- Control how materials are ordered, received, stored and issued, decide when to reorder and how much to order, and price the materials charged to jobs.
- Control the ordering, receipt and issue of materialsFollow materials from the first purchase request to their issue to a job, use the documents and checks that protect inventory, and tell direct materials from indirect materials.
- Set reorder levels and economic order quantitiesCalculate when to place an order and how much to order, so that materials do not run out and too much money is not tied up in inventory.
- Price material issues with FIFO and weighted average costRecord receipts and issues on a stores ledger card, price issues to jobs with first in, first out or weighted average cost, and explain how the choice changes job costs, closing inventory and profit.
- Control the ordering, receipt and issue of materials
- Calculate workers' gross pay under the main pay schemes, then decide which parts of labor cost are charged directly to jobs and which become overhead.
- Calculate gross pay under time, piece and bonus schemesWork out gross pay for time rates, salaries, overtime, piece rates and time-saved bonuses, and explain what each scheme encourages.
- Charge labor costs to jobs and overheadRecord the time each worker spends on each job, analyze gross pay into direct and indirect labor, and treat overtime premium, idle time and employer costs correctly.
- Calculate gross pay under time, piece and bonus schemes
- Collect indirect production costs in cost centers by allocation and apportionment, then move the costs of service cost centers into the production cost centers that do the work on jobs.
- Allocate and apportion overhead to cost centersIdentify cost centers and cost units, charge whole overheads to the center that caused them, and share joint overheads on fair bases in an overhead analysis statement.
- Reapportion service cost center costsMove the overhead of service cost centers into production cost centers with the direct, step-down and reciprocal methods, including service centers that work for each other.
- Allocate and apportion overhead to cost centers
- Calculate overhead absorption rates from budgets, use them to charge overhead to each job, and explain and account for the difference between overhead absorbed and overhead incurred.
- Calculate and apply predetermined overhead ratesChoose an absorption basis, calculate a predetermined rate from budgeted overhead and budgeted activity, and use it to charge overhead to jobs.
- Calculate and account for under- and over-absorbed overheadCompare overhead absorbed with overhead incurred, explain the spending and activity causes of the difference, and record its effect on profit.
- Calculate and apply predetermined overhead rates
- Build up the full cost of a job, a batch or a unit of service from its materials, labor and overhead, set selling and quotation prices, and follow job costs through the accounts.
- Prepare a job cost sheetCollect the direct costs and absorbed overhead of a job from its source documents and lay them out to reach prime cost, production cost and total cost.
- Set selling prices and quotations with markups and marginsAdd profit to a job's total cost as a markup or a margin, convert between the two, and prepare and review a quotation price.
- Cost batches and units of serviceCost a batch of identical items and find the cost per unit, and calculate the cost per unit of a continuing service with an operating cost statement.
- Track job costs through the accountsRecord materials, labor and overhead in work in process, move finished jobs to finished goods and cost of goods sold, and close the overhead account at the end of the period.
- Prepare a job cost sheet
Job Costing study guide
1Account for materials and control inventory
Materials affect a job long before they reach the workshop. Purchasing records protect the business from paying for missing goods, inventory levels help prevent delays, and issue prices determine the cost charged to each order. Follow the materials through these decisions, from an authorized purchase to a priced issue, with checks on both the physical quantity and its value.
1.1 Control the ordering, receipt and issue of materials
Materials move through several hands before their cost reaches a job. Clear records show what was bought, what arrived and where it went. Direct materials can be traced to one job, such as timber for a table. Small supplies such as glue and machine oil are indirect materials and enter production overhead.
From request to payment
The purchasing sequence separates an internal need from an order placed with a supplier:
- A purchase requisition asks Purchasing to obtain materials.
- A purchase order tells the supplier the item, quantity, agreed price and delivery terms.
- The supplier sends a delivery note with the goods. Receiving staff inspect them and prepare a goods received note (GRN) for the quantity and condition actually received.
- The supplier's invoice requests payment.
Before paying, match the invoice to both the purchase order and the GRN. The order establishes authorization and agreed terms; the GRN establishes receipt. If 100 parts were ordered but only 90 arrived, an invoice for 100 needs investigation. Paying from the order alone would overlook the short delivery.
From stores to a job
An authorized materials requisition releases materials from stores. It records the item, quantity and job number or cost center that receives the charge. A materials returned note reverses the cost of unused materials sent back to stores. A materials transfer note shifts materials and their cost from one job to another.
Prenumbered documents help reveal missing records. A supervisor authorizes issues, store access is restricted, and different people order, receive and record goods. A job number makes each charge traceable. These controls protect both the physical materials and the prices calculated from job costs.
Keep quantities and values in agreement
A bin card at the storage location records quantities received, issued and remaining. A stores ledger card, also called an inventory record card, records quantities and their unit costs and values. In a perpetual system, every receipt and issue updates the balance. In a periodic system, a closing count establishes inventory and usage is calculated as:
A physical stocktake checks the records. Periodic stocktaking counts everything at one time; continuous stocktaking checks selected items throughout the year. Suppose the ledger shows 480 parts at $4 each and the count finds 465. The shortage is 15 parts worth $60. Investigate damage, theft and recording errors, record the loss and correct the balance to 465. A normal production loss usually enters production overhead.
Balance availability against storage
Holding costs include storage, insurance, tied-up money and deterioration. Ordering costs arise when orders are placed, delivered, received and checked. Stockouts can stop production, lose sales or force costly emergency purchases.
Just-in-time purchasing reduces inventory by arranging delivery close to use. It reduces holding costs and waste but makes dependable lead times and quality essential: a late or defective delivery can stop the next job.
Key Takeaways
- Direct materials go to the identifiable job; indirect materials enter production overhead.
- Match the invoice, purchase order and goods received note before payment.
- Authorized issue, return and transfer notes keep job charges traceable.
- Physical counts check inventory records and trigger investigation of differences.
- JIT reduces holding costs but depends on reliable deliveries and quality.
1.2 Set reorder levels and economic order quantities
Inventory decisions answer two different questions: when to order and how much to order. Lead time is the delay between ordering and receiving materials. Buffer inventory protects production against high usage or a late delivery.
Set the trigger and warning levels
Use the maximum usage and maximum lead time to set the reorder trigger:
Daily usage ranges from 80 to 120 units, averaging 100. Lead time ranges from 4 to 6 days, averaging 5. The reorder level is 720 units: 120 units per day for 6 days. An average-only trigger of 500 units would leave no cover for the higher usage and longer wait.
