Project Cash Flows and Risk Analysis
IntermediateLesson 6 of 10 in Corporate Finance 1 Course
What you will learn
- Decide which cash flows belong in a project appraisal by comparing the firm with and without the project, including side effects on other products, sunk costs and opportunity costs.
- Compare the firm with and without the projectApply the incremental principle: include every after-tax cash flow the project changes and leave out accounting charges and financing flows it does not change.
- Leave out sunk costs and charge opportunity costsSeparate money already spent or committed from costs the project causes, and charge resources the firm already owns at the value it gives up by using them.
- Compare the firm with and without the project
- Turn forecasts of sales and costs into year-by-year free cash flows, including the tax savings from depreciation, investment in working capital, the initial outlay and the cash flows at the end of the project's life.
- Turn incremental earnings into free cash flowBuild each year's free cash flow from revenue, costs, depreciation and tax, then adjust for capital spending and working capital.
- Value the tax savings from depreciationExplain how depreciation lowers tax, compare depreciation schedules and their present values, and apply the timing of tax payments.
- Forecast working capital investment and its recoveryEstimate the net working capital a project ties up each year, turn changes in it into cash flows and include its recovery at the end.
- Add the start-up and end-of-life cash flows and assemble the forecastInclude the initial investment, after-tax salvage value and other end-of-project flows, then lay out the full timeline and compute NPV.
- Turn incremental earnings into free cash flow
- Treat inflation the same way in cash flows and discount rates, and forecast cash flows whose items inflate at different rates.
- Match nominal cash flows with nominal discount ratesDistinguish nominal and real cash flows and rates, convert between them with the Fisher relation, and keep every appraisal consistent.
- Forecast with different inflation rates for different itemsInflate each revenue and cost item at its own rate from the right base year, include rising working capital and discount the nominal totals.
- Match nominal cash flows with nominal discount rates
- Use sensitivity analysis, break-even analysis and scenarios with probabilities to find the forecasts that drive NPV and to judge how likely a poor outcome is.
- Measure how sensitive NPV is to each forecastChange one forecast at a time, calculate how far each can move before NPV reaches zero and identify the critical variables.
- Find the break-even level of a key forecastSolve for the sales volume, price or other input that gives an NPV of zero, and contrast it with accounting break-even.
- Combine forecasts in scenarios and weigh them by probabilityBuild consistent best, base and worst scenarios, compute expected NPV and its spread, and know what simulation and risk-adjusted discount rates add.
- Measure how sensitive NPV is to each forecast
- Apply after-tax cash flow analysis to choose between leasing an asset and borrowing to buy it, to set the best replacement cycle and to compare assets with unequal lives.
- Compare leasing with borrowing to buyCompare the after-tax costs of leasing and of buying with borrowed money, discounted at the after-tax cost of borrowing.
- Decide when to replace an asset and compare unequal livesUse equivalent annual cost to choose a replacement cycle and to decide when to replace an existing asset, and use equivalent annual benefit for projects with unequal lives.
- Compare leasing with borrowing to buy
Project Cash Flows study guide
1Find the cash flows the project changes
A project can bring in sales while reducing sales elsewhere, use an empty building that could earn rent, or receive a share of costs the firm already pays. Each item needs a with-versus-without comparison. Start with the change in the firm's cash flows, then account for tax and timing. This separates the project's economic effects from the way accountants assign costs or the way the firm raises money.
1.1 The with-versus-without comparison
An incremental cash flow is the firm's cash flow with a project minus its cash flow without that project. The comparison covers the whole firm. A new product's sales are only one part of the change.
Cash and profit answer different questions
Accounting profit records sales when earned and deducts depreciation over an asset's life. Cash can arrive later than a sale, and the asset's purchase was paid for at a different date. For appraisal, start with operating forecasts, calculate their tax effects, then adjust for the timing of cash. Depreciation enters through tax savings; receivables and inventory enter through working capital.
Measure each operating effect after tax. At a 25% marginal tax rate, an extra $10,000 of cash revenue adds $7,500 after tax. The same is true of a $10,000 saving in deductible cash costs. After-tax operating profit still needs a depreciation add-back and adjustments for investment before it becomes free cash flow.
Follow side effects across the firm
Cannibalization, also called erosion, occurs when a new product takes business from an existing one. Suppose a juice line earns $400,000 a year but reduces smoothie revenue by $60,000. Smoothie variable costs also fall by $24,000. The lost pretax contribution is:
Charge $36,000 before tax, or $27,000 after 25% tax, to the new line. Charging all $60,000 ignores the costs avoided when fewer smoothies are made. A synergy works in the other direction: extra contribution from sales of a related product is a project benefit.
The baseline must be realistic. If a competitor would take those smoothie sales even without the juice line, the loss appears on both sides of the comparison. It is then not an extra cost caused by launching the juice.
Check overhead and financing separately
| Item | Treatment | Reason |
|---|---|---|
| Head office assigns 5% of juice revenue, $20,000 | Exclude if total overhead stays unchanged | The charge only reallocates existing costs |
| An additional administrator costs $45,000 | Include the after-tax cost | The firm pays more because it launches the line |
| Interest on the project loan | Exclude from project FCF | Financing cost is reflected in the discount rate |
Interest, loan principal repayments, and dividends stay out of unlevered free cash flow. Subtracting interest and also discounting at the project's cost of capital counts financing cost twice. Borrowing proceeds are not an operating benefit either.
Put the change on its payment date
Time 0 is today. End-of-year cash flows go at times 1, 2, and so on. A payment at the start of year 2 belongs at time 1, the same date as the end of year 1. A payment made today is not discounted.
Once the relevant flows are dated, discount them at the project's cost of capital. Positive NPV means the project creates value after allowing for that required return. An average accounting profit cannot replace this dated cash flow forecast.
Key Takeaways
- Compare the whole firm with and without the project.
- Count lost contribution and extra contribution on related products.
- Include overhead only when total cash spending changes.
- Keep financing flows out of unlevered FCF.
- Date each after-tax cash flow when it occurs.
1.2 Past spending and resources already owned
A cost's relevance depends on what the decision changes. Money already paid can be irrelevant, while a building already owned can carry a substantial project cost.
Leave sunk and unavoidable costs out
A sunk cost has been paid or irrevocably committed and cannot be recovered whichever decision the firm makes. A $50,000 market survey paid last year stays spent whether the juice line launches or not. Exclude it from both the initial investment and future operating costs.
