Budgeting and Budgetary Control

Learn how organizations plan in numbers and use those plans to stay in control. Find out why businesses budget and how the principal budget factor decides where planning starts. Then prepare sales, production, materials, labor and overhead budgets, build a month-by-month cash budget, and combine everything into a budgeted income statement and balance sheet. Finally, flex budgets to the activity actually achieved, calculate and interpret variances, and see how the way budgets are set and used shapes motivation and behavior. Worked examples follow a lamp manufacturer, an outdoor store and a ceramics maker.

BeginnerLesson 8 of 11 in Introduction to Management Accounting Course

What you will learn

  1. Describe what a budget is and what it does for planning, coordination, motivation and control, then follow how the separate budgets are prepared in order and combined into a master budget.
    • Explain what budgets are for and where they fall short
      Define a budget, tell it apart from a forecast, and weigh the benefits of budgetary control against its limitations.
    • Organize the budget process from the principal budget factor to the master budget
      Follow the steps of budget preparation, identify the principal budget factor, and trace how the sales, production, resource, capital and cash budgets combine into the master budget.
  2. Turn the sales plan into the quantities to produce, then budget the materials, purchases, labor and overheads each period needs, in units and in dollars.
    • Prepare the sales budget and the production budget
      Budget sales in units and dollars, then work out how many units to make each period once the inventory plan is taken into account.
    • Budget materials usage and purchases
      Calculate the materials production will use, the quantity and cost of materials to buy once the materials inventory plan is applied, and the goods a trading business must purchase.
    • Budget direct labor, overheads and closing inventory
      Work out the labor hours and cost production needs, allowing for idle time and overtime, budget overheads and selling and administrative expenses from cost behavior, and value the planned closing inventory.
  3. Forecast when cash will come in and go out, build a month-by-month cash budget, and use it to plan for shortages and surpluses.
    • Schedule budgeted cash receipts
      Turn cash and credit sales into the cash expected each month, allowing for discounts, bad debts and other receipts, and budget the closing accounts receivable.
    • Schedule budgeted cash payments
      Work out when purchases, wages, expenses and capital spending will be paid, leave out non-cash items, and budget the closing accounts payable.
    • Prepare, interpret and act on a cash budget
      Lay out a monthly cash budget, carry balances forward, test what-if changes, and recommend actions for a shortage or a surplus.
  4. Bring the functional and cash budgets together into a budgeted income statement and a budgeted balance sheet, and explain why budgeted profit and budgeted cash differ.
    • Prepare a budgeted income statement
      Calculate budgeted revenue, cost of goods sold, gross profit, expenses and net income for the budget period on the accrual basis.
    • Prepare a budgeted balance sheet
      Project the closing assets, liabilities and owner's equity from the opening balance sheet and the other budgets, and check that it balances.
    • Explain why budgeted profit and budgeted cash differ
      Reconcile budgeted net income with the budgeted change in cash, classify budgeted cash flows, and compare the cash budget with a statement of cash flows.
  5. Flex a budget to the level of activity actually achieved, calculate and interpret budget variances, and report them so managers can act.
    • Flex a budget to the actual level of activity
      Explain why a fixed budget can mislead and prepare a flexible budget using variable, fixed, mixed and stepped cost behavior.
    • Calculate, report and act on budget variances
      Compare actual results with the flexible budget, label variances favorable or unfavorable, reconcile budgeted and actual profit, and decide which differences to investigate.
  6. Explain how the way budgets are set and used affects motivation, and recognize and reduce the unhelpful behavior budgets can encourage.
    • Set budgets that motivate
      Compare imposed and participative budgeting, judge how difficult targets should be, and connect budgets with goal congruence, incentives and fair evaluation.
    • Recognize and limit dysfunctional budget behavior
      Identify budgetary slack, spending to use up a budget, short-term decisions and other games, and explain ways to reduce them.

Budgeting study guide

6 chapters

1

Explain why organizations budget and how a budget is built

A budget gives different departments one agreed plan. Sales targets, staffing, purchases and cash must fit together before managers commit resources. Learn how a budget differs from a forecast, what managers gain from comparing plans with results, and why the factor limiting activity determines where preparation starts. The separate budgets are then reviewed together until the business has a workable master budget.

1.1 Explain what budgets are for and where they fall short

A budget is an agreed plan for a future period, expressed in money and often in quantities. Units sold, kilograms bought and hours worked help explain the dollar amounts. Managers approve the plan before the period begins and use it to guide decisions.

A plan and an estimate do different jobs

A forecast estimates what is likely to happen. A budget states what management plans to achieve and what resources it authorizes. Brightline's forecast might say, "April demand will probably be about 2,000 lamps." Its sales budget turns that estimate into a commitment: 2,000 lamps at $40 each, giving $80,000 of revenue.

The forecast informs the decision; the approved budget coordinates action. Managers may authorize more advertising to support a higher sales target or additional training to improve service. Budgeting therefore covers revenues, resources and investment as well as cost control.

Give departments a common plan

Budgets serve several connected purposes:

  • Planning: identify future resource needs and possible cash shortages.
  • Coordination: align sales, production, purchasing and finance.
  • Communication: tell managers what results and resources are expected.
  • Motivation: give people targets to work toward.
  • Authorization: permit spending within agreed limits.
  • Control and evaluation: compare results with the plan and assess performance.

Suppose Brightline plans to sell 2,400 lamps in May. The factory plans to make 2,000 and has 300 available in inventory. That provides only 2,300 lamps, leaving 100 orders uncovered. Comparing the two plans exposes the gap early. Managers can arrange overtime, build inventory sooner or revise the sales plan before accepting orders they cannot fill.

Close the control cycle

Budgetary control connects the plan with actual results. First set and communicate the budget. Then record actual results, compare them with budget, calculate the differences and investigate significant ones. Finally, act on the causes or revise the plan when conditions have changed.

A difference is a variance. If delivery spending exceeds budget, a manager needs to find out whether the business made more deliveries, paid higher rates or used extra trips. Each cause suggests a different response. Preparing a budget and putting it away provides no continuing control.

Recognize the limits

Budgets use estimates, so a carefully prepared plan can still become outdated. Preparation also takes staff time. Rigid spending limits may discourage a worthwhile opportunity, and departments may compete for resources or protect easy targets.

Meeting a target must be interpreted. Spending less after producing fewer units does not establish efficient production. Managers compare costs with an allowance for actual activity and consider quality, customer satisfaction and staff turnover. A cost saving that creates complaints or missed deliveries may harm the business even though the spending line looks favorable.

Key Takeaways

  • A budget is an approved future plan; a forecast estimates a likely outcome.
  • Budgets coordinate quantities, resources and cash as well as setting dollar targets.
  • Budgetary control requires comparison, investigation and action.
  • Evaluate results with actual activity and non-financial performance in view.

1.2 Organize the budget process from the principal budget factor to the master budget

The separate budgets depend on one another. A production plan cannot promise more than available capacity, and a spending plan must be financeable. Preparation starts by finding the factor that limits activity, then builds and checks the linked plans.

Start with the limiting factor

The principal budget factor is the factor that limits activity during the budget period. It is also called the limiting or key budget factor. Sales demand is often the limit, but materials, skilled labor, machine hours, cash or floor space can be the constraint. Identify it first and prepare its budget first.

Suppose demand is 12,000 units, machine time is 5,000 hours and each unit needs 0.5 hours. Maximum production is:

5,000÷0.5=10,000 units

With 500 finished units already available and no closing inventory planned, maximum sales are 10,500 units. Budgeting sales at 12,000 would leave an impossible production requirement unless managers add capacity, perhaps through extra shifts or subcontracting.

Build the linked budgets

Once the constraint is settled, a manufacturer's normal sequence runs from sales to production, materials usage and purchases, direct labor, and overheads. Production costs and inventory plans feed cost of goods sold. Selling and administrative expenses complete the operating plans. The capital expenditure budget records planned asset purchases and sales; the cash budget schedules the resulting receipts and payments.

GroupWhat it plans
Functional or operating budgetsSales, production, resources and operating expenses
Capital expenditure budgetPurchases and sales of long-lived assets
Financial budgetsCash and the closing financial position

The master budget brings the coordinated plans together, summarized in the budgeted income statement, cash budget and budgeted balance sheet. It is prepared for one planned activity level, making it a fixed or static budget. A trading business replaces production and materials schedules with a budget for goods purchased for resale. A service business plans service capacity and hours.

Assign responsibility and allow time to revise

Line managers prepare budgets for their areas. A budget committee coordinates them, with an accountant often serving as budget officer. Owners or the board approve the final plan. A budget manual sets out responsibilities, procedures, formats and deadlines.

The period is usually a year split into months or quarters. Cash may need weekly planning when funds are tight. Shorter periods let managers spot a problem while action can still help.

Drafts are revised until capacity, cash and profit fit. A shortage in the first cash draft may require a revised equipment purchase or borrowing plan. Communicate the approved figures to the managers who will use them, and monitor results during the period.

Use a spreadsheet carefully

Linked input cells let a price or payment-date change update several budgets and make what-if analysis quick. The same links can spread a wrong formula throughout the model. Check formulas, units and versions, and review whether assumptions are realistic. A precise-looking result is still built on estimates.

Key Takeaways

  • Identify the principal budget factor before preparing dependent budgets.
  • The master budget combines operating, capital expenditure and financial plans.
  • A retailer budgets purchases of resale goods in place of production.
  • Managers prepare their areas' plans; the committee coordinates and senior management approves them.
  • Linked spreadsheets speed revisions but require formula and version controls.
2

Prepare the functional budgets for sales, production and resources

Sales give a manufacturer its starting demand, but inventory plans decide how much it must make. Production then determines materials, labor and overhead needs. Follow Brightline Lamps from sales quantities to resource costs, keeping units separate from dollars and purchases separate from usage. A retailer's purchases budget follows the same inventory logic without a manufacturing stage; capacity checks show when a plan needs revision.

2.1 Prepare the sales budget and the production budget

A sales plan answers how many units customers will buy and at what price. A production plan answers how many units the factory must make. Inventory connects them: some sales can come from units already held, while some production must be kept for later sales.

Calculate revenue from the sales plan

The sales budget multiplies budgeted units by the budgeted selling price. Brightline plans a price of $40 per lamp:

MonthLamps soldSales revenue
April2,000$80,000
May2,400$96,000
June2,200$88,000
Quarter6,600$264,000

The forecast behind these figures considers past sales, trends, market research, competitors, economic conditions, planned prices and advertising. It also needs a capacity check. Revenue belongs to the month of sale even when the customer will pay later; collections are scheduled separately.

Work from the units needed

To cover sales and leave closing inventory, the factory needs sales units plus desired closing units. Opening units are already available, so subtract them:

Production=sales+closing inventory−opening inventory

Brightline wants closing finished goods inventory equal to 20% of the next month's sales. April begins with 400 lamps. May sales are 2,400, so April must end with 480. April production is therefore:

2,000+480−400=2,080 lamps

Making only the 2,000 lamps sold would leave inventory at 400, below the planned 480. The extra 80 lamps build that reserve.

