Budgeting and Budgetary Control
BeginnerLesson 8 of 11 in Introduction to Management Accounting Course
What you will learn
- Describe what a budget is and what it does for planning, coordination, motivation and control, then follow how the separate budgets are prepared in order and combined into a master budget.
- Explain what budgets are for and where they fall shortDefine a budget, tell it apart from a forecast, and weigh the benefits of budgetary control against its limitations.
- Organize the budget process from the principal budget factor to the master budgetFollow the steps of budget preparation, identify the principal budget factor, and trace how the sales, production, resource, capital and cash budgets combine into the master budget.
- Explain what budgets are for and where they fall short
- Turn the sales plan into the quantities to produce, then budget the materials, purchases, labor and overheads each period needs, in units and in dollars.
- Prepare the sales budget and the production budgetBudget sales in units and dollars, then work out how many units to make each period once the inventory plan is taken into account.
- Budget materials usage and purchasesCalculate the materials production will use, the quantity and cost of materials to buy once the materials inventory plan is applied, and the goods a trading business must purchase.
- Budget direct labor, overheads and closing inventoryWork out the labor hours and cost production needs, allowing for idle time and overtime, budget overheads and selling and administrative expenses from cost behavior, and value the planned closing inventory.
- Prepare the sales budget and the production budget
- Forecast when cash will come in and go out, build a month-by-month cash budget, and use it to plan for shortages and surpluses.
- Schedule budgeted cash receiptsTurn cash and credit sales into the cash expected each month, allowing for discounts, bad debts and other receipts, and budget the closing accounts receivable.
- Schedule budgeted cash paymentsWork out when purchases, wages, expenses and capital spending will be paid, leave out non-cash items, and budget the closing accounts payable.
- Prepare, interpret and act on a cash budgetLay out a monthly cash budget, carry balances forward, test what-if changes, and recommend actions for a shortage or a surplus.
- Schedule budgeted cash receipts
- Bring the functional and cash budgets together into a budgeted income statement and a budgeted balance sheet, and explain why budgeted profit and budgeted cash differ.
- Prepare a budgeted income statementCalculate budgeted revenue, cost of goods sold, gross profit, expenses and net income for the budget period on the accrual basis.
- Prepare a budgeted balance sheetProject the closing assets, liabilities and owner's equity from the opening balance sheet and the other budgets, and check that it balances.
- Explain why budgeted profit and budgeted cash differReconcile budgeted net income with the budgeted change in cash, classify budgeted cash flows, and compare the cash budget with a statement of cash flows.
- Prepare a budgeted income statement
- Flex a budget to the level of activity actually achieved, calculate and interpret budget variances, and report them so managers can act.
- Flex a budget to the actual level of activityExplain why a fixed budget can mislead and prepare a flexible budget using variable, fixed, mixed and stepped cost behavior.
- Calculate, report and act on budget variancesCompare actual results with the flexible budget, label variances favorable or unfavorable, reconcile budgeted and actual profit, and decide which differences to investigate.
- Flex a budget to the actual level of activity
- Explain how the way budgets are set and used affects motivation, and recognize and reduce the unhelpful behavior budgets can encourage.
- Set budgets that motivateCompare imposed and participative budgeting, judge how difficult targets should be, and connect budgets with goal congruence, incentives and fair evaluation.
- Recognize and limit dysfunctional budget behaviorIdentify budgetary slack, spending to use up a budget, short-term decisions and other games, and explain ways to reduce them.
- Set budgets that motivate
Budgeting study guide
1Explain why organizations budget and how a budget is built
A budget gives different departments one agreed plan. Sales targets, staffing, purchases and cash must fit together before managers commit resources. Learn how a budget differs from a forecast, what managers gain from comparing plans with results, and why the factor limiting activity determines where preparation starts. The separate budgets are then reviewed together until the business has a workable master budget.
1.1 Explain what budgets are for and where they fall short
A budget is an agreed plan for a future period, expressed in money and often in quantities. Units sold, kilograms bought and hours worked help explain the dollar amounts. Managers approve the plan before the period begins and use it to guide decisions.
A plan and an estimate do different jobs
A forecast estimates what is likely to happen. A budget states what management plans to achieve and what resources it authorizes. Brightline's forecast might say, "April demand will probably be about 2,000 lamps." Its sales budget turns that estimate into a commitment: 2,000 lamps at $40 each, giving $80,000 of revenue.
The forecast informs the decision; the approved budget coordinates action. Managers may authorize more advertising to support a higher sales target or additional training to improve service. Budgeting therefore covers revenues, resources and investment as well as cost control.
Give departments a common plan
Budgets serve several connected purposes:
- Planning: identify future resource needs and possible cash shortages.
- Coordination: align sales, production, purchasing and finance.
- Communication: tell managers what results and resources are expected.
- Motivation: give people targets to work toward.
- Authorization: permit spending within agreed limits.
- Control and evaluation: compare results with the plan and assess performance.
Suppose Brightline plans to sell 2,400 lamps in May. The factory plans to make 2,000 and has 300 available in inventory. That provides only 2,300 lamps, leaving 100 orders uncovered. Comparing the two plans exposes the gap early. Managers can arrange overtime, build inventory sooner or revise the sales plan before accepting orders they cannot fill.
Close the control cycle
Budgetary control connects the plan with actual results. First set and communicate the budget. Then record actual results, compare them with budget, calculate the differences and investigate significant ones. Finally, act on the causes or revise the plan when conditions have changed.
A difference is a variance. If delivery spending exceeds budget, a manager needs to find out whether the business made more deliveries, paid higher rates or used extra trips. Each cause suggests a different response. Preparing a budget and putting it away provides no continuing control.
Recognize the limits
Budgets use estimates, so a carefully prepared plan can still become outdated. Preparation also takes staff time. Rigid spending limits may discourage a worthwhile opportunity, and departments may compete for resources or protect easy targets.
Meeting a target must be interpreted. Spending less after producing fewer units does not establish efficient production. Managers compare costs with an allowance for actual activity and consider quality, customer satisfaction and staff turnover. A cost saving that creates complaints or missed deliveries may harm the business even though the spending line looks favorable.
Key Takeaways
- A budget is an approved future plan; a forecast estimates a likely outcome.
- Budgets coordinate quantities, resources and cash as well as setting dollar targets.
- Budgetary control requires comparison, investigation and action.
- Evaluate results with actual activity and non-financial performance in view.
1.2 Organize the budget process from the principal budget factor to the master budget
The separate budgets depend on one another. A production plan cannot promise more than available capacity, and a spending plan must be financeable. Preparation starts by finding the factor that limits activity, then builds and checks the linked plans.
Start with the limiting factor
The principal budget factor is the factor that limits activity during the budget period. It is also called the limiting or key budget factor. Sales demand is often the limit, but materials, skilled labor, machine hours, cash or floor space can be the constraint. Identify it first and prepare its budget first.