The statement "We have already spent $2 million, so we must launch" illustrates the sunk-cost fallacy. Launching can recover value only through future incremental cash flows. The past spending cannot make a future negative-NPV investment worthwhile.
A committed cost can still be a future payment. Rent under an existing office contract must be paid even if the project is rejected. If accepting the project leaves that payment unchanged, exclude it. A new extension to the lease required by the project would be different: the extra future payment would be incremental.
Recoverability matters more than whether cash has already left the bank. A $15,000 deposit refunded on cancellation is not sunk. Continuing gives up the refund. Record that $15,000 opportunity cost at the date the refund would otherwise arrive, without charging the original deposit a second time.
Price the best alternative given up
An opportunity cost is the value of the best alternative use displaced by the project. The firm does not need to write a new check for a cost to exist.
An owned warehouse could earn $30,000 rent each year. Using it for the juice line gives up that income. With rent taxed at 25%, the annual opportunity cost is:
Charge $22,500 each year the rental income is lost. The warehouse's original purchase price does not measure this annual sacrifice.
Use today's after-tax value
Land bought for $200,000 twelve years ago can be sold today for $450,000. With no selling costs and 25% tax on the $250,000 gain:
- Tax on a sale is $62,500.
- Net sale proceeds would be $387,500.
- Using the land gives up $387,500 today, so charge that amount at time 0.
The $200,000 historical cost is not the current opportunity cost. Book value can help calculate sale tax, but it is not a substitute for the proceeds forgone. If the land will be sold when the project ends, that later after-tax sale is a separate future inflow.
An idle resource can have zero cost
An unused machine with no sale value and no alternative use has zero opportunity cost. A manager's existing salary also adds no cost if it is paid either way and no other work is displaced. If using the machine or manager forces the firm to buy capacity or hire someone elsewhere, include the extra replacement spending.
These decisions use the same relevant-cost logic as short-term choices, with long-term appraisal adding tax and discounting.
Key Takeaways
- Exclude spending that cannot be recovered and payments that occur either way.
- A refundable deposit has a relevant refund forgone.
- Charge the best alternative use of an owned resource.
- Measure opportunities at current after-tax values, on the dates forgone.
2Build the free cash flow forecast
Sales and cost forecasts become useful for appraisal only after tax, asset spending, and working capital have been placed on a timeline. Depreciation changes tax without being a cash payment. Inventory and customer credit tie up cash even when profit looks healthy. Build these parts separately, then combine the initial outlay, annual operations, and final recovery or disposal into a complete forecast.
2.1 From operating profit to free cash flow
Free cash flow (FCF) measures the cash a project makes available to its providers of finance after paying operating costs and tax and funding the investment it needs. It is calculated before interest and loan repayments.
Build operating cash flow first
Let Revenue and Costs be incremental sales and cash operating costs, let D be tax-allowable depreciation, and let T be the marginal tax rate. With tax paid in the year the profit arises:
Revenue minus cash costs minus depreciation is EBIT, earnings before interest and taxes. EBIT after tax is called NOPAT or unlevered net income. Adding depreciation back converts this after-tax operating profit to operating cash flow before working capital changes.
A project has revenue of $500,000, cash costs of $300,000, depreciation of $100,000, and tax of 25%:
| Step | Amount |
|---|---|
| Revenue less cash costs | $200,000 |
| Less depreciation: EBIT | $100,000 |
| Less tax of 25%: NOPAT | $75,000 |
| Add back depreciation: OCF | $175,000 |
Depreciation was deducted to calculate tax. Adding it back does not erase the $25,000 tax saving it produced.
Deduct the investment still needed
Capital expenditure (CapEx) is spending on long-lived assets. An increase in net working capital (NWC) is cash tied up in operations. Both reduce the cash available in that year:
If NWC rises by $10,000 and CapEx is zero, the example's FCF is $165,000. If that year also requires a $30,000 equipment addition, FCF falls to $135,000. A decrease in NWC releases cash, so subtracting a negative change adds an inflow.
See the depreciation tax shield directly
The same OCF can be written as:
Here $200,000 after 25% tax gives $150,000. The depreciation tax shield is $25,000, producing the same $175,000 OCF. Use either route, but do not mix them. Adding the whole $100,000 depreciation to after-tax revenue less cash costs would produce $250,000 and overstate cash flow by $75,000.
Use the tax change the firm actually faces
The marginal tax rate applies to additional taxable income. The firm's average tax rate on all past income may differ. Where more than one level of government taxes the extra profit, use the applicable combined marginal rate.
A project with EBIT of negative $40,000 can save $10,000 tax at 25% when the firm has taxable profit elsewhere against which to use the loss. That tax saving is an inflow in the project forecast. Without usable profit now, a loss carryforward can delay the benefit, lowering its present value. Record tax at the date it is paid or saved; a one-year tax delay needs a separate tax row.
Do not deduct interest in EBIT for this calculation. These flows value the investment before financing; the cost of financing, including debt's tax effect where applicable, enters the discount rate.
Key Takeaways
- Deduct tax depreciation before tax and add it back afterward.
- Subtract CapEx and increases in NWC to obtain FCF.
- The equivalent OCF formula adds only the depreciation tax shield.
- Use the marginal tax rate on incremental income.
- Recognize a loss tax benefit when the firm can use it.
- Keep interest and debt repayments out of project FCF.
2.2 Depreciation deductions and their timing
Depreciation is not a second payment for an asset. Its value in appraisal comes from the tax deduction. Use tax-allowable depreciation, which can differ from the depreciation shown in financial statements.
Turn a deduction into a tax saving
The depreciation tax shield is the deduction multiplied by the marginal tax rate. A $400,000 machine depreciated straight-line to zero over four years has annual deductions of $100,000. At 25% tax, each saves $25,000.
With savings at times 1–4 and a 10% discount rate, the four-year annuity factor is 3.1699. Their present value is about $79,247. The deduction's amount and the date the tax is saved both matter.
Compare straight-line and accelerated schedules
Straight-line depreciation gives equal annual deductions. An accelerated schedule gives more of the total deduction earlier. Double-declining balance for a four-year life uses 50% of the opening book value, switching to straight line when that gives at least as much over the remaining life.
| Year | Straight-line deduction | Accelerated deduction | Accelerated tax shield at 25% |
|---|---|---|---|
| 1 | $100,000 | $200,000 | $50,000 |
| 2 | $100,000 | $100,000 | $25,000 |
| 3 | $100,000 | $50,000 | $12,500 |
| 4 | $100,000 | $50,000 | $12,500 |
Both schedules deduct $400,000 and save $100,000 in total tax. At 10%, the accelerated shields are worth $84,045 today, compared with $79,247 under straight line. A profitable firm benefits because it gets the savings sooner. A full first-year deduction gives a $100,000 saving at time 1, worth $90,909 today.
