Standard Costing and Variance Analysis
BeginnerLesson 9 of 11 in Introduction to Management Accounting Course
What you will learn
- Explain what standard costing is and why businesses use it, set realistic standards for materials, labor and overheads, build a standard cost card, and find what the output actually produced should have cost.
- Explain what standard costing is and what it is used forDefine a standard cost, standard costing and a variance, tell a standard apart from a budget, and describe how businesses use standards to plan, control costs and value inventory.
- Choose the type of standard and set quantities and pricesCompare ideal, attainable, current and basic standards, identify who supplies the information for each standard, and build normal waste and unproductive time into standard quantities.
- Build a standard cost cardCalculate standard overhead absorption rates and set out the standard cost, standard profit and standard contribution per unit under absorption and marginal costing.
- Find the standard cost of actual output and read a varianceWork out what the output actually produced should have cost, split a total cost variance into a price part and a quantity part, and label each variance favorable or unfavorable.
- Explain what standard costing is and what it is used for
- Split the total variances for direct material and direct labor into price and quantity parts, handle material bought for inventory and paid hours lost to idle time, and explain what each variance says about the business.
- Calculate material price and usage variancesCalculate the material price, usage and total variances, decide whether the price variance is measured on material bought or used, and explain what each variance means.
- Calculate labor rate, efficiency and idle time variancesCalculate the labor rate, efficiency, idle time and total variances, keep hours paid apart from hours worked, and explain what each labor variance means.
- Calculate material price and usage variances
- Calculate variable and fixed overhead variances, connect the fixed overhead variances with under- and over-absorbed overhead, and split the fixed overhead volume variance into capacity and efficiency parts.
- Calculate variable overhead expenditure and efficiency variancesCalculate the variable overhead expenditure, efficiency and total variances from the hours worked and the standard absorption rate, and explain what they show.
- Calculate fixed overhead expenditure and volume variancesCalculate the fixed overhead expenditure, volume and total variances under absorption costing, relate the total to under- or over-absorbed overhead, and explain how marginal costing treats fixed overhead.
- Split the fixed overhead volume variance into capacity and efficiency variancesExplain the two reasons why output differs from budget, calculate the fixed overhead capacity and efficiency variances, and check that they add up to the volume variance.
- Calculate variable overhead expenditure and efficiency variances
- Calculate sales price and volume variances, prepare an operating statement that reconciles budgeted with actual profit under absorption and marginal costing, and work back from given variances to missing figures.
- Calculate sales price and sales volume variancesCalculate the sales price variance and the sales volume variance on a profit, contribution or revenue basis, and explain what the sales variances show.
- Prepare an operating statement under standard absorption costingReconcile budgeted profit with actual profit in an operating statement that lists every sales and cost variance, and check the result against the actual profit.
- Prepare an operating statement under standard marginal costingReconcile budgeted with actual profit using contribution, explain why the marginal statement has no fixed overhead volume variance, and compare its result with the absorption statement.
- Work back from variances to find missing figuresRearrange the variance formulas to find actual quantities, prices, hours, output and budgeted figures when some variances are given.
- Calculate sales price and sales volume variances
- Explain the likely causes of variances and how they affect each other, decide which variances deserve investigation and what action to take, and judge the strengths and limits of standard costing.
- Explain the causes of variances and how they are linkedConnect each variance with its likely causes and responsible manager, explain how one decision can create several related variances, and tell controllable from uncontrollable causes.
- Decide which variances to investigate and what action to takeApply size, trend, controllability and cost-benefit tests to choose which variances to investigate, and match each kind of finding with a suitable action.
- Evaluate standard costing as a management toolWeigh the advantages and limitations of standard costing, including its behavioral effects and its fit with modern business, and use variance data and non-financial factors to reach a judgment.
- Explain the causes of variances and how they are linked
Variance Analysis study guide
1Set a fair cost target
A business needs a useful target before it can judge its costs. Standard costing starts with the inputs one unit should need and what each input should cost. You will connect those unit figures to a budget, choose realistic allowances, and build a cost card. Then you will compare actual costs with the allowance for the output achieved, so a change in production volume does not get mistaken for a change in performance.
1.1 How standard costs support decisions
A standard cost is the planned cost of one unit of a product or service under expected operating conditions. A standard costing system sets these costs before work begins, compares them with actual results, and investigates the differences. It gives a manager a starting point for asking where performance changed.
Start with one unit
Kestrel Company makes garden benches. Its material standard is 8 kg of wood at $5 per kg, giving $40 of wood per bench. The standard includes both a physical amount and a price. A total of $40 alone would hide whether the plan assumed expensive wood used sparingly or cheaper wood used in larger amounts.
A standard and a budget serve different jobs. The standard labor cost is $54 per bench. A budget for 2,000 benches allows 2,000 × $54 = $108,000 of labor in total. Changing the planned number of benches changes that budget total without changing the unit standard.
Read a variance
A variance is the difference between an actual result and the standard or budget figure used for comparison. A favorable variance, labeled F, increases profit compared with the relevant standard. An unfavorable variance, labeled U, reduces it. The word adverse, often abbreviated A, means the same as unfavorable.
For a cost, spending less than the allowance is favorable. For sales price, receiving more than the standard price is favorable. Always identify what the comparison measures before assigning the label.
Put standards to work
Standards support several everyday decisions:
- Planning: use the unit cost to build budgets or prepare price quotations.
- Control: compare results with the allowance to locate cost differences.
- Inventory valuation: record work in progress and finished goods at standard cost within the system.
- Performance evaluation: discuss results with managers who can influence them.
- Motivation: give employees clear targets for efficient work.
Standard costing works best for repeated operations with measurable inputs, such as food processing or making the same furniture design. A repeated service, such as preparing a standard meal, can also have a useful unit standard. A unique construction project is harder to standardize because its inputs and conditions change from job to job.
Decide where to look
Management by exception directs attention to significant differences. A report might contain twenty small variances and two large ones. Managers can begin with the two large items, then consider trends and links that make smaller items worth investigating.
Variance analysis goes beyond calculating the difference. It separates effects, finds causes, and leads to action. A favorable material price variance may come from a discount or from buying lower-grade wood. If that wood creates enough extra waste, the price saving can leave total cost higher. Purchase records and waste reports help distinguish those explanations before a manager receives credit or blame.
Key Takeaways
- A standard gives a planned cost per unit; a budget gives a total for a level of activity.
- Favorable and unfavorable describe the direction of the profit effect against the relevant standard.
- Standard costing supports planning, control, inventory valuation, performance evaluation, and motivation.
- Variance analysis connects calculations with causes and action.
1.2 Realistic standards and normal allowances
The same actual result can look very different against a tight target and an easy one. Choosing the type of standard determines what performance the business is asking people to achieve.
Choose the target
An ideal standard assumes perfect conditions: no waste, breakdowns, or idle time, with workers at maximum efficiency. Frequent unfavorable variances are likely because ordinary operating problems have no allowance. An ideal target can discourage staff who see no realistic way to meet it.
An attainable standard assumes efficient but realistic work. It allows normal waste, normal downtime, and rest breaks. It remains demanding while giving employees a reachable target.
A current standard reflects present conditions, including existing inefficiencies. It can help during a short unstable period, but offers little pressure to improve. A basic standard stays unchanged for years to reveal long-term trends. As prices and methods change, it becomes less useful for judging current performance.
Standards that are too loose can hide avoidable costs. Standards that are too tight can cause people to give up. Involving workers and responsible managers helps the business set targets they understand and accept.