The minimum level is the reorder level less expected usage during average lead time:
The 220 units are the buffer built into the trigger. Falling below this level is a warning to investigate usage or chase a delivery. With an order quantity of 1,000 units, the maximum level allows for a large delivery arriving after the shortest, lowest-usage wait:
The reorder level is a balance that triggers an order; the reorder quantity is the number bought. Confusing them changes both the timing and size of deliveries.
Find an economical order size
The economic order quantity (EOQ) minimizes annual ordering and holding costs in the basic model:
Here is annual demand in units, is cost per order and is annual holding cost per unit. With demand of 10,000 units, $50 per order and $4 per unit per year:
At 500 units per order, 20 orders cost $1,000 per year. Average cycle inventory is 250 units, costing another $1,000. At 1,000 units per order, ordering costs fall to $500 but holding costs rise to $2,000. Buying more saves orders but ties up more inventory.
The model uses constant demand and lead time, fixed order and holding costs, and no quantity discount. Demand and holding cost must use the same time period. Convert percentage holding costs into money first: 20% of a $20 purchase price is $4 per unit per year. A fixed buffer adds its own holding cost without changing the EOQ.
Check a bulk discount with total annual cost
Include purchases when the unit price changes:
At a $20 unit price, the 500-unit EOQ costs $200,000 for purchases plus $2,000 for ordering and holding: $202,000. A 1% discount for orders of at least 1,000 units lowers annual purchases to $198,000. With holding cost still $4, the 1,000-unit option totals $198,000 + $500 + $2,000 = $200,500. The saving is $1,500 per year. Compare the feasible EOQ and discount thresholds; the lowest unit price alone does not establish the lowest total cost.
Key Takeaways
- Reorder level uses maximum usage and maximum lead time.
- Minimum level deducts average lead-time usage; maximum level adds the order and deducts minimum lead-time usage.
- EOQ balances ordering and holding costs using consistent time units.
- Quantity discounts require comparison of purchase, ordering and holding costs.
1.3 Price material issues with FIFO and weighted average cost
Identical materials may arrive at different prices. An issue-pricing rule assigns those purchase costs between jobs and the materials left in stores. It is a cost-flow rule; the storeroom can move physical items in a different order.
Follow one month's receipts and issues
Opening inventory is 200 units at $5.00. Receive 300 units at $6.00 on the 4th; issue 400 units to Job 31 on the 10th; receive 500 units at $6.32 on the 18th; issue 350 units to Job 32 on the 25th. There are 1,000 units available costing $5,960, with 250 units left at month-end.
First in, first out (FIFO) charges the oldest price layers first. Job 31 takes 200 units at $5 and 200 at $6, costing $2,200. This leaves 100 units at $6. After the next receipt, Job 32 takes those 100 units and 250 at $6.32, costing $600 + $1,580 = $2,180. The remaining 250 units at $6.32 are worth $1,580.
Calculate the weighted average
Under perpetual weighted average cost (AVCO), each receipt creates a new average from the value and quantity now held:
After the first receipt, $2,800 divided by 500 units gives $5.60. Job 31 costs 400 × $5.60 = $2,240, leaving 100 units worth $560. The next receipt gives a value of $560 + $3,160 = $3,720 across 600 units, or $6.20 each. Job 32 costs 350 × $6.20 = $2,170. Closing inventory is $1,550. An issue reduces quantity and value at the same rate, so it leaves the average unchanged.
Periodic AVCO calculates one average at the end of the whole period. Divide $5,960 by 1,000 units to obtain $5.96. All 750 issued units cost $4,470 and the closing 250 cost $1,490. Do not average the three purchase prices without weighting them by quantities.
| Method | Total issues | Closing inventory |
|---|---|---|
| FIFO | $4,380 | $1,580 |
| Perpetual AVCO | $4,410 | $1,550 |
| Periodic AVCO | $4,470 | $1,490 |
Every row totals $5,960. This checks the value movement independently of the method.
Understand the effects and record returns
With rising prices, FIFO gives lower total issue costs and higher closing inventory than AVCO. Individual jobs can differ: FIFO costs Job 31 less but Job 32 more than perpetual AVCO here. The profit effect occurs as job costs reach cost of goods sold; it is not a cash saving from choosing a pricing method.
LIFO, last in, first out, charges the newest layer first. In this example its issues are $2,300 and $2,212, leaving $1,448. It can be used for internal costing; IFRS prohibits it for external inventory reporting, while US GAAP permits it.
Materials returned from a job reverse their original issue price and reduce that job's charge. Under perpetual AVCO, add the returned value and quantity back before recalculating the average. Supplier returns remove their original purchase cost. Pricing a job return at today's purchase price would fail to reverse the amount originally charged.
Key Takeaways
- FIFO issues the oldest cost layers first.
- Perpetual AVCO recalculates after receipts; periodic AVCO uses one period-wide weighted average.
- Opening value plus receipts must equal issues plus closing inventory.
- The methods change cost allocation, not total purchase spending.
- Returns reverse the original cost charged.
- LIFO is allowed under US GAAP but prohibited under IFRS for external reporting.
2Calculate and classify labor costs
Payroll shows what employees earned, but a job needs the cost of the productive time spent on it. Start with time, output and bonus schemes, then separate direct job labor from idle time, general overtime premium and other indirect pay. Matching approved time records to attendance and payroll connects the pay calculation to reliable production costs.
2.1 Calculate gross pay under time, piece and bonus schemes
A pay scheme determines gross pay, the amount earned before employee deductions. Net pay is the amount received after deductions. Employee deductions are still part of gross labor cost: the employer passes them on instead of keeping them.
Pay for time or output
A time rate pays hours worked multiplied by an hourly rate. It suits work where quality matters or individual output is hard to measure. A salary, also called a flat rate, pays a fixed amount per week or month. A straight piece rate pays an amount for each acceptable unit produced.
| Scheme | Calculation | Main incentive |
|---|---|---|
| Time rate | Hours × hourly rate | Attendance and time worked |
| Salary | Fixed periodic amount | Completing the role's work |
| Piece rate | Good units × rate per unit | More acceptable output |
At $18 per hour, a worker with a 40-hour standard week who works 46 hours at time-and-a-half earns $720 for the first 40 hours and $162 for the six overtime hours. Gross pay is $882. Time-and-a-half means $27 for each overtime hour, not a 50% addition to the whole week's pay.
The same total can be separated into all hours at basic rate and the extra overtime premium: 46 × $18 = $828, plus 6 × $9 = $54. This split matters when the pay is later divided between jobs and overhead.
