Overhead and Job Costing

Learn how a business works out what each job really costs. Control and price the materials it uses, calculate pay under time, piece and bonus schemes, and share factory overhead among departments, including service departments that work for each other. Then absorb overhead into jobs with predetermined rates, explain under- and over-absorption, and build job and batch cost sheets that lead to a selling or quotation price.

BeginnerLesson 4 of 11 in Introduction to Management Accounting Course

What you will learn

  1. Control how materials are ordered, received, stored and issued, decide when to reorder and how much to order, and price the materials charged to jobs.
    • Control the ordering, receipt and issue of materials
      Follow materials from the first purchase request to their issue to a job, use the documents and checks that protect inventory, and tell direct materials from indirect materials.
    • Set reorder levels and economic order quantities
      Calculate when to place an order and how much to order, so that materials do not run out and too much money is not tied up in inventory.
    • Price material issues with FIFO and weighted average cost
      Record receipts and issues on a stores ledger card, price issues to jobs with first in, first out or weighted average cost, and explain how the choice changes job costs, closing inventory and profit.
  2. Calculate workers' gross pay under the main pay schemes, then decide which parts of labor cost are charged directly to jobs and which become overhead.
    • Calculate gross pay under time, piece and bonus schemes
      Work out gross pay for time rates, salaries, overtime, piece rates and time-saved bonuses, and explain what each scheme encourages.
    • Charge labor costs to jobs and overhead
      Record the time each worker spends on each job, analyze gross pay into direct and indirect labor, and treat overtime premium, idle time and employer costs correctly.
  3. Collect indirect production costs in cost centers by allocation and apportionment, then move the costs of service cost centers into the production cost centers that do the work on jobs.
    • Allocate and apportion overhead to cost centers
      Identify cost centers and cost units, charge whole overheads to the center that caused them, and share joint overheads on fair bases in an overhead analysis statement.
    • Reapportion service cost center costs
      Move the overhead of service cost centers into production cost centers with the direct, step-down and reciprocal methods, including service centers that work for each other.
  4. Calculate overhead absorption rates from budgets, use them to charge overhead to each job, and explain and account for the difference between overhead absorbed and overhead incurred.
    • Calculate and apply predetermined overhead rates
      Choose an absorption basis, calculate a predetermined rate from budgeted overhead and budgeted activity, and use it to charge overhead to jobs.
    • Calculate and account for under- and over-absorbed overhead
      Compare overhead absorbed with overhead incurred, explain the spending and activity causes of the difference, and record its effect on profit.
  5. Build up the full cost of a job, a batch or a unit of service from its materials, labor and overhead, set selling and quotation prices, and follow job costs through the accounts.
    • Prepare a job cost sheet
      Collect the direct costs and absorbed overhead of a job from its source documents and lay them out to reach prime cost, production cost and total cost.
    • Set selling prices and quotations with markups and margins
      Add profit to a job's total cost as a markup or a margin, convert between the two, and prepare and review a quotation price.
    • Cost batches and units of service
      Cost a batch of identical items and find the cost per unit, and calculate the cost per unit of a continuing service with an operating cost statement.
    • Track job costs through the accounts
      Record materials, labor and overhead in work in process, move finished jobs to finished goods and cost of goods sold, and close the overhead account at the end of the period.

Job Costing study guide

5 chapters

1

Account for materials and control inventory

Materials affect a job long before they reach the workshop. Purchasing records protect the business from paying for missing goods, inventory levels help prevent delays, and issue prices determine the cost charged to each order. Follow the materials through these decisions, from an authorized purchase to a priced issue, with checks on both the physical quantity and its value.

1.1 Control the ordering, receipt and issue of materials

Materials move through several hands before their cost reaches a job. Clear records show what was bought, what arrived and where it went. Direct materials can be traced to one job, such as timber for a table. Small supplies such as glue and machine oil are indirect materials and enter production overhead.

From request to payment

The purchasing sequence separates an internal need from an order placed with a supplier:

  1. A purchase requisition asks Purchasing to obtain materials.
  2. A purchase order tells the supplier the item, quantity, agreed price and delivery terms.
  3. The supplier sends a delivery note with the goods. Receiving staff inspect them and prepare a goods received note (GRN) for the quantity and condition actually received.
  4. The supplier's invoice requests payment.

Before paying, match the invoice to both the purchase order and the GRN. The order establishes authorization and agreed terms; the GRN establishes receipt. If 100 parts were ordered but only 90 arrived, an invoice for 100 needs investigation. Paying from the order alone would overlook the short delivery.

From stores to a job

An authorized materials requisition releases materials from stores. It records the item, quantity and job number or cost center that receives the charge. A materials returned note reverses the cost of unused materials sent back to stores. A materials transfer note shifts materials and their cost from one job to another.

Prenumbered documents help reveal missing records. A supervisor authorizes issues, store access is restricted, and different people order, receive and record goods. A job number makes each charge traceable. These controls protect both the physical materials and the prices calculated from job costs.

Keep quantities and values in agreement

A bin card at the storage location records quantities received, issued and remaining. A stores ledger card, also called an inventory record card, records quantities and their unit costs and values. In a perpetual system, every receipt and issue updates the balance. In a periodic system, a closing count establishes inventory and usage is calculated as:

Usage=opening inventory+purchases−closing inventory

A physical stocktake checks the records. Periodic stocktaking counts everything at one time; continuous stocktaking checks selected items throughout the year. Suppose the ledger shows 480 parts at $4 each and the count finds 465. The shortage is 15 parts worth $60. Investigate damage, theft and recording errors, record the loss and correct the balance to 465. A normal production loss usually enters production overhead.

Balance availability against storage

Holding costs include storage, insurance, tied-up money and deterioration. Ordering costs arise when orders are placed, delivered, received and checked. Stockouts can stop production, lose sales or force costly emergency purchases.

Just-in-time purchasing reduces inventory by arranging delivery close to use. It reduces holding costs and waste but makes dependable lead times and quality essential: a late or defective delivery can stop the next job.

Key Takeaways

  • Direct materials go to the identifiable job; indirect materials enter production overhead.
  • Match the invoice, purchase order and goods received note before payment.
  • Authorized issue, return and transfer notes keep job charges traceable.
  • Physical counts check inventory records and trigger investigation of differences.
  • JIT reduces holding costs but depends on reliable deliveries and quality.

1.2 Set reorder levels and economic order quantities

Inventory decisions answer two different questions: when to order and how much to order. Lead time is the delay between ordering and receiving materials. Buffer inventory protects production against high usage or a late delivery.

Set the trigger and warning levels

Use the maximum usage and maximum lead time to set the reorder trigger:

Reorder level=maximum usage×maximum lead time

Daily usage ranges from 80 to 120 units, averaging 100. Lead time ranges from 4 to 6 days, averaging 5. The reorder level is 720 units: 120 units per day for 6 days. An average-only trigger of 500 units would leave no cover for the higher usage and longer wait.

The minimum level is the reorder level less expected usage during average lead time:

Minimum level=720−(100×5)=220 units

The 220 units are the buffer built into the trigger. Falling below this level is a warning to investigate usage or chase a delivery. With an order quantity of 1,000 units, the maximum level allows for a large delivery arriving after the shortest, lowest-usage wait:

Maximum level=720+1,000−(80×4)=1,400 units

The reorder level is a balance that triggers an order; the reorder quantity is the number bought. Confusing them changes both the timing and size of deliveries.

Find an economical order size

The economic order quantity (EOQ) minimizes annual ordering and holding costs in the basic model:

EOQ=2CoDCh

Here D is annual demand in units, Co is cost per order and Ch is annual holding cost per unit. With demand of 10,000 units, $50 per order and $4 per unit per year:

EOQ=2×50×10,0004=500 units

At 500 units per order, 20 orders cost $1,000 per year. Average cycle inventory is 250 units, costing another $1,000. At 1,000 units per order, ordering costs fall to $500 but holding costs rise to $2,000. Buying more saves orders but ties up more inventory.

The model uses constant demand and lead time, fixed order and holding costs, and no quantity discount. Demand and holding cost must use the same time period. Convert percentage holding costs into money first: 20% of a $20 purchase price is $4 per unit per year. A fixed buffer adds its own holding cost without changing the EOQ.

Check a bulk discount with total annual cost

Include purchases when the unit price changes:

Annual cost=Dp+DQCo+Q2Ch

At a $20 unit price, the 500-unit EOQ costs $200,000 for purchases plus $2,000 for ordering and holding: $202,000. A 1% discount for orders of at least 1,000 units lowers annual purchases to $198,000. With holding cost still $4, the 1,000-unit option totals $198,000 + $500 + $2,000 = $200,500. The saving is $1,500 per year. Compare the feasible EOQ and discount thresholds; the lowest unit price alone does not establish the lowest total cost.

Key Takeaways

  • Reorder level uses maximum usage and maximum lead time.
  • Minimum level deducts average lead-time usage; maximum level adds the order and deducts minimum lead-time usage.
  • EOQ balances ordering and holding costs using consistent time units.
  • Quantity discounts require comparison of purchase, ordering and holding costs.

1.3 Price material issues with FIFO and weighted average cost

Identical materials may arrive at different prices. An issue-pricing rule assigns those purchase costs between jobs and the materials left in stores. It is a cost-flow rule; the storeroom can move physical items in a different order.

Follow one month's receipts and issues

Opening inventory is 200 units at $5.00. Receive 300 units at $6.00 on the 4th; issue 400 units to Job 31 on the 10th; receive 500 units at $6.32 on the 18th; issue 350 units to Job 32 on the 25th. There are 1,000 units available costing $5,960, with 250 units left at month-end.

First in, first out (FIFO) charges the oldest price layers first. Job 31 takes 200 units at $5 and 200 at $6, costing $2,200. This leaves 100 units at $6. After the next receipt, Job 32 takes those 100 units and 250 at $6.32, costing $600 + $1,580 = $2,180. The remaining 250 units at $6.32 are worth $1,580.

Calculate the weighted average

Under perpetual weighted average cost (AVCO), each receipt creates a new average from the value and quantity now held:

Average unit cost=value held after receiptunits held after receipt

After the first receipt, $2,800 divided by 500 units gives $5.60. Job 31 costs 400 × $5.60 = $2,240, leaving 100 units worth $560. The next receipt gives a value of $560 + $3,160 = $3,720 across 600 units, or $6.20 each. Job 32 costs 350 × $6.20 = $2,170. Closing inventory is $1,550. An issue reduces quantity and value at the same rate, so it leaves the average unchanged.

Periodic AVCO calculates one average at the end of the whole period. Divide $5,960 by 1,000 units to obtain $5.96. All 750 issued units cost $4,470 and the closing 250 cost $1,490. Do not average the three purchase prices without weighting them by quantities.

MethodTotal issuesClosing inventory
FIFO$4,380$1,580
Perpetual AVCO$4,410$1,550
Periodic AVCO$4,470$1,490

Every row totals $5,960. This checks the value movement independently of the method.