Carry inventory across the months

May opens with April's closing 480. Its closing target uses June sales: 20% of 2,200 is 440. June opens with 440 and closes with 520, based on July sales of 2,600.

MonthSalesClosing inventoryOpening inventoryProduction
April2,0004804002,080
May2,4004404802,360
June2,2005204402,280

Notice that May production is below sales because inventory falls by 40. The direction of the inventory change gives a quick check on the calculation.

For the quarter, use the opening balance of April and the closing balance of June:

6,600+520−400=6,720 lamps

The three production figures also total 6,720. Do not add the monthly closing inventories: April's closing units become May's opening units and would be counted again.

Check what the factory can deliver

At a normal monthly capacity of 2,300 lamps, May's requirement of 2,360 is 60 too high. Managers can make additional lamps in April, arrange overtime, subcontract or reduce the May sales target. Producing sooner also affects storage, purchases and cash. A service business budgets service hours instead of finished goods; a trading business plans purchases of goods for resale.

Key Takeaways

  • Revenue equals budgeted sales units times budgeted price.
  • Production equals sales plus desired closing finished goods minus opening finished goods.
  • A next-month inventory policy needs next month's sales, including a month beyond the budget period.
  • Quarter totals use the first opening and final closing inventory.
  • Compare production requirements with capacity before approving the plan.

2.2 Budget materials usage and purchases

Production determines materials usage. The materials inventory plan then determines purchases. Keeping these two calculations separate prevents a common error: treating everything bought as if it were used immediately.

Calculate usage before purchases

Brightline uses 2 kg of aluminum per lamp. Multiply the production budget by that input requirement. April's 2,080 lamps need 4,160 kg, May's 2,360 need 4,720 kg, and June's 2,280 need 4,560 kg. Use production units, including lamps made for inventory; sales units would miss those inputs.

The purchases calculation then applies a second inventory adjustment:

Purchases=usage+closing materials−opening materials

Multiply the quantity purchased by the budgeted price per kilogram to find purchases cost. Finished goods and raw materials have separate inventory policies.

Apply the materials inventory plan

Brightline keeps closing aluminum inventory at 25% of the next month's usage. April begins with 1,040 kg. April's closing target is 25% of May's 4,720 kg, or 1,180 kg. June's closing target is specified as 1,200 kg. Aluminum costs $3 per kg.

MonthUsage, kgClosing, kgOpening, kgBuy, kgCost
April4,1601,1801,0404,300$12,900
May4,7201,1401,1804,680$14,040
June4,5601,2001,1404,620$13,860

April's usage costs $12,480, while purchases cost $12,900. The $420 difference is 140 kg added to materials inventory. Buying the material also creates a payment obligation, but the cash leaves according to supplier credit terms.

Allow for input losses

When a percentage of input is lost, the usable output is only the surviving share. If finished products need 4,800 kg and 4% of input is lost, 96% survives:

Input=4,800÷0.96=5,000 kg

Check by applying the loss to input: 4% of 5,000 is 200 kg, leaving 4,800. Adding 4% to the finished requirement gives 4,992 kg, which is too little because the loss percentage applies to the larger input quantity.

Budget a retailer's purchases at cost

Northgate buys finished goods for resale. Sales are $150,000 and gross margin is 40% of sales, leaving cost of goods sold of $90,000. Opening inventory is $20,000 and desired closing inventory is $24,000:

90,000+24,000−20,000=94,000

Keep every inventory figure at cost.

Margin measures gross profit as a percentage of sales; markup measures it as a percentage of cost. Northgate's $60,000 gross profit is a 40% margin but a 66⅔% markup. If 40% were a markup, cost would instead be sales divided by 1.40, or $107,142.86. Read which base the percentage uses before preparing purchases.

Key Takeaways

  • Materials usage follows production, not sales.
  • Purchases adjust usage for the change in materials inventory.
  • Divide by the surviving proportion when a percentage of input is lost.
  • Retail purchases equal cost of goods sold plus closing inventory minus opening inventory.
  • Gross margin uses sales as its base; markup uses cost.
  • Purchases feed payables and cash schedules, with timing set by credit terms.

2.3 Budget direct labor, overheads and closing inventory

After materials, budget the people and overhead resources production needs. Quantities come first: calculate working hours, then apply rates. Cost behavior determines overhead allowances, while the inventory valuation method determines which production costs remain in closing inventory.

Turn production into labor hours

Brightline needs 0.5 labor hours per lamp at $24 per hour. April requires 1,040 hours costing $24,960; May requires 1,180 hours costing $28,320; June requires 1,140 hours costing $27,360. May sales are 2,400 lamps, but production is 2,360, so labor must be based on the smaller production quantity.

Paid hours can exceed productive hours. Idle time is paid time without production, such as waiting for materials. If 5% of paid June hours are idle, only 95% produces lamps:

Paid hours=1,140÷0.95=1,200

At $24 per hour, wages become $28,800. Adding 5% to productive hours gives only 1,197 hours because it applies the percentage to the wrong base.

Separate normal pay from overtime

In a separate May what-if plan, only 1,100 normal hours are available. The remaining 80 hours cost time-and-a-half, or $36 per hour:

1,100×24+80×36=29,280

The same result comes from paying all 1,180 hours at $24 and adding the $12 premium on 80 overtime hours. The $960 premium would also increase May's cash wages payment. Brightline's main plan retains $28,320 for May; the overtime calculation is a changed scenario.

Budget overheads by how they behave

Variable production overhead at $2 per lamp gives $4,160 in April, $4,720 in May and $4,560 in June. Fixed production overhead stays at its $15,000 monthly total within the relevant range. A mixed cost needs its fixed amount plus its variable rate times activity.

Selling and administrative expenses sit outside production: office rent, advertising, sales salaries and delivery are examples. Brightline budgets $9,000 a month. A separate 5% commission on April's $80,000 sales would be $4,000; this varies with sales revenue, not production units.

Some costs involve no current cash payment. Brightline's fixed production overhead includes $3,000 monthly depreciation. Its production cost is the full $15,000, while cash paid for that overhead is $12,000. Depreciation spreads the asset cost over its useful life.

Value what remains in inventory

Brightline's variable production cost per lamp is materials $6, direct labor $12 and variable overhead $2, totaling $20. At the end of June, 1,200 kg of aluminum at $3 is worth $3,600. The 520 finished lamps are worth $10,400 under variable costing.

Absorption costing also assigns a share of fixed production overhead to each finished lamp, producing a higher inventory value. Use the costing basis consistently when linking inventory and cost of goods sold; a variable-cost inventory figure cannot simply be inserted into an otherwise absorption-cost calculation.

Key Takeaways

  • Direct labor hours follow production; labor cost applies the pay rate to those hours.
  • Divide productive hours by the productive share to allow for idle time.
  • Pay overtime hours at the full overtime rate, or add only the premium to normal pay for all hours.
  • Budget each overhead using its fixed, variable or mixed behavior.
  • Depreciation is a production cost without a current cash payment.
  • Variable inventory cost excludes fixed production overhead; absorption inventory cost includes a share.
3

Prepare and interpret a cash budget

Cash planning follows payment dates. A sale can earn revenue this month while bringing cash next month, and an equipment payment can drain cash without becoming an immediate expense. Build receipts and payments schedules, carry the balances from month to month, and identify the size and cause of a shortage. Brightline's three-month plan shows why a healthy quarter total can still leave the business needing finance during the quarter.

3.1 Schedule budgeted cash receipts

Cash receipts depend on when customers pay. A credit sale creates revenue and an amount owed by the customer; it does not create a cash receipt until collection. A receipts schedule follows each month's sales into the months when money is expected.

Separate cash sales and credit collections

Brightline receives 25% of each month's sales immediately. The remaining 75% is collected in the following month. March sales were $72,000, so April collects $54,000 from March customers. April also receives 25% of its own $80,000 sales, or $20,000:

54,000+20,000=74,000

The full three-month schedule is:

ReceiptAprilMayJune
Current cash sales$20,000$24,000$22,000
Previous month's credit sales$54,000$60,000$72,000
Total customer receipts$74,000$84,000$94,000

Each credit collection uses the preceding month's sales. May collects 75% of April's $80,000; June collects 75% of May's $96,000. Using current-month credit sales would bring cash into the budget too soon.

The first month needs information from before the budget period. The final month also leaves an amount uncollected: 75% of June's $88,000, or $66,000, becomes closing accounts receivable.

Apply discounts only to the relevant customers

Consider January credit sales of $50,000. Of those customers, 40% pay in February with a 2% discount, 55% pay in March without a discount and 5% never pay.

February collections are:

50,000×0.40×0.98=19,600

The $20,000 receivable settled in February is cleared by $19,600 cash and a $400 discount. March collections are $27,500. The remaining $2,500 is a bad debt. Total cash from this sales group is $47,100, not the $50,000 originally invoiced. A bad debt is an amount not collected, not a separate cash payment.

Track the receivable balance

The accounts receivable budget, also called a trade receivables budget, follows amounts customers owe. Add credit sales to opening receivables, then deduct cash collections, discounts allowed and bad debts written off. All deductions must relate to those receivables; cash sales never entered the balance.

Northgate begins with $18,000 owed by customers, makes $150,000 of credit sales and collects $146,000. With no discounts or write-offs, closing receivables are:

18,000+150,000−146,000=22,000
Include receipts beyond customers

New borrowing, capital contributed by the owner, share issues, interest received and asset-sale proceeds can also bring in cash. Record the amount received on its expected date.

If equipment with a carrying amount of $7,000 sells for $5,000 cash, enter a $5,000 receipt. The $2,000 loss affects the income statement. Recording only the loss or subtracting it from the proceeds would confuse the accounting result with the cash received.

Key Takeaways

  • Cash receipts follow collection dates, including collections from earlier periods.
  • Cash sales and collections of credit sales need separate lines.
  • Discounts reduce the cash collected; bad debts produce no receipt.
  • Receivables rise with credit sales and fall with collections, discounts and write-offs.
  • An asset sale brings in its cash proceeds, regardless of its gain or loss.

3.2 Schedule budgeted cash payments

A payments schedule follows the dates on which money leaves the business. Start with the purchases and expense budgets, then apply credit terms and payment arrangements. Add asset and financing payments that do not appear among operating expenses.

Follow purchases into their payment months

Brightline pays for aluminum one month after buying it. April therefore pays March purchases of $12,600. May pays April purchases of $12,900, and June pays May purchases of $14,040. The June purchases of $13,860 are paid after the quarter and remain in closing accounts payable.

Materials used are not the starting point for supplier payments. May's production uses 4,720 kg, but its supplier payment settles the 4,300 kg purchased in April. These quantities answer different questions.

