Contract Costing
BeginnerLesson 6 of 11 in Introduction to Management Accounting Course
What you will learn
- Explain why long, site-based work such as construction is costed contract by contract, and compare the main ways a contract price is set and adjusted.
- Describe the features of contract costingDescribe the cost unit, the people and the documents involved in contract costing, and explain how it differs from job costing.
- Compare fixed-price and cost-plus contracts and apply escalation clausesExplain who carries the cost risk in fixed-price and cost-plus contracts, and calculate the price change an escalation clause allows.
- Describe the features of contract costing
- Build the cost side of a contract account: direct materials, labor and expenses, subcontractors, plant on site, allocated overheads and establishment charges.
- Charge materials, labor, direct expenses and subcontractorsCalculate the materials, labor and direct expenses charged to a contract for a period, find its prime cost and add subcontractors' charges.
- Account for plant used on a contractCharge a contract with the cost of using machinery and equipment, including plant sent to the site, transferred, sold or scrapped.
- Add allocated overheads and establishment chargesCharge a contract with its share of costs that are not traceable to one site and complete its total cost.
- Charge materials, labor, direct expenses and subcontractors
- Value the work done, find the notional profit, recognize a prudent share of it, and charge expected losses in full.
- Value work done and calculate notional profitValue work certified and work not certified, find the cost of work certified and calculate notional profit, including for a contract that continues from an earlier year.
- Recognize a prudent share of profit on incomplete contractsCalculate the profit to take on an unfinished contract with the main profit-recognition rules, including in later years and at completion.
- Charge anticipated losses in fullRecognize a loss on a contract as soon as it is known, both when the work to date shows a loss and when the whole contract is expected to make one.
- Value work done and calculate notional profit
- Calculate what the client pays and still owes, including retentions, and present several contracts in one contract costing statement.
- Calculate progress payments, retentions and amounts dueWork out the payment due on each certificate, the retention held and released, and the amount the client still owes.
- Prepare a contract costing statement for several contractsPresent several contracts side by side, find each one's profit or loss to recognize, and total the result for the period.
- Calculate progress payments, retentions and amounts due
Contract Costing study guide
1Understand the contract and its price
A long construction contract ties up people, equipment and cash across several accounting periods. Before working out its result, identify whose work is being costed, which costs belong to that site and how the client has agreed to pay. The pricing method explains who bears rising costs; the contract account then shows what the work actually costs. Certificates connect progress on site with both interim profit and payments.
1.1 How a contract becomes a cost unit
Contract costing collects the costs of a large, long-term project carried out to a customer's specification. A hospital, bridge or road has its own contract account. This lets the contractor see the resources used and the result earned on that particular project.
Follow the work to its site
The cost unit is the individual contract. Work takes place at the customer's site and usually continues beyond one accounting period. Each contract is priced separately, reflecting its own specification. These features explain why site records matter: deliveries, time records and equipment movements must identify the contract that caused them.
Most costs are direct because they can be traced to one site. A site manager's salary, temporary fencing, site security and the site's electricity all belong to that contract. They do not become indirect merely because they are not bricks or building labor. Ask whether the cost exists only because of this site. If it does, charge it directly. Head office administration serves several contracts and needs a sharing basis if it is charged to them.
Know who does what
The contractor carries out the work. The client, also called the contractee, orders and pays for it. Their agreed total price is the contract price. A subcontractor is a separate business hired by the contractor for a defined part, such as electrical installation. The contractor includes that firm's charge in the contract's costs.
The client's architect, engineer or quantity surveyor inspects progress and issues a certificate valuing work completed to the required standard. The certificate is a record of approved work. It supports a progress payment, but the client holds back a percentage called retention, or retainage, as security against defects. The certificate's value and the cash paid therefore differ.
Connect contract costing with job costing
Both methods collect costs for a specific order. A three-day repair of a delivery van in a workshop is a job. A two-year apartment project at the client's site is a contract. Workshop jobs usually absorb production overheads through a predetermined rate. On a construction site, many comparable support costs are directly traceable, leaving a smaller share to allocate.
The long duration also creates two separate period-end decisions. First, how much profit should be reported before the contract is complete? Second, how much must the client pay for work approved so far? Cost records alone answer neither question; the account also needs the certified value, the profit policy and the payment terms.
Waiting until completion to report every dollar of profit would leave earlier years without the profit earned during their work and put it all into the final year. Contract costing recognizes a cautious share while work continues. Expected losses are charged as soon as they can be foreseen. A busy site can therefore have substantial work completed, some profit recognized and a different amount of cash received.
Key Takeaways
- Each contract is a separate cost unit with its own contract account.
- Traceable site support costs are direct costs, including supervision and site utilities.
- Certification values approved work; progress payments follow the payment terms.
- Long duration creates separate calculations for interim profit and cash payments.
1.2 Set the price and share cost risk
A contract's price determines how cost changes affect the contractor and client. Start by identifying whether the agreement fixes a price or reimburses allowable costs. Then read any change-order or escalation terms before calculating an adjustment.
