Property, Plant and Equipment: Measurement and Revaluation
IntermediateLesson 7 of 9 in Intermediate Accounting 1 Course
What you will learn
- Decide when an item is recognized and build its cost from the purchase price, directly attributable costs and dismantling obligations, including assets bought in a bundle, on extended credit, by exchange, for shares or built in-house.
- Build the initial cost of an item from its elementsApply the recognition criteria, sort spending into costs that belong in the asset and costs that are expenses, and add the present value of dismantling and restoration costs.
- Measure cost when an asset is bought in a bundle, on credit, by exchange, for shares or built in-houseApply the cost principle to lump-sum purchases, deferred payment, asset exchanges, share issues and self-constructed assets.
- Build the initial cost of an item from its elements
- Identify qualifying assets and eligible borrowing costs, fix the capitalization period, and calculate the borrowing costs added to cost from specific and general borrowings under IAS 23.
- Decide which borrowing costs are capitalized and for which periodRecognize qualifying assets and eligible borrowing costs, and apply the rules for starting, suspending and ending capitalization.
- Calculate the borrowing costs to capitalize from specific and general borrowingsApply the specific-borrowing method and the capitalization rate to weighted expenditures, respect the limit of costs incurred, and record the result.
- Decide which borrowing costs are capitalized and for which period
- Recognize government grants when it is reasonably assured they will be received and their conditions met, match them to the costs they compensate, present grants related to assets, and account for repayments under IAS 20.
- Recognize grants and account for grants related to incomeApply the definition and recognition criteria of IAS 20, match grants to the costs they compensate, and handle non-monetary grants and below-market government loans.
- Account for grants related to assets and for repaymentsPresent asset grants as deferred income or as a deduction from the asset, release them over the asset's life, and account for a grant that becomes repayable.
- Recognize grants and account for grants related to income
- Depreciate significant parts separately, separate repairs from capital spending, revise estimates prospectively, and measure the gain or loss when an item leaves the books.
- Depreciate significant parts of an asset separatelySplit an asset's cost into significant components, depreciate each over its own life, and keep land apart from buildings.
- Separate repairs from capital spending, part replacements and major inspectionsApply the recognition principle to costs after acquisition: expense day-to-day servicing, capitalize replacements and major inspections, and remove the parts they replace.
- Review useful life, residual value and method, and revise depreciationStart and stop depreciation at the right dates, review estimates every year, and account for revisions prospectively as changes in estimate.
- Derecognize an item and measure the gain or lossRemove an item that is sold or no longer useful, update depreciation to the disposal date, and recognize the gain or loss and any compensation received.
- Depreciate significant parts of an asset separately
- Choose between the cost and revaluation models, record revaluations by class at fair value, treat increases and decreases correctly, and depreciate revalued assets and transfer the surplus.
- Choose the revaluation model and record a revaluationApply the revaluation model to a whole class of assets at fair value, decide how often to revalue, and adjust accumulated depreciation on the revaluation date.
- Record revaluation increases and decreasesDecide which part of a revaluation change goes to other comprehensive income and which to profit or loss, asset by asset.
- Depreciate a revalued asset and transfer the surplus to retained earningsBase depreciation on the revalued amount, make the optional yearly transfer of the surplus within equity, and treat the surplus when the asset is sold.
- Choose the revaluation model and record a revaluation
- Distinguish investment property from owner-occupied property and inventory, measure it under the fair value or cost model, and account for transfers and disposals under IAS 40.
- Tell investment property apart from owner-occupied property and inventoryApply the IAS 40 definition to rentals, land banks, mixed-use buildings, buildings with services and group property, and explain why its accounting differs.
- Measure investment property and account for transfers and disposalsMeasure investment property at cost initially, apply the fair value or cost model afterwards, and account for changes in use and disposals.
- Tell investment property apart from owner-occupied property and inventory
Property, Plant and Equipment study guide
1Build initial asset cost
An asset's cost is more than its invoice price. The amount recorded depends on what was needed to make it work, when it became ready, and how it was acquired. Build that amount by separating asset costs, expenses, tax receivables and financing. Purchases made in bundles, on extended credit or through an exchange need an extra measurement step before depreciation can begin.
1.1 Build the cost before the asset is ready
A machine's recorded cost captures the resources needed to make it capable of operating as intended. Spending that helps sell its output or train its operators serves a different purpose and goes to expense.
Recognize the asset
Property, plant and equipment (PP&E) consists of tangible items held for production, supply, rental or administration and expected to be used for more than one period. Recognize an item when future economic benefits are probable and cost can be measured reliably. Judgment sets the unit of account: small tools may form a group. A spare engine used over several years can be PP&E; ordinary consumable spares are inventory.
Sort the spending
Cost includes the price after discounts and rebates, import duties and non-refundable taxes. Add delivery, site preparation, installation, technical testing and directly related professional fees. Recoverable purchase tax is a receivable. Staff training, launch advertising, opening costs and general administration are expenses.
Capitalization ends when the asset reaches the location and condition needed to operate as intended. A usable machine waiting for customers is already ready. Its idle costs, early operating losses, and later relocation costs stay out of its carrying amount.
Products made during testing have their own accounting. Record their sales proceeds and production costs in profit or loss. Do not deduct the sales proceeds from the machine's cost. Testing checks physical and technical performance, so waiting for profitable output does not extend the capitalization period.
Work through the cost
A machine has a $240,000 list price and a 10% discount. Its purchase price is $216,000. Add import duty of $6,000, delivery of $3,500, site preparation of $4,000, installation of $7,500, testing of $2,000 and an engineer's fee of $3,000. These amounts total $242,000.
The company must remove the machine in 10 years for an estimated $20,000. At 5%, the present value is $12,278, rounded at the end. The total machinery cost is $254,278. The removal obligation is a separate liability:
- Dr Machinery $12,278
- Cr Provision for dismantling $12,278
Recoverable tax of $21,600 is recorded separately as a receivable. Training of $1,800 and advertising of $5,000 produce a $6,800 expense. Test-sale proceeds of $1,200 go to profit or loss, alongside the cost of the samples sold.
Follow the dismantling provision
The $12,278 added to the asset is depreciated with the machine. The provision grows as payment draws closer. First-year unwinding is 5% of $12,278, or $614 after rounding:
- Dr Finance cost $614
- Cr Provision for dismantling $614
This passage-of-time charge is a finance cost. Under the cost model, a later change in the estimated obligation adjusts the asset's cost; a decrease beyond the asset's carrying amount is recognized in profit or loss. Keep the provision calculation separate from ordinary repairs so neither the liability nor the asset is omitted.
Key Takeaways
- Cost includes the net price, directly attributable preparation costs and the initial dismantling obligation.
- Recoverable purchase taxes are receivables; training and launch advertising are expenses.
- Stop capitalizing when the asset is capable of operating as intended.
- Testing sales and their production costs belong in profit or loss.
- Discount a future dismantling obligation; unwind the discount as a finance cost.
1.2 Measure purchases with special payment terms
The way an asset is paid for does not always reveal its cost. A single payment may buy several assets, while a future payment may include financing. Identify the economic transaction before choosing the amount to capitalize.
Allocate a bundle
For a lump-sum purchase, allocate the total price using relative fair values:
Land, a building and equipment cost $1,800,000 together. Their fair values are $600,000, $1,200,000 and $200,000, totaling $2,000,000. The shares are 30%, 60% and 10%, so record $540,000 as land, $1,080,000 as building and $180,000 as equipment. The allocation matters because land usually is not depreciated and the other assets have different lives.