Read piecework thresholds carefully
At $0.80 per acceptable unit, 1,150 units earn $920. A guaranteed minimum pays the higher of piece earnings and the guarantee. With a $600 guarantee, 700 units earn only $560 by piecework, so pay is $600. The guarantee is a floor, not an extra payment added to piece earnings.
A differential piece rate changes at a target. If the first 1,000 units earn $0.80 each and only excess units earn $0.90, 1,150 units earn $800 + $135 = $935. If the scheme instead applies $0.90 to every unit once the target is passed, the same output earns $1,035. The wording determines which units receive the higher rate.
Reward time saved
Time saved is allowed time minus actual time taken. The worker receives basic pay for actual time and a bonus for the saving. For 50 hours allowed, 40 taken and a $20 hourly rate, basic pay is $800.
Under a 50% Halsey scheme:
Total pay is $900. Under the Rowan scheme:
Total pay is $960. The time-taken fraction belongs to Rowan; Halsey uses the stated share of saved-time pay. When there is no time saving, there is no bonus.
A group bonus rewards a team when output depends on joint work. Its sharing rule should be clear and linked to results the workers can influence. Piecework and time-saving schemes need quality checks, since extra speed has little value if units are rejected or work must be redone.
Key Takeaways
- Gross pay includes employee deductions; net pay is what the worker receives.
- Overtime premium is the extra rate applied only to overtime hours.
- A guaranteed minimum is compared with piece earnings, not added to them.
- Differential piecework can apply to excess units or all units, depending on the scheme.
- Halsey and Rowan bonuses use time saved but weight it differently.
2.2 Charge labor costs to jobs and overhead
Paying a worker and costing a job answer different questions. Attendance establishes the time paid for. Job records establish where productive time was spent. A payroll analysis must account for the whole cost, including paid time that did not produce a job.
Match attendance to job time
An attendance record shows total hours at work. A time sheet or job card identifies hours on each job and carries the job number and supervisor approval. Reconcile the sum of job hours, indirect work and idle time to attendance hours. Missing hours otherwise disappear from cost records even though they remain in payroll.
Direct labor is pay for time spent making the product or doing the customer's job. Production supervisors, maintenance staff and storekeepers provide indirect labor, which enters production overhead. Office and sales pay enters non-production expenses.
Separate basic pay from the premium
Overtime hours spent on a job at the basic rate are direct labor. The premium follows its cause. General workload causes a premium shared through production overhead. A customer's urgent request that causes overtime makes the premium a direct cost of that job. This avoids making an ordinary job look expensive just because it happened to be completed in the evening.
Normal unavoidable idle time, such as a routine production interruption, enters production overhead. Abnormal idle time, such as an exceptional prolonged breakdown, is usually written off as a period loss. Record its cause so that management can investigate the disruption.
Analyze a week's gross pay
A worker earns $20 per hour and works 45 hours, including five overtime hours at time-and-a-half. Job records show 42 productive hours and three hours of normal idle time. Overtime arose from general workload.
- Pay all attendance hours at basic rate: 45 × $20 = $900.
- Add the premium: five hours × $10 = $50. Gross pay is $950.
- Charge productive basic pay to jobs: 42 × $20 = $840.
- Charge normal idle pay of $60 and general overtime premium of $50 to production overhead: $110.
The $840 direct charge plus $110 overhead reconciles to $950 gross pay. Charging all 45 hours directly to jobs would hide $60 of idle time in their costs. Charging $27 or $30 per overtime hour and then adding a separate premium would count the premium twice.
Include the employer's extra costs
The employer can also pay payroll taxes, pension contributions and benefits on top of gross pay. These costs form part of employing staff. One approach builds them into the hourly job rate: $20 plus 12% gives $22.40 per hour. Another collects them in production overhead. Use the chosen approach consistently so the cost is neither omitted nor counted in both places.
A payroll analysis separates direct job labor, indirect production labor and non-production labor. Its total reconciles to total payroll cost. The records therefore serve two checks: hours agree with attendance, and amounts agree with pay. An accurate gross-pay total alone cannot show whether the right jobs received the cost.
Key Takeaways
- Reconcile job hours, indirect work and idle time to attendance.
- Basic pay for productive hours goes to jobs; normal idle time enters production overhead.
- The cause of overtime determines whether its premium is overhead or a direct job cost.
- Include employer costs through a loaded job rate or overhead, without double counting.
3Share production overhead among cost centers
Indirect production costs need a route to the jobs that benefit from them. First collect whole costs in the departments that incur them and share common costs on measured bases. Then move service department costs into production departments, allowing for the support they give each other. Each stage preserves the factory total while changing where the cost is held.
3.1 Allocate and apportion overhead to cost centers
Factory rent, machine depreciation and indirect pay support many jobs. Production overhead collects these indirect production costs. A cost center is a department, location or machine where costs are gathered. A cost unit is the output ultimately costed, such as a job or batch.
Decide whether a whole cost belongs to one center
Allocation assigns an entire overhead to the center that incurred it. A maintenance supervisor's pay belongs to Maintenance. Apportionment shares a common overhead among the centers that benefit. Factory rent serves several departments and needs a sharing basis.
Production centers work on jobs; service centers support the production work. Both belong in the first overhead analysis. Maintenance and Stores use space, employ staff and incur costs even though jobs do not pass through them.
| Shared overhead | Useful basis |
|---|---|
| Rent, building insurance and lighting | Floor area |
| Heating | Floor area or heated volume |
| Machine depreciation and insurance | Machinery cost or carrying value |
| Power | Kilowatt-hours or machine hours |
| Canteen and personnel services | Number of employees |
Choose a basis that reflects use or benefit and can be measured. Equal shares are unsuitable when departments clearly consume unequal amounts.
Build an overhead analysis statement
Give each overhead a row and each center a column. Begin with direct allocations. Machining, Assembly, Maintenance and Stores receive indirect materials of $8,000, $5,000, $3,000 and $2,000, and indirect labor of $12,000, $9,000, $14,000 and $7,000.
Now share $60,000 rent, heating and lighting over floor areas of 4,000, 3,000, 2,000 and 1,000 square feet. Total area is 10,000 square feet, so each square foot receives $6. The shares are $24,000, $18,000, $12,000 and $6,000. Leaving service departments out of the denominator would overcharge production departments.
