- Learn
- Business & Economics
- Accounting
- Performance Management
- Specialist Costing Techniques
Specialist Costing Techniques
IntermediateLesson 2 of 9 in Performance Management Course
What you will learn
- Set up an activity-based costing system from activities to product costs, and judge when its more accurate costs are worth the effort of running it.
- Build product costs with ABC, step by stepGroup overheads into activity cost pools, choose cost drivers, calculate driver rates and compare the resulting product costs with a single plant-wide absorption rate.
- Judge the benefits, limits and uses of ABCDecide when ABC is worth implementing, use its information to manage activities and customers, and recognize what ABC cannot tell managers.
- Build product costs with ABC, step by step
- Work back from the price customers will pay to the cost a new product or service must reach, and plan how to close the gap between that target and the estimated cost.
- Derive a target cost and the cost gapCalculate a target cost from a target price and required profit for products and services, and measure how far the current design is from it.
- Close a cost gap and apply target costing to servicesChoose realistic ways to close a cost gap without removing value for customers, and explain why target costing is harder to apply to services.
- Derive a target cost and the cost gap
- Track every cost a product or asset causes from design to disposal, and use whole-life figures to price, choose between alternatives and manage costs early.
- Trace costs across the stages of the life cycleDescribe the stages of a product's life cycle, identify the costs that arise in each, and explain why most costs are committed before production starts.
- Calculate life-cycle cost and profit and use them in decisionsWork out life-cycle cost per unit and life-cycle profit, compare alternatives on whole-life cost, and explain the benefits and limits of the method.
- Trace costs across the stages of the life cycle
- Find the constraint that limits output, measure how well products use it with the throughput accounting ratio, and plan production to earn the most throughput from scarce bottleneck time.
- Find and manage the constraintIdentify the bottleneck resource and apply the theory of constraints and its five focusing steps.
- Calculate, interpret and improve the throughput accounting ratioCalculate throughput, return per factory hour, cost per factory hour and the TA ratio, explain what the ratio means, and suggest ways to raise it.
- Plan production around the bottleneck and evaluate throughput accountingRank products by throughput per bottleneck hour to build the best production plan, and judge where throughput accounting helps and where it misleads.
- Find and manage the constraint
- Classify the costs of achieving quality and of failing to achieve it, report them clearly, and use the figures to decide where quality spending pays off.
- Classify quality costs and prepare a cost of quality reportSort quality-related costs into prevention, appraisal, internal failure and external failure costs, and summarize them in a cost of quality report.
- Use quality cost information in decisionsWeigh spending on prevention and appraisal against the failure costs it avoids, using only the costs a decision changes.
- Classify quality costs and prepare a cost of quality report
- Identify the environmental costs an organization causes, use environmental management accounting techniques to measure and assign them, and support decisions that are financially and environmentally sustainable.
- Identify and classify environmental costsRecognize environmental costs, classify them in the standard frameworks, and explain why traditional systems manage them poorly.
- Apply environmental management accounting techniquesUse input-output analysis, flow cost accounting, activity-based costing and life-cycle costing to measure environmental costs and assign them to their causes.
- Support sustainable decisions as a management accountantAccount for environmental and sustainability factors in costs, performance measures and investment decisions, and explain the management accountant's role.
- Identify and classify environmental costs
Specialist Costing Techniques study guide
1Use ABC to understand overheads
A product can use little machine time yet create many setups, orders, and design changes. Tracing these activities changes the way overhead is shared between products and customers. Work from activity pools to unit costs, then use the results to judge prices, service terms, and improvement priorities. The decision to adopt ABC also needs a practical judgment: will better information change enough decisions to justify collecting and maintaining it?
1.1 From activity pools to product costs
Activity-based costing, or ABC, traces overhead through the activities that products need. It first gathers costs into activity pools, then charges each pool using a driver that reflects its cause. This matters when two products use the factory very differently.
Build the rates
Identify the main activities through staff interviews, time records, and system data. Assign overhead to pools such as setups, machine operation, and material handling. Choose a driver for each pool, record total driver use, and calculate:
Multiply that rate by each product's driver use. Add its charges across the pools, then divide by its output for overhead per unit. Use total driver use across all products in the rate denominator; using one product's output would produce a rate for the wrong quantity.
A transaction driver counts events, such as setups. A duration driver measures time, such as setup hours. If one setup takes much longer than another, hours give a better measure of resource use, but require more recording.
Match the driver to the cost level
| Level | What creates the cost | Example |
|---|---|---|
| Unit | Each unit made | Machine power |
| Batch | Each batch, regardless of size | Setups or first-off inspections |
| Product-sustaining | Supporting a product line | Design changes |
| Facility-sustaining | Keeping the whole site available | Rent or the plant manager's salary |
Facility costs have no clear cause-and-effect driver to individual products. Spreading them across products still involves judgment. ABC improves tracing where a causal driver exists; it cannot make a site-wide cost causal merely by naming a driver.
Work through a factory
Standard has output of 10,000 units and Deluxe 2,000 units. Each unit uses one machine hour. Three pools contain $240,000 for machines, $120,000 for setups, and $60,000 for material handling. Standard uses 10 setups and 10 movements; Deluxe uses 20 setups and 50 movements.
The rates are $20 per machine hour, $4,000 per setup, and $1,000 per movement. For example, the setup rate is $120,000 divided by 30 setups.
| Product | Machine charge | Setup charge | Handling charge | Total | Per unit |
|---|---|---|---|---|---|
| Standard | $200,000 | $40,000 | $10,000 | $250,000 | $25 |
| Deluxe | $40,000 | $80,000 | $50,000 | $170,000 | $85 |
One plant-wide machine-hour rate would be $420,000 divided by 12,000 hours, or $35 per hour. It would charge $35 per unit to both products. Standard would be overcosted by $10 per unit and Deluxe undercosted by $50. Deluxe uses one sixth of machine hours but two thirds of setups and five sixths of movements, so a machine-hour rate misses much of its demand on support work.
Both methods charge $420,000 in total. ABC changes the allocation between products. It also remains a full-cost system: a product's ABC charge includes resource costs that may continue after one order or product is removed.
Key Takeaways
- Calculate each pool rate from the pool cost and total use of its own driver.
- Batch and product-support costs can distort costs based on volume alone.
- Facility-sustaining costs still require an arbitrary allocation.
- ABC changes how overhead is shared; it does not reduce the total spending.
- A full ABC cost is different from the cost a short-term decision changes.
1.2 Turn activity information into better decisions
ABC is most useful when overhead is substantial and products differ in volume, batch size, or complexity. The benefit comes from decisions made with the figures, such as changing customer terms or reducing setups. A more detailed cost report has little value if managers continue making the same choices.
