Contract Costing

Learn how contractors cost long-term, site-based work such as buildings, roads and bridges. Charge materials, labor, subcontractors, plant, overheads and establishment charges to a contract account; value work certified and work not yet certified; and calculate notional profit, the prudent share of profit to recognize and any anticipated loss. Work out progress payments and retentions, compare fixed-price and cost-plus contracts with escalation clauses, and present several contracts in one contract costing statement.

BeginnerLesson 6 of 11 in Introduction to Management Accounting Course

What you will learn

  1. Explain why long, site-based work such as construction is costed contract by contract, and compare the main ways a contract price is set and adjusted.
    • Describe the features of contract costing
      Describe the cost unit, the people and the documents involved in contract costing, and explain how it differs from job costing.
    • Compare fixed-price and cost-plus contracts and apply escalation clauses
      Explain who carries the cost risk in fixed-price and cost-plus contracts, and calculate the price change an escalation clause allows.
  2. Build the cost side of a contract account: direct materials, labor and expenses, subcontractors, plant on site, allocated overheads and establishment charges.
    • Charge materials, labor, direct expenses and subcontractors
      Calculate the materials, labor and direct expenses charged to a contract for a period, find its prime cost and add subcontractors' charges.
    • Account for plant used on a contract
      Charge a contract with the cost of using machinery and equipment, including plant sent to the site, transferred, sold or scrapped.
    • Add allocated overheads and establishment charges
      Charge a contract with its share of costs that are not traceable to one site and complete its total cost.
  3. Value the work done, find the notional profit, recognize a prudent share of it, and charge expected losses in full.
    • Value work done and calculate notional profit
      Value work certified and work not certified, find the cost of work certified and calculate notional profit, including for a contract that continues from an earlier year.
    • Recognize a prudent share of profit on incomplete contracts
      Calculate the profit to take on an unfinished contract with the main profit-recognition rules, including in later years and at completion.
    • Charge anticipated losses in full
      Recognize a loss on a contract as soon as it is known, both when the work to date shows a loss and when the whole contract is expected to make one.
  4. Calculate what the client pays and still owes, including retentions, and present several contracts in one contract costing statement.
    • Calculate progress payments, retentions and amounts due
      Work out the payment due on each certificate, the retention held and released, and the amount the client still owes.
    • Prepare a contract costing statement for several contracts
      Present several contracts side by side, find each one's profit or loss to recognize, and total the result for the period.

Contract Costing study guide

4 chapters

1

Understand the contract and its price

A long construction contract ties up people, equipment and cash across several accounting periods. Before working out its result, identify whose work is being costed, which costs belong to that site and how the client has agreed to pay. The pricing method explains who bears rising costs; the contract account then shows what the work actually costs. Certificates connect progress on site with both interim profit and payments.

1.1 How a contract becomes a cost unit

Contract costing collects the costs of a large, long-term project carried out to a customer's specification. A hospital, bridge or road has its own contract account. This lets the contractor see the resources used and the result earned on that particular project.

Follow the work to its site

The cost unit is the individual contract. Work takes place at the customer's site and usually continues beyond one accounting period. Each contract is priced separately, reflecting its own specification. These features explain why site records matter: deliveries, time records and equipment movements must identify the contract that caused them.

Most costs are direct because they can be traced to one site. A site manager's salary, temporary fencing, site security and the site's electricity all belong to that contract. They do not become indirect merely because they are not bricks or building labor. Ask whether the cost exists only because of this site. If it does, charge it directly. Head office administration serves several contracts and needs a sharing basis if it is charged to them.

Know who does what

The contractor carries out the work. The client, also called the contractee, orders and pays for it. Their agreed total price is the contract price. A subcontractor is a separate business hired by the contractor for a defined part, such as electrical installation. The contractor includes that firm's charge in the contract's costs.

The client's architect, engineer or quantity surveyor inspects progress and issues a certificate valuing work completed to the required standard. The certificate is a record of approved work. It supports a progress payment, but the client holds back a percentage called retention, or retainage, as security against defects. The certificate's value and the cash paid therefore differ.

Connect contract costing with job costing

Both methods collect costs for a specific order. A three-day repair of a delivery van in a workshop is a job. A two-year apartment project at the client's site is a contract. Workshop jobs usually absorb production overheads through a predetermined rate. On a construction site, many comparable support costs are directly traceable, leaving a smaller share to allocate.

The long duration also creates two separate period-end decisions. First, how much profit should be reported before the contract is complete? Second, how much must the client pay for work approved so far? Cost records alone answer neither question; the account also needs the certified value, the profit policy and the payment terms.

Waiting until completion to report every dollar of profit would leave earlier years without the profit earned during their work and put it all into the final year. Contract costing recognizes a cautious share while work continues. Expected losses are charged as soon as they can be foreseen. A busy site can therefore have substantial work completed, some profit recognized and a different amount of cash received.

Key Takeaways

  • Each contract is a separate cost unit with its own contract account.
  • Traceable site support costs are direct costs, including supervision and site utilities.
  • Certification values approved work; progress payments follow the payment terms.
  • Long duration creates separate calculations for interim profit and cash payments.

1.2 Set the price and share cost risk

A contract's price determines how cost changes affect the contractor and client. Start by identifying whether the agreement fixes a price or reimburses allowable costs. Then read any change-order or escalation terms before calculating an adjustment.

Fixed-price and cost-plus agreements

In a fixed-price contract, the total price is agreed at the start. Higher costs reduce the contractor's profit and can create a loss; savings increase its profit. This gives the contractor a strong reason to estimate accurately and control spending. A fixed price covers the original specification. Later client-requested changes, called variations or change orders, are priced separately and change the contract price.

In a cost-plus contract, the client reimburses allowable actual costs and pays an agreed fee. The fee may be a percentage of cost or a fixed amount. Allowable costs of $1,600,000 plus 12% give a fee of $192,000 and a price of $1,792,000. With a fixed fee, rising costs raise the reimbursement but do not raise the fee.

Cost-plus pricing suits work whose cost is hard to estimate, such as emergency storm repairs or a first-of-a-kind project. The client carries most of the risk of allowable costs rising. A percentage fee weakens the incentive to save because higher costs also increase the fee. Clients can define allowable costs, inspect records, agree a fixed fee or set a guaranteed maximum price.

Calculate an escalation claim

An escalation clause adjusts a fixed price for rises in named input rates, commonly materials and labor. It shares inflation risk with the client. A de-escalation clause lowers the price when the named rates fall.

For each eligible input:

  1. Find the increase above its base rate, or above the threshold in the clause.
  2. Multiply that eligible rate increase by the agreed quantity.
  3. Add the separate claims.

Suppose the contract allows 500 tons of steel at a base rate of $800 per ton and 20,000 labor hours at $30 per hour. Actual rates are $860 and $31.50. The steel increase is $60 per ton, giving $30,000. The labor increase is $1.50 per hour, also giving $30,000. The total claim is $60,000.

If 520 tons were actually used because of waste, the claim still uses the allowed 500 tons. The clause compensates for the named price change; the extra quantity remains the contractor's cost.

Apply a threshold before multiplying

Now let the clause cover only the increase beyond 5% of each base rate. The steel threshold is $800 × 1.05 = $840 per ton. The eligible increase is $20, so the steel claim is $10,000. The labor threshold is $30 × 1.05 = $31.50 per hour. The actual rate only reaches it, so there is no eligible labor increase.

The total claim is now $10,000. Applying 5% to the whole contract price would calculate a different quantity. The input list, threshold and allowed quantities each limit what the client reimburses.