Machinery values are $300,000, $100,000, $50,000 and zero. Divide $36,000 depreciation and insurance by the $450,000 machinery value. The rate is 8 cents per dollar of machinery, giving $24,000, $8,000, $4,000 and zero.
Finally, share $14,000 supervision and canteen cost across 70 employees. The $200 per employee rate gives $4,000, $6,000, $2,000 and $2,000 for departments with 20, 30, 10 and 10 staff.
| Center | Initial overhead total |
|---|---|
| Machining | $72,000 |
| Assembly | $46,000 |
| Maintenance | $35,000 |
| Stores | $17,000 |
| Total | $170,000 |
Check both directions
Each shared-cost row must add back to its original cost. The department columns together must add to the full $170,000. These row and column checks catch omitted departments, wrong denominators and arithmetic slips. Service costs remain in their own columns at this stage; they will move to production centers during reapportionment. General administration and selling costs stay outside this production-overhead analysis.
Key Takeaways
- Allocate whole overheads to their identifiable center.
- Apportion shared overheads using a measured basis that reflects benefit.
- Include production and service centers in the initial analysis.
- Check each cost row and the total of all center columns.
3.2 Reapportion service cost center costs
Service centers support production but do not hold the jobs being costed. Reapportionment moves their overhead into production centers before job rates are calculated. The method matters when service centers also work for each other.
Set out the service pattern
Initial costs are $72,000 for Machining, $46,000 for Assembly, $35,000 for Maintenance and $17,000 for Stores. Maintenance supplies 50% of its service to Machining, 30% to Assembly and 20% to Stores. Stores supplies 40%, 40% and 20% to Machining, Assembly and Maintenance.
A service basis can be maintenance hours, stores requisitions, employee numbers or measured percentages. It describes who receives the service, not who originally incurred the overhead.
Use the direct method
Ignore services exchanged between service centers and rescale the remaining production shares. Maintenance's 50:30 becomes 5:3, so Machining receives $21,875 and Assembly $13,125. Stores' 40:40 becomes equal shares of $8,500. The final production totals are $102,375 and $67,625.
Using only 50% and 30% of Maintenance's original cost would leave $7,000 undistributed. Rescaling assigns its entire $35,000.
Use the step-down method
Close one service center at a time. Here Maintenance is closed first, sending $17,500 to Machining, $10,500 to Assembly and $7,000 to Stores. Stores now holds $24,000, including the amount received.
Close Stores next. Do not send anything back to closed Maintenance. Rescale Stores' two remaining 40% shares and send $12,000 to each production center. Final totals are $101,500 and $68,500. The order affects the split; follow a specified order. A common choice closes the center providing the larger value of service to other service centers first.
Recognize all mutual service
The reciprocal method allows service costs to pass both ways. Let and be the full Maintenance and Stores costs, including services received:
Substitute the second equation into the first:
Thus , so Maintenance totals $40,000. Stores totals $25,000. Machining receives 50% of $40,000 plus 40% of $25,000: $30,000. Assembly receives $12,000 plus $10,000: $22,000. Adding their initial costs gives $102,000 and $68,000.
The service totals include internal exchanges. Their $65,000 sum is not extra factory spending: only $52,000 reaches production, equal to the original service costs.
Repeated distribution reaches the same reciprocal result by passing balances back and forth. Distribute Maintenance's $35,000, then Stores' updated $24,000, then the $4,800 returned to Maintenance, then the $960 returned to Stores. Continue until the residue is negligible and distribute that residue to production.
| Method | Service exchanged recognized | Machining | Assembly |
|---|---|---|---|
| Direct | None | $102,375 | $67,625 |
| Step-down | Part | $101,500 | $68,500 |
| Reciprocal | All | $102,000 | $68,000 |
The changed split affects departmental rates and the costs of jobs using those departments.
Key Takeaways
- Reapportion service costs before calculating production-center absorption rates.
- The direct method rescales shares after excluding other service centers.
- Step-down includes costs received from earlier centers and never reopens a closed center.
- Reciprocal equations include the services received from the other service center.
- Repeated distribution approaches the algebraic reciprocal result.
- Total factory overhead stays unchanged under every method.
4Absorb overhead into jobs with predetermined rates
A job can be priced before the factory knows its actual annual overhead. Budgeted rates supply a consistent charge for the machine time, labor time or other activity the job consumes. The later comparison with actual spending reveals the amount under- or over-absorbed. Understanding its cause helps distinguish a rate that needs revision from the period cost of idle capacity.
4.1 Calculate and apply predetermined overhead rates
Overhead absorption charges production overhead to jobs through a rate. It is also called application or recovery. A predetermined rate is set before the period, so a business can cost work and prepare quotations before actual annual costs are known.
Calculate a rate with matching units
Use each production center's overhead after service reapportionment. Machining's $102,000 over 8,500 machine hours gives $12 per machine hour. Assembly's $68,000 over 4,000 direct labor hours gives $17 per direct labor hour. Keep the unit beside the rate: it tells you what quantity to multiply later.
| Production pattern | Suitable absorption basis |
|---|---|
| Machine-intensive work | Machine hours |
| Labor-intensive work | Direct labor hours |
| Identical output units | Units produced |
| A cost-based approach | Direct labor cost, materials cost or prime cost |
A percentage rate needs a cost denominator. If Assembly's direct labor cost budget is $85,000, its rate is 80% of direct labor cost. Do not treat 80% as $80 per hour. A labor-cost basis can charge different overhead to equally time-consuming jobs merely because workers' wage rates differ.
Set activity at normal capacity
Normal capacity is average activity expected across several periods, allowing for ordinary maintenance, breaks and seasonal changes. Theoretical maximum capacity includes time that will not actually be worked. Using it makes the denominator too large and the rate too low.
An unusually quiet year creates the reverse problem: dividing fixed overhead by too few hours overcharges each job. A normal-capacity rate avoids forcing the whole cost of idle capacity onto the few jobs completed. Annual budgets also reduce seasonal swings that would arise from calculating a fresh actual rate every month.
Apply the rate to the job's activity
Job 247 uses 25 machine hours in Machining and 40 direct labor hours in Assembly. It absorbs $300 plus $680, or $980. Completed-job costing uses the hours actually consumed; a quotation uses estimated hours. The budgeted department hours set the rate but are not the hours charged to one job.
Compare a factory-wide rate with department rates
A blanket rate uses one factory-wide basis. Total overhead of $170,000 divided by 6,800 direct labor hours gives $25 per hour.