Understand the effects and record returns

With rising prices, FIFO gives lower total issue costs and higher closing inventory than AVCO. Individual jobs can differ: FIFO costs Job 31 less but Job 32 more than perpetual AVCO here. The profit effect occurs as job costs reach cost of goods sold; it is not a cash saving from choosing a pricing method.

LIFO, last in, first out, charges the newest layer first. In this example its issues are $2,300 and $2,212, leaving $1,448. It can be used for internal costing; IFRS prohibits it for external inventory reporting, while US GAAP permits it.

Materials returned from a job reverse their original issue price and reduce that job's charge. Under perpetual AVCO, add the returned value and quantity back before recalculating the average. Supplier returns remove their original purchase cost. Pricing a job return at today's purchase price would fail to reverse the amount originally charged.

Key Takeaways

  • FIFO issues the oldest cost layers first.
  • Perpetual AVCO recalculates after receipts; periodic AVCO uses one period-wide weighted average.
  • Opening value plus receipts must equal issues plus closing inventory.
  • The methods change cost allocation, not total purchase spending.
  • Returns reverse the original cost charged.
  • LIFO is allowed under US GAAP but prohibited under IFRS for external reporting.
2

Calculate and classify labor costs

Payroll shows what employees earned, but a job needs the cost of the productive time spent on it. Start with time, output and bonus schemes, then separate direct job labor from idle time, general overtime premium and other indirect pay. Matching approved time records to attendance and payroll connects the pay calculation to reliable production costs.

2.1 Calculate gross pay under time, piece and bonus schemes

A pay scheme determines gross pay, the amount earned before employee deductions. Net pay is the amount received after deductions. Employee deductions are still part of gross labor cost: the employer passes them on instead of keeping them.

Pay for time or output

A time rate pays hours worked multiplied by an hourly rate. It suits work where quality matters or individual output is hard to measure. A salary, also called a flat rate, pays a fixed amount per week or month. A straight piece rate pays an amount for each acceptable unit produced.

SchemeCalculationMain incentive
Time rateHours × hourly rateAttendance and time worked
SalaryFixed periodic amountCompleting the role's work
Piece rateGood units × rate per unitMore acceptable output

At $18 per hour, a worker with a 40-hour standard week who works 46 hours at time-and-a-half earns $720 for the first 40 hours and $162 for the six overtime hours. Gross pay is $882. Time-and-a-half means $27 for each overtime hour, not a 50% addition to the whole week's pay.

The same total can be separated into all hours at basic rate and the extra overtime premium: 46 × $18 = $828, plus 6 × $9 = $54. This split matters when the pay is later divided between jobs and overhead.

Read piecework thresholds carefully

At $0.80 per acceptable unit, 1,150 units earn $920. A guaranteed minimum pays the higher of piece earnings and the guarantee. With a $600 guarantee, 700 units earn only $560 by piecework, so pay is $600. The guarantee is a floor, not an extra payment added to piece earnings.

A differential piece rate changes at a target. If the first 1,000 units earn $0.80 each and only excess units earn $0.90, 1,150 units earn $800 + $135 = $935. If the scheme instead applies $0.90 to every unit once the target is passed, the same output earns $1,035. The wording determines which units receive the higher rate.

Reward time saved

Time saved is allowed time minus actual time taken. The worker receives basic pay for actual time and a bonus for the saving. For 50 hours allowed, 40 taken and a $20 hourly rate, basic pay is $800.

Under a 50% Halsey scheme:

Bonus=0.5×(50−40)×20=100

Total pay is $900. Under the Rowan scheme:

Bonus=4050×(50−40)×20=160

Total pay is $960. The time-taken fraction belongs to Rowan; Halsey uses the stated share of saved-time pay. When there is no time saving, there is no bonus.

A group bonus rewards a team when output depends on joint work. Its sharing rule should be clear and linked to results the workers can influence. Piecework and time-saving schemes need quality checks, since extra speed has little value if units are rejected or work must be redone.

Key Takeaways

  • Gross pay includes employee deductions; net pay is what the worker receives.
  • Overtime premium is the extra rate applied only to overtime hours.
  • A guaranteed minimum is compared with piece earnings, not added to them.
  • Differential piecework can apply to excess units or all units, depending on the scheme.
  • Halsey and Rowan bonuses use time saved but weight it differently.

2.2 Charge labor costs to jobs and overhead

Paying a worker and costing a job answer different questions. Attendance establishes the time paid for. Job records establish where productive time was spent. A payroll analysis must account for the whole cost, including paid time that did not produce a job.

Match attendance to job time

An attendance record shows total hours at work. A time sheet or job card identifies hours on each job and carries the job number and supervisor approval. Reconcile the sum of job hours, indirect work and idle time to attendance hours. Missing hours otherwise disappear from cost records even though they remain in payroll.

Direct labor is pay for time spent making the product or doing the customer's job. Production supervisors, maintenance staff and storekeepers provide indirect labor, which enters production overhead. Office and sales pay enters non-production expenses.

Separate basic pay from the premium

Overtime hours spent on a job at the basic rate are direct labor. The premium follows its cause. General workload causes a premium shared through production overhead. A customer's urgent request that causes overtime makes the premium a direct cost of that job. This avoids making an ordinary job look expensive just because it happened to be completed in the evening.

Normal unavoidable idle time, such as a routine production interruption, enters production overhead. Abnormal idle time, such as an exceptional prolonged breakdown, is usually written off as a period loss. Record its cause so that management can investigate the disruption.

Analyze a week's gross pay

A worker earns $20 per hour and works 45 hours, including five overtime hours at time-and-a-half. Job records show 42 productive hours and three hours of normal idle time. Overtime arose from general workload.

  1. Pay all attendance hours at basic rate: 45 × $20 = $900.
  2. Add the premium: five hours × $10 = $50. Gross pay is $950.
  3. Charge productive basic pay to jobs: 42 × $20 = $840.
  4. Charge normal idle pay of $60 and general overtime premium of $50 to production overhead: $110.

The $840 direct charge plus $110 overhead reconciles to $950 gross pay. Charging all 45 hours directly to jobs would hide $60 of idle time in their costs. Charging $27 or $30 per overtime hour and then adding a separate premium would count the premium twice.

Include the employer's extra costs

The employer can also pay payroll taxes, pension contributions and benefits on top of gross pay. These costs form part of employing staff. One approach builds them into the hourly job rate: $20 plus 12% gives $22.40 per hour. Another collects them in production overhead. Use the chosen approach consistently so the cost is neither omitted nor counted in both places.

A payroll analysis separates direct job labor, indirect production labor and non-production labor. Its total reconciles to total payroll cost. The records therefore serve two checks: hours agree with attendance, and amounts agree with pay. An accurate gross-pay total alone cannot show whether the right jobs received the cost.

Key Takeaways

  • Reconcile job hours, indirect work and idle time to attendance.
  • Basic pay for productive hours goes to jobs; normal idle time enters production overhead.
  • The cause of overtime determines whether its premium is overhead or a direct job cost.
  • Include employer costs through a loaded job rate or overhead, without double counting.
3

Share production overhead among cost centers

Indirect production costs need a route to the jobs that benefit from them. First collect whole costs in the departments that incur them and share common costs on measured bases. Then move service department costs into production departments, allowing for the support they give each other. Each stage preserves the factory total while changing where the cost is held.

3.1 Allocate and apportion overhead to cost centers

Factory rent, machine depreciation and indirect pay support many jobs. Production overhead collects these indirect production costs. A cost center is a department, location or machine where costs are gathered. A cost unit is the output ultimately costed, such as a job or batch.

Decide whether a whole cost belongs to one center

Allocation assigns an entire overhead to the center that incurred it. A maintenance supervisor's pay belongs to Maintenance. Apportionment shares a common overhead among the centers that benefit. Factory rent serves several departments and needs a sharing basis.

Production centers work on jobs; service centers support the production work. Both belong in the first overhead analysis. Maintenance and Stores use space, employ staff and incur costs even though jobs do not pass through them.

Shared overheadUseful basis
Rent, building insurance and lightingFloor area
HeatingFloor area or heated volume
Machine depreciation and insuranceMachinery cost or carrying value
PowerKilowatt-hours or machine hours
Canteen and personnel servicesNumber of employees

Choose a basis that reflects use or benefit and can be measured. Equal shares are unsuitable when departments clearly consume unequal amounts.

Build an overhead analysis statement

Give each overhead a row and each center a column. Begin with direct allocations. Machining, Assembly, Maintenance and Stores receive indirect materials of $8,000, $5,000, $3,000 and $2,000, and indirect labor of $12,000, $9,000, $14,000 and $7,000.

Now share $60,000 rent, heating and lighting over floor areas of 4,000, 3,000, 2,000 and 1,000 square feet. Total area is 10,000 square feet, so each square foot receives $6. The shares are $24,000, $18,000, $12,000 and $6,000. Leaving service departments out of the denominator would overcharge production departments.

Machinery values are $300,000, $100,000, $50,000 and zero. Divide $36,000 depreciation and insurance by the $450,000 machinery value. The rate is 8 cents per dollar of machinery, giving $24,000, $8,000, $4,000 and zero.

Finally, share $14,000 supervision and canteen cost across 70 employees. The $200 per employee rate gives $4,000, $6,000, $2,000 and $2,000 for departments with 20, 30, 10 and 10 staff.

CenterInitial overhead total
Machining$72,000
Assembly$46,000
Maintenance$35,000
Stores$17,000
Total$170,000
Check both directions

Each shared-cost row must add back to its original cost. The department columns together must add to the full $170,000. These row and column checks catch omitted departments, wrong denominators and arithmetic slips. Service costs remain in their own columns at this stage; they will move to production centers during reapportionment. General administration and selling costs stay outside this production-overhead analysis.

Key Takeaways

  • Allocate whole overheads to their identifiable center.
  • Apportion shared overheads using a measured basis that reflects benefit.
  • Include production and service centers in the initial analysis.
  • Check each cost row and the total of all center columns.

3.2 Reapportion service cost center costs

Service centers support production but do not hold the jobs being costed. Reapportionment moves their overhead into production centers before job rates are calculated. The method matters when service centers also work for each other.

Set out the service pattern

Initial costs are $72,000 for Machining, $46,000 for Assembly, $35,000 for Maintenance and $17,000 for Stores. Maintenance supplies 50% of its service to Machining, 30% to Assembly and 20% to Stores. Stores supplies 40%, 40% and 20% to Machining, Assembly and Maintenance.

A service basis can be maintenance hours, stores requisitions, employee numbers or measured percentages. It describes who receives the service, not who originally incurred the overhead.

Use the direct method

Ignore services exchanged between service centers and rescale the remaining production shares. Maintenance's 50:30 becomes 5:3, so Machining receives $21,875 and Assembly $13,125. Stores' 40:40 becomes equal shares of $8,500. The final production totals are $102,375 and $67,625.

