Lean Operations
IntermediateLesson 9 of 9 in Operations Management Course
What you will learn
- Describe how the Toyota Production System grew into lean thinking, and use the five lean principles to separate work that creates value from work that does not.
- Trace lean back to the Toyota Production SystemExplain why Toyota built a different production system from mass production, name its two pillars and its foundation, and describe how the word lean spread.
- Apply the five lean principles and classify activities by valueDefine value from the customer's point of view, use the five lean principles in order, and sort activities into value-adding, necessary and pure waste.
- Trace lean back to the Toyota Production System
- Recognize the eight wastes in factories, offices and services, and trace them back to unevenness, overburden and the problems that inventory hides.
- Spot the eight wastes in factories and servicesName and recognize each of the eight wastes in manufacturing and service settings, and tell apart wastes that are easily confused.
- Trace waste back to unevenness, overburden and hidden problemsExplain how unevenness and overburden cause waste, why inventory hides problems, and how reducing inventory shortens lead time.
- Spot the eight wastes in factories and services
- Draw a current-state value stream map, calculate takt time, lead time and flow efficiency from it, and design a future state that flows to customer demand.
- Draw a current-state value stream mapChoose a product family, walk its material and information flows, and record them with standard symbols and data boxes.
- Calculate takt time, lead time and flow efficiencyCompute takt time, inventory in days, value-adding time, process cycle efficiency and staffing for a value stream, and interpret what the numbers show.
- Design the future state of a value streamUse the future-state questions to link processes by flow and pull, choose a pacemaker, level the work and plan the improvements needed.
- Draw a current-state value stream map
- Explain just-in-time and pull, cut setup times so small lots pay off, level the production schedule and size a kanban system that controls inventory.
- Explain just-in-time and the difference between push and pullDescribe just-in-time production, contrast push and pull control, and identify what a just-in-time system needs from suppliers, layout and people.
- Cut setup times so small lots pay offExplain why lean wants small lots, how setup cost drives lot size, and how the SMED method shortens changeovers.
- Level production with heijunkaLevel the volume and mix of production over time, build a mixed-model sequence from daily demand, and explain what leveling requires.
- Size and run a kanban systemDescribe how kanban signals control production and movement, apply the rules of kanban, and calculate how many kanbans a loop needs.
- Explain just-in-time and the difference between push and pull
- Organize workplaces with 5S and visual management, and build quality in through standard work, jidoka and poka-yoke.
- Organize the workplace with 5S and visual managementApply the five steps of 5S to a workshop or office and use visual controls that show at a glance whether work is normal.
- Build quality in with standard work, jidoka and poka-yokeWrite standard work as the baseline for improvement, stop at abnormalities with jidoka and andon, and prevent errors from becoming defects with poka-yoke.
- Organize the workplace with 5S and visual management
- Lead improvement with kaizen, adapt lean tools to service operations and judge where lean works well and where it needs adjusting.
- Run kaizen with PDCA, the five whys and kaizen eventsUse the PDCA cycle and the five whys to solve problems at their root, and plan a kaizen event and daily improvement in a team.
- Apply lean in service operationsAdapt lean principles and tools to services such as banks, hospitals and restaurants, and allow for the customer's role in the process.
- Judge where lean works and where it needs adaptingAssess whether lean fits an operation, weigh its supply risks and environmental effects, and measure progress toward a lean operation.
- Run kaizen with PDCA, the five whys and kaizen events
Lean Operations study guide
1Where lean comes from and how value flows
Lean connects customer value, smooth flow and the people who improve the work. Start with the conditions that led Toyota to develop its production system, then use the five principles to examine a process. A customer visit and a small production line show how much time can pass without value being added. You will learn to distinguish useful transformation, necessary support and waste before choosing an improvement.
1.1 How Toyota shaped lean operations
Lean operations aim to deliver what customers value with less waste of time, materials, effort and space. The tools work together: small lots depend on fast changeovers, pull depends on reliable replenishment, and improvement depends on people who can raise problems.
Why Toyota needed a different system
Henry Ford's moving assembly line of 1913 made mass production famous. Long runs of a standard product spread costs over many units. Specialized machines and stocks between steps helped keep each department busy. After the Second World War, Toyota faced a smaller home market with demand for many models in low volumes. Capital and space were scarce. Long runs of one model would tie up resources in vehicles customers did not yet want.
Toyota developed a way to make small quantities of different models efficiently. Sakichi Toyoda's 1896 power loom stopped when a thread broke; his Type G automatic loom followed in 1924. Stopping at a problem became jidoka, building quality into the process. Kiichiro Toyoda promoted making parts just in time. From the late 1940s, Taiichi Ohno developed the production system on the shop floor with Eiji Toyoda's support.
The TPS house
The Toyota Production System, or TPS, is often shown as a house. Its roof is the goal: high quality, low cost and short lead time. Two pillars hold it up:
- Just-in-time means making what is needed, when it is needed, in the amount needed.
- Jidoka means detecting an abnormality, stopping and dealing with it before defects spread.
The foundation is stable, leveled production, standardized work and continuous improvement. A pull signal cannot keep deliveries on time if machines repeatedly fail. A standard cannot improve if nobody is allowed to question it. These connections explain why copying a tool in isolation often disappoints.
People make the system improve
Toyota's management approach links continuous improvement with respect for people. Employees help improve their own work, and suppliers participate in long-term relationships. An operator who reports an awkward fixture contributes knowledge that a distant manager may miss. Using productivity gains to threaten jobs damages the trust needed to keep finding problems.
John Krafcik used the word lean in his 1988 article, “Triumph of the Lean Production System,” from MIT's auto-industry research. Womack, Jones and Roos brought it to a wider audience in The Machine That Changed the World in 1990. Womack and Jones extended its application in Lean Thinking in 1996.
See the system in a daily schedule
A plant may switch from one monthly run of each of three models to making some of every model each day. Short changeovers make that possible. Smaller lots reduce waiting inventory and reveal quality problems sooner. Workers need training and authority to respond when those problems appear. Lean reaches beyond car plants to hospitals, banks and public offices; each setting starts with its own customer's needs.
Key Takeaways
- TPS links just-in-time with quality built into the process.
- Stable work, leveling and continuous improvement support both pillars.
- Toyota developed small-lot production to serve varied demand with scarce resources.
- Respect for people supports the reporting and solving of problems.
- Lean improvements change how the whole operation works.
1.2 Value, flow and the five lean principles
A process can keep everyone busy while making the customer wait. Lean begins by defining what the customer wants from the product or service, then examining every action needed to deliver it.
Start with value
Value comes from the customer's point of view: what they are willing to pay for, at the right time and price. A patient values a sound diagnosis and effective treatment. Waiting for a room does not create either. Adding a feature that customers never use consumes resources without meeting a need.
Apply the five lean principles in order:
- Specify value: understand the customer's need.
- Identify the value stream: follow all the actions needed to meet it.
- Make value flow: reduce stops between those actions.