Job A uses 30 machine hours, two Machining labor hours and ten Assembly labor hours. Departmental rates charge $360 + $170 = $530; the blanket rate charges 12 labor hours × $25 = $300. Job B uses two machine hours, one Machining labor hour and 20 Assembly labor hours. Departmental overhead is $24 + $340 = $364; blanket overhead is $525.
One labor-based rate undercosts the machine-heavy job and overcosts the labor-heavy one. A blanket rate works when there is one center or jobs use centers in similar proportions. Departmental rates reflect different production patterns. Separate fixed and variable overhead rates can also be calculated from the budget and applied to their matching bases.
Key Takeaways
- Predetermined rates divide budgeted overhead by budgeted activity.
- Normal capacity allows for routine lost time and seasonal changes.
- Apply each rate to the matching job activity, using actual hours for completed work.
- A percentage-of-cost rate needs a cost base, not hours.
- Departmental rates improve costing when jobs use unlike centers in different proportions.
4.2 Calculate and account for under- and over-absorbed overhead
The overhead charged to jobs is based on a budgeted rate. The factory's actual bills can differ from that charge. At period-end, compare absorbed overhead with actual overhead incurred to find the balance that remains unassigned or overcharged.
Calculate the difference
Machining incurs $98,400 and works 8,000 machine hours at $12 per hour. It absorbs $96,000, which is $2,400 less than actual cost: under-absorbed, also called underapplied or under-recovered overhead.
Assembly incurs $70,500 and works 4,300 labor hours at $17. It absorbs $73,100, which is $2,600 more than actual cost: over-absorbed overhead. Across the factory, the $2,600 excess offsets the $2,400 shortage, leaving $200 over-absorbed.
Do not compare absorption with the overhead budget to name the final difference. The budget was used to set the rate; actual cost is the amount that needs recovery.
Explain spending and activity effects
For fixed overhead, spending and activity can push in opposite directions. Machining's budget was $102,000 at 8,500 hours. Spending $98,400 saves $3,600, tending toward over-absorption. Working 500 fewer hours absorbs $6,000 less, tending toward under-absorption. The $6,000 activity shortfall less the $3,600 saving explains the $2,400 under-absorption.
Assembly spends $2,500 above its $68,000 budget but works 300 hours above budget, absorbing an extra $5,100. The activity effect exceeds overspending by $2,600. This spending-and-activity comparison holds the overhead budget fixed; variable overhead also changes with activity.
Close the overhead control account
The production overhead control account records actual overhead as debits and absorbed overhead as credits. A debit balance means actual cost exceeds absorption. A credit balance means absorption exceeds actual cost.
If the balance is closed to cost of goods sold, under-absorption increases that expense and lowers profit. Over-absorption reduces the expense and raises profit. In double-entry terms, close an underapplied balance by debiting cost of goods sold and crediting overhead control; reverse those entries for an overapplied balance.
A small difference is commonly closed this way. A material US adjustment may be shared across work in process, finished goods and cost of goods sold using the applied overhead remaining in each. For $5,000 underapplied and shares of 10%, 30% and 60%, add $500, $1,500 and $3,000 to those accounts. Only the cost-of-goods-sold share immediately reduces profit.
Investigate before changing prices
Under-absorption can arise because spending exceeded the budget, because a rate used unattainable activity, or because activity temporarily fell below normal capacity. These causes lead to different decisions. A temporary production shortfall does not make the normal-capacity charge on each job wrong: unallocated idle-capacity overhead is a period expense. Persistent spending changes may require a revised future rate.
Over-absorption also needs investigation. A persistently excessive rate can make quotations uncompetitive. The period adjustment normally closes the overall account; it does not require rewriting every completed job cost sheet.
Key Takeaways
- Under-absorption means actual overhead exceeds absorbed overhead; over-absorption means the reverse.
- Compute absorption with actual activity at the predetermined rate.
- Fixed-overhead spending and activity effects can offset one another.
- Closing an underapplied balance to cost of goods sold reduces profit.
- A material US difference may be prorated using applied overhead in the affected accounts.
- Temporary idle capacity is a period cost, not a reason to inflate job charges.
5Cost and price jobs and batches
A cost sheet combines traceable job costs with the overhead charges developed from department budgets. Its subtotals serve different purposes: production cost supports inventory, while total cost supports pricing. Extend that structure to batches and services, distinguish markup from margin, and follow production costs through unfinished work, completed goods and the expense recorded when jobs are delivered.
5.1 Prepare a job cost sheet
A custom kitchen, a repair or a consulting assignment has its own requirements and costs. Job costing treats each order as a separate cost unit. Give it a job number, then collect direct costs and its share of overhead on a job cost sheet, also called a job cost card or statement.
Build the cost in layers
| Subtotal | What it contains |
|---|---|
| Prime cost | Direct materials + direct labor + direct expenses |
| Total production cost | Prime cost + absorbed production overhead |
| Total cost for pricing | Production cost + non-production overhead |
| Selling price | Total cost + profit |
Direct expenses belong only to that job, such as subcontracted heat treatment, special equipment hire or design work. An invoice supplies that charge. Materials requisitions less returns supply direct material cost. Approved time sheets supply productive job hours multiplied by the labor rate. Absorption rates supply production overhead.
Prepare Job 247's sheet
Materials requisitioned cost $3,600, with $200 returned to stores. The job therefore uses $3,400 of direct materials.
Machining labor takes 12 hours at $20, costing $240. Assembly labor takes 40 hours at $18, costing $720. Total direct labor is $960. Add $300 subcontracted heat treatment:
The job uses 25 machine hours at $12 and 40 Assembly labor hours at $17. Production overhead is $300 + $680 = $980. Machine hours and labor hours are different measures; the 12 Machining labor hours do not replace the 25 machine hours in absorption.
Administration, selling and distribution overhead is added at 20% of production cost: $1,128. Total cost for pricing is $6,768. The percentage base matters: applying 20% to prime cost would give a different and incorrect charge here.
Add non-production costs for pricing
A business can set the percentage from its budget. Budgeted non-production overhead of $90,000 divided by $450,000 production cost gives 20%. The added charge helps a quotation recover costs outside the factory. It does not turn selling and general administration costs into inventory.
Keep overhead classification consistent. Indirect materials already included in the production rate are not added again as direct job materials. General overtime premium and normal idle pay also enter overhead, so charging them separately to a job would count the wrong costs there.
Apply job costing to services and reconcile the records
Service jobs may use little material. An accounting assignment taking 30 staff hours at $40 costs $1,200 in direct labor. At $25 overhead per staff hour it absorbs $750, giving $1,950 before profit.