Suppose demand is 12,000 units, machine time is 5,000 hours and each unit needs 0.5 hours. Maximum production is:
With 500 finished units already available and no closing inventory planned, maximum sales are 10,500 units. Budgeting sales at 12,000 would leave an impossible production requirement unless managers add capacity, perhaps through extra shifts or subcontracting.
Build the linked budgets
Once the constraint is settled, a manufacturer's normal sequence runs from sales to production, materials usage and purchases, direct labor, and overheads. Production costs and inventory plans feed cost of goods sold. Selling and administrative expenses complete the operating plans. The capital expenditure budget records planned asset purchases and sales; the cash budget schedules the resulting receipts and payments.
| Group | What it plans |
|---|---|
| Functional or operating budgets | Sales, production, resources and operating expenses |
| Capital expenditure budget | Purchases and sales of long-lived assets |
| Financial budgets | Cash and the closing financial position |
The master budget brings the coordinated plans together, summarized in the budgeted income statement, cash budget and budgeted balance sheet. It is prepared for one planned activity level, making it a fixed or static budget. A trading business replaces production and materials schedules with a budget for goods purchased for resale. A service business plans service capacity and hours.
Assign responsibility and allow time to revise
Line managers prepare budgets for their areas. A budget committee coordinates them, with an accountant often serving as budget officer. Owners or the board approve the final plan. A budget manual sets out responsibilities, procedures, formats and deadlines.
The period is usually a year split into months or quarters. Cash may need weekly planning when funds are tight. Shorter periods let managers spot a problem while action can still help.
Drafts are revised until capacity, cash and profit fit. A shortage in the first cash draft may require a revised equipment purchase or borrowing plan. Communicate the approved figures to the managers who will use them, and monitor results during the period.
Use a spreadsheet carefully
Linked input cells let a price or payment-date change update several budgets and make what-if analysis quick. The same links can spread a wrong formula throughout the model. Check formulas, units and versions, and review whether assumptions are realistic. A precise-looking result is still built on estimates.
Key Takeaways
- Identify the principal budget factor before preparing dependent budgets.
- The master budget combines operating, capital expenditure and financial plans.
- A retailer budgets purchases of resale goods in place of production.
- Managers prepare their areas' plans; the committee coordinates and senior management approves them.
- Linked spreadsheets speed revisions but require formula and version controls.
2Prepare the functional budgets for sales, production and resources
Sales give a manufacturer its starting demand, but inventory plans decide how much it must make. Production then determines materials, labor and overhead needs. Follow Brightline Lamps from sales quantities to resource costs, keeping units separate from dollars and purchases separate from usage. A retailer's purchases budget follows the same inventory logic without a manufacturing stage; capacity checks show when a plan needs revision.
2.1 Prepare the sales budget and the production budget
A sales plan answers how many units customers will buy and at what price. A production plan answers how many units the factory must make. Inventory connects them: some sales can come from units already held, while some production must be kept for later sales.
Calculate revenue from the sales plan
The sales budget multiplies budgeted units by the budgeted selling price. Brightline plans a price of $40 per lamp:
| Month | Lamps sold | Sales revenue |
|---|---|---|
| April | 2,000 | $80,000 |
| May | 2,400 | $96,000 |
| June | 2,200 | $88,000 |
| Quarter | 6,600 | $264,000 |
The forecast behind these figures considers past sales, trends, market research, competitors, economic conditions, planned prices and advertising. It also needs a capacity check. Revenue belongs to the month of sale even when the customer will pay later; collections are scheduled separately.
Work from the units needed
To cover sales and leave closing inventory, the factory needs sales units plus desired closing units. Opening units are already available, so subtract them:
Brightline wants closing finished goods inventory equal to 20% of the next month's sales. April begins with 400 lamps. May sales are 2,400, so April must end with 480. April production is therefore:
Making only the 2,000 lamps sold would leave inventory at 400, below the planned 480. The extra 80 lamps build that reserve.
Carry inventory across the months
May opens with April's closing 480. Its closing target uses June sales: 20% of 2,200 is 440. June opens with 440 and closes with 520, based on July sales of 2,600.
| Month | Sales | Closing inventory | Opening inventory | Production |
|---|---|---|---|---|
| April | 2,000 | 480 | 400 | 2,080 |
| May | 2,400 | 440 | 480 | 2,360 |
| June | 2,200 | 520 | 440 | 2,280 |
Notice that May production is below sales because inventory falls by 40. The direction of the inventory change gives a quick check on the calculation.
For the quarter, use the opening balance of April and the closing balance of June:
The three production figures also total 6,720. Do not add the monthly closing inventories: April's closing units become May's opening units and would be counted again.
Check what the factory can deliver
At a normal monthly capacity of 2,300 lamps, May's requirement of 2,360 is 60 too high. Managers can make additional lamps in April, arrange overtime, subcontract or reduce the May sales target. Producing sooner also affects storage, purchases and cash. A service business budgets service hours instead of finished goods; a trading business plans purchases of goods for resale.
Key Takeaways
- Revenue equals budgeted sales units times budgeted price.
- Production equals sales plus desired closing finished goods minus opening finished goods.
- A next-month inventory policy needs next month's sales, including a month beyond the budget period.
- Quarter totals use the first opening and final closing inventory.
- Compare production requirements with capacity before approving the plan.
2.2 Budget materials usage and purchases
Production determines materials usage. The materials inventory plan then determines purchases. Keeping these two calculations separate prevents a common error: treating everything bought as if it were used immediately.
Calculate usage before purchases
Brightline uses 2 kg of aluminum per lamp. Multiply the production budget by that input requirement. April's 2,080 lamps need 4,160 kg, May's 2,360 need 4,720 kg, and June's 2,280 need 4,560 kg. Use production units, including lamps made for inventory; sales units would miss those inputs.
The purchases calculation then applies a second inventory adjustment:
Multiply the quantity purchased by the budgeted price per kilogram to find purchases cost. Finished goods and raw materials have separate inventory policies.
Apply the materials inventory plan
Brightline keeps closing aluminum inventory at 25% of the next month's usage. April begins with 1,040 kg. April's closing target is 25% of May's 4,720 kg, or 1,180 kg. June's closing target is specified as 1,200 kg. Aluminum costs $3 per kg.
| Month | Usage, kg | Closing, kg | Opening, kg | Buy, kg | Cost |
|---|---|---|---|---|---|
| April | 4,160 | 1,180 | 1,040 | 4,300 | $12,900 |
| May | 4,720 | 1,140 | 1,180 | 4,680 | $14,040 |
| June | 4,560 | 1,200 | 1,140 | 4,620 | $13,860 |
April's usage costs $12,480, while purchases cost $12,900. The $420 difference is 140 kg added to materials inventory. Buying the material also creates a payment obligation, but the cash leaves according to supplier credit terms.
Allow for input losses
When a percentage of input is lost, the usable output is only the surviving share. If finished products need 4,800 kg and 4% of input is lost, 96% survives:
Check by applying the loss to input: 4% of 5,000 is 200 kg, leaving 4,800. Adding 4% to the finished requirement gives 4,992 kg, which is too little because the loss percentage applies to the larger input quantity.