Build the other payment lines

Brightline pays wages, variable overhead and selling and administrative expenses in the month incurred. Fixed production overhead includes $3,000 depreciation within its $15,000 total, leaving a $12,000 monthly cash payment. A machine costing $40,000 is paid for in May.

PaymentAprilMayJune
Suppliers$12,600$12,900$14,040
Wages$24,960$28,320$27,360
Variable overhead$4,160$4,720$4,560
Fixed overhead paid$12,000$12,000$12,000
Selling and administration$9,000$9,000$9,000
Machine$0$40,000$0
Total$62,720$106,940$66,960
Distinguish expenses from payments

Depreciation, bad debts and losses on asset sales are non-cash expenses. Leave them out of cash payments. Depreciation allocates an asset's cost over its life; including both the asset payment and depreciation would count the cost twice in the cash plan.

The reverse distinction matters too. Equipment purchases, loan principal repayments, owner's drawings and dividends use cash without being operating expenses. Income tax payments belong in the cash budget when paid, even when they differ from the period's tax expense. Interest on a loan is an expense; repaying the borrowed principal reduces a liability.

A $6,000 annual insurance premium paid in January belongs entirely in January's cash budget. The income statement charges $500 for each month covered. Scheduling $500 of cash every month would fail to show the actual January funding need.

Track what suppliers are still owed

The accounts payable budget, also called a trade payables budget, starts with opening payables. Add credit purchases, then subtract cash paid and discounts received to reach the closing balance.

Northgate starts with $15,000 owed to suppliers, buys $94,000 on credit and pays $92,000. With no discounts, it ends owing:

15,000+94,000−92,000=17,000

This balance goes into the budgeted balance sheet. The $92,000 payment goes into the cash budget, and purchases feed cost of goods sold after the inventory adjustment.

Key Takeaways

  • Schedule supplier payments from purchases and credit terms.
  • Leave depreciation and other non-cash expenses out of payments.
  • Include asset purchases, principal repayments and drawings when cash is paid.
  • Prepaid and unpaid expenses create differences between expense and payment.
  • Closing payables equal opening payables plus credit purchases minus settlements and discounts.

3.3 Prepare, interpret and act on a cash budget

Combine receipts and payments in monthly columns. The purpose is to see the cash available at each date, so balances must carry forward correctly. A positive result for the whole quarter can conceal a shortage in the middle month.

Build the monthly balances

List and total receipts, then list and total payments. Net cash flow is receipts minus payments. Add it to the opening cash balance to obtain closing cash. That closing balance becomes the next month's opening balance.

Brightline starts April with $8,000:

Cash budgetAprilMayJune
Total receipts$74,000$84,000$94,000
Total payments$62,720$106,940$66,960
Net cash flow$11,280−$22,940$27,040
Opening balance$8,000$19,280−$3,660
Closing balance$19,280−$3,660$23,380

May's net cash outflow is $22,940, but its closing shortage is only $3,660 because it begins with $19,280. June begins with that negative balance; resetting June to zero would overstate its closing cash.

Quarterly receipts of $252,000 less payments of $236,620 give a $15,380 increase in cash. Added to the original $8,000, that reaches June's $23,380. This total check does not reveal the May overdraft, so retain the monthly columns.

Diagnose the shortage before choosing finance

A negative closing figure means extra finance is needed by that date. Brightline's May payments include a one-off $40,000 machine. Without it, May payments are $66,940 and net cash inflow is $17,060. Day-to-day trading generates cash; the equipment payment causes the shortage.

Managers can arrange an overdraft for a temporary gap, negotiate staged payment, delay the purchase or lease the machine. A long-lived asset is better matched with long-term finance or owner's capital when it creates a lasting financing need. Arrange finance before the payment falls due.

Other ways to release cash include collecting customer debts sooner, increasing cash sales, negotiating longer supplier credit, reducing inventory, postponing drawings or selling unused assets. Consider the consequences: an early-payment discount reduces receipts, and less inventory can weaken delivery reliability. Choose an action that addresses the cause without damaging the business.

Test the timing of a change

If the machine purchase moves from May to July, May closing cash rises by $40,000 to $36,340. That extra cash carries into June, raising its closing balance to $63,380. July must then include the payment. Delaying expenditure shifts the funding need; it does not remove the purchase.

A spreadsheet keeps assumptions in input cells linked to all affected months. Change the date once and check both the current month and later opening balances. For a surplus, consider an interest-earning deposit, repayment of borrowing, supplier discounts or planned expansion, while retaining enough cash for upcoming payments.

Key Takeaways

  • Net cash flow measures the period's movement; closing cash includes the opening balance.
  • Carry every closing balance into the next period, including negative balances.
  • Monthly columns reveal shortages hidden by a positive quarter total.
  • Match financing and corrective action to the reason for the shortage.
  • A timing change affects later balances as well as the month changed.
  • Plan a useful home for surplus cash while allowing for future payments.
4

Build the budgeted income statement and balance sheet

The master budget must show both the profit the plan earns and the financial position it leaves behind. Use Northgate Outdoor Supplies to assemble an income statement and balance sheet from the supporting schedules. Then trace why its planned profit does not produce an equal increase in cash. Following each change through the statements makes it easier to spot omissions such as drawings, unpaid sales or depreciation.

4.1 Prepare a budgeted income statement

The budgeted income statement shows the revenue and expenses planned for the period. It is also called the budgeted statement of profit or loss. It brings together the operating budgets on the accrual basis: revenue is recorded when earned and expenses when incurred, regardless of payment dates.

Bring in the right figures

Revenue comes from the sales budget. Cost of goods sold comes from purchases or production costs together with the inventory plan. Overhead and selling and administrative budgets supply expenses. Asset records and planned capital expenditure supply depreciation.

For a retailer, goods bought but still held at the end of the period are inventory, not cost of goods sold:

Cost of goods sold=opening inventory+purchases−closing inventory

Northgate starts with inventory of $20,000, budgets purchases of $94,000 and plans closing inventory of $24,000. Goods available cost $114,000; subtracting the $24,000 still held leaves $90,000 as cost of goods sold.

Prepare Northgate's statement
Budgeted income statement for the quarterAmount
Sales revenue$150,000
Cost of goods sold$90,000
Gross profit$60,000
Operating expenses$30,000
Depreciation$3,000
Net income$27,000

Gross profit is sales less the cost of the goods sold. Net income then deducts the period's remaining expenses. Northgate's gross margin is 40%, while its net profit margin is 18%. These measures help managers assess whether the planned prices, sales and costs earn an acceptable return before approval.

Keep financing and assets separate

Northgate expects customer cash collections of $146,000, but revenue is $150,000. The uncollected amount remains in receivables. Using collections as sales would omit revenue earned during the quarter and could include collections from sales made earlier.

Purchases of equipment create assets. Their full cost is not an immediate expense; depreciation charges the portion used during the period. Loan principal repayments reduce a liability. Owner's drawings reduce equity. Deducting any of these as operating expenses would understate profit. Conversely, depreciation and unpaid expenses reduce profit even without a cash payment in the quarter.

Apply the production version consistently

For a manufacturer, cost of goods sold starts with opening finished goods, adds cost of goods manufactured and subtracts closing finished goods. Manufacturing cost draws on materials used, direct labor and production overheads. The costing method determines which costs enter inventory.

Brightline's finished lamps have a variable production cost of $20 each. Variable costing uses that figure and treats fixed production overhead as a period cost. Absorption costing includes a share of fixed production overhead in each unit. Keep the inventory valuation basis aligned with the treatment of production costs throughout the statement.

If Northgate used its $94,000 purchases as cost of goods sold, profit would fall by $4,000. That would expense the inventory increase even though those goods remain available for future sales.

Key Takeaways

  • The income statement records earned revenue and incurred expenses on the accrual basis.
  • Retail cost of goods sold adjusts purchases for opening and closing inventory.
  • Gross profit deducts cost of goods sold; net income also deducts other expenses.
  • Equipment purchases, drawings and loan principal repayments are not operating expenses.
  • Use a consistent costing method for manufactured goods and inventory.

4.2 Prepare a budgeted balance sheet

A budgeted balance sheet projects assets, liabilities and owner's equity at the end of the budget period. It is also called a budgeted statement of financial position. Begin with the opening balances and apply the changes in the supporting budgets.

Trace each closing balance

Use closing cash from the cash budget, receivables and payables from their schedules, and inventory from the closing inventory plan. For equipment, add purchases to the opening carrying amount, subtract the carrying amount of disposals and subtract depreciation. For a loan, add new borrowing and subtract principal repaid.

Owner's equity needs its own roll-forward: opening capital plus capital contributed plus net income minus drawings. Profit belongs to the owner even when the cash has not yet been collected. Drawings reduce the owner's claim without reducing profit.

Start with a balanced opening position

Northgate begins January with cash $12,000, receivables $18,000, inventory $20,000 and net equipment $60,000. Assets total $110,000. Payables of $15,000, a loan of $25,000 and owner's capital of $70,000 also total $110,000.

Its quarter cash budget includes $146,000 customer receipts. Payments are suppliers $92,000, operating expenses $30,000, equipment $10,000, loan principal $5,000 and drawings $9,000. These payments total $146,000, so cash ends unchanged at $12,000.

Apply the budgeted changes

Receivables finish at $22,000 and inventory at $24,000. Equipment increases by the $10,000 purchase and falls by $3,000 depreciation, leaving $67,000. Payables rise to $17,000. The loan falls by $5,000 to $20,000. Capital becomes:

70,000+27,000−9,000=88,000

Northgate introduces no additional capital this quarter.

Closing balance sheet, March 31Amount
Cash$12,000
Accounts receivable$22,000
Inventory$24,000
Equipment, net$67,000
Total assets$125,000
Accounts payable$17,000
Loan$20,000
Owner's capital$88,000
Total liabilities and equity$125,000
Check both sides of each change

If the statement does not balance, trace transactions through all affected balances. Equipment bought for cash increases equipment and reduces cash. A principal repayment reduces cash and the loan. Depreciation reduces equipment and profit, which feeds equity. Drawings reduce cash and capital. Omitting one side leaves the statement inconsistent.

Do not insert a balancing cash figure to hide an error: cash must agree with the cash budget. Common omissions are profit in equity, drawings, depreciation and principal repayments.

With the loan treated as noncurrent, Northgate has current assets of $58,000 and current liabilities of $17,000, a current ratio of about 3.41. This helps assess the planned ability to meet short-term obligations. A corporation reports share capital and retained earnings; closing retained earnings equal opening retained earnings plus net income minus dividends declared.

Key Takeaways

  • Build each closing balance from the opening position and supporting budgets.
  • Cash must agree with the closing cash budget.
  • Equipment changes for purchases, disposals and depreciation; loans change for borrowing and principal repayments.
  • Owner's capital rises with contributions and profit and falls with drawings.
  • Trace both effects of transactions when checking an imbalance.
  • Corporate retained earnings rise with net income and fall with dividends declared.