Key Takeaways

  • A fixed price places most cost risk on the contractor; allowable cost reimbursement shifts it toward the client.
  • A percentage fee rises with allowable costs; a fixed fee does not.
  • Client-requested changes are priced separately from the original work.
  • An escalation claim uses only named inputs and eligible rate increases.
  • Use the agreed quantity even when actual usage is higher.
  • With a threshold, calculate the increase beyond that threshold first.
2

Build the cost side of the account

A contract account measures the cost of work done during the period. That means adjusting deliveries for materials left on site, payments for amounts owed or prepaid, and equipment values for the use made of plant. After calculating direct costs and prime cost, add subcontractors and the agreed shares of central costs. Keeping these workings separate makes it easier to spot an omitted asset balance or an overhead rate applied to the wrong amount.

2.1 Measure materials and direct costs used

The contract account collects the costs belonging to one contract. In a T-account, debit costs and credit reductions in cost or values carried forward. A vertical statement shows the same calculation as additions and deductions down a column.

Materials: follow both deliveries and movements

Include materials delivered directly by suppliers, issued from central stores and transferred in from another contract. Add opening materials on site in a later year. Deduct returns to stores, transfers to other contracts and scrap or surplus sale proceeds. Finally deduct unused closing materials: these remain available for later work.

For Contract 14 in Year 1:

Materials movementAmount
Supplier deliveries$380,000
Issues from stores$45,000
Less returns to stores($8,000)
Less transfer to Contract 15($6,000)
Less materials still on site($27,000)
Materials charged$384,000

A transfer out reduces this contract's cost and becomes a charge to the receiving contract. Closing materials are carried down, marked c/d, and brought down, b/d, as the next year's opening balance. Charging all deliveries immediately would include materials the work has not yet used.

Labor and expenses: match the period

Labor includes site workers and site supervisors. Start with wages paid, add closing wages owing and deduct opening wages owing that were settled in those payments. Opening arrears belong to the previous period; closing arrears belong to this one.

Contract 14 pays $310,000 and still owes $14,000 at year-end, with no opening arrears. Labor charged is $324,000. For a different site paying $90,000, with opening arrears of $4,000 and closing arrears of $7,000, the period's labor is $93,000.

Direct expenses are other traceable site costs, including equipment hire, insurance and site utilities. Amounts paid in advance for a later period are deducted. Contract 14 pays $52,000 of direct expenses, including a $3,000 prepayment, so the expense is $49,000. Its crane hire adds $18,000.

Show prime cost and subcontractors clearly

Prime cost is direct materials plus direct labor plus direct expenses. Contract 14's subtotal is $384,000 + $324,000 + $49,000 + $18,000 = $775,000. Label this subtotal so the direct costs are visible before further charges.

The electrical subcontractor charges $96,000. This is a direct cost of Contract 14, shown here immediately after prime cost. Other layouts include subcontractors within prime cost; the charge must appear once in either layout.

Distinguish normal waste from abnormal loss

Normal waste and minor site damage remain part of the contract's cost. If damaged materials are sold as scrap, credit the proceeds. Materials destroyed in an abnormal event such as a fire are removed from the contract cost and charged to the profit and loss account. Removing the abnormal loss prevents it from distorting the cost of the contract's ordinary work.

Key Takeaways

  • Materials charged include opening stock and receipts, less returns, transfers out, scrap proceeds and closing stock.
  • Labor charged equals wages paid plus closing arrears minus opening arrears.
  • Deduct expenses prepaid for a later period.
  • Label prime cost: direct materials, direct labor and direct expenses.
  • Charge subcontractors once, using the chosen statement layout.
  • Normal waste stays in contract cost; abnormal loss is transferred to profit and loss.

2.2 Charge the use of plant

Plant is the machinery and equipment used on site: excavators, cranes, mixers and scaffolding. A contract bears the value used up while the plant works there. Equipment that still has value at the end remains an asset.

Revalue plant on a long-term site

Under the revaluation method, charge the value of plant when it arrives, or its opening value brought down. Deduct the value of plant remaining at the end or leaving the site. The reduction in value is the charge for use.

Contract 14 receives plant valued at $240,000. Its year-end value is $180,000. The contract's plant charge is $60,000. In a T-account, the $240,000 is a debit and the $180,000 closing asset is a credit. The closing $180,000 becomes next year's opening debit.

Materials left on site and plant left on site are both carried forward, but for different reasons. The materials have not yet been used. The plant has been used and retains value for future use; the account charges only the value consumed.

Charge depreciation for the time used

For short site use or centrally managed equipment, charge the depreciation or internal hire rate for the time on the contract. An excavator costing $120,000 with depreciation of 20% a year has annual depreciation of $24,000. Three months on a site gives a $6,000 charge: $24,000 × 3/12.

Do not also charge the purchase price. Likewise, a revaluation difference already measures depreciation for that plant and period; adding separate depreciation would count the same use twice. Plant fuel, maintenance, repairs and operators' wages are additional direct running costs.

Account for plant that moves or is sold

When plant transfers to another contract or returns to the central yard, deduct its value at that date. The receiving contract or yard takes over that value. The sending contract retains the depreciation arising while it used the plant.

For a site with opening plant of $500,000 and additions of $100,000, suppose a mixer with book value $20,000 is sold for $14,000. Closing plant is $510,000. Separate the calculation into:

  • Depreciation: $500,000 − $20,000 + $100,000 − $510,000 = $70,000.
  • Loss on sale: $20,000 − $14,000 = $6,000.
  • Total plant charge: $76,000.

Deducting the mixer's book value removes it from the pool being revalued. The separate $6,000 loss then captures the shortfall in proceeds. A gain would reduce the contract cost.

An equally valid combined calculation deducts sale proceeds directly: $500,000 + $100,000 − $14,000 − $510,000 = $76,000. Once proceeds have been used in this combined route, do not add the loss on sale again. Before totaling, identify whether a disposal figure is book value or proceeds; they play different roles in the two presentations.

Key Takeaways

  • Charge plant use through depreciation or an internal hire rate, not its whole purchase price.
  • Deduct closing plant and transfer values under the revaluation method.
  • Plant sold can be handled through book value plus a separate loss, or proceeds in a combined calculation.
  • Never charge both methods for the same use or disposal.
  • Add plant running costs separately.

2.3 Apply shared costs to the right base

Some costs support more than one site. A contract bears an agreed share of these costs when the contractor's policy allocates them. Separate the rate from the amount it applies to before doing any multiplication.

Read the overhead basis exactly

Allocated fixed overheads may include central stores, the plant yard or a regional construction department. A policy may charge a percentage of direct materials, direct labor or prime cost. Those bases give different amounts even when the percentage is the same.

Contract 14 is charged construction overheads at 10% of direct material cost. Its materials used are $384,000, so overheads are $38,400. The $425,000 of deliveries and store issues is not the correct base because returns, transfers out and closing materials have already reduced the materials used.

If the basis is "direct material cost plus subcontracting costs," add both amounts before applying the rate. For example, materials of $150,000 and subcontractors of $40,000 at 8% give $15,200. Applying 8% only to materials would omit $3,200. Closing plant affects the plant charge; it does not belong in a materials-based calculation.

Share head office establishment charges

Establishment charges are the contract's share of head office and central administration: directors' and office salaries, head office rent, accounting, estimating and legal departments. They are indirect because they serve the business as a whole. Site supervision, by comparison, is directly traceable to its contract.

A proportional share follows this calculation: shared cost pool × this contract's base ÷ total base for all contracts. If head office costs are $400,000 and prime cost is the basis, a contract with $500,000 of the total $2,000,000 prime cost receives one-quarter of the pool, or $100,000.

Sometimes the total pool must be found first. If one contract's 40% share is $240,000, total head office costs are $240,000 ÷ 0.4 = $600,000. A second contract bearing 60% receives $360,000. Multiplying the first contract's $240,000 by 60% would treat a part as though it were the whole.