- Let the customer pull: let real use authorize more work.
- Pursue perfection: repeat the improvement cycle as new waste becomes visible.
Classify the work
An activity is value-adding only when the customer is willing to pay for it, it changes the product or service in form, fit or function, and it is done right the first time. Reworking a faulty weld consumes effort but fails the third test.
Necessary non-value-adding work adds no customer value but cannot yet be removed because of law, current technology or policy. Invoicing and a required inspection are examples. Reduce the effort involved while preserving what is required. Pure waste, such as searching or avoidable waiting, has no necessary purpose and should be removed.
Work through a customer visit
At a tire service center, a visit includes 10 minutes at the counter, 4 entering details, 25 waiting for a bay, 3 lifting the car, 12 removing and fitting the tire, 5 balancing, 2 checking torque and 4 paying. Total time is 65 minutes. Fitting and balancing add value, totaling 17 minutes. Lifting enables the work but does not itself change what the customer buys, so it is necessary non-value-adding work.
The value-adding share is:
The 35 minutes of waiting are a much larger opportunity than trying to rush the fitting work. The classification directs attention to what delays the customer.
Why smaller transfers improve flow
Consider 10 parts passing through three staffed steps, each taking 1 minute per part. If a whole batch must finish a step before moving, the first finished part emerges after 21 minutes; all 10 finish after 30. With one-piece transfers, the first part finishes after 3 minutes and the tenth after 12. The processing tasks have not become faster. Parts spend less time waiting for their batch.
Pull connects this flow to actual need: a downstream step signals what it has used, and the upstream step replaces it. Producing more to keep an already faster machine busy creates inventory for the next step. Judge the change by customer delivery and total flow, not by the apparent busyness of one department.
Key Takeaways
- Value-adding work must meet all three tests, including being right the first time.
- Shrink necessary non-value-adding work and remove pure waste.
- The five principles run from customer value through repeated improvement.
- Small transfers shorten waiting even when task times stay unchanged.
- Pull lets actual need authorize production.
- Local busyness can create waste elsewhere.
2Find waste and its causes
Waste appears in travel, queues, duplicate work and errors, but its causes often lie elsewhere. Learn to name what you see, measure the loss and follow it back to uneven work or unreliable processes. The eight wastes provide a practical observation checklist. The three Ms and Little’s law then explain how load, inventory and lead time connect, so a team can remove causes while maintaining dependable delivery.
2.1 Recognizing the eight wastes
Waste uses resources without adding value for the customer. Taiichi Ohno identified seven wastes; many lean approaches add unused human talent as an eighth. The mnemonic TIMWOODS helps you scan work systematically.
Follow the item and the person
Transport is unnecessary movement of materials, products or information. Sending a file through several departments or moving a pallet through a temporary storage area adds handling without changing the output.
Inventory is stock beyond the next step's need: raw material, work in progress, finished goods or uncompleted service cases. It occupies space, ties up resources and can become obsolete. An application backlog is inventory even when no physical product exists.
Motion is unnecessary movement by people, including walking, bending, reaching and searching. A technician fetching a tool 30 m away 12 times walks 360 m outward and another 360 m back. Moving the tool to its point of use removes 720 m of travel per shift. Distinguish the person moving from the item being transported.
Waiting is delay when people, machines or work items cannot proceed. Missing information can leave a case waiting just as missing parts can stop an assembly line. Inventory describes how much work is held; waiting describes its delay. A queue can show both.
Look for work made too soon or done twice
Overproduction means making more, earlier or faster than needed. It generates other waste: the excess must be stored, moved and counted, and defects may stay hidden in it. Printing unread reports is overproduction in a service setting.
Overprocessing means doing more work or using more precision or complexity than the requirement needs. Polishing a hidden surface, reentering the same customer details and requiring redundant approvals are examples. Overproduction concerns unwanted output; overprocessing concerns unnecessary work on an output.
Defects are failures to meet requirements, bringing scrap, correction, rework and inspection effort. A wrong invoice and an incorrectly assembled part both create extra work. Finding a defect late also wastes the work added since the defect arose.
Skills, or unused talent, means failing to use people's knowledge and ability. Operators may know why parts jam but never be asked. Skilled nurses may spend hours repeating clerical entries. This waste also weakens the team's ability to remove the others.
Diagnose a work area
In a warehouse, fast-moving items stored at the far end make pickers walk unnecessarily: motion. Moving pallets from receiving to a buffer and then to racks adds transport. Orders held for two hours create waiting, and the stack of held orders is inventory. A supervisor repeating a check already completed reliably by a scanner adds overprocessing.
Name the waste precisely enough to choose a useful change. Moving the pallets fewer times addresses transport. Releasing work in smaller, steadier amounts addresses the order queue. Asking pickers to design storage locations draws on their knowledge as well as reducing motion. A single observation may reveal several linked wastes, so record the quantity or time lost alongside each one.
Key Takeaways
- TIMWOODS names transport, inventory, motion, waiting, overproduction, overprocessing, defects and unused skills.
- Motion concerns people; transport concerns items or information.
- A queue is inventory whose time in the queue is waiting.
- Overproduction creates stock and further handling.
- Unused talent limits improvement across the other wastes.
2.2 Uneven work, hidden problems and lead time
Visible waste often has an upstream cause. Work may arrive in large peaks, equipment may be unreliable, or a buffer may hide a recurring failure. Removing the visible pile without understanding its cause can interrupt deliveries.
Connect the three Ms
Waste, or muda, consumes resources without adding value. Unevenness, or mura, means swings in volume or product mix. Overburden, or muri, pushes people or equipment beyond what they can sustain safely and reliably.
Unevenness can create both other problems. A peak brings overtime, rushed handling and overloaded machines. A trough leaves the same resources waiting. A packing team releases 2,000 weekly orders as 700 on Monday, 300 on each of Tuesday through Thursday and 400 on Friday. Releasing 400 a day gives the same weekly total with a steadier load, where customer timing allows that release pattern.
Variability also comes from breakdowns, missing staff, poor supplies and unclear requirements. Operations absorb it through extra inventory, spare capacity or extra time. Reducing the cause makes less protection necessary. Simply demanding higher output leaves the variability in place.
Lower the water and remove the rocks
In the rocks and water analogy, inventory is the water in a river and problems are submerged rocks. High water lets the boat pass over breakdowns, long setups and late deliveries. Lower water reveals those problems.
Inventory should come down in controlled steps while the team removes each exposed cause. If a machine frequently fails, maintain it and improve reliability as the buffer shrinks. Removing the whole buffer first can leave the next process with no work. Conversely, adding stock every time the failure returns protects today's output but leaves tomorrow's failure likely.
Use Little's law to see the effect
For a stable flow, Little's law relates averages:
A process holds 600 units and finishes 120 per working day. Its average lead time is 5 working days. If work in progress falls to 300 while throughput stays at 120 per day, lead time becomes 2.5 days. The units spend less time waiting; no task needs to be performed twice as fast.