Budget a retailer's purchases at cost
Northgate buys finished goods for resale. Sales are $150,000 and gross margin is 40% of sales, leaving cost of goods sold of $90,000. Opening inventory is $20,000 and desired closing inventory is $24,000:
Keep every inventory figure at cost.
Margin measures gross profit as a percentage of sales; markup measures it as a percentage of cost. Northgate's $60,000 gross profit is a 40% margin but a 66⅔% markup. If 40% were a markup, cost would instead be sales divided by 1.40, or $107,142.86. Read which base the percentage uses before preparing purchases.
Key Takeaways
- Materials usage follows production, not sales.
- Purchases adjust usage for the change in materials inventory.
- Divide by the surviving proportion when a percentage of input is lost.
- Retail purchases equal cost of goods sold plus closing inventory minus opening inventory.
- Gross margin uses sales as its base; markup uses cost.
- Purchases feed payables and cash schedules, with timing set by credit terms.
2.3 Budget direct labor, overheads and closing inventory
After materials, budget the people and overhead resources production needs. Quantities come first: calculate working hours, then apply rates. Cost behavior determines overhead allowances, while the inventory valuation method determines which production costs remain in closing inventory.
Turn production into labor hours
Brightline needs 0.5 labor hours per lamp at $24 per hour. April requires 1,040 hours costing $24,960; May requires 1,180 hours costing $28,320; June requires 1,140 hours costing $27,360. May sales are 2,400 lamps, but production is 2,360, so labor must be based on the smaller production quantity.
Paid hours can exceed productive hours. Idle time is paid time without production, such as waiting for materials. If 5% of paid June hours are idle, only 95% produces lamps:
At $24 per hour, wages become $28,800. Adding 5% to productive hours gives only 1,197 hours because it applies the percentage to the wrong base.
Separate normal pay from overtime
In a separate May what-if plan, only 1,100 normal hours are available. The remaining 80 hours cost time-and-a-half, or $36 per hour:
The same result comes from paying all 1,180 hours at $24 and adding the $12 premium on 80 overtime hours. The $960 premium would also increase May's cash wages payment. Brightline's main plan retains $28,320 for May; the overtime calculation is a changed scenario.
Budget overheads by how they behave
Variable production overhead at $2 per lamp gives $4,160 in April, $4,720 in May and $4,560 in June. Fixed production overhead stays at its $15,000 monthly total within the relevant range. A mixed cost needs its fixed amount plus its variable rate times activity.
Selling and administrative expenses sit outside production: office rent, advertising, sales salaries and delivery are examples. Brightline budgets $9,000 a month. A separate 5% commission on April's $80,000 sales would be $4,000; this varies with sales revenue, not production units.
Some costs involve no current cash payment. Brightline's fixed production overhead includes $3,000 monthly depreciation. Its production cost is the full $15,000, while cash paid for that overhead is $12,000. Depreciation spreads the asset cost over its useful life.
Value what remains in inventory
Brightline's variable production cost per lamp is materials $6, direct labor $12 and variable overhead $2, totaling $20. At the end of June, 1,200 kg of aluminum at $3 is worth $3,600. The 520 finished lamps are worth $10,400 under variable costing.
Absorption costing also assigns a share of fixed production overhead to each finished lamp, producing a higher inventory value. Use the costing basis consistently when linking inventory and cost of goods sold; a variable-cost inventory figure cannot simply be inserted into an otherwise absorption-cost calculation.
Key Takeaways
- Direct labor hours follow production; labor cost applies the pay rate to those hours.
- Divide productive hours by the productive share to allow for idle time.
- Pay overtime hours at the full overtime rate, or add only the premium to normal pay for all hours.
- Budget each overhead using its fixed, variable or mixed behavior.
- Depreciation is a production cost without a current cash payment.
- Variable inventory cost excludes fixed production overhead; absorption inventory cost includes a share.
3Prepare and interpret a cash budget
Cash planning follows payment dates. A sale can earn revenue this month while bringing cash next month, and an equipment payment can drain cash without becoming an immediate expense. Build receipts and payments schedules, carry the balances from month to month, and identify the size and cause of a shortage. Brightline's three-month plan shows why a healthy quarter total can still leave the business needing finance during the quarter.
3.1 Schedule budgeted cash receipts
Cash receipts depend on when customers pay. A credit sale creates revenue and an amount owed by the customer; it does not create a cash receipt until collection. A receipts schedule follows each month's sales into the months when money is expected.
Separate cash sales and credit collections
Brightline receives 25% of each month's sales immediately. The remaining 75% is collected in the following month. March sales were $72,000, so April collects $54,000 from March customers. April also receives 25% of its own $80,000 sales, or $20,000:
The full three-month schedule is:
| Receipt | April | May | June |
|---|---|---|---|
| Current cash sales | $20,000 | $24,000 | $22,000 |
| Previous month's credit sales | $54,000 | $60,000 | $72,000 |
| Total customer receipts | $74,000 | $84,000 | $94,000 |
Each credit collection uses the preceding month's sales. May collects 75% of April's $80,000; June collects 75% of May's $96,000. Using current-month credit sales would bring cash into the budget too soon.
The first month needs information from before the budget period. The final month also leaves an amount uncollected: 75% of June's $88,000, or $66,000, becomes closing accounts receivable.
Apply discounts only to the relevant customers
Consider January credit sales of $50,000. Of those customers, 40% pay in February with a 2% discount, 55% pay in March without a discount and 5% never pay.
February collections are:
The $20,000 receivable settled in February is cleared by $19,600 cash and a $400 discount. March collections are $27,500. The remaining $2,500 is a bad debt. Total cash from this sales group is $47,100, not the $50,000 originally invoiced. A bad debt is an amount not collected, not a separate cash payment.
Track the receivable balance
The accounts receivable budget, also called a trade receivables budget, follows amounts customers owe. Add credit sales to opening receivables, then deduct cash collections, discounts allowed and bad debts written off. All deductions must relate to those receivables; cash sales never entered the balance.
Northgate begins with $18,000 owed by customers, makes $150,000 of credit sales and collects $146,000. With no discounts or write-offs, closing receivables are:
Include receipts beyond customers
New borrowing, capital contributed by the owner, share issues, interest received and asset-sale proceeds can also bring in cash. Record the amount received on its expected date.
If equipment with a carrying amount of $7,000 sells for $5,000 cash, enter a $5,000 receipt. The $2,000 loss affects the income statement. Recording only the loss or subtracting it from the proceeds would confuse the accounting result with the cash received.
Key Takeaways
- Cash receipts follow collection dates, including collections from earlier periods.
- Cash sales and collections of credit sales need separate lines.
- Discounts reduce the cash collected; bad debts produce no receipt.
- Receivables rise with credit sales and fall with collections, discounts and write-offs.
- An asset sale brings in its cash proceeds, regardless of its gain or loss.
3.2 Schedule budgeted cash payments
A payments schedule follows the dates on which money leaves the business. Start with the purchases and expense budgets, then apply credit terms and payment arrangements. Add asset and financing payments that do not appear among operating expenses.