Decide whether ABC is worth running
A diverse factory with frequent small batches can hide cross-subsidies under one volume-based rate. ABC makes those support demands visible. A business with one product or little overhead has less to gain.
Designing and maintaining the system takes time and money. Activities and drivers involve judgment, facility costs remain difficult to trace, and historical rates need updating. Too many pools make the system hard to use; too few can conceal the differences it was meant to reveal. Senior support, staff training, and reliable time surveys matter as much as the formulas. A pilot department can test the approach, while an enterprise resource planning system can supply driver records.
Manage activities and customers
Activity-based management (ABM) uses ABC results to change activities. Operational ABM improves the way work is done or reduces driver use. Strategic ABM changes prices, product ranges, or customer choices.
An assembly step that creates a feature customers value is value-added. Rework and unnecessary material movements are non-value-added activities to reduce. Some support work remains necessary even when customers would not pay for it directly; review its purpose before removing it.
Customer profitability also depends on cost to serve. Two customers each bring $100,000 revenue and $30,000 gross margin. Orders cost $150 each and rush deliveries $400 each.
- Customer A: 10 orders and 2 rush deliveries cost $2,300, leaving $27,700.
- Customer B: 120 orders and 30 rush deliveries cost $30,000, leaving zero.
Equal gross margins conceal very different service demands. Larger consolidated orders or a rush-delivery charge could change Customer B's economics.
Use time-driven ABC
Time-driven ABC needs the cost of practical capacity and the time each task takes. A service department costs $480,000 annually. Ten staff each supply 1,600 practical hours, giving 960,000 minutes. Its capacity rate is:
An 8-minute order costs $4; a 30-minute complaint costs $15. If work uses 840,000 minutes, unused capacity is 120,000 minutes, costing $60,000. Report that unused capacity separately instead of charging the full department cost to the tasks completed.
Test the savings behind a decision
Removing a product reduces recorded driver use, but spending falls only when resources can be released. Deluxe's $80,000 setup charge becomes a saving only if that much setup spending stops. Reassigning salaried staff leaves salaries unchanged. It can still help by earning contribution elsewhere or avoiding other recruitment, but that benefit must be identified separately.
Key Takeaways
- ABC is valuable when different activity demands change worthwhile decisions.
- Operational ABM improves activities; strategic ABM changes commercial choices.
- Customer profitability includes the activities needed to serve the customer.
- Time-driven ABC separates used practical capacity from unused capacity.
- Savings require resource spending to stop; reassignment can create a different benefit.
- Implementation needs reliable data, management support, and usable detail.
2Design to a market-led target cost
A market price and a required return set the spending a new product can support. The design team then has a concrete cost gap to solve before production starts. The arithmetic is simple, but the choice of profit basis and the scope of costs matter. Closing the gap also needs judgment about customer value: cheaper components, fewer steps, or a simpler service must preserve the functions and quality that make the offer worth buying.
2.1 Calculate the target and the gap
Target costing begins with customers and the market. Establish the features customers value and the price they will pay, then subtract the profit the business requires. The resulting cost is a design limit, not a prediction of what the current design will cost.
Cost-plus pricing reverses this sequence: estimate or measure cost, then add a markup to set a price. Target costing asks whether the business can make the desired return at a market-led price.
Turn the price into a cost limit
Define the product, research market prices, set required profit, and derive target cost. Estimate the current design on the same cost basis, then calculate:
A positive gap is the reduction still needed. Zero or a negative gap means the estimate meets the target. Compare like with like: a target covering design, production, marketing, distribution, and after-sales support needs an estimate covering those costs too. ABC can improve overhead estimates, and life-cycle costing brings early and late costs into the calculation.
An appliance has a target price of $250 and a required margin of 20% of selling price. Required profit is $50, leaving a target cost of $200. The estimated cost is $230, so the gap is $30. Expressed as a percentage, that is 15% of target cost or about 13% of estimated cost. Name the denominator when reporting a percentage gap.
Read the profit basis carefully
| Requirement | Calculation of target cost | Result at a $250 price |
|---|---|---|
| 20% margin on price | Price multiplied by 80% | $200.00 |
| 20% markup on cost | Price divided by 1.20 | $208.33 |
A markup is measured against cost; a margin is measured against revenue. With a 20% markup, the selling price is 120% of cost. Subtracting 20% of price would meet a different profit requirement. A 20% margin equals a 25% markup because profit of $50 is one quarter of cost of $200.
Apply it to a service
An annual bookkeeping package sells for $1,800 and requires a 30% margin. Its target cost is $1,260. The current estimate has 18 staff hours at $60, software of $150, and overhead of $210:
The gap is $180. Automated bank feeds reduce staff time to 15 hours, giving $900 of labor and a total of $1,260. The redesign meets the target while preserving the service.
Target costing has its strongest influence before launch, when design choices determine later resource use. Increasing price or accepting less profit changes the target itself. If design changes cannot close the gap, management must decide whether to redesign further, delay, drop the offer, or accept a lower return for a strategic reason.
Key Takeaways
- Target cost is market-led price minus required profit.
- Use estimated cost minus target cost for the gap.
- A margin uses price as its base; a markup uses cost.
- Both sides of the comparison must include the same costs.
- Changing the price or profit requirement changes the target, not the design cost.
2.2 Reduce cost while protecting customer value
Closing a cost gap is a design problem shared by several teams. Purchasing may improve supplier terms, engineers may simplify assembly, and marketing can identify features customers would be willing to lose. The management accountant measures the savings and checks whether they close the gap across the product's life.
Examine the function before cutting its cost
Value engineering reviews a planned product before production. Ask what each component or step does, whether customers need that function, and how to provide it for less. Value analysis applies the same approach to a product already being made.
Practical changes include fewer components, shared standard parts, materials of acceptable quality, easier assembly, better supplier terms, outsourcing, automation, and fewer support activities. ABC helps identify expensive batches, movements, or design changes. Removing a feature customers value can reduce sales, while lower quality can turn an apparent saving into warranty or rework cost.
For the appliance with a $30 gap, a shared housing saves $12 per unit. Reducing the parts count from 24 to 18 saves $8 of assembly cost. A longer supplier contract saves another $6.
The revised estimate is $204 and the target remains $200, leaving a $4 gap. A team should report that remaining shortfall clearly. Calling $26 of savings a completed solution would hide a cost reduction still needed.