Finish the cost statement

Use a clear sequence: direct materials, labor and expenses; prime cost; subcontractors; plant; allocated overheads; establishment charges. For Contract 14:

Cost itemAmount
Prime cost$775,000
Subcontractors$96,000
Plant charge$60,000
Construction overheads$38,400
Establishment charges$85,600
Total cost$1,055,000

The $85,600 establishment charge here is a separate supplied allocation. It is added to, not calculated from, the $38,400 construction overhead charge. Keep the two labels distinct so one pool is not charged twice.

Some contractors leave head office costs as period costs in the profit and loss account. Others apportion them to contracts. Follow the specified policy: a rate or allocation belongs to the contract statement only when that policy charges it there.

Key Takeaways

  • Identify the stated base before applying an overhead rate.
  • Establishment charges share central administration costs among contracts.
  • Find a cost pool from a known share by dividing by that share.
  • Keep direct site costs separate from indirect head office costs.
  • Add each cost pool once to reach total contract cost.
3

Find the result and the amount to recognize

The value approved by the client and the cost of producing that work establish a contract's notional result. An unfinished contract then needs a second decision: how much of that result belongs in profit and loss now. Work through valuation, the specified profit rule and any forecast loss in that order. For a continuing contract, keep totals to date separate from the amount already reported so earlier profit is not counted again.

3.1 Value work and find notional profit

A certificate values approved work at its sales value. Costs record the resources used. Bringing these two measures together reveals the notional profit on work certified, while keeping uncertified work at cost.

Separate the two parts of work done

Work certified has been completed and approved by the client's architect or surveyor. Its value includes profit because it is measured at contract price. Certificate values are cumulative: a later certificate covers the approved work since the contract began.

Work not certified is work completed since the latest certificate. Value it at cost. Adding a profit margin before certification would bring unsupported profit into the account.

Total cost to date includes both certified and uncertified work after deducting materials and plant still on site. To isolate the cost of certified work, subtract the cost of work not certified.

Work through Contract 14

Contract 14 has total cost of $1,055,000, uncertified work costing $55,000 and certified work valued at $1,200,000.

  1. Cost of work certified: $1,055,000 − $55,000 = $1,000,000.
  2. Notional profit: $1,200,000 − $1,000,000 = $200,000.

The profit is notional because the contract is unfinished; future costs can change the final result. It is the profit available before deciding how much to recognize now.

A vertical statement reaches the same answer by adding work certified and work not certified, then deducting total cost. Here the work value is $1,255,000, giving $1,255,000 − $1,055,000 = $200,000. Uncertified work appears on both sides at cost and contributes no profit.

Read the contract account

In a T-account, debit the costs and credit work certified, work not certified c/d, materials on site c/d and plant on site c/d. The balancing notional profit appears on the debit side. That balancing position does not make it an expense; it completes an account whose credit values exceed its costs. The profit is then split between the part recognized and the part retained.

Contract 14's account can show the gross charges and separate credits:

DebitAmountCreditAmount
Materials received$425,000Work certified$1,200,000
Labor charged$324,000Work not certified c/d$55,000
Direct expenses, including crane hire$67,000Materials returned$8,000
Subcontractors$96,000Materials transferred out$6,000
Plant received$240,000Materials on site c/d$27,000
Construction overheads$38,400Plant on site c/d$180,000
Establishment charges$85,600——
Notional profit$200,000——
Total$1,476,000Total$1,476,000

Here closing assets and material movements appear as credits. The vertical calculation already deducted them to reach net cost of $1,055,000; do not deduct them again from that net figure.

Continue into another year

Contract 14 begins Year 2 with opening materials of $27,000, plant of $180,000 and uncertified work of $55,000. These were carried forward from Year 1 and enter the later account as opening debits. Work already done but uncertified at the earlier year-end must still be included when it is certified later.

If cumulative certification reaches $2,400,000 at the end of Year 2, certification during Year 2 is $2,400,000 − $1,200,000 = $1,200,000. Keep these labels visible in your workings: "to date" and "during Year 2" answer different questions. Cash received is a third figure governed by payment terms; it cannot replace certified value in the notional profit calculation.

Key Takeaways

  • Work certified is valued at contract price; work not certified is valued at cost.
  • Cost of work certified equals total cost to date minus uncertified work at cost.
  • Notional profit equals certified value minus the cost of certified work.
  • The vertical and T-account layouts give the same result.
  • Bring closing site balances forward to the next year.
  • Subtract earlier cumulative certification to find certification during a year.

3.2 Choose and apply the profit rule

An unfinished contract still faces cost overruns, defects, disputes and delays. Recognize only the prudent share of its notional profit and carry the rest forward as profit retained. Prudence limits the amount taken now, while matching connects profit with the periods in which work is performed.

Start with stage of completion

Measure the stage as work certified ÷ contract price. Contract 14 has $1,200,000 certified against a $3,000,000 price, so it is 40% complete. This measure uses certified value; cash receipts or cost spent measure something else.

The rules below are alternatives. Use the organization's policy or the rule specified in the question.

Work-certified rule

Profit recognized = notional profit × work certified ÷ contract price.

For Contract 14, $200,000 × 40% = $80,000. Profit retained is $200,000 − $80,000 = $120,000. Cash received does not enter this rule.

Stage-fraction rule

First identify the certified stage, then apply its fraction and the cash ratio:

Certified stageProfit recognizable
Under 25%None
25% to under 50%1/3 × notional profit × cash received ÷ work certified
50% to under 90%2/3 × notional profit × cash received ÷ work certified

Contract 14 is in the one-third band. If cash received is 90% of work certified, profit recognized is 1/3 × $200,000 × 0.9 = $60,000. Profit retained is $140,000. This rule reduces the amount for both incomplete work and incomplete payment. Do not multiply its result by the 40% stage again: that stage selected the fraction.

Nearly complete contracts

At about 90% completion or more, the estimated-profit rule uses the expected final result. Estimated total profit is contract price minus estimated total cost, including completion and defect costs. Multiply that estimated profit by work certified ÷ contract price.

A $3,000,000 contract with estimated total cost of $2,650,000 has expected profit of $350,000. With $2,760,000 certified, the stage is 92% and recognizable profit is $322,000. Some versions add the cash ratio; include it when the specified rule requires it.

Find this year's profit from cumulative figures

For continuing contracts, calculate the recognizable amount to date and subtract profit recognized earlier. At the end of Contract 14's Year 2, cumulative certified value is $2,400,000 and the cost of certified work is $1,950,000. Notional profit is $450,000. Under the work-certified rule, $450,000 × 80% = $360,000 is recognizable to date. Less the $80,000 already recognized leaves $280,000 for Year 2.

At completion, recognize the remaining final profit: final contract price minus total cost minus profit recognized in earlier years. A loss is never reduced by one of these profit fractions.

Key Takeaways

  • Use the specified profit rule; the alternative rules give different answers.
  • Measure stage from work certified divided by contract price.
  • The work-certified rule ignores cash; the stage-fraction rule includes the cash ratio.
  • Profit retained is the unrecognized part of notional profit.
  • Nearly complete work uses estimated total profit under the estimated-profit rule.
  • Subtract earlier recognized profit from the cumulative recognizable amount.
  • At completion, recognize the balance of final profit.

3.3 Recognize the full expected loss

Prudence treats losses more urgently than profit. A profit on unfinished work is recognized cautiously, but a loss is charged in full as soon as it can be foreseen. Check both the result on work certified and the expected result of the whole contract.

Charge a notional loss without a fraction

A notional loss arises when certified work costs more than its certified value. Contract 22 has total cost of $345,000, including $15,000 of uncertified work. Cost of work certified is therefore $330,000. With work certified at $300,000, the notional loss is $30,000.

Charge all $30,000 to profit and loss. Multiplying it by the completion ratio or by one-third would delay part of a loss already shown by the work done. Do not use a profitable contract to reduce this loss before recognizing it. Each contract's result is measured separately.