Follow purchases into their payment months
Brightline pays for aluminum one month after buying it. April therefore pays March purchases of $12,600. May pays April purchases of $12,900, and June pays May purchases of $14,040. The June purchases of $13,860 are paid after the quarter and remain in closing accounts payable.
Materials used are not the starting point for supplier payments. May's production uses 4,720 kg, but its supplier payment settles the 4,300 kg purchased in April. These quantities answer different questions.
Build the other payment lines
Brightline pays wages, variable overhead and selling and administrative expenses in the month incurred. Fixed production overhead includes $3,000 depreciation within its $15,000 total, leaving a $12,000 monthly cash payment. A machine costing $40,000 is paid for in May.
| Payment | April | May | June |
|---|---|---|---|
| Suppliers | $12,600 | $12,900 | $14,040 |
| Wages | $24,960 | $28,320 | $27,360 |
| Variable overhead | $4,160 | $4,720 | $4,560 |
| Fixed overhead paid | $12,000 | $12,000 | $12,000 |
| Selling and administration | $9,000 | $9,000 | $9,000 |
| Machine | $0 | $40,000 | $0 |
| Total | $62,720 | $106,940 | $66,960 |
Distinguish expenses from payments
Depreciation, bad debts and losses on asset sales are non-cash expenses. Leave them out of cash payments. Depreciation allocates an asset's cost over its life; including both the asset payment and depreciation would count the cost twice in the cash plan.
The reverse distinction matters too. Equipment purchases, loan principal repayments, owner's drawings and dividends use cash without being operating expenses. Income tax payments belong in the cash budget when paid, even when they differ from the period's tax expense. Interest on a loan is an expense; repaying the borrowed principal reduces a liability.
A $6,000 annual insurance premium paid in January belongs entirely in January's cash budget. The income statement charges $500 for each month covered. Scheduling $500 of cash every month would fail to show the actual January funding need.
Track what suppliers are still owed
The accounts payable budget, also called a trade payables budget, starts with opening payables. Add credit purchases, then subtract cash paid and discounts received to reach the closing balance.
Northgate starts with $15,000 owed to suppliers, buys $94,000 on credit and pays $92,000. With no discounts, it ends owing:
This balance goes into the budgeted balance sheet. The $92,000 payment goes into the cash budget, and purchases feed cost of goods sold after the inventory adjustment.
Key Takeaways
- Schedule supplier payments from purchases and credit terms.
- Leave depreciation and other non-cash expenses out of payments.
- Include asset purchases, principal repayments and drawings when cash is paid.
- Prepaid and unpaid expenses create differences between expense and payment.
- Closing payables equal opening payables plus credit purchases minus settlements and discounts.
3.3 Prepare, interpret and act on a cash budget
Combine receipts and payments in monthly columns. The purpose is to see the cash available at each date, so balances must carry forward correctly. A positive result for the whole quarter can conceal a shortage in the middle month.
Build the monthly balances
List and total receipts, then list and total payments. Net cash flow is receipts minus payments. Add it to the opening cash balance to obtain closing cash. That closing balance becomes the next month's opening balance.
Brightline starts April with $8,000:
| Cash budget | April | May | June |
|---|---|---|---|
| Total receipts | $74,000 | $84,000 | $94,000 |
| Total payments | $62,720 | $106,940 | $66,960 |
| Net cash flow | $11,280 | −$22,940 | $27,040 |
| Opening balance | $8,000 | $19,280 | −$3,660 |
| Closing balance | $19,280 | −$3,660 | $23,380 |
May's net cash outflow is $22,940, but its closing shortage is only $3,660 because it begins with $19,280. June begins with that negative balance; resetting June to zero would overstate its closing cash.
Quarterly receipts of $252,000 less payments of $236,620 give a $15,380 increase in cash. Added to the original $8,000, that reaches June's $23,380. This total check does not reveal the May overdraft, so retain the monthly columns.
Diagnose the shortage before choosing finance
A negative closing figure means extra finance is needed by that date. Brightline's May payments include a one-off $40,000 machine. Without it, May payments are $66,940 and net cash inflow is $17,060. Day-to-day trading generates cash; the equipment payment causes the shortage.
Managers can arrange an overdraft for a temporary gap, negotiate staged payment, delay the purchase or lease the machine. A long-lived asset is better matched with long-term finance or owner's capital when it creates a lasting financing need. Arrange finance before the payment falls due.
Other ways to release cash include collecting customer debts sooner, increasing cash sales, negotiating longer supplier credit, reducing inventory, postponing drawings or selling unused assets. Consider the consequences: an early-payment discount reduces receipts, and less inventory can weaken delivery reliability. Choose an action that addresses the cause without damaging the business.
Test the timing of a change
If the machine purchase moves from May to July, May closing cash rises by $40,000 to $36,340. That extra cash carries into June, raising its closing balance to $63,380. July must then include the payment. Delaying expenditure shifts the funding need; it does not remove the purchase.
A spreadsheet keeps assumptions in input cells linked to all affected months. Change the date once and check both the current month and later opening balances. For a surplus, consider an interest-earning deposit, repayment of borrowing, supplier discounts or planned expansion, while retaining enough cash for upcoming payments.
Key Takeaways
- Net cash flow measures the period's movement; closing cash includes the opening balance.
- Carry every closing balance into the next period, including negative balances.
- Monthly columns reveal shortages hidden by a positive quarter total.
- Match financing and corrective action to the reason for the shortage.
- A timing change affects later balances as well as the month changed.
- Plan a useful home for surplus cash while allowing for future payments.
4Build the budgeted income statement and balance sheet
The master budget must show both the profit the plan earns and the financial position it leaves behind. Use Northgate Outdoor Supplies to assemble an income statement and balance sheet from the supporting schedules. Then trace why its planned profit does not produce an equal increase in cash. Following each change through the statements makes it easier to spot omissions such as drawings, unpaid sales or depreciation.
4.1 Prepare a budgeted income statement
The budgeted income statement shows the revenue and expenses planned for the period. It is also called the budgeted statement of profit or loss. It brings together the operating budgets on the accrual basis: revenue is recorded when earned and expenses when incurred, regardless of payment dates.
Bring in the right figures
Revenue comes from the sales budget. Cost of goods sold comes from purchases or production costs together with the inventory plan. Overhead and selling and administrative budgets supply expenses. Asset records and planned capital expenditure supply depreciation.
For a retailer, goods bought but still held at the end of the period are inventory, not cost of goods sold:
Northgate starts with inventory of $20,000, budgets purchases of $94,000 and plans closing inventory of $24,000. Goods available cost $114,000; subtracting the $24,000 still held leaves $90,000 as cost of goods sold.
Prepare Northgate's statement
| Budgeted income statement for the quarter | Amount |
|---|---|
| Sales revenue | $150,000 |
| Cost of goods sold | $90,000 |
| Gross profit | $60,000 |
| Operating expenses | $30,000 |
| Depreciation | $3,000 |
| Net income | $27,000 |
Gross profit is sales less the cost of the goods sold. Net income then deducts the period's remaining expenses. Northgate's gross margin is 40%, while its net profit margin is 18%. These measures help managers assess whether the planned prices, sales and costs earn an acceptable return before approval.