Gather the information
Different departments supply different parts of the standard:
| Part of standard | Useful information |
|---|---|
| Material quantity | Product specifications, engineering studies, past usage |
| Material price | Supplier quotations, contracts, discounts, expected price changes |
| Labor hours | Work study, time-and-motion studies, past records |
| Labor rate | Pay agreements and human resources records |
| Overhead rate | Overhead budget and budgeted activity |
Past records help, but a record of inefficient work should not become an attainable target without review. Engineering and work studies help establish what efficient operations should need.
Work backward through normal loss
A bench contains 7.6 kg of finished wood. Normal offcuts are 5% of the wood put in, so 95% of input remains in the bench.
Standard input = 7.6 ÷ 0.95 = 8 kg.
The 8 kg includes 0.4 kg lost: 5% × 8 = 0.4. Adding 5% to the finished quantity gives 7.98 kg, which uses the wrong base. The loss is measured against input, not finished wood.
Paid-time allowances work in the same way. A repair job needs 2.7 productive hours. If 10% of paid time is normally unproductive, productive time is 90% of paid time.
Standard paid time = 2.7 ÷ 0.90 = 3 hours.
The job allows 0.3 unproductive hour. Keep this distinction available when analyzing labor: standard paid hours and standard productive hours measure different things.
Keep the standard useful
Review standards during the budget cycle, usually each year, and sooner after major price or process changes. A machine upgrade can reduce the time a job should take. Leaving the old time standard unchanged could produce favorable variances even when the new machine is being used poorly.
Key Takeaways
- Ideal standards assume perfect conditions; attainable standards include normal operating allowances.
- Current standards reflect present conditions; basic standards preserve a long-term comparison.
- When loss is a percentage of input, divide required output by the proportion that remains.
- Keep productive hours separate from paid hours when the standard includes unproductive time.
- Use department evidence and employee input to set standards, then review them as conditions change.
1.3 The standard cost card
A standard cost card brings the quantity and price standards together for one unit. It makes the cost of materials, labor, and overhead visible before the product is made. The card also supplies the margins used later to explain sales-volume changes.
Calculate the overhead rates first
Kestrel budgets 2,000 benches at 3 direct labor hours each. Budgeted activity is therefore 6,000 labor hours. Its overhead budgets are $24,000 variable and $60,000 fixed.
Variable overhead rate = $24,000 ÷ 6,000 = $4 per labor hour.
Fixed overhead absorption rate = $60,000 ÷ 6,000 = $10 per labor hour.
These are standard rates, set from budget figures. Dividing actual overhead by actual hours would find an actual rate, which answers a different question.
Choose an absorption basis that explains the activity generating overhead. Labor hours can suit labor-intensive work; machine hours can suit machine-intensive work. A single-product business can also use a rate per unit. Keep the same basis when setting the rate and calculating the variances: a rate per machine hour must be multiplied by machine hours.
Build the card for one bench
| Input | Standard quantity × rate | Standard cost |
|---|---|---|
| Direct material | 8 kg × $5 | $40 |
| Direct labor | 3 hours × $18 | $54 |
| Variable overhead | 3 hours × $4 | $12 |
| Fixed overhead | 3 hours × $10 | $30 |
| Full production cost | $136 |
Each row shows the physical input as well as the money amount. The fixed overhead charge is $30 per bench because each bench absorbs three hours at $10 per hour. This is an allocation of the period's fixed overhead to units.
Find profit and contribution
Under absorption costing, the full standard unit cost includes fixed overhead: $136. At a standard selling price of $180, standard profit per bench is $180 − $136 = $44.
Under marginal costing, the unit cost includes variable costs only: $40 + $54 + $12 = $106. Standard contribution is selling price less variable cost: $180 − $106 = $74. Contribution helps cover fixed overhead, then profit.
The budget reaches the same $88,000 profit by either route:
- Absorption: 2,000 × $44 = $88,000.
- Marginal: 2,000 × $74 − $60,000 = $88,000.
The $30 gap between contribution and standard profit is the fixed overhead included in one bench's full cost.
Express output in standard hours
A standard hour measures work at standard efficiency. Actual output of 2,100 benches represents 2,100 × 3 = 6,300 standard hours, even if the factory actually works 6,500 hours. The 6,300 hours describe how much work the output should have required; the 6,500 hours describe time actually spent. Their difference will be used to measure efficiency.
Key Takeaways
- Set standard overhead rates from budgeted overhead and budgeted activity.
- Full cost includes fixed overhead; variable cost excludes it.
- Standard profit equals selling price less full cost; contribution equals selling price less variable cost.
- Standard hours for actual output equal actual units produced times standard hours per unit.
1.4 Compare costs on the same output basis
A factory that makes more units usually needs more materials and labor. Comparing its actual direct cost with the original budget mixes the cost of extra production with the effect of price or efficiency. First find the standard cost of actual output: what the units actually made should have cost.
Allow for the output achieved
A bakery allows 0.5 kg of flour at $1.20 per kg for each loaf. It planned 900 loaves but made 1,000. The allowance for actual output is:
- Standard quantity: 1,000 × 0.5 = 500 kg.
- Standard cost: 500 × $1.20 = $600.
The bakery actually used 520 kg costing $598. Its total material cost variance is standard cost of actual output minus actual cost:
$600 − $598 = $2 F.
The original budget allowed only 900 × 0.5 × $1.20 = $540. Comparing $598 with $540 would show $58 of extra spending, but that includes the cost of producing another 100 loaves. It cannot isolate performance on the 1,000 loaves made.
Separate price from quantity
Build a three-figure comparison:
| Figure | Calculation | Amount |
|---|---|---|
| Actual quantity at actual price | Actual flour cost | $598 |
| Actual quantity at standard price | 520 × $1.20 | $624 |
| Standard quantity at standard price | 500 × $1.20 | $600 |
The difference between $624 and $598 is $26 F on price. The bakery paid less for the flour it actually used. The difference between $600 and $624 is $24 U on quantity. It used 20 kg more than the output allowance, valued at $1.20 each.
The two parts reconcile: $26 F less $24 U = $2 F. The small total hides two larger effects, so a manager should not stop at the net figure.
Keep each effect separate
A price variance uses the actual quantity because the different price was paid on that quantity. A quantity variance uses the standard price because it measures only the money effect of using more or less input. Valuing the extra 20 kg at the actual $1.15 price would mix some of the price saving into the usage calculation.
Here, cost formulas use standard minus actual. A positive result is favorable; a negative result is unfavorable. Many US textbooks reverse the subtraction. Report a positive amount with F or U and check the direction against the underlying event: extra input usage is unfavorable; paying less per input is favorable.
Use the right overhead allowance
The actual-output allowance applies to total direct material and labor variances. Overhead expenditure has a different comparison. Variable overhead expenditure uses the allowance for hours actually worked. Fixed overhead expenditure uses the original fixed overhead budget, because fixed costs are not expected to change with output. Choosing the comparison comes before doing the subtraction.
Key Takeaways
- Calculate standard quantities and hours for actual production before measuring direct-cost performance.
- Use actual quantities for price effects and standard prices for quantity effects.
- Price and quantity parts reconcile to the total when measured on the same input usage.
- A small net variance can hide large offsetting differences.
- Variable overhead expenditure uses actual hours worked; fixed overhead expenditure uses the original budget.
2Explain material and labor cost differences
A total direct-cost variance tells you whether an input cost more or less than its allowance. Splitting it shows whether the difference came from the price paid or the amount used. You will calculate material and labor variances, handle purchases held in inventory, and separate paid idle time from productive work. These distinctions help you direct questions to the right manager and avoid counting the same time loss twice.
2.1 Material prices, usage, and inventory
Material cost can change because the business pays a different price per kilogram or uses a different number of kilograms. The price variance isolates the first effect; the usage variance, also called the quantity variance, isolates the second.