Look ahead even when work so far is profitable

A contract can show a notional profit and still be expected to lose overall. Add the estimated cost to complete to cost incurred so far, including the expected cost of correcting defects. Compare that total with the contract price.

Consider a contract priced at $1,000,000. Costs incurred are $600,000, all for certified work. Certified value is $640,000, so the work to date appears to earn $40,000. However, completion is expected to cost another $460,000. Total expected cost is $1,060,000, producing an anticipated loss of $60,000.

Recognize a $60,000 loss now and take none of the $40,000 notional profit. Looking only at certified work would miss the larger cost still to come.

Make the statement reach the whole loss

The remaining work has a value of $1,000,000 − $640,000 = $360,000, but it is expected to cost $460,000. Its expected loss is $100,000. Charge a provision of $100,000 against the current $40,000 notional profit. The net result becomes a $60,000 loss.

The $100,000 provision and the $60,000 whole-contract loss are different amounts. Subtracting only $60,000 from the $40,000 profit would report a loss of $20,000 and fail to recognize the full expected loss. Subtracting the provision and then charging the whole loss again would double count it.

Update the cost to complete

Snagging means correcting minor defects found near completion; the US term for the list of defects is a punch list. The contractor bears the cost of correcting its work, so the forecast must include these repairs along with the remaining construction work.

Revisit the estimate when costs rise faster than planned, input price rises lack escalation cover, delays may bring penalties or variations are disputed. Use the current best estimate and revise it when new information changes the forecast. The amount is based on an estimate, but waiting for final certainty would leave the current result overstated.

Key Takeaways

  • Charge a notional loss in full without applying a profit fraction.
  • Forecast total cost, including completion and defect correction.
  • A positive notional profit can coexist with an expected whole-contract loss.
  • The provision must make the result equal the full expected loss.
  • Reassess the estimate when costs or conditions change.
4

Calculate cash due and compare contracts

A contractor needs to know both what its work earns and when the client pays. Certificate values, cash received and retention answer different questions. Calculate each payment from the contract's timing terms, then use a consistent statement to compare results across sites. Working down one contract column at a time keeps shared costs, cautious profit and full losses in the right places before the period's results are added together.

4.1 Calculate payments and retention

Progress payments are installments paid while work continues. They are normally based on certificates showing the cumulative value approved to date. Read whether a figure is a cumulative entitlement, the next payment or a retention balance before calculating it.

Calculate the payment on a new certificate

Retention, called retainage in the US, is the share the client withholds as security against defects. A common range is about 3% to 10%, with the actual rate set by the agreement. It remains owed to the contractor and is not a contract cost.

Amount due = cumulative work certified × (1 − retention rate) − payments already received.

With 10% retention, Contract 14's first certificate of $1,200,000 permits a payment of $1,080,000. Its second certificate raises cumulative work certified to $2,100,000. The cumulative payable amount is $1,890,000. After subtracting the first $1,080,000 payment, the new amount due is $810,000.

Retention held is $210,000, or 10% of the cumulative certificate. Paying $1,890,000 again on the second certificate would pay twice for work already covered by the first payment.

Distinguish retention from all money still owed

The client's total balance is cumulative work certified minus cumulative cash received. Once the second payment is made, this is $2,100,000 − $1,890,000 = $210,000, exactly the retention. Before that payment is made, the balance also includes the unpaid $810,000 currently due.

A cash ratio of cash received ÷ work certified enters the stage-fraction profit rule. It is 90% once all payments due under these terms have been made. The work-certified profit rule does not use cash received, so a payment delay does not by itself reduce profit under that rule.

Follow the retention release dates

A common arrangement releases half the retention at practical completion, called substantial completion in the US. The rest is paid after the defects period once the punch-list items have been corrected. On a fully certified $3,000,000 contract with 10% retention, $300,000 is held: $150,000 is released at each stage.

The exact release terms matter. If defects are not corrected, the client may use part of the retained amount to pay another firm to do the work. A retention balance is therefore money withheld for security, with release tied to the agreed conditions.

Some agreements release each certificate's retention after a fixed period. Consider a four-year $8,000,000 contract with equal yearly installments of $2,000,000, less 10% of that year's work certified held for six months. Year 3 certification is $2,500,000. By the end of Year 3, the earlier years' retentions have been released. Cumulative receipts are 3 × $2,000,000 − $250,000 = $5,750,000.

Here only the current year's retention is outstanding. Keeping the earlier released amounts in the deduction would understate cash received. A short timeline of certification, deduction and release dates is useful whenever retentions mature separately.

Key Takeaways

  • Calculate cumulative payment entitlement, then subtract cash already received.
  • Retention is delayed cash owed to the contractor, not an expense.
  • Client balance equals cumulative work certified minus cumulative cash received.
  • An unpaid current payment makes the client balance larger than retention alone.
  • Apply each retention release date before totaling receipts.
  • Only the stage-fraction profit rule uses the cash ratio.

4.2 Build a statement for several contracts

A contract costing statement places separate contract columns beside a total column. Use the same rows throughout, but calculate each contract's costs and result on its own. A common layout makes the differences between sites visible without combining their profit decisions.

Set up the rows

Begin with work certified and work not certified at cost, then total the work value. Deduct materials, labor and direct expenses, showing the prime cost subtotal. Add subcontractors, plant, allocated overheads and establishment charges to reach total cost. Follow with notional profit or loss, the result recognized and profit retained.

For continuing contracts, show opening balances of materials, plant and uncertified work in the appropriate cost workings. Keep cumulative profit calculations separate from the current year's result. Subtract prior recognized profit only after calculating the recognizable amount to date.

Work down each contract column

The following costs are already measured to date. Contracts 21–23 have no separate direct expenses in this example, so prime cost is materials plus labor.

ItemContract 21Contract 22Contract 23Total
Contract price$1,800,000$900,000$2,000,000$4,700,000
Work certified$1,350,000$300,000$200,000$1,850,000
Work not certified$60,000$15,000$10,000$85,000
Work value$1,410,000$315,000$210,000$1,935,000
Materials$420,000$120,000$60,000$600,000
Labor$380,000$130,000$50,000$560,000
Prime cost$800,000$250,000$110,000$1,160,000
Subcontractors$90,000$30,000$20,000$140,000
Plant$70,000$25,000$15,000$110,000
Overheads$64,000$22,000$12,000$98,000
Establishment charges$56,000$18,000$13,000$87,000
Total cost$1,080,000$345,000$170,000$1,595,000

Subtract uncertified work from each total cost to find certified costs of $1,020,000, $330,000 and $160,000. Compare these with the respective certificates to find the notional results below.

Apply the rule before adding results

Under the work-certified rule, the stages are 75%, about 33.3% and 10%. Apply each profitable contract's stage and charge Contract 22's loss in full:

ResultContract 21Contract 22Contract 23Total
Notional profit/(loss)$330,000($30,000)$40,000$340,000
Recognized profit/(loss)$247,500($30,000)$4,000$221,500
Profit retained$82,500$0$36,000$118,500

Under the stage-fraction rule with 90% cash ratios, Contract 21 recognizes $198,000, Contract 22 still charges $30,000 and Contract 23 recognizes nothing because it is under 25% complete. The total is $168,000. A single fraction applied to combined notional profit would overlook these different stages and the full-loss rule.

Read what the results suggest

Contract 21's notional margin is $330,000 ÷ $1,350,000, about 24.4%; Contract 23's is 20%. Contract 22 is losing money and needs a fresh estimate of its cost to complete. Check every column for an anticipated whole-contract loss before accepting the total. A positive overall result does not remove a loss that belongs to one contract.

Key Takeaways

  • Use matching rows and a separate column for each contract.
  • Calculate each contract result and check its forecast loss before totaling.
  • Apply the profit rule separately to each profitable contract.
  • Charge loss-making contracts in full.
  • For continuing work, deduct earlier recognized profit to find the period result.
  • Use margins and forecasts to investigate weak contract performance.

