demand timing are central.
- Revenue management balances prices and booking opportunities for perishable capacity.
- Cost every usable strategy before choosing one.
2.2 Build and cost a chase plan
A planning table keeps quantities, workers, and money separate until the quantities are correct. For each period, first calculate the workforce and inventory movement. Then apply the appropriate cost rate to each movement or balance.
Set up the balances
Record demand by period, beginning stock and workforce, output per worker, and all cost rates. Include capacity limits, ending-stock targets, and backorder policies.
Here, ending inventory equals the previous balance plus all output received minus demand. Output includes regular production, overtime, and subcontracted supply. A negative net inventory balance represents a backorder. Workforce follows a separate balance: current workers equal previous workers plus hires minus layoffs.
Match the pump plant's monthly demand
The plant starts with 25 workers and no stock. Each worker produces 40 pumps per month and earns $3,200 per month. Hiring costs $1,000 per worker, layoffs $1,500, and inventory holding $10 per pump per month on ending stock. Demand totals 7,200 pumps.
| Month | Demand | Workers needed | Hires | Layoffs |
|---|---|---|---|---|
| Jan | 800 | 20 | 0 | 5 |
| Feb | 1,000 | 25 | 5 | 0 |
| Mar | 1,200 | 30 | 5 | 0 |
| Apr | 1,600 | 40 | 10 | 0 |
| May | 1,400 | 35 | 0 | 5 |
| Jun | 1,200 | 30 | 0 | 5 |
Divide each month's demand by 40 to obtain its workforce. Then compare that workforce with the previous month's workforce. January needs five layoffs because the starting workforce is 25; starting the calculation from zero would miss this cost. Production equals demand in each month, so every ending inventory is zero.
Calculate the full cost
The workforce totals 180 worker-months. Regular labor is therefore 180 × $3,200 = $576,000. The 20 hires cost $20,000; the 15 layoffs cost $22,500. With no ending stock or backorders, the total is $618,500.
Regular labor is paid for workers employed, including paid idle time. The shortcut 7,200 pumps × $80 gives the same $576,000 here because all 180 worker-months are fully productive. It would understate cost if workers were paid while idle. It also needs revision when overtime or subcontracted output replaces regular-time production at another rate.
Check practical details
Whole workers cannot be rounded down when that leaves demand uncovered. If 30.5 workers are calculated, 30 workers do not provide enough output. An extra worker, overtime, inventory, or subcontracting must close the gap; show the resulting stock or cost.
Different working-day counts also change the interpretation of monthly demand. Demand of 1,320 over 22 days and 1,200 over 20 days both require 60 pumps daily. Compare capacity on a consistent time basis.
Holding conventions must stay fixed across plans. Ending-inventory costing charges every period's positive ending balance. Average-inventory costing uses a different base and can produce a different ranking. Backorder cost applies to the magnitude of a negative balance, not as a negative holding cost.
Key Takeaways
- Calculate workforce needs before hiring and layoff costs.
- Include the starting workforce in the first period comparison.
- Charge regular labor for paid worker-periods, including paid idle time.
- Carry each ending inventory balance into the next period.
- Use consistent time units and inventory-cost conventions.
2.3 Follow inventory through a level plan
A level plan spreads production across the horizon. Its average output can meet total demand while still missing an early peak, so calculate both the overall rate and every period's inventory balance.
Find the constant rate
For six months of pump demand totaling 7,200, with zero beginning and target ending inventory, the rate is 1,200 pumps per month. At 40 pumps per worker, this requires 30 workers. Hire five in January from the starting workforce of 25.
Beginning stock reduces required production. With 300 pumps initially available and no ending target, total production would be 6,900 and the rate 1,150. Using 1,200 would leave an unplanned 300 pumps at the end.
Carry the stock forward
| Month | Demand | Production | Ending inventory |
|---|---|---|---|
| Jan | 800 | 1,200 | 400 |
| Feb | 1,000 | 1,200 | 600 |
| Mar | 1,200 | 1,200 | 600 |
| Apr | 1,600 | 1,200 | 200 |
| May | 1,400 | 1,200 | 0 |
| Jun | 1,200 | 1,200 | 0 |
February starts with January's 400: add 1,200 and subtract 1,000 to obtain 600. Do not restart each month at zero. April's peak uses 400 pumps from stock; May uses the remaining 200.
Regular labor costs 30 workers × 6 months × $3,200 = $576,000. Hiring costs $5,000. Sum the ending stocks: 1,800 pump-months, costing $18,000 at $10 each. Total cost is $599,000, which is $19,500 below the chase plan.
Check every cumulative position
A plan avoids backorders only if beginning inventory plus cumulative production covers cumulative demand in every period. A zero final balance checks the horizon total but says nothing about earlier shortages.
If January demand were 1,600 with no starting stock, output of 1,200 would leave a 400-unit backlog immediately. Customers must accept that delay for backordering to be usable. On a cumulative graph, inventory equals beginning stock plus cumulative production minus cumulative demand. Start the supply line at beginning stock if you want the vertical gap to show the inventory directly.