Keep the rate and time units aligned. Dividing units by units per day gives days. Use average values over a representative period, so a one-time inventory count does not stand in for an unstable month.
Remove the cause and hold the gain
Go to the work, identify the waste and measure it. Investigate why it occurs, try a change that removes the cause, and make the successful method standard. A rework station may clear faulty output but does not prevent the original defect. Likewise, speeding a machine that already outruns its downstream neighbor builds a larger queue without raising the value stream's output. Check the whole flow when deciding whether an improvement helped.
Key Takeaways
- Unevenness can produce both overload and idle time.
- Reduce the causes of variability as buffers come down.
- Little’s law links average work in progress, throughput and lead time.
- Faster nonbottleneck work can increase queues without increasing output.
3Map and improve the value stream
A value stream map brings customer demand, process performance, inventory and scheduling onto one page. First record the current work and its information flow. Then calculate the required pace, the delays and the staffing lower bound. Use those findings to design a future state with continuous flow, controlled pull links and one scheduled pacemaker, supported by an improvement plan with clear ownership.
3.1 Reading the current value stream
A value stream map follows a product family or a service case from request or receipt to customer delivery. It shows both material flow and the information that tells each process what to do. This wider view reveals delays that a detailed map of one department can miss.
Choose and observe a family
A product family follows similar steps through shared equipment. Map one family at a time, initially from receiving to shipping. Mixing every product on one map makes different routes and requirements hard to see. Assign an owner for the whole value stream because its delays cross departmental boundaries.
Walk the actual route. Start at shipping and work upstream toward receiving, asking what each step needs from its supplier. Count inventory, time work and check actual delivery frequency. Planning-system times are useful background, but direct observation shows how work is running now. Mike Rother and John Shook presented this method in Learning to See in 1998.
Put flow and control on the page
Use customer and supplier icons at the top corners. Draw a process box for an area where material flows continuously; start another where flow stops and stock builds. Under each process, add a data box with observed cycle time, changeover time, uptime, staffing, shifts, net available time, batch size and scrap rate.
Changeover time measures the switch between products. Uptime is the percentage of planned time when the equipment is available to run.
An inventory triangle, marked “I,” records a counted quantity. Striped push arrows show material sent onward without a downstream pull signal. Truck icons show deliveries and their frequency. A timeline along the bottom separates waiting from processing.
Across the top, trace information from customer orders and forecasts through production control to the processes. Straight narrow arrows represent manual messages; zigzag arrows represent electronic messages. Independent schedules sent to every department explain why one process can keep building while the next has no room.
Keep four clocks separate
Cycle time is the observed interval between units leaving a process. Value-adding time measures the time spent changing the product or service in ways the customer values. Lead time measures one unit's complete journey, including waiting. Takt time is net available working time divided by demand: the completion interval required by the customer.
Suppose a process releases one unit every 50 seconds, while each unit waits two days before the next process. The 50 seconds describes cycle time, not the unit's two-day delay. Nor does a fast machine set takt: customer demand does that.
Let the map reveal the next decision
A map with large triangles and short processing times points toward waiting and inventory. A map with many separate schedules points toward push control. A long changeover may explain why a process releases large batches. Record these relationships before selecting tools.
Key Takeaways
- Map one product family and both material and information flows.
- Observe actual times and quantities where work happens.
- Data boxes explain the performance behind the flow symbols.
- Cycle time, value-adding time, lead time and takt answer different questions.
- Use the current map to locate causes and design the future state.
3.2 Calculating the pace and delays of a value stream
A map's numbers connect customer demand to the work and inventory needed to meet it. Begin with one consistent period and keep time units aligned. Then distinguish the pace required from the performance actually observed.
Find takt and compare capacity
A bracket plant runs two shifts of 450 net minutes each. Daily time is 54,000 seconds; daily demand is 900 brackets. Takt is 60 seconds per bracket. Net time excludes planned breaks and meetings. Unplanned downtime is assessed separately, so it is not silently removed to make the demand pace easier.
A cycle longer than 60 seconds cannot sustain this demand. A 54-second machine appears fast enough, but at 85 percent uptime its effective interval over planned time is:
That process needs better availability or more capacity. Faster nominal operation alone has not solved the shortfall.
Turn stock into time
At 900 brackets per day, raw stock for 9,000 brackets represents 10 days. Stocks of 4,500 before welding, 1,800 before assembly and 2,700 finished brackets represent 5, 2 and 3 days. Their total waiting is 20 working days. Production lead time also includes processing, though a few seconds add little at this scale.
Stamping, welding and assembly add 2, 48 and 54 seconds of value-adding time, totaling 104 seconds. To compare this with lead time, convert the 20 working days using 54,000 available seconds per day:
This is about 0.01 percent. The calculation uses working-time units throughout. Most elapsed production time is waiting, so shaving a few seconds from assembly has much less effect on lead time than removing days of stock.
Staff and release work to demand
The theoretical operator requirement is total operator work content per unit divided by takt, rounded up. Include loading, walking and unloading; unattended machine time is not operator work. A 150-second work content at 60-second takt gives 2.5, so three operators are needed if the work can be balanced. Removing 30 seconds of waste reduces the requirement to two.
Pitch gives the release interval for a container:
A pack of 20 at 60-second takt gives 1,200 seconds, or 20 minutes. This lets production control release and collect a small increment of work regularly. Halving the 4,500-part queue saves 2.5 days at unchanged demand; compare that gain with the 10 seconds saved by cutting assembly from 54 to 44 seconds.
Key Takeaways
- Calculate takt from customer demand and net planned working time.
- Check uptime before deciding that cycle time meets takt.
- Convert inventories into days and add processing for total lead time.
- Flow efficiency uses value-adding time and lead time in matching units.
- Staffing uses operator work content, with whole people rounded up.
- Pitch sets a container-sized work interval.
- Reduce the largest delays when the aim is shorter lead time.
3.3 Designing flow, pull and the pacemaker
A future-state map describes a better flow that the team can reach within a defined period, often a year. Design it from customer demand and the current process data. Each production link should support continuous flow or respond to a downstream need.
Work through the design questions
Find takt first. Decide whether to ship directly or from a finished-goods supermarket. Identify where continuous flow can work and where a pull link is needed. Choose the single scheduled process, then decide how to level its product mix and release work at a regular pitch. Finally, name the process improvements that make the design possible.
Use continuous flow between reliable processes with compatible cycles. A cell combining welding and assembly can pass one bracket at a time. Where direct flow is impractical, a supermarket holds a controlled stock of standard parts. Downstream withdrawal authorizes replacement upstream.
A distant supplier, a shared press or a process with long changeovers may need that separation. For custom work, a FIFO lane can hold a fixed maximum quantity in first-in, first-out order. The supplying process stops when the lane is full. Do not place stock between processes that could flow together.
Schedule one point
The pacemaker receives the production schedule and sets the pace for the value stream. It is usually near the customer end. Work downstream flows toward shipping; upstream processes replenish what the pacemaker consumes. Separate schedules at every process can conflict and rebuild push between departments.