Fixed-price and cost-plus agreements
In a fixed-price contract, the total price is agreed at the start. Higher costs reduce the contractor's profit and can create a loss; savings increase its profit. This gives the contractor a strong reason to estimate accurately and control spending. A fixed price covers the original specification. Later client-requested changes, called variations or change orders, are priced separately and change the contract price.
In a cost-plus contract, the client reimburses allowable actual costs and pays an agreed fee. The fee may be a percentage of cost or a fixed amount. Allowable costs of $1,600,000 plus 12% give a fee of $192,000 and a price of $1,792,000. With a fixed fee, rising costs raise the reimbursement but do not raise the fee.
Cost-plus pricing suits work whose cost is hard to estimate, such as emergency storm repairs or a first-of-a-kind project. The client carries most of the risk of allowable costs rising. A percentage fee weakens the incentive to save because higher costs also increase the fee. Clients can define allowable costs, inspect records, agree a fixed fee or set a guaranteed maximum price.
Calculate an escalation claim
An escalation clause adjusts a fixed price for rises in named input rates, commonly materials and labor. It shares inflation risk with the client. A de-escalation clause lowers the price when the named rates fall.
For each eligible input:
- Find the increase above its base rate, or above the threshold in the clause.
- Multiply that eligible rate increase by the agreed quantity.
- Add the separate claims.
Suppose the contract allows 500 tons of steel at a base rate of $800 per ton and 20,000 labor hours at $30 per hour. Actual rates are $860 and $31.50. The steel increase is $60 per ton, giving $30,000. The labor increase is $1.50 per hour, also giving $30,000. The total claim is $60,000.
If 520 tons were actually used because of waste, the claim still uses the allowed 500 tons. The clause compensates for the named price change; the extra quantity remains the contractor's cost.
Apply a threshold before multiplying
Now let the clause cover only the increase beyond 5% of each base rate. The steel threshold is $800 × 1.05 = $840 per ton. The eligible increase is $20, so the steel claim is $10,000. The labor threshold is $30 × 1.05 = $31.50 per hour. The actual rate only reaches it, so there is no eligible labor increase.
The total claim is now $10,000. Applying 5% to the whole contract price would calculate a different quantity. The input list, threshold and allowed quantities each limit what the client reimburses.
Key Takeaways
- A fixed price places most cost risk on the contractor; allowable cost reimbursement shifts it toward the client.
- A percentage fee rises with allowable costs; a fixed fee does not.
- Client-requested changes are priced separately from the original work.
- An escalation claim uses only named inputs and eligible rate increases.
- Use the agreed quantity even when actual usage is higher.
- With a threshold, calculate the increase beyond that threshold first.
2Build the cost side of the account
A contract account measures the cost of work done during the period. That means adjusting deliveries for materials left on site, payments for amounts owed or prepaid, and equipment values for the use made of plant. After calculating direct costs and prime cost, add subcontractors and the agreed shares of central costs. Keeping these workings separate makes it easier to spot an omitted asset balance or an overhead rate applied to the wrong amount.
2.1 Measure materials and direct costs used
The contract account collects the costs belonging to one contract. In a T-account, debit costs and credit reductions in cost or values carried forward. A vertical statement shows the same calculation as additions and deductions down a column.
Materials: follow both deliveries and movements
Include materials delivered directly by suppliers, issued from central stores and transferred in from another contract. Add opening materials on site in a later year. Deduct returns to stores, transfers to other contracts and scrap or surplus sale proceeds. Finally deduct unused closing materials: these remain available for later work.
For Contract 14 in Year 1:
| Materials movement | Amount |
|---|---|
| Supplier deliveries | $380,000 |
| Issues from stores | $45,000 |
| Less returns to stores | ($8,000) |
| Less transfer to Contract 15 | ($6,000) |
| Less materials still on site | ($27,000) |
| Materials charged | $384,000 |
A transfer out reduces this contract's cost and becomes a charge to the receiving contract. Closing materials are carried down, marked c/d, and brought down, b/d, as the next year's opening balance. Charging all deliveries immediately would include materials the work has not yet used.
Labor and expenses: match the period
Labor includes site workers and site supervisors. Start with wages paid, add closing wages owing and deduct opening wages owing that were settled in those payments. Opening arrears belong to the previous period; closing arrears belong to this one.
Contract 14 pays $310,000 and still owes $14,000 at year-end, with no opening arrears. Labor charged is $324,000. For a different site paying $90,000, with opening arrears of $4,000 and closing arrears of $7,000, the period's labor is $93,000.
Direct expenses are other traceable site costs, including equipment hire, insurance and site utilities. Amounts paid in advance for a later period are deducted. Contract 14 pays $52,000 of direct expenses, including a $3,000 prepayment, so the expense is $49,000. Its crane hire adds $18,000.