Calculate the price effect
Kestrel's bench standard is 8 kg of wood at $5 per kg. It makes 2,100 benches and uses 17,500 kg costing $85,750. All this wood was bought and used in the period.
Actual price = $85,750 ÷ 17,500 = $4.90 per kg.
Material price variance = (standard price − actual price) × actual quantity.
($5 − $4.90) × 17,500 = $1,750 F.
If the actual price has many decimal places, avoid rounding it. Calculate actual quantity at standard price less actual cost: 17,500 × $5 − $85,750 gives the same $1,750 F directly.
Calculate the usage effect
Standard quantity for actual output = 2,100 × 8 = 16,800 kg.
Material usage variance = (standard quantity for actual output − actual quantity used) × standard price.
(16,800 − 17,500) × $5 = $3,500 U.
The factory used 700 extra kilograms. Value them at the standard $5, so the usage result measures quantity alone. Using the actual $4.90 would give $3,430 and mix the price effect into usage.
Total material cost variance = $84,000 − $85,750 = $1,750 U. This agrees with $1,750 F on price less $3,500 U on usage. The $84,000 allowance comes from actual production, not the original plan for 2,000 benches.
Distinguish purchases from usage
When material bought exceeds material used, a price variance can be recognized at purchase or at usage. Suppose a business buys 10,000 liters at $2.10, against a $2 standard, and uses 9,000 liters.
- On purchases: ($2 − $2.10) × 10,000 = $1,000 U.
- On usage: ($2 − $2.10) × 9,000 = $900 U now; $100 U follows when the remaining material is used.
Recognizing price differences at purchase reports them promptly to purchasing and lets the remaining 1,000 liters be held at the standard $2 each. Recognizing them at usage delays the price difference attached to unused material. The usage variance always uses material actually consumed. Unused material has not helped make this period's output.
Read the two results together
A favorable price variance can come from discounts, falling market prices, or a cheaper supplier. An unfavorable one can arise from shortages, rush purchases, or higher-grade inputs. Extra usage can reflect waste, theft, faulty machinery, poor materials, or inexperienced staff.
At Kestrel, cheaper wood could explain both the price saving and the extra waste. If purchase and waste records confirm that link, the $1,750 saving was outweighed by $3,500 of extra usage. The purchasing decision then raised material cost by $1,750 overall.
Key Takeaways
- Material price variance measures a price difference on actual purchases or usage, according to the reporting basis.
- Material usage variance values the actual-output quantity difference at standard price.
- A purchase-basis price variance reports the price effect on unused inventory immediately.
- Price and usage variances can offset each other and can share a cause.
- Avoid rounding an actual price when actual quantity at standard price less actual cost is available.
2.2 Wages, working speed, and idle time
Labor cost depends on the rate paid and the hours needed for output. When some paid hours are idle, keep hours paid and hours worked separate. The rate applies to every paid hour; efficiency measures productive work against the output allowance.
Calculate rate and efficiency
Kestrel allows 3 hours at $18 per bench. For 2,100 benches, standard hours are 6,300. Employees work and are paid for 6,500 hours costing $120,250, with no idle time.
Labor rate variance = hours paid × standard rate − actual labor cost.
6,500 × $18 − $120,250 = $3,250 U.
The actual rate is $18.50, so the extra $0.50 was paid on all 6,500 hours. The rate difference could reflect higher pay, overtime premiums, or a different skill mix.
Labor efficiency variance = (standard hours for actual output − hours worked) × standard rate.
(6,300 − 6,500) × $18 = $3,600 U.
Total labor variance = 6,300 × $18 − $120,250 = $6,850 U, matching the two parts. The extra 200 hours may reflect poor materials, slower work, inadequate training, or equipment trouble.
Separate idle hours when there is no allowance
Idle time is paid time without productive work. Suppose the standard rate is $20, with no idle allowance. Employees receive $20,500 for 1,000 paid hours; 50 hours are idle, leaving 950 worked. Output represents 900 standard hours.
- Rate: 1,000 × $20 − $20,500 = $500 U.
- Idle time: 50 × $20 = $1,000 U.
- Efficiency: (900 − 950) × $20 = $1,000 U.
Together these give $2,500 U, equal to 900 × $20 − $20,500. Using all 1,000 paid hours for efficiency and then adding idle time again would count the idle loss twice.
Handle a normal idle allowance consistently
A repair standard allows 2.7 productive hours and 10% idle time: 3 paid hours at $18, or $54 per job. The same cost per productive hour is $54 ÷ 2.7 = $20.
For 100 jobs completed exactly to standard, 300 hours are paid, 30 idle, and 270 worked. Comparing 300 paid standard hours with 270 worked hours at $18 would create a false $540 F efficiency variance.
Two consistent approaches are available. Measure one combined time variance using paid hours at $18, or split productive efficiency and excess idle time using $20 per productive hour. With 320 hours paid, 40 idle, and 280 worked, the expected idle allowance is 10% × 320 = 32 hours:
- Excess idle: (32 − 40) × $20 = $160 U.
- Productive efficiency: (270 − 280) × $20 = $200 U.
Their $360 U total equals (300 − 320) × $18. A separate rate variance still uses actual paid hours at the standard paid-hour rate.
Match responsibility to the cause
Human resources may explain a pay-rate change, but production scheduling may explain overtime premiums. A skilled workforce can cost more per hour yet save enough hours to lower total cost. Use pay records, downtime logs, training records, and material-quality evidence to explain the pattern.
Key Takeaways
- Labor rate variance uses hours paid; a separate productive efficiency variance uses hours worked.
- With no idle allowance, paid idle hours create an unfavorable idle time variance.
- Use one combined paid-time variance or a consistent split when the standard includes idle time.
- With an idle allowance, productive efficiency and excess idle time use the effective productive-hour rate.
- Rate, efficiency, and idle parts must reconcile to total labor cost variance.
- An unfavorable rate variance can accompany better efficiency when higher-paid skilled workers save time.
3Separate overhead spending from activity
Overhead variances explain indirect production costs. Variable overhead follows hours of activity; fixed overhead starts with a period budget and is absorbed into units under absorption costing. You will use these different comparisons to calculate spending, efficiency, and volume effects. You will then split the fixed overhead volume effect into hours available and work achieved, while keeping accounting absorption separate from cash spending.
3.1 Variable overhead spending and efficiency
Variable overhead is an indirect cost that changes with activity, such as machine power or consumable supplies. A standard rate per labor hour or machine hour connects that cost to production. Both absorption and marginal costing include variable overhead in unit cost, so they use the same variable overhead variances.
Use three cost levels
Kestrel's standard variable overhead rate is $4 per labor hour. Actual production of 2,100 benches represents 6,300 standard hours. The factory actually works 6,500 hours and spends $25,350 on variable overhead.
There are three relevant amounts:
- Actual spending: $25,350.
- Allowance for hours worked: 6,500 × $4 = $26,000.
- Allowance for actual output: 6,300 × $4 = $25,200.
Each comparison answers a different question. The middle amount separates what happened during each hour from how many hours the output required.
Calculate the expenditure variance
Variable overhead expenditure variance = actual hours worked × standard rate − actual variable overhead.
$26,000 − $25,350 = $650 F.
The spending was $650 below the allowance for the 6,500 hours actually worked. This variance is also called the spending or rate variance. It can reflect an energy-price change, different prices for supplies, or a change in supplies consumed per hour. Because overhead contains several indirect inputs, the result can mix price and usage-per-hour effects.
Comparing $25,350 directly with the original $24,000 budget would include the effect of working more hours. Comparing it with $25,200 would give the total variance, not the expenditure part.
Calculate the efficiency variance
Variable overhead efficiency variance = (standard hours for actual output − actual hours worked) × standard rate.