Contract Costing examples

4 Walkthroughs

1

Follow a contract from agreement to site

11 steps
Identify the people, direct site costs and pricing terms, then calculate an escalation claim.
  1. 1
    IntroductionStart with one project

    A contractor building a hospital needs to know what that project costs, how much profit it earns and what the client should pay along the way. The contract lasts more than one accounting period, so those questions arise before the building is finished.

    Follow the project from its price agreement to its site records. An escalation clause can pass rate rises to the client; direct costs are traced to the contract. Start by identifying the contract as a separate cost unit.

  2. 2
    ExplanationGive the project its own account

    Each contract has a separate account collecting the costs it causes. The work is large, long-term and built to the client’s specification, usually at the client’s site.

    This is specific-order costing, like job costing. The long duration and site setting add interim profit and payment calculations to the task of collecting costs for one identifiable order.

  3. 3
    ExampleTrace the support cost

    The hospital site employs its own supervisor and security guard. Their wages can be traced to that project, just like the concrete delivered there. They are direct costs even though they support the construction work.

    The head office accountant serves several projects. That salary is a central cost, shared among contracts when the contractor’s policy allocates it.

  4. 4
    ChallengeClassify two salaries

    A bridge site has its own manager. A regional payroll clerk serves five sites. Which salary is directly traceable to the bridge, and why?

    ---reveal---

    The bridge manager’s salary is direct because it serves that contract alone. The payroll clerk’s salary is shared across sites. Classification follows traceability, so a management or support role can still be a direct site cost.

  5. 5
    ConnectionSeparate approval from payment

    The contractor performs the work and the client orders and pays for it. The client’s architect, engineer or surveyor certifies the value completed to the agreed standard.

    A certificate records approved work. A progress payment follows the payment terms, with retention held as security against defects. Certified value can therefore exceed cash already received.

  6. 6
    ExplanationAsk who bears a cost rise

    With a fixed price, higher costs reduce the contractor’s profit; savings increase it. Later client-requested changes are priced separately as change orders, also called variations.

    With cost-plus pricing, the client reimburses allowable actual costs and pays an agreed fee. A percentage fee rises with the allowable costs. A fixed fee stays unchanged when costs rise.

  7. 7
    Key InsightA percentage fee changes the incentive

    If profit is a percentage of reimbursable costs, spending more also raises the fee. This weakens the contractor’s incentive to control costs and leaves the client carrying most of the cost risk.

    Defining allowable costs, inspecting records, choosing a fixed fee or agreeing a guaranteed maximum price can limit that exposure. Cost-plus still suits work whose cost is hard to estimate reliably.

  8. 8
    ExampleCalculate covered rate increases

    An escalation clause allows 500 tons of steel at a base rate of $800 per ton and 20,000 labor hours at $30. Actual rates are $860 and $31.50.

    The steel increase is $60 per ton: 500 tons gives $30,000. The labor increase is $1.50 per hour: 20,000 hours gives another $30,000. The total claim is $60,000, using the agreed quantities.

  9. 9
    ExampleApply the threshold first

    Now let the same clause cover only rate increases beyond 5% of each base. Steel’s threshold is $840 per ton, leaving $20 eligible and a $10,000 claim.

    Labor’s threshold is $31.50 per hour, exactly the actual rate, so there is no eligible increase. The total claim falls to $10,000. The threshold limits the covered part of the rate increase before quantities are applied.

  10. 10
    ChallengeConnect site use with price risk

    A fixed-price road contract allows 300 tons of steel at $700 per ton. Its clause covers the full rise above that base. Actual steel costs $735 per ton, and waste raises use to 315 tons. What claim is allowed, and who bears the extra quantity cost?

    ---reveal---

    The claim is 300 × $35 = $10,500. It uses the agreed 300 tons. The contractor bears the extra quantity cost caused by waste; that cost remains traceable to the road contract.

  11. 11
    RecapKeep three records distinct

    The contract identifies the cost unit. Site records show the resources it uses, including directly traceable support costs. The pricing agreement determines which costs or rate changes the client pays for.

    Certification values approved work and supports staged payments. Keeping the price, actual costs and payment terms distinct prepares the account for profit and cash calculations.

2

Turn site records into contract cost

14 steps
Adjust materials and wages, charge plant use and apply shared costs to complete a contract account.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMeasure the work’s cost
  2. 2
    ExampleStart with materials available
  3. 3
    TipRead the direction of a movement
  4. 4
    ExampleMatch labor and expenses to the year
  5. 5
    ChallengeAdjust wages before totaling
  6. 6
    ExplanationCharge the value plant uses up
  7. 7
    ExampleUse time for short equipment use
  8. 8
    ExampleRemove sold plant from the pool
  9. 9
    ChallengeAvoid counting the disposal twice
  10. 10
    ExplanationApply the rate to its named base
  11. 11
    ExampleRecover the shared cost pool
  12. 12
    ChallengeShare the correct amount
  13. 13
    ChallengeComplete Contract 14’s cost
  14. 14
    RecapFollow the cost layers
3

From work value to recognized profit or loss

18 steps
Calculate notional profit, apply alternative profit rules and recognize the full expected loss.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMake two profit decisions
  2. 2
    ExplanationValue each kind of work correctly
  3. 3
    ExampleFind the certified cost
  4. 4
    Key InsightSee why the vertical layout agrees
  5. 5
    ChallengeRecover notional profit
  6. 6
    ExampleApply the work-certified rule
  7. 7
    ExplanationChoose the stage fraction
  8. 8
    ExampleCompare the alternative result
  9. 9
    ChallengeSelect the fraction from progress
  10. 10
    ExampleUse the estimated final profit
  11. 11
    ExampleFind only the later year’s amount
  12. 12
    ExplanationCharge a loss without a fraction
  13. 13
    ExampleLook beyond the apparent profit
  14. 14
    ExampleFind the provision that reaches the loss
  15. 15
    ChallengeSeparate loss from provision
  16. 16
    TipInclude the defects still to fix
  17. 17
    ChallengeLet the forecast change the decision
  18. 18
    RecapFinish with a forecast check
4

Follow cash and combine contract results

13 steps
Calculate certificate payments, track retention releases and total separately assessed contract results.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionKeep cash and profit on separate tracks
  2. 2
    ExplanationStart from cumulative entitlement
  3. 3
    ExampleDeduct the earlier payment
  4. 4
    ChallengeFind payment due and total owed
  5. 5
    ExampleRelease retention in stages
  6. 6
    ExampleTrack separately maturing retentions
  7. 7
    ExplanationGive every contract its own column
  8. 8
    ExampleCalculate the first contract’s result
  9. 9
    ExampleAdd a loss and an early-stage profit
  10. 10
    Key InsightOne policy still gives different shares
  11. 11
    ChallengeTotal the period results
  12. 12
    ChallengeConnect the statement with cash
  13. 13
    RecapRead the result and the client balance

Contract Costing practice questions

40 Practice Questions in 4 sets

Set 1: Value work and calculate interim profit10 Practice Questions

Question 1 of 10

Opening plant is $320,000 and additions are $70,000. Plant with book value $18,000 is sold for $12,000. Closing plant is $300,000. What total plant cost, including the disposal result, is charged?
  1. $72,000
  2. $90,000
  3. $78,000
  4. $84,000
Show answerHide answer
Answer: C
Depreciation is $320,000 + $70,000 − $18,000 − $300,000 = $72,000. Add the $6,000 loss on sale to get $78,000. Deducting proceeds directly also gives $78,000; adding a separate $6,000 loss after that combined calculation would double count it and give $84,000.

Question 2 of 10

One contract receives 35% of a head office cost pool. The other contract’s 65% share is $156,000. What amount is charged to the first contract?
  1. $84,000
  2. $54,600
  3. $101,400
  4. $240,000
Show answerHide answer
Answer: A
The $156,000 is 65% of the pool, so the total pool is $156,000 ÷ 0.65 = $240,000. The first contract’s 35% share is $84,000. Multiplying $156,000 by 35% gives $54,600, but that applies the share to another contract’s allocation instead of to the whole pool.