Finish a reducing-balance schedule
Under reducing-balance depreciation, apply a fixed percentage to the opening tax written-down value each year. A $400,000 asset at 25% gives deductions of $100,000, $75,000, and $56,250 in years 1–3, leaving $168,750.
In the disposal year, reconcile the remaining tax value with sale proceeds. If the machine is scrapped for zero at the end of year 4, the total final deduction is $168,750. This is the remaining balance; do not add it on top of a separate year-4 deduction. The four tax savings are $25,000, $18,750, $14,062.50, and $42,187.50.
A balancing allowance supplies an extra deduction when proceeds are below the remaining tax value. A balancing charge creates taxable income when proceeds exceed it. Track the opening balance, each deduction, and the final value so the cost is not deducted twice.
Move tax savings when tax is delayed
With tax one year in arrears, a year-1 deduction saves tax at time 2. Straight-line savings for the four-year machine move from times 1–4 to times 2–5. Their present value falls to $72,042. The asset stops operating in year 4, but its last tax effect arrives in year 5.
A deduction helps when taxable income is available to absorb it. Tax schedules are set by tax rules, not by management's choice of financial reporting policy. Historical-cost tax depreciation is fixed in nominal money: rising selling prices do not inflate its tax shield.
Value an uneven shield schedule
The annuity shortcut fits equal shields, but accelerated shields need individual discount factors. For the four-year accelerated schedule above:
The first $50,000 saving is discounted once; the last $12,500 is discounted four times. With tax one year in arrears, change those exponents to 2, 3, 4, and 5. Every saving then has an additional year's discounting, so divide this entire PV by 1.10. Do not move the asset purchase: it remains at time 0. This separation of deduction years and tax cash dates also works when depreciation amounts change annually.
Key Takeaways
- Value tax deductions through the tax they save.
- Accelerated deductions raise the present value of usable tax savings.
- Reconcile the remaining tax value on disposal without double counting.
- With a one-year tax lag, shift all tax effects one year later.
- Keep historical-cost tax shields fixed in nominal money.
2.3 Working capital levels and cash movements
A project may pay suppliers before it collects from customers. The cash needed between those dates is part of the investment, even though it is not a purchase of a long-lived asset.
Find the operating balance tied up
For a project, net working capital is operating cash needed plus inventory and receivables, less payables:
Receivables are sales still unpaid by customers. Payables are amounts still owed to suppliers, whose credit partly finances operations. The cash component is the operating cash balance the project needs, not an unrelated pile of spare cash.
The relevant cash flow is the change in NWC. An increase ties up money and reduces FCF; a decrease releases money and increases FCF.
Move from balances to flows
Suppose required balances are $30,000 at time 0, $50,000 at time 1, $50,000 at time 2, and zero at time 3. Before the project, its NWC is zero.
| Time | Required NWC | Increase in NWC | Cash flow |
|---|---|---|---|
| 0 | $30,000 | $30,000 | −$30,000 |
| 1 | $50,000 | $20,000 | −$20,000 |
| 2 | $50,000 | $0 | $0 |
| 3 | $0 | −$50,000 | +$50,000 |
Subtracting $50,000 again at time 2 would charge for cash already invested. The balance has stayed the same, so no extra cash is needed.
Read the timing of a sales-based rule
NWC is often a percentage of annual sales. If 10% is needed at the start of each sales year, work one date ahead. For sales of $200,000, $300,000, and $250,000 in years 1–3, the required balances are $20,000 at time 0, $30,000 at time 1, and $25,000 at time 2.
The resulting flows are negative $20,000, negative $10,000, positive $5,000, and a final positive $25,000 at time 3. The time-2 release occurs because the next year's forecast sales are lower. If sales rise only because of inflation, a sales-based NWC requirement still rises and needs extra cash.
Recover the final balance
At shutdown, customers pay, remaining inventory is sold, and suppliers are paid. The working capital balance is released. The usual full recovery is not taxed: the initial investment was not a deductible expense. Use a lower recovery if inventory becomes obsolete or receivables cannot be collected.
Full recovery does not make working capital costless. In the first example, the undiscounted flows sum to zero, but their present value at 10% is negative $10,616. Money tied up today is returned later, after the firm has lost the use of it.
Connect profit to collections
If recorded sales are $120,000 and receivables rise by $15,000, cash collected is $105,000. Subtracting the receivables increase through the NWC adjustment removes the sales still unpaid. Do not also reduce the revenue forecast for the same receivables change, or the delay will be counted twice.
Key Takeaways
- An increase in NWC is an outflow; a decrease is an inflow.
- Use changes in the balance, not the whole balance each year.
- A start-of-year requirement is funded before that year starts.
- Add the recoverable final balance at shutdown.
- Full eventual recovery still has a present-value cost.
2.4 The first outlay and the final inflow
A complete forecast needs more than annual operating cash flow. It includes getting the asset ready, funding working capital, and collecting or paying the final amounts when operations end.
Assemble the time-0 investment
The depreciable asset cost includes purchase, shipping, and installation. A $400,000 machine with $10,000 shipping and $30,000 installation has a $440,000 depreciable basis. These payments are capitalized and recovered through tax depreciation.
An expense deductible immediately follows a different tax schedule. Staff training of $20,000 costs $15,000 after 25% tax when the tax saving occurs at the payment date. If tax relief arrives later, show the gross payment now and the saving at that later date. Add initial NWC and the after-tax opportunity value of owned assets used by the project.
Calculate after-tax sale proceeds
Salvage value, also called residual value, is the asset's sale price at the end. Let S be proceeds, BV the tax book value, and T the tax rate:
The taxable amount is the gain above tax book value. At 25%, an asset with BV of $20,000 sold for $60,000 gives a $40,000 gain, $10,000 tax, and $50,000 after-tax proceeds. If sold for $10,000, its $10,000 loss saves $2,500 tax when usable, giving $12,500 after tax. For a fully depreciated asset, after-tax proceeds are the sale price multiplied by one minus the tax rate.
Add final NWC recovery and subtract after-tax cleanup or decommissioning costs. If tax is delayed, split sale cash and sale tax across their actual dates. For a continuing project, a terminal value represents cash flows after the detailed forecast horizon. Place it at the final forecast date and discount it to today; do not count those later flows again separately.