Show prime cost and subcontractors clearly
Prime cost is direct materials plus direct labor plus direct expenses. Contract 14's subtotal is $384,000 + $324,000 + $49,000 + $18,000 = $775,000. Label this subtotal so the direct costs are visible before further charges.
The electrical subcontractor charges $96,000. This is a direct cost of Contract 14, shown here immediately after prime cost. Other layouts include subcontractors within prime cost; the charge must appear once in either layout.
Distinguish normal waste from abnormal loss
Normal waste and minor site damage remain part of the contract's cost. If damaged materials are sold as scrap, credit the proceeds. Materials destroyed in an abnormal event such as a fire are removed from the contract cost and charged to the profit and loss account. Removing the abnormal loss prevents it from distorting the cost of the contract's ordinary work.
Key Takeaways
- Materials charged include opening stock and receipts, less returns, transfers out, scrap proceeds and closing stock.
- Labor charged equals wages paid plus closing arrears minus opening arrears.
- Deduct expenses prepaid for a later period.
- Label prime cost: direct materials, direct labor and direct expenses.
- Charge subcontractors once, using the chosen statement layout.
- Normal waste stays in contract cost; abnormal loss is transferred to profit and loss.
2.2 Charge the use of plant
Plant is the machinery and equipment used on site: excavators, cranes, mixers and scaffolding. A contract bears the value used up while the plant works there. Equipment that still has value at the end remains an asset.
Revalue plant on a long-term site
Under the revaluation method, charge the value of plant when it arrives, or its opening value brought down. Deduct the value of plant remaining at the end or leaving the site. The reduction in value is the charge for use.
Contract 14 receives plant valued at $240,000. Its year-end value is $180,000. The contract's plant charge is $60,000. In a T-account, the $240,000 is a debit and the $180,000 closing asset is a credit. The closing $180,000 becomes next year's opening debit.
Materials left on site and plant left on site are both carried forward, but for different reasons. The materials have not yet been used. The plant has been used and retains value for future use; the account charges only the value consumed.
Charge depreciation for the time used
For short site use or centrally managed equipment, charge the depreciation or internal hire rate for the time on the contract. An excavator costing $120,000 with depreciation of 20% a year has annual depreciation of $24,000. Three months on a site gives a $6,000 charge: $24,000 × 3/12.
Do not also charge the purchase price. Likewise, a revaluation difference already measures depreciation for that plant and period; adding separate depreciation would count the same use twice. Plant fuel, maintenance, repairs and operators' wages are additional direct running costs.
Account for plant that moves or is sold
When plant transfers to another contract or returns to the central yard, deduct its value at that date. The receiving contract or yard takes over that value. The sending contract retains the depreciation arising while it used the plant.
For a site with opening plant of $500,000 and additions of $100,000, suppose a mixer with book value $20,000 is sold for $14,000. Closing plant is $510,000. Separate the calculation into:
- Depreciation: $500,000 − $20,000 + $100,000 − $510,000 = $70,000.
- Loss on sale: $20,000 − $14,000 = $6,000.
- Total plant charge: $76,000.
Deducting the mixer's book value removes it from the pool being revalued. The separate $6,000 loss then captures the shortfall in proceeds. A gain would reduce the contract cost.
An equally valid combined calculation deducts sale proceeds directly: $500,000 + $100,000 − $14,000 − $510,000 = $76,000. Once proceeds have been used in this combined route, do not add the loss on sale again. Before totaling, identify whether a disposal figure is book value or proceeds; they play different roles in the two presentations.
Key Takeaways
- Charge plant use through depreciation or an internal hire rate, not its whole purchase price.
- Deduct closing plant and transfer values under the revaluation method.
- Plant sold can be handled through book value plus a separate loss, or proceeds in a combined calculation.
- Never charge both methods for the same use or disposal.
- Add plant running costs separately.
2.3 Apply shared costs to the right base
Some costs support more than one site. A contract bears an agreed share of these costs when the contractor's policy allocates them. Separate the rate from the amount it applies to before doing any multiplication.
Read the overhead basis exactly
Allocated fixed overheads may include central stores, the plant yard or a regional construction department. A policy may charge a percentage of direct materials, direct labor or prime cost. Those bases give different amounts even when the percentage is the same.
Contract 14 is charged construction overheads at 10% of direct material cost. Its materials used are $384,000, so overheads are $38,400. The $425,000 of deliveries and store issues is not the correct base because returns, transfers out and closing materials have already reduced the materials used.
If the basis is "direct material cost plus subcontracting costs," add both amounts before applying the rate. For example, materials of $150,000 and subcontractors of $40,000 at 8% give $15,200. Applying 8% only to materials would omit $3,200. Closing plant affects the plant charge; it does not belong in a materials-based calculation.
Share head office establishment charges
Establishment charges are the contract's share of head office and central administration: directors' and office salaries, head office rent, accounting, estimating and legal departments. They are indirect because they serve the business as a whole. Site supervision, by comparison, is directly traceable to its contract.