Put responsibility where the choices are made
Designers, engineers, purchasing, marketing, accountants, and key suppliers each control different parts of the outcome. A cheaper material needs engineering approval, a removed feature needs evidence about customer value, and a supplier agreement needs credible terms. Target costing brings these choices together early. It also creates risks: prolonged redesign, pressure on suppliers, and staff stress can follow an unrealistic target.
After launch, kaizen costing sets small, continuous cost-reduction targets during production. It complements the early design focus of target costing. The two methods operate at different points in the product's life.
Define a service unit that can be costed
Services pose several linked difficulties:
| Characteristic | Why costing is harder |
|---|---|
| Intangibility | The promised service can be hard to specify |
| Variability | Different jobs use different amounts of work |
| Inseparability | The customer participates as the service is delivered |
| Perishability | Unused appointment or staff capacity cannot be stored |
Labor and overhead often form a high share of service cost and are difficult to trace to one job. Many service businesses also lack a separate design team. A standard tax return package, vehicle service, or broadband subscription is easier to target-cost than an open-ended consulting assignment: the output, service promise, market price, and repeatable work can be defined.
For a fixed-fee bookkeeping package, automated feeds save staff time without cutting the promised reporting. A reduction that instead removed essential checks could raise error correction and complaint costs later. Evaluate the whole service promise and the consequences of the change, not just the immediate hours removed.
Key Takeaways
- Value engineering reviews planned products; value analysis reviews existing ones.
- Combine verified savings and calculate any gap still left.
- Target costing needs decisions across functions and suppliers.
- Kaizen costing reduces costs continuously during production.
- Standard, repeatable services offer clearer units for target costing.
- Cost reductions must preserve valued functions and quality.
3See costs from design to disposal
A profitable production year can sit between expensive development work and costly obligations after sales end. Life-cycle costing brings these stages together so that launch, pricing, and design decisions reflect the product as a whole. The same logic applies to an asset buyer comparing purchase, running, and disposal costs. Timing matters twice: design decisions commit future spending, and discounting recognizes when future cash costs arise.
3.1 Follow costs across the product life
A product's costs begin before its first sale and can continue after its last. Life-cycle costing gathers costs and revenues across that whole span. It helps managers see whether the offer earns enough over its life, including the early investment and later obligations.
Connect the stages to their costs
| Stage | Sales pattern and typical costs |
|---|---|
| Development | No launch sales yet; research, design, prototypes, testing, tooling |
| Introduction | Low initial sales; launch marketing, distribution setup, staff training |
| Growth | Rising sales; expanding production, selling, and customer support |
| Maturity | Sales level off; production and support, with pressure to reduce unit costs |
| Decline | Falling sales; smaller production runs, inventory clearance, spare-parts support |
| After withdrawal | Warranty, decommissioning, disposal, and site restoration obligations |
Stopping the cost record at withdrawal omits obligations that the product has already created. A final warranty repair still belongs to that product even when no more units are being sold.
Separate commitment, use, and payment
A committed cost is locked in by a decision. An incurred cost arises when resources are used. Cash payment may happen at a different time again.
Choosing a sealed design can commit the business to a particular material, assembly process, and repair approach. Material cost is incurred when material is used in production; payment follows the supplier terms. The designer may spend little at the point of choice while determining large amounts of later spending.
This explains why early cost management has such influence. Once tooling, suppliers, and product specifications are fixed, changing them can be costly. Target costing and value engineering use the period before production to change those commitments.
Why annual figures can hide the picture
Research and often development expenses appear in early years, sometimes in general overheads. Sales arrive later. After withdrawal, support or restoration costs may appear in a year with no product revenue. Judging only the production years can overstate the offer's return, while judging only development years can make a worthwhile product look unsuccessful.
A life-cycle view associates these amounts with the product across periods. It supports a management decision without changing the timing rules used in external financial reporting. Keep the product cost record as forecasts become actual results, so a changed sales outlook or higher warranty cost feeds into the remaining plan.
Choose the perspective
The producer's view follows research, launch, production, and support through withdrawal and later obligations. The owner's view follows an asset from purchase and installation through running, maintenance, and disposal, less resale value. The same item can have different cost records for its maker and its buyer because each incurs different costs.
Short product lives make recovery of development spending harder. With fewer selling periods, the early prices and sales volumes must recover a larger share of pre-production cost. This is one reason a design team needs a forecast of the entire life before deciding that an attractive production margin is enough.
Key Takeaways
- Life-cycle costing follows costs and revenues beyond the selling years.
- Design decisions commit spending before the resources are used.
- Incurred cost and cash payment can occur at different times.
- The producer and the asset owner have different whole-life perspectives.
3.2 Calculate whole-life cost and profit
Start with a consistent lifetime and a complete list of costs. Distinguish one-time amounts, annual amounts, and costs per unit. Only then add them. Dividing an incomplete total by output gives a precise-looking answer that still omits part of the product's cost.
Build the lifetime total
A product will sell 80,000 units over four years at $50 each. Its forecast costs are:
| Cost | Lifetime calculation | Amount |
|---|---|---|
| Research and development | One-time total | $480,000 |
| Variable production | 80,000 units at $18 | $1,440,000 |
| Fixed production | Four years at $200,000 | $800,000 |
| Marketing | Lifetime total | $320,000 |
| Support and warranty | 80,000 units at $2 | $160,000 |
| Decommissioning | End-of-life total | $100,000 |
| Total | $3,300,000 |
Revenue is $4,000,000, so life-cycle profit is $700,000, or $8.75 per unit. Production cost alone is $2,240,000, or $28 per unit. The apparent $22 production margin has to cover development, marketing, support, and closure costs before it becomes lifetime profit.
Compare assets at present value
The owner's whole-life cost includes purchase and installation, running and maintenance, and disposal, less resale proceeds. When cash flows occur over years, discount them so that amounts at different dates have a common basis.
Machine A costs $50,000, runs for five years at $8,000 annually, and has $5,000 resale value. Machine B costs $38,000, runs at $11,000 annually, and has $2,000 resale value. Both have equal service lives. At 10%, use the five-year annuity factor 3.791 for equal year-end running costs and the year-5 factor 0.621 for resale:
A costs $1,236 less at present value despite its higher purchase price. Without discounting, the totals are $85,000 and $91,000. Resale is subtracted because it is an inflow, and it receives the factor for the year in which it arrives.
Use the result in decisions
Whole-life information can support launch decisions, cost recovery through prices, and design trade-offs. Extra development spending may be worthwhile if it reduces production waste or warranty claims over many units. Earlier launch can bring revenue forward; a longer selling life or earlier breakeven can improve the product's return.
These figures depend on forecasts of price, volume, costs, and life. Update the estimates as evidence changes. Check that annual fixed costs cover every year and that shared costs are allocated once across the products using them. Charging an entire shared development cost to each product would overstate the total needed for the business as a whole.