Keep financing and assets separate
Northgate expects customer cash collections of $146,000, but revenue is $150,000. The uncollected amount remains in receivables. Using collections as sales would omit revenue earned during the quarter and could include collections from sales made earlier.
Purchases of equipment create assets. Their full cost is not an immediate expense; depreciation charges the portion used during the period. Loan principal repayments reduce a liability. Owner's drawings reduce equity. Deducting any of these as operating expenses would understate profit. Conversely, depreciation and unpaid expenses reduce profit even without a cash payment in the quarter.
Apply the production version consistently
For a manufacturer, cost of goods sold starts with opening finished goods, adds cost of goods manufactured and subtracts closing finished goods. Manufacturing cost draws on materials used, direct labor and production overheads. The costing method determines which costs enter inventory.
Brightline's finished lamps have a variable production cost of $20 each. Variable costing uses that figure and treats fixed production overhead as a period cost. Absorption costing includes a share of fixed production overhead in each unit. Keep the inventory valuation basis aligned with the treatment of production costs throughout the statement.
If Northgate used its $94,000 purchases as cost of goods sold, profit would fall by $4,000. That would expense the inventory increase even though those goods remain available for future sales.
Key Takeaways
- The income statement records earned revenue and incurred expenses on the accrual basis.
- Retail cost of goods sold adjusts purchases for opening and closing inventory.
- Gross profit deducts cost of goods sold; net income also deducts other expenses.
- Equipment purchases, drawings and loan principal repayments are not operating expenses.
- Use a consistent costing method for manufactured goods and inventory.
4.2 Prepare a budgeted balance sheet
A budgeted balance sheet projects assets, liabilities and owner's equity at the end of the budget period. It is also called a budgeted statement of financial position. Begin with the opening balances and apply the changes in the supporting budgets.
Trace each closing balance
Use closing cash from the cash budget, receivables and payables from their schedules, and inventory from the closing inventory plan. For equipment, add purchases to the opening carrying amount, subtract the carrying amount of disposals and subtract depreciation. For a loan, add new borrowing and subtract principal repaid.
Owner's equity needs its own roll-forward: opening capital plus capital contributed plus net income minus drawings. Profit belongs to the owner even when the cash has not yet been collected. Drawings reduce the owner's claim without reducing profit.
Start with a balanced opening position
Northgate begins January with cash $12,000, receivables $18,000, inventory $20,000 and net equipment $60,000. Assets total $110,000. Payables of $15,000, a loan of $25,000 and owner's capital of $70,000 also total $110,000.
Its quarter cash budget includes $146,000 customer receipts. Payments are suppliers $92,000, operating expenses $30,000, equipment $10,000, loan principal $5,000 and drawings $9,000. These payments total $146,000, so cash ends unchanged at $12,000.
Apply the budgeted changes
Receivables finish at $22,000 and inventory at $24,000. Equipment increases by the $10,000 purchase and falls by $3,000 depreciation, leaving $67,000. Payables rise to $17,000. The loan falls by $5,000 to $20,000. Capital becomes:
Northgate introduces no additional capital this quarter.
| Closing balance sheet, March 31 | Amount |
|---|---|
| Cash | $12,000 |
| Accounts receivable | $22,000 |
| Inventory | $24,000 |
| Equipment, net | $67,000 |
| Total assets | $125,000 |
| Accounts payable | $17,000 |
| Loan | $20,000 |
| Owner's capital | $88,000 |
| Total liabilities and equity | $125,000 |
Check both sides of each change
If the statement does not balance, trace transactions through all affected balances. Equipment bought for cash increases equipment and reduces cash. A principal repayment reduces cash and the loan. Depreciation reduces equipment and profit, which feeds equity. Drawings reduce cash and capital. Omitting one side leaves the statement inconsistent.
Do not insert a balancing cash figure to hide an error: cash must agree with the cash budget. Common omissions are profit in equity, drawings, depreciation and principal repayments.
With the loan treated as noncurrent, Northgate has current assets of $58,000 and current liabilities of $17,000, a current ratio of about 3.41. This helps assess the planned ability to meet short-term obligations. A corporation reports share capital and retained earnings; closing retained earnings equal opening retained earnings plus net income minus dividends declared.
Key Takeaways
- Build each closing balance from the opening position and supporting budgets.
- Cash must agree with the closing cash budget.
- Equipment changes for purchases, disposals and depreciation; loans change for borrowing and principal repayments.
- Owner's capital rises with contributions and profit and falls with drawings.
- Trace both effects of transactions when checking an imbalance.
- Corporate retained earnings rise with net income and fall with dividends declared.
4.3 Explain why budgeted profit and budgeted cash differ
Northgate plans $27,000 net income, yet cash stays at $12,000. Profit measures earned revenue less incurred expenses. Cash measures receipts less payments, including asset and financing flows. A reconciliation explains how the two results fit together.
Start with profit and remove non-cash effects
Northgate's net income includes $3,000 depreciation. Add it back because it reduced profit without using cash in the quarter. The add-back creates no cash; it reverses an expense when moving from profit to cash flow.
Credit sales also create timing differences. Receivables rise by $4,000, meaning that amount of revenue has not become cash. Inventory rises by $4,000, tying up funds in unsold goods. Payables rise by $2,000, meaning some purchases have not yet been paid for.
| Reconciliation to operating cash flow | Amount |
|---|---|
| Net income | $27,000 |
| Add depreciation | $3,000 |
| Deduct increase in receivables | −$4,000 |
| Deduct increase in inventory | −$4,000 |
| Add increase in payables | $2,000 |
| Cash from operating activities | $24,000 |
Check the same result directly: customer receipts $146,000 less suppliers $92,000 and operating expenses paid $30,000 equal $24,000.
Add investing and financing flows
The equipment payment of $10,000 uses cash without being a full current expense. Loan principal of $5,000 and drawings of $9,000 also use cash without reducing profit. Deducting these three amounts from $24,000 operating cash leaves no net change in cash.
Classify the flows by their purpose:
| Activity | Examples | Northgate's net flow |
|---|---|---|
| Operating | Customers, suppliers, employees and operating expenses | $24,000 |
| Investing | Purchases and sales of noncurrent assets | −$10,000 |
| Financing | Borrowing, principal repayments and owner transactions | −$14,000 |
The total is zero, consistent with unchanged opening and closing cash. The $27,000 profit instead raises capital before drawings are deducted.
Understand the practical risk
A growing, profitable business can run short of cash when more funds are tied up in receivables and inventory. Customers may owe enough to support a healthy profit while cash is unavailable to pay wages. This can be part of overtrading, where growth strains the funds supporting operations.
A loss-making business may temporarily have cash because it borrowed or sold assets. Neither a cash balance nor a profit figure answers both questions: managers need to know whether operations earn a return and whether payments can be met.