The pacemaker is a control choice, while a bottleneck is a capacity constraint. Identify the actual capacity problems as well as deciding where to schedule.
Build a practical future state
In the bracket plant with 60-second takt, combine welding and assembly. Measured operator work content is 110 seconds per bracket, including handling and walking but excluding unattended machine running. The staffing lower bound is:
Round up to two operators and check that the sequence can be balanced so each can finish within takt. A total below two takt intervals does not by itself establish a workable split.
Plan a one-day finished-goods supermarket, 1.5 days of stamped parts and two days of raw material supplied daily. Waiting falls from 20 days to approximately 4.5 days. To support the smaller stamped-parts stock, reduce stamping changeovers from 60 minutes to under 10 so each part can be made daily.
Turn the drawing into work
Mark required improvements as kaizen bursts, such as the changeover reduction or an uptime repair. Divide implementation into loops, starting at the pacemaker. Give each loop an owner, a measurable target and a date, and review progress across departments. A stock target needs a replenishment method that can maintain it. Once the future state is working, it becomes the current state for the next round of improvement.
Key Takeaways
- Use continuous flow where the processes can support it.
- Use controlled supermarkets or FIFO where direct flow is impractical.
- Schedule the pacemaker to coordinate the value stream.
- Check work balance after calculating a staffing lower bound.
- Give every required improvement an owner, target and date.
4Make small-lot pull production work
Just-in-time becomes workable through a connected set of decisions. Pull signals control releases, quick changeovers make small lots economical, and leveling gives upstream processes a steadier load. Kanban translates that design into quantities and replenishment rules. You will connect the control logic to setup economics, a mixed-model sequence and a container calculation that includes the full time needed to replenish.
4.1 Just-in-time and downstream pull
Just-in-time, or JIT, makes and delivers what is needed, at the time and in the quantity needed. It also tackles the problems that make extra stock seem necessary. Pull control is one way to connect that aim to daily decisions.
What authorizes the work?
In push, a process makes its scheduled quantity and sends it onward whether the next process is ready or not. Each department may meet its own plan while work accumulates between them.
In pull, actual downstream use authorizes production or delivery upstream. A card, an empty container, a marked space or an electronic message can carry that authorization. If downstream slows, fewer signals return, so upstream production slows too. The number of circulating signals limits how much work can enter the loop.
For example, a plant shipping 250 units per day with 2,000 units of average work in progress has an eight-day average lead time. If it can sustain the same throughput while limiting work in progress to 500 units, Little's law gives two days. Pull controls releases; process reliability makes the lower limit workable.
Two forms of pull
Replenishment pull replaces standard items after they are used. A supermarket can contain goods before the final customer orders; their withdrawal triggers replacement. Pull therefore does not mean that every part must be produced from scratch after a final order arrives.
Sequential pull serves made-to-order work through bounded FIFO lanes. A custom cake should follow its order, not replenish a shelf of identical cakes. An operation can combine replenishment for frequent standard parts with sequential flow for rare or custom items.
Build the conditions for JIT
Small, frequent deliveries require dependable suppliers and consistent quality. Long-term supplier partnerships help solve delivery and quality problems across the whole route. Simply forcing a supplier to hold the old stock moves the burden without improving the value stream.
Inside the operation, cells shorten travel and help cross-trained employees manage several steps. Fast setups make small lots practical. Leveled schedules give suppliers a steadier load. Preventive maintenance reduces failures, and employees need authority to stop when an abnormality occurs. These conditions support one another: smaller buffers expose failures quickly, while better reliability makes those smaller buffers sustainable.
Judge the outcome across the flow
Lower inventory can free floor space, shorten lead time and reveal defects before many units are made. Small lots can also make it easier to change product mix as demand changes. These gains depend on stable replenishment, not on deleting every buffer at once.
Watch what happens when a downstream process stops. If upstream keeps producing because its schedule says so, the operation is still pushing across that link. A lean response is to follow the pull limit, resolve the problem and restore flow. Keeping a machine busy is a poor reason to make goods the next process cannot yet use.
Key Takeaways
- JIT joins demand-based production with removal of the causes of excess stock.
- Push follows an independent plan; pull responds to downstream use.
- Replenishment pull can hold a controlled stock of standard goods.
- Sequential pull fits custom work through bounded FIFO links.
- Reliable equipment, suppliers and schedules support small buffers.
- Assess suppliers and internal processes as one value stream.
4.2 Quick changeovers and economical small lots
Small lots spend less time waiting and let an operation make each product more often. Long setups make those benefits expensive: every switch consumes machine time and setup effort. Lean reduces that cost so that small lots become practical.
See the lot-size trade-off
For a lot used evenly under steady demand, average cycle stock is half the lot size. A lot of 1,000 gives average stock of 500; a lot of 200 gives 100. This describes stock created by the lot, not any extra safety stock.
The economic order quantity model recalls the trade-off between setup and holding costs:
Here demand per year is , cost per setup is and holding cost per unit per year is . With demand of 12,000, setup cost of $150 and holding cost of $4, the model gives about 949 units. Instead of accepting this lot as fixed, lean asks how to lower the setup cost.
For a target lot of 300, rearrange the relationship:
The lot falls to about one third while setup cost falls to one tenth. Lot size depends on the square root of setup cost, so halving setup cost does not halve the economic lot.
Separate stopped work from preparation
Single-minute exchange of die, or SMED, aims for a changeover below 10 minutes. Shigeo Shingo developed the method around two kinds of work. Internal setup requires the machine to stop. External setup can happen while it runs.
Observe the full changeover and record each element. Separate the two kinds of work, then convert suitable internal tasks to external tasks: fetch tools, prepare paperwork and preheat the next die before stopping. Streamline the remaining stopped work with locating pins, quick clamps, preset heights and safe parallel tasks. Improve external work too, using carts and fixed storage, then write the new method into standard work.
Follow the saved minutes
A press stops for 80 minutes per changeover. Preparing tools, paperwork and the die takes 35 minutes that can occur while the press runs. Moving it outside the stop leaves 45 minutes. Better clamps, preset heights and fewer trial adjustments cut the remaining stop to 9 minutes, about an 89 percent reduction overall.
With 120 minutes available for changeovers each day, the old method allows 1.5 changes on average; the new one allows about 13.3. The team can make smaller lots and return to each product more often. If the press is a bottleneck and output is short, some saved time can instead produce additional units.
Reducing lot size before shortening setup multiplies the number of long stops. Check the available production time and the need for flexibility before changing the schedule. A faster stop is also only part of the gain: inefficient external preparation still consumes people's time and should be improved.
Key Takeaways
- Average cycle stock is half the lot under steady, even use.
- Lower setup cost makes smaller economic lots possible.
- SMED aims for single-digit changeover minutes.
- Move suitable preparation outside the machine stop, then streamline both kinds of work.
- Use saved bottleneck time for flexibility or output according to the need.