Test a smaller workforce
Keep 28 workers, producing 1,120 monthly, and subcontract 240 pumps in each of April and May. Ending stocks become 320, 440, 360, 120, 80, and zero. This needs three initial hires and buys 480 pumps externally.
The cost is $537,600 regular labor + $3,000 hiring + $13,200 holding + $52,800 subcontracting = $606,600. The external price is $110 per pump, compared with $80 regular labor per fully productive pump. Lower payroll alone therefore does not make this plan cheaper. A level workforce with subcontracting is a mixed use of options, even though its internal staffing stays level.
Key Takeaways
- Beginning inventory reduces the production needed over the horizon.
- A level rate that balances total demand can still create early shortages.
- Sum all positive ending stocks to calculate ending-inventory holding cost.
- Check subcontracting cost alongside the payroll it replaces.
2.4 Compare cost, feasibility, and risk
A mixed plan can delay hiring, carry less inventory, and accept a limited backlog. Evaluate these changes together: a saving in one row can create a larger cost or an unacceptable service result elsewhere.
Cost a mixed pump plan
Keep 25 workers in January, hire two in February, then five in March. Hold 32 workers from March through June. Output is 1,000, 1,080, 1,280, 1,280, 1,280, and 1,280 pumps, totaling 7,200.
Against demand of 800, 1,000, 1,200, 1,600, 1,400, and 1,200, ending balances are 200, 280, 360, 40, −80, and zero. May's negative 80 means customers wait for 80 pumps delivered in June. June production must serve that backlog as well as June demand.
The 180 worker-months cost $576,000. Seven hires cost $7,000. Positive ending stocks total 880 pump-months, costing $8,800. The 80 pump-months backordered cost $2,000 at $25 each. Total cost is $593,800.
| Plan | Total cost |
|---|---|
| Mixed | $593,800 |
| Level, 30 workers | $599,000 |
| Level workforce of 28 plus subcontracting | $606,600 |
| Chase | $618,500 |
The mixed plan is cheapest among these candidates under these costs. It is acceptable only if the planned May delay is allowed. Spreadsheet comparison proves which tested candidate costs least; it does not prove that no better plan exists.
Test a cost change
Suppose holding falls from $10 to $4 per pump per month. Recalculate only the affected row while keeping the other costs intact.
The 30-worker level plan becomes $576,000 + $5,000 + 1,800 × $4 = $588,200. The mixed plan becomes $576,000 + $7,000 + 880 × $4 + $2,000 = $588,520. Level is now cheaper by $320. Lower holding cost favors the plan carrying more inventory.
Sensitivity analysis shows how robust a decision is. A narrow cost advantage deserves close attention to forecast error, supplier reliability, customer patience, and the availability of trained workers. Repeated layoffs can damage skills and morale; more inventory can become obsolete if demand falls. These effects help define the cheapest acceptable plan.
Understand what models decide
A linear program can choose output, inventories, backorders, and workforce changes together when costs and constraints are linear. Its minimum is conditional on that model's costs and constraints.
A transportation model has a narrower role. Regular-time, overtime, and subcontract capacities are fixed sources; period demands are destinations. Producing early adds holding cost for each period the unit waits. The model allocates supply within those capacities. It does not choose how many people to hire or lay off.
Review the chosen plan in the monthly S&OP cycle. Updated demand and actual performance can change the best response, while the near periods move into item-level master scheduling.
Key Takeaways
- Cost positive stock and negative backlog separately.
- Compare plans with the same demand, starting conditions, and cost conventions.
- Sensitivity analysis changes one input and follows its effect on the ranking.
- The cheapest acceptable plan must meet service, workforce, and supply constraints.
- A transportation model allocates fixed capacities; a general linear program can choose workforce changes.
- A spreadsheet comparison finds the best tested candidate, not a guaranteed overall optimum.
3Schedule end items and calculate their parts
A monthly family total leaves several questions unanswered: which products will be ready, when customers can receive them, and which parts production needs. The master production schedule supplies the item quantities and dates. The bill of materials supplies the product structure. Together they turn an aggregate commitment into a plan that can support order promises and component calculations without losing track of existing stock.
3.1 Build the master schedule and promise deliveries
The master production schedule (MPS) names the end items or modules to make, their quantities, and their completion periods. Its totals must agree with the family plan, and key-resource capacity must support it.
Choose what to schedule
Make-to-stock firms schedule finished products. Assemble-to-order firms schedule modules and options, then use a final assembly schedule for each customer's combination. Make-to-order and engineer-to-order firms schedule work against actual orders. The MPS is a supply decision built from demand and constraints; it is not simply a copy of the forecast.
Calculate projected stock
Outside a demand time fence, a common rule uses the larger of forecast and booked orders:
Projected available balance (PAB) is expected ending stock after planned demand. Add a production lot when the balance would otherwise fall below zero or the safety-stock target.