(6,300 − 6,500) × $4 = $800 U.
The factory used 200 more labor hours than the output should have required. At the standard variable overhead rate, those hours account for $800 of extra cost. The total variance is $25,200 − $25,350 = $150 U, which agrees with $650 F less $800 U.
Connect the result to operations
Kestrel's labor efficiency variance also uses the 200-hour difference. The same slower work is valued at $18 per hour for labor and $4 per hour for variable overhead. These are two money effects of one time problem. Investigating them as separate unrelated failures would miss that link.
If a factory absorbs variable overhead on machine hours, use standard and actual machine hours throughout. A labor-hours efficiency result cannot be multiplied by a machine-hour rate.
Variable overhead is usually treated as arising during work, with none incurred during idle time. For a period with 1,000 hours paid and 50 idle, use 950 hours worked in these calculations. A machine breakdown can still affect output and other costs, but the variable overhead allowance follows the hours on which that overhead is incurred.
Key Takeaways
- Variable overhead expenditure compares spending with the allowance for actual hours worked.
- Variable overhead efficiency values the extra or saved hours at the standard overhead rate.
- The two parts reconcile to the actual-output allowance less actual overhead.
- Use the absorption basis consistently, including the correct type of hours.
- Labor and overhead efficiency variances can measure different cost effects of the same extra hours.
3.2 Fixed overhead spending, volume, and absorption
Fixed overhead includes costs such as factory rent, supervisor salaries, insurance, and depreciation. Within the relevant short-term activity range, these costs are not expected to change with output. Under absorption costing, the business charges them to units using a standard rate.
Start with absorbed overhead
Kestrel budgets $60,000 of fixed overhead for 6,000 labor hours. The standard rate is $10 per hour, or $30 per bench. Actual output of 2,100 benches represents 6,300 standard hours, so fixed overhead absorbed is:
6,300 × $10 = $63,000.
Absorbed overhead is the amount charged to production. It is separate from the $62,000 the business actually incurs.
Compare spending with the budget
Fixed overhead expenditure variance = budgeted fixed overhead − actual fixed overhead.
$60,000 − $62,000 = $2,000 U.
This is also called the fixed overhead spending or budget variance. It keeps the original budget because fixed costs are not expected to rise simply because output rises. Flexing the budget to $63,000 would fold the production-volume effect into the spending comparison.
Higher rent, supervisor pay, unexpected repairs, or additional depreciation can create an unfavorable expenditure variance. A favorable result can reflect real savings, but it can also arise when maintenance or training is delayed.
Compare absorbed overhead with the budget
Fixed overhead volume variance = fixed overhead absorbed − budgeted fixed overhead.
$63,000 − $60,000 = $3,000 F.
The hourly form is (6,300 − 6,000) × $10. The unit form is (2,100 − 2,000) × $30. Both measure the same extra production. This is also called the production volume variance.
The favorable label means more fixed overhead was absorbed than planned. It is an allocation effect, with no cash saving in the calculation. Actual fixed spending was above budget even though the volume variance was favorable.
Reconcile the total
Total fixed overhead variance = absorbed fixed overhead − actual fixed overhead.
$63,000 − $62,000 = $1,000 F.
The parts agree: $3,000 F on volume less $2,000 U on expenditure = $1,000 F. The $1,000 is over-absorbed fixed overhead. When actual fixed overhead exceeds the absorbed amount, the total is unfavorable and overhead is under-absorbed.
A manager rewarded for favorable volume variances may increase production beyond sales. That absorbs more overhead but creates inventory, uses cash, and may increase storage needs. Output, sales, and inventory records help judge the result.
Compare marginal costing
Marginal costing treats fixed overhead as a period cost. It does not absorb fixed overhead into units, so there is no fixed overhead volume variance. The $2,000 U expenditure variance remains: the business still needs to explain why its period cost exceeded the budget.
Key Takeaways
- Fixed overhead absorbed uses standard hours for actual output, multiplied by the standard rate.
- Expenditure compares actual fixed overhead with the original budget.
- Volume compares absorbed fixed overhead with budgeted fixed overhead.
- Total fixed overhead variance equals over- or under-absorption and reconciles to expenditure plus volume.
- A favorable volume variance reflects absorption, without a cash saving.
- Marginal costing has only the fixed overhead expenditure variance.
3.3 Why fixed overhead volume changes
The fixed overhead volume variance measures output against budget in standard hours. Output can differ because the business works a different number of hours or because it produces at a different speed. Capacity and efficiency separate those two effects.
Put the hours in order
Kestrel budgets 6,000 hours, works 6,500 hours, and produces output worth 6,300 standard hours. Its fixed overhead rate is $10 per hour.
Think of a bridge from budgeted hours to output:
- Move from 6,000 budgeted hours to 6,500 actual hours worked: 500 extra hours of capacity used.
- Move from 6,500 worked hours to 6,300 standard hours of output: output fell 200 hours short of what those working hours should have achieved.
The net movement is 300 hours above budget, the same activity difference used in the volume variance.
Calculate capacity
Fixed overhead capacity variance = (actual hours worked − budgeted hours) × fixed overhead rate.
(6,500 − 6,000) × $10 = $5,000 F.
Working more hours than planned is favorable in this absorption comparison because more working time was available to absorb fixed overhead. Extra shifts or overtime can produce this result. Breakdowns, strikes, staff shortages, or low demand can leave hours worked below budget and give an unfavorable capacity variance.
Capacity uses hours actually worked. Paid idle hours do not provide productive capacity in this calculation.
Calculate efficiency
Fixed overhead efficiency variance = (standard hours for actual output − actual hours worked) × fixed overhead rate.
(6,300 − 6,500) × $10 = $2,000 U.
The factory took 200 extra hours for its output. This is the same hours difference used in labor efficiency and, on the same hours basis, variable overhead efficiency. Their rates differ because each measures a different cost attached to the time difference.
Check the bridge in money
Capacity plus efficiency equals volume:
$5,000 F less $2,000 U = $3,000 F.
A four-amount layout also works:
| Amount | Value |
|---|---|
| Actual fixed overhead | $62,000 |
| Budgeted fixed overhead | $60,000 |
| Actual hours at standard rate | $65,000 |
| Standard hours of output at standard rate | $63,000 |
Expenditure compares $60,000 with $62,000. Capacity compares $65,000 with $60,000. Efficiency compares $63,000 with $65,000. The last two comparisons explain the move from budgeted to absorbed overhead.
In an operating statement, include the $3,000 F volume variance or its $5,000 F capacity and $2,000 U efficiency parts. Including all three counts the same volume effect twice. This split needs an hours basis: a per-unit rate alone, without standard hours per unit, is enough for volume but does not provide the hours needed for capacity and efficiency.
Key Takeaways
- Capacity compares actual hours worked with budgeted hours.
- Fixed overhead efficiency compares standard output hours with actual hours worked.
- Capacity and efficiency reconcile to the volume variance.
- Include volume or its two parts in a reconciliation, avoiding double counting.
4Explain the movement from budgeted to actual profit
Sales and production variances come together in an operating statement. The statement shows how each difference moves profit away from the budget. You will choose the correct sales margin, reconcile the full set of variances under absorption and marginal costing, and check the result against actual revenue and costs. You will also work backward from a reported variance when a price, quantity, hour total, or budget figure is missing.
4.1 Sales prices and the margin on extra sales
Sales variances separate the selling-price effect from the number of units sold. Keep units sold separate from units produced: sales variances follow sales; production cost variances follow production.
Calculate the price variance
Kestrel budgets 2,000 benches at $180 each. It actually sells 2,100 benches at $175 each.