4.3 Leveling volume and product mix
A plant can meet weekly totals while giving suppliers and customers an uneven daily experience. Production leveling, or heijunka, spreads volume and product mix over time. Smaller, regular releases reduce the peaks passed upstream.
Level the mix
Suppose a factory makes only model A on Monday and model B on Tuesday. A's parts are needed in a large wave, then not at all. A customer ordering B just after its run may wait until the next cycle. Making some of each model frequently reduces those gaps.
Daily demand is 240 A, 120 B and 60 C, totaling 420 units. With 420 net minutes, takt is one minute per unit. Reduce the demand ratio:
A repeating seven-unit cycle must contain four A units, two B units and one C unit. The sequence “A B A C A B A” meets that mix and spreads the models through the cycle. Repeating it 60 times makes the daily quantities exactly. A short sequence is useful only if changeovers are short enough to support the switches.
Level the volume
Volume leveling produces at the average demand rate while a planned finished-goods buffer absorbs short swings. If orders vary between 380 and 460 around a 420 daily average, producing 420 daily gives a steadier load. On a 460-order day, stock supplies the difference; on a 380-order day, stock can recover.
The plan must follow the real average. A sustained increase is a reason to reset the level, not to keep building at an outdated rate. Buffer size and replenishment need to support the actual variation. Leveling smooths the production response without changing what customers ordered.
Release work at regular intervals
A heijunka box has rows for products and columns for pitch intervals. Cards in its slots show what the pacemaker should make in each interval. A material handler takes one pitch of cards at a time, so a daily plan becomes small, regular work releases.
For a 20-minute pitch, the board gives the team a clear checkpoint every 20 minutes. It also makes an empty slot or missed interval visible. The aim is a steady pattern of production and withdrawal, which upstream processes can replenish predictably.
Protect the workable sequence
Leveling depends on fast changeovers, reliable work and a short frozen schedule period. Continually replacing the next slot with an urgent request sends instability back to suppliers. A frozen period protects the immediate sequence while later slots can be revised as demand changes.
Do not confuse an equal mix with a leveled mix. Making A, B and C in equal quantities would miss the 4:2:1 demand. Leveling keeps the required proportions and spreads them across time. Volume and mix must both be considered: a daily total can be smooth while large model batches still create parts shortages and long waits.
Key Takeaways
- Heijunka levels both volume and product mix.
- A repeating sequence must preserve demand proportions.
- A planned buffer can absorb short demand swings around the level rate.
- Fast setups and a short frozen period support a stable sequence.
4.4 Signals and container counts in a kanban loop
A kanban is a signal authorizing a fixed quantity of a particular item to be made or moved. A card is common, but an empty container, marked space or electronic message can perform the same control function.
Follow one replenishment loop
A downstream process takes a full container from a supermarket. The returned production signal tells upstream to replace exactly that quantity. The full replacement returns with its identification. A production kanban authorizes making; a withdrawal kanban authorizes moving goods. In a two-card system, withdrawing a container returns its production card while a withdrawal card travels with the goods. A signal kanban triggers a batch when stock reaches a set level at a process with long changeovers.
A two-bin system is a simple loop: consume the first bin, use its empty state to trigger replenishment, and work from the second bin while the first is refilled. Replenishment must finish before the covering stock is used up.
Keep authorization disciplined
Downstream withdraws only the specified item and quantity. Upstream makes only the authorized item, quantity and sequence. Nothing is produced or moved without its signal. Goods retain their kanban identification, and defects or incorrect quantities do not pass downstream. Reduce the number of signals carefully as the process improves.
Extra production to keep a machine busy breaks the limit. A lost card can cause a shortage because it removes authorization from circulation. Adding cards to cover every recurring delay increases inventory without removing the delay.
Size the loop
Use the full replenishment lead time: signal travel, waiting, production or delivery, and the return of the full container.
Round up to a whole container. At 480 units per day and two days' replenishment, demand during lead time is 960 units. Half a day's safety stock adds 240. With 60 per container, the loop needs 20 kanbans.
The safety-factor form gives the same result:
Here is demand per day, is full replenishment time in days, and is units per container. The safety factor is . The factor is a fraction of demand during lead time, not necessarily a fraction of one day's demand. Keep the demand rate and lead-time units consistent.
Interpret the ceiling
If containers hold 70 instead, the required count is about 17.1, so use 18. The authorized container capacity is 1,260 units. Rounding down to 17 would provide only 1,190, below the planned 1,200 units of cover.
Use replenishment loops for fairly steady, repeating demand. Rare custom items can accumulate unused stock in such a loop and may fit made-to-order FIFO better. Recalculate counts when demand, lead time or container size changes. Shorter, more reliable replenishment can support fewer cards; remove them gradually while checking shortages and delivery.
Key Takeaways
- Production and withdrawal kanbans authorize different actions.
- Actual use triggers fixed-quantity replenishment.
- Size the loop using full replenishment time plus safety stock.
- Round container counts up and multiply by container size to find the ceiling.
- Maintain the signal rules when work slows or problems occur.
- Recalculate the loop when its demand or replenishment conditions change.
5Make normal work visible and build quality in
A stable operation makes the right method easy to follow and problems easy to notice. Begin with 5S and visual controls that reduce searching and trigger action when conditions depart from normal. Then connect standard work to takt and use jidoka, andon and error-proofing to protect quality. The examples show the difference between inspecting a defect early and preventing the error that creates it.
5.1 Keeping an orderly workplace and visible controls
A missing tool or unclear stock location interrupts work every time it is needed. 5S creates an orderly workplace where people can follow a standard and see abnormalities quickly. It works in a supply room or shared drive as well as on a factory floor.
Work through the five steps
Sort, or seiri, removes what the current work does not need. Red-tagging puts doubtful items in a holding area for a defined review period. This avoids keeping everything “just in case” while allowing a decision before disposal.
Set in order, or seiton, assigns a labeled place to what remains. Put frequent-use items close to where they are used. A shadow board shows where each tool belongs; an empty outline makes a missing tool visible. Arrange for easy return as well as easy retrieval.
Shine, or seiso, combines cleaning with inspection. Wiping equipment can reveal a leak, loose bolt or worn part early. Cleaning that only improves appearance misses this purpose.
Standardize, or seiketsu, makes the first three steps routine. Photos of the correct state, assigned responsibilities, cleaning schedules and short checklists show what should happen and who does it. Sustain, or shitsuke, keeps the routine through habits, audits and leaders who follow up and support it. Some workplaces add safety as a sixth S, called 6S.
Measure what changed
A maintenance technician searches 15 times per shift, averaging 6 minutes each time: 90 minutes. Sorting equipment, using shadow boards and labeling drawers reduce each search to one minute. Search time becomes 15 minutes, freeing 75 minutes for maintenance.
In an office, delete outdated shared files, agree on folder names and place current templates where staff can find them. Assign someone to maintain the structure and review it. The tools differ, but the problem is the same: people lose time looking for the right resource.