Separate credit from cost
Payment beyond normal credit terms is measured at the cash price equivalent. A machine available for $300,000 now or $330,000 in one year is initially recorded at $300,000:
- Dr Machinery $300,000
- Cr Payable $300,000
The $30,000 difference becomes interest over the year. If a cash price is unavailable, discount the promised payments at a market rate. Interest is added to the asset only when IAS 23's capitalization rules apply. Using the full future payment as cost would overstate depreciation and hide financing expense.
Measure an exchange
Use fair value when an exchange has commercial substance and at least one asset's fair value is reliably measurable. Commercial substance means a significant change in the risk, timing or amount of future cash flows, or in the entity-specific value of the business affected. A different physical item alone does not establish that change.
Use the fair value of the asset given up unless the received asset's fair value is more clearly evident. An old truck has cost of $90,000, accumulated depreciation of $60,000 and fair value of $34,000. With $50,000 cash paid, the new truck costs $84,000 and the gain is $4,000:
- Dr New truck $84,000
- Dr Accumulated depreciation $60,000
- Cr Old truck $90,000
- Cr Cash $50,000
- Cr Gain on exchange $4,000
If the exchange lacks commercial substance, or neither fair value is reliable, use the old carrying amount plus cash: $30,000 plus $50,000 gives $80,000, with no gain. Under US GAAP, cash of at least 25% of the exchange's fair value makes it monetary for both parties; the $50,000 here exceeds that threshold, so the US result is $84,000 even without commercial substance.
Shares and construction
For an asset acquired by issuing shares, use the asset's fair value under IFRS 2; use the shares' fair value only if the asset's cannot be estimated reliably. Land worth $150,000 acquired for 10,000 shares of $1 par value gives Dr Land $150,000; Cr Share capital $10,000; Cr Share premium $140,000. Par value sets the equity split, not the land's cost.
Self-construction includes materials, direct labor and directly attributable production overhead. Materials of $400,000, labor of $250,000 and relevant overhead of $60,000 give cost of $710,000. Expense $15,000 of abnormal waste and $30,000 of head-office costs. An outside quotation of $800,000 does not create internal profit; eligible borrowing costs are added separately.
Key Takeaways
- Allocate a bundle using each asset's share of total fair value.
- Separate extended-credit interest from the cash price equivalent.
- Fair-value exchange accounting requires commercial substance and reliable fair value.
- A carrying-amount exchange does not recognize a gain.
- An asset acquired for shares is measured using the asset's reliable fair value.
- Self-construction excludes abnormal waste, general administration and internal profit.
2Capitalize borrowing costs
A long construction project can tie up borrowed money for months or years. IAS 23 makes the related borrowing costs part of a qualifying asset's cost during its preparation. The key decisions are which asset qualifies, which dates count, and which funding method applies. A timeline fixes the eligible period; a separate calculation then measures the interest to add to construction in progress.
2.1 Set the borrowing-cost timeline
Borrowing costs directly attributable to preparing a qualifying asset become part of its cost under IAS 23. Capitalization is required. Interest on an asset that is already ready for use is an expense.
Identify a qualifying asset
A qualifying asset necessarily takes a substantial period to prepare for its intended use or sale. A power plant, a long construction project or inventory requiring lengthy production can qualify. A ready-to-use machine, financial asset or quickly manufactured inventory does not. There is no automatic rule that every expensive asset qualifies.
IAS 23 permits an exemption for qualifying assets measured at fair value and inventories produced in large quantities repetitively. Otherwise, eligible costs must be capitalized. Borrowing costs include effective-interest charges, interest on lease liabilities and foreign-exchange differences to the extent they adjust interest costs. Dividends and a return imputed on the company's own money are not borrowing costs.
Start when three conditions meet
Capitalization begins when the company simultaneously incurs asset expenditures and borrowing costs and undertakes activities needed to prepare the asset. Necessary activities can be technical or administrative. Obtaining permits and designing the building can count before physical construction begins. Buying land and holding it without development activity does not start capitalization.
A timeline helps identify the first date on which all three conditions exist. The loan date alone may be too early; the first day on the construction site may be too late if meaningful preparation is already underway.
Suspend for an extended interruption
Suspend capitalization during an extended period without active development. Interest during a three-month planning dispute is expensed if preparation has stopped. Do not suspend while substantial technical or administrative work continues. A delay that is a necessary part of construction, such as normal seasonal high water at a bridge site, also does not require suspension.
The cause and activity matter together. A site can look quiet while design work continues, so physical inactivity alone does not settle the accounting.
Stop at substantial completion
Cease capitalization when substantially all preparation is complete. Minor decoration or routine paperwork does not keep the period open, and waiting for the first customer does not extend it. For independently usable sections, stop separately when each section is ready. For an integrated plant whose sections cannot work alone, stop when the combined asset is ready.
Apply the dates
A warehouse project starts on March 1, 2025, with spending, borrowing costs and preparation all underway. Work stops for a planning dispute from July 1 through September 30. It resumes on October 1 and finishes on February 28, 2026. The first tenant arrives May 1.
Eligible months are March–June 2025 (four months) and October 2025–February 2026 (five months). Capitalize nine months in total. Expense the three-month stoppage and interest from March 1, 2026 onward. Interest in March and April 2026 remains an expense even though the warehouse has not yet earned rental income.
Key Takeaways
- A qualifying asset necessarily takes substantial time to become ready.
- Start only when expenditures, borrowing costs and preparation activities coexist.
- Suspend during extended inactive development, with exceptions for necessary delays and continuing technical work.
- Stop at substantial completion, including separately usable parts.
2.2 Calculate specific and general borrowing costs
After setting the eligible period, match the funding to the calculation. A project loan has identifiable costs. General borrowing requires a weighted rate and time-weighted asset expenditures.
Use a specific loan
For funds borrowed specifically for a qualifying asset, capitalize actual borrowing costs during the eligible period less income from temporarily investing those funds. A $3,000,000 loan at 6% finances a distribution center built throughout 2025. Interest is $180,000 and temporary investment income is $20,000, leaving $160,000 capitalized.
One way to record the amounts is:
- Dr Construction in progress $180,000; Cr Interest payable $180,000.
- Dr Cash $20,000; Cr Construction in progress $20,000.
The net addition to construction is $160,000. US GAAP generally does not make this investment-income deduction when measuring capitalized interest under ASC 835-20.
Find a general borrowing rate
A company has a $4,000,000 loan at 5% and $6,000,000 of bonds at 7.5%, both outstanding all year. Annual interest is $200,000 plus $450,000, totaling $650,000. Divide that by total debt of $10,000,000 to obtain 6.5%. A simple average of 5% and 7.5% would ignore the larger bond balance.
If debt balances change during the period, time-weight them in the rate calculation. Exclude a specific construction loan from the general pool until substantially all preparation of its asset is complete. If that loan remains outstanding afterward, it joins the pool for other qualifying assets.