Sales price variance = (actual selling price − standard selling price) × actual units sold.
($175 − $180) × 2,100 = $10,500 U.
The $5 shortfall applies to all 2,100 sales. Using the budgeted 2,000 units would miss the lower price on 100 units. A selling price above standard is favorable because it raises revenue and profit on the actual sales.
Choose the volume margin
Sales volume variance = (actual units sold − budgeted units sold) × standard margin per unit.
The margin depends on the costing method:
| Basis | Standard margin | Kestrel's volume variance |
|---|---|---|
| Absorption costing | Profit, $44 per bench | 100 × $44 = $4,400 F |
| Marginal costing | Contribution, $74 per bench | 100 × $74 = $7,400 F |
Extra sales bring revenue and require costs. The margin measures what is left after the costs included in that basis. Multiplying by the $136 full cost would value costs, not the profit earned from the extra sales.
Distinguish revenue from profit
A revenue analysis values extra sales at the standard selling price. Kestrel's revenue-volume variance is 100 × $180 = $18,000 F. Together with the $10,500 U price variance, it explains the revenue increase of $7,500:
Actual revenue $367,500 − budgeted revenue $360,000 = $7,500 F.
The $18,000 figure cannot be used as the volume gain in a profit reconciliation. It leaves out the cost of the extra units. A reconciliation beginning with budgeted profit needs standard profit or contribution, according to the costing method.
Interpret a price cut
A lower price may encourage more sales, but sales can also change because of advertising, demand, competitors, or product quality. Sales records alone do not establish which change caused the extra units.
Kestrel's absorption sales variances net to $4,400 F less $10,500 U = $6,100 U. To evaluate the price cut itself with unchanged fixed costs, use contribution. If the cut caused all 100 extra sales, the extra contribution offsets $7,400 of the price shortfall, leaving $3,100 U.
The two results differ by $3,000, or 100 benches × $30 of fixed overhead per bench. The absorption operating statement shows that amount in the fixed overhead volume variance when the extra benches are also produced. Keep that accounting allocation separate from the contribution relevant to the pricing decision.
Key Takeaways
- Sales price variance uses the actual number of units sold.
- Value sales volume at standard profit under absorption costing or standard contribution under marginal costing.
- A revenue-volume variance explains revenue, not profit.
- Use sales and other business evidence to assess the link between a price change and volume.
- With unchanged fixed costs, contribution measures the profit benefit from extra sales.
4.2 The absorption operating statement
An operating statement explains the difference between budgeted and actual profit by listing the sales and cost variances. It is also called a standard costing profit reconciliation statement. Each favorable variance is added; each unfavorable variance is subtracted.
Start with the sales-volume change
Kestrel's budgeted profit is 2,000 benches × $44 standard profit = $88,000. Under absorption costing, the extra 100 sales are valued at the $44 standard profit.
Budgeted profit $88,000 + sales volume variance $4,400 F = $92,400 standard profit on actual sales.
Check the subtotal directly: 2,100 actual sales × $44 = $92,400. It is the profit those sales would earn if selling price and all unit costs matched the standards.
Next subtract the sales price variance of $10,500 U. The running subtotal becomes $81,900. Only the selling-price difference has been allowed for at this point; production cost differences still need to be included.
Bring in every production variance
| Cost variance | Favorable | Unfavorable |
|---|---|---|
| Material price | $1,750 | |
| Material usage | $3,500 | |
| Labor rate | $3,250 | |
| Labor efficiency | $3,600 | |
| Variable overhead expenditure | $650 | |
| Variable overhead efficiency | $800 | |
| Fixed overhead expenditure | $2,000 | |
| Fixed overhead volume | $3,000 | |
| Total | $5,400 | $13,150 |
Net production cost variances = $5,400 − $13,150 = $7,750 U.
Actual profit = $81,900 − $7,750 = $74,150.
The complete bridge is $88,000 + $4,400 − $10,500 + $5,400 − $13,150. Showing the signs or separate columns makes each effect on profit visible.
Check profit independently
Kestrel produced and sold 2,100 benches, so there is no inventory change in this example. Actual sales revenue is 2,100 × $175 = $367,500. Actual production costs are:
$85,750 materials + $120,250 labor + $25,350 variable overhead + $62,000 fixed overhead = $293,350.
Actual revenue less those costs is $367,500 − $293,350 = $74,150, confirming the statement. The overall profit shortfall is $88,000 − $74,150 = $13,850 U, which must also equal the net effect of every variance in the statement.
Avoid duplicate adjustments
Fixed overhead volume may be replaced by capacity $5,000 F and efficiency $2,000 U. Their net is still $3,000 F. Use the total or the parts, never both. The same principle applies when a report gives a total material variance and its price and usage parts.
When production and sales differ, cost variances still cover all production, and sales variances cover units sold. With inventory carried at standard cost and variances recognized for the period, inventory holds no production variances. The standard profit on actual sales remains the sales starting point.
Key Takeaways
- Absorption statements value the sales-volume change at standard profit.
- Standard profit on actual sales equals actual units sold times standard profit per unit.
- Add favorable and subtract unfavorable sales and production variances.
- Check the result against actual profit and the overall profit movement.
- Use a total variance or its parts, avoiding duplicate adjustments.
4.3 The marginal operating statement
Under marginal costing, contribution connects sales revenue with profit. Unit costs include variable costs, while all fixed overhead is charged to the period. The operating statement therefore uses standard contribution for the sales-volume effect and has no fixed overhead volume, capacity, or efficiency variance.
Start from budgeted contribution
Kestrel's standard contribution is $74 per bench. Budgeted contribution is 2,000 × $74 = $148,000.
Add the sales volume variance at contribution: 100 × $74 = $7,400 F. This gives $155,400 standard contribution on actual sales, also found as 2,100 × $74.
Subtract the $10,500 U sales price variance. The subtotal is $144,900 before variable production cost differences.
Adjust the variable costs
Include the same material, labor, and variable overhead variances used under absorption costing:
| Variable cost variance | Signed effect |
|---|---|
| Material price | +$1,750 |
| Material usage | −$3,500 |
| Labor rate | −$3,250 |
| Labor efficiency | −$3,600 |
| Variable overhead expenditure | +$650 |
| Variable overhead efficiency | −$800 |
| Net | −$8,750 |
Actual contribution = $144,900 − $8,750 = $136,150.
Now charge the fixed overhead. Subtract the $60,000 budget, then subtract the $2,000 U expenditure variance:
$136,150 − $60,000 − $2,000 = $74,150 actual profit.
Equivalently, subtract actual fixed overhead of $62,000 once. Subtracting both actual overhead and its expenditure variance would count the overspend twice.
Check the contribution directly
Actual revenue is $367,500. Actual variable costs are $85,750 + $120,250 + $25,350 = $231,350. Their difference is $136,150, the same contribution reached by the statement.
The marginal and absorption statements reach the same actual profit here because production equals sales. They display the volume effect differently. The $7,400 marginal volume variance exceeds the $4,400 absorption figure by $3,000. The absorption statement supplies that $3,000 through its favorable fixed overhead volume variance.
Explain an inventory difference
With no opening inventory, suppose Kestrel makes 2,100 benches but sells only 2,000. Closing inventory is 100 benches. Absorption costing includes $30 of fixed overhead in each unsold bench, carrying $3,000 forward. Marginal costing charges that fixed overhead to the current period. Absorption profit is therefore $3,000 higher.
When inventory falls, fixed overhead carried from earlier periods is released under absorption costing, making its profit lower than marginal profit on the same constant-rate basis. Inventory movement must be considered before expecting the two methods to report the same profit.