A proportional share follows this calculation: shared cost pool × this contract's base ÷ total base for all contracts. If head office costs are $400,000 and prime cost is the basis, a contract with $500,000 of the total $2,000,000 prime cost receives one-quarter of the pool, or $100,000.
Sometimes the total pool must be found first. If one contract's 40% share is $240,000, total head office costs are $240,000 ÷ 0.4 = $600,000. A second contract bearing 60% receives $360,000. Multiplying the first contract's $240,000 by 60% would treat a part as though it were the whole.
Finish the cost statement
Use a clear sequence: direct materials, labor and expenses; prime cost; subcontractors; plant; allocated overheads; establishment charges. For Contract 14:
| Cost item | Amount |
|---|---|
| Prime cost | $775,000 |
| Subcontractors | $96,000 |
| Plant charge | $60,000 |
| Construction overheads | $38,400 |
| Establishment charges | $85,600 |
| Total cost | $1,055,000 |
The $85,600 establishment charge here is a separate supplied allocation. It is added to, not calculated from, the $38,400 construction overhead charge. Keep the two labels distinct so one pool is not charged twice.
Some contractors leave head office costs as period costs in the profit and loss account. Others apportion them to contracts. Follow the specified policy: a rate or allocation belongs to the contract statement only when that policy charges it there.
Key Takeaways
- Identify the stated base before applying an overhead rate.
- Establishment charges share central administration costs among contracts.
- Find a cost pool from a known share by dividing by that share.
- Keep direct site costs separate from indirect head office costs.
- Add each cost pool once to reach total contract cost.
3Find the result and the amount to recognize
The value approved by the client and the cost of producing that work establish a contract's notional result. An unfinished contract then needs a second decision: how much of that result belongs in profit and loss now. Work through valuation, the specified profit rule and any forecast loss in that order. For a continuing contract, keep totals to date separate from the amount already reported so earlier profit is not counted again.
3.1 Value work and find notional profit
A certificate values approved work at its sales value. Costs record the resources used. Bringing these two measures together reveals the notional profit on work certified, while keeping uncertified work at cost.
Separate the two parts of work done
Work certified has been completed and approved by the client's architect or surveyor. Its value includes profit because it is measured at contract price. Certificate values are cumulative: a later certificate covers the approved work since the contract began.
Work not certified is work completed since the latest certificate. Value it at cost. Adding a profit margin before certification would bring unsupported profit into the account.
Total cost to date includes both certified and uncertified work after deducting materials and plant still on site. To isolate the cost of certified work, subtract the cost of work not certified.
Work through Contract 14
Contract 14 has total cost of $1,055,000, uncertified work costing $55,000 and certified work valued at $1,200,000.
- Cost of work certified: $1,055,000 − $55,000 = $1,000,000.
- Notional profit: $1,200,000 − $1,000,000 = $200,000.
The profit is notional because the contract is unfinished; future costs can change the final result. It is the profit available before deciding how much to recognize now.
A vertical statement reaches the same answer by adding work certified and work not certified, then deducting total cost. Here the work value is $1,255,000, giving $1,255,000 − $1,055,000 = $200,000. Uncertified work appears on both sides at cost and contributes no profit.
Read the contract account
In a T-account, debit the costs and credit work certified, work not certified c/d, materials on site c/d and plant on site c/d. The balancing notional profit appears on the debit side. That balancing position does not make it an expense; it completes an account whose credit values exceed its costs. The profit is then split between the part recognized and the part retained.
Contract 14's account can show the gross charges and separate credits:
| Debit | Amount | Credit | Amount |
|---|---|---|---|
| Materials received | $425,000 | Work certified | $1,200,000 |
| Labor charged | $324,000 | Work not certified c/d | $55,000 |
| Direct expenses, including crane hire | $67,000 | Materials returned | $8,000 |
| Subcontractors | $96,000 | Materials transferred out | $6,000 |
| Plant received | $240,000 | Materials on site c/d | $27,000 |
| Construction overheads | $38,400 | Plant on site c/d | $180,000 |
| Establishment charges | $85,600 | — | — |
| Notional profit | $200,000 | — | — |
| Total | $1,476,000 | Total | $1,476,000 |
Here closing assets and material movements appear as credits. The vertical calculation already deducted them to reach net cost of $1,055,000; do not deduct them again from that net figure.
Continue into another year
Contract 14 begins Year 2 with opening materials of $27,000, plant of $180,000 and uncertified work of $55,000. These were carried forward from Year 1 and enter the later account as opening debits. Work already done but uncertified at the earlier year-end must still be included when it is certified later.
If cumulative certification reaches $2,400,000 at the end of Year 2, certification during Year 2 is $2,400,000 − $1,200,000 = $1,200,000. Keep these labels visible in your workings: "to date" and "during Year 2" answer different questions. Cash received is a third figure governed by payment terms; it cannot replace certified value in the notional profit calculation.