Build a complete three-year forecast
A machine costs $300,000 at time 0 and is depreciated to zero over three years. Annual revenue is $250,000, annual cash costs are $100,000, and tax is 25% paid in the same year. NWC of $20,000 is invested initially and fully recovered at time 3. The machine sells then for $30,000.
Annual depreciation is $100,000. EBIT is $50,000, tax is $12,500, and after-tax EBIT is $37,500. Add back depreciation to get OCF of $137,500. Final after-tax salvage is $22,500.
| Cash flow | Time 0 | Year 1 | Year 2 | Year 3 |
|---|---|---|---|---|
| Operating cash flow | $0 | $137,500 | $137,500 | $137,500 |
| Asset purchase | −$300,000 | $0 | $0 | $0 |
| NWC investment or release | −$20,000 | $0 | $0 | $20,000 |
| After-tax salvage | $0 | $0 | $0 | $22,500 |
| FCF | −$320,000 | $137,500 | $137,500 | $180,000 |
At a 10% cost of capital:
The project creates about $53,873 of value, with an IRR of about 18.9%. Before discounting, check that total depreciation plus final book value equals the depreciable cost, and that the NWC rows contain both the initial investment and the final release.
Extend the table for delayed tax
If the same three-year project pays all operating and disposal tax one year in arrears, keep the purchase, NWC, and gross sale receipts on their original dates. Before operating tax, annual cash from revenue less costs is $150,000. The revised FCF row is:
- Time 0: negative $320,000.
- Time 1: $150,000, before the first operating tax is paid.
- Time 2: $137,500, after year-1 tax of $12,500.
- Time 3: $187,500, including gross sale receipts and NWC recovery, less year-2 tax.
- Time 4: negative $20,000, comprising year-3 operating tax of $12,500 and sale tax of $7,500.
The asset is gone at time 4, but the project still changes the firm's tax payment. Ending the forecast at time 3 would omit that final outflow.
Key Takeaways
- Capitalize shipping and installation with the asset purchase.
- Tax the disposal gain or recognize a usable disposal loss.
- Separate cash receipts and tax effects when their dates differ.
- Include initial NWC, final recovery, and shutdown costs.
- Place continuation value at the last explicit forecast date.
- Discount the completed FCF row to calculate NPV.
3Keep inflation and discounting consistent
A forecast can show future dollars or today's purchasing power. Either approach works when the discount rate uses the same basis. The practical difficulty comes when selling prices, materials, and wages rise at different rates while tax deductions stay fixed in money. Start by identifying the price date of every input, then build a forecast whose cash flows and discount rate describe the same purchasing power.
3.1 Nominal money and real purchasing power
Nominal cash flows are the money amounts expected on their payment dates. Real cash flows express those amounts in today's purchasing power. A nominal rate measures money growth; a real rate measures purchasing-power growth.
Convert rates with the Fisher relation
Let i be the nominal rate, r the real rate, and h general inflation. The exact relation is:
A 5% real return with 3% inflation requires a nominal return of 8.15%:
Adding 5% and 3% gives an 8% approximation, omitting the interaction between return and inflation. Use the exact relation in an appraisal.
To find a real rate from a 10% nominal rate and 3% inflation, divide the growth factors:
Simply subtracting inflation would give 7%, which is not the exact purchasing-power return.
Convert dated cash flows
Multiply a real time-t cash flow by the general price-level factor to express it in future money:
Divide a nominal amount by the same factor to express it in today's purchasing power. The exponent follows the cash flow date: a time-3 amount includes three years of price-level change.
A project earns $100,000 a year for three years in today's prices. With inflation of 3%, the nominal flows are $103,000, $106,090, and $109,272.70. Each successive payment contains another year's inflation.
Match each flow to its rate
| Cash flow basis | Matching rate | Meaning |
|---|---|---|
| Today's purchasing power | Real rate | Both exclude general price-level growth |
| Future money amounts | Nominal rate | Both include general price-level growth |
Discounting the three real $100,000 flows at 5% gives $272,324.80. Discounting their nominal equivalents at 8.15% gives the same present value. Inflation in the numerator is offset by inflation in the matching discount factor.
Mixing bases changes the answer. Nominal flows discounted at the real 5% give about $288,716, too high. Real flows discounted at the nominal 8.15% give about $257,014, too low. The second mistake can arise when today's prices are copied directly into a forecast and discounted at a quoted nominal cost of capital.
Keep fixed money amounts fixed
Historical-cost depreciation shields do not rise with general prices. A lease fixing payments at $29,000 a year also specifies nominal amounts. Do not inflate them simply because prices elsewhere are rising.
The nominal approach is often easier with tax: inflate the appropriate sales and costs, leave fixed contractual amounts and tax deductions unchanged, calculate nominal tax, and use a nominal discount rate. A real forecast can also work, but each fixed nominal amount must be deflated separately.
Inflation erodes the purchasing power of a fixed tax shield. This can reduce project value even when selling prices rise, because the deduction does not keep pace with taxable operating income. A real approach is especially convenient in before-tax appraisals where every cash flow rises with general inflation.
Key Takeaways
- Match nominal flows with nominal rates and real flows with real rates.
- Use growth-factor multiplication or division for exact rate conversion.
- Convert each cash flow using its own date.
- Historical-cost tax shields and fixed contractual payments stay nominally fixed.
3.2 Different price rises in one forecast
General inflation describes the price level. A project's selling price, wages, and materials can each move at a different rate. Those specific inflation rates determine the forecast amounts for individual items.
Check the price date before inflating
A figure stated "in current prices" is a time-0 price. Year 1 needs one inflation step, year 2 needs two, and so on:
A figure already stated in year-1 money has already received the first step. Inflating it again for year 1 would count inflation twice. Label base prices and dates before calculating the rows.
Inflate revenue and each cost separately
A project sells 10,000 units each year. Today's price is $20 per unit, rising 4% annually. Today's variable cost is $8 per unit, rising 6%. Fixed costs are $50,000 in current prices, rising 3%. This example is before tax.
| Forecast item | Year 1 | Year 2 |
|---|---|---|
| Revenue | $208,000 | $216,320 |
| Variable costs | $84,800 | $89,888 |
| Fixed costs | $51,500 | $53,045 |
| Net operating cash flow | $71,700 | $73,387 |
For year 1, price becomes $20.80 and variable cost becomes $8.48. Multiply each by 10,000 units, then deduct the inflated fixed costs. For year 2, compound each rate twice from today's base. The second-year variable cost is $8 multiplied by 1.06 squared, not simply $8 plus two un-compounded 6% increases.