Weight the expenditures
For a store still being built at year-end, expenditures are $1,200,000 on March 1, $1,800,000 on July 1 and $600,000 on November 1. Weight each for its eligible months outstanding:
| Payment | Weight | Weighted expenditure |
|---|---|---|
| $1,200,000 | 10/12 | $1,000,000 |
| $1,800,000 | 6/12 | $900,000 |
| $600,000 | 2/12 | $100,000 |
Weighted expenditures total $2,000,000. At 6.5%, capitalized borrowing costs are $130,000. Only cash payments, transfers of other assets and interest-bearing liabilities enter qualifying expenditures. Deduct grants and progress payments received for the asset, with their timing reflected in the weighting.
Check the limit and entry
Capitalization cannot exceed borrowing costs actually incurred. Here $130,000 is below $650,000. Record:
- Dr Construction in progress $130,000
- Dr Interest expense $520,000
- Cr Interest payable $650,000
For mixed funding, identify the part financed by the specific loan first. Apply the general rate only to the expenditure financed from general funds; do not charge both funding methods to the same spending. Keep a record of the dates and funding allocation so the specific loan is not also included in the general rate.
Capitalized interest becomes part of the completed asset. It reaches profit or loss through depreciation when the asset becomes available for use, or through cost of sales for qualifying inventory. Capitalization changes timing; it does not remove the cost from accounting.
Key Takeaways
- Specific-loan capitalization deducts temporary investment income under IAS 23.
- Weight general debt balances when calculating the capitalization rate.
- Weight eligible expenditures for their eligible time outstanding.
- Grants and progress payments reduce qualifying expenditures.
- Do not capitalize more borrowing costs than were incurred.
- Apply specific and general funding to different portions of expenditure.
3Account for government support
Government support can pay for wages, equipment or other operating costs. The accounting follows the grant's conditions and the costs it compensates, so receiving cash and earning income can happen in different periods. IAS 20 provides recognition rules and presentation choices. Those choices affect the reported asset, liability and expense lines, while a later repayment can create an immediate charge to profit.
3.1 Recognize grants as the related costs arise
A government grant transfers resources in return for meeting conditions connected with operating activities. Government may act through local, national or international agencies. A normal sale to a government customer remains a trading transaction.
Decide when to recognize
IAS 20 requires reasonable assurance both that the grant will be received and that its conditions will be met. Receiving cash alone does not establish compliance. A forgivable government loan becomes a grant when reasonable assurance exists that the forgiveness conditions will be satisfied.
Assistance that cannot reasonably be valued, such as free technical advice, is disclosed as government assistance instead of recorded as a grant. The grant rules apply to measurable resource transfers within IAS 20.
Match income to the costs
Recognize a grant in profit or loss systematically over the periods in which the compensated costs are expensed. A grant is not an owner's contribution and cannot be credited directly to equity.
A company receives $60,000 on January 1, 2025 to fund trainee wages over two years. Reasonable assurance exists and the wages arise evenly. The receipt creates deferred income:
- Dr Cash $60,000
- Cr Deferred grant income $60,000
At the end of 2025, release $30,000:
- Dr Deferred grant income $30,000
- Cr Grant income $30,000
The remaining $30,000 is released as the 2026 wages are expensed. Grant income may appear separately, in other income, or as a deduction from the related expense. Those choices change presentation but leave profit the same.
A grant for costs already incurred, or immediate support with no future related costs, is recognized when receivable. A $25,000 award compensating flood losses already expensed is income in the period it becomes receivable; do not reopen the earlier year's loss.
Measure non-cash support
A non-monetary grant, such as land, is usually measured at fair value. Record both the land and grant at that amount. IAS 20 also permits a nominal amount for both. Keep the measurement choice consistent between the resource and the grant; recording a fair-value asset with a nominal grant would break that pairing.
Separate a subsidized loan
A below-market government loan contains a borrowing and a grant benefit. Measure the loan initially at fair value under IFRS 9. The excess of cash received over that initial liability is the grant, recognized in line with the costs it supports.
For a three-year $1,000,000 loan at 1% with annual interest, discounted at a 6% market rate, the present value of the $10,000 annual payments is $26,730 and the final principal is $839,619. The initial loan is $866,349 and the grant is $133,651:
- Dr Cash $1,000,000
- Cr Loan liability $866,349
- Cr Deferred grant income $133,651
First-year effective interest is $51,981 after rounding, although cash interest is $10,000. The difference increases the loan liability.
US GAAP comparison
ASU 2025-10 adds grant accounting to Topic 832 with a probable recognition threshold. It is mandatory for public business entities for annual periods beginning after December 15, 2028, and for other business entities after December 15, 2029; early adoption is permitted. It builds on IAS 20 but is not identical, so the IFRS reasonable-assurance test remains the rule for this calculation.
Key Takeaways
- Recognize a grant only with reasonable assurance of receipt and compliance.
- Recognize income in the periods of the compensated expenses.
- A grant is not credited directly to equity.
- Recognize compensation for past costs when the grant becomes receivable.
- A below-market loan separates a fair-value liability from a grant benefit.
3.2 Present asset grants and account for repayment
An asset grant's primary condition is the purchase, construction or acquisition of a long-term asset. IAS 20 allows two ways to present it. Both spread the benefit over the periods that bear the related costs.
Compare the two presentations
A machine costs $500,000, has a five-year life and no residual value. A $100,000 grant supports its purchase. Depreciation is straight-line.
| Presentation | Annual depreciation | Annual grant income | Net annual charge |
|---|---|---|---|
| Deferred income | $100,000 | $20,000 | $80,000 |
| Deduct from asset | $80,000 | None separately | $80,000 |
Under deferred income, record the machine at $500,000 and the grant as a $100,000 liability. At the end of year 1, the asset is $400,000 and deferred income is $80,000. Of that liability, $20,000 is current because it will be released next year; $60,000 is non-current.
Under the deduction method, initially record the asset net at $400,000. After $80,000 depreciation, its carrying amount is $320,000. The same profit arises through different income-statement lines and different asset and liability balances. Do not deduct the grant from cost and also recognize separate grant income: that would count its benefit twice.
Cash-flow presentation can show the asset payment and grant receipt separately, making the gross investment visible whichever balance-sheet presentation is used.
Follow the cost pattern
Release the grant in the same pattern as depreciation. A reducing-balance asset needs a matching release pattern, not an automatic equal annual amount. Several grant conditions may create different expense patterns, requiring portions of the grant to be recognized on different bases.
Land is usually not depreciated, but its grant can still support future costs. Land worth $400,000 is provided on condition that the company builds a factory with a 40-year useful life. Recognize the grant over the factory's life at $10,000 a year from when the factory is in use. Receipt of non-depreciable land does not make the grant immediate income.
Record a repayment
A grant becoming repayable is a change in estimate. For an income grant, use any remaining deferred income first and expense the excess. For an asset grant, reduce deferred income or increase the asset, with the cumulative extra depreciation recognized immediately.
Suppose the full machine grant becomes repayable after two years. Under deferred income, $60,000 remains and $40,000 has been released:
- Dr Deferred grant income $60,000
- Dr Grant repayment expense $40,000
- Cr Liability to government $100,000
Under deduction, the asset stands at $240,000. Restore the $100,000 grant to the asset, then charge $40,000 of extra depreciation, leaving $300,000. Entries are Dr Machinery $100,000; Cr Liability to government $100,000; then Dr Depreciation expense $40,000; Cr Accumulated depreciation $40,000. The $300,000 is the carrying amount that would exist without the grant. Prior years are not restated.
For qualifying construction, a received grant also reduces the expenditures used for borrowing-cost capitalization. Under the new US Topic 832 model, asset grants may use a deferred income or cost accumulation approach, with the latter reducing the asset's carrying amount.