Unfinished job sheets support the work in process account. Add their production-cost subtotals, not their pricing totals or selling prices, to reconcile work in process. Completed unsold jobs support finished goods on the same production-cost basis. Job numbers and authorized records let the accountant trace a ledger difference back to the materials, time or overhead charge that caused it.
Key Takeaways
- Prime cost combines direct materials, direct labor and direct expenses.
- Production cost adds absorbed production overhead.
- Non-production overhead is added for pricing and excluded from inventory.
- Returns reduce materials charged to the job.
- Unfinished jobs reconcile to work in process at production cost.
5.2 Set selling prices and quotations with markups and margins
A cost-plus price starts with total cost and adds profit. The percentage can be based on cost or on selling price. The amount used as the denominator determines whether the instruction is a markup or a margin.
Add a markup to cost
A markup expresses profit as a percentage of cost:
Job 247 costs $6,768. A 25% markup gives $1,692 profit and an $8,460 price. That profit is 20% of the selling price because $1,692 divided by $8,460 is 0.20. A 25% markup therefore does not earn a 25% margin.
Work backward from a margin
A margin expresses profit as a percentage of selling price. A 25% margin leaves cost as 75% of price:
For the same $6,768 cost, divide by 0.75 to get $9,024. Profit is $2,256. Checking $2,256 divided by $9,024 confirms a 25% margin.
| Pricing instruction | Price | Profit |
|---|---|---|
| 25% markup on $6,768 | $8,460 | $1,692 |
| 25% margin on selling price | $9,024 | $2,256 |
Convert percentages using their decimal values:
A 50% markup gives a 33⅓% margin. A 25% margin requires a 33⅓% markup. The profit amount is the same in either description, but its share of cost is larger because cost is the smaller denominator.
Build a quotation before work begins
A quotation uses estimated materials, labor hours and machine hours at current prices and predetermined rates. Add non-production overhead on its stated base, then add profit on total cost. Once a quote is accepted, an underestimate can reduce the profit available on that order.
Suppose Job 247 is accepted at $8,460, but actual total cost becomes $7,200. Profit falls to $1,260, about 14.9% of selling price. The business cannot restore the original profit merely by recording the planned markup again. Compare actual quantities, prices and hours with the estimate to improve future quotations.
Keep sales tax separate and test commercial sense
For an illustrative 10% sales tax, the $8,460 price becomes a $9,306 invoice total. Tax collected for the government is neither job profit nor part of the tax-exclusive selling price. Calculate the profit first, then add the tax when a tax-inclusive quotation is needed.
At budgeted activity, predetermined rates recover budgeted overhead. Full recovery of actual spending still depends on absorbed overhead covering the actual cost. A cost-plus calculation also needs a market check: customers may not accept the proposed price. Compare the quote with competitors and customer demand before treating the calculated profit as achievable.
Key Takeaways
- Markup measures profit against cost; margin measures it against selling price.
- For a margin, divide cost by one minus the margin.
- Quotations use estimated activity and current input costs.
- Compare actual total cost with the accepted price to find actual profit.
- Add sales tax after profit and exclude it from job earnings.
5.3 Cost batches and units of service
A batch groups identical items produced together, such as a printing run or a set of components. Batch costing collects the group's cost like one job, then divides it among the good units. A continuing service instead uses the total cost and output of a period.
Cost the batch before dividing
Batch 12 starts 410 garden chairs. Ten rejects are a normal production loss, leaving 400 good chairs. Its direct materials cost $6,200; 120 labor hours at $18 cost $2,160; setup costs $440; and 80 machine hours at $12 absorb $960 of overhead.
Dividing by all 410 chairs started would spread costs over units that cannot be sold. Normal rejects are borne by the good output. The unit cost is a share of the batch total, not a new overhead charge.
With a 30% markup on this cost base, each chair sells for $31.72. The 400-chair batch sells for $12,688. If a pricing instruction also calls for non-production costs, include those in the specified base before adding profit.
Spread setup across the units
A setup prepares equipment once for the batch. A $440 setup costs $1.10 per unit across 400 chairs and $0.55 across 800. Larger batches reduce setup cost per unit but increase average inventory and holding costs. Doubling batch size does not halve materials or labor per unit when those inputs still vary with output.
Choose a unit that measures the service
A delivery firm, bus company, hospital or hotel can collect period costs in an operating cost statement. Divide total cost by the service units delivered. Some useful units combine two dimensions:
| Service | Composite cost unit |
|---|---|
| Freight transport | Tonne-kilometer |
| Passenger transport | Passenger-kilometer |
| Hospital care | Patient-day |
| Hotel accommodation | Room-night |
A composite unit reflects both the amount served and the duration or distance. A 12-tonne load carried 150 kilometers produces 1,800 tonne-kilometers. Adding 12 and 150 gives no meaningful service output.
Prepare and use a service rate
A delivery firm's annual costs are drivers' pay $180,000, fuel $96,000, depreciation $60,000, insurance and licenses $24,000, maintenance $30,000 and administration $50,000. Total operating cost is $440,000. For 2,000,000 tonne-kilometers:
At a 25% markup, the charge is $0.275 per tonne-kilometer. Carry that precision into the trip calculation. The 1,800 tonne-kilometer delivery costs $396 and is charged at $495. Rounding the rate to $0.28 first would change the charge.
Use job costing for distinct customer orders, batch costing for groups made together and service costing for repeated service output. The chosen unit must fit both the cost total and the output period used in the calculation.
Key Takeaways
- Divide total batch cost by good units when normal rejects are borne by good output.
- Setup occurs once per batch, so its cost per unit falls as batch size rises.
- Service unit cost divides period operating cost by period service output.
- Composite units multiply linked measures such as load and distance.
- Keep sufficient rate precision until the final charge is calculated.
5.4 Track job costs through the accounts
A job cost sheet supplies detail; control accounts collect the same production costs in the general ledger. Costs move from materials into unfinished work, then completed goods and finally cost of goods sold. The sale itself is recorded separately at selling price.
Follow the production flow
For a transfer, debit the account receiving the cost and credit the account giving it up. Direct materials issued move from materials inventory to work in process. Indirect materials move to production overhead control. Direct labor and direct expenses enter work in process; indirect production labor enters overhead control.
Actual overhead is debited to overhead control. Absorbed overhead is credited there and debited to work in process at the predetermined rate. Work in process holds the applied share, not all the actual overhead bills.