Using only 50% and 30% of Maintenance's original cost would leave $7,000 undistributed. Rescaling assigns its entire $35,000.

Use the step-down method

Close one service center at a time. Here Maintenance is closed first, sending $17,500 to Machining, $10,500 to Assembly and $7,000 to Stores. Stores now holds $24,000, including the amount received.

Close Stores next. Do not send anything back to closed Maintenance. Rescale Stores' two remaining 40% shares and send $12,000 to each production center. Final totals are $101,500 and $68,500. The order affects the split; follow a specified order. A common choice closes the center providing the larger value of service to other service centers first.

Recognize all mutual service

The reciprocal method allows service costs to pass both ways. Let m and s be the full Maintenance and Stores costs, including services received:

m=35,000+0.2s,s=17,000+0.2m

Substitute the second equation into the first:

m=35,000+0.2(17,000+0.2m)=38,400+0.04m

Thus 0.96m=38,400, so Maintenance totals $40,000. Stores totals $25,000. Machining receives 50% of $40,000 plus 40% of $25,000: $30,000. Assembly receives $12,000 plus $10,000: $22,000. Adding their initial costs gives $102,000 and $68,000.

The service totals include internal exchanges. Their $65,000 sum is not extra factory spending: only $52,000 reaches production, equal to the original service costs.

Repeated distribution reaches the same reciprocal result by passing balances back and forth. Distribute Maintenance's $35,000, then Stores' updated $24,000, then the $4,800 returned to Maintenance, then the $960 returned to Stores. Continue until the residue is negligible and distribute that residue to production.

MethodService exchanged recognizedMachiningAssembly
DirectNone$102,375$67,625
Step-downPart$101,500$68,500
ReciprocalAll$102,000$68,000

The changed split affects departmental rates and the costs of jobs using those departments.

Key Takeaways

  • Reapportion service costs before calculating production-center absorption rates.
  • The direct method rescales shares after excluding other service centers.
  • Step-down includes costs received from earlier centers and never reopens a closed center.
  • Reciprocal equations include the services received from the other service center.
  • Repeated distribution approaches the algebraic reciprocal result.
  • Total factory overhead stays unchanged under every method.
4

Absorb overhead into jobs with predetermined rates

A job can be priced before the factory knows its actual annual overhead. Budgeted rates supply a consistent charge for the machine time, labor time or other activity the job consumes. The later comparison with actual spending reveals the amount under- or over-absorbed. Understanding its cause helps distinguish a rate that needs revision from the period cost of idle capacity.

4.1 Calculate and apply predetermined overhead rates

Overhead absorption charges production overhead to jobs through a rate. It is also called application or recovery. A predetermined rate is set before the period, so a business can cost work and prepare quotations before actual annual costs are known.

Calculate a rate with matching units
Predetermined rate=budgeted overheadbudgeted activity

Use each production center's overhead after service reapportionment. Machining's $102,000 over 8,500 machine hours gives $12 per machine hour. Assembly's $68,000 over 4,000 direct labor hours gives $17 per direct labor hour. Keep the unit beside the rate: it tells you what quantity to multiply later.

Production patternSuitable absorption basis
Machine-intensive workMachine hours
Labor-intensive workDirect labor hours
Identical output unitsUnits produced
A cost-based approachDirect labor cost, materials cost or prime cost

A percentage rate needs a cost denominator. If Assembly's direct labor cost budget is $85,000, its rate is 80% of direct labor cost. Do not treat 80% as $80 per hour. A labor-cost basis can charge different overhead to equally time-consuming jobs merely because workers' wage rates differ.

Set activity at normal capacity

Normal capacity is average activity expected across several periods, allowing for ordinary maintenance, breaks and seasonal changes. Theoretical maximum capacity includes time that will not actually be worked. Using it makes the denominator too large and the rate too low.

An unusually quiet year creates the reverse problem: dividing fixed overhead by too few hours overcharges each job. A normal-capacity rate avoids forcing the whole cost of idle capacity onto the few jobs completed. Annual budgets also reduce seasonal swings that would arise from calculating a fresh actual rate every month.

Apply the rate to the job's activity
Job overhead=job activity×predetermined rate

Job 247 uses 25 machine hours in Machining and 40 direct labor hours in Assembly. It absorbs $300 plus $680, or $980. Completed-job costing uses the hours actually consumed; a quotation uses estimated hours. The budgeted department hours set the rate but are not the hours charged to one job.

Compare a factory-wide rate with department rates

A blanket rate uses one factory-wide basis. Total overhead of $170,000 divided by 6,800 direct labor hours gives $25 per hour.

Job A uses 30 machine hours, two Machining labor hours and ten Assembly labor hours. Departmental rates charge $360 + $170 = $530; the blanket rate charges 12 labor hours × $25 = $300. Job B uses two machine hours, one Machining labor hour and 20 Assembly labor hours. Departmental overhead is $24 + $340 = $364; blanket overhead is $525.

One labor-based rate undercosts the machine-heavy job and overcosts the labor-heavy one. A blanket rate works when there is one center or jobs use centers in similar proportions. Departmental rates reflect different production patterns. Separate fixed and variable overhead rates can also be calculated from the budget and applied to their matching bases.

Key Takeaways

  • Predetermined rates divide budgeted overhead by budgeted activity.
  • Normal capacity allows for routine lost time and seasonal changes.
  • Apply each rate to the matching job activity, using actual hours for completed work.
  • A percentage-of-cost rate needs a cost base, not hours.
  • Departmental rates improve costing when jobs use unlike centers in different proportions.

4.2 Calculate and account for under- and over-absorbed overhead

The overhead charged to jobs is based on a budgeted rate. The factory's actual bills can differ from that charge. At period-end, compare absorbed overhead with actual overhead incurred to find the balance that remains unassigned or overcharged.

Calculate the difference

Machining incurs $98,400 and works 8,000 machine hours at $12 per hour. It absorbs $96,000, which is $2,400 less than actual cost: under-absorbed, also called underapplied or under-recovered overhead.

Assembly incurs $70,500 and works 4,300 labor hours at $17. It absorbs $73,100, which is $2,600 more than actual cost: over-absorbed overhead. Across the factory, the $2,600 excess offsets the $2,400 shortage, leaving $200 over-absorbed.

Do not compare absorption with the overhead budget to name the final difference. The budget was used to set the rate; actual cost is the amount that needs recovery.

Explain spending and activity effects

For fixed overhead, spending and activity can push in opposite directions. Machining's budget was $102,000 at 8,500 hours. Spending $98,400 saves $3,600, tending toward over-absorption. Working 500 fewer hours absorbs $6,000 less, tending toward under-absorption. The $6,000 activity shortfall less the $3,600 saving explains the $2,400 under-absorption.

Assembly spends $2,500 above its $68,000 budget but works 300 hours above budget, absorbing an extra $5,100. The activity effect exceeds overspending by $2,600. This spending-and-activity comparison holds the overhead budget fixed; variable overhead also changes with activity.

Close the overhead control account

The production overhead control account records actual overhead as debits and absorbed overhead as credits. A debit balance means actual cost exceeds absorption. A credit balance means absorption exceeds actual cost.

If the balance is closed to cost of goods sold, under-absorption increases that expense and lowers profit. Over-absorption reduces the expense and raises profit. In double-entry terms, close an underapplied balance by debiting cost of goods sold and crediting overhead control; reverse those entries for an overapplied balance.

A small difference is commonly closed this way. A material US adjustment may be shared across work in process, finished goods and cost of goods sold using the applied overhead remaining in each. For $5,000 underapplied and shares of 10%, 30% and 60%, add $500, $1,500 and $3,000 to those accounts. Only the cost-of-goods-sold share immediately reduces profit.

Investigate before changing prices

Under-absorption can arise because spending exceeded the budget, because a rate used unattainable activity, or because activity temporarily fell below normal capacity. These causes lead to different decisions. A temporary production shortfall does not make the normal-capacity charge on each job wrong: unallocated idle-capacity overhead is a period expense. Persistent spending changes may require a revised future rate.

Over-absorption also needs investigation. A persistently excessive rate can make quotations uncompetitive. The period adjustment normally closes the overall account; it does not require rewriting every completed job cost sheet.

Key Takeaways

  • Under-absorption means actual overhead exceeds absorbed overhead; over-absorption means the reverse.
  • Compute absorption with actual activity at the predetermined rate.
  • Fixed-overhead spending and activity effects can offset one another.
  • Closing an underapplied balance to cost of goods sold reduces profit.
  • A material US difference may be prorated using applied overhead in the affected accounts.
  • Temporary idle capacity is a period cost, not a reason to inflate job charges.
5

Cost and price jobs and batches

A cost sheet combines traceable job costs with the overhead charges developed from department budgets. Its subtotals serve different purposes: production cost supports inventory, while total cost supports pricing. Extend that structure to batches and services, distinguish markup from margin, and follow production costs through unfinished work, completed goods and the expense recorded when jobs are delivered.

5.1 Prepare a job cost sheet

A custom kitchen, a repair or a consulting assignment has its own requirements and costs. Job costing treats each order as a separate cost unit. Give it a job number, then collect direct costs and its share of overhead on a job cost sheet, also called a job cost card or statement.

Build the cost in layers
SubtotalWhat it contains
Prime costDirect materials + direct labor + direct expenses
Total production costPrime cost + absorbed production overhead
Total cost for pricingProduction cost + non-production overhead
Selling priceTotal cost + profit

Direct expenses belong only to that job, such as subcontracted heat treatment, special equipment hire or design work. An invoice supplies that charge. Materials requisitions less returns supply direct material cost. Approved time sheets supply productive job hours multiplied by the labor rate. Absorption rates supply production overhead.

Prepare Job 247's sheet

Materials requisitioned cost $3,600, with $200 returned to stores. The job therefore uses $3,400 of direct materials.

Machining labor takes 12 hours at $20, costing $240. Assembly labor takes 40 hours at $18, costing $720. Total direct labor is $960. Add $300 subcontracted heat treatment:

Prime cost=3,400+960+300=4,660

The job uses 25 machine hours at $12 and 40 Assembly labor hours at $17. Production overhead is $300 + $680 = $980. Machine hours and labor hours are different measures; the 12 Machining labor hours do not replace the 25 machine hours in absorption.

Production cost=4,660+980=5,640

Administration, selling and distribution overhead is added at 20% of production cost: $1,128. Total cost for pricing is $6,768. The percentage base matters: applying 20% to prime cost would give a different and incorrect charge here.

Add non-production costs for pricing

A business can set the percentage from its budget. Budgeted non-production overhead of $90,000 divided by $450,000 production cost gives 20%. The added charge helps a quotation recover costs outside the factory. It does not turn selling and general administration costs into inventory.

Keep overhead classification consistent. Indirect materials already included in the production rate are not added again as direct job materials. General overtime premium and normal idle pay also enter overhead, so charging them separately to a job would count the wrong costs there.