Compare plans with past cash reports
A cash budget looks forward and serves managers' planning needs, often month by month. A statement of cash flows reports actual past flows in operating, investing and financing categories for owners, lenders and other users. Comparing actual flows with the budget helps explain changed collections, spending or financing. Budgeted flows can use the same activity categories while still remaining a forecast of the future.
Key Takeaways
- Depreciation is added back because it reduced profit without a cash payment.
- Rising receivables and inventory reduce operating cash relative to profit; rising payables increase it.
- Equipment, borrowing, repayments and owner transactions explain further profit–cash differences.
- Operating, investing and financing flows together explain the change in cash.
- A cash budget plans future flows; a statement of cash flows reports actual past flows.
5Use fixed and flexible budgets to control performance
Actual activity often differs from the level in the approved plan. Before judging spending, work out what the budget allows for the output actually achieved. Use Ridgeway Ceramics to flex variable, fixed, mixed and stepped costs, then calculate variances and reconcile the change in profit. A useful report separates the effect of volume from the remaining differences and helps managers decide what to investigate.
5.1 Flex a budget to the actual level of activity
A fixed budget is prepared for one planned activity level. If actual output changes, comparing costs with that original total mixes the effect of activity with the effect of spending. A flexible budget calculates the allowance for actual activity using the budgeted cost behavior.
Compare like levels of activity
Ridgeway planned 10,000 vases at materials cost of $6 each, giving $60,000. Actual output is 9,000 and materials cost is $56,700. The fixed comparison appears $3,300 favorable, but the allowance for 9,000 vases is only $54,000. Actual cost exceeds that by $2,700.
Use actual output with budgeted rates. Actual rates belong in actual results; using them to flex the budget would erase the differences the comparison should reveal.
Flex each line by its behavior
Ridgeway sells all the vases it produces, so sales and output use the same unit count:
| Line | Budgeted basis | At 10,000 vases | At 9,000 vases |
|---|---|---|---|
| Revenue | $40 per vase | $400,000 | $360,000 |
| Materials | $6 per vase | $60,000 | $54,000 |
| Direct labor | $12 per vase | $120,000 | $108,000 |
| Variable overhead | $2 per vase | $20,000 | $18,000 |
| Fixed overhead | $45,000 total | $45,000 | $45,000 |
| Profit | Revenue less all costs | $155,000 | $135,000 |
Fixed overhead stays at its budgeted total within the relevant range. When sales and production differ, flex revenue to actual units sold and production costs to actual units produced.
Separate mixed costs
Maintenance of $5,000 plus $0.50 per vase allows $9,500 at 9,000 vases. Only the variable part follows output.
If only two activity totals are given, high-low can identify the parts. Power costs $26,000 at 8,000 vases and $30,000 at 10,000. The $4,000 change across 2,000 vases gives $2 per vase. Deducting $20,000 variable cost from the higher total leaves $10,000 fixed. At 9,000 vases, power is budgeted at $28,000.
Respect cost steps
One supervisor costs $6,000 a quarter and can oversee up to 4,000 vases. Output of 7,000 needs two supervisors, costing $12,000; 9,000 needs three, costing $18,000. Both 9,000 and 10,000 lie in the same three-supervisor band. Scaling $18,000 by 90% would incorrectly allow $16,200: a whole third supervisor is still needed.
Flexible budgets also help plan before the period begins. Ridgeway earns contribution of $20 per vase after variable production cost of $20. With fixed overhead $45,000, profit is $115,000 at 8,000 vases, $135,000 at 9,000 and $155,000 at 10,000. This range shows the volume effect while holding the price and cost assumptions constant.
Key Takeaways
- Flex the allowance to actual activity with budgeted prices and cost rates.
- Variable totals change with activity; fixed totals stay unchanged within the relevant range.
- Split mixed costs into fixed and variable parts.
- Stepped costs follow whole capacity bands, not proportional scaling.
- Use units sold for revenue and units produced for production costs.
- Flexible budgets can compare possible activity levels before the period as well as support control afterward.
5.2 Calculate, report and act on budget variances
A budget variance is the difference between an actual amount and its budget. Against a fixed budget it includes the effect of different activity. Against a flexed budget it shows the remaining revenue and cost differences at actual activity. Label results favorable (F) when they increase profit and unfavorable (U) when they reduce it. Unfavorable is also called adverse (A).
Prepare a flexed variance report
Ridgeway actually sells 9,000 vases at $39 each. Revenue is $351,000. Actual production costs total $232,100, leaving $118,900 profit. Compare with the flexed budget for 9,000 vases:
| Line | Flexed budget | Actual | Variance |
|---|---|---|---|
| Revenue | $360,000 | $351,000 | $9,000 U |
| Materials | $54,000 | $56,700 | $2,700 U |
| Direct labor | $108,000 | $110,000 | $2,000 U |
| Variable overhead | $18,000 | $18,900 | $900 U |
| Fixed overhead | $45,000 | $46,500 | $1,500 U |
| Profit | $135,000 | $118,900 | $16,100 U |
Higher revenue is favorable; higher cost is unfavorable. A plus sign alone cannot express both meanings clearly. For materials, $2,700 above allowance is 5.0% of the $54,000 flexed budget.
Reconcile the profit difference
The fixed budget planned $155,000 profit. Selling 1,000 fewer vases at budgeted contribution of $20 reduces profit by $20,000, giving flexed profit of $135,000. The $16,100 unfavorable flexible budget variance then brings profit to $118,900:
This accounts for the full $36,100 shortfall. For costs alone, flexed production cost is $225,000 and actual cost is $232,100. The $7,100 difference equals the four cost variances added together; the revenue variance is excluded from this cost reconciliation.
Decide what to investigate
Management by exception focuses attention on significant differences. Dollar size, percentage size, repeated trends and critical items all matter. Ridgeway's materials variance is 5.0%, fixed overhead about 3.3%, revenue 2.5% and labor about 1.9%. A recurring smaller difference may need action before a one-time larger one.
A report identifies where results differ, but investigation establishes why. Materials might cost more because prices rose or waste increased. Labor might rise through overtime or slow work. Discounts might reduce revenue. The budget itself might also have been unrealistic. Treat these as possible causes until evidence supports one.
Choose action with the whole business in view
Supplier negotiation, training, equipment repair, pricing changes or a revised plan should address the cause found. Cheaper materials can save purchasing cost while increasing waste and labor time. Reduced advertising may create a favorable expense variance while weakening future demand. Include quality, reliability, customer satisfaction and morale in the decision.
Evaluate managers on what they can control. A head-office rent decision should not be treated as a production manager's operating failure. Reports are most useful when they arrive promptly and support explanation and action.
Key Takeaways
- Revenue above budget is favorable; cost above budget is unfavorable.
- A flexed comparison separates remaining performance differences from the effect of volume.
- Reconcile fixed profit to flexed profit, then to actual profit.
- A cost-only reconciliation excludes revenue variances.
- Investigate significant sizes, percentages, trends and critical items.
- Check causes, controllability and non-financial effects before choosing action.