Question 3 of 10

Work costing $42,000 has been completed since the last certificate. Its expected sales value is $50,000. At what amount should this uncertified work enter the contract account?
  1. $50,000
  2. $8,000
  3. $46,000
  4. $42,000
Show answerHide answer
Answer: D
Uncertified work is valued at its $42,000 cost. The expected $50,000 sales value contains an $8,000 margin that is not taken on work still awaiting certification. Using that sales value would bring profit into the account before the client’s approval supports it.

Question 4 of 10

A contract shows $1,460,000 cumulative work certified at the current year-end and $890,000 at the previous year-end. How much was certified during the current year?
  1. $1,460,000
  2. $2,350,000
  3. $570,000
  4. $890,000
Show answerHide answer
Answer: C
The current certificate includes everything certified since the contract began. Subtract the earlier cumulative $890,000 from $1,460,000 to get $570,000 certified this year. Using $1,460,000 as this year’s figure would count work already certified in the previous period again.

Question 5 of 10

A $2,400,000 contract has certified work of $960,000 and notional profit of $150,000. Under the work-certified rule, how much profit is recognized to date?
  1. $60,000
  2. $54,000
  3. $150,000
  4. $90,000
Show answerHide answer
Answer: A
Certified stage is $960,000 ÷ $2,400,000 = 40%. Applying it to $150,000 notional profit gives $60,000 recognizable to date. The $90,000 remainder is profit retained, not profit recognized; it stays unrecognized against the uncertainty of finishing the contract.

Question 6 of 10

A contract priced at $1,800,000 has work certified of $630,000, cost of certified work of $540,000 and cash received of $567,000. Use the stage-fraction rule. What profit is recognizable to date?
  1. $31,500
  2. $54,000
  3. $30,000
  4. $27,000
Show answerHide answer
Answer: D
Notional profit is $630,000 − $540,000 = $90,000, and the certified stage is 35%, selecting one-third. The cash ratio is 90%, so profit is 1/3 × $90,000 × 0.9 = $27,000. The $31,500 result uses the work-certified rule instead of the specified stage-fraction rule.

Question 7 of 10

At the end of Year 2, a $2,500,000 contract has certified work of $2,000,000 and certified cost of $1,600,000, both cumulative. Earlier recognized profit was $95,000. Under the work-certified rule, what profit belongs to Year 2?
  1. $320,000
  2. $225,000
  3. $305,000
  4. $80,000
Show answerHide answer
Answer: B
Cumulative notional profit is $400,000 and the certified stage is 80%, giving $320,000 recognizable to date. Deduct the $95,000 already recognized to get $225,000 for Year 2. Reporting $320,000 as the current-year result would count the earlier profit a second time.

Question 8 of 10

A contract has certified work valued at $410,000 and total cost of $460,000, including $20,000 of uncertified work. It is 40% complete. What notional loss is charged now?
  1. $12,000
  2. $20,000
  3. $30,000
  4. $50,000
Show answerHide answer
Answer: C
Certified cost is $460,000 − $20,000 = $440,000, exceeding certified value by $30,000. Charge the full $30,000 loss now. The $12,000 result applies the 40% completion fraction to the loss, but cautious profit fractions do not reduce a loss already identified.

Question 9 of 10

A $96,000 machine is depreciated at 25% per year and used on a site for two months. What depreciation is charged to that site?
  1. $24,000
  2. $4,000
  3. $12,000
  4. $16,000
Show answerHide answer
Answer: B
Annual depreciation is $96,000 × 25% = $24,000. Two months’ use costs $24,000 × 2/12 = $4,000. Charging the full $24,000 would assign twelve months of depreciation to a contract that used the machine for only two months.

Question 10 of 10

A site has opening materials of $24,000, receipts of $132,000, transfers out of $7,000 and closing materials of $19,000. What materials cost belongs to its work?
  1. $106,000
  2. $137,000
  3. $168,000
  4. $130,000
Show answerHide answer
Answer: D
Materials available are $24,000 + $132,000 = $156,000. Deduct $7,000 transferred out and $19,000 still on site to get $130,000 used. The $106,000 figure omits opening materials, even though those resources were available for the current period’s work.
Set 2: Identify costs and build the account10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A contractor hires a security guard exclusively for a bridge site. How should the guard’s wages be classified?
  1. A shared establishment charge
  2. A direct cost of the bridge
  3. A plant department overhead
  4. A period administration cost
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A contractor is comparing a two-day workshop repair with an 18-month school construction project at the client’s site. What extra accounting need arises from the school project’s duration?
  1. Allocate all site salaries through one overhead rate.
  2. Postpone every profit calculation until work is complete.
  3. Use client receipts as the value of completed work.
  4. Calculate interim profit and staged client payments.
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A fixed-price contract remains at $960,000 while estimated costs rise from $810,000 to $855,000. What is the revised expected profit?
  1. $105,000
  2. $150,000
  3. $195,000
  4. $45,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A cost-plus contract reimburses allowable costs and pays a fixed $54,000 fee. Allowable costs increase from $600,000 to $660,000 with no change in scope. What total price is payable?
  1. $654,000
  2. $719,400
  3. $714,000
  4. $660,000
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A new contract receives materials costing $146,000. It returns $9,000 to stores and has $17,000 unused at year-end. There are no other movements. What materials cost is charged?
  1. $137,000
  2. $146,000
  3. $154,000
  4. $120,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A contract’s wages paid are $186,000, including opening arrears of $8,000. Closing wages owing are $11,000. Direct expenses paid are $29,000, including $4,000 for next year. What combined labor and direct-expense cost belongs to this period?
  1. $222,000
  2. $214,000
  3. $230,000
  4. $211,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Plant arrives at a contract at a value of $175,000 and is valued at $139,000 at year-end. No plant leaves or is added. What revaluation charge belongs to the contract?
  1. $36,000
  2. $139,000
  3. $175,000
  4. $314,000
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Overheads are charged at 12% of direct materials used plus subcontractor charges. Materials used are $225,000, subcontractors $50,000 and direct labor $180,000. What overhead charge applies?
  1. $21,600
  2. $27,000
  3. $33,000
  4. $54,600
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Total contract cost is $478,000 after site-asset deductions. Work not certified costs $28,000 and work certified is valued at $525,000. What is notional profit?
  1. $47,000
  2. $75,000
  3. $103,000
  4. $28,000
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A cumulative certificate values work at $780,000. Retention is 8%, and previous payments received total $515,000. What further payment is due now?
  1. $265,000
  2. $717,600
  3. $243,800
  4. $202,600
Show answerHide answer

Save this lesson to see this answer.