A marginal report makes the contribution from sales visible and avoids a favorable fixed overhead volume signal from producing unsold units. Managers can pair it with inventory and delivery measures when assessing production decisions.
Key Takeaways
- Marginal statements value the sales-volume change at standard contribution.
- Variable cost variances adjust contribution; fixed overhead is then charged to the period.
- Keep fixed overhead expenditure, but omit fixed overhead volume and its parts.
- The two methods agree on profit when inventory does not change.
- An inventory increase carries fixed overhead forward under absorption costing, raising its profit relative to marginal costing.
- Charge budgeted fixed overhead plus its variance, or actual fixed overhead once.
4.4 Find a missing figure from a variance
A variance formula can be read backward. A money difference divided by its price or rate reveals the physical difference in kilograms, hours, or units. First identify what the variance compares and what its favorable or unfavorable label means.
Recover material quantity and price
Suppose the standard quantity for actual output is 4,000 kg at $6 per kg. A material usage variance of $1,200 U means more material was used than allowed.
Extra quantity = $1,200 ÷ $6 = 200 kg.
Actual quantity = 4,000 + 200 = 4,200 kg.
Now suppose the price variance on that usage is $840 F. The price saving per kilogram is $840 ÷ 4,200 = $0.20. Actual price is $6 − $0.20 = $5.80. Actual material cost is 4,200 × $5.80 = $24,360.
Check both directions: (4,000 − 4,200) × $6 gives $1,200 U, and ($6 − $5.80) × 4,200 gives $840 F. Use standard price to recover a usage difference; actual price would mix the two effects.
Recover output from an hours difference
A product allows 2 hours per unit at $15 per hour. Employees work 2,900 hours with no idle time. The efficiency variance is $1,500 F.
Hours saved = $1,500 ÷ $15 = 100 hours.
Standard hours for the output must be greater than actual hours: 2,900 + 100 = 3,000 standard hours. Output is 3,000 ÷ 2 = 1,500 units. A favorable efficiency result means the work should have taken longer than it actually did.
Recover a fixed overhead budget
Actual fixed overhead is $50,000 and expenditure variance is $2,000 U. Spending exceeded budget, so budgeted fixed overhead is $48,000.
At $8 per hour, budgeted activity is $48,000 ÷ $8 = 6,000 hours. A $4,000 F volume variance means output exceeded budget by $4,000 ÷ $8 = 500 standard hours. Standard hours for actual output are therefore 6,500.
Do not apply the cost-spending direction to every variance. An unfavorable fixed overhead volume variance means output below budget. An unfavorable capacity variance means fewer hours worked than budgeted. Neither means that a cash cost exceeded its allowance.
Recover sales and statement figures
A sales price variance of $6,000 U on 3,000 sales means a price shortfall of $2 per unit. With a $50 standard selling price, actual price is $48.
For a whole operating statement, use actual profit = budgeted profit + favorable variances − unfavorable variances. If one variance is missing, isolate the unexplained movement. Preserve its direction as well as its amount: a $2,000 upward adjustment is favorable, while the same amount deducted from profit is unfavorable.
Key Takeaways
- Divide a quantity or hours variance by the standard price or rate to recover the physical difference.
- Read the direction from the named variance before adding or subtracting the difference.
- Use actual quantity for a reverse price calculation and actual sales for a reverse selling-price calculation.
- Check the recovered figure by putting it back into the original formula.
5Turn variance reports into useful action
A variance report locates differences, but business records explain their causes. You will connect related variances, judge what managers can control, and decide where investigation is worth its cost. You will also assess standard costing itself: how it supports planning and control, how targets affect behavior, and why quality, delivery, and people measures belong beside the cost figures when managers decide what to change.
5.1 Causes, responsibility, and linked effects
A variance gives a starting point for an investigation. Responsibility accounting directs it to a manager who can act, but the manager shown on the report may need evidence from other departments. One decision can affect several variances at once.
Follow the operational cause
Material price usually leads to purchasing. Material usage and labor efficiency usually lead to production. Labor rate may lead to human resources for pay changes or to production for overtime scheduling. Budget holders explain overhead spending; sales and marketing explain selling prices and sales volume.
These links guide questions. They are not a reason to judge a manager from the variance label alone. Overtime premiums appear in labor rate even when poor production scheduling caused the overtime.
Trace a chain of related effects
Buying lower-grade wood can lower the purchase price but increase waste. Defects can also slow workers, increase variable overhead attached to their hours, and lead to customer returns. A favorable price result can therefore sit beside unfavorable usage, efficiency, and sales results.
At Kestrel, the material price saving is $1,750 F and extra usage costs $3,500 U. If the cheaper wood caused both, the material effect is $1,750 U overall. Check delivery batches, scrap records, and quality tests to establish the connection.
Using lower-paid, less skilled employees can create a similar trade-off. Labor rate may be favorable, while extra time creates unfavorable labor, variable overhead, and fixed overhead efficiency variances. Those efficiency variances use one hours difference at three rates; they do not necessarily describe three separate operational causes.
Evaluate the sales trade-off
A price cut creates an unfavorable sales price variance and aims to increase sales volume. Kestrel's $10,500 U price result is partly offset by $4,400 F volume at standard profit, leaving $6,100 U in the absorption sales section.
For the pricing decision, with unchanged fixed costs, the extra contribution is $7,400. If the cut caused all the extra sales, the net effect is $3,100 U. Compare competitor prices, promotions, and market demand before attributing the volume change to the cut.
A machine breakdown has another linked pattern: paid idle time, fewer working hours than budgeted, and possibly repair spending. Downtime logs can connect the idle time, capacity, and overhead expenditure variances.
Separate influence from outside change
A controllable variance has a cause the responsible manager can influence. An uncontrollable variance comes from outside that manager's influence, such as a market-wide input-price rise or a national pay award. An unavoidable price rise may call for revised standards or selling prices. A preventable rush order may call for better scheduling.
A useful explanation names the variance, connects it to evidence in the business, explains any related effects, and proposes an action. For example, rising scrap after a supplier switch supports checking material quality before blaming employee effort. Staff training records, customer complaints, turnover, and delivery records help test competing explanations.
Key Takeaways
- Direct a variance to the manager able to investigate or influence its cause.
- One decision can create several linked favorable and unfavorable variances.
- Judge a linked decision using its net effect and relevant operational evidence.
- Separate controllable operational causes from changes outside the manager’s influence.
- Use contribution to evaluate extra sales when fixed costs are unchanged.
5.2 Choose an investigation and follow it through
Investigations use staff time and money. Management by exception focuses effort where finding and correcting a cause is likely to help. Size is a starting point; repeated patterns, controllability, and links between variances also matter.
Compare size on a suitable base
Consider both dollars and percentage of the relevant standard amount. Kestrel's material usage variance is $3,500 ÷ $84,000 × 100 = about 4.2% of standard material cost. Labor efficiency is $3,600 ÷ $113,400 × 100 = about 3.2%. Fixed overhead expenditure is $2,000 ÷ $60,000 × 100 = about 3.3% of budgeted fixed overhead.
Suppose the policy is to investigate any variance above 4% or above $5,000. Using standard revenue on actual sales, $378,000, as the sales base, this selects:
- Material usage: about 4.2%.
- Fixed overhead volume: $3,000 ÷ $60,000 = 5%.
- Sales price: $10,500, even though it is only about 2.8% of its base.
If fixed overhead volume is assessed through its parts, capacity is $5,000 ÷ $60,000 = about 8.3% and qualifies through the percentage test. The policy says or: either threshold is enough. The other Kestrel variances fall below both thresholds on these bases.
Look beyond one month's size
A $900 U variance every month for six months totals $5,400 U. A worn machine or an outdated standard may be creating a lasting pattern, even when each monthly amount is small. Small random movements in both directions are less likely to justify action. A control chart can help draw attention to results outside set limits.