Apply job costing to services and reconcile the records

Service jobs may use little material. An accounting assignment taking 30 staff hours at $40 costs $1,200 in direct labor. At $25 overhead per staff hour it absorbs $750, giving $1,950 before profit.

Unfinished job sheets support the work in process account. Add their production-cost subtotals, not their pricing totals or selling prices, to reconcile work in process. Completed unsold jobs support finished goods on the same production-cost basis. Job numbers and authorized records let the accountant trace a ledger difference back to the materials, time or overhead charge that caused it.

Key Takeaways

  • Prime cost combines direct materials, direct labor and direct expenses.
  • Production cost adds absorbed production overhead.
  • Non-production overhead is added for pricing and excluded from inventory.
  • Returns reduce materials charged to the job.
  • Unfinished jobs reconcile to work in process at production cost.

5.2 Set selling prices and quotations with markups and margins

A cost-plus price starts with total cost and adds profit. The percentage can be based on cost or on selling price. The amount used as the denominator determines whether the instruction is a markup or a margin.

Add a markup to cost

A markup expresses profit as a percentage of cost:

Price=cost×(1+markup)

Job 247 costs $6,768. A 25% markup gives $1,692 profit and an $8,460 price. That profit is 20% of the selling price because $1,692 divided by $8,460 is 0.20. A 25% markup therefore does not earn a 25% margin.

Work backward from a margin

A margin expresses profit as a percentage of selling price. A 25% margin leaves cost as 75% of price:

Price=cost1−margin

For the same $6,768 cost, divide by 0.75 to get $9,024. Profit is $2,256. Checking $2,256 divided by $9,024 confirms a 25% margin.

Pricing instructionPriceProfit
25% markup on $6,768$8,460$1,692
25% margin on selling price$9,024$2,256

Convert percentages using their decimal values:

Margin=markup1+markup,markup=margin1−margin

A 50% markup gives a 33⅓% margin. A 25% margin requires a 33⅓% markup. The profit amount is the same in either description, but its share of cost is larger because cost is the smaller denominator.

Build a quotation before work begins

A quotation uses estimated materials, labor hours and machine hours at current prices and predetermined rates. Add non-production overhead on its stated base, then add profit on total cost. Once a quote is accepted, an underestimate can reduce the profit available on that order.

Suppose Job 247 is accepted at $8,460, but actual total cost becomes $7,200. Profit falls to $1,260, about 14.9% of selling price. The business cannot restore the original profit merely by recording the planned markup again. Compare actual quantities, prices and hours with the estimate to improve future quotations.

Keep sales tax separate and test commercial sense

For an illustrative 10% sales tax, the $8,460 price becomes a $9,306 invoice total. Tax collected for the government is neither job profit nor part of the tax-exclusive selling price. Calculate the profit first, then add the tax when a tax-inclusive quotation is needed.

At budgeted activity, predetermined rates recover budgeted overhead. Full recovery of actual spending still depends on absorbed overhead covering the actual cost. A cost-plus calculation also needs a market check: customers may not accept the proposed price. Compare the quote with competitors and customer demand before treating the calculated profit as achievable.

Key Takeaways

  • Markup measures profit against cost; margin measures it against selling price.
  • For a margin, divide cost by one minus the margin.
  • Quotations use estimated activity and current input costs.
  • Compare actual total cost with the accepted price to find actual profit.
  • Add sales tax after profit and exclude it from job earnings.

5.3 Cost batches and units of service

A batch groups identical items produced together, such as a printing run or a set of components. Batch costing collects the group's cost like one job, then divides it among the good units. A continuing service instead uses the total cost and output of a period.

Cost the batch before dividing

Batch 12 starts 410 garden chairs. Ten rejects are a normal production loss, leaving 400 good chairs. Its direct materials cost $6,200; 120 labor hours at $18 cost $2,160; setup costs $440; and 80 machine hours at $12 absorb $960 of overhead.

Batch cost=6,200+2,160+440+960=9,760 Cost per good chair=9,760400=24.40

Dividing by all 410 chairs started would spread costs over units that cannot be sold. Normal rejects are borne by the good output. The unit cost is a share of the batch total, not a new overhead charge.

With a 30% markup on this cost base, each chair sells for $31.72. The 400-chair batch sells for $12,688. If a pricing instruction also calls for non-production costs, include those in the specified base before adding profit.

Spread setup across the units

A setup prepares equipment once for the batch. A $440 setup costs $1.10 per unit across 400 chairs and $0.55 across 800. Larger batches reduce setup cost per unit but increase average inventory and holding costs. Doubling batch size does not halve materials or labor per unit when those inputs still vary with output.

Choose a unit that measures the service

A delivery firm, bus company, hospital or hotel can collect period costs in an operating cost statement. Divide total cost by the service units delivered. Some useful units combine two dimensions:

ServiceComposite cost unit
Freight transportTonne-kilometer
Passenger transportPassenger-kilometer
Hospital carePatient-day
Hotel accommodationRoom-night

A composite unit reflects both the amount served and the duration or distance. A 12-tonne load carried 150 kilometers produces 1,800 tonne-kilometers. Adding 12 and 150 gives no meaningful service output.

Prepare and use a service rate

A delivery firm's annual costs are drivers' pay $180,000, fuel $96,000, depreciation $60,000, insurance and licenses $24,000, maintenance $30,000 and administration $50,000. Total operating cost is $440,000. For 2,000,000 tonne-kilometers:

Cost per tonne-kilometer=440,0002,000,000=0.22

At a 25% markup, the charge is $0.275 per tonne-kilometer. Carry that precision into the trip calculation. The 1,800 tonne-kilometer delivery costs $396 and is charged at $495. Rounding the rate to $0.28 first would change the charge.

Use job costing for distinct customer orders, batch costing for groups made together and service costing for repeated service output. The chosen unit must fit both the cost total and the output period used in the calculation.

Key Takeaways

  • Divide total batch cost by good units when normal rejects are borne by good output.
  • Setup occurs once per batch, so its cost per unit falls as batch size rises.
  • Service unit cost divides period operating cost by period service output.
  • Composite units multiply linked measures such as load and distance.
  • Keep sufficient rate precision until the final charge is calculated.

5.4 Track job costs through the accounts

A job cost sheet supplies detail; control accounts collect the same production costs in the general ledger. Costs move from materials into unfinished work, then completed goods and finally cost of goods sold. The sale itself is recorded separately at selling price.

Follow the production flow

For a transfer, debit the account receiving the cost and credit the account giving it up. Direct materials issued move from materials inventory to work in process. Indirect materials move to production overhead control. Direct labor and direct expenses enter work in process; indirect production labor enters overhead control.

Actual overhead is debited to overhead control. Absorbed overhead is credited there and debited to work in process at the predetermined rate. Work in process holds the applied share, not all the actual overhead bills.

When a job is completed, its production cost moves to finished goods. When delivered to the customer, the cost moves to cost of goods sold. General administration and selling expenses enter the income statement directly. Their pricing charges and profit on job sheets do not enter inventory.

Reconcile a month's unfinished work

Opening work in process is $10,000. During the month, direct materials issued are $42,000 and direct labor is $30,000. There are no separate direct expenses. Overhead is applied at $15 per direct labor hour for 2,300 hours, adding $34,500. Completed jobs costing $95,000 leave work in process.

Closing WIP=10,000+42,000+30,000+34,500−95,000=21,500

The unfinished job sheets must total $21,500 at production cost. Cost of goods manufactured is the completed-job transfer:

Completed cost=opening WIP+production costs added−closing WIP

Here $116,500 available less $21,500 unfinished equals $95,000 completed. Production costs added include direct expenses whenever a job incurs them.

Reconcile completed goods and overhead

Opening finished goods is $5,000. Add the $95,000 completed and deduct $80,000 cost of jobs delivered, leaving $20,000 finished goods. Delivered jobs leave at their production cost, even if their selling price is much higher.

Actual overhead consists of $3,000 indirect materials, $8,000 indirect labor and $25,000 other factory costs, totaling $36,000. The control account has $36,000 of debits and $34,500 of credits, leaving $1,500 underapplied. Closing it to cost of goods sold raises the expense from $80,000 to $81,500 and clears the overhead account.

Trace a difference to its source

A missing materials return overstates both the job and work in process if the job is unfinished. A completed job left in work in process makes that account too high and finished goods too low. Charging actual overhead to work in process while also applying the rate counts overhead twice. Reconcile the production-cost subtotals to the ledger and use source documents to locate the charge or transfer that failed.

Key Takeaways

  • Direct costs and applied production overhead enter work in process.
  • Actual overhead enters overhead control; applied overhead leaves it for work in process.
  • Completed jobs move to finished goods and delivered jobs to cost of goods sold at production cost.
  • Cost of goods manufactured is the production cost of completed jobs.
  • Job sheets reconcile to inventory without non-production charges or profit.
  • Close or allocate the overhead control balance at period-end.

Job Costing examples

5 Walkthroughs

1

Control materials and price their issues

18 steps
Follow purchasing controls, calculate inventory levels and EOQ, and work through FIFO and weighted average issues.
  1. 1
    IntroductionFollow a material from purchase to job

    A material has two trails: where the physical units go and where their cost goes. A job can be delayed by a missing delivery or mispriced by a missing return.

    Follow the documents first (order, receipt and invoice must match), then decide when and how much to order (the reorder level and EOQ), and finally price issues to jobs with FIFO and AVCO. The checks work together: quantities protect availability, while values support job costs.

  2. 2
    ExplanationAuthorize the purchase and verify receipt

    A purchase requisition asks Purchasing to buy materials. The purchase order goes to the supplier with the agreed quantity, price and delivery terms.

    When the goods arrive, receiving staff count and inspect them and prepare a goods received note. The supplier's delivery note accompanies the goods; the buyer's receipt record states what actually arrived.

  3. 3
    Key InsightMatch before payment

    Compare the supplier invoice with the purchase order and goods received note. The order proves what was authorized; the receipt record proves what arrived.

    If an order and invoice both show 100 units but the receipt shows 90, the agreement between order and invoice is insufficient. Investigate the missing ten units before approving payment.

  4. 4
    ExplanationTrack issues, returns and transfers

    An authorized materials requisition identifies the item, quantity and job charged when materials leave stores. A return note reduces the original job charge when unused materials come back. A transfer note moves the charge to another job.

    Direct materials enter the identified job. Indirect supplies enter production overhead. A job number and supervisor approval make the movement traceable.

  5. 5
    ChallengeFind the missing receipt evidence

    Purchasing ordered 80 panels. The invoice charges for 80, but receiving staff found only 76. What record establishes the quantity actually received, and why is the order insufficient?

    ---reveal---

    The goods received note establishes actual receipt. The purchase order shows the authorized purchase, so it cannot establish that the four missing panels arrived.

  6. 6
    TipCheck inventory without stopping every day

    A bin card tracks quantities at the storage location; a stores ledger card also tracks unit costs and values. Perpetual records update each receipt and issue. A physical count still checks whether records match reality.