Key Takeaways
- Work certified is valued at contract price; work not certified is valued at cost.
- Cost of work certified equals total cost to date minus uncertified work at cost.
- Notional profit equals certified value minus the cost of certified work.
- The vertical and T-account layouts give the same result.
- Bring closing site balances forward to the next year.
- Subtract earlier cumulative certification to find certification during a year.
3.2 Choose and apply the profit rule
An unfinished contract still faces cost overruns, defects, disputes and delays. Recognize only the prudent share of its notional profit and carry the rest forward as profit retained. Prudence limits the amount taken now, while matching connects profit with the periods in which work is performed.
Start with stage of completion
Measure the stage as work certified ÷ contract price. Contract 14 has $1,200,000 certified against a $3,000,000 price, so it is 40% complete. This measure uses certified value; cash receipts or cost spent measure something else.
The rules below are alternatives. Use the organization's policy or the rule specified in the question.
Work-certified rule
Profit recognized = notional profit × work certified ÷ contract price.
For Contract 14, $200,000 × 40% = $80,000. Profit retained is $200,000 − $80,000 = $120,000. Cash received does not enter this rule.
Stage-fraction rule
First identify the certified stage, then apply its fraction and the cash ratio:
| Certified stage | Profit recognizable |
|---|---|
| Under 25% | None |
| 25% to under 50% | 1/3 × notional profit × cash received ÷ work certified |
| 50% to under 90% | 2/3 × notional profit × cash received ÷ work certified |
Contract 14 is in the one-third band. If cash received is 90% of work certified, profit recognized is 1/3 × $200,000 × 0.9 = $60,000. Profit retained is $140,000. This rule reduces the amount for both incomplete work and incomplete payment. Do not multiply its result by the 40% stage again: that stage selected the fraction.
Nearly complete contracts
At about 90% completion or more, the estimated-profit rule uses the expected final result. Estimated total profit is contract price minus estimated total cost, including completion and defect costs. Multiply that estimated profit by work certified ÷ contract price.
A $3,000,000 contract with estimated total cost of $2,650,000 has expected profit of $350,000. With $2,760,000 certified, the stage is 92% and recognizable profit is $322,000. Some versions add the cash ratio; include it when the specified rule requires it.
Find this year's profit from cumulative figures
For continuing contracts, calculate the recognizable amount to date and subtract profit recognized earlier. At the end of Contract 14's Year 2, cumulative certified value is $2,400,000 and the cost of certified work is $1,950,000. Notional profit is $450,000. Under the work-certified rule, $450,000 × 80% = $360,000 is recognizable to date. Less the $80,000 already recognized leaves $280,000 for Year 2.
At completion, recognize the remaining final profit: final contract price minus total cost minus profit recognized in earlier years. A loss is never reduced by one of these profit fractions.
Key Takeaways
- Use the specified profit rule; the alternative rules give different answers.
- Measure stage from work certified divided by contract price.
- The work-certified rule ignores cash; the stage-fraction rule includes the cash ratio.
- Profit retained is the unrecognized part of notional profit.
- Nearly complete work uses estimated total profit under the estimated-profit rule.
- Subtract earlier recognized profit from the cumulative recognizable amount.
- At completion, recognize the balance of final profit.
3.3 Recognize the full expected loss
Prudence treats losses more urgently than profit. A profit on unfinished work is recognized cautiously, but a loss is charged in full as soon as it can be foreseen. Check both the result on work certified and the expected result of the whole contract.
Charge a notional loss without a fraction
A notional loss arises when certified work costs more than its certified value. Contract 22 has total cost of $345,000, including $15,000 of uncertified work. Cost of work certified is therefore $330,000. With work certified at $300,000, the notional loss is $30,000.
Charge all $30,000 to profit and loss. Multiplying it by the completion ratio or by one-third would delay part of a loss already shown by the work done. Do not use a profitable contract to reduce this loss before recognizing it. Each contract's result is measured separately.
Look ahead even when work so far is profitable
A contract can show a notional profit and still be expected to lose overall. Add the estimated cost to complete to cost incurred so far, including the expected cost of correcting defects. Compare that total with the contract price.
Consider a contract priced at $1,000,000. Costs incurred are $600,000, all for certified work. Certified value is $640,000, so the work to date appears to earn $40,000. However, completion is expected to cost another $460,000. Total expected cost is $1,060,000, producing an anticipated loss of $60,000.
Recognize a $60,000 loss now and take none of the $40,000 notional profit. Looking only at certified work would miss the larger cost still to come.
Make the statement reach the whole loss
The remaining work has a value of $1,000,000 − $640,000 = $360,000, but it is expected to cost $460,000. Its expected loss is $100,000. Charge a provision of $100,000 against the current $40,000 notional profit. The net result becomes a $60,000 loss.
The $100,000 provision and the $60,000 whole-contract loss are different amounts. Subtracting only $60,000 from the $40,000 profit would report a loss of $20,000 and fail to recognize the full expected loss. Subtracting the provision and then charging the whole loss again would double count it.