Make the abnormal easy to see
Visual management shows the state of work at a glance. Labels and floor markings show locations; minimum and maximum stock lines show limits; a production board compares actual output with plan.
A visual display communicates information, such as a poster. A visual control makes a departure from normal visible and calls for action. Stock below its minimum line needs replenishment. An empty kanban slot or an andon signal needs a defined response. A board nobody updates or acts on has little control value.
Choose the normal condition, the signal and the response together. Staff should know what the minimum line means, who replenishes and when. An isolated cleanup before a visitor arrives will not maintain that system. Involve the people doing the work when setting locations and standards, and use follow-up to solve what makes the routine hard to maintain.
Key Takeaways
- 5S makes resources easy to find and problems easy to see.
- Shine includes inspection for equipment problems.
- Standardize and sustain keep the first three steps working.
- A visual control shows an abnormal condition and prompts a response.
- Design workplace standards with the people who use them.
5.2 Standard work and quality at the source
Reliable flow needs work that can be repeated and a way to respond when it goes wrong. Standard work establishes the current best method. Jidoka and error-proofing help prevent a problem from traveling through the value stream.
Establish a baseline for improvement
Standard work has three elements: takt time, the operator's work sequence and standard in-process stock, the minimum stock needed to run the sequence smoothly. Write it with the people who do the task and revise it when a better method is verified.
At 60-second takt, a sequence contains loading 8 seconds, bracket assembly 12, walking 4, fastening 15, testing 10, and unloading and walking back 7. The total is 56 seconds, leaving 4 seconds within takt. A 66-second sequence would fall behind and need waste removal or rebalancing. Include handling and walking; counting only transformation time understates the operator's load.
Without a stable method, a team cannot tell whether a changed result came from an improvement or from people working differently.
Detect, stop and solve
Jidoka builds in the ability to detect an abnormality and stop. Its sequence is to detect, stop, fix the immediate problem and remove its root cause. Automatic detection also frees people from continuously watching a machine that can stop itself.
An andon is a cord, button, light or board used to call for help. A team leader responds. On many Toyota-style lines, unresolved problems cause a stop at a fixed point. The temporary output loss prevents the same fault from being repeated or passed onward. A signal without a prompt response leaves the operator carrying the problem alone.
Prevent errors from becoming defects
An error is a mistaken action or condition, such as loading a part backward. A defect is the resulting failure to meet a requirement. Poka-yoke, or error-proofing, was promoted by Shigeo Shingo. Its devices prevent an error or make it immediately visible. A control device blocks operation until the part is correctly seated. A warning device signals the problem but depends on someone responding.
Source inspection checks conditions before or during processing. A fixture that cannot clamp a reversed part prevents that loading error from producing a defect. Self-inspection checks output immediately after a step; it finds a defect early but after it has been created. End inspection finds it later still.
If 2 percent of 1,000 daily units lack a clip, 20 need repair. Repair at the station takes one minute each; after final assembly it takes 25. Early detection saves:
A sensor that prevents release until the clip is present goes further by stopping the incomplete unit before it moves on. Investigate the process that allowed the omission; telling an operator to remember more carefully leaves the same error opportunity in place.
Key Takeaways
- Standard work records takt, sequence and minimum in-process stock.
- Operators help write and improve the standard.
- Jidoka detects abnormalities, stops and drives root-cause action.
- Andon signals need a prompt support response.
- An error is a mistaken action or condition; a defect is failed output.
- Control devices block the error; warning devices call attention to it.
- Source inspection checks conditions, while self-inspection checks the completed step.
6Keep improving and adapt lean to the operation
Lean develops through repeated problem-solving, not a single redesign. Learn how a team tests changes, verifies causes and holds gains through daily kaizen. Then apply the same thinking to service queues and customer variation. Finally, assess supply risk, environmental effects and performance measures so that shorter lead times and lower inventory support reliable delivery, quality and safe work.
6.1 Running daily kaizen and focused improvements
Kaizen means continuous improvement through small changes by everyone. Each successful change becomes the new standard, which gives the next improvement a stable starting point. Large, radical redesign is often called kaikaku.
Use PDCA to learn from a change
The Plan–Do–Check–Act cycle grew from Walter Shewhart's work and was popularized by W. Edwards Deming.
- Plan: define the problem, observe the current condition, investigate causes, choose a countermeasure and set a target.
- Do: test the change, preferably on a small scale.
- Check: compare the measured result with the target.
- Act: adopt and share a successful method as standard work, or use what the test taught you to plan again.
“Check” needs a comparison, not simply a report that the team completed its tasks. “Act” must hold a verified gain; rolling out a change before checking it can spread a new problem.
Investigate where the work happens
The gemba is the place where work is done. A gemba walk lets managers and teams see the actual conditions instead of relying entirely on reports. Ask the people doing the job and verify the explanation against what happens.
The five whys follows causes until the team reaches a process condition it can change. Five is a guide, not a required count. Orders ship late because packing lacks boxes. Boxes ran out because nobody noticed the stock falling. Reordering depends on someone seeing an empty shelf. There is no reorder signal because packaging was omitted from the kanban design. A two-bin loop for each box size addresses that cause.
Stopping at “someone forgot” does not explain why the process allowed a missed action to interrupt delivery. Check each causal link; some problems have several contributing causes and need more than one chain of investigation.
Combine events with daily improvement
A kaizen event brings a cross-functional team together for a few days, often three to five, to improve one process. A five-day pattern is to observe and learn, analyze waste, test changes, refine and document them, then report results and assign follow-up. The event needs owners who complete the remaining actions afterward.
Daily improvement uses short team meetings, problem boards, suggestions and coaching. An A3 report, on a 297 × 420 mm sheet, structures the background, current condition, target, cause analysis, countermeasures, plan and follow-up. Its purpose is clear PDCA thinking, not a crowded page of charts.
Make participation worthwhile
People need to trust that removing waste will not threaten their employment. Many lean organizations move freed capacity to other useful work and commit that productivity improvements will not cost employment. Leaders support participation by acting on ideas, recognizing useful contributions and helping teams check results. Measures such as lead time, defects and inventory show whether the change improved the customer's flow.
Key Takeaways
- PDCA tests a countermeasure and makes a successful result standard.
- Investigate causes at the gemba and verify each why.
- Five whys can branch and need not stop at exactly five questions.
- Kaizen events need follow-up; daily kaizen keeps improvement active.
- Trust and timely action on ideas support employee participation.
- An A3 report organizes problem-solving on one page.
6.2 Improving services around the customer
Lean service follows a customer or case from request to completion. Its aim is the same as in manufacturing: deliver what the customer values with less waste. In services, much of the work and waiting is hidden in information systems.
Adapt the view of flow
Customers may be present and take part in the process. Arrivals, requests, ability to complete a form, effort and preferences can all vary. Unused service capacity today often cannot be stored for tomorrow. A vacant appointment disappears, even while a backlog may remain elsewhere.