6Explain how budgets affect people's behavior
A budget shapes decisions because it gives people targets and often affects their rewards. How managers set those targets, share information and discuss results can strengthen effort or encourage games. Compare imposed and participative approaches, distinguish realistic planning from stretch targets, and examine slack, wasteful spending and short-term cuts. The aim is to make meeting a department's target support the whole organization.
6.1 Set budgets that motivate
Budgets influence effort because they define success and often determine rewards. A motivating budget combines useful local knowledge, accepted targets and fair evaluation. Goal congruence exists when people pursuing their own targets also advance the organization's goals.
Compare who sets the budget
| Approach | Strengths | Risks |
|---|---|---|
| Top-down or imposed | Fast; aligns targets with strategy; reduces managers' direct opportunity to pad their proposals | May overlook local knowledge and create little ownership |
| Bottom-up or participative | Uses operating knowledge; builds commitment; supports realistic detail | Takes time; allows slack; needs coordination with strategy |
In practice, management may set overall objectives while responsible managers propose details and negotiate. Participation gives the people delivering a plan a chance to explain what is achievable. It also gives them influence over targets, so informed review remains necessary.
Brightline's head office estimates May sales at 2,000 lamps from past trends. The sales manager knows a new retailer will buy 400 per month from May and proposes 2,400. Ignoring that information would leave the production plan 400 lamps short of real demand. The manager's contribution improves coordination, not just morale.
Choose targets people will work toward
A very easy target offers little reason for extra effort. A target viewed as impossible can lead people to give up or manipulate results. Challenging but achievable targets that managers accept tend to support motivation.
A stretch target expresses an aspiration. A realistic planning estimate expresses what management expects. These figures serve different purposes. Putting an optimistic stretch sales target into the cash budget overstates expected collections and can hide a financing need. Keep the cash plan grounded in realistic expectations even when the sales team also works toward a more demanding aspiration.
Align rewards with the result the business needs
A bonus for staying below a maintenance budget focuses attention on that cost. It can also encourage postponing repairs until after the reward date. The current expense line improves while equipment reliability deteriorates.
Combine financial targets with measures of quality, customer satisfaction, staff development and longer-term results. A purchasing manager should consider the effect of material choices on production waste and complaints, as well as the invoice price. That aligns departmental success with the business's overall result.
Make evaluation fair and useful
Managers need timely reports and an allowance flexed to actual activity. Responsibility must follow control: a production manager can influence material usage but may have no influence over factory rent negotiated by head office. Separate controllable and uncontrollable items so the discussion centers on decisions the manager can change.
Open discussion of a variance helps managers explain operating conditions and agree improvements. Rigid punishment for every missed figure raises pressure to hide problems. Local knowledge is most useful when people can report a developing problem early enough for others to respond.
Key Takeaways
- Goal congruence aligns departmental targets with organizational success.
- Participation brings local knowledge and ownership but also requires informed review.
- Challenging, achievable and accepted targets tend to motivate.
- Use realistic expectations for planning and distinguish them from stretch aspirations.
- Combine budget rewards with long-term and non-financial measures.
- Evaluate managers with timely flexed reports and controllable responsibilities.
6.2 Recognize and limit dysfunctional budget behavior
A manager can meet a target while harming the organization. This is dysfunctional behavior. The incentive system may make an unhelpful choice personally rewarding, so prevention needs attention to how targets and rewards work.
Recognize budgetary slack
Budgetary slack is deliberate padding: overstating expected costs or understating expected revenue to make a target easier. A manager expecting costs of $50,000 submits $56,000. The $6,000 difference is 12% of the realistic estimate.
Slack can protect a bonus or provide a cushion against uncertainty. Managers may also pad because they expect senior management to cut every request. Blanket cuts then reinforce the incentive to pad again next year. Resources become tied to misleading plans, and inflated cost estimates can lead to prices that are too high.
Distinguish deliberate padding from an honest estimate that later proves wrong. A changing forecast reflects new expectations; slack intentionally misrepresents the expectation when the proposal is made.
Notice spending driven by the budget rule
"Spend it or lose it" arises when unused funds are removed and future budgets depend on current spending. A department with $4,000 left in the final week buys equipment it does not need to protect next year's allocation. It meets the spending plan but wastes resources.
Review whether the purchase serves a real operating need. Budget evaluation should value a justified saving, not make spending the full allowance the safest way to secure future resources.
Look beyond the reporting date
Short-termism means improving the current result at the expense of future performance. Cutting training, maintenance, research or marketing can reduce this period's expenses while damaging future capability or revenue. The dollar saving must be weighed against the effect on service, equipment and staff.
Manipulating results is another risk. Heavy discounts may pull future sales into the current period. Delaying the recording of a cost makes reported performance misleading and raises ethical issues. Decisions based on those figures then begin from a false picture of the business.
Check effects across departments
A purchasing manager rewarded only for low material prices may buy poor-quality inputs. Purchasing meets its target while production faces waste and extra labor, and customers may face faulty products. The separate budgets should support one coordinated outcome, so investigate the total effect across departments.
Reduce the incentive to game results
Participation alone does not remove slack: it gives managers more influence over proposals. Review their estimates against operating evidence, past results and useful benchmarks. Ask someone who understands the work to challenge assumptions.
Reward forecast accuracy and longer-term results as well as budget performance. Use flexed comparisons, separate controllable items and include quality and customer measures. A culture where managers can explain variances openly makes it easier to surface problems; automatic punishment gives them a reason to hide them.
Key Takeaways
- Slack deliberately makes targets easier through inflated costs or understated revenue.
- Spend-it-or-lose-it rules can reward wasteful year-end purchases.
- Short-term cuts can damage future results; manipulated records mislead decisions.
- A departmental saving can create larger costs elsewhere.
- Reduce gaming through informed review, fair evaluation and broader rewards.
Budgeting examples
1Build a plan the business can deliver
10 steps
- 1IntroductionTurn intentions into a workable plan
A business can have plenty of customer demand and still promise more than its factory or cash can support. Budgeting brings the separate plans together before that happens.
Follow a plan from its forecast through coordination and approval. Then see how comparing actual results with the approved figures gives managers a reason to investigate and act.
- 2ExplanationSeparate the estimate from the commitment
A forecast estimates a likely outcome. A budget is management's agreed plan and commitment of resources.
"April demand will probably be about 2,000 lamps" is a forecast. Brightline's approved sales plan specifies 2,000 lamps at $40, giving $80,000 revenue. That agreed quantity guides production, while the expected payment pattern will guide cash planning.
- 3ExampleFind the gap between sales and supply
Brightline plans 2,400 May sales. Production plans 2,000 lamps and expects 300 in opening inventory.
Only 2,300 lamps are available, so the plans leave 100 orders uncovered. Bringing sales and production together exposes the gap before orders are missed. Managers can revise production, inventory or the sales plan while there is still time to act.
- 4ChallengeDecide whether comparison is enough
A manager prepares a budget and records actual spending but never compares the two. What part of budgetary control is missing?