Update the cost to complete
Snagging means correcting minor defects found near completion; the US term for the list of defects is a punch list. The contractor bears the cost of correcting its work, so the forecast must include these repairs along with the remaining construction work.
Revisit the estimate when costs rise faster than planned, input price rises lack escalation cover, delays may bring penalties or variations are disputed. Use the current best estimate and revise it when new information changes the forecast. The amount is based on an estimate, but waiting for final certainty would leave the current result overstated.
Key Takeaways
- Charge a notional loss in full without applying a profit fraction.
- Forecast total cost, including completion and defect correction.
- A positive notional profit can coexist with an expected whole-contract loss.
- The provision must make the result equal the full expected loss.
- Reassess the estimate when costs or conditions change.
4Calculate cash due and compare contracts
A contractor needs to know both what its work earns and when the client pays. Certificate values, cash received and retention answer different questions. Calculate each payment from the contract's timing terms, then use a consistent statement to compare results across sites. Working down one contract column at a time keeps shared costs, cautious profit and full losses in the right places before the period's results are added together.
4.1 Calculate payments and retention
Progress payments are installments paid while work continues. They are normally based on certificates showing the cumulative value approved to date. Read whether a figure is a cumulative entitlement, the next payment or a retention balance before calculating it.
Calculate the payment on a new certificate
Retention, called retainage in the US, is the share the client withholds as security against defects. A common range is about 3% to 10%, with the actual rate set by the agreement. It remains owed to the contractor and is not a contract cost.
Amount due = cumulative work certified × (1 − retention rate) − payments already received.
With 10% retention, Contract 14's first certificate of $1,200,000 permits a payment of $1,080,000. Its second certificate raises cumulative work certified to $2,100,000. The cumulative payable amount is $1,890,000. After subtracting the first $1,080,000 payment, the new amount due is $810,000.
Retention held is $210,000, or 10% of the cumulative certificate. Paying $1,890,000 again on the second certificate would pay twice for work already covered by the first payment.
Distinguish retention from all money still owed
The client's total balance is cumulative work certified minus cumulative cash received. Once the second payment is made, this is $2,100,000 − $1,890,000 = $210,000, exactly the retention. Before that payment is made, the balance also includes the unpaid $810,000 currently due.
A cash ratio of cash received ÷ work certified enters the stage-fraction profit rule. It is 90% once all payments due under these terms have been made. The work-certified profit rule does not use cash received, so a payment delay does not by itself reduce profit under that rule.
Follow the retention release dates
A common arrangement releases half the retention at practical completion, called substantial completion in the US. The rest is paid after the defects period once the punch-list items have been corrected. On a fully certified $3,000,000 contract with 10% retention, $300,000 is held: $150,000 is released at each stage.
The exact release terms matter. If defects are not corrected, the client may use part of the retained amount to pay another firm to do the work. A retention balance is therefore money withheld for security, with release tied to the agreed conditions.
Some agreements release each certificate's retention after a fixed period. Consider a four-year $8,000,000 contract with equal yearly installments of $2,000,000, less 10% of that year's work certified held for six months. Year 3 certification is $2,500,000. By the end of Year 3, the earlier years' retentions have been released. Cumulative receipts are 3 × $2,000,000 − $250,000 = $5,750,000.
Here only the current year's retention is outstanding. Keeping the earlier released amounts in the deduction would understate cash received. A short timeline of certification, deduction and release dates is useful whenever retentions mature separately.
Key Takeaways
- Calculate cumulative payment entitlement, then subtract cash already received.
- Retention is delayed cash owed to the contractor, not an expense.
- Client balance equals cumulative work certified minus cumulative cash received.
- An unpaid current payment makes the client balance larger than retention alone.
- Apply each retention release date before totaling receipts.
- Only the stage-fraction profit rule uses the cash ratio.
4.2 Build a statement for several contracts
A contract costing statement places separate contract columns beside a total column. Use the same rows throughout, but calculate each contract's costs and result on its own. A common layout makes the differences between sites visible without combining their profit decisions.
Set up the rows
Begin with work certified and work not certified at cost, then total the work value. Deduct materials, labor and direct expenses, showing the prime cost subtotal. Add subcontractors, plant, allocated overheads and establishment charges to reach total cost. Follow with notional profit or loss, the result recognized and profit retained.
For continuing contracts, show opening balances of materials, plant and uncertified work in the appropriate cost workings. Keep cumulative profit calculations separate from the current year's result. Subtract prior recognized profit only after calculating the recognizable amount to date.