Key Takeaways
- Convert annual and per-unit figures to lifetime totals before adding.
- Life-cycle profit includes development, support, and end-of-life obligations.
- Discount recurring costs and terminal proceeds at the correct dates.
- A higher purchase price can buy a lower whole-life cost.
- Update long-range forecasts and avoid counting shared costs twice.
4Make the best use of a bottleneck
When one stage limits sales output, improving every machine equally wastes effort. Throughput accounting directs attention to the scarce resource and the sales it supports. First identify and manage the constraint, then calculate the return each product earns from its time. Use those rates to plan a product mix within demand and contract limits, while keeping the short-term treatment of labor and factory spending clear.
4.1 Find the stage that limits output
The theory of constraints, developed by Eliyahu Goldratt, focuses on the constraint limiting a system's output. Its aim is to increase throughput while keeping inventory and operating expense low. A bottleneck has insufficient capacity relative to the work demanded of it; it is not simply the machine with the fewest hours available.
Compare demand with capacity
Demand is 10,000 units. Each unit requires 0.2 cutting hours and 0.5 assembly hours. Cutting has 2,500 hours available and assembly has 4,000.
| Resource | Hours needed for demand | Hours available | Result |
|---|---|---|---|
| Cutting | 2,000 | 2,500 | Spare capacity |
| Assembly | 5,000 | 4,000 | Bottleneck |
Assembly limits output to 8,000 units because each unit requires half an hour. Cutting uses only 1,600 hours for that output. Its remaining time cannot compensate for missing assembly time: the resources perform different jobs.
With several products, add the hours required by all products at each stage before comparing with that stage's capacity. The constraint depends on the workload and can change when the mix changes.
Apply the five focusing steps
- Identify the constraint through the demand-capacity comparison.
- Exploit it: get the most productive use from existing capacity.
- Subordinate other work to its pace.
- Elevate it by adding capacity.
- Repeat the analysis when the constraint is broken.
Exploitation includes reducing setup time, arranging coverage through breaks and shift changes, and keeping a small buffer of work ready before the bottleneck. Inspect input before the scarce stage so that defective work does not consume capacity needed for good output.
Subordination means releasing and scheduling other work around the bottleneck's needs. Idle time at a non-bottleneck can be appropriate. Keeping cutting fully busy in the example would create work awaiting assembly, tying up material and space without producing more completed sales.
Elevation adds capacity through another machine, an extra shift, or outsourcing some work. Consider it after getting better use from existing capacity because extra resources cost money. Expanding assembly can make cutting the next constraint, so the cycle returns to identification.
Look beyond the factory
Demand itself is the constraint when customers will buy less than the factory can produce. A supplier's limited material deliveries can also restrict output. More machine time cannot solve either problem by itself.
An hour lost at the active bottleneck loses an hour of system output. Saving an hour at a resource with spare capacity leaves completed output unchanged while the bottleneck remains. Compare improvement proposals by their effect on the constraint and sales, not by local utilization percentages alone. Otherwise, a department may appear more efficient while inventory builds and total profit stays unchanged.
Key Takeaways
- Identify the bottleneck by comparing required work with available capacity.
- Exploit existing capacity before paying to elevate it.
- Schedule other resources around the bottleneck, accepting their idle time.
- Protect bottleneck time from defects, missing inputs, and avoidable setups.
- Repeat the analysis after capacity or product mix changes.
- The active constraint can be demand or supply outside the factory.
4.2 Measure the return from scarce time
Throughput accounting treats direct material as the only truly variable cost in the short run. Throughput is sales revenue less direct material cost. Direct labor and all other operating costs belong in total factory costs (TFC), treated as fixed over the short decision period.
Calculate the three rates
The throughput accounting ratio, TPAR, compares the return from an hour of the bottleneck with the factory cost per available bottleneck hour. Use the same period for factory costs and available hours. Adding the hours of different machines would inflate the denominator and understate the cost of scarce time.
Work through three products
The assembly bottleneck has 4,000 hours and TFC of $260,000, making factory cost $65 per hour.
| Product | Price | Material | Throughput | Bottleneck hours | Return per hour | TPAR |
|---|---|---|---|---|---|---|
| X | $60 | $20 | $40 | 0.50 | $80.00 | 1.23 |
| Y | $80 | $30 | $50 | 0.80 | $62.50 | 0.96 |
| Z | $45 | $15 | $30 | 0.25 | $120.00 | 1.85 |
For X, throughput is $40 and each unit occupies half an hour, giving $80 per hour. Dividing by $65 gives 1.23, rounded to two decimal places. Y earns the largest amount per unit but occupies enough time to have the lowest hourly return.
Interpret the ratio as a rate comparison
A TPAR above 1 earns throughput faster than the factory cost per hour. If all available bottleneck time earned that return, the factory would cover TFC and make a profit. Below 1, the hourly return would not cover the factory cost rate.
A below-1 ratio is not a reason to reject positive-throughput work when its hours would otherwise be idle and TFC stay fixed. The work still adds throughput without increasing those fixed costs. When hours are scarce, compare its return with the return displaced from another product.
Improve the components
A higher price or lower material cost increases throughput per unit. Less bottleneck time raises the hourly return. If X's time falls from 0.5 to 0.4 hours, return rises to $100 per hour and its TPAR becomes about 1.54. Lower TFC also raises the ratio. Check the operational and market effects of each proposed change; a price increase that loses valuable sales needs a fuller decision.
Throughput accounting values inventory at material cost only. Making unsold goods therefore creates no profit from carrying fixed factory cost into inventory. Under absorption costing, increased closing inventory can carry fixed production overhead into a later period and raise current reported profit. The throughput view keeps attention on sales through the constraint.
Key Takeaways
- Throughput deducts direct materials; labor and other operating costs enter TFC.
- Both hourly rates use bottleneck time.
- TPAR compares hourly throughput with factory cost per available bottleneck hour.
- Positive throughput can be worthwhile below a TPAR of 1 if capacity would be idle.
- Improve price, material use, bottleneck productivity, or factory spending.
- Unsold production adds no throughput profit.
4.3 Build a product mix that fits capacity
A factory with scarce bottleneck time must choose what to make first. Rank products by throughput per bottleneck hour, then allocate hours up to demand. Throughput per unit alone misses how long each sale occupies the scarce resource.