The variable cost starts at 40% of selling price. By year 2 it is about 41.6%. Operating cash flow still rises, but the margin per sales dollar is squeezed. Using 4% for every row would miss the faster cost increase.
Fund working capital in future money
Suppose NWC is 10% of each year's nominal sales, funded at the start of that year. Year-1 sales of $208,000 require $20,800 at time 0. Year-2 sales of $216,320 require $21,632 at time 1, an additional $832.
At the end of the two-year project, release $21,632. Combining the operating and NWC rows gives:
- Time 0: negative $20,800.
- Time 1: $71,700 less $832, giving $70,868.
- Time 2: $73,387 plus $21,632, giving $95,019.
The higher selling price needs extra working capital even though volume stays at 10,000 units. Do not freeze the NWC balance at its current-price estimate.
Add tax on the same basis
With tax, subtract nominal cash costs and historical-cost tax depreciation from nominal revenue to obtain taxable operating profit. The depreciation deduction is not inflated. Place the resulting tax payment on its due date.
Use general inflation to convert between nominal and real discount rates. Use each specific rate to forecast its own cash item. Discount the completed nominal FCF row at the nominal cost of capital.
Key Takeaways
- Inflate current-price inputs from time 0, including year 1.
- Apply the specific rate for each revenue and cost item.
- Base sales-linked NWC on nominal sales and fund it on time.
- Keep tax depreciation at historical-cost amounts.
- Use general inflation for rate conversion and specific inflation for forecast rows.
4Test the forecast and the downside
A positive base-case NPV depends on forecasts that may be wrong. Sensitivity analysis identifies the inputs with little room for error. Break-even analysis turns that room into a threshold, while scenarios show what happens when related inputs move together. Probability weights and a view of the possible losses help managers judge a project's appeal without treating one forecast as a certain outcome.
4.1 Find the forecasts with little room for error
Sensitivity analysis changes one input while keeping the others at base-case values, then recalculates NPV. It identifies fragile forecasts, but it does not tell you how likely a change is.
Risk describes outcomes to which probabilities can be assigned. Under uncertainty, probabilities cannot be estimated reliably. Longer project lives usually make forecasts harder to judge because more distant events can change the outcome.
Establish one base case
A machine costs $500,000 today, lasts five years, and has no salvage value or NWC requirement. Depreciation is $100,000 a year. Annual volume is 20,000 units at $32, variable cost is $18 per unit, and fixed cash costs are $100,000. Tax is 25%, paid in the same year, and the cost of capital is 10%.
Annual contribution is $280,000. Subtract fixed costs and depreciation to get EBIT of $80,000. After tax and the depreciation add-back, OCF is $160,000. The five-year annuity factor is about 3.7908, giving NPV of $106,526 using the unrounded factor.
A 10% fall in volume to 18,000 units cuts NPV to $26,919. A 5% increase in variable cost to $18.90 cuts it to $55,350. These are separate tests: each changes just one input.
Measure the adverse percentage change to zero NPV
For a proportional change in a forecast cash flow, the sensitivity margin is:
The denominator must match what changes. A price change affects revenue at fixed volume. A volume change affects both sales and variable costs, so it acts on contribution.
| Input | Affected after-tax PV | Adverse margin |
|---|---|---|
| Volume | $796,065 contribution | 13.4% fall |
| Selling price | $1,819,578 revenue | 5.9% fall |
| Variable cost | $1,023,513 variable costs | 10.4% rise |
| Fixed cash costs | $284,309 fixed costs | 37.5% rise |
Selling price is the critical variable: its smallest margin means it takes the smallest proportional error to eliminate NPV. Research, pilot sales, or a firm customer contract can help test that forecast.
Recalculate linked effects
An increase in asset cost also raises depreciation deductions when the tax basis rises with the price. The affected net present cost is the $500,000 price less the PV of its $25,000 annual shields, or $405,230. The investment margin is therefore 26.3%. Dividing by the full $500,000 would miss the tax benefit of the higher basis.
For the discount rate, solve for the rate that gives zero NPV: the IRR, about 18.0% here. That is about 8 percentage points above the 10% cost of capital. It is not an 8% proportional increase.
Recognize the limits
A price fall can accompany a volume fall. One-at-a-time tests cannot show the combined effect, and a narrow margin does not establish a high probability of loss. Sensitivity identifies exposure; it does not reduce it. Scenarios and probability estimates add the linked changes and likelihoods that this method leaves out.
Build the affected present values
For price sensitivity, base annual revenue is $640,000. A 1% price fall at unchanged volume removes 1% of that revenue, or $6,400 before tax. The annual after-tax loss is $4,800, and its five-year PV is about $18,196. Dividing $106,526 by that loss per percentage point gives about 5.9 percentage points of price reduction.
For volume, a 1% fall removes 200 units. Each unit would contribute $14 before tax, so the annual after-tax loss is $2,100 and its PV is about $7,961. This is why the volume denominator is contribution: the variable costs avoided on the 200 units offset part of the lost revenue. The same 1% change has a different cash effect for price and volume.
Key Takeaways
- Change one input at a time in a sensitivity test.
- Divide by the PV of the after-tax cash flows that actually change.
- Use contribution for volume sensitivity and revenue for price sensitivity.
- Allow for changes in depreciation shields when the asset price changes.
- The smallest adverse margin identifies a critical forecast.
- The IRR is the break-even discount rate.
- Sensitivity gives exposure, not the probability of loss.
4.2 Solve for the level that makes NPV zero
NPV break-even is the value of an input that makes project NPV zero while other inputs remain at their base levels. It is a value threshold: at that input, the project earns the required return but creates no extra value.
Find the annual cash flow required
Use the five-year machine with a $500,000 initial outlay, a 10% cost of capital, no salvage, and no NWC. Equal annual OCF must have a present value of $500,000. Divide by the five-year annuity factor:
The displayed factor is rounded; full-precision discount factors give the stated threshold to the nearest dollar. This first step translates the value target into an annual cash flow target.
Solve for annual sales volume
Price is $32, variable cost is $18 per unit, fixed cash costs are $100,000, depreciation is $100,000, and tax is 25%. For annual volume Q:
Collecting terms gives:
Set that expression equal to the required $131,899. Add $50,000 to both sides and divide by $10.50. The continuous break-even volume is about 17,324 units. For a decision requiring whole units, round the exact threshold upward to the next whole unit that meets it.
The base volume of 20,000 is about 13.4% above the threshold when the fall is measured from the forecast. This matches the volume sensitivity margin because the two methods describe the same adverse change.