Key Takeaways
- An asset grant is presented as deferred income or deducted from the asset.
- Both methods give the same net profit but different reported line items and balances.
- Release the benefit in the pattern of the related costs.
- Repayment uses deferred income first; an excess reaches profit or loss immediately.
- A repayment under the deduction method restores cost and recognizes cumulative extra depreciation.
- A non-depreciable asset's grant can be recognized over the costs of meeting its conditions.
4Manage assets under the cost model
An asset can contain parts that wear out on different schedules. Its carrying amount also changes as parts are replaced, inspections are renewed and estimates change. Apply the recognition principle again to later spending, keep depreciation tied to the benefits consumed, and remove amounts that no longer belong in the accounts. A disposal calculation starts with an updated carrying amount, including depreciation through the disposal date.
4.1 Depreciate significant components separately
An asset can stay in service for decades while some of its parts need replacement much sooner. Component depreciation assigns the cost of each significant part to the periods that consume that part's benefits.
Split cost before calculating depreciation
Under IAS 16, separately depreciate each part whose cost is significant relative to the whole asset. An aircraft may have separate airframe, engine and cabin components. A building may have a structure, roof, elevators and heating system. The total cost does not change when it is split.
Parts sharing the same useful life and depreciation method can be grouped. Remaining parts that are individually insignificant can form one group, using reasonable approximation. A company may also choose to separate a part that is not significant.
The cost-model carrying amount is cost less accumulated depreciation and impairment losses. The depreciable amount is cost less residual value. Residual value estimates today's net disposal proceeds for an asset already at its expected end-of-life age and condition. Useful life reflects expected use by this entity, which can be shorter than physical life.
Work through an aircraft
An aircraft costs $60,000,000. Allocate $36,000,000 to the airframe, $18,000,000 to engines and $6,000,000 to the cabin. Straight-line depreciation is calculated separately:
| Part | Cost less residual | Life | Annual charge |
|---|---|---|---|
| Airframe | $36,000,000 − $6,000,000 | 25 years | $1,200,000 |
| Engines | $18,000,000 − $2,000,000 | 8 years | $2,000,000 |
| Cabin | $6,000,000 − $0 | 5 years | $1,200,000 |
The total is $4,400,000 a year. Treating the whole aircraft as one 25-year asset with an $8,000,000 residual would give $2,080,000. That slower charge would leave too much engine and cabin cost in the asset during the early years.
The component records also identify what to remove when an engine is replaced. Without them, a company may capitalize the replacement while leaving the old engine in its carrying amount.
Separate land from a building
A $5,000,000 property includes land worth $2,000,000. The building's $3,000,000 cost over 40 years gives annual depreciation of $75,000 with no residual value. Depreciating the whole property would incorrectly charge $125,000.
Land usually has unlimited life and is not depreciated. Depleting sites, such as quarries or landfill sites, are exceptions. A rise in land value does not reduce the building's depreciable amount: the two are separate assets.
Choose the consumption pattern
Use the method that reflects how each component's benefits are consumed. Straight-line, reducing-balance and units-of-production methods can fit different patterns. A revenue-based depreciation method is prohibited for PP&E because sales revenue also reflects prices, demand and inflation. Higher sales prices do not by themselves mean the machine has used up more of its service potential.
US GAAP permits component depreciation but does not require it. Under IFRS, significant parts must receive separate treatment even if a single whole-asset life would be easier to calculate.
Key Takeaways
- Separately depreciate significant parts with different lives or methods.
- Grouping parts is appropriate when their lives and methods match.
- Component allocation changes depreciation timing, not total asset cost.
- Land and buildings are separate; land is usually not depreciated.
- A revenue-based depreciation method is prohibited for PP&E.
4.2 Replace parts without counting them twice
Later spending needs the same recognition test as initial cost: probable future economic benefits and reliable measurement. The label on an invoice does not decide whether the amount becomes an asset.
Expense routine servicing
Day-to-day servicing includes labor, consumables and small parts used to keep an asset operating. Record repairs and maintenance expense when incurred. A large annual maintenance bill is still an expense if it represents ordinary servicing. Relocating equipment or reorganizing operations also does not add to the equipment's carrying amount.
A replacement of an identifiable part can qualify as an asset even if described as a repair. A new roof or furnace lining brings benefits over its own service period. Capitalize the new part and derecognize the old part's remaining carrying amount. Both actions are needed.
Remove the replaced component
A building cost $3,000,000, including a $300,000 roof with a 15-year life and no residual value. Straight-line yearly depreciation is $20,000. After 10 years, accumulated roof depreciation is $200,000 and its carrying amount is $100,000.
The company installs a new roof for $420,000. Remove the old roof:
- Dr Accumulated depreciation—roof $200,000
- Dr Loss on derecognition $100,000
- Cr Building—old roof $300,000
Then recognize the replacement:
- Dr Building—new roof $420,000
- Cr Cash $420,000
The building's carrying amount increases by a net $320,000, not $420,000. The $100,000 loss records the old roof's unused cost. Depreciate the new roof over its own useful life from when it is available for use.
The old component must be removed even if it was not separately identified at acquisition. When its carrying amount is unknown, use replacement cost as an indication of the original cost, then allow for depreciation through the replacement date. The estimate needs to represent the old component at acquisition; today's price is evidence, not automatically the old carrying amount.
Treat a major inspection as a component
A major inspection required to keep operating can create a service benefit until the next inspection. Capitalize it when recognition criteria are met and remove the previous inspection component's remaining carrying amount. No physical part has to be replaced for this rule to apply.
A ship costs $10,000,000. A required inspection every three years is expected to cost $600,000, identifying that portion within the purchase price. With no residual values, annual depreciation is $200,000 for the inspection and $470,000 for the remaining $9,400,000 structure over 20 years.
After three years, the first inspection component is fully depreciated and removed. The next inspection costs $660,000, producing a new component depreciated at $220,000 a year until the next inspection. If a previous inspection still had a balance, that balance would be expensed on replacement. Capitalizing each new inspection while retaining the previous one's balance would report overlapping rights to the same operating period.
Key Takeaways
- Routine servicing is expensed even when its total cost is large.
- Capitalize a qualifying replacement and remove the old part's carrying amount.
- Estimate the old component when it was not separately recorded.
- A required major inspection can be a depreciable component.
4.3 Revise depreciation from the date estimates change
Useful life and residual value are estimates about future use and disposal. New information can change them without making the earlier estimates errors. Start with the carrying amount at the change date.
Use the right start and stop dates
Depreciation begins when an asset is available for use: in the location and condition needed to operate as intended. The first production date or first sale may come later. It ceases at the earlier of derecognition and classification as held for sale under IFRS 5.
Temporary idleness does not stop time-based depreciation. A machine can lose service potential through age and obsolescence even while unused. Under units of production, the charge can be zero when no output is produced. Once an asset is fully depreciated, no further depreciable amount remains.
Review three estimates
Review useful life, residual value and depreciation method at least at each financial year-end. Useful life is the remaining period or output expected from the asset. Residual value uses the net disposal proceeds expected for the asset's end-of-use age and condition, assessed using current prices. The method reflects consumption of benefits.
A revised life, residual value or method is a change in accounting estimate under IAS 8. Apply it prospectively to the carrying amount from the date of change. Do not recalculate all prior depreciation using the newly estimated total life.