Check the demand for hours
Products X, Y, and Z have throughput per unit of $40, $50, and $30. They need 0.5, 0.8, and 0.25 bottleneck hours per unit. Maximum demand is 3,000 X, 2,500 Y, and 4,000 Z. Meeting it all would need:
Only 4,000 hours are available. Hourly returns are $80 for X, $62.50 for Y, and $120 for Z. The priority is therefore Z, then X, then Y. Although Z earns the least throughput per unit, four units fit into one bottleneck hour.
Allocate hours in priority order
| Product | Units made | Hours used | Throughput |
|---|---|---|---|
| Z | 4,000 | 1,000 | $120,000 |
| X | 3,000 | 1,500 | $120,000 |
| Y | 1,875 | 1,500 | $93,750 |
| Total | 4,000 | $333,750 |
Divide the remaining 1,500 hours by 0.8 hours per Y to obtain 1,875 units. Deduct TFC of $260,000 once from total throughput to get profit of $73,750. The factory cost rate helps interpret TPAR; deducting both an allocated hourly factory charge and the full TFC would count the same spending twice.
Ranking by throughput per unit instead would start with Y, then X, leaving hours for only 2,000 Z. Throughput would be $305,000, which is $28,750 lower. The difference comes from using scarce hours less effectively.
Honor commitments before ranking the balance
A contract minimum has to be supplied first. Reserve the hours needed for all mandatory units, then apply the hourly ranking to the remaining hours and unmet demand. Do not allocate the whole capacity to the highest-return product before considering a contractual obligation.
Y's TPAR is about 0.96, yet its last 1,500 hours add $93,750 of throughput. Rejecting Y would leave that time unused after the higher-return demand was met. With TFC unchanged, profit would fall by the lost throughput.
Know what the ranking assumes
The logic resembles contribution per limiting factor, but throughput accounting deducts only materials. A contribution ranking can differ when products have different variable labor or overhead costs. Throughput ranking suits short-term, highly automated settings where those costs remain fixed.
Over a longer period, labor and overhead can change. They still need active control. Also check the constraint again after changing the mix or adding capacity: the original bottleneck may cease to be the limiting stage.
Key Takeaways
- Reserve contractual minimum quantities before allocating discretionary hours.
- Rank the remaining demand by throughput per bottleneck hour.
- Stop at each product’s demand, then move to the next product.
- Deduct total factory costs once after calculating total throughput.
- The ranking relies on short-term cost behavior and the active bottleneck.
5Understand what quality costs
Quality spending has two purposes: achieving the required standard and dealing with failures to meet it. A cost of quality report shows where the money goes, while an incremental decision tests whether extra prevention is worth its cost. The recorded figures need context because lost customers and disruption can be harder to measure than scrap. Use the categories to identify causes and compare actions, including their effects on future costs.
5.1 Classify and report quality costs
Quality means meeting specification and being fit for the customer's use. Its costs include the work needed to achieve that standard and the losses created when it is missed. A cost of quality report organizes both sides so managers can see the balance between prevention, checking, and failure.
Classify by purpose and discovery point
| Category | Purpose or timing | Examples |
|---|---|---|
| Prevention | Stop defects arising | Quality training, design reviews, supplier programs, preventive maintenance |
| Appraisal | Check whether standards are met | Incoming inspection, product testing, quality audits |
| Internal failure | Defect found before delivery | Scrap, rework, re-inspection, related downtime |
| External failure | Defect found after delivery | Warranty repair, returns, complaints, recalls, lost sales |
Conformance costs combine prevention and appraisal. Non-conformance costs combine internal and external failure. Spending to check a product is appraisal even if every item passes; the activity's purpose is finding defects.
Read what the work actually does. Evaluating a supplier's quality system helps prevent defects, while inspecting an incoming shipment is appraisal. Calibrating test equipment supports appraisal. Reworking items rejected before dispatch is internal failure, while repairing the same fault under warranty is external failure. Ordinary inspection and re-inspection after a failure belong in different categories.
Build a report
A manufacturer has revenue of $10,000,000. Its annual report gathers the following amounts:
- Prevention: training $40,000, supplier programs $25,000, design reviews $15,000; total $80,000.
- Appraisal: incoming inspection $30,000 and product testing $50,000; total $80,000.
- Internal failure: scrap $90,000, rework $60,000, downtime $30,000; total $180,000.
- External failure: warranty $120,000 and returns handling $40,000; total $160,000.
Total quality cost is $500,000, or 5% of revenue. Conformance costs are $160,000, representing 32% of quality cost. Non-conformance costs are $340,000, or 68%. State whether a percentage uses revenue or total quality cost as its denominator; those answer different questions.
Interpret the pattern
Most recorded spending here follows defects. That pattern supports investigating prevention, but it does not by itself quantify the best extra investment. A decision needs the expected changes in failure cost and the cost of the proposed action.
Compare the categories over time and against sales. Rising sales can increase total warranty expense even while the warranty cost per sale falls. Consistent reporting helps separate changes in scale from changes in quality performance.
Many failure costs remain outside the accounts: customers quietly leaving, reputation damage, complaint-related management time, and production disruption. A low recorded complaint cost can coexist with serious customer losses. Use complaints, returns, and customer-retention information alongside the financial report to understand the cost of poor quality.
Key Takeaways
- Classify prevention and appraisal by the purpose of the activity.
- Classify failure costs by whether defects are found before or after delivery.
- Conformance combines prevention and appraisal; non-conformance combines failures.
- Name the denominator when reporting quality cost percentages.
- Recorded failure costs can omit lost sales, reputation damage, and disruption.
5.2 Decide whether prevention pays
Prevention stops defects at their source; appraisal finds them. Both reduce the failure costs that reach later stages, but they work differently. A defect discovered after delivery can require more repair work and affect the customer as well as the factory.
Compare two views of quality spending
| View | How total quality cost is understood |
|---|---|
| Traditional | Extra prevention eventually costs more than the remaining failures avoided, leaving an optimum with some defects |
| Modern, zero-defects | Recorded and hidden failure costs are so large that continued prevention lowers total quality cost; the goal is right first time |
These are ways of understanding the cost relationship. A specific proposal still needs evidence about its incremental costs and benefits. Reducing an inspection budget may improve this month's spending figure while allowing more failures to reach customers later.
Work through an improvement proposal
A manufacturer spends $180,000 annually on internal failure and $160,000 on external failure. An extra $60,000 of annual prevention is expected to reduce internal failures by 40% and external failures by 25%.
The combined saving is $112,000. Subtract the $60,000 extra prevention to obtain a net annual benefit of $52,000. The decision improves profit because the avoided failures exceed the added spending.
The existing inspection team stays under either choice. Its unchanged cost is irrelevant to this comparison. The team still belongs in a full cost of quality report, but adding its cost to one side of the proposal would distort the decision.