    Continuous stocktaking spreads counts through the year. JIT reduces the amount stored, but reliable suppliers and quality become essential because little buffer remains.

  7. 7
    ExampleTrigger the order before stock runs out

    Daily usage reaches 120 units and lead time reaches six days. Set the reorder level from those maxima:

    120×6=720 units

    Place an order when inventory falls to 720. This covers the longest lead time at the highest usage. Using average usage and lead time would remove that protection.

  8. 8
    ExampleSeparate the buffer from the delivery size

    Average usage is 100 units daily and average lead time five days. Expected usage while waiting is 500 units, leaving a minimum level of 220 from the 720-unit trigger.

    With a 1,000-unit order, minimum usage of 80 and minimum lead time four days, maximum inventory is:

    720+1,000−80×4=1,400 units
  9. 9
    ExplanationBalance fewer orders against more storage

    Larger orders reduce the number of orders placed but increase average inventory. EOQ finds the basic model's least-cost order size:

    EOQ=2CoDCh

    Use annual demand for D, cost per order for Co and annual holding cost per unit for Ch. Convert a percentage holding charge to money before substituting.

  10. 10
    ExampleCalculate and check the EOQ

    Demand is 10,000 units annually, ordering costs $50 per order and holding costs $4 per unit per year. The formula gives an EOQ of 500 units.

    That means 20 orders costing $1,000. Average cycle inventory is 250 units, also costing $1,000 annually. Equal basic ordering and holding costs check this result. A fixed buffer adds holding cost without changing the EOQ.

  11. 11
    ExampleCheck whether a discount pays

    At a $20 unit price, 500-unit orders cost $202,000 annually including purchases, ordering and holding. A 1% price reduction for 1,000-unit orders changes those costs to $198,000, $500 and $2,000: $200,500 total.

    The larger order saves $1,500 despite extra holding cost. The lowest purchase price alone cannot show whether a discount is worthwhile.

  12. 12
    ChallengeChoose the right time units

    Demand is stated as 900 units per month, while holding cost is $3 per unit per year. What demand figure belongs in an annual EOQ calculation, and why?

    ---reveal---

    Use 10,800 units per year. Multiplying monthly demand by 12 puts demand and holding cost on the same annual basis; using 900 with an annual holding cost would understate the order size.

  13. 13
    ExamplePrice the oldest layers first

    Opening inventory is 200 units at $5. Receive 300 at $6, then issue 400. FIFO uses all 200 oldest units and 200 from the newer layer:

    200×5+200×6=2,200

    The issue costs $2,200 and leaves 100 units at $6. FIFO describes which costs are assigned; physical materials can leave stores in a different order.

  14. 14
    ExampleUpdate the moving average

    For the same first receipt, perpetual AVCO divides $2,800 by 500 units, giving $5.60 each. Issuing 400 costs $2,240 and leaves 100 units worth $560.

    Receive another 500 units costing $3,160. The new average is $3,720 divided by 600, or $6.20. Keep the remaining value from the previous average when adding the new receipt.

  15. 15
    ConnectionUse the average until the next receipt

    At $6.20 per unit, issuing 350 units costs $2,170 and leaves 250 worth $1,550. The issue reduces value and quantity in the same proportion, so it does not change the average.

    Periodic AVCO instead divides the whole period's $5,960 by 1,000 available units. Its single $5.96 average gives total issues of $4,470 and closing inventory of $1,490.

  16. 16
    TipKeep returns tied to their original charge

    A return from a job reverses the price originally charged to that job. Add that quantity and value back to stores and recalculate a perpetual average. A supplier return removes the original purchase price.

    FIFO leaves recent purchase layers in closing inventory. LIFO issues recent layers first; external reporting permits LIFO under US GAAP but prohibits it under IFRS.

  17. 17
    ChallengeCheck a cost trail and a return

    Opening inventory and receipts cost $4,800. Issues total $3,500. A job then returns $120 of those materials. What are net issues and closing inventory after the return?

    ---reveal---

    Net issues fall to $3,380 and closing inventory rises to $1,420. The total remains $4,800. The return moves an existing cost back to stores; it does not create another purchase.

  18. 18
    RecapConnect control with cost

    A reliable material charge needs an authorized movement, enough physical inventory and a consistent pricing method. Invoice matching checks purchases; issue and return records identify the job; stocktaking checks the recorded balance.

    Inventory levels and EOQ support supply decisions. FIFO and AVCO divide purchase value between issues and the balance left. Reconcile both quantities and value when a difference appears.

2

Calculate earnings and assign labor costs

13 steps
Calculate time, piecework and bonus pay, then reconcile direct labor and overhead to payroll.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionCalculate pay, then trace its cost
  2. 2
    ExplanationKeep gross earnings separate from take-home pay
  3. 3
    ExampleSplit overtime pay into two parts
  4. 4
    ExplanationApply the piecework floor and threshold
  5. 5
    ExampleCalculate the Halsey bonus
  6. 6
    ExampleCalculate the Rowan bonus
  7. 7
    ChallengeInterpret a differential scheme
  8. 8
    ExplanationMatch hours to the work done
  9. 9
    Key InsightFollow the cause of the premium
  10. 10
    ExampleReconcile a worker’s week
  11. 11
    ChallengeFind the direct and indirect shares
  12. 12
    TipInclude costs paid by the employer
  13. 13
    RecapUse pay records to support job charges
3

Analyze and reapportion factory overhead

15 steps
Build department totals and compare direct, step-down and reciprocal service-cost distributions.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionMove shared factory costs toward jobs
  2. 2
    ExplanationDistinguish where costs collect from what is costed
  3. 3
    ExplanationAssign whole costs before sharing common costs
  4. 4
    ExampleApportion the premises cost
  5. 5
    ExampleAdd the other analysis rows
  6. 6
    ChallengeShare a new building cost
  7. 7
    ExplanationWrite the service pattern before distributing
  8. 8
    ExampleRescale the direct-method shares
  9. 9
    ExampleClose Maintenance first under step-down
  10. 10
    ExampleFinish the step-down distribution
  11. 11
    ExplanationSet up reciprocal service equations
  12. 12
    ExampleSolve and distribute the full totals
  13. 13
    ConnectionReach the same result by repeated distribution
  14. 14
    ChallengeCheck the total after mutual service
  15. 15
    RecapPreserve the total while changing its destination
4

Apply overhead and explain the balance

13 steps
Choose and apply predetermined rates, then explain and close under- or over-absorbed overhead.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionCharge jobs before the final bills arrive
  2. 2
    ExampleDivide the budget by its matching activity
  3. 3
    ExplanationChoose a base and a normal activity level
  4. 4
    ExampleApply each rate to the right job hours
  5. 5
    Key InsightSee what a blanket rate can hide
  6. 6
    ChallengeCalculate one job’s overhead
  7. 7
    ExampleCompare application with actual overhead
  8. 8
    ExampleSeparate saving from lost absorption
  9. 9
    ExplanationRead and close the control balance
  10. 10
    ConnectionAllocate a material adjustment
  11. 11
    ChallengeExplain a net balance from two causes
  12. 12
    TipInvestigate before changing the next quote
  13. 13
    RecapKeep the three amounts distinct
5

Cost and price work, then track the accounts

19 steps
Prepare job and batch costs, distinguish markup from margin, cost services and reconcile production accounts.

Save this lesson to follow every Walkthrough step by step.

  1. 1
    IntroductionBuild a cost, set a price and follow the work
  2. 2
    ExampleBuild prime cost from source records
  3. 3
    ExampleAdd production overhead, then other costs
  4. 4
    ChallengeChoose the inventory subtotal
  5. 5
    ExampleAdd profit on the cost base
  6. 6
    ExampleRecover price from a required margin
  7. 7
    ChallengeTest the denominator
  8. 8
    ConnectionReview the accepted quote against actual costs
  9. 9
    ExampleCost the good output of a batch
  10. 10
    Key InsightSpread setup without losing its full cost
  11. 11
    ExampleMeasure continuing service output
  12. 12
    ChallengeCompare a batch with normal rejects
  13. 13
    ExplanationSend actual and applied overhead to different places
  14. 14
    ExampleTransfer completed and delivered jobs at cost
  15. 15
    ExampleReconcile unfinished work
  16. 16
    ExampleClose the overhead difference
  17. 17
    ChallengeComplete the account flow
  18. 18
    ChallengeConnect the sheet, inventory and profit
  19. 19
    RecapMatch each total to its purpose

Job Costing practice questions

60 Practice Questions in 6 sets

Set 1: Materials control, order sizes and issue pricing10 Practice Questions

Question 1 of 10

A job returns $84 of unused materials to stores. What adjustment is needed on its cost sheet?
  1. Increase direct materials by $84.
  2. Reduce production overhead by $84.
  3. Reduce direct materials by $84.
  4. Increase direct expenses by $84.
Show answerHide answer
Answer: C
The return reverses $84 of material cost originally charged to the job, so direct materials falls by that amount. Reducing overhead would leave the job’s direct materials overstated; the returned item was charged to the job itself, not to the shared overhead pool.

Question 2 of 10

A supplier invoice and purchase order both show 240 brackets. The receiving record shows 228. What should the payment clerk do?
  1. Approve payment because invoice and order quantities agree.
  2. Resolve the 12-unit shortfall before approving payment.
  3. Change the receiving quantity to match the purchase order.
  4. Charge the extra 12 units to the next customer job.
Show answerHide answer
Answer: B
The receiving record shows a 12-unit difference from the invoice, so the clerk needs to resolve the shortage before payment. Agreement between invoice and purchase order checks the ordered terms but does not establish receipt. Altering the receipt record would conceal the delivery difference.

Question 3 of 10

A workshop has repeated shortages. One employee orders parts, confirms deliveries and updates inventory records; issue notes lack job numbers. What paired control change addresses both missing goods and mischarged jobs?
  1. Add more frequent supplier orders and allow verbal authorization of issues.
  2. Compare invoices only with purchase orders and post all issues to one job.
  3. Count materials annually and let the same employee approve all write-offs.
  4. Separate ordering from receipt recording and require approved job-numbered issues.
Show answerHide answer
Answer: D
Separating ordering from receipt recording makes independent checking possible, while approved job-numbered issues trace withdrawals to the right cost sheet. Annual counts alone may detect a shortage late but leave the same employee controlling the evidence and do not correct missing job identification.

Question 4 of 10

A part’s maximum usage is 75 units per day and its maximum lead time is eight days. At what inventory balance should a new order be triggered?
  1. 600 units
  2. 83 units
  3. 300 units
  4. 750 units
Show answerHide answer
Answer: A
The reorder trigger must cover eight days at the maximum 75 units per day, giving 600 units. Adding the two figures gives 83, but combines different measures without calculating the number of parts needed during the wait. The result is a balance in units, not an order count.