---reveal---
The manager needs to compare results, investigate significant variances and act on the causes. The plan can still help preparation, but recording figures alone does not show where the business is moving away from its agreed targets.
- 5Key InsightUse budgets for more than cost cutting
An advertising budget can authorize more spending to support planned sales. A labor budget can reveal a need to hire. Budgeting coordinates resources with the result the business wants.
The same figures communicate expectations, give people targets and provide a basis for evaluation. A lower spending figure still needs interpretation: fewer units or damaged service can make a saving misleading.
- 6ExplanationFind what limits activity first
The principal budget factor is the constraint limiting activity in the period. Identify it first because dependent budgets must fit within it.
Sales demand often sets the limit. Skilled labor, materials, machine time, cash or space can constrain the business instead. Preparing resource budgets before resolving that constraint risks building a detailed plan that cannot be delivered.
- 7ExampleCalculate the capacity ceiling
Customers would buy 12,000 units, but only 5,000 machine hours are available. Each unit needs 0.5 hours:
With 500 units already held and no closing reserve required, sales can reach 10,500. Meeting the full demand would require added capacity; the sales forecast alone cannot supply the missing machine hours.
- 8ConnectionJoin the budgets into one set
After resolving the constraint, a manufacturer links sales to production, then to materials, labor and overheads. Inventory and operating costs feed profit; capital spending and payment dates feed cash.
The master budget coordinates these plans and summarizes profit, cash and the closing balance sheet. Line managers prepare proposals, a committee coordinates them and owners or the board approve them.
- 9ChallengeRespond to a cash problem in the draft
A draft sales and production plan fits capacity, but the cash budget shows that the planned machine payment cannot be funded. What should happen before approval?
---reveal---
Managers must revise and coordinate the linked plans, perhaps arranging finance or changing the purchase timing. A workable production quantity alone is insufficient when the spending cannot be paid for. The revisions must flow through cash and asset budgets.
- 10RecapFollow the plan through to action
Start with realistic information and the factor limiting activity. Make departmental quantities and timing agree, then check the combined profit, cash and financial position before approval.
During the period, record actual results, compare them with suitable budget allowances and act on significant differences. A spreadsheet speeds revisions, but its formulas and assumptions still need checking.
2Turn lamp sales into production resources
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionFollow the quantities before the dollars
- 2ExamplePrice the sales plan
- 3ExplanationSet the finished goods reserve
- 4ExampleCalculate April production
- 5ChallengeCarry the reserve into May
- 6ExplanationTranslate lamps into aluminum usage
- 7ExampleAdjust usage to find purchases
- 8ChallengeFind input when some material is lost
- 9ConnectionUse the retailer’s version
- 10ExampleTurn production into labor hours
- 11ExampleAllow for paid idle time
- 12ExamplePrice the overtime hours once
- 13ChallengeSeparate an overhead cost from its payment
- 14ExplanationApply overhead drivers
- 15ExampleValue the closing inventories
- 16ChallengeTrace an inventory policy change
- 17RecapKeep each schedule’s job clear
3Build Brightline’s monthly cash plan
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionFind when the money moves
- 2ExplanationFollow each group of customers
- 3ExampleCalculate April customer receipts
- 4ChallengeApply a discount to one collection group
- 5ExplanationUse supplier terms for payment dates
- 6ExampleComplete the payment schedule
- 7ChallengeDecide how a debt repayment appears
- 8ExampleCalculate the first closing balance
- 9ExampleCarry cash into the difficult month
- 10Key InsightRead the shortage amount correctly
- 11ChallengeIdentify the cause before choosing action
- 12ExampleMove the machine payment to July
- 13ConnectionUse the quarter as a check
- 14RecapRead the budget as a funding timetable
4Build statements that agree with the cash plan
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionBring the supporting budgets together
- 2ExplanationUse earned revenue and incurred expense
- 3ExampleFind the cost of the goods sold
- 4ChallengeComplete the profit calculation
- 5ExplanationRoll forward the asset balances
- 6ExampleRoll forward the financing balances
- 7ExampleCheck the closing position
- 8ChallengeTrace drawings through both sides
- 9ExplanationReverse the non-cash deduction
- 10ExampleAllow for uncollected sales and inventory
- 11ExampleAllow for unpaid purchases
- 12ChallengeFind the cash change after other flows
- 13ConnectionClassify flows and compare periods
- 14RecapCheck the same plan in three views
5Separate volume from budget variances
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionChoose a fair comparison
- 2ExampleQuestion the apparent materials saving
- 3ExplanationKeep budgeted rates and actual activity
- 4ChallengeFlex the fixed and variable parts
- 5ExampleCheck a capacity step
- 6TipMatch the allowance to the right activity
- 7ExplanationLabel the effect on profit
- 8ExampleAdd the remaining cost differences
- 9ChallengeReconcile the complete profit gap
- 10ExampleMeasure the materials difference
- 11Key InsightTreat causes as questions to investigate
- 12ChallengeChoose what to examine before rewarding a saving
- 13RecapMove from comparison to a justified response
6Set targets that support good decisions
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionAsk what the target rewards
- 2ExplanationCompare imposed and participative plans
- 3ExampleUse the knowledge close to the work
- 4ChallengeKeep aspiration out of expected collections
- 5ConnectionEvaluate what the manager can influence
- 6ExampleFind deliberate padding
- 7ChallengeDiagnose the year-end purchase
- 8ExplanationLook beyond the current result
- 9ChallengeRepair a cross-department incentive
- 10TipReduce the reason to hide problems
- 11RecapMake departmental success help the whole business
Budgeting practice questions
Set 1: Connect plans, resources and cash10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Carry budgets into financial results10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Check timing, valuation and performance10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Diagnose linked budgeting decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Integrate budgets and challenge the conclusions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Absorption costing
Accounts payable
Accounts receivable
Accrual basis
B
Bad debt
Budget
Budget committee
Budget manual
Budget period
Budget variance
Budgetary control
Budgetary slack
Budgeted balance sheet
Budgeted income statement
C
Capital expenditure budget
Carrying amount
Cash budget
Cash payments schedule
Cash receipts schedule
Closing cash balance
Controllable cost
Coordination
Cost of goods sold
D
Direct labor budget
Dysfunctional behavior
F
Favorable variance
Financing cash flow
Finished goods inventory
Fixed budget
Flexible budget
Forecast
Functional budget
G
Goal congruence
Gross margin
I
Idle time
Imposed budgeting
Investing cash flow
L
Loan principal
M
Management by exception
Markup
Master budget
Material loss
Materials purchases budget
Materials usage budget
Mixed cost
N
Net cash flow
Net profit margin
Non-cash expense
O
Operating cash flow
Overtime premium
Owner's capital
P
Participative budgeting
Performance evaluation
Principal budget factor
Production budget
Production capacity
Production overhead
Profit reconciliation
R
Results manipulation
Retained earnings
S
Sales budget
Selling and administrative expenses
Settlement discount
Short-termism
Spend it or lose it
Statement of cash flows
Stepped fixed cost
Stretch target
U
Unfavorable variance
W
What-if analysis