A favorable variance can also deserve investigation. It may identify a saving worth repeating, a loose standard, or maintenance postponed at the expense of future reliability. Check the cause before recommending that the favorable result become a new target.
Compare expected benefit with cost
An investigation costs $800. There is a 30% chance of finding a correctable cause that would save $4,000.
Expected benefit = 0.30 × $4,000 = $1,200.
The expected benefit exceeds the investigation cost by $400, so the investigation is worthwhile on these figures. The possible $4,000 saving alone would overstate its value because success is uncertain.
Match action to the finding
| Finding | Suitable response |
|---|---|
| Recording or measurement error | Correct the records |
| Outdated or unrealistic standard | Revise the standard |
| Random fluctuation | Take no corrective action |
| Controllable operational problem | Repair equipment, retrain, improve scheduling, or change supplier |
| Uncontrollable change in conditions | Revise plans, prices, or future budgets |
Send reports promptly to the responsible manager. Record the finding and follow up on the action. A corrected process should improve later results; a revised standard should make future comparisons more useful.
Key Takeaways
- Use dollars, percentages, trends, controllability, standard reliability, and linked effects to prioritize investigations.
- Apply each threshold to the stated comparison base and read “or” and “above” carefully.
- Expected benefit equals the probability of a useful finding times the saving if successful.
- Investigate significant favorable variances as well as unfavorable ones.
- Match the response to the cause and follow up promptly.
- Repeated small variances can reveal a lasting problem.
5.3 Judge the value of standard costing
Standard costing is useful when its targets help people plan, identify problems, and improve operations. Its value depends on how standards are set, how quickly reports arrive, and what managers do with the results. A favorable total alone is an incomplete measure of business performance.
Identify the benefits
Unit standards give a business practical figures for budgets and price quotations. Standard inventory values simplify routine records. Clear targets help employees understand expected performance, and variance splits show where cost differences arose. Management by exception lets managers concentrate on significant results.
These benefits are strongest in repeated operations where inputs can be measured and standards remain reasonably stable. A factory producing a standard bench design can compare many similar units. A business producing unique designs has less comparable work and must spend more effort establishing useful allowances.
Weigh the cost and timeliness
Setting and updating standards takes time and money. Input prices, technology, and production methods can change faster than the annual budget cycle. A favorable time variance after a machine upgrade may simply reflect an outdated allowance. Monthly reports may also arrive after a defect has affected many batches.
Automation changes which figures matter. When machines replace direct labor, overhead becomes a larger share of cost and labor variances become less central. Managers need measures that reflect the main resources and processes now used by the business.
Consider behavior
A manager judged only on material price may buy cheap material that increases defects. A production manager rewarded for fixed overhead volume may build unsold inventory. A spending target may encourage delaying maintenance or training. An unattainable standard can discourage staff, while a blame culture encourages them to hide problems.
Attainable standards, developed with the people responsible and reviewed regularly, improve acceptance. Reports work better when managers use them to find causes and improve work. Employees are more likely to report a fault early when doing so leads to a repair instead of automatic blame.
Add measures of quality and service
Just-in-time production and total quality management emphasize continuous improvement and fewer defects. A fixed waste allowance can become a comfortable target if people stop trying to improve it. Cost reports also need information about quality, delivery reliability, customer loyalty, staff morale, supplier relationships, environmental effects, and reputation.
Paying more for a reliable material can increase input price while reducing scrap, rework, and complaints. Assess the whole result before rejecting the supplier because of an unfavorable price variance.
Reach a supported judgment
Kestrel's profit is $13,850 below budget. Its largest individual variance is sales price, $10,500 U. Higher sales offset part of that shortfall, while production variances net to $7,750 U, including $6,850 U in labor.
A useful judgment would prioritize the pricing decision and labor performance, check whether cheaper wood contributed to waste and slower work, and review the labor standard. It would also ask whether the price response retained customers and whether defects rose. The best action is the one that improves the business after these linked financial and non-financial effects are considered.
Key Takeaways
- Standard costing supports planning and control when operations repeat and targets remain useful.
- Standards require upkeep; late reports and changing methods reduce their value.
- Variance-only targets can encourage poor quality, excess inventory, or delayed maintenance.
- Combine cost information with quality, delivery, customer, employee, and environmental measures.
- An evaluation applies evidence to the business and reaches a supported judgment.
Variance Analysis examples
1Build a standard and use a fair comparison
16 steps
- 1IntroductionWhat should this output have cost?
A manager sees a higher cost and needs to know why. Did the factory make more units, pay more for inputs, or use more inputs per unit?
A standard cost gives a planned cost for one unit under expected operating conditions. We will build that target, then apply it to the output actually achieved so that changes in volume do not obscure changes in performance.
- 2ExampleOne bench and the whole budget
Kestrel's labor standard is $54 per bench. Its budget for 2,000 benches is $108,000 in total.
The standard describes one unit; multiplying it by planned units creates a budget. This link lets the business plan total spending, quote prices, and later compare results with a clear target. Repeated products and services make these unit comparisons easier to establish.
- 3ExplanationRead favorable and unfavorable
A variance is a difference between an actual result and the standard or budget used for comparison. Favorable, F, raises profit against that comparison; unfavorable, U, reduces it. Adverse, or A, means unfavorable.
For a cost, below the allowance is favorable. For a selling price, above standard is favorable. Read what the figure measures before attaching the label.
- 4ChallengeA unit target becomes a budget
A repeated cleaning service has a standard cost of $32 per visit. It plans 240 visits. What cost budget follows, and why is $32 not the budget total?
---reveal---
240 × $32 = $7,680. The $32 standard describes one visit, while the budget covers 240 visits. A later comparison of actual spending must also take account of how many visits were completed.
- 5ExplanationChoose a reachable target
An ideal standard assumes perfect conditions with no waste or downtime. An attainable standard expects efficient work but includes normal waste and breaks.
A current standard reflects present conditions, including inefficiencies. A basic standard remains unchanged for years to reveal trends. Choosing a target affects behavior: an unreachable target can discourage effort, while a loose target can hide waste.
- 6ExampleFind input before normal loss
A finished bench contains 7.6 kg of wood. Normal offcuts are 5% of the input, leaving 95% in the bench.
Standard input = 7.6 ÷ 0.95 = 8 kg.
The check is 8 × 95% = 7.6 kg retained. Adding 5% to the finished amount uses the wrong base. Use specifications and work studies alongside past records when setting quantities, so inefficient past work does not become the target.
- 7ChallengeAllow for paid time without work
A maintenance job needs 4.25 productive hours. Normal unproductive time is 15% of paid time. How many paid hours should the standard allow?
---reveal---
Productive time is 85% of paid time, so 4.25 ÷ 0.85 = 5 paid hours. The remaining 0.75 hour is the allowance. Keep paid and productive hours separate when later comparing labor performance.
- 8ExampleSet overhead rates from the plan
Kestrel budgets 2,000 benches at 3 hours each: 6,000 labor hours. Variable overhead is budgeted at $24,000 and fixed overhead at $60,000.
The rates are $24,000 ÷ 6,000 = $4 variable overhead per hour, and $60,000 ÷ 6,000 = $10 fixed overhead per hour.
Use budget figures to set standard rates. Actual costs and hours enter when measuring the variances.
- 9ExampleComplete the cost card
Each bench uses materials costing 8 × $5 = $40 and labor costing 3 × $18 = $54.
Its three labor hours also carry $12 variable overhead and $30 fixed overhead. The full standard cost is $136. Excluding fixed overhead gives a $106 variable cost.