When a job is completed, its production cost moves to finished goods. When delivered to the customer, the cost moves to cost of goods sold. General administration and selling expenses enter the income statement directly. Their pricing charges and profit on job sheets do not enter inventory.
Reconcile a month's unfinished work
Opening work in process is $10,000. During the month, direct materials issued are $42,000 and direct labor is $30,000. There are no separate direct expenses. Overhead is applied at $15 per direct labor hour for 2,300 hours, adding $34,500. Completed jobs costing $95,000 leave work in process.
The unfinished job sheets must total $21,500 at production cost. Cost of goods manufactured is the completed-job transfer:
Here $116,500 available less $21,500 unfinished equals $95,000 completed. Production costs added include direct expenses whenever a job incurs them.
Reconcile completed goods and overhead
Opening finished goods is $5,000. Add the $95,000 completed and deduct $80,000 cost of jobs delivered, leaving $20,000 finished goods. Delivered jobs leave at their production cost, even if their selling price is much higher.
Actual overhead consists of $3,000 indirect materials, $8,000 indirect labor and $25,000 other factory costs, totaling $36,000. The control account has $36,000 of debits and $34,500 of credits, leaving $1,500 underapplied. Closing it to cost of goods sold raises the expense from $80,000 to $81,500 and clears the overhead account.
Trace a difference to its source
A missing materials return overstates both the job and work in process if the job is unfinished. A completed job left in work in process makes that account too high and finished goods too low. Charging actual overhead to work in process while also applying the rate counts overhead twice. Reconcile the production-cost subtotals to the ledger and use source documents to locate the charge or transfer that failed.
Key Takeaways
- Direct costs and applied production overhead enter work in process.
- Actual overhead enters overhead control; applied overhead leaves it for work in process.
- Completed jobs move to finished goods and delivered jobs to cost of goods sold at production cost.
- Cost of goods manufactured is the production cost of completed jobs.
- Job sheets reconcile to inventory without non-production charges or profit.
- Close or allocate the overhead control balance at period-end.
Job Costing examples
1Control materials and price their issues
18 steps
- 1IntroductionFollow a material from purchase to job
A material has two trails: where the physical units go and where their cost goes. A job can be delayed by a missing delivery or mispriced by a missing return.
Follow the documents first (order, receipt and invoice must match), then decide when and how much to order (the reorder level and EOQ), and finally price issues to jobs with FIFO and AVCO. The checks work together: quantities protect availability, while values support job costs.
- 2ExplanationAuthorize the purchase and verify receipt
A purchase requisition asks Purchasing to buy materials. The purchase order goes to the supplier with the agreed quantity, price and delivery terms.
When the goods arrive, receiving staff count and inspect them and prepare a goods received note. The supplier's delivery note accompanies the goods; the buyer's receipt record states what actually arrived.
- 3Key InsightMatch before payment
Compare the supplier invoice with the purchase order and goods received note. The order proves what was authorized; the receipt record proves what arrived.
If an order and invoice both show 100 units but the receipt shows 90, the agreement between order and invoice is insufficient. Investigate the missing ten units before approving payment.
- 4ExplanationTrack issues, returns and transfers
An authorized materials requisition identifies the item, quantity and job charged when materials leave stores. A return note reduces the original job charge when unused materials come back. A transfer note moves the charge to another job.
Direct materials enter the identified job. Indirect supplies enter production overhead. A job number and supervisor approval make the movement traceable.
- 5ChallengeFind the missing receipt evidence
Purchasing ordered 80 panels. The invoice charges for 80, but receiving staff found only 76. What record establishes the quantity actually received, and why is the order insufficient?
---reveal---
The goods received note establishes actual receipt. The purchase order shows the authorized purchase, so it cannot establish that the four missing panels arrived.
- 6TipCheck inventory without stopping every day
A bin card tracks quantities at the storage location; a stores ledger card also tracks unit costs and values. Perpetual records update each receipt and issue. A physical count still checks whether records match reality.
Continuous stocktaking spreads counts through the year. JIT reduces the amount stored, but reliable suppliers and quality become essential because little buffer remains.
- 7ExampleTrigger the order before stock runs out
Daily usage reaches 120 units and lead time reaches six days. Set the reorder level from those maxima:
Place an order when inventory falls to 720. This covers the longest lead time at the highest usage. Using average usage and lead time would remove that protection.
- 8ExampleSeparate the buffer from the delivery size
Average usage is 100 units daily and average lead time five days. Expected usage while waiting is 500 units, leaving a minimum level of 220 from the 720-unit trigger.
With a 1,000-unit order, minimum usage of 80 and minimum lead time four days, maximum inventory is:
- 9ExplanationBalance fewer orders against more storage
Larger orders reduce the number of orders placed but increase average inventory. EOQ finds the basic model's least-cost order size:
Use annual demand for , cost per order for and annual holding cost per unit for . Convert a percentage holding charge to money before substituting.
- 10ExampleCalculate and check the EOQ
Demand is 10,000 units annually, ordering costs $50 per order and holding costs $4 per unit per year. The formula gives an EOQ of 500 units.
That means 20 orders costing $1,000. Average cycle inventory is 250 units, also costing $1,000 annually. Equal basic ordering and holding costs check this result. A fixed buffer adds holding cost without changing the EOQ.
- 11ExampleCheck whether a discount pays
At a $20 unit price, 500-unit orders cost $202,000 annually including purchases, ordering and holding. A 1% price reduction for 1,000-unit orders changes those costs to $198,000, $500 and $2,000: $200,500 total.
The larger order saves $1,500 despite extra holding cost. The lowest purchase price alone cannot show whether a discount is worthwhile.
- 12ChallengeChoose the right time units
Demand is stated as 900 units per month, while holding cost is $3 per unit per year. What demand figure belongs in an annual EOQ calculation, and why?
---reveal---
Use 10,800 units per year. Multiplying monthly demand by 12 puts demand and holding cost on the same annual basis; using 900 with an annual holding cost would understate the order size.
- 13ExamplePrice the oldest layers first
Opening inventory is 200 units at $5. Receive 300 at $6, then issue 400. FIFO uses all 200 oldest units and 200 from the newer layer:
The issue costs $2,200 and leaves 100 units at $6. FIFO describes which costs are assigned; physical materials can leave stores in a different order.
- 14ExampleUpdate the moving average
For the same first receipt, perpetual AVCO divides $2,800 by 500 units, giving $5.60 each. Issuing 400 costs $2,240 and leaves 100 units worth $560.