Follow costs that actually change
Incremental analysis includes extra training, material saved through less scrap, and fewer warranty claims. If a reported failure cost includes fixed salaries that will continue, distinguish the accounting reduction in activity from a reduction in resource spending. Released capacity can have value, but that value needs a use and should be measured separately.
Estimate lost future sales or other unrecorded failures when they could change the choice. State those estimates clearly so managers can see their influence. Evidence such as repeat-purchase rates and complaint trends can help assess whether a forecast improvement is credible.
Link the categories to environmental costs
The same prevention–checking–failure logic can organize environmental spending. Cleaner process design is prevention; emissions monitoring is detection; treating waste before release is internal failure; cleaning pollution after release is external failure. The environmental framework also separates costs paid by the business from harm borne by society.
A proposal may therefore change several reports at once. Less defective production can reduce scrap purchases, handling, and disposal. Trace each saving to its cause and count it once, even when it supports both a quality objective and an environmental objective.
Key Takeaways
- Compare the extra prevention cost with the failure costs avoided.
- Only costs and benefits changed by the proposal enter its incremental result.
- Traditional and zero-defects views differ in their view of total quality cost.
- Include material hidden failure costs with clear estimates.
- Do not count a scrap or waste saving twice across different objectives.
6Make environmental costs visible
Environmental costs often disappear into general overhead or arise long after the activity that caused them. Physical records of material, water, energy, and waste help reveal the causes. Connect those records to money costs, choose drivers that reflect the products responsible, and compare options across their lives. Sustainability decisions also need measures of social and environmental outcomes, with internal valuations kept distinct from actual payments.
6.1 Identify the costs and who bears them
Environmental costs arise from an organization's impact on the environment and its efforts to manage that impact. They include material and energy use, water, treatment and disposal, permits, monitoring, fines, cleanup, and reporting. Some are easy to see on invoices; others sit inside overhead or appear only much later.
Classify the costs for the question being asked
A widely used US Environmental Protection Agency framework distinguishes four groups:
| Group | What it identifies | Example |
|---|---|---|
| Conventional | Ordinary resources with environmental relevance | Materials, energy, equipment |
| Potentially hidden | Recorded costs whose identity disappears in overhead | Monitoring or permit fees |
| Contingent | Costs dependent on future events | Possible polluted-site cleanup |
| Image and relationship | Spending linked to stakeholder relationships | Environmental reporting |
A recorded permit fee can be hidden from the product manager even though the accounts include it. A contingent cleanup estimate concerns a possible future liability. These are different reasons for a cost to be missed in a routine product cost.
A second framework asks where the cost occurs in preventing or dealing with pollution. Prevention avoids pollution through process design, training, and supplier selection. Detection checks compliance through monitoring, tests, and audits. Internal failure deals with pollution produced but not yet released, including treatment and pollution control equipment. External failure follows release.
External failure can be realized, meaning paid by the business, such as river cleanup or compensation. It can also be unrealized or societal, meaning borne by others through harm to health or ecosystems. The firm's cash record therefore captures only part of the wider impact. The two frameworks answer different questions; one cost can be described within each.
Assign a treatment pool by its cause
Annual wastewater treatment is $300,000. Product A uses 70% of labor hours but generates 20% of effluent. Product B uses 30% of labor hours and generates 80% of effluent.
| Product | Labor-based charge | Effluent-based charge |
|---|---|---|
| A | $210,000 | $60,000 |
| B | $90,000 | $240,000 |
An effluent driver puts the cost where the treatment demand arises. The business still spends $300,000, but B's cleaner-production opportunities become more visible. Treating disposal alone as the cost of waste would miss the purchased material and processing already consumed by the wasted output.
Explain why costs are hard to manage
Product-level records may be missing, impacts may lack market prices, and restoration can occur years after production ends. Changing regulation also affects forecasts. Start with a clear cost definition, reliable physical records, and an assignment method managers can use. Better information can support lower material and energy use, avoided cleanup and fines, and stronger relationships with customers, investors, and regulators.
Key Takeaways
- Environmental costs include ordinary resources as well as treatment and cleanup.
- Recorded environmental costs can lose their identity in overhead.
- Internal environmental failure occurs before release; external failure follows release.
- Societal harm can be borne outside the business.
- Use a causal environmental driver to assign a treatment cost pool.
6.2 Connect physical flows with money costs
Environmental management accounting (EMA) combines physical and financial information for internal decisions. The best technique depends on the question: locating a material loss needs different information from comparing a product's lifetime disposal cost.
Reconcile what enters and leaves
Input-output analysis builds a mass balance. For a process without inventory changes, material input must be explained by product, recorded waste, and other outputs such as emissions. With 1,000 kg entering, 900 kg of product and 60 kg of recorded waste account for 960 kg. Investigate the missing 40 kg, or 4% of input, as possible leakage, evaporation, theft, or measurement error. An unexplained balance identifies a problem to investigate; it does not establish its cause.
When stocks change, reconcile opening and closing material as well. A rise in material held in the process is different from a physical loss. Put all comparable flows into consistent physical units before checking the balance.
Show the full cost of waste
Flow cost accounting follows material through the organization and distinguishes material costs, system costs, and delivery and disposal costs. System costs include the labor and processing overhead spent handling the flows. ISO 14051's material flow cost accounting framework separately presents material, energy, system, and waste management costs.
A process uses 10,000 kg of material costing $50,000 and incurs $30,000 of system costs. It yields 8,000 kg of product and 2,000 kg of waste. Disposal costs $6,000. Sharing material and system costs by mass gives:
| Destination | Material | System | Disposal | Total |
|---|---|---|---|---|
| Product, 80% | $40,000 | $24,000 | $0 | $64,000 |
| Waste, 20% | $10,000 | $6,000 | $6,000 | $22,000 |
The waste costs $22,000, although the disposal invoice is only $6,000. Reducing waste by 200 kg saves $1,000 of purchases if input purchases fall by 200 kg at $5 per kg with unchanged good output. At a disposal charge of $3 per kg it also saves $600. The assigned system cost is not all a saving: check which processing resources or spending change.
Choose causal drivers and the right time span
Environmental ABC separates treatment, permits, or inspections from general overhead and assigns them through effluent volume, hazardous waste mass, or relevant inspection counts. It reveals the products and processes causing costs.
Environmental life-cycle costing follows money costs from raw material supply through production and use to disposal, including restoration and decommissioning. It can justify a design that costs more initially but is cheaper to dismantle or recycle.