At a $180 selling price, standard profit is $44 and standard contribution is $74. The $30 difference is fixed overhead per bench.
- 10ChallengeFind the two unit margins
A storage box has standard price $70, materials $18, labor $20, variable overhead $7, and fixed overhead $9. What are standard profit and contribution?
---reveal---
Variable cost is $18 + $20 + $7 = $45; full cost is $54. Standard profit is $70 − $54 = $16, and contribution is $70 − $45 = $25. Contribution is measured before charging fixed overhead.
- 11ExplanationApply the target to actual output
A bakery allows 0.5 kg of flour at $1.20 for each loaf. It planned 900 loaves but made 1,000.
The actual-output allowance is 1,000 × 0.5 = 500 kg, costing $600. This is the right direct-material comparison. Using the $540 original budget would include the cost of making another 100 loaves in the apparent performance difference.
- 12ExampleA small total hides two effects
The bakery uses 520 kg costing $598. Actual quantity at the standard price is 520 × $1.20 = $624.
Price: $624 − $598 = $26 F.
Usage: $600 − $624 = $24 U.
The net is just $2 F, but the factory used extra flour while buying it more cheaply. Price is measured on actual quantity; usage is valued at standard price to keep the effects separate.
- 13ChallengeSeparate extra output from extra input
A bottle allows 0.2 kg of resin at $4 per kg. Production was planned at 1,000 bottles but reached 1,100. Actual resin cost was $920. What is the total material variance?
---reveal---
Actual output allows 1,100 × 0.2 = 220 kg, costing $880. The total is $880 − $920 = $40 U. Comparing with the original $800 budget would mix the cost of 100 extra bottles with performance.
- 14TipChoose the allowance before subtracting
For total direct material and labor variances, use the standard cost of actual output. Variable overhead expenditure uses the allowance for hours actually worked. Fixed overhead expenditure uses the original fixed budget.
Here, cost formulas use standard minus actual. Report a positive amount with F or U so that the direction stays clear even when another book reverses the subtraction.
- 15ChallengeBuild the target and flex it
A stool allows 2 hours of labor at $21. Budgeted fixed overhead is $24,000 for 4,000 labor hours. What labor-plus-fixed-overhead allowance applies to 300 stools?
---reveal---
Fixed rate = $24,000 ÷ 4,000 = $6 per hour. Each stool carries $42 labor and $12 fixed overhead. For 300 stools the combined allowance is 300 × $54 = $16,200, using 600 standard hours of output.
- 16RecapKeep quantities, rates, and activity distinct
Build unit targets from quantities and standard prices or rates. Include normal allowances in a realistic standard, and keep its input basis clear.
For a direct-cost comparison, apply that unit target to actual production. Then separate the price of inputs from the amount used. An operating report becomes more useful when its manager can see both effects instead of one small net difference.
2Track materials and paid working time
16 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionTwo reasons direct costs change
- 2ExampleStart with the wood actually used
- 3ExampleValue extra wood at the standard price
- 4ChallengeSplit a fresh material result
- 5ExplanationBuy now, use later
- 6ChallengeLocate the deferred price difference
- 7ExampleSeparate Kestrel’s pay-rate effect
- 8ExampleSeparate time from pay rate
- 9ChallengeRecover output from efficient work
- 10ExplanationPaid hours include idle hours
- 11TipKeep idle time from entering twice
- 12ExplanationA normal idle allowance changes the split
- 13ExampleSplit time with the effective rate
- 14ChallengeChoose a consistent time comparison
- 15ChallengeJudge a linked input decision
- 16RecapCheck every split against its total
3Build the overhead variance bridge
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionFollow cost behavior
- 2ExplanationThree variable overhead amounts
- 3ExampleSeparate spending from time
- 4ChallengeUse machine hours consistently
- 5ConnectionOne hours problem, several cost effects
- 6ExplanationAbsorb fixed overhead into output
- 7ExampleKeep fixed expenditure on the original budget
- 8ExampleFind the volume effect
- 9ChallengeCombine fixed spending and volume
- 10Key InsightA favorable result can reward unsold production
- 11ExplanationBridge three hours totals
- 12ExampleCalculate capacity
- 13ExampleCalculate efficiency and reconcile
- 14ChallengeLess time, faster output
- 15TipUse the total or the parts
- 16ChallengeReconcile from the split
- 17RecapName the comparison before choosing hours
4Reconcile profit and recover missing figures
20 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake every profit movement visible
- 2ExampleMeasure the selling-price shortfall
- 3ExampleChoose the volume margin
- 4ChallengeDistinguish revenue from profit
- 5ExampleStart the absorption statement
- 6ExampleCollect favorable production effects
- 7ExampleComplete the absorption bridge
- 8ConnectionCheck actual profit directly
- 9ChallengeCount the activity effect once
- 10ExampleBegin with contribution
- 11ExampleReach actual contribution and profit
- 12Key InsightThe two volume presentations agree
- 13ChallengeInventory changes the profit comparison
- 14ExampleTurn money back into material
- 15ExampleWork backward through fixed overhead
- 16ChallengeRecover quantity and spending
- 17TipUse the unexplained profit movement
- 18ConnectionEvaluate the price decision with contribution
- 19ChallengeConnect a margin to a complete statement
- 20RecapCheck the margin, signs, and total
5Choose a useful response to a variance report
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMove from a figure to a decision
- 2ExplanationFollow responsibility to the cause
- 3ExampleTrace a supplier decision through production
- 4ChallengeExplain several effects of one event
- 5ExplanationUse a stated investigation policy
- 6ChallengeApply percentage and dollar tests
- 7ExampleAllow for the chance of success
- 8ChallengeMatch the action to the finding
- 9ExplanationUse the strengths where they fit
- 10ExampleTargets can change behavior
- 11ChallengeJudge a saving with quality evidence
- 12ConnectionKeep measures aligned with modern work
- 13ChallengePrioritize a linked pattern
- 14TipComplete the control loop
- 15RecapSupport the action with evidence
Variance Analysis practice questions
Set 1: Labor time and variable overhead10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Standards, cost cards, and material performance10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Fixed overhead and sales effects10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Profit reconciliations and missing figures10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Investigate causes and judge business performance10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Absorption costing
Actual contribution
Attainable standard
B
Basic standard
Budgeted contribution
C
Controllable variance
Corrective action
Current standard
E
Effective productive-hour rate
Expected benefit
F
Favorable variance
Fixed overhead
Fixed overhead absorbed
Fixed overhead absorption rate
Fixed overhead capacity variance
Fixed overhead efficiency variance
Fixed overhead expenditure variance
Fixed overhead volume variance
H
Hours paid
I
Ideal standard
Idle time
Idle time variance
Interdependent variances
Investigation threshold
J
Just-in-time production
L
Labor efficiency variance
Labor rate variance
M
Management by exception
Marginal costing
Material price variance
Material usage variance
N
Net production cost variance
Non-financial performance measure
Normal loss
O
Operating statement
Over-absorbed overhead
P
Purchase-basis price variance
Q
Quantity effect
R
Relative size
Responsibility accounting
Revenue-based sales volume variance
S
Sales price variance
Sales volume variance
Standard contribution
Standard contribution on actual sales
Standard cost
Standard cost card
Standard cost of actual output
Standard costing
Standard hour
Standard profit
Standard profit on actual sales
Standard quantity for actual output
T
Total direct-input cost variance
Total quality management
Total sales revenue variance
Total variable overhead variance
U
Uncontrollable variance
Under-absorbed overhead
Unfavorable variance
Unproductive time
Usage-basis price variance
V
Variable overhead
Variable overhead efficiency variance
Variable overhead expenditure variance
Variance
Variance analysis
W
Work study
About this lesson