Start with 50 pumps, no safety stock, and a fixed MPS lot of 100. Forecasts are 40 in weeks 1–4 and 60 in weeks 5–8. Orders are 45, 30, 20, 10, 5, 0, 0, and 0.
| Week | Planning demand | MPS receipt | PAB |
|---|---|---|---|
| 1 | 45 | 0 | 5 |
| 2 | 40 | 100 | 65 |
| 3 | 40 | 0 | 25 |
| 4 | 40 | 100 | 85 |
| 5 | 60 | 0 | 25 |
| 6 | 60 | 100 | 65 |
| 7 | 60 | 0 | 5 |
| 8 | 60 | 100 | 45 |
Week 2 would end at −35 without a receipt, so the 100-unit lot raises its balance to 65. Adding forecast and orders would count overlapping demand twice.
Calculate what sales can promise
Available-to-promise (ATP) counts supply not committed to booked orders. It excludes forecast demand. Discrete ATP is calculated initially and in each MPS receipt period, covering orders until just before the next MPS receipt.
Week 1 ATP is 50 − 45 = 5. Week 2 ATP is 100 − (30 + 20) = 50. Week 4 ATP is 100 − (10 + 5) = 85. Weeks 6 and 8 each have 100 uncommitted units.
A new request for 60 pumps by week 3 has only 5 + 50 = 55 units of ATP available by then. Promise 55 by week 3 and five from week 4, or review the production plan. Later supply cannot satisfy an earlier delivery date. If a later ATP bucket is negative, reduce an earlier uncommitted balance to cover it before promising more.
Protect the near schedule
The frozen zone permits exceptional changes with senior approval; the slushy zone permits scheduler-managed trade-offs; the liquid zone is more flexible. Inside the demand time fence, planning usually considers booked orders without the remaining forecast. Inside the planning time fence, the master scheduler controls changes that the system would otherwise make automatically.
These controls address different issues: demand recognition and supply-plan stability. Rough-cut capacity planning checks whether key resources can produce the MPS before it drives the component plan.
Key Takeaways
- The MPS converts family volume into specific supply quantities and dates.
- PAB commonly covers the larger of forecast and orders, subject to the demand time fence.
- ATP subtracts booked orders, not forecast demand.
- Only ATP available by the requested date supports that delivery promise.
- Time fences control demand recognition and schedule changes.
- Check key-resource capacity before relying on the MPS.
3.2 Calculate parts from a bill of materials
A bill of materials (BOM) lists what one parent item requires and the quantity of each component. Demand for those components follows the parent's plan, which lets the planner calculate it instead of forecasting it separately.
Read the structure
Independent demand comes from forecasts, customer orders, or both, without being derived from another item's production requirements. Spare parts sold to customers can have independent demand. Dependent demand comes from a parent plan: 200 chairs needing five casters each create a requirement for 1,000 casters.
A product structure tree puts the end item at level 0, its direct components at level 1, and their components at level 2. One office chair needs:
- One seat assembly, one base, and four direct-assembly bolts.
- Each seat assembly needs one cushion, one seat frame, and six bolts.
- Each base needs five casters and one star frame.
Explode, then net at each level
With no inventory, 200 chairs need 200 seats and bases, 200 cushions and seat frames, 1,000 casters, 200 star frames, and 2,000 bolts. The bolts combine two branches: 800 for final chair assembly and 1,200 for seat assembly.
Now put 50 completed seat assemblies in stock. Only 150 seats need making. Cushion and seat-frame requirements drop to 150 each. Bolts become 800 + 150 × 6 = 1,700. The stocked seats already contain their cushions, frames, and bolts. Exploding all 200 gross seats before subtracting stock would buy parts for work that is already done.
An item's low-level code is the deepest level where it appears anywhere in the structure. Bolts appear at levels 1 and 2, so their code is 2. Processing by that code gathers both branches' requirements before netting bolt stock once.
Choose a useful BOM form
| Form | Purpose |
|---|---|
| Single-level | List one parent's direct components |
| Indented | Display all product levels |
| Modular | Plan standard options before final configuration |
| Planning | Split family demand using expected percentages |
| Phantom | Pass requirements through a subassembly built and used immediately |
Four seat colors and three base types give 12 final combinations but seven option modules. A planning BOM might split seat demand 60% black and 40% gray. Those percentages plan expected mix; actual order configuration still determines the final build.
Work backward through lead times
Cumulative lead time is the longest dependent path to the finished product. Chair assembly takes one week, seat assembly two, and cushion purchasing three. That path takes six weeks; parallel branches are not added together.
For shipment at the end of week 8, chair assembly occupies week 8, seat assembly weeks 6–7, and cushion procurement weeks 3–5. Release the cushion order at the start of week 3 for availability at the start of week 6. Labeling period starts and ends avoids an extra week's error.
Engineering changes must update quantities and versions, while inventory and lead-time records must reflect reality. The same structure applies to a meal recipe or a surgical kit: a planned service creates requirements for its ingredients or supplies.
Key Takeaways
- Dependent demand is calculated from parent plans; independent demand has its own demand source.
- Net intermediate stock before exploding the work still required.
- Add requirements from every branch before netting a shared component.
- Low-level codes delay processing until all parent requirements are known.
- Cumulative lead time follows the longest dependent path.
- BOM forms support different planning tasks, including options and immediate-use subassemblies.