Question 5 of 10

Reorder level is 960 units, average usage is 140 per day and average lead time is five days. What is the minimum inventory level?
  1. 700 units
  2. 820 units
  3. 1,660 units
  4. 260 units
Show answerHide answer
Answer: D
Average lead-time use is 700 units, so the 960-unit trigger leaves a 260-unit minimum level. Reporting 700 gives the expected consumption while waiting, not the inventory buffer remaining after that consumption. Adding usage to the trigger would move in the wrong direction.

Question 6 of 10

Annual demand is 14,400 units, order cost is $45 and holding cost is $4 per unit per year. What is the basic EOQ?
  1. About 402 units
  2. About 569 units
  3. About 805 units
  4. About 32 units
Show answerHide answer
Answer: B
The EOQ is 2×45×14,400/4=324,000, about 569 units. About 402 results from omitting the factor of two. The formula balances annual ordering and holding costs; it returns units per order, not the number of orders placed.

Question 7 of 10

Annual demand is 12,000 units, price $10 each, order cost $30 and annual holding cost $2 per unit. Compare 600-unit orders with 1,200-unit orders earning a 1% discount on all units. Holding cost stays $2. What is the annual saving from the larger orders?
  1. $900
  2. $1,200
  3. $300
  4. $1,500
Show answerHide answer
Answer: A
At 600 units, annual purchases, orders and holding total $121,200. At 1,200 units they total $120,300, giving a $900 saving. The $1,200 purchase saving alone overstates the benefit because the net ordering-and-holding cost rises by $300 when the order size doubles.

Question 8 of 10

Stores hold 80 units at $9 followed by 120 units at $11. What does a 100-unit FIFO issue cost?
  1. $1,100
  2. $1,020
  3. $940
  4. $900
Show answerHide answer
Answer: C
FIFO charges the oldest 80 units at $9 and the next 20 at $11, totaling $940. Charging all 100 at $9 gives $900 but ignores that only 80 units remain in that layer. The issue must use a second purchase price once the oldest layer is exhausted.

Question 9 of 10

Stores hold 60 units worth $480. A receipt adds 140 units costing $1,400. Under perpetual AVCO, what does the next 50-unit issue cost?
  1. $500
  2. $470
  3. $400
  4. $450
Show answerHide answer
Answer: B
After the receipt, 200 units cost $1,880, making the weighted average $9.40. The 50-unit issue therefore costs $470. Averaging the $8 and $10 prices equally gives $9 and a $450 issue, but the larger receipt must receive more weight than the opening quantity.

Question 10 of 10

Opening inventory is 100 units at $4. Receive 100 at $6, issue 150, then receive 200 at $8. No other movements occur. By how much does perpetual AVCO closing value exceed periodic AVCO closing value?
  1. $150
  2. $250
  3. $225
  4. $375
Show answerHide answer
Answer: C
Periodic AVCO gives $6.50 across all 400 available units and values the remaining 250 at $1,625. Perpetual AVCO leaves $250 after the issue, then adds $1,600, giving $1,850. The difference is $225; using only the issue’s price difference would ignore the 250 units in closing inventory.
Set 2: Pay schemes, labor analysis and service departments10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A worker attends 44 hours at $25 basic pay, including four time-and-a-half overtime hours and two normal idle hours. General workload causes overtime. How much pay enters production overhead?
  1. $50
  2. $150
  3. $100
  4. $1,150
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

An urgent customer order causes six overtime hours at a $20 basic rate and time-and-a-half pay. All six hours are productive. The employer adds 10% of this gross pay to the job rate instead of overhead. What direct labor cost belongs to the job?
  1. $132
  2. $198
  3. $180
  4. $192
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Assembly alone incurs a $7,200 production supervisor salary. How should the whole amount first enter an overhead analysis?
  1. Allocate $7,200 to Assembly.
  2. Apportion $7,200 by floor area.
  3. Charge $7,200 to a single job.
  4. Reapportion $7,200 from Stores.
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Factory rent is $45,000. Cutting uses 900 square feet, Finishing 600 and Maintenance 300. What rent is apportioned to Cutting?
  1. $27,000
  2. $22,500
  3. $15,000
  4. $30,000
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A service center’s direct-method production shares are 60% to Cutting and 20% to Finishing. What fraction of its full cost goes to Cutting?
  1. 60%
  2. 80%
  3. 66⅔%
  4. 75%
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Under step-down, Maintenance distributes $18,000: 50% to Cutting, 30% to Finishing and 20% to Stores. Stores originally holds $8,400 and then shares its total equally between production centers. How much does Cutting receive from Stores?
  1. $4,200
  2. $9,000
  3. $5,040
  4. $6,000
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Service centers have full reciprocal costs m=18,000+0.1s and s=9,000+0.2m. What is the full cost of Maintenance, rounded to the nearest dollar?
  1. $19,286
  2. $18,900
  3. $19,800
  4. $21,600
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A worker makes 820 acceptable units at $0.75 each with a guaranteed minimum of $650. What is gross pay?
  1. $650
  2. $615
  3. $1,265
  4. $35
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A worker’s basic rate is $22 per hour. The standard week is 35 hours, actual attendance is 39 hours and overtime pays double time. What is gross pay?
  1. $858
  2. $902
  3. $946
  4. $1,034
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A task allows 30 hours and takes 24 at a basic rate of $15 per hour. How much more total pay does Rowan give than a 50% Halsey scheme?
  1. $45
  2. $72
  3. $18
  4. $27
Show answerHide answer

Save this lesson to see this answer.

Set 3: Overhead rates, job sheets and prices10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A department budgets $117,000 overhead for 9,000 machine hours. What is its predetermined rate?
  1. $13 per labor hour
  2. $0.077 per machine hour
  3. $117 per machine hour
  4. $13 per machine hour
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

Cutting applies $11 per machine hour and Assembly $16 per labor hour. A job uses 28 Cutting machine hours, eight Cutting labor hours and 14 Assembly labor hours. What overhead does it absorb?
  1. $396
  2. $532
  3. $756
  4. $312
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Fixed overhead is $120,000. Normal capacity is 10,000 machine hours, theoretical maximum 12,000 and this unusually quiet year’s expected activity 6,000. A job uses 40 machine hours. What charge uses normal capacity?
  1. $480
  2. $400
  3. $800
  4. $720
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

Actual overhead is $63,500 and overhead absorbed is $66,000. What is the balance?
  1. $2,500 under-absorbed
  2. $129,500 over-absorbed
  3. $2,500 over-absorbed
  4. $63,500 under-absorbed
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

Actual overhead is $91,200. The predetermined rate is $14 per labor hour and actual activity is 6,300 hours. What adjustment to profit follows if the balance is closed to cost of goods sold?
  1. Profit rises by $3,000.
  2. Profit falls by $3,000.
  3. Profit falls by $91,200.
  4. Profit rises by $88,200.
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Fixed overhead is budgeted at $144,000 for 12,000 hours. Actual spending is $147,000 and actual activity is 12,500 hours. What is the net overhead balance?
  1. $3,000 under-absorbed
  2. $6,000 over-absorbed
  3. $3,000 over-absorbed
  4. $9,000 under-absorbed
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A job has $1,850 net direct materials, $960 direct labor and a $290 direct expense. What is prime cost?
  1. $3,100
  2. $2,810
  3. $2,140
  4. $1,250
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A job requisitions $2,800 material and returns $160. Direct labor is $1,020, direct expenses $240 and applied overhead $900. Non-production overhead is 15% of production cost. What is total cost for pricing?
  1. $4,800
  2. $5,385
  3. $5,704
  4. $5,520
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Total job cost is $2,400 and profit is a 30% markup on cost. What is the tax-exclusive selling price?
  1. $3,120
  2. $3,428.57
  3. $2,472
  4. $720
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A job costs $3,360 and needs a 20% profit margin on selling price. What tax-exclusive price should be quoted?
  1. $4,032
  2. $4,200
  3. $4,480
  4. $2,688
Show answerHide answer

Save this lesson to see this answer.

Set 4: Batches, service units and account flows10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

A batch has $8,100 total cost and 450 good units. What is cost per unit?
  1. $20
  2. $18
  3. $16.20
  4. $22.50
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A batch starts 520 pieces. Twenty normal rejects leave good output for sale. Total batch cost is $11,250. What is cost per good unit?
  1. $22.50
  2. $21.63
  3. $23.40
  4. $562.50
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

A 240-unit batch costs $5,760 including one $480 setup. All other costs vary directly with good units. What is cost per unit for 480 good units with the same single setup?
  1. $24
  2. $12
  3. $22
  4. $23
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A freight service costs $315,000 for 1,500,000 tonne-kilometers. It quotes a 12-tonne delivery over 180 kilometers with a 25% markup on cost. What is the tax-exclusive charge?
  1. $453.60
  2. $604.80
  3. $567.00
  4. $540.00
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A manufacturing job is completed but has not been delivered. To which account is its production cost transferred?
  1. Cost of goods sold
  2. Production overhead control
  3. Finished goods
  4. Sales revenue
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

Opening WIP is $7,500. Direct materials, labor and expenses added total $38,000; overhead applied is $12,500. Completed jobs cost $45,000. What is closing WIP?
  1. $500
  2. $13,000
  3. $20,500
  4. $25,500
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Opening finished goods is $9,000, cost of goods manufactured is $72,000 and closing finished goods is $14,000. What is unadjusted cost of goods sold?
  1. $67,000
  2. $77,000
  3. $81,000
  4. $86,000
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

Actual factory overhead includes $2,400 indirect materials, $7,600 indirect labor and $22,000 other overhead. Applied overhead is $34,500. Unadjusted cost of goods sold is $86,000. If the balance is closed there, what is adjusted cost of goods sold?
  1. $88,500
  2. $86,000
  3. $120,500
  4. $83,500
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A tax-exclusive quote is $1,250 and an illustrative 8% sales tax is added. What is the customer’s invoice total?
  1. $1,350
  2. $1,250
  3. $1,150
  4. $1,562.50
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

A job is quoted at $7,200 including 20% markup on estimated total cost. Actual total cost is 10% above the estimate, and the tax-exclusive price stays fixed. What is actual profit margin?
  1. 10%
  2. 16⅔%
  3. 20%
  4. 8⅓%
Show answerHide answer

Save this lesson to see this answer.