Receive another 500 units costing $3,160. The new average is $3,720 divided by 600, or $6.20. Keep the remaining value from the previous average when adding the new receipt.
- 15ConnectionUse the average until the next receipt
At $6.20 per unit, issuing 350 units costs $2,170 and leaves 250 worth $1,550. The issue reduces value and quantity in the same proportion, so it does not change the average.
Periodic AVCO instead divides the whole period's $5,960 by 1,000 available units. Its single $5.96 average gives total issues of $4,470 and closing inventory of $1,490.
- 16TipKeep returns tied to their original charge
A return from a job reverses the price originally charged to that job. Add that quantity and value back to stores and recalculate a perpetual average. A supplier return removes the original purchase price.
FIFO leaves recent purchase layers in closing inventory. LIFO issues recent layers first; external reporting permits LIFO under US GAAP but prohibits it under IFRS.
- 17ChallengeCheck a cost trail and a return
Opening inventory and receipts cost $4,800. Issues total $3,500. A job then returns $120 of those materials. What are net issues and closing inventory after the return?
---reveal---
Net issues fall to $3,380 and closing inventory rises to $1,420. The total remains $4,800. The return moves an existing cost back to stores; it does not create another purchase.
- 18RecapConnect control with cost
A reliable material charge needs an authorized movement, enough physical inventory and a consistent pricing method. Invoice matching checks purchases; issue and return records identify the job; stocktaking checks the recorded balance.
Inventory levels and EOQ support supply decisions. FIFO and AVCO divide purchase value between issues and the balance left. Reconcile both quantities and value when a difference appears.
2Calculate earnings and assign labor costs
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionCalculate pay, then trace its cost
- 2ExplanationKeep gross earnings separate from take-home pay
- 3ExampleSplit overtime pay into two parts
- 4ExplanationApply the piecework floor and threshold
- 5ExampleCalculate the Halsey bonus
- 6ExampleCalculate the Rowan bonus
- 7ChallengeInterpret a differential scheme
- 8ExplanationMatch hours to the work done
- 9Key InsightFollow the cause of the premium
- 10ExampleReconcile a worker’s week
- 11ChallengeFind the direct and indirect shares
- 12TipInclude costs paid by the employer
- 13RecapUse pay records to support job charges
3Analyze and reapportion factory overhead
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMove shared factory costs toward jobs
- 2ExplanationDistinguish where costs collect from what is costed
- 3ExplanationAssign whole costs before sharing common costs
- 4ExampleApportion the premises cost
- 5ExampleAdd the other analysis rows
- 6ChallengeShare a new building cost
- 7ExplanationWrite the service pattern before distributing
- 8ExampleRescale the direct-method shares
- 9ExampleClose Maintenance first under step-down
- 10ExampleFinish the step-down distribution
- 11ExplanationSet up reciprocal service equations
- 12ExampleSolve and distribute the full totals
- 13ConnectionReach the same result by repeated distribution
- 14ChallengeCheck the total after mutual service
- 15RecapPreserve the total while changing its destination
4Apply overhead and explain the balance
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionCharge jobs before the final bills arrive
- 2ExampleDivide the budget by its matching activity
- 3ExplanationChoose a base and a normal activity level
- 4ExampleApply each rate to the right job hours
- 5Key InsightSee what a blanket rate can hide
- 6ChallengeCalculate one job’s overhead
- 7ExampleCompare application with actual overhead
- 8ExampleSeparate saving from lost absorption
- 9ExplanationRead and close the control balance
- 10ConnectionAllocate a material adjustment
- 11ChallengeExplain a net balance from two causes
- 12TipInvestigate before changing the next quote
- 13RecapKeep the three amounts distinct
5Cost and price work, then track the accounts
19 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionBuild a cost, set a price and follow the work
- 2ExampleBuild prime cost from source records
- 3ExampleAdd production overhead, then other costs
- 4ChallengeChoose the inventory subtotal
- 5ExampleAdd profit on the cost base
- 6ExampleRecover price from a required margin
- 7ChallengeTest the denominator
- 8ConnectionReview the accepted quote against actual costs
- 9ExampleCost the good output of a batch
- 10Key InsightSpread setup without losing its full cost
- 11ExampleMeasure continuing service output
- 12ChallengeCompare a batch with normal rejects
- 13ExplanationSend actual and applied overhead to different places
- 14ExampleTransfer completed and delivered jobs at cost
- 15ExampleReconcile unfinished work
- 16ExampleClose the overhead difference
- 17ChallengeComplete the account flow
- 18ChallengeConnect the sheet, inventory and profit
- 19RecapMatch each total to its purpose
Job Costing practice questions
Set 1: Materials control, order sizes and issue pricing10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Pay schemes, labor analysis and service departments10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Overhead rates, job sheets and prices10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Batches, service units and account flows10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Connect material, labor, overhead and pricing decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 6: Analyze reciprocal costs, capacity and full cost flows10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Allocation
Apportionment
B
Batch costing
Bin card
Blanket rate
Buffer inventory
C
Composite cost unit
Control account
Cost center
Cost of goods manufactured
Cost of goods sold
Cost unit
Cost-plus pricing
D
Departmental rate
Differential piece rate
Direct labor
Direct materials
Direct method
E
Economic order quantity
F
Finished goods
First in, first out
G
Goods received note
Gross pay
Group bonus
Guaranteed minimum
H
Halsey bonus
Holding cost
I
Idle time
Indirect labor
Indirect materials
J
Job cost sheet
Job costing
Just-in-time purchasing
L
Last in, first out
Lead time
M
Margin
Markup
Materials requisition
Maximum inventory level
Minimum inventory level
N
Net pay
Normal capacity
O
Operating cost statement
Ordering cost
Over-absorbed overhead
Overhead absorption
Overhead analysis statement
Overhead control account
Overtime premium
P
Payroll analysis
Periodic AVCO
Perpetual AVCO
Perpetual inventory system
Piece rate
Predetermined overhead rate
Prime cost
Production overhead
Proration
Purchase order
Purchase requisition
Q
Quotation
R
Reapportionment
Reciprocal method
Reorder level
Reorder quantity
Repeated distribution
Rowan bonus
S
Salary
Service cost center
Setup cost
Step-down method
Stockout cost
Stocktaking
Stores ledger card
T
Three-way match
Time rate
Time sheet
Total production cost
U
Under-absorbed overhead
W
Weighted average cost
Work in process
About this lesson
Make your own Study Materials
Turn your notes, slides and documents into Study Guides, Practice Questions, Flashcards and 6 more tools.