4Plan materials and choose order sizes
Component demand arrives in bursts because it follows the work scheduled for parent products. Material requirements planning turns those bursts into dated order proposals. Work through the inventory arithmetic first, then examine how order sizes change setup and holding costs. The final step is keeping the plan useful as orders, deliveries, and inventory records change, including when the same logic is used in distribution or services.
4.1 Turn requirements into dated orders
Material requirements planning (MRP) combines the MPS, BOM, inventory, open orders, and lead times. For each item it calculates quantities and dates, then proposes orders and messages for planners to act on.
Read the six rows
| Row | Meaning |
|---|---|
| Gross requirements | Total demand in the period |
| Scheduled receipts | Orders already released and due to arrive |
| Projected on hand | Expected inventory after the period's activity |
| Net requirements | Shortfall after stock, receipts, and safety stock |
| Planned order receipts | Suggested future arrivals |
| Planned order releases | Suggested starts or placements, offset by lead time |
Scheduled receipts are existing commitments. Planned receipts remain proposals until released. Counting both as if they were separate deliveries would overstate supply.
Net one period at a time
Available supply before a new planned receipt equals previous projected stock plus scheduled receipts. Then calculate:
Apply the lot-sizing rule to obtain the planned receipt. Ending projected stock equals available plus that receipt minus gross requirements. Move the receipt backward by the lead time to place its planned release.
Safety stock belongs inside the maximum. If available stock already covers demand and the safety target, there is no net requirement. Adding the safety target after reducing a negative shortage to zero would create an unnecessary order.
Complete a chair-base record
Start with 40 bases, a scheduled receipt of 60 in week 2, one-week lead time, lot-for-lot ordering, and no safety stock. All receipts are available at the start of their week.
| Week | Gross requirements | Scheduled receipts | Net requirements | Planned receipts | Ending stock |
|---|---|---|---|---|---|
| 1 | 30 | 0 | 0 | 0 | 10 |
| 2 | 50 | 60 | 0 | 0 | 20 |
| 3 | 0 | 0 | 0 | 0 | 20 |
| 4 | 80 | 0 | 60 | 60 | 0 |
| 5 | 20 | 0 | 20 | 20 | 0 |
| 6 | 70 | 0 | 70 | 70 | 0 |
Week 2 has 10 carried forward plus 60 arriving: after 50 are used, 20 remain. Week 4 needs 80 but has only 20, so its planned receipt is 60. Release that order in week 3. Releases for the following receipts are 20 in week 4 and 70 in week 5.
Pass the right dates to components
Each base requires five casters. The base releases create caster gross requirements of 300 in week 3, 100 in week 4, and 350 in week 5. Use parent releases: casters must be available when base work starts, not when the completed bases arrive.
MRP repeats this logic down the structure in low-level-code order. With base safety stock of 10, week 4's requirement becomes 80 + 10 − 20 = 70. Safety lead time offers a different buffer by planning an earlier arrival. If a release date falls in the past, normal lead time is no longer achievable; the planner must expedite, change supply, or revise the parent schedule.
Key Takeaways
- Available supply includes previous projected stock and scheduled receipts.
- Net requirements include the safety target before applying the zero floor.
- Lot sizing sets receipt quantities; lead-time offsetting sets release dates.
- Parent planned releases generate component gross requirements.
- A past-due planned release needs action, not silent acceptance.
4.2 Compare order sizes and their costs
Lot sizing trades the cost of starting another order against the cost of carrying units early. Compare rules on the same dated requirements; a low purchase quantity alone does not measure the planning cost.
Keep the cost basis fixed
Weekly requirements are 50, 0, 60, 70, 0, 40, 80, and 20 units. Setup costs $90 per order; holding costs $0.50 per unit per week on ending inventory. There is no starting stock, and receipts arrive at the start of a week.
Lot-for-lot (L4L) orders exactly each nonzero requirement: six orders and no carried inventory. Cost is 6 × $90 = $540. It fits expensive-to-hold items or inexpensive setups.
Apply EOQ and POQ
Economic order quantity (EOQ) gives a fixed quantity using average demand:
Average weekly demand is 40, so annual demand is 2,080. Annual holding is $26 per unit. With setup cost $90, EOQ is 120 units. Use the same time basis for demand and holding.
Ordering 120 in weeks 1, 4, and 7 gives ending stocks of 70, 70, 10, 60, 60, 20, 60, and 40. Their sum is 390 unit-weeks. Cost is $270 setup + $195 holding = $465, with 40 units left after week 8. Fixed lots can leave units waiting through gaps in requirements.
Period order quantity (POQ) uses EOQ to choose a time interval: 120 ÷ 40 = three weeks. Each order covers the actual requirements of its interval. Order 110 in week 1 for weeks 1–3, 110 in week 4 for weeks 4–6, and 100 in week 7 for weeks 7–8. Ending stocks total 220 unit-weeks, so cost is $270 + $110 = $380, with no ending remnant.
Balance part-periods
A part-period is one unit held for one period. Part period balancing (PPB) groups future requirements to bring carrying cost close to one setup cost. The economic part period is 90 ÷ 0.50 = 180 unit-weeks.