Recalculate the future charge
A machine cost $500,000 on January 1, 2021. Its original life was 10 years and residual value $50,000. Annual straight-line depreciation was $45,000. Four years of charges total $180,000, leaving $320,000 on January 1, 2025.
New information now supports four more years of use and a $40,000 residual value. For straight-line depreciation, use the revised residual and remaining life:
Here the remaining depreciable amount is $280,000, giving $70,000 a year from 2025:
- Dr Depreciation expense $70,000
- Cr Accumulated depreciation $70,000
No catch-up charge is needed for 2021–2024. The old $45,000 reflected the estimates then in place. A method change follows the same prospective principle: apply the new pattern to the carrying amount at the change date.
If residual value rises to at least the carrying amount, depreciation is zero until residual value falls below that carrying amount. A residual estimate does not increase the asset's carrying amount; it changes the amount left to allocate.
Distinguish an estimate from an error
New operating experience or a revised replacement plan supports an estimate change. An arithmetic mistake or failure to use information already available is an error and is corrected retrospectively. Calling a known calculation mistake a new estimate would hide the earlier misstatement.
Depreciation is not always an immediate income-statement expense. Factory machinery depreciation can form inventory cost, and equipment depreciation incurred in constructing a building can form building cost. The destination follows the activity that consumes the asset's benefits.
Key Takeaways
- Start depreciation when available for use, even before actual use.
- Review life, residual value and method at least annually.
- Apply revised estimates prospectively to the current carrying amount.
- An arithmetic mistake is an error, not a new estimate.
- Depreciation may enter another asset's cost when used to produce that asset.
4.4 Update the carrying amount before disposal
Derecognition removes an asset when it is disposed of or when no benefits are expected from either its use or disposal. A sale, donation, scrapping or abandonment can therefore end asset recognition.
Calculate in date order
First record depreciation to the disposal date. Then calculate the carrying amount and compare it with net proceeds. The resulting gain or loss belongs in profit or loss. Ordinary PP&E disposal gains are not revenue.
A machine cost $80,000 and has accumulated depreciation of $48,000 on January 1, 2025. Its annual depreciation is $8,000. It is sold on June 30 for $36,000, with $1,000 selling costs.
- Six months' depreciation is $4,000.
- Accumulated depreciation becomes $52,000.
- The carrying amount is $28,000.
- Net proceeds are $35,000, giving a $7,000 gain.
Record depreciation before removing the asset:
- Dr Depreciation expense $4,000
- Cr Accumulated depreciation $4,000
Then record the net cash and remove both cost and accumulated depreciation:
- Dr Cash $35,000
- Dr Accumulated depreciation $52,000
- Cr Machinery $80,000
- Cr Gain on disposal $7,000
Using the January carrying amount of $32,000 would give only a $3,000 gain and omit the current depreciation. Omitting selling costs would overstate the gain by $1,000.
Identify when the sale occurs
The disposal date is when the buyer obtains control, using IFRS 15's control principles. Signing an agreement or receiving a deposit does not necessarily transfer control. Measure the consideration using the transaction-price rules. If payment is deferred and includes financing, use its cash price equivalent for disposal proceeds and recognize the remainder as interest income over time.
Keep compensation separate
The loss of an asset, a third-party compensation claim and the acquisition of a replacement are separate events. A warehouse with a $400,000 carrying amount burns down in 2025. Derecognize it and recognize the $400,000 loss in 2025.
If an insurer accepts a $520,000 claim in 2026, recognize compensation income when that amount becomes receivable in 2026. A replacement warehouse has its own cost. An expected insurance recovery does not erase the earlier loss before the compensation is receivable.
Handle two special balances
A company that routinely sells assets previously held for rental transfers them to inventory at carrying amount when rental stops and they become held for sale. A rental-car company's ordinary fleet sales then create revenue under IFRS 15. This differs from an occasional sale of equipment used in production.
For a revalued asset, compare proceeds with the revalued carrying amount, updated for depreciation. Any revaluation surplus remaining in equity can be transferred directly to retained earnings. It is not added to the disposal gain and never passes through profit or loss.
Key Takeaways
- Derecognize on disposal or when no future benefits remain.
- Record depreciation through the disposal date before calculating the gain or loss.
- Compare net proceeds with the updated carrying amount.
- Recognize third-party compensation separately when receivable.
- Routine sales of former rental assets pass through inventory and can generate revenue.
- A remaining revaluation surplus transfers within equity, outside the disposal gain.
5Revalue PP&E and track the surplus
The revaluation model updates a class of property, plant and equipment to fair value. It also creates a history to track for each asset: some changes affect profit or loss, while others affect other comprehensive income and equity. Revaluation changes the basis for future depreciation. Later transfers of the surplus stay within equity, including when the asset is sold, so the surplus and disposal gain need separate calculations.
5.1 Revalue an entire asset class
IAS 16 permits a cost model or a revaluation model after initial recognition. The choice applies to an entire class of assets with similar nature and use, such as machinery or buildings. It cannot be applied only to the individual assets whose values have risen.
Set the measurement policy
Under revaluation, carry an asset at fair value on the revaluation date less later accumulated depreciation and impairment losses. Fair value is an exit price in an orderly transaction between market participants at the measurement date. It is not the owner's special value in use, an insurance amount or a tax valuation.
Market evidence commonly supports land and building values. Specialized assets may require an income or current replacement cost approach. Reliable measurement is required. Revalue often enough to avoid a material gap between carrying amount and reporting-date fair value. Volatile values can require annual revaluation; stable values may permit three- or five-year intervals.
Revalue the class together. A rolling process is permitted when completed within a short period and kept current. This prevents selective gains and inconsistent measurement dates within the same class.
Update accumulated depreciation
A building costs $1,000,000 on January 1, 2024, with a 20-year life, no residual value and straight-line depreciation. On December 31, 2025, accumulated depreciation is $100,000, leaving a $900,000 carrying amount. Fair value is $1,080,000. The increase is $180,000.
The elimination method clears accumulated depreciation against gross cost:
- Dr Accumulated depreciation $100,000
- Cr Building $100,000
This leaves the building at $900,000. Record the increase:
- Dr Building $180,000
- Cr Revaluation surplus through OCI $180,000
Gross cost is now $1,080,000 with zero accumulated depreciation.
Compare proportional restatement
The proportional factor is $1,080,000 divided by $900,000, or 1.2. Multiply gross cost and accumulated depreciation by that factor. Gross becomes $1,200,000; accumulated depreciation becomes $120,000. The entry is:
- Dr Building $200,000
- Cr Accumulated depreciation $20,000
- Cr Revaluation surplus through OCI $180,000
Net carrying amount is again $1,080,000. The methods alter the gross presentation, not the net increase. Comparing fair value directly with original gross cost would miss the depreciation already recognized.
Policy change and disclosures
The first move from cost to revaluation is a policy change treated as a revaluation from that date under IAS 16. Earlier periods are not restated as if the company had always used fair values. Disclose the effective revaluation date, whether an independent valuer participated, and the carrying amount that the class would have had under the cost model.
US GAAP does not permit this upward revaluation model for PP&E. Historical cost less accumulated depreciation and impairment remains the basis, so an IFRS revaluation surplus does not have a direct US PP&E equivalent.
Key Takeaways
- Apply the revaluation policy to a whole class.