Life-cycle assessment under ISO 14040 evaluates potential environmental impacts using physical flows and impact measures. It is different from life-cycle costing's money amounts. Valuing environmental harm in money requires an additional valuation basis, such as a carbon price. EMA supports internal choices; its data can also support external reporting, which has a different purpose.
Key Takeaways
- Input-output analysis finds unexplained physical differences, including inventory changes.
- Flow costing assigns material and processing costs to waste as well as disposal.
- A waste cost allocation is different from the saving obtainable by reducing waste.
- Environmental ABC assigns overhead through the activity causing it.
- Life-cycle costing measures money costs; life-cycle assessment evaluates impacts.
- EMA supplies internal decision information that can also feed reporting.
6.3 Evaluate sustainability choices and performance
Sustainability means meeting present needs without compromising future generations' ability to meet theirs, following the 1987 Brundtland Report. John Elkington's triple bottom line brings economic, social, and environmental performance together as “profit, people, planet.” A management accountant helps turn those aims into decisions and credible measures.
Give emissions a decision value
An internal carbon price assigns a value to emissions in planning. A firm makes 400,000 units, each causing 2.5 kg CO2e, and chooses an illustrative internal price of $80 per tonne.
The internal charge is $80,000 annually, or $0.20 per unit. Convert kilograms to tonnes before applying a per-tonne price. CO2e expresses different greenhouse gases on a common carbon-dioxide-equivalent basis.
The internal value is a cash cost only where payments actually arise, for example through an emissions tax or allowances. A shadow charge can change the ranking of investments while leaving their immediate cash flows unchanged.
Keep cash and carbon-adjusted payback distinct
A compressor costs $40,000 and saves 120,000 kWh annually. With example electricity pricing of $0.15 per kWh, the cash saving is $18,000 a year. Cash payback is about 2.22 years.
Using an illustrative factor of 0.25 kg CO2e per kWh, avoided emissions are 30,000 kg, or 30 tonnes annually. At the internal $80 price, that is $2,400 of carbon value. The combined annual benefit is $20,400 and carbon-adjusted payback about 1.96 years. It becomes a cash benefit only to the extent that an actual emissions payment is avoided. If the electricity saving already includes the same emissions charge, adding it again would double count.
Measure outcomes and resource intensity
Use financial and non-financial measures together. Examples include energy or water per unit, CO2e per unit or per $1,000 revenue, the share of waste recycled, accident rates, and the share of suppliers passing sustainability audits. Specify the period, boundary, and denominator consistently. An intensity measure can improve while total emissions rise if output grows, so examine totals as well.
Data are often difficult to obtain and verify, especially across suppliers and customers. Some effects have no market price, and benefits can arrive much later than the spending. Unsupported claims create a greenwashing risk. Separate measured results from forecasts and explain the basis of any monetary valuation.
Apply the accountant's role
Identify environmental and social costs, incorporate them in budgets and forecasts, and compare investment options across their lives. Design targets that reward sustainable behavior and challenge proposals that overlook later obligations. Reliable internal data can support external reporting, including ISSB's IFRS S1 and S2, issued in 2023. A decision record should show energy, material, waste, risk, and stakeholder effects without counting the same benefit in several lines.
Key Takeaways
- Use economic, social, and environmental measures together.
- Convert emissions to the units used by the carbon price.
- Internal carbon value is cash only where an actual payment changes.
- Keep cash payback separate from carbon-adjusted payback.
- Track totals alongside intensity measures and verify the data behind claims.
- Build sustainability costs and benefits into decisions without double counting.
Specialist Costing Techniques examples
1Trace overhead and test a customer decision
12 steps
- 1IntroductionStart with the work products create
Two products can occupy the same machine time per unit but create very different demands on setup staff. A single hourly rate hides that difference. ABC (activity-based costing) traces overhead to its causes, so product costs are not distorted.
Follow a factory making 8,000 Regular and 2,000 Specialist units. First trace overhead through machine use and setups. Then use the same idea to judge a customer decision, where an assigned cost and a cash saving can differ.
- 2ExplanationDefine the two pools
The factory has $200,000 of machine-related overhead and $100,000 of setup overhead. Every unit needs one machine hour. Regular requires 10 setups; Specialist needs 30.
Machines supply a unit-level activity, while setups support batches. Separate pools let each product receive a charge for the work it creates instead of treating every overhead as proportional to output.
- 3ExampleCalculate each driver rate
Total machine use is 10,000 hours, so the machine rate is:
The 40 setups give a setup rate of $2,500 per setup. Each denominator uses total activity across both products. The output count happens to equal machine hours here, but setup cost still needs its own driver.
- 4ExampleCharge Regular for its activities
Regular receives $160,000 of machine overhead from its 8,000 hours. Its 10 setups add $25,000.
Dividing by 8,000 units gives $23.125 overhead per unit, or $23.13 rounded at the end. The low setup demand is spread across a large output; it is not charged the same setup cost per unit as Specialist.
- 5ChallengeComplete the comparison
Specialist uses 2,000 machine hours and 30 setups. What is its ABC overhead per unit, and how does it compare with the single rate for all $300,000 overhead?
---reveal---
Its machine charge is $40,000 and setup charge $75,000, totaling $115,000. ABC cost is $57.50 per unit. A single rate of $30 per machine hour charges only $30 per unit, undercosting Specialist by $27.50.
- 6TipUse a causal driver
Setup counts work when setups use similar resources. If Specialist setups take much longer, collect setup hours and use a duration rate.
A causal driver makes the pool meaningful. Site rent has no equivalent product-level cause, so assigning facility-sustaining costs still requires an arbitrary basis. A larger number of pools cannot remove that limitation.
- 7ConnectionMove from a report to an action
ABC reveals a support-heavy product; ABM asks what to do about the activities. Operational ABM could reduce changeovers or unnecessary movements. Strategic ABM could alter prices, product mix, or customer terms.
The factory should weigh the decisions it can improve against the cost of surveys, records, training, and rate updates. A detailed report needs a practical use to justify its upkeep.
- 8ExampleCompare customer service demands
Two customers each provide $24,000 gross margin. Processing an order costs $100 and a rush delivery $300.
A customer with 20 orders and 4 rush deliveries uses $3,200 of service activity, leaving $20,800 after those charges. Another with 100 orders and 20 rush deliveries uses $16,000, leaving $8,000. Gross margin alone hides the difference in cost to serve.
- 9Key InsightKeep unused time visible
A support team costs $240,000 and supplies 480,000 practical minutes. Its rate is $0.50 per minute. If tasks use 420,000 minutes, the remaining 60,000 minutes cost $30,000.
Time-driven ABC reports that unused capacity separately. Charging the full department spending only to completed tasks would make them look more resource-intensive simply because the team has spare time.