Solve for price instead
Hold volume at 20,000 units. Replace the $32 price in the OCF expression with an unknown price and again set OCF equal to $131,899. The resulting break-even price is about $30.13, or 5.9% below the $32 forecast. Do not reduce both price and volume in this calculation: it is a one-input threshold.
Keep accounting break-even separate
Accounting break-even sets EBIT to zero. It covers fixed cash costs and depreciation through contribution:
At that continuous volume, OCF equals depreciation, $100,000 a year. Those receipts recover the $500,000 investment in undiscounted terms over five years, but do not earn the 10% required return. Their present value is only about $379,079, leaving NPV about negative $120,921.
The investment threshold is therefore NPV break-even. An EBIT forecast just above zero is not enough to justify acceptance.
Use a full forecast when flows vary
The annuity shortcut applies to equal annual cash flows. With changing volumes, tax delays, or different annual costs, adjust the chosen input in the full forecast until NPV reaches zero. A spreadsheet's goal-seek function can do this. Keep the depreciation tax shield inside the forecast; omitting it overstates the cash contribution needed from sales.
Key Takeaways
- NPV break-even earns the required return with zero value added.
- For constant annual flows, divide the investment by the annuity factor first.
- Solve the after-tax OCF expression for one input.
- Accounting break-even covers depreciation but does not earn the required return.
- Use the full dated forecast for uneven cash flows.
4.3 Scenarios, probabilities, and possible losses
Scenario analysis changes several forecasts together to describe a coherent outcome. A recession might reduce both selling price and sales volume. A best case, base case, and worst case each need their own internally consistent inputs.
Recalculate the project in each state
For the five-year machine, keep variable cost at $18, fixed cash costs at $100,000, depreciation at $100,000, tax at 25%, and the discount rate at 10%. Change price and annual volume together:
| Scenario | Price | Volume | NPV |
|---|---|---|---|
| Worst | $30 | 16,000 | −$143,666 |
| Base | $32 | 20,000 | $106,526 |
| Best | $34 | 24,000 | $402,207 |
In the worst case, EBIT is negative $8,000 a year. Its tax benefit is usable because the firm has taxable profit elsewhere. Without that immediate offset, the tax row and NPV would change.
Choose combinations that fit the scenario's story. A price war should not be modeled as high prices and high volume unless a specific business reason supports that combination. Related inputs cannot be paired arbitrarily just to produce a desired range.
Weight values by probabilities
The expected NPV is the sum of each NPV multiplied by its probability:
With probabilities of 0.25, 0.50, and 0.25, the weighted amounts are approximately negative $35,917, positive $53,263, and positive $100,552. They add to expected NPV of $117,898. The probabilities must sum to one.
The probability of negative NPV is 25%, because only the worst scenario is negative. It is not found by dividing the expected NPV by the investment.
Examine the spread as well as the average
Calculate standard deviation by subtracting expected NPV from each outcome, squaring each difference, weighting by its probability, and taking the square root of their sum:
This gives about $193,330, showing a wide spread around the mean. The worst case destroys $143,666 of value. A manager needs to consider whether the firm can absorb that outcome as well as whether expected NPV is positive.
Expected NPV describes a probability-weighted average across repetitions. A single project produces one outcome. The average need not occur: none of the three scenarios has an NPV of $117,898. Estimated probabilities can also be subjective or based on limited evidence.
Extend the analysis with simulation
Monte Carlo simulation assigns probability distributions to uncertain inputs, samples them repeatedly, and recalculates NPV thousands of times. The result estimates a distribution of values and a chance of negative NPV. Preserve relationships between inputs, such as prices and volumes moving together. Independently sampling inputs that are actually linked can create implausible combinations and distort the result.
A risk-adjusted discount rate applies a higher required return to riskier operating cash flows. An adjusted payback rule instead requires a shorter recovery period for riskier projects. That rule is simple but ignores cash flows after its cutoff. Neither approach repairs an inconsistent cash flow forecast or poor probability estimates.
Key Takeaways
- Change related forecasts together in coherent scenarios.
- Expected NPV is a probability-weighted average, not a guaranteed result.
- Add the probabilities of negative-NPV states to find the loss probability.
- Consider the size and spread of downside outcomes.
- Simulation needs credible distributions and links between inputs.
- A shorter payback cutoff ignores later cash flows.
5Choose how to obtain and replace an asset
After deciding that an asset is worth using, compare the cash cost of leasing it with the cash cost of buying it. The tax benefits and payment dates differ, so the financing comparison needs its own discount rate. For assets used repeatedly, also ask how long to keep each one. Equivalent annual amounts put replacement cycles of different lengths on a common basis.
5.1 The after-tax cost of leasing and buying
A lease-or-buy comparison asks how to pay for an asset the firm has already decided to use. The investment decision comes first, using the project's cost of capital. The financing comparison then chooses the lower present-value cost.
Identify the different cash flows
| Lease | Buy |
|---|---|
| Lease payments at their payment dates | Purchase price today |
| Tax relief on deductible lease payments | Tax savings from depreciation |
| Costs borne only by the lessee | After-tax residual value and owner-only costs |
Identical operating costs cancel. Leasing gives up the owner's depreciation tax shield and residual value, so both belong in the buy forecast. Check maintenance responsibilities and flexibility separately when the contract terms differ.
Use the after-tax borrowing rate
Fixed lease obligations resemble debt payments. Discount the financing comparison at the after-tax cost of borrowing, not the operating project's cost of capital. With an 8% pretax borrowing rate and 25% tax:
Do not add loan interest and principal repayment to a buy option that already includes the purchase price. For a $100,000 loan, after-tax annual interest of $6,000 plus the eventual $100,000 principal has a PV of $100,000 at 6%. The initial purchase price already represents that financing cost.
Calculate the buy option
A machine costs $100,000, lasts four years, and has zero residual value. Straight-line tax depreciation is $25,000 annually. Tax is 25%, with relief at each year end. The annual shield is $6,250 at times 1–4.
At 6%, the four-year annuity factor is about 3.4651. Present-value cost of buying is $100,000 less the PV of those shields, about $78,343 using the unrounded factor.
Date lease payments and tax relief separately
The lease costs $29,000 at the start of each of four years: times 0–3. Tax relief of $7,250 arrives at the end of each corresponding year: times 1–4.
| Time | Lease payment | Tax relief | Net cash flow |
|---|---|---|---|
| 0 | −$29,000 | $0 | −$29,000 |
| 1–3, each | −$29,000 | $7,250 | −$21,750 |
| 4 | $0 | $7,250 | +$7,250 |
Discounting each net flow at 6% gives a lease cost of $81,395. Buying is cheaper by about $3,052. Multiplying every advance payment by 0.75 on its payment date would bring the tax relief forward incorrectly.