Set 3: Apply pricing rules and forecast the result10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A cost-plus contract uses a percentage fee. What happens to that fee when allowable actual costs increase and the percentage stays unchanged?
  1. It rises with the allowable costs.
  2. It stays fixed at the original fee.
  3. It falls as allowable costs rise.
  4. It becomes the unspent cost budget.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

An escalation clause covers only steel-rate increases beyond 4% of a $750 base rate, using an agreed 400 tons. The actual rate is $810 and actual usage is 430 tons. What claim is allowed?
  1. $24,000
  2. $25,800
  3. $12,900
  4. $12,000
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A head office pool of $360,000 is shared in proportion to prime cost. A contract’s prime cost is $420,000 out of a $1,400,000 total. What establishment charge does it receive?
  1. $151,200
  2. $108,000
  3. $252,000
  4. $120,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A profitable contract is 60% complete and has a 90% cash ratio. Its notional profit is $210,000. Under the stage-fraction rule, how much is recognizable to date?
  1. $126,000
  2. $63,000
  3. $140,000
  4. $189,000
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A nearly complete contract has price $4,000,000, costs to date of $3,100,000 and estimated completion costs of $400,000. Certified work is $3,680,000. Use estimated total profit × certified stage, with no cash factor. What profit is recognizable to date?
  1. $828,000
  2. $460,000
  3. $500,000
  4. $368,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A completed contract has final price $1,720,000 and total cost $1,390,000. Profit of $205,000 was recognized in earlier years. What additional profit is recognized at completion?
  1. $330,000
  2. $535,000
  3. $125,000
  4. $185,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A $1,250,000 contract has cost $760,000 so far and is expected to require another $545,000, including defect correction. What whole-contract loss should be recognized now?
  1. $55,000 loss
  2. $35,000 loss
  3. $20,000 loss
  4. $490,000 profit
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A $900,000 contract has certified work of $585,000 and cost to date of $550,000, all on certified work. Completion is expected to cost $395,000. What provision against the notional result produces the full expected contract loss?
  1. $45,000
  2. $35,000
  3. $10,000
  4. $80,000
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A three-year contract pays $900,000 at each year-end, less 6% of that year’s work certified held for four months. Certification in Year 3 is $1,100,000. Earlier years’ retentions have been released. How much cash has been received by the end of Year 3?
  1. $2,538,000
  2. $2,634,000
  3. $2,700,000
  4. $2,646,000
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Under the work-certified rule, Contract A has notional profit of $160,000 at 75% completion; B has a $22,000 notional loss; C has notional profit of $80,000 at 30% completion. No whole-contract losses are forecast for A or C, and no profit was recognized earlier. What total result is recognized?
  1. $218,000 profit
  2. $100,800 profit
  3. $122,000 profit
  4. $144,000 profit
Show answerHide answer

Save this lesson to see this answer.

Set 4: Resolve period balances and compare contracts10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

In a vertical contract costing statement, what costs form prime cost before separately presented subcontractor charges?
  1. Materials, labor and allocated overheads
  2. Materials, plant and head office charges
  3. Labor, plant and direct site expenses
  4. Direct materials, labor and expenses
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

Opening plant is $210,000, additions $90,000, plant transferred out at $45,000 and closing plant $185,000. A draft charges the revaluation difference and adds another $20,000 depreciation for the same plant and period. What total plant-use charge is correct?
  1. $90,000
  2. $70,000
  3. $115,000
  4. $50,000
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A draft includes all $430,000 of materials received in cost and values $35,000 of uncertified work at $44,000. It reports $92,000 notional profit. Closing unused materials of $18,000 have not been deducted. What is corrected notional profit?
  1. $83,000
  2. $119,000
  3. $101,000
  4. $110,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Under the work-certified rule, contract price, certified value and certified cost remain unchanged while the client delays a payment. How does the delay affect profit recognizable to date?
  1. It leaves recognizable profit unchanged.
  2. It reduces profit by the unpaid amount.
  3. It reduces profit by the retention rate.
  4. It postpones all profit until payment.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A $3,200,000 contract has cumulative certified work of $2,240,000, cumulative certified cost of $1,760,000 and cumulative cash received of $2,016,000. Earlier profit recognized is $86,000. Under the stage-fraction rule, what profit belongs to the current year?
  1. $336,000
  2. $250,000
  3. $202,000
  4. $288,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A $1,600,000 contract has certified work of $1,080,000 and cost to date of $1,020,000, all on certified work. Remaining construction is estimated at $550,000, plus $75,000 of punch-list repairs. No result was recognized earlier. What result should be recognized now?
  1. $60,000 profit
  2. $45,000 loss
  3. $30,000 profit
  4. $105,000 loss
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Cumulative certified work is $950,000, retention is 10% and cash received is $790,000. What amounts are currently due excluding retention, and held as retention?
  1. $160,000 due; $95,000 retained
  2. $65,000 due; $160,000 retained
  3. $95,000 due; $65,000 retained
  4. $65,000 due; $95,000 retained
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A fully certified $2,200,000 contract has 8% retention. Half is released at substantial completion and half after the defects period. After the first release, with all other payments made, what does the client still owe?
  1. $88,000
  2. $176,000
  3. $2,024,000
  4. $2,112,000
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Two contracts use the work-certified rule. Contract M has $240,000 cumulative notional profit, a 60% stage and $52,000 recognized earlier. Contract N has $150,000 cumulative notional profit, an 80% stage and $74,000 recognized earlier. Neither forecasts a whole-contract loss. What combined profit belongs to the current period?
  1. $264,000
  2. $126,000
  3. $138,000
  4. $190,000
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A multi-contract statement totals $184,000 recognized profit. One column contributes $24,000 profit, but a revised forecast requires that contract to show a $36,000 whole-contract loss. No result on that contract was recognized earlier. What is the corrected statement total?
  1. $148,000
  2. $160,000
  3. $196,000
  4. $124,000
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

56 Key Terms, each with its definition

A

Abnormal material loss
An abnormal material loss is a loss from an exceptional event, removed from the contract’s costs and charged to profit and loss.
Materials destroyed by a site fire are separated from the cost of the contract’s normal work.
Accrued wages
Accrued wages are wages earned by workers but still unpaid at period-end; they are added when calculating the period’s labor cost.
The last week’s unpaid site wages are included in this year’s charge even though payment follows later.
Allocated fixed overhead
An allocated fixed overhead is a contract’s share of central support costs, charged using an agreed base and allocation policy.
The regional construction department’s costs are shared using a percentage of direct material cost.
Allocation base
An allocation base is the measure used to share a cost pool among contracts, such as direct materials, labor or prime cost.
When prime cost is the base, each contract’s share follows its proportion of total prime cost.
Allowable cost
An allowable cost is an actual cost the client agrees to reimburse under a cost-plus contract’s rules about eligible spending.
The client checks site invoices against the agreement before including them in reimbursable costs.
Anticipated loss
An anticipated loss is the excess of estimated total contract cost over contract price, recognized in full when it can be foreseen.
A profitable result so far does not prevent a loss when the forecast remaining work is too costly.

B

Balance brought down (b/d)
A balance brought down is a prior period’s closing amount entered as an opening balance in the new period’s contract account.
The new year begins with debits for the materials, plant and uncertified work brought down from last year.
Balance carried down (c/d)
A balance carried down is a closing amount retained for the next period, such as materials, plant or uncertified work still on site.
Closing materials of $18,000 are carried down at year-end before appearing as next year’s opening balance.
Book value
Book value is the recorded remaining value of plant at a date, used to value a transfer or calculate the result on disposal.
A mixer’s $14,000 book value is compared with its $10,000 sale proceeds to find a $4,000 loss.