- 10ChallengeTest whether a charge can be saved
A customer provides $21,000 contribution before support. ABC assigns $25,000 support cost, but dropping the customer ends only $8,000 spending. Remaining resources stay paid and unused. Should dropping it improve short-term profit?
---reveal---
No. Losing $21,000 contribution while saving $8,000 reduces profit by $13,000. The ABC loss includes retained support spending, so it cannot be used as the decision saving.
- 11ChallengeConnect product tracing with capacity
Specialist's setup activity falls after redesign, but the setup team stays on salary and uses the released time on another product. What should managers distinguish when evaluating the redesign?
---reveal---
The activity charge falls, but salaries do not. Measure any extra contribution or avoided spending from the new use separately. Better tracing identifies the resource demand; a decision still needs the change in spending or benefit.
- 12RecapRead the cost before acting on it
Trace machine and batch activity through their own drivers, then compare the resulting product costs. Use ABM to change work or commercial choices where the information justifies it.
Before treating a falling activity charge as a saving, identify what happens to the resources. Practical capacity, task use, avoidable spending, and the value of a new use answer different parts of the management decision.
2Work backward from price to an affordable design
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionSet the commercial problem
- 2ExampleFind the profit and target cost
- 3TipKeep the cost scope consistent
- 4ChallengeChange the profit basis
- 5ExplanationReview the function of each component
- 6ExampleAdd the design savings
- 7ConnectionContinue after production starts
- 8ExplanationDefine a repeatable service
- 9ChallengeTest a service redesign
- 10ChallengeDistinguish a saving from a new target
- 11RecapReport both the reduction and the result
3Calculate the return across the whole life
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionLook across the selling years
- 2ExplanationFollow the costs before and after sales
- 3ExampleLocate the early decision
- 4ChallengeFind the best moment to act
- 5ExampleSet out the lifetime forecast
- 6ExampleConvert and total the costs
- 7ExampleFind profit and the omitted costs
- 8ChallengeChange a stage and test the lifetime effect
- 9ConnectionSwitch to the asset owner
- 10ExampleCalculate a present-value comparison
- 11ChallengeRead the forecasts behind the choice
- 12RecapMatch the cost to its lifetime basis
4Plan sales through a scarce assembly stage
19 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionMake scarce time count
- 2ExampleCompare work with available hours
- 3ChallengeCheck what another machine would solve
- 4ExplanationExploit assembly first
- 5Key InsightLet other resources follow its pace
- 6ConnectionElevate and identify again
- 7ExampleFind throughput per unit
- 8ExampleFind the factory cost rate
- 9ExamplePut unit returns on an hourly basis
- 10ExampleCompare returns with factory cost
- 11ChallengeUse an idle hour sensibly
- 12TipImprove a ratio through its parts
- 13ExplanationRank the demand
- 14ExampleAllocate the 3,000 hours
- 15ExampleConvert the plan into profit
- 16ChallengeAdd a binding customer commitment
- 17ConnectionKnow when the model needs revision
- 18ChallengeConnect product speed with the system constraint
- 19RecapKeep the plan tied to the constraint
5Turn a quality report into an improvement decision
11 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionFollow the cost of a defect
- 2ExplanationSeparate prevention from checking
- 3ExplanationPlace failures before or after delivery
- 4ChallengeClassify a short sequence
- 5ExampleRead a quality report
- 6ExampleMeasure the proposed change
- 7ChallengeTest the arithmetic with a new proposal
- 8Key InsightConsider losses outside the accounts
- 9ConnectionCompare the quality-cost views
- 10ChallengeCheck whether an activity reduction saves cash
- 11RecapUse the report and decision for different purposes
6Trace waste costs and value cleaner choices
20 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionConnect resources with the decisions they support
- 2ExplanationFind costs hidden in ordinary accounts
- 3ExplanationLocate the pollution boundary
- 4ExampleAssign treatment by its cause
- 5ChallengeClassify two environmental activities
- 6ExampleReconcile the physical material
- 7ChallengeAccount for inventory changes
- 8ExampleAttach costs to the physical flows
- 9ExampleSee the full waste total
- 10Key InsightSeparate allocated cost from saving
- 11ConnectionChoose a technique for a different question
- 12ChallengeDecide whether the waste change pays
- 13ExplanationDefine performance more broadly
- 14ExampleCalculate the cash saving first
- 15ExampleAdd an internal carbon value
- 16TipCheck the measurement denominator
- 17ChallengeIdentify what changes the cash measure
- 18ConnectionBuild the information into management
- 19ChallengeAudit a combined improvement claim
- 20RecapKeep physical, financial, and social results clear
Specialist Costing Techniques practice questions
Set 1: Build costs and identify the decision10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Compare alternatives and trace the effects10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Choose drivers and protect scarce resources10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Test assumptions and compare full outcomes10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Integrate costing methods in management decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Activity cost pool
Activity-based management
Annuity factor
Appraisal cost
B
Batch-level cost
Bottleneck
C
Carbon-adjusted payback
CO2e
Committed cost
Conformance cost
Constraint
Contingent environmental cost
Contractual minimum
Cost driver
Cost gap
Cost of quality report
Cost per factory hour
Cost to serve
Cost-plus pricing
Cross-functional team
Customer profitability
D
Demand ceiling
Driver rate
Duration driver
E
Elevation
Emissions intensity
Environmental ABC
Environmental detection cost
Environmental management accounting
Exploitation
External quality failure cost
F
Facility-sustaining cost
Flow cost accounting
G
Greenwashing
H
Hidden quality cost
I
Image and relationship cost
Incremental cost
Incurred cost
Input-output analysis
Internal carbon price
Internal environmental failure cost
Internal quality failure cost
K
Kaizen costing
L
Life-cycle assessment
Life-cycle cost per unit
Life-cycle costing
Life-cycle profit
M
Markup
Material flow cost accounting
N
Net benefit
O
Opportunity cost of bottleneck time
P
Potentially hidden environmental cost
Practical capacity
Present value
Prevention cost
Product life cycle
Product mix
Product-sustaining cost
Profit margin
R
Realized external environmental cost
Return per factory hour
S
Service perishability
Societal environmental cost
Subordination
Sustainability
System cost
T
Target cost
Throughput
Throughput accounting ratio
Time-driven ABC
Total factory costs
Triple bottom line
U
Unused capacity cost
V
Value analysis
Value engineering
W
Whole-life ownership cost
Z
Zero-defects view
About this lesson
Make your own Study Materials
Turn your notes, slides and documents into Study Guides, Practice Questions, Flashcards and 6 more tools.