- Fair value is a market-participant exit price at the measurement date.
- Revalue often enough to prevent a material reporting-date difference.
- Elimination and proportional adjustment produce the same net carrying amount.
- The first revaluation does not restate earlier periods.
5.2 Route revaluation changes to OCI or profit
The direction of a revaluation is only the first decision. Its destination also depends on earlier revaluations of the same asset. Track that history asset by asset.
Apply the routing rules
An increase goes to other comprehensive income (OCI) and accumulates in equity as a revaluation surplus. However, the part reversing an earlier revaluation loss in profit or loss is recognized in profit or loss first.
A decrease goes to profit or loss unless a credit balance remains in that asset's revaluation surplus. Use that surplus through OCI first, then charge any excess to profit or loss. A surplus on another asset cannot absorb the decrease, even within the same revalued class.
| Current change | First allocation | Remaining amount |
|---|---|---|
| Increase after earlier loss in profit or loss | Reverse that loss in profit or loss | OCI and surplus |
| Decrease with a surplus on the same asset | Reduce surplus through OCI | Loss in profit or loss |
Follow one piece of land
Land costs $500,000 and is not depreciated. At the end of year 1 its fair value is $650,000. The $150,000 increase has no earlier loss to reverse:
- Dr Land $150,000
- Cr Revaluation surplus through OCI $150,000
At the end of year 2 fair value falls to $470,000. The decrease is $180,000. The first $150,000 removes the surplus; the remaining $30,000 is a loss:
- Dr Revaluation surplus through OCI $150,000
- Dr Revaluation loss—profit or loss $30,000
- Cr Land $180,000
At the end of year 3 fair value rises to $560,000. The $90,000 increase first reverses the $30,000 loss, leaving $60,000 for OCI:
- Dr Land $90,000
- Cr Revaluation gain—profit or loss $30,000
- Cr Revaluation surplus through OCI $60,000
The asset ends at $560,000, with a $60,000 surplus. Sending the whole recovery to OCI would fail to reverse the loss that previously reduced profit.
Keep separate histories
Suppose a second parcel has its own $80,000 surplus. It does not change any entry for the first parcel. Class-wide revaluation determines which assets must be measured; asset-specific history determines where each increase or decrease is reported. A single pooled surplus ledger can therefore give the wrong income-statement result.
Revaluation OCI is not subsequently reclassified to profit or loss. The accumulated surplus stays in equity until it is reduced by a later decrease or transferred within equity as the asset is used or derecognized.
Recognize the associated tax effect
If the tax base remains at cost, an upward revaluation creates a taxable temporary difference. On the $150,000 first-year increase and a 25% rate, deferred tax is $37,500. Charge that tax effect to OCI, leaving a net surplus of $112,500. The tax effect follows the location of the revaluation gain; it does not turn the gain into operating revenue.
Key Takeaways
- Route an increase to profit or loss to reverse that asset's earlier loss, then to OCI.
- Route a decrease against the same asset's surplus first, then to profit or loss.
- Do not offset revaluation histories across different assets.
- Revaluation OCI is not recycled to profit or loss.
- Related deferred tax on an OCI increase is also recognized in OCI.
5.3 Depreciate the new amount and track the surplus
Revaluation affects future depreciation even though much of the increase bypasses profit or loss. The asset is consumed at its updated carrying amount, and the surplus is tracked separately in equity.
Use the remaining useful life
A building originally cost $1,000,000 and had a 20-year life with no residual value and straight-line depreciation. After two years, it is revalued from $900,000 to $1,080,000. Eighteen years remain. Annual depreciation from the following year is $60,000, found by dividing the revalued amount by the remaining life.
- Dr Depreciation expense $60,000
- Cr Accumulated depreciation $60,000
Continuing the old $50,000 charge would allocate only the historical-cost amount. Revaluation does not restart the original 20-year life. Review residual value and remaining life as usual, then use those current estimates.
Transfer the realized portion within equity
The company may transfer part of the surplus to retained earnings as the asset is used. The transfer equals depreciation on the revalued amount less depreciation on original cost. Here the difference is $10,000 each year:
- Dr Revaluation surplus $10,000
- Cr Retained earnings $10,000
This transfer is optional. It is neither income nor an offset against depreciation expense. Profit includes the full $60,000 charge; the equity entry only changes the labels within total equity. If no annual transfer is made, the surplus remains until a later permitted transfer or revaluation decrease.
Where deferred tax was recognized on the surplus, transfer the amount net of the related deferred tax. At 25%, a $10,000 excess-depreciation amount gives a $7,500 equity transfer.
Separate disposal from the remaining surplus
The building is sold two years after revaluation for $1,000,000. Two $60,000 depreciation charges reduce its carrying amount to $960,000. The disposal gain is $40,000, measured against that revalued carrying amount.
With annual transfers, $160,000 remains in the original $180,000 surplus after two $10,000 transfers. It may be moved directly to retained earnings on derecognition:
- Dr Revaluation surplus $160,000
- Cr Retained earnings $160,000
Adding the surplus to the $40,000 gain would recycle it into profit or loss, which IAS 16 does not allow. Without annual transfers, the full remaining $180,000 could instead be transferred within equity on disposal.
Compare the profit pattern
Under historical cost, four years of $50,000 depreciation leave an $800,000 carrying amount and a $200,000 disposal gain. The total depreciation and gain net to zero across the four years.
Under revaluation, depreciation totals $220,000: $100,000 before revaluation and $120,000 afterward. The $40,000 gain leaves a net $180,000 charge to profit or loss. The separate $180,000 revaluation increase went through OCI. Total equity reaches the same endpoint, but its route through profit, OCI and equity transfers differs.
Key Takeaways
- Depreciate the revalued amount over the remaining useful life.
- An optional annual transfer equals excess depreciation, net of related deferred tax.
- Surplus transfers stay within equity and do not reduce depreciation expense.
- Measure disposal gain against the revalued carrying amount.
- A remaining surplus may transfer to retained earnings on derecognition, without recycling.
6Classify and measure investment property
A building's accounting depends on how it is used. Rental income and long-term growth in value point toward investment property; production, administration and ordinary property sales point elsewhere. IAS 40 then offers a fair value model with a different profit pattern from IAS 16 revaluation. Classify the property first, apply the chosen measurement model, and revisit classification when evidence shows an actual change in use.
6.1 Classify a property's actual use
Investment property is land or a building held to earn rentals, for capital appreciation, or both. Its cash flows arise largely independently of the entity's other assets. An operating factory earns returns together with the production business, so it is owner-occupied PP&E.
Distinguish three purposes
IAS 40 investment property includes land held for long-term appreciation, land with an undecided future use, a building leased out under operating leases and a vacant building held for such rentals. Property under construction for future investment use is already within IAS 40. The holder can be an owner or a lessee holding a right-of-use asset.
Property used for production, administration or employee accommodation is owner-occupied PP&E. Property reserved for future owner-occupation is also PP&E. Property developed for ordinary-course sale is inventory under IAS 2. Property leased out under a finance lease produces a lessor receivable instead of investment property.
| Use | Classification |
|---|---|
| Office building held for independent tenants | Investment property |
| Building used as the company's headquarters | PP&E |
| Apartments built by a developer for ordinary sale | Inventory |
A rise in market value does not override the property's use. A headquarters remains PP&E while it is occupied by the owner, even if its value is rising quickly.