From week 1, including week 3 creates 60 × 2 = 120 part-periods. Adding week 4 would create another 70 × 3 = 210, making 330 in total. The 120 total is closer to 180 than 330, so stop at week 3. Continue from the next uncovered requirement. Here PPB matches POQ at $380; another pattern can give different results.
Recognize the minimum for the model
Wagner–Whitin uses dynamic programming to compare ordering intervals over a finite horizon. For these requirements it orders 50 in week 1, 130 in week 3, and 140 in week 6. Setup costs $270. Holding is 190 unit-weeks, costing $95, for a minimum of $365.
It is optimal for the stated single-item model with known requirements and no capacity limit. It can tie a simpler rule, and its plan can change substantially when requirements change. Real systems also apply minimum quantities, maximum quantities, and pack multiples. Large parent lots create lumpy component requirements, so lot-for-lot is often useful lower in the BOM.
Key Takeaways
- Compare setup plus holding cost using the same requirements and horizon.
- EOQ fixes quantity; POQ fixes a coverage interval and varies quantity.
- PPB chooses coverage by comparing part-periods with setup cost divided by holding cost.
- Wagner–Whitin finds a minimum under its single-item finite-horizon model.
- Order modifiers can change the quantity proposed by a lot-sizing rule.
- Large parent lots can amplify lumpiness in component demand.
4.3 Keep the material plan useful as things change
An MRP run is a calculation based on records. Accurate records, controlled replanning, and prompt action on exceptions turn that calculation into a useful operating plan.
Maintain the inputs
Inventory errors change net requirements. A wrong BOM quantity multiplies the error across every parent order. An unrealistic lead time can produce a date that looks valid but cannot be met. Open-order records must also show quantities, dates, and actual status.
Cycle counting checks selected items throughout the year and investigates differences. Firms often target inventory accuracy of 95% or higher. Counting alone is not enough: the cause may be a missed receipt, an unrecorded issue, scrap, or the wrong item code. Correct the transaction process as well as the stock number.
Replan and trace changes
Regenerative MRP recalculates the whole plan at intervals. Net-change MRP recalculates affected items when something changes, such as a late delivery or a revised customer order. More frequent calculation gives quicker information, but planners still need to decide which changes deserve action.
Pegging traces a component requirement back to the parent orders that created it. A shortage of 350 casters in week 5 can be traced to 70 base starts, then to chairs and the customer orders they support. That trace helps prioritize the shortage by its consequences.
An action notice asks the planner to release, expedite, postpone, or cancel an order. Expedite brings supply earlier; de-expedite moves it later. A proposed date change is not the same as a confirmed supplier commitment.
Control nervousness
System nervousness occurs when small changes in higher-level plans trigger large, frequent changes below. Changing a parent lot can shift both the quantity and date of several component orders. Suppliers and production teams can spend more time chasing changes than completing stable work.
Time fences and firm planned orders protect selected quantities and dates from automatic revision. Ignoring immaterial changes and choosing less sensitive lot rules can also help. Firming an order does not make a shortage disappear: it leaves a protected decision that a planner must review when conditions change.
Check the resources separately
Standard MRP assumes unlimited capacity and fixed lead times. It may propose more work than a center can perform. Capacity planning checks that resource requirement, while shop-floor kanban signals can control actual replenishment. These tools can work together: MRP plans material timing, capacity planning tests resources, and pull signals manage local execution.
Some systems plan with exact dates instead of weekly buckets. This bucketless detail changes the time representation; it does not remove the need for accurate lead times or feasible capacity.
Extend the logic
A caterer calculates ingredient needs from meals and recipes. A hospital calculates supplies from scheduled procedures and standard kits. Distribution requirements planning (DRP) applies time-phased netting through a warehouse network. Regional warehouses calculate replenishment orders, and those requirements flow to the central warehouse or plant. Combine all downstream requirements before netting central stock, just as shared-component requirements are combined in a BOM.
Key Takeaways
- Accurate stock, BOM, lead-time, and open-order data are essential to reliable MRP.
- Regeneration recalculates everything; net change recalculates affected items.
- Pegging connects a shortage with the orders it threatens.
- Action notices need planner action and confirmation where appropriate.
- Firm orders and time fences reduce nervousness without removing genuine shortages.
- MRP, capacity checks, and kanban serve complementary planning and execution roles.
- DRP passes downstream replenishment needs upstream through a distribution network.
5Check resources and connect the business
A materials plan can be arithmetically correct and still ask a work center to do too much. Capacity checks compare the plan with the hours people and equipment can supply, then feed changes back into planning. Follow those checks from the master schedule to detailed orders, and see how closed-loop MRP, MRP II, and ERP connect operational information with purchasing, sales, staffing, and finance.
5.1 Compare work-center load with capacity
A capacity check asks whether the resources can perform the planned work in time. Keep the level of detail appropriate: key resources for the master schedule, then individual work centers for the material plan.