4.3 Explain why budgeted profit and budgeted cash differ

Northgate plans $27,000 net income, yet cash stays at $12,000. Profit measures earned revenue less incurred expenses. Cash measures receipts less payments, including asset and financing flows. A reconciliation explains how the two results fit together.

Start with profit and remove non-cash effects

Northgate's net income includes $3,000 depreciation. Add it back because it reduced profit without using cash in the quarter. The add-back creates no cash; it reverses an expense when moving from profit to cash flow.

Credit sales also create timing differences. Receivables rise by $4,000, meaning that amount of revenue has not become cash. Inventory rises by $4,000, tying up funds in unsold goods. Payables rise by $2,000, meaning some purchases have not yet been paid for.

Reconciliation to operating cash flowAmount
Net income$27,000
Add depreciation$3,000
Deduct increase in receivables−$4,000
Deduct increase in inventory−$4,000
Add increase in payables$2,000
Cash from operating activities$24,000

Check the same result directly: customer receipts $146,000 less suppliers $92,000 and operating expenses paid $30,000 equal $24,000.

Add investing and financing flows

The equipment payment of $10,000 uses cash without being a full current expense. Loan principal of $5,000 and drawings of $9,000 also use cash without reducing profit. Deducting these three amounts from $24,000 operating cash leaves no net change in cash.

Classify the flows by their purpose:

ActivityExamplesNorthgate's net flow
OperatingCustomers, suppliers, employees and operating expenses$24,000
InvestingPurchases and sales of noncurrent assets−$10,000
FinancingBorrowing, principal repayments and owner transactions−$14,000

The total is zero, consistent with unchanged opening and closing cash. The $27,000 profit instead raises capital before drawings are deducted.

Understand the practical risk

A growing, profitable business can run short of cash when more funds are tied up in receivables and inventory. Customers may owe enough to support a healthy profit while cash is unavailable to pay wages. This can be part of overtrading, where growth strains the funds supporting operations.

A loss-making business may temporarily have cash because it borrowed or sold assets. Neither a cash balance nor a profit figure answers both questions: managers need to know whether operations earn a return and whether payments can be met.

Compare plans with past cash reports

A cash budget looks forward and serves managers' planning needs, often month by month. A statement of cash flows reports actual past flows in operating, investing and financing categories for owners, lenders and other users. Comparing actual flows with the budget helps explain changed collections, spending or financing. Budgeted flows can use the same activity categories while still remaining a forecast of the future.

Key Takeaways

  • Depreciation is added back because it reduced profit without a cash payment.
  • Rising receivables and inventory reduce operating cash relative to profit; rising payables increase it.
  • Equipment, borrowing, repayments and owner transactions explain further profit–cash differences.
  • Operating, investing and financing flows together explain the change in cash.
  • A cash budget plans future flows; a statement of cash flows reports actual past flows.
5

Use fixed and flexible budgets to control performance

Actual activity often differs from the level in the approved plan. Before judging spending, work out what the budget allows for the output actually achieved. Use Ridgeway Ceramics to flex variable, fixed, mixed and stepped costs, then calculate variances and reconcile the change in profit. A useful report separates the effect of volume from the remaining differences and helps managers decide what to investigate.

5.1 Flex a budget to the actual level of activity

A fixed budget is prepared for one planned activity level. If actual output changes, comparing costs with that original total mixes the effect of activity with the effect of spending. A flexible budget calculates the allowance for actual activity using the budgeted cost behavior.

Compare like levels of activity

Ridgeway planned 10,000 vases at materials cost of $6 each, giving $60,000. Actual output is 9,000 and materials cost is $56,700. The fixed comparison appears $3,300 favorable, but the allowance for 9,000 vases is only $54,000. Actual cost exceeds that by $2,700.

Use actual output with budgeted rates. Actual rates belong in actual results; using them to flex the budget would erase the differences the comparison should reveal.

Flex each line by its behavior

Ridgeway sells all the vases it produces, so sales and output use the same unit count:

LineBudgeted basisAt 10,000 vasesAt 9,000 vases
Revenue$40 per vase$400,000$360,000
Materials$6 per vase$60,000$54,000
Direct labor$12 per vase$120,000$108,000
Variable overhead$2 per vase$20,000$18,000
Fixed overhead$45,000 total$45,000$45,000
ProfitRevenue less all costs$155,000$135,000

Fixed overhead stays at its budgeted total within the relevant range. When sales and production differ, flex revenue to actual units sold and production costs to actual units produced.

Separate mixed costs

Maintenance of $5,000 plus $0.50 per vase allows $9,500 at 9,000 vases. Only the variable part follows output.

If only two activity totals are given, high-low can identify the parts. Power costs $26,000 at 8,000 vases and $30,000 at 10,000. The $4,000 change across 2,000 vases gives $2 per vase. Deducting $20,000 variable cost from the higher total leaves $10,000 fixed. At 9,000 vases, power is budgeted at $28,000.

Respect cost steps

One supervisor costs $6,000 a quarter and can oversee up to 4,000 vases. Output of 7,000 needs two supervisors, costing $12,000; 9,000 needs three, costing $18,000. Both 9,000 and 10,000 lie in the same three-supervisor band. Scaling $18,000 by 90% would incorrectly allow $16,200: a whole third supervisor is still needed.

Flexible budgets also help plan before the period begins. Ridgeway earns contribution of $20 per vase after variable production cost of $20. With fixed overhead $45,000, profit is $115,000 at 8,000 vases, $135,000 at 9,000 and $155,000 at 10,000. This range shows the volume effect while holding the price and cost assumptions constant.

Key Takeaways

  • Flex the allowance to actual activity with budgeted prices and cost rates.
  • Variable totals change with activity; fixed totals stay unchanged within the relevant range.
  • Split mixed costs into fixed and variable parts.
  • Stepped costs follow whole capacity bands, not proportional scaling.
  • Use units sold for revenue and units produced for production costs.
  • Flexible budgets can compare possible activity levels before the period as well as support control afterward.

5.2 Calculate, report and act on budget variances

A budget variance is the difference between an actual amount and its budget. Against a fixed budget it includes the effect of different activity. Against a flexed budget it shows the remaining revenue and cost differences at actual activity. Label results favorable (F) when they increase profit and unfavorable (U) when they reduce it. Unfavorable is also called adverse (A).

Prepare a flexed variance report

Ridgeway actually sells 9,000 vases at $39 each. Revenue is $351,000. Actual production costs total $232,100, leaving $118,900 profit. Compare with the flexed budget for 9,000 vases:

LineFlexed budgetActualVariance
Revenue$360,000$351,000$9,000 U
Materials$54,000$56,700$2,700 U
Direct labor$108,000$110,000$2,000 U
Variable overhead$18,000$18,900$900 U
Fixed overhead$45,000$46,500$1,500 U
Profit$135,000$118,900$16,100 U

Higher revenue is favorable; higher cost is unfavorable. A plus sign alone cannot express both meanings clearly. For materials, $2,700 above allowance is 5.0% of the $54,000 flexed budget.

Reconcile the profit difference

The fixed budget planned $155,000 profit. Selling 1,000 fewer vases at budgeted contribution of $20 reduces profit by $20,000, giving flexed profit of $135,000. The $16,100 unfavorable flexible budget variance then brings profit to $118,900:

155,000−20,000−16,100=118,900

This accounts for the full $36,100 shortfall. For costs alone, flexed production cost is $225,000 and actual cost is $232,100. The $7,100 difference equals the four cost variances added together; the revenue variance is excluded from this cost reconciliation.

Decide what to investigate

Management by exception focuses attention on significant differences. Dollar size, percentage size, repeated trends and critical items all matter. Ridgeway's materials variance is 5.0%, fixed overhead about 3.3%, revenue 2.5% and labor about 1.9%. A recurring smaller difference may need action before a one-time larger one.

A report identifies where results differ, but investigation establishes why. Materials might cost more because prices rose or waste increased. Labor might rise through overtime or slow work. Discounts might reduce revenue. The budget itself might also have been unrealistic. Treat these as possible causes until evidence supports one.

Choose action with the whole business in view

Supplier negotiation, training, equipment repair, pricing changes or a revised plan should address the cause found. Cheaper materials can save purchasing cost while increasing waste and labor time. Reduced advertising may create a favorable expense variance while weakening future demand. Include quality, reliability, customer satisfaction and morale in the decision.

Evaluate managers on what they can control. A head-office rent decision should not be treated as a production manager's operating failure. Reports are most useful when they arrive promptly and support explanation and action.

Key Takeaways

  • Revenue above budget is favorable; cost above budget is unfavorable.
  • A flexed comparison separates remaining performance differences from the effect of volume.
  • Reconcile fixed profit to flexed profit, then to actual profit.
  • A cost-only reconciliation excludes revenue variances.
  • Investigate significant sizes, percentages, trends and critical items.
  • Check causes, controllability and non-financial effects before choosing action.
6

Explain how budgets affect people's behavior

A budget shapes decisions because it gives people targets and often affects their rewards. How managers set those targets, share information and discuss results can strengthen effort or encourage games. Compare imposed and participative approaches, distinguish realistic planning from stretch targets, and examine slack, wasteful spending and short-term cuts. The aim is to make meeting a department's target support the whole organization.

6.1 Set budgets that motivate

Budgets influence effort because they define success and often determine rewards. A motivating budget combines useful local knowledge, accepted targets and fair evaluation. Goal congruence exists when people pursuing their own targets also advance the organization's goals.

Compare who sets the budget
ApproachStrengthsRisks
Top-down or imposedFast; aligns targets with strategy; reduces managers' direct opportunity to pad their proposalsMay overlook local knowledge and create little ownership
Bottom-up or participativeUses operating knowledge; builds commitment; supports realistic detailTakes time; allows slack; needs coordination with strategy

In practice, management may set overall objectives while responsible managers propose details and negotiate. Participation gives the people delivering a plan a chance to explain what is achievable. It also gives them influence over targets, so informed review remains necessary.

Brightline's head office estimates May sales at 2,000 lamps from past trends. The sales manager knows a new retailer will buy 400 per month from May and proposes 2,400. Ignoring that information would leave the production plan 400 lamps short of real demand. The manager's contribution improves coordination, not just morale.

Choose targets people will work toward

A very easy target offers little reason for extra effort. A target viewed as impossible can lead people to give up or manipulate results. Challenging but achievable targets that managers accept tend to support motivation.

A stretch target expresses an aspiration. A realistic planning estimate expresses what management expects. These figures serve different purposes. Putting an optimistic stretch sales target into the cash budget overstates expected collections and can hide a financing need. Keep the cash plan grounded in realistic expectations even when the sales team also works toward a more demanding aspiration.