Work down each contract column
The following costs are already measured to date. Contracts 21–23 have no separate direct expenses in this example, so prime cost is materials plus labor.
| Item | Contract 21 | Contract 22 | Contract 23 | Total |
|---|---|---|---|---|
| Contract price | $1,800,000 | $900,000 | $2,000,000 | $4,700,000 |
| Work certified | $1,350,000 | $300,000 | $200,000 | $1,850,000 |
| Work not certified | $60,000 | $15,000 | $10,000 | $85,000 |
| Work value | $1,410,000 | $315,000 | $210,000 | $1,935,000 |
| Materials | $420,000 | $120,000 | $60,000 | $600,000 |
| Labor | $380,000 | $130,000 | $50,000 | $560,000 |
| Prime cost | $800,000 | $250,000 | $110,000 | $1,160,000 |
| Subcontractors | $90,000 | $30,000 | $20,000 | $140,000 |
| Plant | $70,000 | $25,000 | $15,000 | $110,000 |
| Overheads | $64,000 | $22,000 | $12,000 | $98,000 |
| Establishment charges | $56,000 | $18,000 | $13,000 | $87,000 |
| Total cost | $1,080,000 | $345,000 | $170,000 | $1,595,000 |
Subtract uncertified work from each total cost to find certified costs of $1,020,000, $330,000 and $160,000. Compare these with the respective certificates to find the notional results below.
Apply the rule before adding results
Under the work-certified rule, the stages are 75%, about 33.3% and 10%. Apply each profitable contract's stage and charge Contract 22's loss in full:
| Result | Contract 21 | Contract 22 | Contract 23 | Total |
|---|---|---|---|---|
| Notional profit/(loss) | $330,000 | ($30,000) | $40,000 | $340,000 |
| Recognized profit/(loss) | $247,500 | ($30,000) | $4,000 | $221,500 |
| Profit retained | $82,500 | $0 | $36,000 | $118,500 |
Under the stage-fraction rule with 90% cash ratios, Contract 21 recognizes $198,000, Contract 22 still charges $30,000 and Contract 23 recognizes nothing because it is under 25% complete. The total is $168,000. A single fraction applied to combined notional profit would overlook these different stages and the full-loss rule.
Read what the results suggest
Contract 21's notional margin is $330,000 ÷ $1,350,000, about 24.4%; Contract 23's is 20%. Contract 22 is losing money and needs a fresh estimate of its cost to complete. Check every column for an anticipated whole-contract loss before accepting the total. A positive overall result does not remove a loss that belongs to one contract.
Key Takeaways
- Use matching rows and a separate column for each contract.
- Calculate each contract result and check its forecast loss before totaling.
- Apply the profit rule separately to each profitable contract.
- Charge loss-making contracts in full.
- For continuing work, deduct earlier recognized profit to find the period result.
- Use margins and forecasts to investigate weak contract performance.
Contract Costing examples
1Follow a contract from agreement to site
11 steps
- 1IntroductionStart with one project
A contractor building a hospital needs to know what that project costs, how much profit it earns and what the client should pay along the way. The contract lasts more than one accounting period, so those questions arise before the building is finished.
Follow the project from its price agreement to its site records. An escalation clause can pass rate rises to the client; direct costs are traced to the contract. Start by identifying the contract as a separate cost unit.
- 2ExplanationGive the project its own account
Each contract has a separate account collecting the costs it causes. The work is large, long-term and built to the client’s specification, usually at the client’s site.
This is specific-order costing, like job costing. The long duration and site setting add interim profit and payment calculations to the task of collecting costs for one identifiable order.
- 3ExampleTrace the support cost
The hospital site employs its own supervisor and security guard. Their wages can be traced to that project, just like the concrete delivered there. They are direct costs even though they support the construction work.
The head office accountant serves several projects. That salary is a central cost, shared among contracts when the contractor’s policy allocates it.
- 4ChallengeClassify two salaries
A bridge site has its own manager. A regional payroll clerk serves five sites. Which salary is directly traceable to the bridge, and why?
---reveal---
The bridge manager’s salary is direct because it serves that contract alone. The payroll clerk’s salary is shared across sites. Classification follows traceability, so a management or support role can still be a direct site cost.
- 5ConnectionSeparate approval from payment
The contractor performs the work and the client orders and pays for it. The client’s architect, engineer or surveyor certifies the value completed to the agreed standard.
A certificate records approved work. A progress payment follows the payment terms, with retention held as security against defects. Certified value can therefore exceed cash already received.
- 6ExplanationAsk who bears a cost rise
With a fixed price, higher costs reduce the contractor’s profit; savings increase it. Later client-requested changes are priced separately as change orders, also called variations.
With cost-plus pricing, the client reimburses allowable actual costs and pays an agreed fee. A percentage fee rises with the allowable costs. A fixed fee stays unchanged when costs rise.
- 7Key InsightA percentage fee changes the incentive
If profit is a percentage of reimbursable costs, spending more also raises the fee. This weakens the contractor’s incentive to control costs and leaves the client carrying most of the cost risk.
Defining allowable costs, inspecting records, choosing a fixed fee or agreeing a guaranteed maximum price can limit that exposure. Cost-plus still suits work whose cost is hard to estimate reliably.