Set 5: Connect material, labor, overhead and pricing decisions10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

Maximum daily usage is 55 units and maximum lead time nine days. What reorder level covers both maxima?
  1. 64 units
  2. 605 units
  3. 495 units
  4. 440 units
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

Job records show 36 productive hours and four normal idle hours at a $19 basic rate, with no overtime. Employer costs are 10% of gross pay and all enter production overhead. What total overhead arises?
  1. $76
  2. $144.40
  3. $83.60
  4. $152
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Under step-down, service center A starts at $24,000 and supplies Production X 50%, Y 25% and B 25%. Center B starts at $12,000 and, after A closes, serves X and Y in a 2:1 ratio. How much total service cost goes to Y?
  1. $12,000
  2. $10,000
  3. $18,000
  4. $14,000
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A plant-wide rate is $20 per labor hour. Departmental rates are $18 per machine hour in Cutting and $12 per labor hour in Assembly. A job uses 20 machine hours, five Cutting labor hours and ten Assembly labor hours. By how much does the blanket rate undercost overhead?
  1. $300
  2. $180
  3. $120
  4. $360
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A $7,200 underapplied overhead difference is to be prorated. Relevant applied overhead is $9,000 in WIP, $15,000 in finished goods and $36,000 in cost of goods sold. What immediate reduction in profit results?
  1. $7,200
  2. $1,800
  3. $2,880
  4. $4,320
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

An assignment takes 26 staff hours at a cost of $48 per hour and absorbs overhead at $32 per staff hour. A $150 specialist fee is direct to this assignment. What is production cost?
  1. $2,230
  2. $2,080
  3. $1,398
  4. $2,380
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

A quote uses $4,200 production cost plus non-production overhead at 10% of production cost. It needs a 30% margin and then an illustrative 5% sales tax. What is the tax-inclusive quote?
  1. $6,600
  2. $6,306.30
  3. $6,930
  4. $6,300
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A batch starts 640 units, with 40 normal rejects. Direct costs are $12,600, a separate setup costs $600 and overhead is 90 machine hours at $20. What tax-exclusive unit price gives a 20% margin on this production-cost base?
  1. $30.00
  2. $31.25
  3. $29.30
  4. $25.00
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

Opening WIP is $6,000. Materials issued are $28,000 direct and $2,000 indirect; labor is $19,000 direct and $5,000 indirect. Other actual overhead is $9,000, applied overhead $15,000 and completed jobs $52,000. What is closing WIP?
  1. $17,000
  2. $16,000
  3. $23,000
  4. $10,000
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Stores hold 150 units worth $1,050 under perpetual AVCO. A job returns 30 unused units originally issued at $6 each. What is the revised average unit cost?
  1. About $6.83
  2. $7.00
  3. $6.00
  4. $6.50
Show answerHide answer

Save this lesson to see this answer.

Set 6: Analyze reciprocal costs, capacity and full cost flows10 Practice Questions

Save this lesson to see every answer and practice every set.

Question 1 of 10

Which side of production overhead control records the overhead applied to WIP?
  1. Debit
  2. Credit
  3. Debit and credit equally
  4. Neither side
Show answerHide answer

Save this lesson to see this answer.

Question 2 of 10

A part has reorder level 840, order quantity 1,400, minimum usage 70 per day and minimum lead time four days. What is maximum inventory level?
  1. 2,240 units
  2. 560 units
  3. 1,120 units
  4. 1,960 units
Show answerHide answer

Save this lesson to see this answer.

Question 3 of 10

Maintenance starts at $26,000 and Stores at $12,000. Each supplies 20% of its service to the other, with the rest going to production. What are the full reciprocal service totals?
  1. Maintenance $28,400.00; Stores $17,200.00
  2. Maintenance $31,000.00; Stores $18,200.00
  3. Maintenance $29,583.33; Stores $17,916.67
  4. Maintenance $26,000.00; Stores $12,000.00
Show answerHide answer

Save this lesson to see this answer.

Question 4 of 10

A fixed-overhead rate uses $180,000 at normal capacity of 15,000 hours. Actual spending remains $180,000, but temporary weak demand reduces activity to 12,000 hours. What adjustment preserves the normal-capacity job charge?
  1. Expense $36,000 unallocated overhead in the period.
  2. Increase each completed job’s overhead charge by 25%.
  3. Carry the $36,000 unallocated overhead as an inventory asset.
  4. Reduce actual overhead spending in the ledger to $144,000.
Show answerHide answer

Save this lesson to see this answer.

Question 5 of 10

A worker makes 1,080 acceptable units in 45 hours. Piece pay is $0.70 for the first 1,000 and $0.90 only above that. Guaranteed time earnings are 40 hours at $17 plus five hours at time-and-a-half. The higher amount is paid. What is gross pay?
  1. $772.00
  2. $900.00
  3. $1,579.50
  4. $807.50
Show answerHide answer

Save this lesson to see this answer.

Question 6 of 10

A business quotes $5,500 before sales tax and expects total cost of $4,400. What are its markup and margin?
  1. 25% markup; 20% margin
  2. 20% markup; 25% margin
  3. 25% markup; 25% margin
  4. 20% markup; 20% margin
Show answerHide answer

Save this lesson to see this answer.

Question 7 of 10

Opening WIP is $8,000, direct materials $35,000, direct labor $27,000, direct expenses $3,000 and applied overhead $18,000. Closing WIP is $11,000. Opening finished goods is $7,000 and closing finished goods $10,000. What is unadjusted cost of goods sold?
  1. $80,000
  2. $74,000
  3. $77,000
  4. $95,000
Show answerHide answer

Save this lesson to see this answer.

Question 8 of 10

A shuttle service spends $81,000 and carries 900 passengers each over 150 kilometers. What is cost per passenger-kilometer?
  1. $90.00
  2. $0.60
  3. $540.00
  4. $0.006
Show answerHide answer

Save this lesson to see this answer.

Question 9 of 10

A center budgets $72,000 overhead and $96,000 direct labor cost and absorbs overhead as a percentage of labor cost. A job’s direct labor costs $640. What overhead is applied?
  1. $640
  2. $853.33
  3. $1,120
  4. $480
Show answerHide answer

Save this lesson to see this answer.

Question 10 of 10

Opening inventory is 120 units at $3. Receive 180 at $4, issue 200, then receive 100 at $5 and issue 80. Under perpetual AVCO, what is closing inventory value?
  1. $580
  2. $480
  3. $516
  4. $500
Show answerHide answer

Save this lesson to see this answer.

Stuck on your own question? Homework Help

Key Terms

81 Key Terms, each with its definition

A

Allocation
Allocation assigns the whole of an identifiable overhead cost to the single cost center that incurred it, without dividing it among centers.
The allocation of a maintenance supervisor's salary puts the entire amount in the Maintenance column.
Apportionment
Apportionment divides a shared overhead cost among benefiting cost centers using a measured basis that reflects their use or benefit.
Rent apportionment by floor area gives a larger charge to the department occupying more of the building.

B

Batch costing
Batch costing collects the costs of identical items made together as one group, then divides the batch total among its good output units.
A printer uses batch costing for a single run of 2,000 identical booklets ordered by a customer.
Bin card
A bin card is a record kept at an inventory storage location showing quantities received, issued and remaining for a particular item.
The storekeeper updates the bin card when 25 hinges are issued to the workshop for a customer order.
Blanket rate
A blanket rate is one factory-wide overhead absorption rate applied to all jobs using a single common activity or cost basis.
A labor-hour blanket rate may undercost an order that uses substantial machine time but little labor.
Buffer inventory
Buffer inventory is extra material held to protect production against usage above expectations or deliveries arriving later than expected.
The factory uses buffer inventory while waiting for a delivery delayed by two days beyond its usual lead time.

C

Composite cost unit
A composite cost unit combines two output measures to describe a service, such as tonne-kilometers for load carried over a distance.
A tonne-kilometer is a composite cost unit that makes an eight-tonne, 90-kilometer trip equal 720 units.
Control account
A control account is a general-ledger total supported by detailed records, such as the unfinished job sheets underlying work in process.
The WIP control account is reconciled with the production-cost subtotals on all unfinished job cost sheets.
Cost center
A cost center is a department, location, function or machine for which a business collects costs before assigning them to output.
Machining is a cost center whose factory costs are later absorbed by jobs using machine hours.
Cost of goods manufactured
Cost of goods manufactured is the production cost of jobs completed during a period and transferred from work in process to finished goods.
Cost of goods manufactured includes a job completed this month even if part of its cost arose last month.
Cost of goods sold
Cost of goods sold is the production cost transferred from finished goods for the jobs sold, with applicable period-end overhead adjustments.
Cost of goods sold increases by $1,500 when a small underapplied overhead balance is closed to that account.
Cost unit
A cost unit is the unit of product or service for which costs are measured, such as a job, a batch or a patient-day.
A print shop chooses each customer's distinct order as its cost unit when preparing job cost sheets.
Cost-plus pricing
Cost-plus pricing sets a selling price by adding a profit amount or percentage to a specified cost base for the product or service.
Cost-plus pricing still needs a market check because a calculated price may exceed what customers will pay.

D

Departmental rate
A departmental rate is an overhead absorption rate calculated for one production center using that center's budget and selected activity basis.
Assembly's departmental rate uses labor hours while Machining's rate uses machine hours for its jobs.
Differential piece rate
A differential piece rate pays different amounts per unit at specified output levels, according to the scheme's threshold rules.
A differential piece rate pays $0.90 for units above a target while earlier units still earn $0.80.
Direct labor
Direct labor is the pay for employees' productive time that can be traced to making a particular product or carrying out a particular job.
A mechanic's approved hours repairing one customer's vehicle are recorded as direct labor on that job.
Direct materials
Direct materials are physical inputs whose costs can be traced to a specific job or product without an impractical amount of work.
Timber cut for a custom cabinet is charged as direct materials on that cabinet's job cost sheet.
Direct method
The direct method distributes service-center costs only to production centers, ignoring services exchanged between the service centers.
The direct method rescales production shares of 50% and 30% into a 5:3 ratio to distribute the full cost.

E

Economic order quantity
The economic order quantity is the order size that minimizes the combined annual costs of ordering and holding inventory in the basic model.
An economic order quantity of 500 units balances annual ordering costs with cycle-inventory holding costs.

F

Finished goods
Finished goods are completed products held at production cost before their cost is transferred to cost of goods sold on delivery or sale.
Finished goods increases when the factory completes an order that has not yet been delivered to its buyer.
First in, first out
First in, first out is an inventory pricing method that charges the oldest available purchase costs to issues before using more recent costs.
Under first in, first out, a job's large issue can consume the remaining units from two purchase layers.

G

Goods received note
A goods received note is the buyer's record of the quantity and condition of goods actually received from a supplier.
A goods received note records 95 usable parts when five of a 100-part delivery arrive damaged.
Gross pay
Gross pay is the amount an employee earns before deductions for personal taxes, contributions or other amounts withheld from the employee.
An employee's gross pay stays part of labor cost even when some of it is sent directly to tax authorities.
Group bonus
A group bonus is an incentive payment shared among a team when its combined output or performance meets the pay scheme’s stated conditions.
An assembly team shares a group bonus because the finished output depends on all members working together.
Guaranteed minimum
A guaranteed minimum is a floor on earnings under a pay scheme, paid when calculated piecework earnings would be lower.
The guaranteed minimum protects a worker whose piece earnings fall during a machine breakdown.