Align rewards with the result the business needs

A bonus for staying below a maintenance budget focuses attention on that cost. It can also encourage postponing repairs until after the reward date. The current expense line improves while equipment reliability deteriorates.

Combine financial targets with measures of quality, customer satisfaction, staff development and longer-term results. A purchasing manager should consider the effect of material choices on production waste and complaints, as well as the invoice price. That aligns departmental success with the business's overall result.

Make evaluation fair and useful

Managers need timely reports and an allowance flexed to actual activity. Responsibility must follow control: a production manager can influence material usage but may have no influence over factory rent negotiated by head office. Separate controllable and uncontrollable items so the discussion centers on decisions the manager can change.

Open discussion of a variance helps managers explain operating conditions and agree improvements. Rigid punishment for every missed figure raises pressure to hide problems. Local knowledge is most useful when people can report a developing problem early enough for others to respond.

Key Takeaways

  • Goal congruence aligns departmental targets with organizational success.
  • Participation brings local knowledge and ownership but also requires informed review.
  • Challenging, achievable and accepted targets tend to motivate.
  • Use realistic expectations for planning and distinguish them from stretch aspirations.
  • Combine budget rewards with long-term and non-financial measures.
  • Evaluate managers with timely flexed reports and controllable responsibilities.

6.2 Recognize and limit dysfunctional budget behavior

A manager can meet a target while harming the organization. This is dysfunctional behavior. The incentive system may make an unhelpful choice personally rewarding, so prevention needs attention to how targets and rewards work.

Recognize budgetary slack

Budgetary slack is deliberate padding: overstating expected costs or understating expected revenue to make a target easier. A manager expecting costs of $50,000 submits $56,000. The $6,000 difference is 12% of the realistic estimate.

Slack can protect a bonus or provide a cushion against uncertainty. Managers may also pad because they expect senior management to cut every request. Blanket cuts then reinforce the incentive to pad again next year. Resources become tied to misleading plans, and inflated cost estimates can lead to prices that are too high.

Distinguish deliberate padding from an honest estimate that later proves wrong. A changing forecast reflects new expectations; slack intentionally misrepresents the expectation when the proposal is made.

Notice spending driven by the budget rule

"Spend it or lose it" arises when unused funds are removed and future budgets depend on current spending. A department with $4,000 left in the final week buys equipment it does not need to protect next year's allocation. It meets the spending plan but wastes resources.

Review whether the purchase serves a real operating need. Budget evaluation should value a justified saving, not make spending the full allowance the safest way to secure future resources.

Look beyond the reporting date

Short-termism means improving the current result at the expense of future performance. Cutting training, maintenance, research or marketing can reduce this period's expenses while damaging future capability or revenue. The dollar saving must be weighed against the effect on service, equipment and staff.

Manipulating results is another risk. Heavy discounts may pull future sales into the current period. Delaying the recording of a cost makes reported performance misleading and raises ethical issues. Decisions based on those figures then begin from a false picture of the business.

Check effects across departments

A purchasing manager rewarded only for low material prices may buy poor-quality inputs. Purchasing meets its target while production faces waste and extra labor, and customers may face faulty products. The separate budgets should support one coordinated outcome, so investigate the total effect across departments.

Reduce the incentive to game results

Participation alone does not remove slack: it gives managers more influence over proposals. Review their estimates against operating evidence, past results and useful benchmarks. Ask someone who understands the work to challenge assumptions.

Reward forecast accuracy and longer-term results as well as budget performance. Use flexed comparisons, separate controllable items and include quality and customer measures. A culture where managers can explain variances openly makes it easier to surface problems; automatic punishment gives them a reason to hide them.

Key Takeaways

  • Slack deliberately makes targets easier through inflated costs or understated revenue.
  • Spend-it-or-lose-it rules can reward wasteful year-end purchases.
  • Short-term cuts can damage future results; manipulated records mislead decisions.
  • A departmental saving can create larger costs elsewhere.
  • Reduce gaming through informed review, fair evaluation and broader rewards.

Budgeting examples

6 Walkthroughs

1

Build a plan the business can deliver

10 steps
Connect budgeting purposes with constraints, responsibility and the master budget.
  1. 1
    IntroductionTurn intentions into a workable plan

    A business can have plenty of customer demand and still promise more than its factory or cash can support. Budgeting brings the separate plans together before that happens.

    Follow a plan from its forecast through coordination and approval. Then see how comparing actual results with the approved figures gives managers a reason to investigate and act.

  2. 2
    ExplanationSeparate the estimate from the commitment

    A forecast estimates a likely outcome. A budget is management's agreed plan and commitment of resources.

    "April demand will probably be about 2,000 lamps" is a forecast. Brightline's approved sales plan specifies 2,000 lamps at $40, giving $80,000 revenue. That agreed quantity guides production, while the expected payment pattern will guide cash planning.

  3. 3
    ExampleFind the gap between sales and supply

    Brightline plans 2,400 May sales. Production plans 2,000 lamps and expects 300 in opening inventory.

    Only 2,300 lamps are available, so the plans leave 100 orders uncovered. Bringing sales and production together exposes the gap before orders are missed. Managers can revise production, inventory or the sales plan while there is still time to act.

  4. 4
    ChallengeDecide whether comparison is enough

    A manager prepares a budget and records actual spending but never compares the two. What part of budgetary control is missing?

    ---reveal---

    The manager needs to compare results, investigate significant variances and act on the causes. The plan can still help preparation, but recording figures alone does not show where the business is moving away from its agreed targets.

  5. 5
    Key InsightUse budgets for more than cost cutting

    An advertising budget can authorize more spending to support planned sales. A labor budget can reveal a need to hire. Budgeting coordinates resources with the result the business wants.

    The same figures communicate expectations, give people targets and provide a basis for evaluation. A lower spending figure still needs interpretation: fewer units or damaged service can make a saving misleading.

  6. 6
    ExplanationFind what limits activity first

    The principal budget factor is the constraint limiting activity in the period. Identify it first because dependent budgets must fit within it.

    Sales demand often sets the limit. Skilled labor, materials, machine time, cash or space can constrain the business instead. Preparing resource budgets before resolving that constraint risks building a detailed plan that cannot be delivered.

  7. 7
    ExampleCalculate the capacity ceiling

    Customers would buy 12,000 units, but only 5,000 machine hours are available. Each unit needs 0.5 hours:

    5,000÷0.5=10,000 units

    With 500 units already held and no closing reserve required, sales can reach 10,500. Meeting the full demand would require added capacity; the sales forecast alone cannot supply the missing machine hours.

  8. 8
    ConnectionJoin the budgets into one set

    After resolving the constraint, a manufacturer links sales to production, then to materials, labor and overheads. Inventory and operating costs feed profit; capital spending and payment dates feed cash.

    The master budget coordinates these plans and summarizes profit, cash and the closing balance sheet. Line managers prepare proposals, a committee coordinates them and owners or the board approve them.

  9. 9
    ChallengeRespond to a cash problem in the draft

    A draft sales and production plan fits capacity, but the cash budget shows that the planned machine payment cannot be funded. What should happen before approval?

    ---reveal---

    Managers must revise and coordinate the linked plans, perhaps arranging finance or changing the purchase timing. A workable production quantity alone is insufficient when the spending cannot be paid for. The revisions must flow through cash and asset budgets.

  10. 10
    RecapFollow the plan through to action

    Start with realistic information and the factor limiting activity. Make departmental quantities and timing agree, then check the combined profit, cash and financial position before approval.

    During the period, record actual results, compare them with suitable budget allowances and act on significant differences. A spreadsheet speeds revisions, but its formulas and assumptions still need checking.

2

Turn lamp sales into production resources

17 steps
Calculate finished goods, materials, labor, overheads and inventory values in sequence.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionFollow the quantities before the dollars
  2. 2
    ExamplePrice the sales plan
  3. 3
    ExplanationSet the finished goods reserve
  4. 4
    ExampleCalculate April production
  5. 5
    ChallengeCarry the reserve into May
  6. 6
    ExplanationTranslate lamps into aluminum usage
  7. 7
    ExampleAdjust usage to find purchases
  8. 8
    ChallengeFind input when some material is lost
  9. 9
    ConnectionUse the retailer’s version
  10. 10
    ExampleTurn production into labor hours
  11. 11
    ExampleAllow for paid idle time
  12. 12
    ExamplePrice the overtime hours once
  13. 13
    ChallengeSeparate an overhead cost from its payment
  14. 14
    ExplanationApply overhead drivers
  15. 15
    ExampleValue the closing inventories
  16. 16
    ChallengeTrace an inventory policy change
  17. 17
    RecapKeep each schedule’s job clear
3

Build Brightline’s monthly cash plan

14 steps
Schedule receipts and payments, carry balances forward and test the machine purchase timing.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionFind when the money moves
  2. 2
    ExplanationFollow each group of customers
  3. 3
    ExampleCalculate April customer receipts
  4. 4
    ChallengeApply a discount to one collection group
  5. 5
    ExplanationUse supplier terms for payment dates
  6. 6
    ExampleComplete the payment schedule
  7. 7
    ChallengeDecide how a debt repayment appears
  8. 8
    ExampleCalculate the first closing balance
  9. 9
    ExampleCarry cash into the difficult month
  10. 10
    Key InsightRead the shortage amount correctly
  11. 11
    ChallengeIdentify the cause before choosing action
  12. 12
    ExampleMove the machine payment to July
  13. 13
    ConnectionUse the quarter as a check
  14. 14
    RecapRead the budget as a funding timetable
4

Build statements that agree with the cash plan

14 steps
Assemble Northgate’s profit and closing position, then reconcile the unchanged cash balance.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionBring the supporting budgets together
  2. 2
    ExplanationUse earned revenue and incurred expense
  3. 3
    ExampleFind the cost of the goods sold
  4. 4
    ChallengeComplete the profit calculation
  5. 5
    ExplanationRoll forward the asset balances
  6. 6
    ExampleRoll forward the financing balances
  7. 7
    ExampleCheck the closing position
  8. 8
    ChallengeTrace drawings through both sides
  9. 9
    ExplanationReverse the non-cash deduction
  10. 10
    ExampleAllow for uncollected sales and inventory
  11. 11
    ExampleAllow for unpaid purchases
  12. 12
    ChallengeFind the cash change after other flows
  13. 13
    ConnectionClassify flows and compare periods
  14. 14
    RecapCheck the same plan in three views
5

Separate volume from budget variances

13 steps
Flex Ridgeway’s budget and reconcile the gap between planned and actual profit.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionChoose a fair comparison
  2. 2
    ExampleQuestion the apparent materials saving
  3. 3
    ExplanationKeep budgeted rates and actual activity
  4. 4
    ChallengeFlex the fixed and variable parts
  5. 5
    ExampleCheck a capacity step
  6. 6
    TipMatch the allowance to the right activity
  7. 7
    ExplanationLabel the effect on profit
  8. 8
    ExampleAdd the remaining cost differences
  9. 9
    ChallengeReconcile the complete profit gap
  10. 10
    ExampleMeasure the materials difference
  11. 11
    Key InsightTreat causes as questions to investigate
  12. 12
    ChallengeChoose what to examine before rewarding a saving
  13. 13
    RecapMove from comparison to a justified response
6

Set targets that support good decisions

11 steps
Compare target-setting approaches and diagnose the incentives behind budget games.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionAsk what the target rewards
  2. 2
    ExplanationCompare imposed and participative plans
  3. 3
    ExampleUse the knowledge close to the work
  4. 4
    ChallengeKeep aspiration out of expected collections
  5. 5
    ConnectionEvaluate what the manager can influence
  6. 6
    ExampleFind deliberate padding
  7. 7
    ChallengeDiagnose the year-end purchase
  8. 8
    ExplanationLook beyond the current result
  9. 9
    ChallengeRepair a cross-department incentive
  10. 10
    TipReduce the reason to hide problems
  11. 11
    RecapMake departmental success help the whole business

Budgeting practice questions

50 Practice Questions in 5 sets

Set 1: Connect plans, resources and cash10 Practice Questions

Question 1 of 10

A studio sells $42,000 in August and $36,000 in July. It collects 30% in the sale month and 70% one month later. What customer cash arrives in August?
  1. $37,800
  2. $42,000
  3. $40,200
  4. $12,600
Show answerHide answer
Answer: A
August receives $12,600 from its own sales and $25,200 from July, totaling $37,800. Using all $42,000 of August sales would treat credit revenue as immediate cash. The uncollected part of August sales instead enters September collections under this payment pattern.