Map one customer or case across departments and include the customer's own time. A queue of claims is inventory, time awaiting approval is waiting, and reentering details is overprocessing. Correcting an erroneous form is defect-related work. Unread reports are overproduction, while ignoring staff suggestions wastes talent.
Bowen and Youngdahl introduced the term “lean service” in 1998. The application requires attention to these service conditions, not simply a copy of a factory layout.
Choose tools that fit the work
Use 5S in supply rooms and shared drives, visual controls for case status, two-bin systems for supplies and leveled appointments for routine demand. Checklists can support reliable sequences; forms that refuse invalid entries can prevent errors. Virginia Mason adopted its production system in 2002, including patient safety alerts that apply the andon idea by stopping a process when a risk is seen.
Standardize the parts where unwanted variation creates errors, while keeping judgment where customers need it. Clear form instructions reduce avoidable variation. Staff trained to handle unusual requests accommodate variation the customer values. A rigid script can obstruct care or problem-solving.
Work through a loan service
A bank's loan approval takes 12 working days of eight hours, or 5,760 working minutes. Hands-on work totals 90 minutes: data entry 10, credit check 15, underwriting 40, approval sign-off 5 and documents 20. In the bank's value analysis, underwriting and document preparation create the 60 minutes of customer value; the other steps are necessary non-value-adding work.
A redesigned process reduces approval queues and limits cases held at each desk. Lead time falls to three working days, or 1,440 minutes, while value-adding work stays at 60 minutes. Efficiency rises to about 4.17 percent. Counting all 90 hands-on minutes as value-adding would ignore the value classification.
Leave room to respond
Chasing 100 percent staff utilization is risky when arrivals and service times vary: queues grow as utilization approaches full capacity. Cutting staff can therefore increase customer waiting even if each employee appears busier. Assess end-to-end lead time, quality and customer experience alongside resource use. Some spare capacity lets the service respond to the variation that remains.
Key Takeaways
- Include customer time and invisible information queues in a service map.
- Adapt visual controls, checklists, 5S and pull to the service process.
- Reduce variation customers do not value and accommodate variation they do value.
- Hands-on time and value-adding time can differ.
- Variable arrivals require spare capacity to keep waiting manageable.
6.3 Adapting lean and measuring the result
Lean fits stable, repetitive demand and reliable processes especially well. Customized work, strong seasonality and fragile supply routes need adaptations. Choose buffers, capacity and control methods to match the actual risks and customer needs.
Match flow to demand and supply
Standard items with dependable replenishment can use frequent small lots and supermarkets. Custom items may fit sequential pull through bounded FIFO lanes. Leveled production can meet changing daily demand through a planned finished-goods buffer, provided the level follows the real average.
Agility is the ability to respond quickly to volatile demand. A supply chain can combine lean upstream production, where demand is aggregated and steadier, with responsive capacity or stock near the customer. The two aims can support different parts of the same chain.
Low inventory increases exposure when supply fails. After the 2011 Great East Japan Earthquake, Toyota mapped suppliers more deeply and arranged several months of stock of certain critical semiconductors. Reporting in 2021 described how that protection helped production during the chip shortage. Place protection against an identified risk and review the risk as conditions change.
Check environmental effects
Reducing scrap, overproduction, unnecessary movement and occupied space often saves materials and energy. Frequent small deliveries can, however, increase transport emissions if vehicles carry little. A milk run consolidates collections from several suppliers on a regular route. Evaluate the whole delivery pattern, not just the reduction in inventory inside one building.
Measure flow, quality and safety
Use a small set of measures: lead time, inventory, process cycle efficiency, on-time delivery, first-pass yield and safety. First-pass yield tracks output that meets requirements without rework. A shorter queue is not a successful gain if defects or injuries rise.
Inventory turns compare a cost flow with inventory valued on the same basis:
With annual cost of goods sold of $12 million and average inventory of $2 million, turns are six per year. Reducing average inventory to $1 million at the same cost flow gives 12 turns, roughly a month of average stock instead of two. Check delivery and supply reliability as stock falls.
Keep improvement from fading
Tools alone do not sustain lean. Leaders need to observe the work, coach people and maintain standards after the first project. Using improvements to cut jobs undermines participation. Lean emphasizes flow and waste removal; Six Sigma emphasizes variation and defects through statistical methods. They can complement each other. Start by identifying the main loss: waiting across a flow, or inconsistent output requiring a different depth of analysis.
Key Takeaways
- Adapt pull and buffers to the pattern of demand and supply risk.
- Agility adds responsiveness where demand is volatile.
- Evaluate transport emissions as well as material and inventory savings.
- Inventory turns use cost of goods sold and average inventory on matching valuation bases.
- Check delivery, first-pass yield and safety alongside flow gains.
- Leadership, standards and employee involvement sustain the gains.
Lean Operations examples
1Follow a product from customer need to delivery
11 steps
- 1IntroductionStart with the customer
A customer wants a working product delivered on time. The operation may spend much of the delivery period moving it, holding it or correcting it.
Lean examines that whole journey. We will connect Toyota's production system to five principles, then compare two ways to move a small batch through three steps.
- 2ExplanationWhy small lots mattered
Ford's moving assembly line of 1913 made long runs of standard products economical. Postwar Toyota faced a smaller market wanting a varied model mix, with little capital or space.
Small quantities of several models fit that demand, but only if switching products and dealing with problems became efficient. This need shaped a connected production system.
- 3ConnectionTwo pillars support the same goal
TPS combines just-in-time, producing the needed amount at the needed time, with jidoka, detecting abnormalities and stopping to build quality in.
Stable, leveled work and continuous improvement support both. Sakichi Toyoda's self-stopping looms supplied jidoka's roots; Kiichiro Toyoda promoted just-in-time, and Taiichi Ohno developed the system with Eiji Toyoda's support.
- 4ChallengeA signal without reliable work
A factory introduces pull cards, but machines frequently fail and operators are discouraged from reporting problems. Why will the cards alone struggle to improve delivery?
---reveal---
Pull depends on reliable replenishment. Failures interrupt it, and discouraged reporting leaves their causes unresolved. TPS also needs stable work and employees who can identify and solve problems.
- 5ExplanationFollow the five principles
Begin by specifying value from the customer's view. Then identify the value stream, including the steps that add no value.
Make value flow through fewer stops. Let the customer pull by authorizing work through actual need. Pursue perfection by repeating the cycle as improvements expose the next loss. The order keeps tools connected to a customer purpose.
- 6ExampleClassify a service visit
A tire visit takes 65 minutes. Fitting takes 12 minutes and balancing 5, giving 17 value-adding minutes. Waiting at the counter and for a bay takes 35 minutes.
Lifting the car takes another 3 minutes. It enables the repair but does not itself change what the customer buys, so it is necessary non-value-adding work. It belongs in the total time, not the value-adding total.
- 7ChallengeRework changes the product too
A frame has an incorrect weld. Repairing it changes the frame into the required shape. Does that make the repair value-adding?
---reveal---
No. Value-adding work must be wanted by the customer, change form, fit or function, and be done right the first time. The repair fails the last test. It consumes resources to correct a defect that should not have occurred.