C

Cash ratio
The cash ratio in the stage-fraction rule is cumulative cash received divided by cumulative work certified, reducing interim profit.
If $810,000 has been received against $900,000 certified, the stage-fraction cash ratio is 90%.
Change order (variation)
A change order, also called a variation, is a client-requested change to the original work that is priced separately.
The client requests an additional entrance, and its agreed price changes the contract price.
Client (contractee)
A client, also called a contractee, is the party that orders the work and pays the contractor under the agreed contract terms.
The client receives certificates of approved work and makes the related progress payments.
Client balance
The client balance is cumulative work certified less cumulative cash received, including retention and other unpaid certified amounts.
Before an interim payment is made, the client balance can exceed the retention currently held.
Closing materials on site
Closing materials on site are unused materials remaining at period-end, deducted from current cost and carried into the next period.
Unused steel worth $12,000 reduces the current material charge and becomes next year’s opening balance.
Combined recognized result
A combined recognized result is the sum of separately calculated contract profits and full losses belonging to the same period.
A $110,000 recognized profit and a $25,000 recognized loss give a combined $85,000 profit.
Contract account
A contract account is the separate record collecting the costs and work values of one contract to measure its result.
The account for one school project records its materials, labor, plant use and certified work.
Contract costing
Contract costing is a method that collects costs for a large, long-term project carried out to a client’s specification at its site.
A builder keeps separate contract accounts for a hospital extension and a bridge under construction.
Contract costing statement
A contract costing statement presents work values, costs and recognized results for one or several contracts in a consistent layout.
Columns for three sites show each contract’s prime cost, notional result and profit retained.
Contractor
A contractor is the business that undertakes the agreed work for the client and collects the project’s costs in its contract account.
The contractor orders concrete, employs site workers and hires a specialist electrical subcontractor.
Cost of work certified
The cost of work certified is total cost to date less uncertified work at cost, after the closing site assets have been deducted.
From $520,000 total adjusted cost, subtract $30,000 uncertified work to isolate certified cost.
Cost pool
A cost pool is a total amount of shared costs collected before allocating it among contracts using the stated shares or base.
A known 40% allocation of $80,000 reveals a head office cost pool of $200,000 for all contracts.
Cost unit
A cost unit is the item, service or project whose cost is measured; in contract costing, it is the individual contract.
Costs recorded against Contract 62 show what that particular road project has used and earned.
Cost-plus contract
A cost-plus contract reimburses allowable actual costs and adds an agreed fee, calculated as a percentage or a fixed amount.
Emergency repair costs are reimbursed, with the agreed fee added to determine the client’s price.
Cumulative certificate
A cumulative certificate states the total value of work approved since the contract began, including amounts certified earlier.
Subtract the previous certificate total to find how much additional work was certified this year.
Current-period result
A current-period result is the profit or loss belonging to the period, with earlier recognized profit removed from a cumulative calculation.
The contractor deducts $64,000 taken last year from the recognizable total before reporting this year.

D

De-escalation clause
A de-escalation clause reduces the contract price when specified input rates fall, following the adjustment terms in the agreement.
A fall in a covered material rate reduces the price when the contract contains a de-escalation clause.
Direct site cost
A direct site cost is a cost traceable to one contract, including site support costs incurred exclusively for that project.
The temporary site office’s electricity is charged directly to the contract served by that office.

E

Escalation clause
An escalation clause adjusts a contract price for increases in named input rates above agreed base rates or thresholds.
A steel-price clause allows a claim for eligible rate increases using the agreed steel quantity.
Establishment charges
Establishment charges are allocated head office and central administration costs, such as office rent and accounting salaries.
A contract receives 30% of the head office pool under the contractor’s agreed allocation policy.
Estimated cost to complete
Estimated cost to complete is the forecast cost of all remaining contract work, including expected defect correction and snagging.
The forecast includes both the final construction stage and repairs identified on the punch list.
Estimated-profit rule
The estimated-profit rule for nearly complete work multiplies estimated total profit by the share of contract price certified.
A reliable cost-to-complete estimate lets a nearly finished contract base its calculation on expected final profit.

F

Fixed-price contract
A fixed-price contract sets the price for the specified work in advance, leaving the contractor to bear most cost-overrun risk.
When concrete costs rise without a price adjustment, the fixed-price contractor’s profit falls.

I

Internal plant hire charge
An internal plant hire charge is a charge from a central plant department to a contract for the equipment’s use on that site.
The plant department charges a road contract for the months its excavator works on the project.

L

Loss on plant disposal
A loss on plant disposal is the excess of book value over proceeds when plant is sold or scrapped, charged once to the contract.
The plant working separates depreciation from the loss when a mixer is sold below its book value.

N

Notional loss
A notional loss arises when certified work costs more than its certified value; the whole amount is charged to profit and loss.
Certified work costing $460,000 against a $430,000 certificate gives a $30,000 notional loss.
Notional profit
Notional profit is certified work’s value minus its cost, before applying the rule for profit recognized on an unfinished contract.
A contract can show $90,000 notional profit while only part of that amount is recognized now.
Notional profit margin
A notional profit margin is notional profit divided by work certified, expressed as a percentage of that certified sales value.
A $54,000 notional profit on $270,000 certified work gives a 20% margin for comparing sites.

P

Plant
Plant is machinery and equipment used on a contract, whose cost of use is measured by depreciation or an applicable hire charge.
An excavator still worth $64,000 at year-end retains an asset value after its current site use.
Prepayment
A prepayment is an amount paid for a future period’s expense, deducted when measuring the expense belonging to the current period.
The part of a site insurance payment covering next year is removed from this year’s direct expenses.
Prime cost
Prime cost is the total of direct materials, direct labor and direct expenses, shown as a labeled subtotal in the cost statement.
The contractor totals materials, site wages and equipment hire before adding shared overheads.
Profit recognized
Profit recognized is the share of a contract’s profit taken to profit and loss for the relevant period under the specified rule.
A cumulative recognizable total is reduced by earlier recognized profit to find this year’s amount.
Profit retained
Profit retained is the portion of notional profit not yet recognized, carried forward as a reserve against unfinished-work uncertainty.
If notional profit is $120,000 and $48,000 is recognized, the contract retains $72,000 of profit.
Progress payment
A progress payment is an installment the client pays while a contract continues, normally based on certified work and payment terms.
The second progress payment deducts cash already received from the new cumulative entitlement.
Provision for remaining-work loss
A provision for remaining-work loss is a charge against the notional result that makes the recognized result equal the full expected loss.
A $70,000 provision turns a $25,000 notional profit into a $45,000 anticipated whole-contract loss.
Prudence
Prudence is caution in recognizing uncertain profit, while charging foreseeable contract losses in full as soon as they are identified.
The contractor retains some interim profit because completing the remaining work can bring extra costs.

R

Retention (retainage)
Retention, or retainage, is certified money withheld by the client as security until the agreed completion and defect conditions are met.
The client holds $45,000 from certified work and pays it later under the retention release terms.
Retention period
A retention period is the agreed time for which certified money is withheld before release, subject to the contract’s conditions.
A six-month retention from one certificate can be released while a later certificate’s retention remains held.
Revaluation method
The revaluation method measures plant use from opening and arrival values less the values of plant remaining or leaving the site.
A crane’s arrival value less its closing site value gives depreciation when it has no other movements.

S

Snagging (punch-list repairs)
Snagging is correcting minor defects found near completion; in the US, the list of defects needing correction is a punch list.
Expected costs of correcting faulty doors and finishes are added to the contract’s completion forecast.
Stage of completion
The stage of completion used in these rules is work certified divided by contract price, measuring the share of value approved.
Certified work of $750,000 on a $1,500,000 contract gives a certified stage of completion of 50%.
Stage-fraction rule
The stage-fraction rule selects a profit fraction from certified progress and, in the profit bands, also applies the cash ratio.
A contract at 60% completion uses two-thirds of notional profit before multiplying by its cash ratio.
Subcontractor
A subcontractor is a separate business hired by the main contractor to carry out a specified part of the contract’s work.
A roofing subcontractor’s invoice is charged to the building contract that required its work.
Substantial completion
Substantial completion, also called practical completion, is a completion stage at which some agreements release part of the retention.
Under a half-release arrangement, the client pays half the accumulated retention at substantial completion.

W

Work certified
Work certified is completed work approved by the client’s architect or surveyor, valued at contract price including profit margin.
A certificate values approved bridge work at $860,000, even though the client has paid less cash.
Work not certified
Work not certified is work completed since the latest certificate and valued at cost because the client has not yet approved its value.
Construction completed after the inspection is carried in the account without adding a profit margin.
Work-certified rule
The work-certified rule recognizes notional profit multiplied by work certified divided by contract price, without a cash factor.
A contract at a 40% certified stage recognizes 40% of its notional profit under the work-certified rule.

About this lesson

By StudeliReport a mistake

Make your own Study Materials

Turn your notes, slides and documents into Study Guides, Practice Questions, Flashcards and 6 more tools.