The break-even annual lease payment is about $27,913. At that payment, the two present-value costs are equal with all other terms unchanged. At $29,000, leasing is above the threshold.
Check the choice beyond the headline payment
Using a 10% project rate for these same flows gives lease cost of $78,137 and buy cost of $80,188, reversing the ranking incorrectly. The rate must match the financing cash flows.
Also compare obsolescence risk, maintenance, cancellation terms, and exposure to resale value. Under IFRS 16, most lessee leases appear as assets and liabilities, with specified exemptions. A lease is not a general way to keep an obligation off the balance sheet. Tax deductibility and tax timing still determine the cash comparison.
Key Takeaways
- Compare leasing and buying after accepting the investment itself.
- Use the after-tax borrowing rate for the financing cash flows.
- Include depreciation shields and residual value in the buy option.
- Place advance lease payments and later tax relief on separate dates.
- Do not add loan repayments to a buy cost that includes the purchase price.
- Check maintenance, flexibility, and obsolescence as well as PV cost.
5.2 Compare replacement cycles on an annual basis
Keeping an asset longer spreads its purchase cost over more years, but running costs may rise and resale value may fall. The cheapest single cycle is not necessarily the cheapest way to provide service repeatedly.
Convert one cycle to an annual cost
The equivalent annual cost (EAC) is a constant annual payment with the same PV as one replacement cycle's costs:
Use positive cost amounts consistently and choose the lowest EAC for the required service. The annuity factor must use the same discount rate as the cycle PV.
A machine costs $50,000. Running costs in years 1–3 are $8,000, $11,000, and $15,000. Resale values at those dates are $32,000, $22,000, and $12,000. Use a 10% cost of capital, before tax and without inflation.
Calculate each cycle separately
For a one-year cycle, pay $50,000 today and $8,000 running costs at time 1, then receive $32,000 on sale. Net time-1 receipts are $24,000. PV cost is about $28,182, which divided by the 0.9091 annuity factor gives an EAC of $31,000.
For two years, include $8,000 at time 1 and net proceeds of $11,000 at time 2: resale of $22,000 less running costs of $11,000. For three years, include the first two running costs and a net final cost of $3,000: $15,000 running costs less $12,000 resale.
| Cycle | PV cost | Annuity factor | EAC |
|---|---|---|---|
| 1 year | $28,182 | 0.9091 | $31,000 |
| 2 years | $48,182 | 1.7355 | $27,762 |
| 3 years | $68,618 | 2.4869 | $27,592 |
Using full-precision factors, three years has the lowest EAC. Choosing the smallest PV cost would select one year even though its annual cost is highest. In a three-year cycle, count only the year-3 resale; the machine cannot also be sold at the year-1 and year-2 prices.
Decide whether to keep an old machine
The old machine can be sold for $15,000 now or $10,000 in a year. Next year's running cost is $14,000. Keeping it gives up today's sale proceeds. Express all costs at the end of the year:
This one-year cost is below the new machine's $27,592 EAC. Keep the old machine for another year, then reassess as running costs and resale values change.
Compare benefits over unequal lives
For repeatable, mutually exclusive projects, equivalent annual benefit (EAB) equals NPV divided by the life-specific annuity factor. At 10%, project A has $40,000 NPV over three years, giving $16,085 a year. B has $52,000 NPV over five years, giving $13,717 a year. A supplies more annual value despite its lower single-cycle NPV. For projects that will not repeat, compare their NPVs directly.
EAC and EAB assume replacement on the same terms indefinitely, with costs constant in real terms. Technological change can make that assumption weak, especially when annual values are close. Include tax shields and disposal tax in after-tax cycles. Discount today's-price costs at a real rate when modeling inflation in real terms.
Show the cycle cost rows explicitly
The two-year cost calculation is:
The three-year calculation is:
A negative final net cost is a receipt, as in the two-year cycle. In the three-year cycle, final running costs exceed resale, so the last net amount is an outflow. A disposal receipt does not remove the running cost incurred during that final year. These signs must be correct before the PV is divided by an annuity factor; annualizing cannot repair a missing running cost or a duplicated resale.
Key Takeaways
- Divide each cycle PV by its own annuity factor.
- Choose the lowest EAC for repeatable equivalent service.
- Include only the resale at the end of the chosen cycle.
- Compare the old asset’s one-year keep cost with the new asset’s EAC.
- Choose the highest EAB for repeatable mutually exclusive projects.
- Use direct NPV comparison for one-time projects.
- Check repeatability, tax, inflation, and technological change.
Project Cash Flows examples
1Choose what belongs in the project
10 steps
- 1IntroductionCompare two futures
A firm is considering a new packaging line. Compare its future cash with the line against its future cash without it.
Include effects elsewhere in the firm, such as lost product sales or rent forgone. Measure each change after tax at its cash date.
- 2ExplanationStart with the whole firm
An incremental cash flow is the with-project amount minus the without-project amount for the whole firm.
An accounting allocation may leave total cash unchanged. A lost rental income matters even if the project never writes a rent check.
- 3ExampleMeasure lost contribution
The line adds a product that cuts an existing product's annual revenue by $72,000. Making fewer old products saves $27,000 of variable costs.
Lost contribution is $45,000 before tax. At 25% tax, the annual cash cost of cannibalization is $33,750. Charging the full $72,000 would overlook the production costs avoided when those sales disappear.
- 4ChallengeWould the sales disappear anyway?
The old product would lose the same $72,000 of revenue and save the same $27,000 of costs because a competitor is entering, whether or not the firm adds its new line. What erosion cost belongs in the line's forecast?
---reveal---
Zero. The old-product loss appears with and without the line. It is part of the baseline decline, so charging it again would attribute the competitor's effect to the firm's decision.
- 5TipCheck a head-office charge
A $14,000 allocation from an unchanged head-office budget is excluded: the firm spends no more.
A $38,000 technician hired only for the new line is included. Both the extra salary and its tax saving change the firm's cash flow.
- 6ConnectionSeparate operating value from financing
Exclude interest, principal repayments, and dividends from unlevered project FCF. Financing cost enters the discount rate.
A start-of-year-2 payment belongs at time 1. Putting it at time 2 understates its PV by discounting it for an extra year.