Match the check to the plan
Resource requirements planning checks aggregate plans against major resources. Rough-cut capacity planning (RCCP) checks the MPS at bottlenecks or other key resources. A bill of resources gives the standard hours required per end item. If 200 chairs need 0.4 standard hours each, assembly load is 80 standard hours. Against 70 available, the MPS needs a 10-hour remedy before it can be relied on.
Capacity requirements planning (CRP) checks detailed MRP orders using their routings: the centers visited, setup time, and run time per unit. Include work from planned orders and existing released orders, placed in the periods when that work is due.
Use comparable hours
Utilization is the share of available time spent working on production. Efficiency compares standard hours earned with actual worked hours. Two welders, eight hours a day for five days, provide 80 labor-hours. At 90% utilization, 72 are worked. At 95% efficiency, rated output is 68.4 standard hours. Compare that with loads stated in standard hours, not directly with clock hours.
For one order:
Setup is charged once per batch visiting the center. Run time rises with quantity.
Read a load report
Base orders of 60, 20, and 70 units are released in weeks 3, 4, and 5. Each batch needs 1.5 standard setup hours plus 0.6 standard hours per unit. Other items contribute 30, 25, and 40 standard hours.
| Week | Base load | Other load | Total | Percent of 68.4 |
|---|---|---|---|---|
| 3 | 37.5 | 30 | 67.5 | 98.7% |
| 4 | 13.5 | 25 | 38.5 | 56.3% |
| 5 | 43.5 | 40 | 83.5 | 122.1% |
Week 5 is 15.1 standard hours over capacity; week 4 has 29.9 spare. Average load across the weeks would hide the overload.
Change capacity or move work
Overtime, another shift, an alternate center, or subcontracting can add capacity. Releasing earlier, splitting lots, changing lot sizes, or revising the MPS can move or reduce load.
Split the week-5 base batch into 30 extra bases in week 4 and 40 in week 5. Week 4 now has its original 20-base batch plus a separate 30-base batch: 13.5 + 19.5 + 25 = 58.0 standard hours. Week 5 needs 1.5 + 0.6 × 40 + 40 = 65.5. Both fit, at the cost of one extra setup and a week of holding 30 bases.
A load profile displays these period loads against capacity. CRP reports overloads using infinite loading; it does not automatically resolve them or sequence jobs. Feedback must lead to a revised, checked plan.
Key Takeaways
- RCCP checks key MPS resources; CRP checks detailed MRP work-center loads.
- Convert available clock hours to standard-hour capacity using utilization and efficiency.
- Order load includes a setup plus run time for every unit.
- Check each period, since spare hours later do not resolve an earlier overload.
- Splitting or moving work can add setups and inventory costs.
- CRP identifies overloads; planners must choose and check remedies.
5.2 Connect planning through MRP II and ERP
Planning systems widened as companies needed to connect material calculations with resources, money, and execution. The distinction between the systems is the scope of the decisions and information they connect.
Follow the widening scope
| System | Main addition |
|---|---|
| MRP | Calculate material quantities and dates |
| Closed-loop MRP | Add capacity checks and feedback from execution |
| MRP II | Integrate manufacturing resources, finance, S&OP, and what-if planning |
| ERP | Connect processes across the enterprise |
MRP developed in the 1960s and spread widely in the 1970s. The term ERP came into use around 1990. MRP II means manufacturing resource planning; it connects labor and other manufacturing resources with financial consequences. In a closed loop, actual receipts, output, and capacity performance feed back so the plan can be corrected.
Follow one transaction
An enterprise resource planning (ERP) suite links modules through a shared database. Core areas include sales and order management, purchasing, inventory, manufacturing planning, distribution, finance, and human resources.
A customer orders 50 chairs. Order entry checks ATP and confirms the date. Inventory is reserved; planning updates requirements; purchasing acts on proposed supply orders. Production releases work, the warehouse records shipment, and accounting issues the invoice and updates receivables and the general ledger. The same order identity and quantities remain visible through the process.
This integration reduces separate re-entry. A receipt entered by the warehouse can update purchasing's open quantity and inventory's stock position, giving finance the same transaction basis. A common database reduces conflicting records, but an incorrect entry can still spread incorrect information.
Weigh benefits and drawbacks
Shared data improves order and inventory visibility, reduces re-keying errors, supports consistent processes, and can speed financial closing. It gives S&OP more timely information about actual demand, supply, and costs.
The drawbacks include high cost, long and risky projects, process changes required by standard software, difficult upgrades after extensive customization, and continued dependence on data quality. Integration cannot compensate for unrecorded scrap or an unrealistic supplier lead time.
ERP also supports service organizations. A university can connect purchasing, supplies, staffing, and finance. A hospital can link scheduling information with staffing and supply needs. Manufacturing modules are relevant only where the organization's processes need them.
Distinguish software from decisions
An on-premises system runs on company-managed servers. Cloud ERP delivered as software-as-a-service (SaaS) is subscription software operated and updated by the vendor. ERP may also connect with customer relationship management, supply chain management, and e-commerce systems.
ERP contains MRP as one planning function; its enterprise scope is broader. It calculates and shares information, while people agree on the S&OP plan, set commitments, review the master schedule, and act on exceptions. A proposed purchase order becomes an actual commitment through the organization's release process.