Question 2 of 10

A business pays $4,700 for equipment in October. Its October depreciation is $390, with no other equipment payments. What equipment-related cash payment belongs in October?
  1. $5,090
  2. $4,700
  3. $4,310
  4. $390
Show answerHide answer
Answer: B
The cash budget records the $4,700 paid for the equipment. Depreciation of $390 allocates asset cost to the income statement and involves no October payment. Adding it to the purchase would count a non-cash charge as a second cash outflow for the asset.

Question 3 of 10

A retailer has opening inventory of $16,000, purchases of $72,000 and closing inventory of $19,000. What is budgeted cost of goods sold?
  1. $72,000
  2. $75,000
  3. $53,000
  4. $69,000
Show answerHide answer
Answer: D
Goods available cost $88,000; deducting $19,000 still held leaves $69,000 as cost of goods sold. Using purchases of $72,000 would expense the $3,000 increase in inventory. Those unsold goods remain an asset available for a later sales period.

Question 4 of 10

A factory budgets variable packaging cost at $1.80 per item and actually produces 6,500 items. What is its flexed packaging allowance?
  1. $6,500
  2. $18,000
  3. $11,700
  4. $13,000
Show answerHide answer
Answer: C
A variable cost allowance uses the budgeted rate multiplied by actual activity: 6,500 items at $1.80 gives $11,700. The number of items alone is not a dollar cost. Flexing retains the planned rate so the later actual-cost comparison can reveal any spending difference.

Question 5 of 10

Head office asks branch managers to propose budgets using local demand information, then negotiates the final figures. What budgeting approach uses that involvement?
  1. Imposed budgeting
  2. Participative budgeting
  3. Management by exception
  4. Fixed-cost budgeting
Show answerHide answer
Answer: B
Participative budgeting involves the managers responsible for delivering the plan in preparing its detail. Final approval can still rest with head office. An imposed approach would set the figures centrally and pass them down, without this local role in proposing the budget.

Question 6 of 10

A bakery will use 720 kg of flour, has 110 kg available and plans to finish with 140 kg. Flour costs $4 per kg. What is its budgeted purchases cost?
  1. $2,880
  2. $2,760
  3. $3,000
  4. $3,440
Show answerHide answer
Answer: C
The bakery must buy 720 plus 140 minus 110, or 750 kg; at $4 per kg this costs $3,000. The $2,880 figure prices only the flour used. It omits the extra 30 kg needed to increase inventory to the planned closing quantity.

Question 7 of 10

A chair maker plans to sell 1,450 chairs, begins with 180 and wants 230 in closing inventory. How many chairs must it produce?
  1. 1,500 chairs
  2. 1,400 chairs
  3. 1,680 chairs
  4. 1,860 chairs
Show answerHide answer
Answer: A
Sales require 1,450 chairs and the inventory reserve must increase by 50, so production is 1,500. Subtracting closing inventory and adding opening inventory gives 1,400, but reverses the adjustment. Inventory is rising, so production must be greater than sales.

Question 8 of 10

A café approves $3,200 for staff training next quarter. What budget purpose gives the manager permission to spend this amount?
  1. Forecasting
  2. Authorization
  3. Performance evaluation
  4. Coordination
Show answerHide answer
Answer: B
Authorization gives a manager permission to use resources within an approved amount. Forecasting estimates a likely outcome but does not itself approve the training expenditure. The spending decision here has already been agreed, so it is part of the budget.

Question 9 of 10

After comparing actual delivery spending with budget, a manager finds repeated excess fuel use. What next step completes the control cycle?
  1. Approve the same budget and stop reviewing fuel use.
  2. Treat the difference as permission for extra spending.
  3. Replace the spending report with the sales forecast.
  4. Investigate the cause and take corrective action.
Show answerHide answer
Answer: D
Budgetary control uses a significant variance to prompt investigation and action. Simply recording the excess leaves the cause unchanged, so comparison alone does not complete the cycle. The manager needs evidence about fuel use before choosing an appropriate operating response.

Question 10 of 10

A buyer earns a bonus for low purchase prices. Cheaper fabric saves $1,800 but adds $2,600 in repair and rework costs. How should management assess the combined cost effect and revise the bonus to support the whole business?
  1. Costs rose $800; include quality and rework in the bonus.
  2. Costs fell $800; include quality and rework in the bonus.
  3. Costs rose $800; reward purchase-price savings alone.
  4. Costs fell $4,400; reward purchase-price savings alone.
Show answerHide answer
Answer: A
The purchase saving is outweighed by rework, increasing combined cost by $800. Including quality and rework in the bonus aligns the buyer with the overall result. Keeping a price-only bonus recognizes the local saving while preserving the incentive that created larger costs elsewhere.
Set 2: Carry budgets into financial results10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A workshop can obtain only 900 kg of a special material; labor and machines are available for more output than this permits. What is its principal budget factor?
  1. Skilled labor capacity
  2. Machine-hour capacity
  3. Material availability
  4. The budget timetable
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A bike maker holds closing inventory at 15% of next month’s sales. March sales are 800 bikes, April sales 1,000, and March opens with 130 bikes. What is March production?
  1. 820 bikes
  2. 790 bikes
  3. 850 bikes
  4. 950 bikes
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A print shop needs 855 productive hours. It expects 5% of paid hours to be idle and pays $20 per hour. What labor cost should it budget?
  1. $17,100
  2. $17,955
  3. $19,000
  4. $18,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Of $80,000 in February credit sales, 35% is collected in March with a 3% discount, 60% in April without a discount and 5% is written off. How much total cash is collected from these sales?
  1. $76,000
  2. $75,160
  3. $73,720
  4. $77,600
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A repair shop opens November with $4,500, receives $18,200 and pays $25,400. What is its closing cash balance before new finance?
  1. −$7,200
  2. $2,700
  3. −$2,700
  4. $11,700
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A store budgets gross profit of $48,000, operating expenses of $26,000 and depreciation of $4,000. What is its budgeted net income?
  1. $22,000
  2. $26,000
  3. $14,000
  4. $18,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

An owner begins with capital of $62,000, contributes $7,000, earns budgeted profit of $15,000 and plans drawings of $9,000. What is closing capital?
  1. $75,000
  2. $68,000
  3. $84,000
  4. $93,000
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Factory rent is budgeted at $12,000 a month throughout the relevant range. Actual output is 20% below plan and remains in that range. What is flexed rent?
  1. $9,600
  2. $12,000
  3. $14,400
  4. $10,000
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Flexed delivery cost is $8,400 and actual delivery cost is $8,950. What is the flexible budget variance?
  1. $550 favorable
  2. $8,400 unfavorable
  3. $8,950 favorable
  4. $550 unfavorable
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A sales team’s stretch target is $240,000, while its realistic sales expectation is $210,000. Half of sales are collected immediately. Why would using the stretch target distort the immediate-receipts budget?
  1. It would overstate expected immediate receipts by $30,000.
  2. It would understate expected immediate receipts by $15,000.
  3. It would overstate expected immediate receipts by $15,000.
  4. It would understate expected immediate receipts by $30,000.
Show answerHide answer

Save this lesson to see this answer.

Set 3: Check timing, valuation and performance10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A manager expects next year’s repairs to cost $24,000 but deliberately submits $27,000 to make the target easier. What behavior is this?
  1. An updated forecast
  2. Budgetary slack
  3. A stepped fixed cost
  4. Management by exception
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A business has demand for 8,600 units, 3,600 machine hours and a requirement of 0.45 hours per unit. It has no finished goods inventory. What maximum sales volume can the current capacity support?
  1. 8,600 units
  2. 7,740 units
  3. 9,200 units
  4. 8,000 units
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A store budgets sales of $168,000 at a markup of 40% on cost. Opening inventory is $22,000 and closing inventory is planned at $28,000. What purchases should it budget?
  1. $106,800
  2. $126,000
  3. $114,000
  4. $120,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A workshop must produce 1,600 items at 0.4 labor hours each. It has 600 normal hours at $25; extra hours cost time-and-a-half. With no idle time, what is total labor cost?
  1. $16,000
  2. $17,500
  3. $16,500
  4. $15,000
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A shop opens with payables of $11,000, buys $54,000 on credit and ends owing $14,000. There are no discounts. How much cash does it pay suppliers?
  1. $51,000
  2. $54,000
  3. $57,000
  4. $43,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A business plans closing cash of −$6,000 in May and $9,000 in June. It moves a $14,000 equipment payment from May to June, with all else unchanged. What are the revised May and June closing balances?
  1. $8,000 and $23,000
  2. −$6,000 and −$5,000
  3. $8,000 and $9,000
  4. $8,000 and −$5,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A business opens with equipment carrying amount of $46,000, buys $8,000 of equipment and budgets $5,000 depreciation. There are no disposals. What is closing equipment carrying amount?
  1. $54,000
  2. $49,000
  3. $41,000
  4. $59,000
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Budgeted profit is $32,000 and depreciation $4,000. Receivables rise $6,000, inventory falls $2,000 and payables fall $3,000. Equipment payments are $10,000 and principal repayments $5,000. With no other reconciling items, what is the net cash change?
  1. $10,000 increase
  2. $20,000 increase
  3. $24,000 increase
  4. $14,000 increase
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Budgeted maintenance is $6,400 plus $0.80 per unit. Actual output is 7,000 units. What is the flexed maintenance allowance?
  1. $12,000
  2. $5,600
  3. $10,080
  4. $13,440
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Materials spending is $18,900 against a flexed allowance of $18,000. What percentage variance should the report show?
  1. 5% favorable
  2. 4.76% unfavorable
  3. 5% unfavorable
  4. 4.76% favorable
Show answerHide answer

Save this lesson to see this answer.