- 8ExampleMove the whole batch
Ten parts pass through three staffed steps taking one minute per part. Each step holds the batch until all 10 are complete.
Step 1 releases the batch at minute 10. Step 2 releases it at minute 20. Step 3 finishes the first part at minute 21 and the tenth at minute 30. Much of each part's journey is waiting for the rest of its batch.
- 9ExampleMove one part at a time
Keep the same three steps and processing times, but transfer each part as soon as it is ready.
The first part finishes step 1 at minute 1, step 2 at minute 2 and step 3 at minute 3. The next finished part follows each minute, so the tenth finishes at minute 12. Task speed stays the same; smaller transfers remove batch waiting.
- 10ChallengeConnect efficiency to customer need
The first step now keeps making extra parts after downstream demand is met. Why can that decision undermine the benefit of one-piece flow?
---reveal---
Extra parts create inventory and waiting even if the machine looks productive. Flow needs pull as well as small transfers: upstream work must respond to downstream need. The customer gains from reliable delivery, not from an unused pile of parts.
- 11RecapRead the whole operation
Use the customer need to define value, trace the full value stream and examine what interrupts flow. Pull limits releases, while jidoka protects the work as it happens.
When judging a proposed improvement, ask what it changes for the customer's journey and what stable work, employee support and problem-solving it requires.
2Find the cause behind the queue
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionObserve before selecting a tool
- 2ExplanationUse TIMWOODS as a scan
- 3ExampleOne queue, two observations
- 4ChallengeToo much output or too much work?
- 5ExplanationConnect peaks to overload
- 6ExampleKeep the weekly total, smooth the release
- 7AnalogyLower the water carefully
- 8ExampleCalculate the current average delay
- 9ChallengeA smaller pile with the same output
- 10ChallengeA busy upstream machine
- 11RecapTurn an observation into an improvement
3Calculate and redesign a bracket value stream
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionConnect demand to the whole route
- 2ExplanationMap one family by observation
- 3ExampleRecord the stops and the control
- 4ChallengeA fast cycle and a slow journey
- 5ExampleStep 1: find the customer pace
- 6ExampleStep 2: include uptime
- 7ExampleStep 3: turn stock into days
- 8ExampleStep 4: calculate flow efficiency
- 9ChallengeWhere does a lead-time gain come from?
- 10ExplanationStep 5: connect compatible processes
- 11ExampleStep 6: check the people needed
- 12ConnectionStep 7: release work by container
- 13ExampleStep 8: attach conditions to stock targets
- 14ChallengeOne schedule, several replenishment links
- 15RecapUse the numbers to choose the links
4Build a small-lot pull system
18 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake replenishment workable
- 2ExplanationRead the authorization
- 3ChallengeStock before the final order
- 4ConnectionSupport the signal with reliability
- 5ExplanationWhy long setups favor large lots
- 6ExampleStep 1: see the economic relationship
- 7ExampleStep 2: work backward from a target lot
- 8ExplanationSeparate preparation from the stop
- 9ChallengeWhat happened to the stopped time?
- 10ExplanationLevel the demanded mix
- 11ChallengeLevel volume without ignoring demand
- 12TipProtect the next release
- 13ExplanationFollow a container through the loop
- 14ExampleStep 1: calculate the required cover
- 15ExampleStep 2: translate cover into containers
- 16ChallengeA shorter production task
- 17ChallengeA useful setup gain
- 18RecapCheck the connected design
5Make the right work easy and errors visible
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionSee normal work clearly
- 2ExplanationSort and arrange for use
- 3ConnectionClean, inspect and maintain
- 4ExampleMeasure the search time
- 5ChallengeA poster or a control?
- 6ExplanationSet the current best method
- 7ExampleCheck the work against takt
- 8ExplanationStop and call for support
- 9ExplanationCheck conditions before defects form
- 10ChallengeWarning or prevention?
- 11ExampleCompare early and late repair
- 12ChallengeKeep the improvement working
- 13RecapLink the device to the work
6Improve a process and judge the wider result
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionA change needs evidence
- 2ExplanationPlan a test, then learn from it
- 3ExampleFind the missing replenishment rule
- 4ChallengeWhat belongs in Act?
- 5TipKeep the event connected to daily work
- 6ExplanationFollow a service case
- 7ExampleSeparate touch time from value time
- 8ExampleRemove waiting without rushing the decision
- 9ChallengeWhy keep some spare service capacity?
- 10ExplanationChoose protection for a specific risk
- 11ExampleCheck inventory turns on a cost basis
- 12ChallengeA stock gain with a transport cost
- 13ChallengeA faster service with more corrections
- 14RecapHold gains across several measures
Lean Operations practice questions
Set 1: Read the map and control replenishment10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Demand gives takt of 45 seconds because 420 minutes equal 25,200 seconds. The effective cycle is:
It exceeds takt, so the station cannot sustain demand. Comparing the 42-second running cycle alone ignores downtime and incorrectly suggests spare capacity.
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Lead-time demand is 540 units, and adding 90 safety units gives 630. The container requirement is:
Round up to 13. Twelve containers hold only 600 units, below planned cover. Safety stock is added to lead-time demand before dividing by the container quantity.
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: See value, waste and the pace of demand10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Use setup, staffing and quality evidence10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Judge a lean design under changing conditions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Combine flow, capacity and improvement choices10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
A3 report
Agility
Andon
C
Changeover
Continuous flow
Customer value
Customer-introduced variability
Cycle time
D
Defect
E
Economic lot size
Error
External setup
F
FIFO lane
First-pass yield
Five whys
Frozen schedule period
Future-state map
G
Gemba
H
Heijunka
Heijunka box
I
Information flow
Internal setup
Inventory turns
Inventory waste
J
Jidoka
Just-in-time
K
Kaikaku
Kaizen
Kaizen burst
Kaizen event
Kanban
L
Lead time
Lean operations
Lean service
Lean Six Sigma
Little’s law
M
Mass production
Milk run
Mixed-model sequence
Motion waste
N
Necessary non-value-adding activity
Net available working time
O
One-piece flow
Operator work content
Overburden (muri)
Overprocessing
Overproduction
P
Pacemaker
PDCA
Pitch
Poka-yoke
Process cycle efficiency
Process data box
Product family
Production kanban
Pull production
Pure waste
Push production
R
Replenishment lead time
Replenishment pull
Respect for people
Risk buffer
S
Self-inspection
Sequential pull
Service backlog
Service utilization
Set in order
Shine
Signal kanban
SMED
Sort
Source inspection
Standard in-process stock
Standard work
Standardize
Supermarket
Sustain
T
Takt time
Toyota Production System
Transport waste
Two-bin system
U
Unevenness (mura)
Unused talent
Uptime
V
Value stream
Value stream mapping
Value-adding activity
Value-adding time
Variability
Visual control
Visual management
W
Waiting waste
Withdrawal kanban
#
5S