Key Takeaways
- Closed-loop MRP adds capacity and execution feedback to materials planning.
- MRP II connects manufacturing resources and their financial consequences.
- ERP links enterprise processes through shared data.
- Integration reduces duplicate entry but still depends on accurate transactions.
- People retain planning choices and responsibility for acting on exceptions.
Aggregate Planning examples
1Agree on one demand and supply plan
11 steps
- 1IntroductionStart with a decision that needs several teams
Sales expects a peak in four months. Operations can meet it with overtime or an earlier inventory build, while finance wants less cash tied up in stock. Each team sees part of the decision.
Follow how the planning hierarchy places that choice, then use S&OP to turn the competing views into a common operating plan.
- 2ExplanationPlace the decision on the right horizon
Long-range planning chooses basic capacity, such as facilities and major equipment, usually more than a year ahead. Intermediate planning, often 3–18 months, chooses how to use that capacity. Short-range planning assigns specific jobs and people in the coming weeks and days.
A four-month choice between overtime and stored output belongs to aggregate planning. Building a new plant belongs to a longer-range decision.
- 3ExampleUse a family total before choosing each model
A maker plans 1,200 road bikes in March. The family shares assembly resources, so its combined volume helps estimate the workforce and hours required.
The MPS later splits that total into 300 small, 500 medium, and 400 large bikes by week. Those quantities reconcile to 1,200. MRP then calculates their parts, and short-term schedules assign the jobs.
- 4ChallengeSort out an overloaded planning meeting
A monthly meeting spends most of its time deciding which customer order will run first on a machine tomorrow. Its family demand and staffing gaps remain unresolved. What planning levels have become confused?
---reveal---
Tomorrow’s job assignment is short-range scheduling. The S&OP meeting needs to resolve family volume, supply, and financial trade-offs, leaving detailed job sequencing to the appropriate scheduling process.
- 5ExplanationBuild the monthly decision sequence
Start with updated actual sales, production, inventory, and forecasts. Demand review adds market knowledge; supply review checks resources and develops responses. Reconciliation compares those responses with the financial plan.
The executive meeting chooses among unresolved trade-offs and approves one plan. Meeting names vary, but the work must end in decisions with owners, not only a refreshed report.
- 6ExampleRead a make-to-stock gap
A family starts with 500 units, plans to make 1,100, and expects sales of 1,250. Projected ending inventory is 500 + 1,100 − 1,250 = 350 units.
The target is 400, leaving a 50-unit gap. Supply review can test 50 more units of production; reconciliation can compare that response with accepting lower stock. The target is not extra customer demand.
- 7ConnectionTrack waiting orders in make-to-order
A make-to-order operation tracks backlog: beginning orders waiting + new orders − shipments. Beginning backlog of 180, new orders of 900, and shipments of 950 leave 130 units waiting.
A growing backlog can extend delivery times. A sustained decline can leave future capacity idle. Reading backlog alongside available capacity helps the team see both customer delay and the approaching workload.
- 8ExampleTranslate sales into a financial gap
A plan to sell 1,200 units at an average price of $250 produces $300,000 revenue. The budget expects $330,000, so the gap is $30,000.
Producing more stock does not itself create revenue. The team needs additional sales that supply can support, another commercial response, or a revised financial forecast. This is why finance participates before the plan is approved.
- 9ChallengeConnect the stock target with the revenue target
A family expects sales of 1,000 units at $90, against a $99,000 revenue target. Supply can make 1,100 units, but demand review still supports only 1,000 sales. Does producing all 1,100 close the revenue gap?
---reveal---
No. Sales still produce $90,000 revenue, leaving $9,000 short. The extra 100 units increase inventory. Reconciliation must address the demand or financial gap as well as the feasible output volume.
- 10TipKeep the horizon useful
Roll the plan forward each month: replace the completed period with actuals, update future assumptions, and add a new far period. Review forecast accuracy, plan attainment, stock or backlog, and delivery performance.
Keep forecasts distinct from targets. If actual output is 1,140 against 1,200 planned, attainment is 95%; the next question is what caused the gap and which future decisions need to change.
- 11RecapCarry the agreed volume into detailed planning
The family plan now has a demand view, a supply response, and a financial interpretation. Leaders can approve a common volume plan, while planners turn it into products and dates.
That handoff works when the MPS reconciles with family totals and returns material or capacity constraints for review before they become delivery failures.