Set 4: Diagnose linked budgeting decisions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A department spends 8% less than its fixed cost budget after its activity falls 15%. What further comparison is needed to evaluate cost performance?
  1. Compare actual spending with a budget flexed to actual activity.
  2. Compare the spending percentage only with last year’s spending.
  3. Compare actual spending with cash collected from customers.
  4. Compare the spending saving with the original sales target.
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A maker has 2,800 labor hours, needs 0.5 hours per unit and has 300 finished units. Demand is 6,200 and desired closing inventory is 200. Without extra labor, what is the highest feasible sales budget?
  1. 5,600 units
  2. 5,900 units
  3. 5,700 units
  4. 6,200 units
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A maker plans monthly sales of 900, 1,100 and 1,000 units, followed by 1,200 next month. Closing inventory is 25% of next month’s sales and opening inventory is 240. What is quarter production?
  1. 3,000 units
  2. 3,060 units
  3. 3,010 units
  4. 3,585 units
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A factory must produce 1,500 units containing 3 kg of usable material each. It loses 10% of material input, opens with 700 kg and wants 900 kg at the end. What quantity must it purchase?
  1. 4,700 kg
  2. 5,150 kg
  3. 5,000 kg
  4. 5,200 kg
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Opening receivables are $12,000. Credit sales are $64,000, cash collected from those receivables is $59,000, discounts allowed are $1,000 and write-offs $2,000. What is closing receivables?
  1. $17,000
  2. $14,000
  3. $15,000
  4. $20,000
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A business has cash of $2,000, receives $26,000 and pays $31,000 next month, including an $8,000 machine. Management requires closing cash of $4,000. How much new finance is needed if it keeps the machine purchase?
  1. $7,000
  2. $3,000
  3. $5,000
  4. $8,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A store budgets sales of $125,000, cost of goods sold of $76,000, operating expenses of $29,000 and depreciation of $3,000. It also plans drawings of $6,000. What is net income?
  1. $11,000
  2. $20,000
  3. $17,000
  4. $23,000
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A wholesaler earns $22,000 profit including $3,000 depreciation, while cash falls $4,000. Receivables rise $5,000, inventory rises $7,000 and payables rise $2,000. There are no other operating adjustments. What combined net outflow from investing and financing explains the cash change?
  1. $15,000
  2. $11,000
  3. $25,000
  4. $19,000
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Flexed profit is $71,000. Revenue is $2,400 below flexed budget, materials cost $900 below it and other costs $1,300 above it. What is actual profit?
  1. $68,200
  2. $66,400
  3. $70,000
  4. $73,800
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Factory rent is negotiated entirely by head office. A production manager controls material usage but has no role in the rent decision. How should rent be treated when evaluating that manager?
  1. Reduce it in proportion to actual production.
  2. Assign it to the manager as a controllable cost.
  3. Show it separately as an uncontrollable item.
  4. Remove it from the organization’s cost budget.
Show answerHide answer

Save this lesson to see this answer.

Set 5: Integrate budgets and challenge the conclusions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A factory can make 7,000 units in normal hours. Sales of 7,500, closing inventory of 500 and opening inventory of 600 are planned. Overtime adds up to 600 units of capacity. What minimum overtime output makes the plan feasible?
  1. 500 units
  2. 600 units
  3. 400 units
  4. 100 units
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A retailer budgets $208,000 sales at a 35% gross margin. Opening and closing inventory are $31,000 and $39,000. Suppliers allow one month’s credit and the opening payable is $24,000, all due this month. All budgeted purchases occur this month. What are purchases and this month’s supplier payment?
  1. $135,200 purchases; $24,000 payment
  2. $143,200 purchases; $24,000 payment
  3. $143,200 purchases; $143,200 payment
  4. $162,074 purchases; $24,000 payment
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A factory budgets 2,400 units at 0.6 labor hours per unit. At $22 per hour, with no idle time or overtime, what is budgeted direct labor cost?
  1. $52,800
  2. $19,008
  3. $33,000
  4. $31,680
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A business has opening receivables of $9,000, all collected in June. June sales are $70,000, with 20% cash and 80% credit. Half of June credit sales is collected in June with a 2% discount; the rest next month. What are June customer receipts and closing receivables?
  1. $50,440 receipts; $28,000 receivables
  2. $51,000 receipts; $28,000 receivables
  3. $50,440 receipts; $28,560 receivables
  4. $41,440 receipts; $28,000 receivables
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Credit purchases are $36,000 in May and $42,000 in June, paid one month later. June also pays $9,600 wages, $12,000 annual insurance and $4,000 loan principal. June depreciation is $1,500. What are total June payments and June closing payables?
  1. $67,600 payments; $42,000 payables
  2. $63,100 payments; $42,000 payables
  3. $61,600 payments; $36,000 payables
  4. $61,600 payments; $42,000 payables
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Opening capital is $80,000; contributions are $6,000, profit $18,000 and drawings $10,000. Closing assets are cash $14,000, receivables $29,000, inventory $37,000 and equipment $58,000. Closing payables are $20,000. What closing loan balance makes the budgeted position consistent?
  1. $30,000
  2. $34,000
  3. $24,000
  4. $18,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A business receives $16,000 from a new bank loan. Under the operating, investing and financing classification, what type of cash inflow is it?
  1. Operating inflow
  2. Financing inflow
  3. Investing inflow
  4. Sales revenue inflow
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

At output of 4,000 units, power costs are $17,000; at 6,000 they are $21,000. Each supervisor costs $4,500 and handles up to 2,500 units. Using high-low for power, what combined power and supervision allowance applies at 5,200 units?
  1. $32,900
  2. $28,400
  3. $31,200
  4. $30,560
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Fixed budget profit is $96,000 for 8,000 units. Budgeted contribution is $18 per unit and actual volume is 7,500. Fixed costs stay unchanged. Actual profit is $82,000. What total flexible budget variance remains after allowing for volume?
  1. $14,000 unfavorable
  2. $5,000 unfavorable
  3. $9,000 unfavorable
  4. $5,000 favorable
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A manager spends $5,000 on unused supplies in December solely because unspent funds reduce next year’s allocation. What change most directly removes that incentive?
  1. Base next year’s funds only on this year’s spending.
  2. Require the full remaining balance to be spent sooner.
  3. Increase the bonus for exhausting the annual budget.
  4. Review future needs and reward justified savings.
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

70 Key Terms, each with its definition

A

Absorption costing
Absorption costing values manufactured inventory with variable production costs and an allocated share of fixed production overhead per unit.
Lamps in closing inventory with a $20 variable production cost carry a higher unit value under absorption costing.
Accounts payable
Accounts payable are amounts owed to suppliers from credit purchases, increased by new credit purchases and reduced by settlements and discounts.
A retailer that buys $94,000 on credit and pays $92,000 increases the amount owed by $2,000.
Accounts receivable
Accounts receivable are amounts customers still owe from credit sales, reduced by collections, settlement discounts and debts written off.
A retailer's uncollected sales leave $22,000 receivables at quarter-end in its budgeted balance sheet.
Accrual basis
The accrual basis records revenue when earned and expenses when incurred, so reported profit need not follow the timing of cash collections and payments.
A retailer records $150,000 sales for a quarter even though its customer receipts for that quarter are only $146,000.

B

Bad debt
A bad debt is a customer amount that will not be collected, removed from receivables without creating either a cash receipt or a cash payment.
The uncollectible 5% of $50,000 credit sales contributes no cash to the collections schedule.
Budget
A budget is an agreed plan for a future period, expressed in money and often quantities, that guides decisions and authorizes resources.
A lamp maker's budget links a lamp sales target with the factory resources and cash needed to deliver it.
Budget committee
A budget committee is a group of senior managers that coordinates departmental budget proposals before the complete plan is approved.
The committee asks sales and production managers to resolve a gap between demand and factory capacity.
Budget manual
A budget manual is the written set of procedures, deadlines, formats and responsibilities used to prepare and coordinate an organization's budgets.
The manual tells the purchasing manager when the materials proposal must reach the budget officer.
Budget period
A budget period is the future time interval covered by a plan, commonly a year divided into shorter periods for preparation and control.
Monthly cash columns reveal a May shortage that disappears within the quarter's combined cash total.
Budget variance
A budget variance is the difference between an actual amount and its budget, with the meaning depending on whether the budget is fixed or flexed.
Materials costing $56,700 are $3,300 below a vase maker's fixed budget but $2,700 above its flexed allowance.
Budgetary control
Budgetary control is the process of setting budgets, comparing them with actual results, investigating differences and taking action.
A manager investigates rising fuel use after the delivery report shows repeated spending above allowance.
Budgetary slack
Budgetary slack is deliberate overstatement of expected costs or understatement of expected revenues to create targets that are easier to achieve.
A manager expecting $50,000 of costs submits $56,000, building $6,000 of padding into the request.
Budgeted balance sheet
A budgeted balance sheet projects the assets, liabilities and owner's equity at the end of a future period using the opening position and linked plans.
A retailer's March 31 budgeted assets and its liabilities plus equity both total $125,000.
Budgeted income statement
A budgeted income statement projects revenues, cost of goods sold, other expenses and net income for the future budget period on the accrual basis.
A retailer's budgeted income statement for a quarter shows $27,000 net income after operating expenses and depreciation.

C

Capital expenditure budget
A capital expenditure budget plans purchases and sales of long-lived assets, supplying amounts and dates for linked cash and asset budgets.
A planned $40,000 machine purchase in May enters May's cash budget and the equipment projection.
Carrying amount
A carrying amount is the value at which an asset is reported after depreciation and other relevant reductions, distinct from cash sale proceeds.
Equipment with $7,000 carrying amount sold for $5,000 cash creates a $2,000 loss on disposal.
Cash budget
A cash budget is a forward plan of receipts, payments and resulting balances by period, used to identify financing needs and available surpluses.
A lamp maker's monthly cash budget shows that buying a machine creates a shortage at the end of May.
Cash payments schedule
A cash payments schedule places expected outflows in the periods when suppliers, employees and other parties are actually due to receive money.
A lamp maker pays for aluminum bought in April in May because its supplier allows one month's credit.
Cash receipts schedule
A cash receipts schedule places expected cash inflows into the periods when customers and other sources are expected to provide the money.
A lamp maker's April receipts combine April cash sales with collections from the credit sales made in March.
Closing cash balance
A closing cash balance is the opening balance plus the period's net cash flow, carried forward as the next period's starting cash position.
May begins with $19,280 and loses $22,940, so its closing balance is a $3,660 shortage.
Controllable cost
A controllable cost is a cost a particular manager can influence within that manager's authority and the time period being evaluated.
A production manager can influence materials usage but cannot change rent negotiated entirely by head office.
Coordination
Coordination aligns the plans of different departments so that their quantities, timing and resources support one workable organizational plan.
Sales shares its expected orders with production, allowing purchasing to arrange the necessary materials.
Cost of goods sold
Cost of goods sold is the cost assigned to goods sold during the period, found for a retailer by adjusting purchases for opening and closing inventory.
A retailer deducts $24,000 of closing goods from $114,000 of goods available to obtain $90,000 cost of goods sold.