- 8ExampleCalculate covered rate increases
An escalation clause allows 500 tons of steel at a base rate of $800 per ton and 20,000 labor hours at $30. Actual rates are $860 and $31.50.
The steel increase is $60 per ton: 500 tons gives $30,000. The labor increase is $1.50 per hour: 20,000 hours gives another $30,000. The total claim is $60,000, using the agreed quantities.
- 9ExampleApply the threshold first
Now let the same clause cover only rate increases beyond 5% of each base. Steel’s threshold is $840 per ton, leaving $20 eligible and a $10,000 claim.
Labor’s threshold is $31.50 per hour, exactly the actual rate, so there is no eligible increase. The total claim falls to $10,000. The threshold limits the covered part of the rate increase before quantities are applied.
- 10ChallengeConnect site use with price risk
A fixed-price road contract allows 300 tons of steel at $700 per ton. Its clause covers the full rise above that base. Actual steel costs $735 per ton, and waste raises use to 315 tons. What claim is allowed, and who bears the extra quantity cost?
---reveal---
The claim is 300 × $35 = $10,500. It uses the agreed 300 tons. The contractor bears the extra quantity cost caused by waste; that cost remains traceable to the road contract.
- 11RecapKeep three records distinct
The contract identifies the cost unit. Site records show the resources it uses, including directly traceable support costs. The pricing agreement determines which costs or rate changes the client pays for.
Certification values approved work and supports staged payments. Keeping the price, actual costs and payment terms distinct prepares the account for profit and cash calculations.
2Turn site records into contract cost
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMeasure the work’s cost
- 2ExampleStart with materials available
- 3TipRead the direction of a movement
- 4ExampleMatch labor and expenses to the year
- 5ChallengeAdjust wages before totaling
- 6ExplanationCharge the value plant uses up
- 7ExampleUse time for short equipment use
- 8ExampleRemove sold plant from the pool
- 9ChallengeAvoid counting the disposal twice
- 10ExplanationApply the rate to its named base
- 11ExampleRecover the shared cost pool
- 12ChallengeShare the correct amount
- 13ChallengeComplete Contract 14’s cost
- 14RecapFollow the cost layers
3From work value to recognized profit or loss
18 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake two profit decisions
- 2ExplanationValue each kind of work correctly
- 3ExampleFind the certified cost
- 4Key InsightSee why the vertical layout agrees
- 5ChallengeRecover notional profit
- 6ExampleApply the work-certified rule
- 7ExplanationChoose the stage fraction
- 8ExampleCompare the alternative result
- 9ChallengeSelect the fraction from progress
- 10ExampleUse the estimated final profit
- 11ExampleFind only the later year’s amount
- 12ExplanationCharge a loss without a fraction
- 13ExampleLook beyond the apparent profit
- 14ExampleFind the provision that reaches the loss
- 15ChallengeSeparate loss from provision
- 16TipInclude the defects still to fix
- 17ChallengeLet the forecast change the decision
- 18RecapFinish with a forecast check
4Follow cash and combine contract results
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionKeep cash and profit on separate tracks
- 2ExplanationStart from cumulative entitlement
- 3ExampleDeduct the earlier payment
- 4ChallengeFind payment due and total owed
- 5ExampleRelease retention in stages
- 6ExampleTrack separately maturing retentions
- 7ExplanationGive every contract its own column
- 8ExampleCalculate the first contract’s result
- 9ExampleAdd a loss and an early-stage profit
- 10Key InsightOne policy still gives different shares
- 11ChallengeTotal the period results
- 12ChallengeConnect the statement with cash
- 13RecapRead the result and the client balance
Contract Costing practice questions
Set 1: Value work and calculate interim profit10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Identify costs and build the account10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Apply pricing rules and forecast the result10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Resolve period balances and compare contracts10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Abnormal material loss
Accrued wages
Allocated fixed overhead
Allocation base
Allowable cost
Anticipated loss
B
Balance brought down (b/d)
Balance carried down (c/d)
Book value
C
Cash ratio
Change order (variation)
Client (contractee)
Client balance
Closing materials on site
Combined recognized result
Contract account
Contract costing
Contract costing statement
Contractor
Cost of work certified
Cost pool
Cost unit
Cost-plus contract
Cumulative certificate
Current-period result
D
De-escalation clause
Direct site cost
E
Escalation clause
Establishment charges
Estimated cost to complete
Estimated-profit rule
F
Fixed-price contract
I
Internal plant hire charge
L
Loss on plant disposal
N
Notional loss
Notional profit
Notional profit margin
P
Plant
Prepayment
Prime cost
Profit recognized
Profit retained
Progress payment
Provision for remaining-work loss
Prudence
R
Retention (retainage)
Retention period
Revaluation method
S
Snagging (punch-list repairs)
Stage of completion
Stage-fraction rule
Subcontractor
Substantial completion
W
Work certified
Work not certified
Work-certified rule
About this lesson