2Build chase, level, and mixed plans
20 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionFollow one demand peak through several plans
- 2ExplanationChoose where flexibility will come from
- 3ExplanationDistinguish the three strategies
- 4ExampleUse booking times as a demand lever
- 5ChallengeChoose a response for nonstorable output
- 6ExampleOrganize the pump data
- 7ExampleFind the chase workforce
- 8ExampleAdd paid labor and workforce-change costs
- 9ChallengeNotice the first workforce change
- 10ExplanationFind a level rate that meets the ending target
- 11ExampleCarry level inventory through the peak
- 12ExampleCost the level plan
- 13ChallengeCheck the early months as well as the total
- 14ExampleTest a smaller core team
- 15ExampleBuild a mixed workforce plan
- 16ExamplePrice the mixed plan
- 17ChallengeDecide whether the cheapest plan is usable
- 18ExampleChange the holding rate
- 19ConnectionKnow what the comparison proves
- 20RecapCarry a defensible plan into S&OP
3Turn family volume into products and parts
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionAdd the detail customers and production need
- 2ExplanationSchedule the right item for the business
- 3ExampleBuild the first projected balances
- 4ExampleContinue the schedule through higher demand
- 5ExplanationCalculate uncommitted supply
- 6ChallengeMake a promise that respects the date
- 7TipProtect the schedule without confusing the fences
- 8ExplanationRead one chair’s structure
- 9ExampleAllow for completed assemblies before multiplying
- 10Key InsightGather shared-part demand before netting
- 11ChallengeNet a different product structure
- 12ExampleWork backward along the longest path
- 13ChallengeConnect the promise with the product lead time
- 14RecapPass a dated and netted plan to MRP
4Calculate MRP orders and compare lot rules
19 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionSeparate the shortage from the proposed order
- 2ExplanationRead the record in order
- 3ExampleCarry stock through weeks with existing supply
- 4ExamplePlan the receipts and move their releases back
- 5ChallengeMake the safety-stock target part of netting
- 6ConnectionCreate component demand at the production start
- 7ExplanationChoose what an order should cover
- 8ExampleCalculate a fixed EOQ
- 9ExampleUse the EOQ to choose an interval
- 10ExampleBalance carrying exposure against one setup
- 11ChallengeCount every period a unit waits
- 12Key InsightRecognize the optimal model and its limits
- 13ExplanationMaintain the facts behind the calculation
- 14ExampleUse pegging to prioritize a shortage
- 15TipStabilize what needs to stay committed
- 16ChallengeRespond to an early requirement
- 17ConnectionCarry time-phased logic beyond the factory
- 18ChallengeFollow a parent change all the way down
- 19RecapTake a checked proposal to execution
5Check the hours and connect the systems
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionTest whether the plan can actually be done
- 2ExplanationChoose the capacity check for the plan
- 3ExampleConvert available time into rated output
- 4ExampleAdd batch setup and run time
- 5ExampleMove work and include the extra setup
- 6ChallengeTest a proposed capacity remedy
- 7Key InsightTreat the load report as a signal to act
- 8ExplanationFollow the expanding scope of planning systems
- 9ExampleFollow an order through shared records
- 10ChallengeFind the limit of integration
- 11ConnectionApply enterprise integration in services
- 12ChallengeConnect a shop-floor delay with the business promise
- 13RecapClose the loop with a revised commitment
Aggregate Planning practice questions
Set 1: Practice 1: Read the plan and calculate the next step10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Practice 2: Trace quantities, costs, and commitments10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Practice 3: Diagnose the constraint and revise the plan10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Practice 4: Test decisions across the planning chain10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Action notice
Aggregate planning
Available-to-promise (ATP)
B
Backorder
Backorder cost
Bill of materials (BOM)
BOM explosion
Bucketless planning
C
Capacity requirements planning (CRP)
Chase strategy
Closed-loop MRP
Counterseasonal mixing
Cross-training
Cumulative demand
Cumulative lead time
Cumulative supply
Cycle counting
D
Demand review
Demand time fence
Dependent demand
Disaggregation
Distribution requirements planning (DRP)
E
Economic order quantity (EOQ)
Economic part period
Efficiency
Enterprise resource planning (ERP)
F
Feasible plan
Final assembly schedule
Firm planned order
Frozen zone
G
Gross requirements
H
Holding cost
I
Independent demand
Integrated business planning (IBP)
Inventory balance
L
Lead-time offsetting
Level production rate
Level strategy
Linear programming
Liquid zone
Load profile
Long-range planning
Lot sizing
Lot-for-lot (L4L)
Low-level code
M
Manufacturing resource planning (MRP II)
Master production schedule (MPS)
Material requirements planning (MRP)
Mixed strategy
Modular BOM
N
Net requirements
Net-change MRP
O
On-premises ERP
Order backlog
Order modifier
P
Paid idle time
Part period balancing (PPB)
Pegging
Period order quantity (POQ)
Phantom BOM
Plan attainment
Planned order receipt
Planned order release
Planning BOM
Planning horizon
Planning time fence
Product family
Projected available balance (PAB)
Q
Quantity per
R
Rated capacity
Reconciliation
Regenerative MRP
Regular-time production
Revenue management
Rolling horizon
Rough-cut capacity planning (RCCP)
Routing
S
Safety lead time
Sales and operations planning (S&OP)
Scenario
Scheduled receipt
Sensitivity analysis
Setup cost
Shared database
Short-range planning
Slushy zone
Software-as-a-service (SaaS)
Standard hour
Subcontracting
Supply review
System nervousness
T
Transportation model
U
Utilization
W
Wagner–Whitin algorithm
Worker-month
Workforce balance
About this lesson
Make your own Study Materials
Turn your notes, slides and documents into Study Guides, Practice Questions, Flashcards and 6 more tools.