- 7ExplanationTest whether past money can return
The firm paid $22,000 for a nonrefundable design study. That cost is sunk because it cannot be recovered whether the line launches or not.
It also paid an $8,000 deposit that is refundable if it rejects the project today. Proceeding gives up that refund, making $8,000 relevant today. A payment's recoverability, not simply its age, decides whether it is sunk.
- 8ExampleValue the space the line uses
The line would use an owned storehouse that can otherwise earn $28,000 rent a year. There are no rental expenses, and tax is 25% in the same year.
The after-tax rent forgone is $21,000 annually. Charge this opportunity cost to the line during the rental periods it displaces. The storehouse's old purchase price does not measure what using it gives up now.
- 9ChallengeAssemble the relevant annual cost
The line gives up the $28,000 annual rent and requires the $38,000 technician. Rent and salary are subject to the same 25% tax rate. Existing overhead and past design spending do not change. What annual after-tax cost comes from rent and staffing?
---reveal---
The total pretax cost is $66,000. After tax it is $49,500. Both the rental income lost and the extra salary change the firm's cash flow; the unchanged allocation and sunk study do not.
- 10RecapUse the decision as the dividing line
Select the future cash differences caused by acceptance. Include side effects and alternatives forgone, then apply tax and timing.
Exclude sunk spending, unchanged committed payments, and overhead allocations that do not increase cash spending.
2Build and check a four-year cash forecast
17 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionGive each part its own schedule
- 2ExampleCalculate EBIT
- 3ExampleTurn earnings into operating cash
- 4ChallengeUse the shield route
- 5Key InsightA project loss can lower total tax
- 6ExampleDate the annual shield
- 7ConnectionEarlier deductions have more value
- 8ChallengeMove a shield one year later
- 9ExplanationFund the balance before operating
- 10ExampleWrite the NWC cash flow row
- 11ChallengeTranslate a changing balance
- 12ExampleCalculate the machine’s final sale
- 13ExampleCombine the dated pieces
- 14ChallengeAudit the final flow
- 15ExampleDiscount the completed row
- 16TipCheck rows before discount factors
- 17RecapRead the forecast across time
3Forecast inflation without mixing money bases
10 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionChoose the money basis
- 2ExplanationMatch purchasing power to purchasing power
- 3ExampleConvert rates exactly
- 4ChallengeReverse the rate conversion
- 5ExampleInflate each operating row
- 6ExampleCalculate nominal OCF
- 7TipCount from the quoted price date
- 8ChallengeFund nominal sales in advance
- 9Key InsightA fixed shield shrinks in real value
- 10RecapUse the right rate for the right job
4Find the forecast’s weak points
14 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionStart from one checked base case
- 2ExampleCalculate base NPV
- 3ExplanationChoose the affected denominator
- 4ChallengeIdentify the more fragile forecast
- 5TipSeparate exposure from likelihood
- 6ExampleFind the required annual OCF
- 7ExampleSolve the volume threshold
- 8ChallengeCheck the accounting threshold
- 9ExampleChange price and volume together
- 10ExampleAdd a coherent upside
- 11ChallengeWeight the three outcomes
- 12ConnectionModel a distribution of outcomes
- 13ChallengeCan separate margins certify a scenario?
- 14RecapAsk three different risk questions
5Choose financing and replacement timing
15 steps
Save this lesson to follow every Walkthrough step by step.
- 1IntroductionSeparate two asset decisions
- 2ExplanationUse the debt-like rate
- 3ExampleValue buying
- 4ExampleDate leasing and its tax relief
- 5ChallengeChoose the lower present cost
- 6Key InsightThe purchase already represents funding cost
- 7ExplanationPut cycles on the same annual basis
- 8ExampleCalculate the first cycle’s EAC
- 9ExampleCompare a longer cycle
- 10ChallengeKeep the existing machine?
- 11TipSell the asset once per cycle
- 12ConnectionAnnualize value for repeatable projects
- 13ChallengeDecide which comparison fits
- 14ChallengeKeep the two rates in their roles
- 15RecapLet the comparison set the method
Project Cash Flows practice questions
Set 1: Choose relevant flows and build annual cash flow10 Practice Questions
Question 1 of 10
Show answerHide answer
Question 2 of 10
Show answerHide answer
Question 3 of 10
Show answerHide answer
Question 4 of 10
Show answerHide answer
Question 5 of 10
Show answerHide answer
Question 6 of 10
Show answerHide answer
Question 7 of 10
Show answerHide answer
Question 8 of 10
Show answerHide answer
Question 9 of 10
Show answerHide answer
Question 10 of 10
Show answerHide answer
Set 2: Tax schedules and complete project timelines10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 3: Inflation, purchasing power, and working capital10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 4: Sensitivity, break-even, and scenario decisions10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Set 5: Lease costs, replacement, and integrated appraisal10 Practice Questions
Save this lesson to see every answer and practice every set.
Question 1 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 2 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 3 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 4 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 5 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 6 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 7 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 8 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 9 of 10
Show answerHide answer
Save this lesson to see this answer.
Question 10 of 10
Show answerHide answer
Save this lesson to see this answer.
Stuck on your own question? Homework Help
Key Terms
A
Accelerated depreciation
Accounting break-even
Adjusted payback
Advance lease payment
After-tax borrowing rate
After-tax salvage
Allocated overhead
B
Balancing allowance
Balancing charge
Break-even discount rate
Break-even lease payment
C
Cannibalization
Capital expenditure
Change in NWC
Committed cost
Critical variable
Current prices
D
Decommissioning cost
Depreciable basis
Depreciation tax shield
E
EBIT
Equivalent annual benefit
Equivalent annual cost
Expected NPV
F
Fisher relation
Free cash flow
G
General inflation
Goal seek
I
Incremental cash flow
L
Lease tax relief
Lease-or-buy decision
M
Marginal tax rate
Monte Carlo simulation
N
Net working capital
Nominal cash flow
Nominal forecast
NOPAT
NPV break-even
O
One-year keep cost
Operating cash flow
Opportunity cost
P
Payables
R
Real cash flow
Real discount rate
Receivables
Reducing-balance depreciation
Repeatability assumption
Replacement cycle
Risk
Risk-adjusted discount rate
S
Salvage value
Scenario analysis
Sensitivity analysis
Sensitivity margin
Specific inflation rate
Standard deviation of NPV
Straight-line depreciation
Sunk cost
Sunk-cost fallacy
Synergy
T
Tax written-down value
Tax-allowable depreciation
Terminal value
U
Uncertainty
Unlevered cash flow
W
Working capital recovery