Divide mixed-use property when possible
When rented and owner-used portions can be sold separately, account for them separately. The same applies if the portions could be leased separately under finance leases.
A 10-floor building has eight equal-value floors rented to outsiders and two used for the owner's head office. If floors can be sold separately, 80% is investment property and 20% PP&E. If they cannot be separated, classify the whole property as investment property only when owner use is insignificant. Here 20% is significant, so the whole inseparable building is PP&E.
This judgment turns on separability and the significance of owner use. A simple majority-of-floor-space test is not the IAS 40 rule.
Consider services to occupants
Security and maintenance that are insignificant to a rental arrangement do not prevent investment-property treatment. Significant services change the nature of the activity. An owner-operated hotel supplies accommodation together with substantial guest services and is PP&E. Income from occupants alone does not make every property investment property.
Choose the reporting perspective
A subsidiary leases a building to its parent for offices. In the subsidiary's own statements, the property can be investment property because it is rented to another entity. In consolidated statements, the group occupies the offices, so the property is owner-occupied PP&E.
Disclose the classification criteria when judgment is difficult. The classification sets up the later measurement decision; it is not a free choice based on which model gives the preferred profit. Under US GAAP, most entities have no separate investment-property category and carry rental real estate at depreciated cost.
Key Takeaways
- Investment property earns rentals or capital appreciation, independently of operating assets.
- Property developed for ordinary sale is inventory; owner-use property is PP&E.
- Separate mixed-use portions when they can be sold separately.
- Significant owner-provided services can make a property PP&E.
- An intragroup rental can be investment property individually but PP&E on consolidation.
- Undecided-use land is investment property.
6.2 Measure investment property and track changes in use
Investment property starts at cost, including directly related transaction costs such as legal fees and transfer taxes. After initial recognition, choose the fair value or cost model as the policy for investment property.
Compare the models
Under the fair value model, remeasure at every reporting date. Changes go to profit or loss and no depreciation is charged. A building purchased for $5,000,000 with $150,000 transaction costs starts at $5,150,000. A year-end fair value of $5,400,000 gives:
- Dr Investment property $250,000
- Cr Fair value gain—profit or loss $250,000
If the next year-end value is $5,250,000, record a $150,000 loss in profit or loss. This is different from IAS 16 revaluation: there is no revaluation surplus for these subsequent IAS 40 fair value changes.
The cost model uses cost less accumulated depreciation and impairment, with fair value disclosed in the notes. Under the fair value model, measurement generally covers all investment property. In the exceptional case of an acquired or completed property's reliably unmeasurable fair value, that property uses cost until disposal. A policy switch from fair value to cost rarely meets the requirement for more relevant information.
Include investment property under construction
Construction for future investment use is within IAS 40. Under the fair value model, use fair value during construction when reliably measurable. If it is not yet reliable but is expected to become reliable at completion, carry cost only until reliable measurement becomes possible or construction finishes, whichever is earlier. Completion is not an automatic reason to defer a fair value already measurable during construction.
Transfer only on evidence of changed use
An intention alone is insufficient. Owner occupation beginning, owner occupation ending, development for ordinary sale beginning, or inventory being leased out under an operating lease can provide evidence. Deciding to sell an investment property without development does not itself turn the property into inventory.
For a fair-value investment property becoming PP&E or inventory, fair value at the transfer date is deemed cost. From inventory into fair-value investment property, the difference between carrying amount and fair value goes to profit or loss.
For owner-occupied PP&E becoming fair-value investment property, apply IAS 16 through the transfer date. Treat the transfer-date difference as an IAS 16 revaluation, including the same-asset reversal rules. Later fair value changes follow IAS 40 in profit or loss.
Record a transfer and disposal
A company leaves its office building and rents it to an outside tenant. Cost is $3,200,000 and accumulated depreciation is $800,000 at transfer. Fair value is $3,000,000, with no previous revaluation loss. Record:
- Dr Investment property $3,000,000
- Dr Accumulated depreciation $800,000
- Cr Building $3,200,000
- Cr Revaluation surplus through OCI $600,000
That transfer-date surplus remains in equity and may transfer to retained earnings on disposal. Subsequent fair value gains go to profit or loss.
On disposal, compare net proceeds with carrying amount. A property carried at $5,250,000 sells for $5,300,000 with $80,000 selling costs. Net proceeds are $5,220,000, producing a $30,000 loss in profit or loss.
Key Takeaways
- Initial cost includes transaction costs.
- The fair value model records changes in profit or loss without depreciation.
- The cost model depreciates and discloses fair value.
- Reliably measurable fair value can apply during construction.
- Transfers require evidence of an actual change in use.
- A PP&E-to-fair-value investment-property transfer follows IAS 16 at the transfer date.
- Disposal gain or loss uses net proceeds less carrying amount.
Property, Plant and Equipment examples
1Build and check initial asset cost
13 steps
- 1IntroductionFind the amount that belongs in the asset
An asset purchase often contains several accounting events. A delivery payment may enter machinery cost, tax may become a receivable, and training may be an expense. Adding only the costs that make the asset ready is capitalization, and it sets the base for depreciation.
Follow a machine from its invoice to readiness, then compare acquisitions paid for with a bundle price, credit, another asset or shares. The aim is a cost that represents the asset acquired.
- 2ExplanationCheck recognition and purpose
PP&E is tangible, held for operating, rental or administrative use, and expected to serve more than one period. Recognize it when future benefits are probable and cost is reliably measurable.
A long-term spare engine can qualify even while it is waiting in storage. Consumable spares are inventory. The expected role and duration determine which definition fits.
- 3ExampleSort the invoice and preparation costs
A packaging machine has a $120,000 net price. Delivery is $2,400, installation $5,600, recoverable tax $12,000 and training $3,000.
Price, delivery and installation make the machine capable of operating. Their subtotal is $128,000. Record the tax as a receivable and training as an expense. These two amounts do not become part of the machine's depreciation base.
- 4ExampleAdd the removal obligation
The machine also creates a removal obligation with a present value of $7,000. Add this amount to the $128,000 subtotal, giving machinery cost of $135,000.
Record Dr Machinery $7,000 and Cr Dismantling provision $7,000 for this element. At a 5% discount rate, first-year unwinding is $350: Dr Finance cost and Cr Provision. The unwinding does not increase machinery cost.
- 5Key InsightDecide when cost accumulation ends
The machine passes its technical tests on April 30. The first customer order is filled in June. Its capability, not the sales date, ends capitalization of preparation costs.
Sales of test output are separate: recognize both sales proceeds and output-production costs in profit or loss. Waiting for commercial demand does not make advertising, idle costs or early losses part of the asset.
- 6ChallengeCheck a proposed cost adjustment
The machine is ready on April 30. In May the company spends $4,000 moving it to a different operating site and sells testing samples for $900. Should either amount change machinery cost?
---reveal---
Neither changes the machine's cost. Expense the relocation, and recognize the sample sale in profit or loss with its production cost. The machine had already reached its intended operating condition.
- 7ExampleAllocate a bundle by relative values
A company pays $1,050,000 for land and a workshop. Their fair values are $400,000 and $1,000,000, totaling $1,400,000.
The workshop receives 1,000,000 ÷ 1,400,000 of the price, or $750,000; land receives $300,000. Use the agreed price as the total to allocate. Recording each standalone fair value would create $350,000 of cost that was not paid.