D

Direct labor budget
A direct labor budget calculates the hours and wages needed for planned production using time requirements, wage rates and working arrangements.
A lamp maker whose May production requires 1,180 hours at $24 budgets $28,320 in wages before any overtime change.
Dysfunctional behavior
Dysfunctional behavior helps an individual or department meet a target while harming the organization through waste, distortion or damaging decisions.
A buyer meets a price target with poor inputs that create larger labor and waste costs in production.

F

Favorable variance
A favorable variance increases profit relative to the budget, arising from revenue above its allowance or a cost below the relevant allowance.
Spending $900 less than a flexed materials allowance gives a $900 favorable cost variance.
Financing cash flow
Financing cash flow is cash from borrowing and owner funding, less principal repayments and distributions such as drawings and dividends.
A retailer's $5,000 principal repayment and $9,000 drawings produce a $14,000 financing outflow.
Finished goods inventory
Finished goods inventory consists of completed products held for sale, linking what a manufacturer produces with what it sells across periods.
When a lamp maker holds 480 lamps at the end of April, they become the opening finished goods balance for May's production plan.
Fixed budget
A fixed budget is prepared for one planned activity level and remains at those amounts when actual output or sales volume differs from the plan.
A vase maker's original materials budget stays at $60,000 even when it makes only 9,000 vases.
Flexible budget
A flexible budget applies budgeted prices and cost behavior to actual activity or several possible levels, providing allowances for meaningful comparison.
At 9,000 vases, a vase maker's $6 material rate gives a $54,000 allowance against actual spending.
Forecast
A forecast is an estimate of what is likely to happen, used to inform planning without itself being an approved management commitment.
A demand forecast suggests likely orders before managers decide the sales target and spending plan.
Functional budget
A functional budget is a plan for one operating area, such as sales, production, materials, labor or selling and administrative expenses.
A lamp maker's labor budget turns planned lamp production into the hours and wages the factory needs.

G

Goal congruence
Goal congruence exists when pursuing individual or departmental targets also advances the organization's goals, aligning local decisions with overall success.
A purchasing target considers rework and quality so that a lower invoice price also benefits the whole business.
Gross margin
Gross margin is gross profit expressed as a percentage of sales revenue, showing the share of sales remaining after the cost of goods sold.
A retailer's $60,000 gross profit on $150,000 sales gives a 40% gross margin in its quarter plan.

I

Idle time
Idle time is paid working time during which no production occurs, such as time spent waiting for materials or for a broken machine to restart.
With 5% of paid hours idle, 1,140 productive hours require wages for 1,200 hours in a what-if plan for June.
Imposed budgeting
Imposed budgeting is a top-down approach in which senior management sets targets and passes them to the managers responsible for delivering them.
Head office sets a branch's sales figure without first asking its manager about changes in local demand.
Investing cash flow
Investing cash flow is cash received or paid for noncurrent assets, including the proceeds of asset sales and payments for equipment purchases.
A retailer's $10,000 equipment purchase appears as an investing outflow in its classified cash plan.

L

Loan principal
Loan principal is the borrowed amount still owed, separate from interest, with repayments reducing both cash and the outstanding loan balance.
A $5,000 principal payment lowers a retailer's loan from $25,000 to $20,000 without reducing net income.

M

Management by exception
Management by exception concentrates investigation on significant differences, judged by size, recurrence or the operational importance of the item.
A repeated materials overspend may receive attention before a larger one-time difference with a known cause.
Markup
Markup is gross profit expressed as a percentage of cost, so a selling price with a 40% markup equals 140% of the underlying cost.
A retailer using 40% markup finds cost by dividing sales by 1.40, instead of taking 60% of sales.
Master budget
A master budget is the complete coordinated set of plans, summarized in budgeted profit, cash flows and the closing financial position.
Managers review the combined budgets to check that planned sales can be produced and financed.
Material loss
Material loss is the share of input that does not remain in usable finished output, increasing the quantity of input needed for production.
A 4% input loss means 4,800 usable kilograms require 5,000 kilograms to enter the process.
Materials purchases budget
A materials purchases budget plans the quantity and cost to buy after adjusting usage for desired closing and available opening raw materials.
A lamp maker buys 4,300 kg in April because its materials inventory must rise as well as cover production use.
Materials usage budget
A materials usage budget calculates the quantity of raw materials production will consume by applying the input requirement to planned output.
Making 2,080 lamps at 2 kg each requires 4,160 kg of aluminum, including inputs for lamps kept in inventory.
Mixed cost
A mixed cost has a fixed component and a component that changes with activity, which must be treated separately when preparing or flexing a budget.
Maintenance of $5,000 plus $0.50 per vase becomes $9,500 at output of 9,000 vases.

N

Net cash flow
Net cash flow is the difference between receipts and payments during a period, measuring cash movement before adding the opening balance.
A lamp maker with April receipts of $74,000 and payments of $62,720 has a net inflow of $11,280.
Net profit margin
Net profit margin expresses net income as a percentage of sales revenue, showing the share left after the period's expenses have been deducted.
A retailer's $27,000 net income divided by $150,000 sales gives an 18% budgeted net profit margin.
Non-cash expense
A non-cash expense reduces accounting profit without a cash payment for that charge, so it is excluded from a cash payments schedule.
When a lamp maker's fixed overhead includes $3,000 depreciation, that amount is removed when finding overhead cash paid.

O

Operating cash flow
Operating cash flow is the net cash from customer, supplier, employee and other operating transactions, distinct from asset and financing flows.
A retailer generates $24,000 operating cash despite earning $27,000 profit on the accrual basis.
Overtime premium
An overtime premium is the extra pay above the normal hourly rate for overtime hours, added when normal-rate pay for those hours is already counted.
At $24 normal pay and $36 overtime pay, the overtime premium is $12 for each overtime hour.
Owner's capital
Owner's capital is the owner's equity claim, increased by capital contributed and net income and reduced by drawings in a sole-proprietor business.
A retailer's $70,000 opening capital rises with $27,000 profit and falls with $9,000 drawings to $88,000.

P

Participative budgeting
Participative budgeting involves responsible managers in proposing the plans for their areas, bringing operating knowledge into target setting.
A lamp maker's sales manager includes a known new customer's 400 monthly lamps in the proposed sales budget.
Performance evaluation
Performance evaluation judges results against appropriate targets, considering activity, responsibility and relevant non-financial outcomes.
A factory manager's review considers waste and product quality alongside the cost of making the output.
Principal budget factor
The principal budget factor is the constraint that limits organizational activity in the budget period and determines where preparation starts.
Machine hours limit production to 10,000 units even though customers would buy 12,000 units.
Production budget
A production budget states the units to make after adjusting planned sales for desired closing finished goods and available opening finished goods.
A lamp maker building inventory in April produces 2,080 lamps even though its April sales plan is 2,000 lamps.
Production capacity
Production capacity is the maximum output available from resources such as labor and machines over a stated time period under the planned conditions.
A factory limited to 2,300 lamps in normal hours must adjust a May plan that requires 2,360 lamps.
Production overhead
Production overhead comprises indirect manufacturing costs, such as factory support and depreciation, budgeted according to their cost behavior.
A lamp maker allows variable overhead per lamp and a separate fixed factory overhead total each month.
Profit reconciliation
A profit reconciliation explains how the budgeted profit becomes the actual profit by accounting for the activity effect and remaining variances.
A vase maker's $155,000 fixed budget profit falls by $20,000 for volume and $16,100 for flexible budget variances.

R

Results manipulation
Results manipulation distorts recorded or timed performance to meet a target, undermining the reliability of the budget comparison and later decisions.
Delaying the recording of a cost makes the reported period look better without improving the operation.
Retained earnings
Retained earnings are accumulated corporate profits kept in the business, increased by net income and reduced by dividends declared to shareholders.
A corporation carries current profit into retained earnings before accounting for declared dividends.

S

Sales budget
A sales budget sets out planned units sold and selling prices for each period, giving the revenue that supports the rest of the operating plan.
A lamp maker planning to sell 2,000 lamps at $40 in April has budgeted sales revenue of $80,000 before considering collection dates.
Selling and administrative expenses
Selling and administrative expenses are operating costs outside production, such as advertising, sales salaries and office rent, budgeted by their drivers.
A sales commission varies with revenue, while a fixed office rent stays at its monthly budgeted total.
Settlement discount
A settlement discount is a reduction in the amount a customer must pay for meeting specified early-payment terms, lowering the cash collected.
A 2% discount on $20,000 settled clears the debt with $19,600 cash and a $400 reduction.
Short-termism
Short-termism sacrifices future performance to improve the current budget result, such as by cutting necessary maintenance, training or research.
Postponing an essential repair helps this year's cost figure but increases the risk of a later breakdown.
Spend it or lose it
Spend-it-or-lose-it behavior occurs when managers use unnecessary remaining funds to protect future budgets that would otherwise be reduced.
A department buys unneeded equipment in December solely to avoid losing next year's spending allowance.
Statement of cash flows
A statement of cash flows reports actual receipts and payments for a past period in operating, investing and financing activity categories.
Managers compare actual classified flows with their cash plan to investigate changed collections or spending.
Stepped fixed cost
A stepped fixed cost stays constant within an activity band and then changes by a whole amount when another block of capacity becomes necessary.
Supervisors covering up to 4,000 vases each require three whole salaries at output of 9,000 vases.
Stretch target
A stretch target is an ambitious aspiration used to encourage effort, distinct from the realistic expectation needed to plan resources and cash.
The sales team aims beyond expected demand, while the cash budget retains a realistic collections estimate.

U

Unfavorable variance
An unfavorable variance reduces profit relative to the budget, arising from revenue below its allowance or a cost above the relevant allowance.
A vase maker's $351,000 revenue is $9,000 below its $360,000 flexed revenue allowance, so it is unfavorable.

W

What-if analysis
What-if analysis changes an input to a budget model and traces its effect through the linked schedules, results and later period balances.
Moving a planned May machine payment to July raises both May and June closing cash before the payment falls due.

About this lesson

By StudeliReport a mistake

Make your own Study Materials

Turn your notes, slides and documents into Study Guides, Practice Questions, Flashcards and 6 more tools.

Get Started