H

Halsey bonus
A Halsey bonus pays the worker a stated share of the basic-rate value of time saved, in addition to pay for actual time taken.
A 50% Halsey bonus pays half the hourly-rate value of the ten hours saved on a production task.
Holding cost
A holding cost is the cost of carrying inventory over time, including storage, insurance, deterioration and the money tied up in materials.
The annual holding cost rises when a workshop orders large batches of parts that remain unused for months.

I

Idle time
Idle time is paid time when production workers cannot work on jobs, such as time lost while waiting for materials or a machine repair.
Three hours of normal idle time are charged to production overhead after a short machinery interruption.
Indirect labor
Indirect labor is production pay that cannot be traced to a specific job, including production support staff and normal nonproductive time.
The production supervisor's indirect labor cost is collected with other factory overhead for absorption.
Indirect materials
Indirect materials are production supplies whose costs are collected in overhead because tracing them to individual jobs is impractical.
Machine oil used across many orders is treated as indirect materials in the factory overhead budget.

J

Job cost sheet
A job cost sheet is the detailed record of a job's direct materials, direct labor, direct expenses and absorbed overhead, with cost subtotals.
The accountant deducts returned timber from the job cost sheet for a cabinet before calculating that cabinet's prime cost.
Job costing
Job costing collects direct costs and applied overhead separately for each distinct customer order, project or assignment treated as a cost unit.
A custom kitchen maker uses job costing because each customer's design uses different materials and time.
Just-in-time purchasing
Just-in-time purchasing arranges material deliveries close to the time of use to reduce the inventory held and its associated costs.
A furniture maker uses just-in-time purchasing for bulky boards when suppliers can deliver reliably.

L

Last in, first out
Last in, first out is an inventory pricing method that assigns the most recently acquired cost layers to material issues before older layers.
Last in, first out can leave old purchase prices in closing inventory after newer units are issued.
Lead time
Lead time is the interval between placing an order for materials and receiving those materials so they can be used in production.
A supplier's six-day lead time means the factory needs enough material to cover usage during that wait.

M

Margin
A margin is profit expressed as a percentage of selling price, leaving the rest of that price to cover the associated total cost.
A 20% margin on a $500 selling price means $100 profit and $400 total cost for the completed job.
Markup
A markup is profit expressed as a percentage of the cost used as the pricing base, added to that cost to calculate selling price.
A 25% markup on a $400 total cost adds $100 profit and produces a tax-exclusive selling price of $500.
Materials requisition
A materials requisition is an authorized record requesting an issue from stores and identifying the job or center to charge.
The storekeeper releases wood against a materials requisition carrying the job number of the cabinet order that will use it.
Maximum inventory level
The maximum inventory level is the reorder level plus the order quantity less consumption at minimum usage during minimum lead time.
A balance above the maximum inventory level warns that too much money may be tied up in unused parts.
Minimum inventory level
The minimum inventory level is the reorder level less average usage during average lead time, representing the buffer built into the trigger.
A balance below the minimum inventory level prompts the storekeeper to check usage and chase a delivery.

N

Net pay
Net pay is the amount an employee receives after deductions are taken from gross earnings for the relevant pay period.
A worker with $900 gross pay and $180 employee deductions receives net pay of $720 for the week.
Normal capacity
Normal capacity is expected average production activity over several periods, allowing for routine maintenance and seasonal or cyclical changes.
Using normal capacity keeps a temporarily quiet month from inflating the fixed-overhead charge per job.

O

Operating cost statement
An operating cost statement gathers the costs of providing a continuing service over a period so a cost per service unit can be calculated.
A bus company's operating cost statement combines drivers' pay, fuel, depreciation and other period costs.
Ordering cost
An ordering cost is a cost incurred when placing and processing an inventory order, such as order administration and receiving checks.
A fixed ordering cost of $50 makes twenty orders twice as expensive to process as ten orders.
Over-absorbed overhead
Over-absorbed overhead is the amount by which overhead charged to output at the predetermined rate exceeds actual production overhead.
Over-absorbed overhead reduces cost of goods sold when its credit balance is closed to that expense.
Overhead absorption
Overhead absorption assigns production overhead to cost units using a rate applied to the activity or cost basis consumed by each unit.
Overhead absorption charges a machine-intensive order for the machine hours it uses in production.
Overhead analysis statement
An overhead analysis statement lists overhead costs by row and cost centers by column to show how indirect production costs are distributed.
The overhead analysis statement checks that department totals add back to the original factory overhead.
Overhead control account
An overhead control account collects actual production overhead as debits and records overhead applied to work in process as credits.
A debit balance in the overhead control account indicates that some actual overhead remains underapplied.
Overtime premium
An overtime premium is the extra pay above the basic hourly rate earned for hours worked beyond the standard working time.
At a $20 basic rate and time-and-a-half pay, the overtime premium is $10 for each overtime hour.

P

Payroll analysis
A payroll analysis divides employment cost among direct job labor, indirect production labor and non-production labor for the period.
The payroll analysis must account for the whole pay total after job hours and idle time are reconciled.
Periodic AVCO
Periodic AVCO is weighted average costing that calculates one unit cost from all opening inventory and receipts for the whole period.
Periodic AVCO prices the month's issues only after the total value and quantity available are known.
Perpetual AVCO
Perpetual AVCO is weighted average costing that recalculates the unit cost after each receipt using the quantity and value then held.
Perpetual AVCO updates the average when a new delivery arrives at a higher price than the existing balance.
Perpetual inventory system
A perpetual inventory system updates inventory quantities and values whenever a receipt or issue is recorded during the period.
A perpetual inventory system reduces the recorded balance as soon as materials leave stores for a job.
Piece rate
A piece rate is a pay scheme that rewards each acceptable unit produced at a specified amount per unit of output.
A worker earns $800 under a piece rate of $1 per good unit after producing 800 acceptable parts.
Predetermined overhead rate
A predetermined overhead rate divides budgeted overhead by budgeted activity before the period starts to support timely job costing.
A predetermined overhead rate of $12 per machine hour charges $300 to a job using 25 machine hours.
Prime cost
Prime cost is the total of direct materials, direct labor and direct expenses that can be traced to a specific job or unit of output.
The job's prime cost includes the invoice for heat treatment subcontracted specifically for that order.
Production overhead
Production overhead is indirect manufacturing cost, including indirect materials, indirect labor and other factory costs shared across jobs.
Factory rent enters production overhead and reaches jobs through the selected absorption rates.
Proration
Proration distributes an overhead adjustment across work in process, finished goods and cost of goods sold using their applied-overhead shares.
Proration assigns 10% of an underapplied difference to WIP when WIP holds 10% of the relevant applied overhead.
Purchase order
A purchase order is the business's formal instruction to a supplier specifying the goods, quantities, prices and delivery terms agreed.
Purchasing sends a purchase order for 200 panels after the workshop's request receives approval.
Purchase requisition
A purchase requisition is an internal request asking the purchasing department to obtain specified materials or supplies.
The workshop sends a purchase requisition when its inventory of metal sheets reaches the reorder level.

Q

Quotation
A quotation is a selling price offered before a job begins, built from estimated input quantities, costs, overhead charges and planned profit.
A repairer's quotation uses estimated labor hours because the work has not yet been completed.

R

Reapportionment
Reapportionment transfers service-center overhead to the production centers that benefit, before production overhead absorption rates are set.
Maintenance reapportionment uses the hours of repair work supplied to each receiving department.
Reciprocal method
The reciprocal method recognizes all services exchanged between service centers when assigning their combined costs to production centers.
The reciprocal method uses simultaneous equations when Maintenance and Stores both support each other.
Reorder level
The reorder level is the inventory balance that triggers a new order, calculated here from maximum usage and maximum lead time.
For a part with a reorder level of 720 units, the storekeeper places an order when the part's balance falls to 720 units.
Reorder quantity
The reorder quantity is the number of units purchased each time an inventory order is placed, separate from the level that triggers it.
A reorder quantity of 1,000 units tells Purchasing how much to buy when the inventory trigger is reached.
Repeated distribution
Repeated distribution successively shares service-center balances back and forth until the remaining amount is negligible for the cost analysis.
Repeated distribution approaches the same departmental totals as the algebraic reciprocal calculation.
Rowan bonus
A Rowan bonus values time saved at the hourly rate and multiplies it by actual time taken divided by the time allowed for the task.
A Rowan bonus changes when the ratio of actual time to allowed time changes for a time-saving task.

S

Salary
A salary is a fixed amount of gross pay for a week or month, independent of the employee’s recorded hours or number of units produced.
A production planner receives a monthly salary because output is not measured as individual units.
Service cost center
A service cost center is a department that supports production or other departments, with its costs later reapportioned to production centers.
Maintenance is a service cost center whose costs are distributed using the repair hours supplied.
Setup cost
A setup cost is the cost of preparing equipment or a production line for a batch, incurred once for that batch rather than for each unit.
A $440 setup cost is spread over twice as many units when the batch increases from 400 items to 800.
Step-down method
The step-down method distributes one service center at a time and prevents later service charges from returning to a center already closed.
The step-down method adds Maintenance's charge to Stores before distributing the updated Stores total.
Stockout cost
A stockout cost arises when inventory is unavailable, such as lost sales, idle production time or the extra cost of emergency purchases.
The factory incurs a stockout cost when missing bearings leave its machine and operator unable to work.
Stocktaking
Stocktaking is the physical counting of inventory and comparison with recorded balances to identify shortages, damage or recording errors.
Continuous stocktaking checks selected materials each day instead of closing stores for one full count.
Stores ledger card
A stores ledger card is an inventory record showing receipts, issues and balances in quantities, unit costs and total values.
The accountant checks the stores ledger card before pricing the next issue of steel to a repair job.

T

Three-way match
A three-way match compares a supplier invoice with the purchase order and goods received note before payment is authorized.
The three-way match reveals that an invoice charges for ten more units than the receiving staff counted.
Time rate
A time rate is a pay scheme in which earnings depend on the hours worked multiplied by an agreed amount per hour.
A repair shop uses a time rate because careful work and fault diagnosis matter more than unit counts.
Time sheet
A time sheet is a record of time spent on specific jobs or activities, identified by job number and checked against paid attendance.
The supervisor approves the time sheet before its hours are charged to the customer's repair order.
Total production cost
Total production cost combines prime cost with absorbed production overhead and supplies the cost basis for manufacturing inventory.
The total production cost of unfinished jobs agrees with the work in process balance in the ledger.

U

Under-absorbed overhead
Under-absorbed overhead is the amount by which actual production overhead exceeds the overhead charged to output at the predetermined rate.
Under-absorbed overhead is $2,400 when actual factory cost is $98,400 and jobs absorbed $96,000.

W

Weighted average cost
Weighted average cost is an inventory pricing method that divides the total value of available units by their total quantity to find a unit cost.
Weighted average cost gives a larger purchase more influence on the average than a small purchase.
Work in process
Work in process is the production cost accumulated on unfinished jobs, including direct costs and overhead applied at predetermined rates.
Work in process falls when a completed job's production cost is transferred into finished goods inventory.

About this lesson

By StudeliReport a mistake