- 8ExplanationSeparate an extended payment
Equipment costs $180,000 cash or $198,000 after one year beyond normal credit terms. Start the asset and payable at $180,000. The extra $18,000 is interest over the year.
If no cash price is quoted, discount the payments at a market rate. This separates acquiring the asset from financing it; a long-lived asset does not automatically qualify for capitalized interest.
- 9ExampleMeasure an exchange in two stages
An old machine carries $24,000 and has a reliable $29,000 fair value. The company pays $31,000 cash for a different machine, and the exchange has commercial substance.
The new cost is $60,000: the $29,000 fair value surrendered plus cash. The gain is $5,000: fair value surrendered less its $24,000 carrying amount. Removing old cost and depreciation completes the journal entry.
- 10ConnectionKeep the exchange condition visible
Commercial substance requires a significant cash-flow or affected-business-value change. If the preceding exchange lacked it, IFRS cost would be $24,000 plus $31,000 cash, or $55,000, with no gain.
US GAAP has a monetary-exchange threshold when cash is at least 25% of fair value. That rule can make the US and IFRS measurements differ even for the same exchange.
- 11ExplanationAccount for shares and self-construction
Land worth $210,000 is acquired for 15,000 shares of $1 par value. Record Dr Land $210,000; Cr Share capital $15,000; Cr Share premium $195,000.
A self-built asset uses actual qualifying materials, labor and attributable overhead. Exclude abnormal waste and internal profit. A higher contractor quotation is not evidence that the company earned a profit from constructing its own asset.
- 12ChallengeCombine a purchase with preparation
A ready-to-install machine is bought for $220,000 payable in one year; its cash price is $200,000. Installation costs $9,000 and training costs $2,500. Preparation is brief. What initial machinery cost and financing difference result?
---reveal---
Machinery cost is $209,000: the $200,000 cash price plus installation. The $20,000 credit difference is interest over the year, and training is expensed. Short preparation does not create an IAS 23 qualifying asset.
- 13RecapKeep cost, finance and expenses separate
Start with recognition, then identify the amount exchanged for the asset. Add qualifying preparation and an initial dismantling obligation. Allocate bundles and separate credit interest before future depreciation begins.
For exchanges, commercial substance and reliable value determine the basis. Shares and self-construction each need their own cost measure; neither par value nor an internal profit creates asset cost.
2Capitalize interest over the right period
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionDraw a timeline before calculating interest
- 2ExplanationIdentify substantial preparation
- 3ExampleFind the first eligible date
- 4ExplanationDistinguish an inactive stoppage
- 5Key InsightChoose the end date
- 6ChallengeCount the eligible months
- 7ExampleCalculate a specific-loan amount
- 8ExampleWeight the general debt pool
- 9ExampleWeight the actual project payments
- 10ConnectionCheck the ceiling and journal entry
- 11ChallengeApply a received grant
- 12ChallengeBring timing and funding together
- 13RecapKeep the three checks in order
3Match grants to costs and handle repayment
12 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionSeparate support received from income earned
- 2ExplanationCheck reasonable assurance
- 3ExampleMatch a wage grant
- 4ExampleSeparate a loan from its subsidy
- 5ChallengeChoose the income period
- 6ExampleSet up an asset-grant comparison
- 7ExampleCalculate each annual profit effect
- 8ConnectionCompare year-end balances
- 9ExampleAccount for a repayment after two years
- 10Key InsightRebuild the net asset on repayment
- 11ChallengeConnect matching and repayment
- 12RecapFollow the costs the grant compensates
4Depreciate, replace and dispose of assets
16 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionTrack the service left in each part
- 2ExampleSeparate a building and its roof
- 3Key InsightKeep the allocation distinct from value
- 4ChallengeTry a component calculation
- 5ExampleRemove the roof being replaced
- 6ExplanationCheck what the invoice actually buys
- 7ChallengeFind the missing entry
- 8ExplanationBegin when available for use
- 9ExampleRevise the future charge
- 10ConnectionDistinguish a new estimate from an error
- 11ChallengeCalculate from a revised estimate
- 12ExampleUpdate through the sale date
- 13ExampleCompare with net proceeds
- 14ExplanationSeparate compensation from replacement
- 15ChallengeCombine an estimate change and disposal
- 16RecapKeep the records current at each event
5Revalue assets and follow the surplus
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionTrack value and the asset's history
- 2ExplanationChoose the class and measurement date
- 3ExampleEliminate accumulated depreciation
- 4ExampleCompare proportional restatement
- 5ChallengeCheck the two methods
- 6ExampleBuild an asset-specific surplus
- 7ExampleAllocate the next decrease
- 8ChallengeApply a recovery
- 9ConnectionInclude the related deferred tax
- 10ExampleDepreciate the revalued amount
- 11Key InsightMake an optional equity transfer
- 12ChallengeCombine depreciation, disposal and equity
- 13RecapDistinguish the three destinations
6Classify and measure investment property
13 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionLet use determine the property category
- 2ExplanationCompare independent returns with operating use
- 3ExampleDecide whether mixed portions can be separated
- 4ConnectionCheck services and the reporting entity
- 5ChallengeClassify a developer's project
- 6ExampleStart at acquisition cost
- 7ExampleRecord the first fair value change
- 8Key InsightRequire evidence before transferring
- 9ExampleMove fair-value property into owner use
- 10ExampleTransfer in the opposite direction
- 11ChallengeConnect classification with a new measurement
- 12ExampleMeasure a disposal on net proceeds
- 13RecapKeep IAS 40 distinct from IAS 16 revaluation
Property, Plant and Equipment practice questions
Set 1: Asset measurement: first decisions10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Apply the rules to new transactions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Combine measurement and timing10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Judge exceptions and reporting effects10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Integrate the full asset lifecycle10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Ancillary services
Asset-deduction method
Available for use
B
Below-market government loan
Boot
Borrowing costs
C
Capital appreciation
Capitalization period
Capitalization rate
Cash price equivalent
Change in accounting estimate
Change in use
Class of PP&E
Commercial substance
Component depreciation
Consolidated financial statements
Construction in progress
Cost model
Cost-model fair value disclosure
Cumulative additional depreciation
D
Deemed cost
Deferred grant income
Depreciable amount
Derecognition
Derecognition loss on replacement
Directly attributable cost
Discount unwinding
Dismantling provision
Disposal gain or loss
E
Elimination method
Excess depreciation
F
Fair value
Fair value gain or loss
Fair value model
Forgivable loan
G
General borrowings
Government grant
Grant related to assets
Grant related to income
Grant repayment
H
Held-for-sale classification
I
Investment property
Investment property under construction
L
Lump-sum purchase
M
Major inspection component
Mixed-use property
N
Net disposal proceeds
Non-monetary grant
Nonmonetary exchange
O
Other comprehensive income
Owner-occupied property
P
Prior-period error
Property, plant and equipment
Proportional restatement
Prospective application
Q
Qualifying asset
R
Reasonable assurance
Recoverable purchase tax
Recycling
Repairs and maintenance
Replacement component
Residual value
Retained earnings
Revaluation model
Revaluation reversal
Revaluation surplus
S
Self-constructed asset
Share premium
Specific borrowing
Substantial completion
Suspension of capitalization
T
Taxable temporary difference
Temporary investment income
Third-party compensation
Transaction costs
U
Unit of account
Useful life
W
Weighted average accumulated expenditures
About this lesson